Lessons Learned from Constructing the Trans-Alaska Oil Pipeline

Gao ID: EMD-78-52 June 15, 1978

In 1968, a feasibility cost study estimated that an oil pipeline system from Prudhoe Bay to Valdez, Alaska, would cost $863 million for a 500,000 barrel-a-day line or $1.046 billion for a 1.2 million barrel-a-day capacity. After construction began in 1975, the Alyeska Pipeline Service Company, the agent for the companies designing and building the pipeline, established a base control budget of about $6.4 billion. By December 1977, this budget had been exceeded by about $1.5 billion. The $19.8 million additional direct labor hours needed to complete the project accounted for most of the $1.5 billion increase.

Several key lessons can be learned from Alyeska's experience and applied to similar future projects: (1) first and subsequent cost estimates should be viewed with skepticism; (2) as much site-specific data as is economically practicable should be obtained; (3) technical and geological uncertainties should be thoroughly investigated; (4) government approval should be contingent on detailed planning for management control, including budgetary controls; and (5) the Alaska natural gas pipeline project's expenditures should have an ongoing government audit to protect the public interest. Alyeska's contract with its execution contractors were reimbursable cost-plus-fixed-fee and fixed overhead; the contractors did not have the financial incentive to minimize costs as they would have had under other contractual arrangements such as fixed-price contracts. Alyeska's experience showed that the no-strike clause in the project labor agreement prevented section-wide or project-wide strikes. Contractor personnel generally interpreted the environmental requirements less restrictively than did government personnel, and Alyeska had to make some adjustments to accomodate the government's interpretation.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.