Construction Management Problems Have Delayed Completion of the New Plutonium Facilities at Rocky Flats, Colorado

Gao ID: PSAD-78-90 June 2, 1978

Cost, schedule, and performance data of new plutonium facilities under construction at Rocky Flats, Colorado, and Los Alamos, New Mexico, were reviewed. Both projects are under the administration and management of the Department of Energy's Albuquerque Operations Office (A00). The Rocky Flats nuclear weapons plant is the key producer of plutonium parts used in nuclear weapons, and the Los Alamos Scientific Laboratory is one of the agency's two nuclear weapons research and development facilities.

Unnecessary cost growth and schedule delays were experienced at the Rocky Flats project because of poor design control, unrealistic schedules, premature contract awards for mechanical equipment installations, and poor estimating and cost control practices. The AOO compounded cost and schedule problems by not exercising adequate project management. It relied on its contractors to manage the project, and its success or failure depended on the contractor's performance rather than on agency management. AOO employed similar organizational and management approaches at Rocky Flats and Los Alamos, but the Los Alamos project was more successful because the agency and its contractors worked together more effectively. New procedures implemented by AOO should improve the management of future construction projects.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: No director on record Team: No team on record Phone: No phone on record


The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.