Ineffective Management and Oversight of DOE's P-Reactor at Savannah River, S.C., Raises Safety Concern

Gao ID: T-RCED-88-68 September 30, 1988

GAO discussed the recent events surrounding the start-up of the Department of Energy's (DOE) P-reactor at the Savannah River Plant, focusing on how well DOE managed the contractors who operated the facility. GAO found that: (1) reactor operators failed to inform either management or DOE of a restart problem until the nuclear reactor shut itself down; (2) reactor operators did not inform DOE of a small power increase until the next day; and (3) DOE ordered the reactor shut down until the contractor could address DOE safety and communications concerns. GAO also found that: (1) DOE and the contractor failed to ensure start-up operational safety; (2) DOE and the contractor failed to properly calculate start-up reactivity; and (3) DOE approved the restart based on the contractor's explanation without an assessment or complete understanding of the explanation. GAO believes that DOE needs: (1) strong line-management responsibility and accountability for safety; (2) an effective environmental safety and health organization to oversee how line management carries out its role; (3) an independent organization outside DOE control to oversee the DOE internal safety program; and (4) to ensure that it addresses safety concerns in a timely and effective manner.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.