Although new natural gas legislation has made major changes in the regulation of natural gas supplies, gas already flowing in the interstate system prior to the new act generally remains dedicated to the interstate market unless an abandonment authorization is approved. Because of possible unauthorized diversion of these supplies to more profitable markets, a review was done of the Federal Energy Regulatory Commission's (FERC) control over them.

The review found that natural gas has been diverted from interstate commerce to more profitable intrastate markets. Interstate sources of natural gas have been abandoned without FERC approval. Procedures for detecting abandonments and diversions have only recently been addressed by FERC and need strengthening. The authority to assess civil penalties against violators was needed. The extent to which the natural gas supplies have been diverted was difficult to ascertain. Recent instances of natural gas supply shortages may have been caused by these diversions.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: No director on record Team: No team on record Phone: No phone on record


The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.