Space Acquisitions
DOD Delivering New Generations of Satellites, but Space System Acquisition Challenges Remain
Gao ID: GAO-11-590T May 11, 2011
Despite decades of significant investment, most of the Department of Defense's (DOD) large space acquisition programs have collectively experienced billions of dollars in cost increases, stretched schedules, and increased technical risks. Significant schedule delays of as much as 9 years have resulted in potential capability gaps in missile warning, military communications, and weather monitoring. These problems persist, with other space acquisition programs still facing challenges in meeting their targets and aligning the delivery of assets with appropriate ground and user systems. To address cost increases, DOD reduced the number of satellites it would buy, reduced satellite capabilities, or terminated major space system acquisitions. Broad actions have also been taken to prevent their occurrence in new programs, including better management of the acquisition process and oversight of its contractors and resolution of technical and other obstacles to DOD's ability to deliver capability. This testimony will focus on the (1) status of space system acquisitions, (2) results of GAO's space-related reviews over the past year and the challenges they signify, (3) efforts DOD has taken to address causes of problems and increase credibility and success in its space system acquisitions as well as efforts currently underway, and (4) what remains to be done.
Over the past two decades, DOD has had difficulties with nearly every space acquisition program, with years of cost and schedule growth, technical and design problems, and oversight and management weaknesses. However, to its credit, DOD continues to make progress on several of its programs--such as the Space Based Infrared System High and Advanced Extremely High Frequency programs--and is expecting to deliver significant advances in capability as a result. But other programs continue to be susceptible to cost and schedule challenges. For example, the Global Positioning System (GPS) IIIA program's total cost has increased by about 10 percent over its original estimate, and delays in the Mobile User Objective System continue the risk of a capability gap in ultra high frequency satellite communications. In 2010, GAO assessed DOD's efforts to (1) upgrade and sustain GPS capabilities and (2) commercialize or incorporate into its space acquisition program the space technologies developed by small businesses. These reviews underscore the varied challenges that still face the DOD space community as it seeks to complete problematic legacy efforts and deliver modernized capabilities--for instance, the need for more focused coordination and leadership for space activities--and highlight the substantial barriers and challenges that small businesses must overcome to gain entry into the government space arena. DOD continues to work to ensure that its space programs are more executable and produce a better return on investment. Many of the actions it has been taking address root causes of problems, though it will take time to determine whether these actions are successful. For example, DOD is working to ensure that critical technologies are matured before large-scale acquisition programs begin and requirements are defined early in the process and are stable throughout. Additionally, DOD and the Air Force are working to streamline management and oversight of the national security space enterprise. While DOD actions to date have been good, more changes to processes, policies, and support may be needed--along with sustained leadership and attention--to help ensure that these reforms can take hold, including addressing the diffuse leadership for space programs. While some changes to the leadership structure have recently been made and others are being studied, it is too early to tell how effective they will be in streamlining management and oversight of space system acquisitions. Finally, while space system acquisition workforce capacity is essential if new weapon programs are to be successful, DOD continues to face gaps in technical and programmatic expertise for space.
GAO-11-590T, Space Acquisitions: DOD Delivering New Generations of Satellites, but Space System Acquisition Challenges Remain
This is the accessible text file for GAO report number GAO-11-590T
entitled 'Space Acquisitions: DOD Delivering New Generations of
Satellites, but Space System Acquisition Challenges Remain' which was
released on May 11, 2011.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
United States Government Accountability Office:
GAO:
Testimony:
Before the Subcommittee on Strategic Forces, Committee on Armed
Services, U.S. Senate:
For Release on Delivery:
Expected at 2:30 p.m. EDT:
Wednesday, May 11, 2011:
Space Acquisitions:
DOD Delivering New Generations of Satellites, but Space System
Acquisition Challenges Remain:
Statement of Cristina T. Chaplain, Director:
Acquisition and Sourcing Management:
GAO-11-590T:
GAO Highlights:
Highlights of GAO-11-590T, a testimony before the Subcommittee on
Strategic Forces, Committee on Armed Services, U.S. Senate.
Why GAO Did This Study:
Despite decades of significant investment, most of the Department of
Defense‘s (DOD) large space acquisition programs have collectively
experienced billions of dollars in cost increases, stretched
schedules, and increased technical risks. Significant schedule delays
of as much as 9 years have resulted in potential capability gaps in
missile warning, military communications, and weather monitoring.
These problems persist, with other space acquisition programs still
facing challenges in meeting their targets and aligning the delivery
of assets with appropriate ground and user systems.
To address cost increases, DOD reduced the number of satellites it
would buy, reduced satellite capabilities, or terminated major space
system acquisitions. Broad actions have also been taken to prevent
their occurrence in new programs, including better management of the
acquisition process and oversight of its contractors and resolution of
technical and other obstacles to DOD‘s ability to deliver capability.
This testimony will focus on the (1) status of space system
acquisitions, (2) results of GAO‘s space-related reviews over the past
year and the challenges they signify, (3) efforts DOD has taken to
address causes of problems and increase credibility and success in its
space system acquisitions as well as efforts currently underway, and
(4) what remains to be done.
What GAO Found:
Over the past two decades, DOD has had difficulties with nearly every
space acquisition program, with years of cost and schedule growth,
technical and design problems, and oversight and management
weaknesses. However, to its credit, DOD continues to make progress on
several of its programs”-such as the Space Based Infrared System High
and Advanced Extremely High Frequency programs”-and is expecting to
deliver significant advances in capability as a result. But other
programs continue to be susceptible to cost and schedule challenges.
For example, the Global Positioning System (GPS) IIIA program‘s total
cost has increased by about 10 percent over its original estimate, and
delays in the Mobile User Objective System continue the risk of a
capability gap in ultra high frequency satellite communications.
In 2010, GAO assessed DOD‘s efforts to (1) upgrade and sustain GPS
capabilities and (2) commercialize or incorporate into its space
acquisition program the space technologies developed by small
businesses. These reviews underscore the varied challenges that still
face the DOD space community as it seeks to complete problematic
legacy efforts and deliver modernized capabilities”-for instance, the
need for more focused coordination and leadership for space
activities”-and highlight the substantial barriers and challenges that
small businesses must overcome to gain entry into the government space
arena.
DOD continues to work to ensure that its space programs are more
executable and produce a better return on investment. Many of the
actions it has been taking address root causes of problems, though it
will take time to determine whether these actions are successful. For
example, DOD is working to ensure that critical technologies are
matured before large-scale acquisition programs begin and requirements
are defined early in the process and are stable throughout.
Additionally, DOD and the Air Force are working to streamline
management and oversight of the national security space enterprise.
While DOD actions to date have been good, more changes to processes,
policies, and support may be needed-”along with sustained leadership
and attention”-to help ensure that these reforms can take hold,
including addressing the diffuse leadership for space programs. While
some changes to the leadership structure have recently been made and
others are being studied, it is too early to tell how effective they
will be in streamlining management and oversight of space system
acquisitions. Finally, while space system acquisition workforce
capacity is essential if new weapon programs are to be successful, DOD
continues to face gaps in technical and programmatic expertise for
space.
View [hyperlink, http://www.gao.gov/products/GAO-11-590T] or key
components. For more information, contact Cristina Chaplain at (202)
512-4841 or chaplainc@gao.gov.
[End of section]
Chairman Nelson, Ranking Member Sessions, and Members of the
Subcommittee:
I am pleased to be here today to discuss the Department of Defense's
(DOD) space acquisitions. Each year, DOD spends billions of dollars to
acquire space-based capabilities to support current military and other
government operations, as well as to enable DOD to transform the way
it collects and disseminates information. Despite the significant
investment in space, the majority of large-scale acquisition programs
in DOD's space portfolio have experienced problems during the past two
decades that have driven up costs by hundreds of millions and even
billions of dollars, stretched schedules by years, and increased
technical risks. To address the cost increases, DOD altered its
acquisitions by reducing the number of satellites it intended to buy,
reducing the capabilities of the satellites, or terminating major
space system acquisitions. Moreover, along with the cost increases,
many space acquisitions have experienced significant schedule delays--
of as much as 9 years--resulting in potential capability gaps in areas
such as missile warning, military communications, and weather
monitoring. These problems persist; however, the Air Force and the
Office of the Secretary of Defense have taken a wide range of actions
to prevent them from occurring in new programs.
My testimony today will focus on the (1) the status of space system
acquisitions, (2) results of our space-related reviews over the past
year and the challenges they signify, (3) the efforts DOD has taken to
address causes of problems and increase credibility and success in its
space system acquisitions as well as efforts currently under way, and
(4) what remains to be done. Notably, DOD has acknowledged the
acquisition problems of the past and recognizes the need for better
management of the acquisition process and oversight of its
contractors. More important, several high-risk space programs appear
to have finally resolved technical and other obstacles and have
started to or are close to beginning to deliver capability. However,
other space acquisition programs--including the Global Positioning
System (GPS) IIIA and Mobile User Objective System (MUOS)--continue to
face challenges in meeting their cost and schedule targets and
aligning the delivery of space assets with the ground and user systems
needed to support and take advantage of new capability. Moreover, it
may take years for acquisition improvements to take root and produce
benefits that will enable DOD to realize a better return on its
investment in space. Importantly, DOD has taken steps to decide how to
best organize, lead, and support space activities. But more may be
needed in light of the wide range of stakeholders and past issues with
diffuse leadership.
The work that supports this statement was performed in accordance with
generally accepted government auditing standards. Those standards
require that we plan and perform the audit to obtain sufficient,
appropriate evidence to provide a reasonable basis for our findings
and conclusions based on our audit objectives. We believe that the
evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives. Additional details on our
scope and methodology are provided in appendix II.
Status of Space Acquisitions: Challenges Persist:
A long-standing problem in DOD space acquisitions is that program and
unit costs tend to go up significantly from initial cost estimates,
while in some cases the capability that was to be delivered goes down.
Figure 1 compares original cost estimates and current cost estimates
for the broader portfolio of major space acquisitions for fiscal years
2010 through 2015. The wider the gap between original and current
estimates, the fewer dollars DOD has available to invest in new
programs. As shown in the figure, cumulative estimated costs for the
major space acquisition programs have increased by about $13.9 billion
from initial estimates for fiscal years 2010 through 2015, almost a
286 percent increase. The declining investment in the later years is
the result of mature programs that have planned lower out-year
funding, cancellation of several development efforts, and the
exclusion of space acquisition efforts for which total cost data were
unavailable (such as new investments).
Figure 1: Comparison between Original Cost Estimates and Current Cost
Estimates for Selected Major Space Acquisition Programs for Fiscal
Years 2010 through 2015:
[Refer to PDF for image: multiple line graph]
Fiscal year 2011 dollars:
Fiscal year: 2010;
Original cost estimate: $1.35 billion;
Current cost estimate: $4.80 billion.
Fiscal year: 2011;
Original cost estimate: $1.15 billion;
Current cost estimate: $4.24 billion.
Fiscal year: 2012;
Original cost estimate: $1.34 billion;
Current cost estimate: $3.74 billion.
Fiscal year: 2013;
Original cost estimate: $726.6 million;
Current cost estimate: $2.77 billion.
Fiscal year: 2014;
Original cost estimate: $238.4 million;
Current cost estimate: $2.02 billion.
Fiscal year: 2015;
Original cost estimate: $67.4 million;
Current cost estimate: $1.26 billion.
Cumulative cost increase: $13.9 billion.
Source: GAO analysis of DOD data.
Note: Includes Advanced Extremely High Frequency, Global Broadcast
System, Global Positioning System II and III, Mobile User Objective
System, Space Based Infrared System High, and Wideband Global SATCOM.
Does not include the Evolved Expendable Launch Vehicle (which is in
sustainment) and planned new space acquisition efforts--such as
Defense Weather Satellite System, Joint Space Operations Center
Mission System, Space Based Space Surveillance Follow-on, and Space
Fence--for which total cost data were unavailable.
[End of figure]
When space system investments other than established acquisition
programs of record--such as the Defense Weather Satellite System
(DWSS) and Space Fence programs--are also considered, DOD's space
acquisition investments remain significant through fiscal year 2016,
as shown in figure 2. Although estimated costs for selected space
acquisition programs decrease 21 percent between fiscal years 2010 and
2015, they start to increase in fiscal year 2016. And, according to
current DOD estimates, costs for two programs--Advanced Extremely High
Frequency (AEHF) and Space Based Infrared System (SBIRS) High--are
expected to significantly increase in fiscal years 2017 and 2018. The
costs are associated with the procurement of additional blocks of
satellites and are not included in the figure because they have not
yet been reported or quantified.
Figure 2: Estimated Costs for Selected DOD Space Programs for Fiscal
Years 2010 through 2016:
[Refer to PDF for image: line graph]
Fiscal year: 2010;
Estimated costs: $7.52 billion.
Fiscal year: 2011;
Estimated costs: $7.16 billion.
Fiscal year: 2012;
Estimated costs: $7.39 billion.
Fiscal year: 2013;
Estimated costs: $6.81 billion.
Fiscal year: 2014;
Estimated costs: $6.67 billion.
Fiscal year: 2015;
Estimated costs: $5.95 billion.
Fiscal year: 2016;
Estimated costs: $6.28 billion.
Source: GAO analysis of DOD data.
Note: The acquisition efforts include Advanced Extremely High
Frequency, Evolved Expendable Launch Vehicle, Global Broadcast
Service, Global Positioning System II, Global Positioning System III,
Joint Space Operations Center Mission System, Mobile User Objective
System, National Polar-orbiting Operational Environmental Satellite
System/Defense Weather Satellite System, Precision Tracking Space
System, Space Based Infrared System High, Space Situational Awareness
Systems, Space Tracking and Surveillance System, and Wideband Global
SATCOM.
[End of figure]
Figures 3 and 4 reflect differences in total program and unit costs
for satellites from the time the programs officially began to their
most recent cost estimates. As figure 4 shows, in several cases, DOD
has increased the number of satellites. The figures reflect total
program cost estimates developed in fiscal year 2010.
Figure 3: Differences in Unit Costs from Program Start and Most Recent
Estimates:
[Refer to PDF for image: vertical bar graph]
Fiscal year 2011 dollars in billions:
Program and start date: SBIRS High; 1996;
Initial unit cost: $0.90 billion;
Most recent unit cost: $3.01 billion.
Program and start date: GPS; II 2000;
Initial unit cost: $0.19 billion;
Most recent unit cost: $0.23 billion.
Program and start date: WGS; 2000;
Initial unit cost: $0.39 billion;
Most recent unit cost: $0.52 billion.
Program and start date: AEHF; 2001;
Initial unit cost: $1.26 billion;
Most recent unit cost: $2.31 billion.
Program and start date: NPOESS; 2002;
Initial unit cost: $1.10 billion;
Most recent unit cost: Program restructured in 2010.
Program and start date: MUOS; 2004;
Initial unit cost: $1.10 billion;
Most recent unit cost: $1.15 billion.
Program and start date: GPS III; 2008;
Initial unit cost: $0.49 billion;
Most recent unit cost: $0.53 billion.
Source: GAO analysis of DOD data.
Legend: SBIRS = Space Based Infrared System High; GPS = Global
Positioning System; WGS = Wideband Global SATCOM; AEHF = Advanced
Extremely High Frequency; NPOESS = National Polar-orbiting Operational
Environmental Satellite System; MUOS = Mobile User Objective System.
[End of figure]
Figure 4: Differences in Total Costs from Program Start to Most Recent
Estimates:
[Refer to PDF for image: vertical bar graph]
Fiscal year 2011 dollars:
Program and start date: SBIRS High 1996;
Initial estimated cost and number of satellites: $4.52 billion; 5
satellites;
Most recent estimate: $18.05 billion; 1 more satellite and deferred
requirements.
Program and start date: GPS II 2000;
Initial estimated cost and number of satellites: $6.13 billion; 33
satellites;
Most recent estimate: $7.49 billion.
Program and start date: WGS 2000;
Initial estimated cost and number of satellites: $1.18 billion;
Most recent estimate: $3.62 billion; 4 more satellites.
Program and start date: AEHF 2001;
Initial estimated cost and number of satellites: $6.28 billion; 5
satellites;
Most recent estimate: $13.88 billion; 1 more satellite.
Program and start date: NPOESS 2002;
Initial estimated cost and number of satellites: $6.58 billion; 6
satellites;
Most recent estimate: Program restructures in 2010.
Program and start date: MUOS 2004;
Initial estimated cost and number of satellites: $6.62 billion; 6
satellites;
Most recent estimate: $6.88 billion.
Program and start date: GPS III 2008;
Initial estimated cost and number of satellites: $3.88 billion; 8
satellites;
Most recent estimate: $4.26 billion.
Source: GAO analysis of DOD data.
Legend: SBIRS = Space Based Infrared System High; GPS = Global
Positioning System; WGS = Wideband Global SATCOM; AEHF = Advanced
Extremely High Frequency; NPOESS = National Polar-orbiting Operational
Environmental Satellite System; MUOS = Mobile User Objective System.
[End of figure]
Several space acquisition programs are years behind schedule. Figure 5
highlights the additional estimated months needed for programs to
launch their first satellites. These additional months represent time
not anticipated at the programs' start dates. Generally, the further
schedules slip, the more DOD is at risk of not sustaining current
capabilities. For example, delays in launching the first MUOS
satellite have placed DOD's ultra high frequency communications
capabilities at risk of falling below the required availability level.
Figure 5: Total Number of Estimated or Actual Months from Program
Start to Initial Launch:
[Refer to PDF for image: stacked vertical bar graph]
Program and start date: SBIRS High 1996;
Initial estimated number of months: 68;
Difference in estimates: 107;
Total: 175 months.
Program and start date: GPS IIF 2000;
Initial estimated number of months: 68;
Difference in estimates: 55;
Total: 123 months.
Program and start date: WGS 2000;
Initial estimated number of months: 39;
Difference in estimates: 44;
Total: 83 months.
Program and start date: AEHF 2001;
Initial estimated number of months: 39;
Difference in estimates: 68;
Total: 107 months.
Program and start date: NPOESS 2002;
Initial estimated number of months: 80;
Total is unknown because program was restructured.
Program and start date: MUOS 2004;
Initial estimated number of months: 63;
Difference in estimates: 26;
Total: 89 months.
Program and start date: GPS III 2008;
Initial estimated number of months: 71;
Difference in estimates: 0;
Total: 71 months.
Source: GAO analysis of DOD data.
Legend: SBIRS = Space Based Infrared System High; GPS = Global
Positioning System; WGS = Wideband Global SATCOM; AEHF = Advanced
Extremely High Frequency; NPOESS = National Polar-orbiting Operational
Environmental Satellite System; MUOS = Mobile User Objective System.
[End of figure]
Some Acquisition Programs Appear to Have Overcome Problems, but Other
Programs Still Susceptible to Cost and Schedule Overruns:
DOD had long-standing difficulties on nearly every space acquisition
program, struggling for years with cost and schedule growth, technical
or design problems, as well as oversight and management weaknesses.
However, to its credit, it continues to make progress on several of
its high-risk space programs, and is expecting to deliver significant
advances in capability as a result. The Missile Defense Agency's (MDA)
Space Tracking and Surveillance System (STSS) demonstration satellites
were launched in September 2009. Additionally, DOD launched its first
GPS IIF satellite in May 2010 and plans to launch the second IIF
satellite in June 2011--later than planned, partially because of
system-level problems identified during testing. It also launched the
first AEHF satellite in August 2010--although it has not yet reached
its final planned orbit because of an anomaly with the satellite's
propulsion system--and launched the Space Based Space Surveillance
(SBSS) Block 10 satellite in September 2010. DOD is scheduled to
launch a fourth Wideband Global SATCOM (WGS) satellite broadening
communications capability available to warfighters--in late 2011, and
a fifth WGS satellite in early 2012. The Evolved Expendable Launch
Vehicle (EELV) program had its 41st consecutive successful operational
launch in May of this year.
One program that appears to have recently overcome remaining technical
problems is the SBIRS High satellite program. The first of six
geosynchronous earth-orbiting (GEO) satellites (two highly elliptical
orbit sensors have already been launched) was launched in May 2011 and
is expected to continue the missile warning mission with sensors that
are more capable than the satellites currently on orbit. Total cost
for the SBIRS High program is currently estimated at over $18 billion
for six GEO satellites,[Footnote 1] representing a program unit cost
of over $3 billion, about 233 percent more than the original unit cost
estimate. Additionally, the launch of the first GEO satellite
represents a delay of approximately 9 years. The reasons for the delay
include poor government oversight of the contractor, unanticipated
technical complexities, and rework. The program office is working to
rebaseline the SBIRS High contract cost and schedule estimates for the
sixth time. Because of the problems on SBIRS High, in 2007, DOD began
a follow-on system effort, which was known as Third Generation
Infrared Surveillance (3GIRS), to run in parallel with the SBIRS High
program. DOD canceled the 3GIRS effort in fiscal year 2011, but plans
to continue providing funds under the SBIRS High program for one of
the 3GIRS infrared demonstrations.
While DOD is having success in readying some satellites for launch,
other space acquisition programs face challenges that could further
increase cost and delay delivery targets. The programs that may be
susceptible to cost and schedule challenges include MUOS and the GPS
IIIA program. Delays in the MUOS program have resulted in critical
potential capability gaps for military and other government users. The
GPS IIIA program was planned with an eye toward avoiding problems that
plagued the GPS IIF program and it incorporated many of the best
practices recommended by GAO, but the schedule leaves little room for
potential problems and there is a risk that the ground system needed
to operate the satellites will not be ready when the first satellite
is launched. Additionally, the National Polar-orbiting Operational
Environmental Satellite System (NPOESS) was restructured as a result
of poor program performance and cost overruns, which caused schedule
delays. These delays have resulted in a potential capability gap for
weather and environmental monitoring. Furthermore, new space system
acquisition efforts getting underway--including the Air Force's Joint
Space Operations Center Mission System (JMS) and Space Fence, and
MDA's Precision Tracking and Surveillance System (PTSS)--face
potential development challenges and risks, but it is too early to
tell how significant they may be to meeting cost, schedule, and
performance goals.
Table 1 describes the status of these efforts in more detail.
Table 1: Status of Major Space Acquisition Efforts:
Systems achieving or nearing launch that have overcome technical and
other problems:
GPS IIF (positioning, navigation, and timing):
The first GPS IIF satellite, launched in May 2010, is designed to
upgrade timing and navigation accuracy and add a new signal for
civilian use. The satellite was delayed over 4 1/2 years from its
original launch date mostly because of development challenges. The
cost of the GPS IIF program is expected to be about $1.6 billion--
about $870 million over the original cost estimate of $729 million.
(This approximately 119 percent cost increase is not apparent in
figures 3 and 4 because the GPS II modernization program includes the
development and procurement of 33 satellites, only 12 of which are IIF
satellites.) As a result of continued technical challenges in
producing the GPS IIF satellites, the program continues to experience
schedule delays as well as increased funding shortfalls.
AEHF (communications):
The first AEHF satellite launched in August 2010. AEHF satellites are
expected to deliver 10 times the communications bandwidth that is
available today for secure and protected communications. The launch of
the first satellite slipped almost 6 years. The program has decided
that the design specifications for the first three satellites will
remain unchanged for satellites four through six, which will thus be
clones except for the replacement of obsolete parts. The initial
operational capability date is currently unknown because of an anomaly
in the propulsion system of the first satellite, which has delayed it
from reaching its planned orbit--it is expected to reach final orbit
in August 2011. The program office will delay the launch of the second
AEHF satellite until (1) it is cleared for flight in light of the
first AEHF propulsion system anomaly and (2) the first satellite is on
orbit and tested. The third AEHF satellite is expected to launch about
8 months after the second satellite is launched. The notional launch
dates for satellites four through six are 2017, 2018, and 2020,
respectively. The Air Force is in the process of developing a new
acquisition program baseline that includes these satellites.
SBSS (space situational awareness):
The first SBSS Block 10 satellite launched in September 2010 and is
expected to provide greatly improved space situational awareness to
help better understand location and mission capabilities of all
satellites and other objects in space. The satellite launched more
than 3 years later than originally planned--in part because of launch
vehicle issues unrelated to the satellite. The program was
restructured in 2006 after an independent review found that the
requirements were overstated and its cost and schedule targets could
not be met. Efforts to develop a follow-on system have been
discontinued, pending an ongoing study directed by the Office of the
Secretary of Defense.
Programs still susceptible to cost and schedule overruns:
NPOESS/DWSS (climate and weather monitoring):
In February 2010, the Executive Office of the President announced a
restructure of the NPOESS program, directing the acquisition and
development of separate military and civil weather satellite programs.
The NPOESS program had continued to experience technical problems
resulting in further cost and schedule increases. The Air Force plans
to acquire the DWSS to satisfy military weather requirements, and the
National Oceanographic and Atmospheric Administration will acquire the
Joint Polar Satellite System and a shared common ground system to
address civil weather and environmental requirements. The DWSS program
is expected to satisfy environmental monitoring requirements in the
early morning orbit by developing and launching two satellites, with
an initial launch capability no earlier than 2018.
MUOS (communications):
The MUOS communications satellite program now estimates a 26-month
delay--from March 2010 to May 2012--in the delivery of on-orbit
capability from the first satellite. Design issues with ultra high
frequency (UHF) reflectors continue to pose cost and schedule risks
for the program. In July 2009, a Navy-initiated review of the program
found that while the technical challenges the program was experiencing
could be solved, the MUOS budget was inadequate and its schedule was
optimistic. As a result, the program developed new cost and schedule
baselines. The acquisition program baseline has been under revision
since December 2009, but has not yet been approved. According to the
program, the prime contract cost baseline, which includes $162 million
in engineering change proposals, has increased about 61 percent since
contract award in September 2004. The importance of the first MUOS
launch increased because of the unexpected failure of two legacy
satellites. The MUOS program office is addressing the potential
capability gap by activating dual digital receiver unit operations on
a legacy satellite, examining the potential of purchasing or leasing
commercial UHF satellite communications services, and examining the
feasibility of expanded digital receiver unit operations on the legacy
payloads of the MUOS satellites.
GPS III (positioning, navigation, and timing):
While the GPS III program has been structured by the Air Force to
prevent the mistakes made on the IIF program, the Air Force aims to
deliver the GPS IIIA satellites 3 years faster than it did the IIF
satellites. According to Air Force officials, the IIIA contractor
retained some of its workforce from the IIR-M program and plans to
incorporate a previously developed satellite bus--efforts that reduce
program risk. Also, the program has taken measures to maintain stable
requirements, use mature technologies, and provide more contractor
oversight. However, we continue to believe that the IIIA schedule is
optimistic given the program's late start, past trends in space
acquisitions, and challenges facing the new contractor. According to
our analysis of data contained in selected acquisition reports for the
GPS IIIA program, total program costs have increased about 10 percent
over the original estimate established for the start of product
development. According to the Air Force, the increase is due in part
to unanticipated costs resulting from issues such as technical
complexities involved in developing the satellite vehicle bus and
software development. To increase confidence in the schedule for
delivering the ground control system for IIIA (the next generation
operational control segment known as OCX), the GPS Directorate added
16 months of development time to the effort. This means that the first
block of OCX is now scheduled to be fielded in August 2015, 15 months
after the May 2014 planned launch of the first GPS IIIA satellite. To
address this issue, the GPS Directorate is considering funding a
parallel effort that accelerates existing launch and checkout
requirements to develop a command and control capability for the first
GPS IIIA satellites. However, GPS Directorate officials indicated that
the effort would not enable the utilization of new capabilities
offered by GPA IIIA satellites, including a military signal designed
to enable resistance to jamming and three civil signals.
Development initiatives getting under way:
JMS (space situational awareness):
GAO's best practices work has shown that large system projects divided
into a series of smaller incremental acquisition efforts--made on the
basis of reliable analysis of estimated costs, expected benefits, and
anticipated risks--permits informed investment decision making.
However, our ongoing work has shown that the JMS acquisition was not
adopting an incremental approach--the effort instead consisted of a
single increment delivered in a series of releases--as exemplified by
its plans to proceed without knowledge of all critical technologies
and deferral of other planning activities. This lack of knowledge
could result in unanticipated costs and other programmatic risks to
the acquisition effort. Although our best practices work and DOD
guidance call for critical technologies to be identified and matured
by development start,[A] the JMS program did not plan to identify and
assess the maturity of all critical technologies by that time.
Instead, JMS plans were to identify and assess critical technologies
prior to each release. Consequently, the program would not have
assurance that the needed technologies will be mature when needed and
that cost estimates--based on the development of all releases--were
reliable.b Additionally, JMS and DOD officials pointed to data
integration issues as one of the top risks for the JMS program. More
specifically, JMS will need to integrate data from numerous
heterogeneous sources, many of which are not net-centric. To ensure
that the data from these sources are compatible, the Air Force is
currently working to ensure that these sources are net-centric before
JMS is complete. Furthermore, our best practices work has shown that
maturing technology to technology readiness level (TRL) 7 prior to
development start reduces risk to meeting cost, schedule, and
performance goals.c However, the JMS program planned to use
technologies, such as service information exchange capabilities to
allow applications to send data and information to other applications
and servers, that only have been matured to TRL 6 or greater prior to
the start of development for each release. A recent independent
program assessment commissioned by the Office of the Under Secretary
of Defense for Acquisition, Technology and Logistics (AT&L) has
prompted the Air Force to revise the JMS acquisition strategy, which
may help to address the above challenges and risks.
Space Fence (space situational awareness):
The primary Space Fence risk, according to the Electronic Systems
Center, is that JMS will need to be available to process Space Fence
data, as the amount of data provided will result in an increase in
uncued detection and tracking capacity from 10,000 to 100,000 objects.
Additionally, the Space Fence program office stated other risks of the
development effort include large-scale integration and calibration of
radar arrays, scalability of the design for the digital beam
former,[D] and development of information assurance certification
criteria. Furthermore, all five critical Space Fence technologies
identified by the program office are immature--one at TRL 4 and four
at TRL 5--which increases risk to cost and schedule goals. Given that
technology discovery cannot be scheduled, the immature technologies
raise the risk of having to defer product development until these
technologies become mature. Although mature backup critical
technologies exist--which could be used if the primary technologies do
not mature by the start of system development--all have potentially
higher acquisition costs and in some cases higher operating costs as
well, according to the program office. While the program has a
critical technology maturity goal of TRL 6 prior to preliminary design
review (which is in accordance with DOD's acquisition policy),e our
best practices work has shown technology development to TRL 7 could
significantly reduce risk to meeting cost, schedule, and performance
goals.
PTSS (ballistic missile defense):
In alignment with GAO best practices, MDA plans to build two prototype
satellites to define the system performance and focus on cost-
effective production in an industrial environment. Also consistent
with GAO best practices, MDA plans to separate technology discovery
from technology development by ensuring that critical technologies are
matured before large-scale acquisition begins. MDA plans to utilize
systems and components for the PTSS design that are currently used in
commercial satellite sensors without significantly altering form, fit,
or function. Additionally, the Director of MDA stated that a hallmark
of the PTSS satellites will be their relatively small size and
simplistic design. MDA also plans to follow an incremental path toward
meeting user needs by using currently available technology to deliver
near-term capabilities while maintaining the flexibility to add
capabilities later. However, in order to meet its optimistic schedule
to field an operational constellation by fiscal year 2018, MDA plans
to conduct prototyping efforts beginning in fiscal year 2011 and
launch two prototype satellites in fiscal year 2015. MDA also plans to
launch a minimum of seven additional satellites by fiscal year 2018.
Although PTSS is not yet far enough along in development to determine
whether MDA's current acquisition plans are overly optimistic, other
DOD space programs, for example, SBIRS High, have experienced long
development times to launch initial satellites. Also, the development
initiative must overcome several technology design challenges. For
example, AT&L officials have identified key technical design
challenges including developing sufficient sensitivity to detect and
track postboost ballistic missiles, tracking large raids of ballistic
missiles, and mass-producing payloads. According to AT&L officials,
the program plans to address these design challenges through the use
of computer modeling and simulations and refining payload design
models. MDA will collect critical risk reduction data during STSS
flight tests to help inform PTSS design.
Source: GAO analysis of DOD data and previous GAO reports.
[A] The Office of the Director, Defense Research and Engineering,
Department of Defense Technology Readiness Assessment (TRA) Deskbook,
Table 3-1 and Appendix B (July 2009), and Department of Defense
Instruction 5000.02, Operation of the Defense Acquisition System, enc.
2 paras. 5.a and 5.d.(4) (Dec. 8, 2008).
[B] According to DOD, it selected a single increment, multiple release
approach as the most efficient means to develop capabilities when
needed, based on technology maturity and available funding.
[C] The National Aeronautics and Space Administration originally
developed TRLs as a tool to assess technology maturity. TRLs are
measured on a scale from 1 to 9, beginning with paper studies of a
technology's feasibility (TRL 1) and culminating with application of
the technology in its final form and under mission conditions (TRL 9).
Demonstration that pieces will work together in a laboratory is TRL 4.
Demonstration in a simulated environment is TRL 5. Our best practices
work has shown that a TRL 7--demonstration of a technology in a
realistic environment--is the level of technology maturity that
constitutes a low risk for starting a product development program. We
ordinarily assess satellite technologies that have achieved TRL 6, a
prototype demonstrated in a relevant environment, as fully mature
because of the difficulty of demonstrating maturity in a realistic
environment--space. However, this does not apply to programs such as
JMS and Space Fence which are ground based.
[D] In general terms, the Space Fence phased array radar--analogous to
tens of thousands to hundreds of thousands of miniature radar
antennas--is to use digital beam forming, which allows the antennas to
work in concert, creating sufficient power transmitted and received to
conduct the space surveillance and tracking mission.
[E] Department of Defense Instruction 5000.02, Operation of the
Defense Acquisition System, enc. 2 para. 5.d.(7) (Dec. 8, 2008),
states that a project shall exit the technology development phase when
the technology has been demonstrated in a relevant environment, which
is TRL 6.
[End of table]
Results of GAO Space-Related Reviews over the Past Year:
Over the past year, we have completed reviews of sustaining and
upgrading GPS capabilities and commercializing space technologies
under the Small Business Innovation Research program (SBIR),[Footnote
2] and we have ongoing reviews of (1) DOD space situational awareness
(SSA) acquisition efforts, (2) parts quality for DOD, MDA, and the
National Aeronautics and Space Administration (NASA), and (3) a new
acquisition strategy being developed for the EELV program. These
reviews, discussed further below, underscore the varied challenges
that still face the DOD space community as it seeks to complete
problematic legacy efforts and deliver modernized capabilities. Our
reviews of GPS and space situational awareness, for instance, have
highlighted the need for more focused coordination and leadership for
space activities that touch a wide range of government, international,
and industry stakeholders; while our review of the SBIR program
highlighted the substantial barriers and challenges small business
must overcome to gain entry into the government space arena.
* GPS. We found that the GPS IIIA schedule remains ambitious and could
be affected by risks such as the program's dependence on a ground
system that will not be completed until after the first IIIA launch.
We found that the GPS constellation availability had improved, but in
the longer term, a delay in the launch of the GPS IIIA satellites
could still reduce the size of the constellation to fewer than 24
operational satellites--the number that the U.S. government commits
to--which might not meet the needs of some GPS users. We also found
that the multiyear delays in the development of GPS ground control
systems were extensive. Although the Air Force had taken steps to
enable quicker procurement of military GPS user equipment, there were
significant challenges to its implementation. This has had a
significant impact on DOD as all three GPS segments--space, ground
control, and user equipment--must be in place to take advantage of new
capabilities. Additionally, we found that DOD had taken some steps to
better coordinate all GPS segments, including laying out criteria and
establishing visibility over a spectrum of procurement efforts, but it
did not go as far as we recommended in 2009 in terms of establishing a
single authority responsible for ensuring that all GPS segments are
synchronized to the maximum extent practicable.[Footnote 3] Such an
authority is warranted given the extent of delays, problems with
synchronizing all GPS segments, and importance of new capabilities to
military operations. As a result, we reiterated the need to implement
our prior recommendation.
* Small Business Innovation Research (SBIR). In response to a request
from this subcommittee, we found that while DOD is working to
commercialize space-related technologies under its SBIR program by
transitioning these technologies into acquisition programs or the
commercial sector, it has limited insight into the program's
effectiveness.[Footnote 4] Specifically, DOD has invested about 11
percent of its fiscal years 2005-2009 research and development funds
through its SBIR program to address space-related technology needs.
Additionally, DOD is soliciting more space-related research proposals
from small businesses. Further, DOD has implemented a variety of
programs and initiatives to increase the commercialization of SBIR
technologies and has identified instances where it has transitioned
space-related technologies into acquisition programs or the commercial
sector. However, DOD lacks complete commercialization data to
determine the effectiveness of the program in transitioning space-
related technologies into acquisition programs or the commercial
sector. Of the nearly 500 space-related contracts awarded in fiscal
years 2005 through 2009, DOD officials could not, for various reasons,
identify the total number of technologies that transitioned into
acquisition programs or the commercial sector. Further, there are
challenges to executing the SBIR program that DOD officials
acknowledge and are planning to address, such as the lack of
overarching guidance for managing the DOD SBIR program.
Under this review, most stakeholders we spoke with--DOD, prime
contractors, and small business officials--generally agreed that small
businesses participating in the DOD SBIR program face difficulties
transitioning their space-related technologies into acquisition
programs or the commercial sector. Although we did not assess the
validity of the concerns cited, stakeholders we spoke with identified
challenges inherent to developing space technologies; challenges
because of the SBIR program's administration, timing, and funding
issues; and other challenges related to participating in the DOD space
system acquisitions environment. For example, some small-business
officials said that working in the space community is challenging
because the technologies often require more expensive materials and
testing than other technologies. They also mentioned that delayed
contract awards and slow contract disbursements have caused financial
hardships. Additionally, several small businesses cited concerns with
safeguarding their intellectual property.
* Space Situational Awareness (SSA). We have found that while DOD has
significantly increased its investment and planned investment in SSA
acquisition efforts in recent years to address growing SSA capability
shortfalls, most efforts designed to meet these shortfalls have
struggled with cost, schedule, and performance challenges and are
rooted in systemic problems that most space system acquisition
programs have encountered over the past decade. Consequently, in the
past 5 fiscal years, DOD has not delivered significant new SSA
capabilities as originally expected. Capabilities that were delivered
served to sustain or modernize existing systems versus closing
capability gaps. To its credit, last fall the Air Force launched a
space-based sensor that is expected to appreciably enhance SSA.
However, two critical acquisition efforts that are scheduled to begin
development within the next 2 years--Space Fence and JMS--face
development challenges and risks, such as the use of immature
technologies and planning to deliver all capabilities in a single,
large increment versus smaller and more manageable increments. It is
essential that these acquisitions are placed on a solid footing at the
start of development to help ensure that their capabilities are
delivered to the warfighter as and when promised. DOD plans to begin
delivering other new capabilities in the coming 5 years, but it is too
early to determine the extent to which these additions will address
capability shortfalls.
We have also found that there are significant inherent challenges to
executing and overseeing the SSA mission, largely because of the sheer
number of governmentwide organizations and assets involved in the
mission. This finding is similar to what we have reported from other
space system acquisition reviews over the years. Additionally, while
the recently issued National Space Policy assigns SSA responsibility
to the Secretary of Defense, the Secretary does not necessarily have
the corresponding authority to execute this responsibility. However,
actions, such as development of a national SSA architecture, are being
taken that could help facilitate management and oversight
governmentwide. The National Space Policy, which recognizes the
importance of SSA, directs other positive steps, such as the
determination of roles, missions, and responsibilities to manage
national security space capabilities and the development of options
for new measures for improving SSA capabilities. Furthermore, the
recently issued National Security Space Strategy could help guide the
implementation of the new space policy. We expect our report based on
this review to be issued in June 2011.
* Parts quality for DOD, MDA, and NASA. Quality is paramount to the
success of DOD space systems because of their complexity, the
environment they operate in, and the high degree of accuracy and
precision needed for their operations. Yet in recent years, many
programs have encountered difficulties with quality workmanship and
parts. For example, DOD's AEHF protected communications satellite has
yet to reach its intended orbit because of a blockage in a propellant
line. Also, MDA's STSS program experienced a 15-month delay in the
launch of demonstration satellites because of a faulty manufacturing
process of a ground-to-spacecraft communication system part.
Furthermore, NASA's Mars Science Laboratory program experienced a 1-
year delay in the development of the descent and cruise stage
propulsion systems because of a welding process error. We plan to
issue a report on the results of a review that focuses specifically on
parts quality issues in June 2011. We are examining the extent to
which parts quality problems are affecting DOD, MDA, and NASA space
and missile defense programs; the causes of these problems; and
initiatives to detect and prevent parts quality problems.
* EELV acquisition strategy. DOD spends billions of dollars on launch
services and infrastructure through two families of commercially owned
and operated vehicles under the EELV program. This investment allows
the nation to launch its national security satellites that provide the
military and intelligence community with advanced space-based
capabilities. DOD is preparing to embark on a new acquisition strategy
for the EELV program. Given the costs and importance of space launch
activities, it is vital that this strategy maximize cost efficiencies
while still maintaining a high degree of mission assurance and a
healthy industrial base. We are currently reviewing activities leading
up to the strategy and plan to issue a report on the results of this
review in June 2011. In particular, we are examining whether DOD has
the knowledge it needs to develop a new EELV acquisition strategy and
the extent to which there are important factors that could affect
launch acquisitions.
DOD Has Taken and Is Taking Actions to Address Space and Weapon
Acquisition Problems:
DOD continues to work to ensure that its space programs are more
executable and produce a better return on investment. Many of the
actions it has been taking address root causes of problems, though it
will take time to determine whether these actions are successful and
they need to be complemented by decisions on how best to lead,
organize, and support space activities.
Causes of Acquisition Problems and Best Practices for Avoiding Them:
Our past work has identified a number of causes of the cost growth and
related problems, but several consistently stand out. First, on a
broad scale, DOD has tended to start more weapon programs than it can
afford, creating a competition for funding that encourages low cost
estimating, optimistic scheduling, overpromising, suppressing bad
news, and for space programs, forsaking the opportunity to identify
and assess potentially more executable alternatives. Programs focus on
advocacy at the expense of realism and sound management. Invariably,
with too many programs in its portfolio, DOD is forced to continually
shift funds to and from programs--particularly as programs experience
problems that require additional time and money to address. Such
shifts, in turn, have had costly, reverberating effects.
Second, DOD has tended to start its space programs too early, that is,
before it has the assurance that the capabilities it is pursuing can
be achieved within available resources and time constraints. This
tendency is caused largely by the funding process, since acquisition
programs attract more dollars than efforts concentrating solely on
proving technologies. Nevertheless, when DOD chooses to extend
technology invention into acquisition, programs experience technical
problems that require large amounts of time and money to fix.
Moreover, when this approach is followed, cost estimators are not well
positioned to develop accurate cost estimates because there are too
many unknowns. Put more simply, there is no way to accurately estimate
how long it would take to design, develop, and build a satellite
system when critical technologies planned for that system are still in
relatively early stages of discovery and invention.
Third, programs have historically attempted to satisfy all
requirements in a single step, regardless of the design challenges or
the maturity of the technologies necessary to achieve the full
capability. DOD has preferred to make fewer but heavier, larger, and
more complex satellites that perform a multitude of missions rather
than larger constellations of smaller, less complex satellites that
gradually increase in sophistication. This has stretched technology
challenges beyond current capabilities in some cases and vastly
increased the complexities related to software. Programs also seek to
maximize capability on individual satellites because it is expensive
to launch them. Figure 6 illustrates the various factors that can
break acquisitions.
Figure 6: Key Underlying Problems that Can Break Acquisitions:
[Refer to PDF for image: illustration]
Broken Acquisitions:
* Technology immature;
* Software needs poorly understood;
* Requirements unstable;
* Funding unstable;
* Inadequate contracting strategy;
* Inadequate contractor oversight;
* Alternatives not considered;
* Optimistic cost & schedule estimates.
Source: GAO.
[End of figure]
Many of these underlying issues affect the broader weapons portfolio
as well, though we have reported that space programs are particularly
affected by the wide disparity of users, including DOD, the
intelligence community, other federal agencies, and in some cases,
other countries, U.S. businesses, and citizens. Moreover, problematic
implementation of an acquisition strategy in the 1990s, known as Total
System Performance Responsibility, for space systems resulted in
problems on a number of programs because it was implemented in a
manner that enabled requirements creep and poor contractor
performance--the effects of which space programs are finally
overcoming. We have also reported on shortfalls in resources for
testing new technologies, which, coupled with less expertise and fewer
contractors available to lead development efforts, have magnified the
challenge of developing complex and intricate space systems.
Our work--which is largely based on best practices in the commercial
sector--has recommended numerous actions that can be taken to address
the problems we identified. Generally, we have recommended that DOD
separate technology discovery from acquisition, follow an incremental
path toward meeting user needs, match resources and requirements at
program start, and use quantifiable data and demonstrable knowledge to
make decisions to move to next phases. We have also identified
practices related to cost estimating, program manager tenure, quality
assurance, technology transition, and an array of other aspects of
acquisition program management that could benefit space programs.
These practices are highlighted in appendix I.
Actions to Improve Space and Weapon System Acquisitions:
Over the past several years, DOD has implemented or has been
implementing a number of actions to reform how space and weapon
systems are acquired, both through its own initiatives as well as
those required by statute. Additionally, DOD is evaluating and
proposing new actions to increase space system acquisition efficiency
and effectiveness. Because many of these actions are relatively new,
or not yet fully implemented, it is too early to tell whether they
will be effective or effectively implemented.
For space in particular, DOD is working to ensure that critical
technologies are matured before large-scale acquisition programs
begin, requirements are defined early in the process and are stable
throughout, and system design remains stable. DOD also intends to
follow incremental or evolutionary acquisition processes versus
pursuing significant leaps in capabilities involving technology risk
and has done so with the only new major satellite program undertaken
by the Air Force in recent years--GPS IIIA. DOD is also providing more
program and contractor oversight and putting in place military
standards and specifications in its acquisitions. Additionally, DOD
and the Air Force are working to streamline management and oversight
of the national security space enterprise. For example, all Air Force
space system acquisition responsibility has been aligned to the office
that has been responsible for all other Air Force acquisition efforts,
and the Defense Space Council--created last year--is reviewing, as one
of its first agenda items, options for streamlining the many
committees, boards, and councils involved in space issues. These and
other actions that have been taken or are being taken that could
improve space system acquisition outcomes are described in table 2.
Table 2: Actions Taken or Being Taken That Could Benefit Space System
Acquisition Outcomes:
Category: National policy;
Actions:
* In June 2010, the President of the United States issued the new
National Space Policy which establishes overarching national policy
for the conduct of U.S. space activities. The policy states that the
Secretary of Defense and the Director of National Intelligence are
responsible for developing, acquiring, and operating space systems and
supporting information systems and networks to support U.S. national
security and enable defense and intelligence operations. The policy
helps to clarify the Secretary of Defense's roles and responsibilities
for coordinating space system acquisitions that span DOD and federal
agencies, such as those for space situational awareness;
* In January 2011, the Secretary of Defense and the Director of
National Intelligence issued the National Security Space Strategy to
build on the National Space Policy and help inform planning,
programming, acquisition, operations, and analysis.
Category: Acquisition policy;
Actions:
* We expressed concern over DOD's tailored national security space
acquisition policy--initially issued in 2003--primarily because it did
not alter DOD's practice of committing to major investments before
knowing what resources will be required to deliver promised
capability. Instead, the policy encouraged development of leading-edge
technology within product development, that is, at the same time the
program manager is designing the system and undertaking other product
development activities. In 2009, DOD eliminated the space acquisition
policy and moved the acquisition of space systems under DOD's updated
acquisition guidance for defense acquisition programs (DOD Instruction
5000.02). In October 2010, the Under Secretary of Defense for
Acquisition, Technology and Logistics issued a new space acquisition
policy to be incorporated into DOD Instruction 5000.02 that introduces
specific management and oversight processes for acquiring major space
systems, including retaining the requirement for independent program
assessments to be conducted prior to major acquisition milestones.
Category: Management and oversight;
Actions:
* In August 2010, the Secretary of Defense announced the elimination
of the Office of the Assistant Secretary of Defense for Networks and
Information Integration (ASD/NII) as part of a broader effort to
eliminate organizations that perform duplicative functions or that
have outlived their purpose.[A] The elimination of this organization
may help to reduce the problems associated with the wide range of
stakeholders within DOD responsible for overseeing the development of
space-based capabilities;
* In May 2009, Air Force leadership signed the Acquisition Improvement
Plan which lists five initiatives for improving how the Air Force
obtains new capabilities.[B] One of these initiatives relates to
establishing clear lines of authority and accountability within
acquisition organizations. In August 2010, the Secretary of the Air
Force transferred space system acquisition responsibility from the
Under Secretary of the Air Force to the Assistant Secretary of the Air
Force for Acquisition, thereby aligning all Air Force acquisition
responsibility to one office. As part of this realignment, the Program
Executive Officer for Space now reports to the Assistant Secretary of
the Air Force for Acquisition (previously, the Program Executive
Officer for Space reported to the Under Secretary of the Air Force);
* In November 2010, the Deputy Secretary of Defense authorized the
disestablishment of the National Security Space Office (NSSO).[C] The
elimination of this office may also help to streamline national
security space system acquisition management and oversight.
Furthermore, the Deputy Secretary of Defense revalidated the Secretary
of the Air Force as DOD Executive Agent for Space and directed the
creation of a Defense Space Council (DSC)--chaired by the DOD
Executive Agent for Space and with representatives from across DOD--to
inform, coordinate, and resolve space issues for DOD. The DSC held its
first meeting in December 2010. According to DOD, first on the
council's agenda was streamlining the many defense and national
security space committees, boards, and councils by reviewing more than
15 space-related organizations and making recommendations on their
cancellation, consolidation, dissolution, or realignment under the DSC.
Category: Requirements;
Actions:
* Another of the Air Force's Acquisition Improvement Plan initiatives
covers requirements generation and includes the direction for the Air
Force to certify that the acquisition community can successfully
fulfill required capabilities in conjunction with the Air Force
Requirements for Operational Capabilities Council. Certification means
the required capabilities can be translated in a clear and unambiguous
way for evaluation in a source selection, are prioritized if
appropriate, and are organized into feasible increments of capability.
Category: Program management assistance;
Actions:
* The Space and Missile Systems Center--the Air Force's primary
organization responsible for acquiring space systems--resurrected a
program management assistance group in 2007 to help mitigate program
management, system integration, and program control deficiencies
within specific ongoing programs. This group assists and supplements
wing commanders and program offices in fixing common problems, raising
core competencies, and providing a consistent culture that sweeps
across programs. As we reported last year, the GPS Wing Commander
stated this group was an integral part of the overall process
providing application-oriented training, templates, analyses, and
assessments vital to the GPS IIIA baseline review. According to a
senior program management assistance group official, the group has
provided assistance to other major programs, including GPS OCX, SBIRS
High, and SBSS.
Category: Workforce;
Actions:
* Another initiative in the Air Force's Acquisition Improvement Plan
is to revitalize the acquisition workforce by, among other things,
increasing the number of authorized positions and providing for
additional hiring, examining the proper mix of military and civilian
personnel, and establishing training and experience objectives as part
of the career paths for each acquisition specialty and increasing the
availability of specialized training. Also, as we reported last year,
the Air Force was continuing efforts to bring space operators and
space system acquirers together through the Advanced Space Operations
School and the National Security Space Institute. The Air Force
anticipated that this higher-level education would be integral to
preparing space leaders with the best acquisition know-how.
Category: Cost estimating;
Actions:
* The Air Force took actions to strengthen cost estimating. For
example, we recommended that the Secretary of the Air Force ensure
that cost estimates are updated as major events occur within a program
that could have a material impact on cost, and that the roles and
responsibilities of the various Air Force cost-estimating
organizations be clearly articulated.[D] An Air Force policy directive
now requires that cost estimates for major programs be updated
annually, and lays out roles and responsibilities for Air Force cost-
estimating organizations. Additionally, the Joint Space Cost Council--
formed in 2007 with membership across industry and military and civil
government agencies--is actively working to improve cost credibility
and realism in estimates, budgets, schedules, data, proposals, and
program execution. For example, one initiative has developed a
standard work breakdown structure that is being vetted through
industry and government.
Category: Military standards;
Actions:
* Over the last several years, the Air Force Space and Missile Systems
Center has taken action aimed at preventing parts quality problems by
issuing policy relating to specifications and standards. It is
requiring the GPS IIIA program development contractor to meet these
specifications and standards.
Source: GAO analysis of DOD data and previous GAO reports.
[A] The ASD/NII's responsibilities included serving as the principal
staff assistant on nonintelligence space matters; information
technology, including National Security Systems; information resource
management; and sensitive information integration. The ASD/NII also
served as the principal staff assistant for issues such as command and
control and net-centric capabilities.
[B] The Secretary of the Air Force and Chief of Staff of the Air Force
issued the Acquisition Improvement Plan to recapture acquisition
excellence by rebuilding an Air Force acquisition culture that
delivers products and services as promised--on time, within budget,
and in compliance with all laws, policies, and regulations. The plan
consists of five initiatives: (1) revitalize the Air Force acquisition
workforce, (2) improve the requirements generation process, (3)
instill budget and financial discipline, (4) improve major Air Force
systems source selections, and (5) establish clear lines of authority
and accountability within acquisition organizations.
[C] As part of this direction, the Deputy Secretary of Defense
authorized the establishment of a jointly manned space office to
restructure and replace the NSSO. The NSSO supported the Secretary of
the Air Force who, as the DOD Executive Agent for Space, was
responsible for developing, coordinating, and integrating plans and
programs for space systems and the acquisition of DOD space major
defense acquisition programs, and was responsible for executing the
space major defense acquisition programs, when delegated that
authority by the Under Secretary of Defense for Acquisition,
Technology and Logistics. The specific roles and responsibilities of
the DOD Executive Agent for Space are defined in Department of Defense
Directive 5101.2, DOD Executive Agent for Space (June 3, 2003).
[D] GAO, Space Acquisitions: DOD Needs to Take More Action to Address
Unrealistic Initial Cost Estimates of Space Systems, GAO-07-96
(Washington, D.C.: Nov. 17, 2006).
[End of table]
At the DOD-wide level, and as we reported last year, Congress and DOD
have recently taken major steps toward reforming the defense
acquisition system in ways that may increase the likelihood that
weapon programs will succeed in meeting planned cost and schedule
objectives.[Footnote 5] In particular, new DOD policy and legislative
provisions place greater emphasis on front-end planning and
establishing sound business cases for starting programs.[Footnote 6]
For example, the provisions require programs to invest more time and
resources to refine concepts through practices such as early systems
engineering, strengthen cost estimating, develop technologies, build
prototypes, hold early milestone reviews, and develop preliminary
designs before starting system development. These provisions are
intended to enable programs to refine a weapon system concept and make
cost, schedule, and performance trade-offs before significant
commitments are made. In addition, DOD policy requires establishment
of configuration steering boards that meet annually to review program
requirements changes as well as to make recommendations on proposed
descoping options that could reduce program costs or moderate
requirements. Fundamentally, these provisions should help (1) programs
replace risk with knowledge and (2) set up more executable programs.
Key DOD and legislative provisions compared with factors we identified
in programs that have been successful in meeting cost and schedule
baselines are summarized in table 3.
Table 3: Comparison of Factors Contributing to Meeting Cost and
Schedule Goals and Recent Acquisition Reform Initiatives:
Success factor:
* Establish a sound, executable business case;
Recent acquisition reform initiatives:
* Overall, strong emphasis on front-end planning (pre-systems
acquisition).
Success factor:
* Incremental approach to acquiring capabilities;
Recent acquisition reform initiatives:
* Incremental development emphasized, with each increment that
provides a significant increase in capability to be managed separately.
Success factor:
* Clear, well-defined requirements;
Recent acquisition reform initiatives:
* Early reviews to be conducted prior to start of development
(Milestone B);
* Enhanced requirements for Analysis of Alternatives;
* New leadership positions established to enhance systems engineering
and developmental testing.
Success factor:
* Leverage mature technologies;
Recent acquisition reform initiatives:
* Independent review of technology maturity and integration risk prior
to Milestone B;
* Competitive prototypes;
* Preliminary Design Review to be conducted earlier, prior to
Milestone B.
Success factor:
* Establish realistic cost and schedule estimates;
Recent acquisition reform initiatives:
* New position and organization established to review and conduct
independent cost estimates for major defense acquisition programs and
provide cost-estimating guidance DOD-wide;
* Early cost estimate required for Milestone A;
* Confidence level for cost estimates to be reported.
Execute business case in disciplined manner:
Success factor:
* Resist new requirements;
Recent acquisition reform initiatives:
* Configuration steering boards established to stabilize requirements;
* Post-Critical Design Review assessment required to review progress.
Source: GAO analysis of the Weapon Systems Acquisition Reform Act of
2009, Pub. L. No. 111-23 and Department of Defense Instruction 5000.02
(Dec. 8, 2008).
[End of table]
Furthermore, the Ike Skelton National Defense Authorization Act for
Fiscal Year 2011, signed into law on January 7, 2011, contains further
direction aimed at improving acquisition outcomes, including, among
other things, a requirement for the Secretary of Defense to issue
guidance on the use of manufacturing readiness levels (including
specific levels that should be achieved at key milestones and decision
points), elevating the role of combatant commanders in DOD's
requirements-setting process, and provisions for improving the
acquisition workforce.[Footnote 7]
While it is too soon to determine if Congress's and DOD's reform
efforts will improve weapon program outcomes, DOD has taken steps to
implement the provisions. For example, in December 2009, the
department issued a new implementation policy, which identifies roles
and responsibilities and institutionalizes many of the requirements of
the Weapon Systems Acquisition Reform Act of 2009. DOD has also filled
several key leadership positions created by the legislation, including
the Directors for Cost Assessment and Program Evaluation,
Developmental Test and Evaluation, Systems Engineering, and
Performance Assessments and Root Cause Analyses. To increase
oversight, the department embarked on a 5-year effort to increase the
size of the acquisition workforce by up to 20,000 personnel by 2015.
Furthermore, the department began applying the acquisition reform
provisions to some new programs currently in the planning pipeline.
For example, many of the pre-Milestone B programs we reviewed this
year as part of our annual assessment of selected weapon programs
planned to conduct preliminary design reviews before going to
Milestone B, although fewer are taking other actions, such as
developing prototypes, that could improve their chances of success.
With respect to space system acquisitions, particularly GPS III--DOD's
newest major space system acquisition--has embraced the knowledge-
based concepts behind our previous recommendations as a means of
preventing large cost overruns and schedule delays.
Additionally, the Office of the Secretary of Defense and the Air Force
are proposing new acquisition strategies for satellites and launch
vehicles:
* In June of last year, and as part of the Secretary of Defense's
Efficiencies Initiative,[Footnote 8] the Under Secretary of Defense
for Acquisition, Technology and Logistics began an effort to restore
affordability and productivity in defense spending. Major thrusts of
this effort include targeting affordability and controlling cost
growth, incentivizing productivity and innovation in industry,
promoting real competition, improving tradecraft in services
acquisition, and reducing nonproductive processes and bureaucracy. As
part of this effort, the Office of the Secretary of Defense and the
Air Force are proposing a new acquisition strategy for procuring
satellites, called the Evolutionary Acquisition for Space Efficiency
(EASE), to be implemented starting in fiscal year 2012. Primary
elements of this strategy include block buys of two or more satellites
(economic order quantities) using a multiyear procurement construct,
use of fixed-price contracting, stable research and development
investment, evolutionary development, and stable requirements.
According to DOD, EASE is intended to help stabilize funding,
staffing, and subtier suppliers; help ensure mission continuity;
reduce the impacts associated with obsolescence and production breaks;
and increase long-term affordability with cost savings of over 10
percent. DOD anticipates first applying the EASE strategy to procuring
two AEHF satellites beginning in fiscal year 2012, followed by
procurement of two SBIRS High satellites beginning in fiscal year
2013. According to the Air Force, it will consider applying the EASE
strategy--once it is proven--to other space programs, such as GPS III.
We have not yet conducted a review of the EASE strategy to assess the
potential benefits, challenges, and risks of its implementation.
Questions about this approach would include the following:
- What are the major risks incurred by the government in utilizing the
EASE acquisition strategy?
- What level of risks (known unknowns and unknown unknowns) is being
assumed in the estimates of savings to be accrued from the EASE
strategy?
- How are evolutionary upgrades to capabilities to be pursued under
EASE?
- How does the EASE acquisition strategy reconcile with the current
federal and DOD acquisition policy, acquisition and financial
management regulations, and law?
* The Air Force is developing a new acquisition strategy for its EELV
program. Primarily, under the new strategy, the Air Force and National
Reconnaissance Office are expected to initiate block buys of eight
first stage booster cores--four for each EELV family, Atlas V and
Delta IV--per year over 5 years to help stabilize the industrial base,
maintain mission assurance, and avoid cost increases. As mentioned
earlier, we have initiated a review of the development of the new
strategy and plan to issue a report on our findings in June 2011.
Given concerns raised through recent studies about visibility into
costs and the industrial base supporting EELV, it is important that
this strategy be supported with reliable and accurate data.
Additional Actions Leadership, Organization, and Support May Still Be
Needed:
The actions that the Office of the Secretary of Defense and the Air
Force have been taking to address acquisition problems listed in
tables 2 and 3 are good steps. However, more changes to processes,
policies, and support may be needed--along with sustained leadership
and attention--to help ensure that these reforms can take hold,
including addressing the diffuse leadership for space programs.
Diffuse leadership has had a direct impact on the space system
acquisition process, primarily because it has made it difficult to
hold any one person or organization accountable for balancing needs
against wants, for resolving conflicts among the many organizations
involved with space, and for ensuring that resources are dedicated
where they need to be dedicated. This has hampered DOD's ability to
synchronize delivery of space, ground, and user assets for space
programs. For instance, many of the cost and schedule problems we
identified on the GPS program were tied in part to diffuse leadership
and organizational stovepipes throughout DOD, particularly with
respect to DOD's ability coordinate delivery of space, ground, and
user assets. Additionally, we have recently reported that DOD faces a
situation where satellites with advances in capability will be
residing for years in space without users being able to take full
advantage of them because investments and planning for ground, user,
and space components were not well coordinated.[Footnote 9]
Specifically, we found that the primary cause for user terminals not
being well synchronized with their associated space systems is that
user terminal development programs are typically managed by different
military acquisition organizations than those managing the satellites
and ground control systems.
Recent studies and reviews examining the leadership, organization, and
management of national security space have found that there is no
single authority responsible below the President and that authorities
and responsibilities are spread across the department.[Footnote 10] In
fact, the national security space enterprise comprises a wide range of
government and nongovernment organizations responsible for providing
and operating space-based capabilities serving both military and
intelligence needs.
While some changes to the leadership structure have recently been
made--including revalidating the role of the Secretary of the Air
Force as the DOD Executive Agent for Space, disestablishing the Office
of the Assistant Secretary of Defense for Networks and Information
Integration and the National Security Space Office, and aligning Air
Force space system acquisition responsibility into a single Air Force
acquisition office--and others are being studied, it is too early to
tell how effective these changes will be in streamlining management
and oversight of space system acquisitions. Additionally, while the
recently issued National Space Policy assigns responsibilities for
governmentwide space capabilities, such as those for SSA, it does not
necessarily assign the corresponding authority to execute the
responsibilities.
Finally, adequate workforce capacity is essential for the front-end
planning activities now required by acquisition reform initiatives for
new weapon programs to be successful. However, studies have identified
insufficient numbers of experienced space system acquisition personnel
and inadequate continuity of personnel in project management positions
as problems needing to be addressed in the space community. For
example, a recent Secretary of the Air Force-directed Broad Area
Review of space launch noted that while the Air Force Space and
Missile Systems Center workforce had decreased by about 25 percent in
the period from 1992 to 2010, the number of acquisition programs had
increased by about 41 percent in the same time period.[Footnote 11]
Additionally, our own studies have identified gaps in key technical
positions, which we believed increased acquisition risks. For
instance, in a 2008 review of the EELV program, we found that
personnel shortages in the EELV program office occurred particularly
in highly specialized areas.[Footnote 12] According to the EELV
program office and Broad Area Review, this challenge persists.
Concluding Remarks:
DOD is working to position itself to improve its space system
acquisitions. After more than a decade of acquisition difficulties--
which have created potential gaps in capability, diminished DOD's
ability to invest in new space systems, and lessened DOD's credibility
to deliver high-performing systems within budget and on time--DOD is
starting to launch new generations of satellites that promise vast
enhancements in capability. In 1 year, DOD has or expects to have
launched newer generations of navigation, communications, SSA, and
missile warning satellites. Moreover, given the nation's fiscal
challenges, DOD's focus on fixing problems and implementing reforms
rather than taking on new, complex, and potentially higher-risk
efforts is promising. However, challenges to keeping space system
acquisitions on track remain, including pursuing evolutionary
acquisitions over revolutionary ones, managing requirements, providing
effective coordination across the diverse organizations interested in
space-based capabilities, and ensuring that technical and programmatic
expertise are in place to support acquisitions. DOD's newest major
space system acquisition efforts, such as GPS IIIA, DWSS, JMS, Space
Fence, and the follow-on to the SBSS will be key tests of how well
DOD's reforms and reorganizations have positioned it to manage these
challenges. We look forward to working with DOD to help ensure that
these and other challenges are addressed.
Chairman Nelson, Ranking Member Sessions, this completes my prepared
statement. I would be happy to respond to any questions you or other
Members of the Subcommittee may have at this time.
Contacts and Acknowledgments:
For further information about this statement, please contact Cristina
Chaplain at (202) 512-4841 or chaplainc@gao.gov. Contact points for
our Offices of Congressional Relations and Pubic Affairs may be found
on the last page of this statement. Individuals who made key
contributions to this statement include Art Gallegos, Assistant
Director; Kristine Hassinger; Arturo Holguín; Rich Horiuchi; Roxanna
Sun; and Bob Swierczek.
[End of section]
Appendix I: Actions Needed to Address Space and Weapon Acquisition
Problems:
Before undertaking new programs:
* Prioritize investments so that projects can be fully funded and it
is clear where projects stand in relation to the overall portfolio.
* Follow an evolutionary path toward meeting mission needs rather than
attempting to satisfy all needs in a single step.
* Match requirements to resources--that is, time, money, technology,
and people--before undertaking a new development effort.
* Research and define requirements before programs are started and
limit changes after they are started.
* Ensure that cost estimates are complete, accurate, and updated
regularly.
* Commit to fully fund projects before they begin.
* Ensure that critical technologies are proven to work as intended
before programs are started.
* Assign more ambitious technology development efforts to research
departments until they are ready to be added to future generations
(increments) of a product.
* Use systems engineering to close gaps between resources and
requirements before launching the development process.
During program development:
* Use quantifiable data and demonstrable knowledge to make go/no-go
decisions, covering critical facets of the program such as cost,
schedule, technology readiness, design readiness, production
readiness, and relationships with suppliers.
* Do not allow development to proceed until certain thresholds are
met--for example, a high proportion of engineering drawings completed
or production processes under statistical control.
* Empower program managers to make decisions on the direction of the
program and to resolve problems and implement solutions.
* Hold program managers accountable for their choices.
* Require program managers to stay with a project to its end.
* Hold suppliers accountable to deliver high-quality parts for their
products through such activities as regular supplier audits and
performance evaluations of quality and delivery, among other things.
* Encourage program managers to share bad news, and encourage
collaboration and communication.
Source: GAO.
[End of table]
[End of section]
Appendix II:
[End of section]
Scope and Methodology:
In preparing this testimony, we relied on our body of work in space
programs, including previously issued GAO reports on assessments of
individual space programs, common problems affecting space system
acquisitions, and the Department of Defense's (DOD) acquisition
policies. We relied on our best practices studies, which comment on
the persistent problems affecting space system acquisitions, the
actions DOD has been taking to address these problems, and what
remains to be done, as well as Office of the Secretary of Defense and
Air Force documents addressing these problems and actions. We also
relied on work performed in support of our annual weapons system
assessments, and analyzed DOD funding estimates to assess cost
increases and investment trends for selected major space system
acquisition programs. The GAO work used in preparing this statement
was conducted in accordance with generally accepted government
auditing standards. Those standards require that we plan and perform
the audit to obtain sufficient, appropriate evidence to provide a
reasonable basis for our findings and conclusions based on our audit
objectives. We believe that the evidence obtained provides a
reasonable basis for our findings and conclusions based on our audit
objectives.
[End of section]
Footnotes:
[1] The $18 billion does not include the cost of two replenishment
sensors, which the Air Force does not include as part of the SBIRS
High baseline.
[2] GAO, Global Positioning System: Challenges in Sustaining and
Upgrading Capabilities Persist, [hyperlink,
http://www.gao.gov/products/GAO-10-636] (Washington, D.C., Sept. 15,
2010) and Space Acquisitions: Challenges in Commercializing
Technologies Developed under the Small Business Innovation Research
Program, [hyperlink, http://www.gao.gov/products/GAO-11-21]
(Washington, D.C.: Nov. 10, 2010).
[3] GAO, Global Positioning System: Significant Challenges in
Sustaining and Upgrading Widely Used Capabilities, [hyperlink,
http://www.gao.gov/products/GAO-09-325] (Washington, D.C.: Apr. 30,
2009).
[4] The Small Business Innovation Development Act of 1982, Pub. L. No.
97-219, established the SBIR program to stimulate technological
innovation, use small businesses to meet federal research and
development needs, foster and encourage participation by minority and
disadvantaged persons in technological innovation, and increase
private-sector commercialization of innovations derived from federal
research and development.
[5] GAO, Defense Acquisitions: Strong Leadership Is Key to Planning
and Executing Stable Weapon Programs, [hyperlink,
http://www.gao.gov/products/GAO-10-522] (Washington, D.C.: May 6,
2010).
[6] In December 2008, DOD revised its acquisition instruction--
Department of Defense Instruction 5000.02, Operation of the Defense
Acquisition System. The Weapon Systems Acquisition Reform Act of 2009,
Pub. L. No. 111-23, was enacted May 22, 2009.
[7] Pub. L. No. 111-383.
[8] In May 2010, the Secretary of Defense announced the Defense
Efficiencies Initiative to increase efficiencies, reduce overhead
costs, and eliminate redundant functions in order to improve the
effectiveness of the DOD enterprise. The goal is to apply savings from
this initiative to force structure and modernization.
[9] GAO, Defense Acquisitions: Challenges in Aligning Space System
Components, [hyperlink, http://www.gao.gov/products/GAO-10-55]
(Washington, D.C.: Oct. 29, 2009).
[10] Institute for Defense Analyses, Leadership, Management, and
Organization for National Security Space: Report to Congress of the
Independent Assessment Panel on the Organization and Management of
National Security Space (Alexandria, Va., July 2008), and House
Permanent Select Committee on Intelligence, Report on Challenges and
Recommendations for United States Overhead Architecture (Washington,
D.C., Oct. 2008).
[11] Institute for Defense Analyses, Launch Broad Area Review 2010
(BAR-X) (Alexandria, Va., June, 2010).
[12] GAO, Space Acquisitions: Uncertainties in the Evolved Expendable
Launch Vehicle Program Pose Management and Oversight Challenges,
[hyperlink, http://www.gao.gov/products/GAO-08-1039] (Washington,
D.C.: Sept. 26, 2008).
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: