The Energy Department's (DOE) nuclear material and facility stabilization program, created in 1992, has become a major part of DOE's environmental management efforts. At the beginning of fiscal year 1995, DOE was planning to spend $813 million on managing surplus facilities that were awaiting decontamination and decommissioning and on providing electrical, transportation, and other landlord-type services at key environmental management sites near Hanford, Washington; Idaho Falls, Idaho; and Rocky Flats, Colorado. DOE officials say that they can reduce future program costs by deactivating surplus facilities--which involves removing radioactive and hazardous materials that DOE must otherwise safeguard and monitor until the facilities are decontaminated and decommissioned--and by upgrading inefficient utilities and other services at sites managed by the program. This report (1) determines the proportion of the program's fiscal year 1995 budget that is allocated to projects that could reduce the program's future costs, (2) estimates the difference between the savings that these projects could generate and the costs DOE could incur to obtain these savings, and (3) determines the reliability of DOE's estimates for net savings from major deactivation projects.

GAO found that DOE: (1) has allocated about 31 percent of the program's available FY 1995 funding to 24 deactivation projects at three key sites to reduce future program costs; (2) could realize a combined net savings of $458 million from 11 projects over 10 to 30 years; (3) has not developed a process for consistently estimating the net savings from deactivation projects, resulting in its inability to develop reliable or complete estimates of potential net savings from these projects; and (4) must be able to target funds more effectively, since it expects that the number of facilities managed by the program may increase from 1,560 to about 5,900 facilities by 1997.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone:


The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.