Nuclear Waste

Status of DOE's Nuclear Waste Site Characterization Activities Gao ID: RCED-87-103FS March 20, 1987

Pursuant to a congressional request, GAO reviewed the status of the Department of Energy's (DOE) planned site characterization activities under the Nuclear Waste Policy Act of 1982.

GAO found that: (1) in January 1987, DOE extended some site characterization milestones by 5 years; (2) each site had unique technical problems that DOE needed to resolve, including the potential for radioactive groundwater contamination, and unforeseen construction problems; (3) existing cost estimates were very tentative because site characterization costs were greatly affected by the amount of time needed to complete the phase; and (4) the Office of Civilian Radioactive Waste Management developed a comprehensive quality assurance program as a viable part of its construction license application.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.