Department of Energy

Uncertainties and Management Problems Have Hindered Cleanup at Two Nuclear Waste Sites Gao ID: T-RCED-00-248 July 12, 2000

This testimony describes the challenges and uncertainties facing the Department of Energy (DOE) in the Paducah, Kentucky, uranium cleanup and the oversight and management of the in-tank precipitation project at Savannah River. DOE expects to complete the Paducah cleanup by 2010 at a cost of about $1.3 billion. However, billions of dollars and many years will be needed to address areas at the Paducah site that are not in the cleanup plan, such as the nearly 1 million cubic feet of waste and scrap in a storage area and 16 unused and inactive buildings and structures. By not including these areas in the plan, the Paducah cleanup managers cannot assess risk or plan cleanup on a comprehensive basis. Therefore, the picture of the cleanup task is distorted. It took DOE and its contractor, the Westinghouse Savannah River Corporation, a decade and nearly half a billion dollars to decide that the in-tank precipitation process would not work safely and efficiently as designed. Furthermore, (1) the contractor tended to react to problems after they occurred; (2) DOE lacked the necessary personnel to ensure adequate oversight of the project; (3) DOE and Westinghouse began construction before the design was completed; and (4) neither understood the cause of the technical problems, fundamentally because they did not understand the chemistry involved in the process.

GAO noted that: (1) DOE expects to complete the cleanup of the Paducah site by 2010 at a cost of about $1.3 billion; (2) however, numerous technical, funding, and regulatory uncertainties present challenges to DOE's ability to complete the cleanup within this timeframe and cost estimate; (3) technical uncertainties include the planned use of technologies that are unproven or perhaps not well suited to the site's conditions; (4) even when the planned cleanup has been carried out, billions of dollars and many years will be needed to address areas at the Paducah site that are not in the cleanup plan; (5) for example, the plan does not include cleaning up nearly 1 million cubic feet of waste and scrap in areas known as DOE Material Storage Areas and 16 unused and inactive buildings and structures; (6) some of the waste and scrap material pose a risk of an uncontrolled nuclear reaction that could threaten worker safety; (7) by not including these areas in the plan, the Paducah cleanup managers cannot assess risk or plan cleanup on a comprehensive, sitewide basis; (8) therefore, the picture of the cleanup task at hand is distorted; (9) a number of management and oversight problems caused DOE and Westinghouse Savannah River Corporation, DOE's contractor, to spend almost a half billion dollars and to take about a decade before deciding that the ITP process would not work safely and efficiently as designed; (10) for example, in 1993, a technical review team reported that the contractor tended to react to problems after they occurred, rather than working to prevent them in the first place; (11) the team also found that DOE lacked the necessary personnel for adequate oversight; (12) DOE and the contractor encountered delays in starting up the ITP facility because they had begun construction before the design of the process was completed; (13) DOE and the contractor encountered delays in starting up the ITP facility because they had begun construction before the design of the process was completed; (14) DOE and the contractor also did not adequately understand the cause of the technical problems--such as a lack of understanding of the chemistry involved in the ITP process--that made the process unworkable; (15) problems that led to the ITP failure may have continued in DOE's efforts to find an alternative; and (16) an October 1999 National Research Council report states that contractors appear to be focusing on an engineering solution on the basis of untested assumptions.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.