Nuclear Security
DOE Needs to Resolve Significant Issues Before It Fully Meets the New Design Basis Threat
Gao ID: GAO-04-623 April 27, 2004
A successful terrorist attack on Department of Energy (DOE) sites containing nuclear weapons or the material used in nuclear weapons could have devastating consequences for the site and its surrounding communities. Because of these risks, DOE needs an effective safeguards and security program. A key component of an effective program is the design basis threat (DBT), a classified document that identifies the potential size and capabilities of terrorist forces. The terrorist attacks of September 11, 2001, rendered the then-current DBT obsolete. GAO examined DOE's response to the September 11, 2001, terrorist attacks, identified why DOE took almost 2 years to develop a new DBT, analyzed the higher threat in the new DBT, and identified the remaining issues that need to be resolved in order for DOE to meet the threat contained in the new DBT.
DOE took a series of actions in response to the terrorist attacks of September 11, 2001. While each of these has been important, DOE must press forward with additional actions to ensure that it is fully prepared to provide a timely and cost effective defense. DOE took immediate steps to improve physical security in the aftermath of the September 11, 2001, terrorist attacks. DOE's most visible effort involved moving to higher levels of security readiness, known as security condition (SECON) levels. While this effort has increased the visible deterrence at DOE sites, it has been expensive and has resulted in fatigue, retention problems, and less training for most sites' protective forces. In addition, the effectiveness of these increased SECON levels generally have not been assessed using the vulnerability assessment tools, such as computer modeling and full-scale force-on-force exercises, that DOE routinely uses to develop protective force strategies for its sites. Development of the new DBT took almost 2 years because of (1) delays in developing an intelligence community assessment--known as the Postulated Threat--of the terrorist threat to nuclear weapon facilities and (2) DOE's lengthy comment and review process for developing policy. In addition, during the DBT development process, there were sharp debates within DOE and other government organizations over the size and capabilities of future terrorist threats and the availability of resources to meet these threats that contributed to the delay. While the May 2003 DBT identifies a larger terrorist threat than did the previous DBT, the threat identified in the new DBT in most cases is less than the threat identified in the intelligence community's Postulated Threat, on which the DBT has been traditionally based. The new DBT identifies new possible terrorist acts such as radiological, chemical, or biological sabotage. However, the criteria that DOE has selected for determining when facilities may need to be protected against these forms of sabotage may not be sufficient. DOE has been slow to resolve a number of significant issues, such as issuing additional DBT implementation guidance, developing DBT implementation plans, and developing budgets to support these plans, that may affect the ability of its sites to fully meet the threat contained in the new DBT in a timely fashion. Consequently, DOE's deadline to meet the requirements of the new DBT by the end of fiscal year 2006 is probably not realistic for some sites.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-04-623, Nuclear Security: DOE Needs to Resolve Significant Issues Before It Fully Meets the New Design Basis Threat
This is the accessible text file for GAO report number GAO-04-623
entitled 'Nuclear Security: DOE Needs to Resolve Significant Issues
Before It Fully Meets the New Design Basis Threat' which was released
on April 27, 2004.
This text file was formatted by the U.S. General Accounting Office
(GAO) to be accessible to users with visual impairments, as part of a
longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to the Chairman, Subcommittee on National Security, Emerging
Threats, and International Relations, Committee on Government Reform,
House of Representatives:
United States General Accounting Office:
GAO:
April 2004:
Nuclear Security:
DOE Needs to Resolve Significant Issues Before It Fully Meets the New
Design Basis Threat:
GAO-04-623:
GAO Highlights:
Highlights of GAO-04-623, a report to the Chairman, Subcommittee on
National Security, Emerging Threats, and International Relations,
House Committee on Government Reform
Why GAO Did This Study:
A successful terrorist attack on Department of Energy (DOE) sites
containing nuclear weapons or the material used in nuclear weapons
could have devastating consequences for the site and its surrounding
communities. Because of these risks, DOE needs an effective safeguards
and security program. A key component of an effective program is the
design basis threat (DBT), a classified document that identifies the
potential size and capabilities of terrorist forces. The terrorist
attacks of September 11, 2001, rendered the then-current DBT obsolete.
GAO examined DOE‘s response to the September 11, 2001, terrorist
attacks, identified why DOE took almost 2 years to develop a new DBT,
analyzed the higher threat in the new DBT, and identified the
remaining issues that need to be resolved in order for DOE to meet the
threat contained in the new DBT.
What GAO Found:
DOE took a series of actions in response to the terrorist attacks of
September 11, 2001. While each of these has been important, DOE must
press forward with additional actions to ensure that it is fully
prepared to provide a timely and cost effective defense.
* DOE took immediate steps to improve physical security in the
aftermath of the September 11, 2001, terrorist attacks. DOE‘s most
visible effort involved moving to higher levels of security readiness,
known as security condition (SECON) levels. While this effort has
increased the visible deterrence at DOE sites, it has been expensive
and has resulted in fatigue, retention problems, and less training for
most sites‘ protective forces. In addition, the effectiveness of these
increased SECON levels generally have not been assessed using the
vulnerability assessment tools, such as computer modeling and full-
scale force-on-force exercises, that DOE routinely uses to develop
protective force strategies for its sites.
* Development of the new DBT took almost 2 years because of (1) delays
in developing an intelligence community assessment”known as the
Postulated Threat”of the terrorist threat to nuclear weapon facilities
and (2) DOE‘s lengthy comment and review process for developing
policy. In addition, during the DBT development process, there were
sharp debates within DOE and other government organizations over the
size and capabilities of future terrorist threats and the availability
of resources to meet these threats that contributed to the delay.
* While the May 2003 DBT identifies a larger terrorist threat than did
the previous DBT, the threat identified in the new DBT in most cases
is less than the threat identified in the intelligence community‘s
Postulated Threat, on which the DBT has been traditionally based. The
new DBT identifies new possible terrorist acts such as radiological,
chemical, or biological sabotage. However, the criteria that DOE has
selected for determining when facilities may need to be protected
against these forms of sabotage may not be sufficient.
DOE has been slow to resolve a number of significant issues, such as
issuing additional DBT implementation guidance, developing DBT
implementation plans, and developing budgets to support these plans,
that may affect the ability of its sites to fully meet the threat
contained in the new DBT in a timely fashion. Consequently, DOE‘s
deadline to meet the requirements of the new DBT by the end of fiscal
year 2006 is probably not realistic for some sites.
What GAO Recommends:
GAO is making a series of recommendations to the Secretary of Energy
to strengthen DOE‘s ability to meet the requirements of the new DBT
and to strengthen the department‘s ability to deal with future
terrorist threats. DOE did not comment on the specific
recommendations, but said that it would consider them as part of its
Departmental Management Challenges for 2004.
www.gao.gov/cgi-bin/getrpt?GAO-04-623.
To view the full product, including the scope and methodology, click
on the link above. For more information, contact Robin M. Nazzaro at
(202) 512-3841 or nazzaror@gao.gov.
[End of section]
Contents:
Letter:
Results in Brief:
Background:
DOE Took Immediate Steps to Improve Security in the Aftermath of
September 11, 2001, but the Effectiveness of These Steps Is Uncertain:
Development of the New DBT Took Almost 2 Years Because of Delays in
Developing the Postulated Threat and DOE's Lengthy Review and Comment
Process:
The May 2003 DBT Identifies a Larger Terrorist Threat, but in Most
Cases is Less Than the Terrorist Threat Identified by an Important
Intelligence Community Assessment:
DOE Has Been Slow to Resolve a Number of Significant Issues That May
Affect the Ability of its Sites to Fully Meet the Threat Contained in
the New DBT:
Conclusions:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Comments from the Department of Energy:
Appendix II: GAO Contact and Staff Acknowledgments:
GAO Contact:
Staff Acknowledgments:
Abbreviations:
DBT: design basis threat:
DOD: Department of Defense:
DOE: Department of Energy:
EM: Office of Environmental Management:
NNSA: National Nuclear Security Administration:
SECON: security condition:
United States General Accounting Office:
Washington, DC 20548:
April 27, 2004:
The Honorable Christopher Shays:
Chairman, Subcommittee on National Security, Emerging Threats, and
International Relations:
Committee on Government Reform:
House of Representatives:
Dear Mr. Chairman:
The Department of Energy (DOE) has long recognized that a successful
terrorist attack on a site containing nuclear weapons or the material
used in nuclear weapons-called special nuclear material-could have
devastating consequences for the site and its surrounding communities.
Weapons or special nuclear material are present at the three design
laboratories-the Los Alamos National Laboratory in Los Alamos, New
Mexico; the Lawrence Livermore National Laboratory in Livermore,
California; and the Sandia National Laboratory in Albuquerque, New
Mexico-and two production sites-the Pantex Plant in Amarillo, Texas,
and the Y-12 Plant in Oak Ridge, Tennessee, operated by the National
Nuclear Security Administration (NNSA)-a separately organized agency
within DOE. Special[Footnote 1] nuclear material is also present at
former production sites, including the Savannah River Site in Savannah
River, South Carolina, and the Hanford Site in Richland, Washington.
These former sites are now being cleaned up by DOE's Office of
Environmental Management (EM). Furthermore, [Footnote 2] NNSA's Office
of Secure Transportation transports these materials among the sites and
between the sites and Department of Defense (DOD) bases. Contractors
operate each site for DOE. NNSA[Footnote 3] and EM have field offices
collocated with each site. In fiscal year 2004, NNSA and EM expect to
spend nearly $900 million on physical security at their sites. Physical
security combines security equipment, personnel, and procedures to
protect facilities, information, documents, or material against theft,
sabotage, diversion, or other criminal acts.
All the sites listed above have facilities that contain Category I
special nuclear material. Category I material includes specified
quantities of plutonium and highly enriched uranium in the following
forms: (1) assembled nuclear weapons and test devices; (2) pure
products containing higher concentrations of plutonium or highly
enriched uranium, such as major nuclear components and recastable
metal; and (3) high-grade materials, such as carbides, oxides,
solutions, and nitrates. The risks associated with Category I special
nuclear materials vary but include the nuclear detonation of a weapon
or test device at or near design yield, the creation of improvised
nuclear devices capable of producing a nuclear yield, theft for use in
an illegal nuclear weapon, and the potential for sabotage in the form
of radioactive dispersal.
Because Category I special nuclear material poses such risks, DOE's
effective management of the safeguards and security program, which
includes developing safeguards and security policies and overseeing
contractors' activities, is essential to preventing an unacceptable,
adverse impact on national security.[Footnote 4] To manage potential
risks, DOE has developed a design basis threat (DBT), a classified
document that identifies the potential size and capabilities of
terrorist forces. DOE's DBT is based on an intelligence community
assessment known as the Postulated Threat. The DBT is a key component
of DOE's well-established, risk-based security practices. DOE requires
the contractors operating its sites to provide sufficient protective
forces and equipment to defend against the threat contained in the DBT.
The effectiveness of these protective systems is periodically assessed
through a process known as a vulnerability assessment. The DBT in
effect on September 11, 2001, had been DOE policy since June 1999. DOE
replaced the 1999 DBT in May 2003 to better reflect the current and
projected terrorist threats that resulted from the September 11, 2001,
attacks.
Following the September 11, 2001, terrorist attacks, you asked us to
review physical security at DOE sites that have facilities with
Category I special nuclear material. Specifically, as agreed with your
office, we (1) examined DOE's response to the September 11, 2001,
attacks; (2) identified the reasons DOE needed almost 2 years to
develop a new DBT; (3) analyzed the higher threat contained in the new
DBT; and (4) identified the remaining issues that need to be resolved
in order for DOE to fully defend against the threat contained in the
new DBT.[Footnote 5]
To determine how DOE responded to the terrorist attacks of September
11, 2001, we reviewed relevant DOE policy and planning documents,
including orders and guides, particularly DOE Order 470.1 and DOE
Notice 473.6. In addition, we met with officials from DOE headquarters
and site offices, as well as contractors who operate DOE sites. The
primary offices we obtained information from were DOE's Office of
Security, DOE's Office of Independent Oversight and Performance
Assurance, DOE's Office of Environmental Management, NNSA's Office of
Defense Nuclear Security, and NNSA's Nuclear Safeguards and Security
Program. To review augmented security measures put into place after
September 11, 2001, from March 2002 through June 2003, we visited nine
DOE sites and one DOE program office that handle Category I special
nuclear material. Specifically, we visited the Los Alamos National
Laboratory and the NNSA Office of Los Alamos Site Operations in New
Mexico, the Sandia National Laboratory and the NNSA Office of Kirtland
Site Operations in New Mexico, the Lawrence Livermore National
Laboratory and the NNSA Livermore Site Office in California, the Y-12
Plant and the NNSA Y-12 Site Office in Tennessee, the Pantex Plant and
the NNSA Office of Amarillo Site Operations in Texas, and the NNSA's
Office of Secure Transportation in New Mexico. We also visited the
Savannah River Site and EM's Savannah River Operations Office in South
Carolina, the Rocky Flats Environmental Technology Site and EM's Rocky
Flats Field Office in Colorado, the Hanford Site and EM's Richland
Operations Office in Washington, and the Idaho National Engineering and
Environmental Laboratory and EM's Idaho Falls Operations Office in
Idaho.
To determine why DOE needed almost 2 years to develop a new DBT, we
reviewed historical documents, the four draft DBTs produced between May
2002 and April 2003, the final May 2003 DBT, and other threat guidance
provided to us by DOE's Office of Security. We also reviewed associated
field and program office comments on the draft DBTs and threat
guidance. We discussed the DBT development process with DOE's Office of
Security, DOE's Office of Independent Oversight and Performance
Assurance, EM and NNSA headquarters security offices, and federal and
contractor personnel at all of the sites and field offices we visited.
We also discussed postulated terrorist threats to nuclear weapon
facilities with two DOD organizations: the Office of the Assistant
Secretary of Defense for Command, Control, Communications, and
Intelligence; and the Defense Intelligence Agency. We also reviewed The
Postulated Threat to U.S. Nuclear Weapon Facilities and Other Selected
Strategic Facilities, henceforth referred to as the Postulated Threat,
which is the intelligence community's January 2003 official assessment
of potential terrorist threats to nuclear weapon facilities. From May
2002 to May 2003, DOE denied us access to the draft DBTs it was
developing; however, in May 2003, we were able to obtain access to the
documents and complete our review.
To analyze the higher threat level contained in the new DBT, we
examined previous DBTs and related documents provided to us by DOE's
Office of Security. We traced how key parameters of the new DBT, such
as the size of terrorist forces and the treatment of improvised nuclear
devices, evolved during the 2002 through 2003 DBT development process
and compared these parameters with previous DBTs and the Postulated
Threat. We discussed the higher threat level and other key threat
aspects contained in the final 2003 DBT, such as the graded threat
approach; improvised nuclear device concerns; and radiological,
chemical, and biological sabotage criteria; with DOE's Office of
Security; DOE's Office of Independent Oversight and Performance
Assurance; EM and NNSA headquarters security offices; federal and
contractor personnel at all of the sites and field offices we visited;
DOD's Office of the Assistant Secretary of Defense for Command,
Control, Communications, and Intelligence; and the Defense Intelligence
Agency. In order to determine what industry security standards exist to
prevent terrorist acts of sabotage at industrial chemical facilities,
we reviewed a report we issued in March 2003 on measures used to
protect commercial chemical facilities.:
[Footnote 6]To identify the remaining issues that DOE must resolve
before it can fully meet the threat contained in the new DBT, we met
with DOE, EM, and NNSA headquarters security offices, as well as field
security officials. We also reviewed relevant documents these offices
provided. In particular, we reviewed recent Office of Independent
Oversight and Performance Assurance inspection reports that identified
some of the challenges associated with meeting the threat contained in
the new DBT. DOE did not provide us with preliminary cost estimates for
meeting the requirements of the DBT on the grounds that these costs had
not yet been officially determined; however, DOE's Budget Office did
outline for us potential mechanisms for funding DBT implementation over
the next several years. We performed our work from December 2001
through April 2004 in accordance with generally accepted government
auditing standards.
Results in Brief:
DOE took immediate steps to improve physical security in the aftermath
of the September 11, 2001, terrorist attacks. DOE's most visible effort
involved moving to higher levels of security readiness, known as
security condition (SECON) levels. On September 11, 2001, within a
matter of hours, DOE sites went from their then-normal SECON level
4-terrorist threat level low-to SECON level 2-terrorist threat level
high. Sites were required to increase, among other things, the number
of vehicle inspections and badge checks, the distance between public
and sensitive areas to protect against large truck bombs, and the
number of protective forces on duty, and to more heavily arm these
forces. While sites are now at SECON level 3, most of these
requirements still exist. Increased SECON levels have been expensive in
both their financial cost and their toll on the readiness of the
protective forces. Specifically, operating at the increased SECON
levels has resulted in between $18,000 to $200,000 in unplanned costs
per week at each site-primarily the result of overtime costs for the
protective forces. More importantly, according to a June 2003 DOE
Inspector General's report, the large amounts of overtime needed to
meet these SECON requirements have resulted in fatigue, retention
problems, and less training for protective forces. While [Footnote 7]
the SECON levels have increased the visible deterrence at DOE sites,
the effectiveness of the SECON levels in place at most sites has not
been assessed using the vulnerability assessment tools, such as
computer modeling and full-scale force-on-force exercises, that DOE
uses to develop protective force strategies for its sites.
Consequently, DOE cannot assure itself that these enhanced requirements
are providing effective increases in security. In its comments on our
report, DOE has agreed to explore procedures to incorporate the
evaluation of increased SECON levels into its vulnerability
assessments.
Development of the DBT took almost 2 years because of delays in
developing the Postulated Threat and DOE's lengthy review and comment
process for developing policy. DOE's new DBT is based on a study known
as the Postulated Threat, which was developed by the U.S. intelligence
community. The intelligence community originally planned to complete
the Postulated Threat by April 2002; however, the document was not
completed and officially released until January 2003, about 9 months
behind the original schedule. According to DOE and DOD officials, this
delay resulted from other demands placed on the intelligence community
after September 11, 2001, as well as from sharp debates among the
organizations developing the Postulated Threat over the size and
capabilities of future terrorist threats and the resources needed to
meet these threats. While waiting for the new Postulated Threat, DOE
developed several drafts of its new DBT. During this process, debates,
similar to those that occurred during the development of the Postulated
Threat, emerged in DOE over the size of the future threat and the
availability of resources to meet it. DOE developed the DBT using DOE's
policy process, which emphasizes developing consensus through a review
and comment process by program offices, such as EM and NNSA. However,
many DOE and contractor officials found that the policy process for
developing the new DBT was laborious and not timely, especially given
the more dangerous threat environment that has existed since September
11, 2001. As a result, during the time it took DOE to develop the new
DBT, its sites were only required to defend against the terrorist group
defined in the 1999 DBT, which in the aftermath of September 11, 2001,
DOE officials realized was obsolete.
While the May 2003 DBT identifies a larger terrorist group than did the
previous DBT, the threat identified in the new DBT, in most cases, is
less than the terrorist threat identified in the intelligence
community's Postulated Threat. The Postulated Threat estimated that the
force attacking a nuclear weapons site would probably be a relatively
small group of terrorists, although it was possible that an adversary
might use a greater number of terrorists if that was the only way to
attain an important strategic goal. In contrast to the Postulated
Threat, DOE is preparing to defend against a significantly smaller
group of terrorists attacking many of its facilities. Specifically,
only for its sites and operations that handle nuclear weapons, is DOE
currently preparing to defend against an attacking force that
approximates the lower range of the threat identified in the Postulated
Threat. For its other Category I special nuclear material sites, all of
which fall under the Postulated Threat's definition of a nuclear
weapons site, DOE is requiring these sites to be prepared to defend
against a terrorist force significantly smaller than was identified in
the Postulated Threat. DOE based its departure from the Postulated
Threat on the conclusions of its own subject matter experts on what
they judged likely to be the most credible, near-term terrorist threats
to its facilities. The new DBT also identifies new possible terrorist
acts such as radiological, chemical, or biological sabotage. However,
the criteria that DOE has selected for determining when facilities may
need to be protected against these forms of sabotage may not be
sufficient. For example, for chemical sabotage, the 2003 DBT requires
sites to protect to ’industry standards." However, in March 2003, we
reported that such standards currently do not exist. Consequently,
without appropriate standards, DOE cannot ensure that its sites and
facilities are adequately protected against the full range of
consequences that might result from terrorist acts.
While DOE issued the final DBT in May 2003, it has been slow to resolve
a number of significant issues, such as issuing additional DBT
implementation guidance, developing DBT implementation plans, and
developing budgets to support these plans, that may affect the ability
of DOE sites to fully meet the threat contained in the new DBT. For
example, DOE has only recently issued additional DBT implementation
guidance-several months behind DOE's original schedule-and developed
initial DBT implementation plans. DOE officials currently do not have
any official estimates of the overall costs of DBT implementation. In
addition, DOE officials believed that budget information provided by
sites for inclusion in the fiscal year 2005 budget was of generally
poor quality because most sites had not yet completed the necessary
vulnerability assessments to determine their resource requirements.
Moreover, other important DBT-related issues remain unresolved. For
example, the Secretary of Energy has not yet designated, as called for
in the new DBT, which, if any, of DOE's sites have improvised nuclear
device concerns. If a site is designated to have such a concern, it may
be required to shift to a more demanding and costly protection
strategy. As a result of these issues, DOE is unlikely to meet its own
fiscal year 2006 deadline for full implementation of the requirements
of the new DBT. Specifically, some sites estimate that it could take as
long as 5 years, given adequate funding, to fully meet the requirements
of the new DBT. Because some sites will be unable to effectively
counter the threat contained in the new DBT for a period of up to
several years, these sites probably are at higher risk under the new
DBT than they were under the old DBT.
We are making recommendations to the Secretary of Energy that are
intended to strengthen DOE's ability to meet the requirements of the
new DBT, as well as to strengthen the department's ability to deal with
future terrorist threats. We are also recommending that the Secretary
report to the Congress on departmental progress in meeting the threat
contained in the new DBT and reducing risks to critical facilities at
its sites.
We provided DOE with a draft of this report for review and comment. In
its written comments, DOE said it was committed to the development and
promulgation of an accurate and comprehensive DBT policy. DOE did not
comment specifically on our recommendations other than to say that the
department would consider them as part of its Departmental Management
Challenges for 2004. DOE has identified the DBT as a major departmental
initiative within the National Security Management Challenge.
Background:
From the beginning of the Manhattan Project in the 1940s, a primary
mission of DOE and its predecessor organizations has been to design,
test, and build the nation's nuclear weapons. To accomplish this
mission, DOE constructed a vast nuclear weapons complex throughout the
United States. Much of this complex was devoted to the production and
fabrication of weapons components made from two special nuclear
materials-plutonium and highly enriched uranium.
The end of the Cold War changed the department's focus from building
new weapons to extending the lives of existing weapons, disposing of
surplus nuclear material, and cleaning up no longer needed weapons
sites. NNSA is responsible for extending the lives of existing weapons
in the stockpile and for ultimately disposing of surplus nuclear
material, while EM is responsible for cleaning up former nuclear
weapons sites. Contractors, who are responsible for protecting
classified information, nuclear materials, nuclear weapons, and nuclear
weapons components, operate both NNSA and EM sites.
In addition to NNSA and EM, DOE has two other important security
organizations. DOE's Office of Security develops and promulgates orders
and policies, such as the DBT, to guide the department's safeguards and
security programs. DOE's Office of Independent Oversight and
Performance Assurance supports the department by, among other things,
independently evaluating the effectiveness of contractors' performance
in safeguards and security. It also performs follow-up reviews to
ensure that contractors have taken effective corrective actions and
appropriately addressed weaknesses in safeguards and security.
The key component of DOE's well-established, risk-based security
practices is the DBT, a classified document that identifies the
characteristics of the potential threats to DOE assets. The DBT has
been traditionally based on a classified, multiagency intelligence
community assessment of potential terrorist threats, known as the
Postulated Threat. The DBT considers a variety of threats in addition
to terrorists. Other adversaries considered in the DBT include
criminals, psychotics, disgruntled employees, violent activists, and
spies. The DBT also considers the threat posed by insiders, individuals
who have authorized, unescorted access to any part of DOE facilities
and programs. Insiders may operate alone or may assist an adversary
group. Insiders are routinely considered to provide assistance to the
terrorist groups found in the DBT. The threat from terrorist groups is
generally the most demanding threat contained in the DBT.
DOE counters the terrorist threat specified in the DBT with a
multifaceted protective system. While specific measures vary from site
to site, all protective systems at DOE's most sensitive sites employ a
defense-in-depth concept that includes:
* a variety of integrated alarms and sensors capable of detecting
intruders;
* physical barriers, such as fences and antivehicle obstacles;
* numerous access control points, such as turnstiles, badge readers,
vehicle inspection stations, special nuclear material detectors, and
metal detectors;
* operational security procedures, such as a ’two person" rule that
prevents only one person from having access to special nuclear
material;
* hardened facilities and/or vaults; and:
* a heavily armed paramilitary protective force equipped with such
items as automatic weapons, night vision equipment, body armor, and
chemical protective gear.
Depending on the material, protective systems at DOE Category I special
nuclear material sites are designed to accomplish the following
objectives in response to the terrorist threat:
* Denial of access. For some potential terrorist objectives, such as
the creation of an improvised nuclear device, DOE may employ a
protection strategy that requires the engagement and neutralization of
adversaries before they can acquire hands-on access to the assets.
* Denial of task. For nuclear weapons or nuclear test devices that
terrorists might seek to steal, DOE requires the prevention and/or
neutralization of the adversaries before they can complete a specific
task, such as stealing such devices.
* Containment with recapture. Where the theft of nuclear material
(instead of a nuclear weapon) is the likely terrorist objective, DOE
requires that adversaries not be allowed to escape the facility and
that DOE protective forces recapture the material as soon as possible.
This objective requires the use of specially trained and well-equipped
special response teams.
The effectiveness of the protective system is formally and regularly
examined through vulnerability assessments. A vulnerability assessment
is a systematic evaluation process in which qualitative and
quantitative techniques are applied to detect vulnerabilities and
arrive at effective protection of specific assets, such as special
nuclear material. To conduct such assessments, DOE uses, among other
things, subject matter experts, such as U.S. Special Forces; computer
modeling to simulate attacks; and force-on-force performance testing,
in which the site's protective forces undergo simulated attacks by a
group of mock terrorists.
The results of these assessments are documented at each site in a
classified document known as the Site Safeguards and Security Plan. In
addition to identifying known vulnerabilities, risks, and protection
strategies for the site, the Site Safeguards and Security Plan formally
acknowledges how much risk the contractor and DOE are willing to
accept. Specifically, for more than a decade, DOE has employed a risk
management approach that seeks to direct resources to its most critical
assets-in this case Category I special nuclear material-and mitigate
the risks to these assets to an acceptable level. Levels of risk-high,
medium, and low-are assigned classified numerical values and are
derived from a mathematical equation that compares a terrorist group's
capabilities with the overall effectiveness of the crucial elements of
the site's protective forces and systems.
Historically, DOE has striven to keep its most critical assets at a low
risk level and may insist on immediate compensatory measures should a
significant vulnerability develop that increases risk above the low
risk level. Compensatory measures could include such things as
deploying additional protective forces or curtailing operations until
the asset can be better protected. In response to a September 2000 DOE
Inspector General's report recommending that DOE establish a policy on
what actions are required once high or moderate risk is identified, in
September 2003, DOE's Office of Security issued a policy clarification
stating that identified high risks at facilities must be formally
reported to the Secretary of Energy or Deputy Secretary within 24
hours. In addition, under this policy clarification, identified high
and moderate risks require corrective actions and regular reporting.
Through a variety of complementary measures, DOE ensures that its
safeguards and security policies are being complied with and are
performing as intended. Contractors perform regular self-assessments
and are encouraged to uncover any problems themselves. In addition to
routine oversight, DOE Orders require field offices to comprehensively
survey contractors' operations for safeguards and security every year.
These surveys, which can draw upon subject matter experts throughout
the complex, generally take about 2 weeks to conduct and cover such
areas as program management, protection program operations, information
security, nuclear materials control and accountability, and personnel
security. The survey team assigns ratings of satisfactory, marginal, or
unsatisfactory. DOE's Office of Independent Oversight and Performance
Assurance provides yet another check through its comprehensive
inspection program. This office performs such inspections roughly every
18 months at each DOE site that has specified quantities of Category I
special nuclear material. All deficiencies (findings) identified during
a survey require the contractors to take corrective action.
DOE Took Immediate Steps to Improve Security in the Aftermath of
September 11, 2001, but the Effectiveness of These Steps Is Uncertain:
DOE took immediate steps to improve physical security in the aftermath
of the September 11, 2001, terrorist attacks. These steps included the
following:
* Raised the level of security readiness. Presidential Decision
Directive 39, issued in June 1995, states that the United States shall
give the highest priority to developing effective capabilities to
detect, prevent, and defeat terrorists seeking nuclear weapons or
materials. In response, DOE Notice 473.6 specifies SECONs that have to
be implemented at its Category I special nuclear material sites in
response to a terrorist threat. On September 11, 2001, within a matter
of hours, DOE sites went from their then-normal SECON level 4-terrorist
threat level low-to SECON level 2-terrorist threat level high. Sites
were required to implement nearly 30 additional measures, such as
increasing vehicle inspections and badge checks; increasing stand-off
distances between public and sensitive areas to protect against large
vehicle bombs; activating and manning emergency operations centers on a
continuous basis; and more heavily arming and increasing the number of
protective forces on duty. Sites maintained SECON level 2 through
October 2001 before dropping to an enhanced SECON level 3. The sites
have returned to SECON level 2 several times since September 11, 2001,
most recently in December 2003, when the national threat warning system
was elevated to Orange Alert. The new baseline for security at DOE
sites is generally assumed to be the measures currently associated with
SECON level 3.
* Denial protection strategies. On October 3, 2001, the Secretary of
Energy issued a classified directive ordering all sites to develop and
implement plans to move to a denial protection strategy. DOE Manual
5632.1C-1 states that a denial protection strategy should be used where
unauthorized access presents an unacceptable risk. In this regard,
denial programs are designed to prevent an unauthorized opportunity to
credibly initiate a nuclear dispersal or detonation or to use available
materials for on-site assembly of an improvised nuclear device. Denial
has typically been understood to mean that terrorists would never gain
access to certain types of special nuclear material. The October 2001
directive also increased levels of performance testing for the
protection of special nuclear material at DOE's most critical
facilities to ensure that these denial strategies were effective.
* Conducted security reviews, studies, and analyses. DOE conducted a
number of security-related reviews, studies, and analyses. For example,
within days after the terrorist attacks, DOE and NNSA officials
conducted a classified assessment of their facilities' vulnerabilities
to an attack by aircraft, such as the attacks that occurred on
September 11, 2001, or large vehicle bombs. NNSA also organized a 90-
day Combating Terrorism Task Force, composed of 12 federal and
contractor employee teams that looked at a number of security areas.
One team, the site-by-site security review and vulnerability assessment
group, identified and set priorities for over 80 security improvement
projects, totaling more than $2 billion, that could be completed within
5 to 6 years. These projects ranged from hiring additional protective
forces to consolidating special nuclear material.
* Increased liaison with federal, state, and local authorities. Before
the September 11 terrorist attacks, DOE headquarters offices and sites
maintained a variety of relationships, memoranda of understanding, and
other formal and informal communications with organizations such as the
Federal Aviation Administration, Federal Bureau of Investigation, and
state and local law enforcement and emergency management agencies.
After the terrorist attacks, DOE officials increased their
communications with these organizations and established direct links
through sites' emergency operations centers. Because of the potential
threat of aircraft attacks created by the September 11 attacks and
because of such attacks' potentially devastating consequences, sites
worked closely with the Federal Aviation Administration and the U.S.
military.
Several benefits have resulted from these immediate measures. With
respect to improved security, DOE security officials believe that the
implementation of SECON levels 2 and 3 has, for example, increased the
visible deterrence at DOE sites by placing more protective forces
around the sites. Studies and analyses have also resulted in different
and less vulnerable storage strategies for some special nuclear
material. For example, one NNSA site purchased special fire and blast-
resistant safes to store special nuclear material. Finally, some long-
recognized security enhancement projects have received more funding,
such as the construction of a new storage facility at an NNSA site, and
efforts to control access to public areas and roads adjacent to several
NNSA sites.
While these measures have produced several positive outcomes, they have
also had the following negative impacts:
* First, the role of the implemented SECON measures in improving DOE
physical security is uncertain. While DOE Notice 473.6, which
established the department's SECON levels, does not explicitly require
SECON measures to be performance tested, DOE Manual 473.2-2 states that
performance tests must be used to realistically evaluate and verify the
effectiveness of protective force programs. While some of the SECON
measures, such as vehicle inspection checkpoints, have undergone some
limited performance testing of their effectiveness, most DOE sites
generally have not assessed the SECON level measures in place using the
vulnerability assessment tools, such as computer modeling and full-
scale force-on-force performance tests, that play such a key role in
developing and verifying protective strategies at their sites.
Consequently, the effectiveness of SECON measures against other aspects
of the 2003 DBT, such as a larger group of well-armed terrorists, is
largely unknown. In its comments on our report, DOE agreed to explore
procedures to incorporate the evaluation of increased SECON levels into
its vulnerability assessments.
* Second, increased SECON measures have been expensive. DOE sites
estimate that it costs each site from $18,000 to nearly $200,000 per
week in unplanned expenditures to implement the required SECON level 2
and 3 measures. Most of these expenses result from overtime pay to
protective forces. The costs of the higher SECON levels, however, can
be measured in more than just budget dollars. Specifically, a June 2003
DOE Inspector General's report found that the large amounts of overtime
needed to meet the higher SECON requirements have resulted in fatigue,
reduced readiness, retention problems, reduced training, and fewer
force-on-force performance tests for the protective forces. Additional
protective forces have been hired and trained in an effort to provide
some relief; however, the DOE Inspector General has found that the
deployment of additional protective forces has been delayed by slow
processing of the necessary security clearances.
* Third, the increased operational costs associated with the higher
SECON levels can hinder or preclude sites from making investments that
could improve their security over the long term. For example, according
to a NNSA security official, because of the high costs of maintaining
SECON measures, one site had to delay purchasing weaponry and
ammunition for its protective forces to use to defeat commercially
available armored vehicles that could be used by terrorists.
* Fourth, the sites did not complete the implementation of the
Secretary's October 3, 2001, denial directive because of confusion over
its meaning and because of the projected high costs of implementation.
Over the years, DOE has issued varying guidance on denial protection
strategies and, as a result, the sites have approached denial
protection from different perspectives. For example, some NNSA sites
and operations have implemented the most stringent form of denial,
which is now defined as denial of access. In contrast, other NNSA sites
have plans in place to interrupt terrorists who have gained access to
materials, now called a denial of task protection strategy. Most EM
sites have practiced containment protection strategies augmented by
recapture and recovery capabilities. For sites that did not already
have a denial strategy in place, moving to a full denial of access
strategy appears to be enormously expensive, with some sites estimating
it would cost from about $30 million to $200 million to implement the
directive completely. Moreover, the performance testing requirements of
this directive have generally not been conducted because of the already
large amounts of protective force overtime required by the higher SECON
levels. For example, a NNSA security official at one site estimated it
would have to conduct as many as 30 full-scale force-on-force
performance tests each year to comply with the Secretary's Directive.
The 2003 DBT, however, has now replaced this directive by explicitly
defining denial of access and denial of task protection strategies and
when these strategies should be employed.
* Finally, while liaison with other agencies is important, DOE
officials anticipate that any terrorist attacks on their facilities
will be short and violent and be over before any external responders
can arrive. In addition, because some DOE sites are close to airports
and/or major flight routes, they may receive little warning of aircraft
attacks, and U.S. military aircraft may have little opportunity to
intercept these attacks.
Development of the New DBT Took Almost 2 Years Because of Delays in
Developing the Postulated Threat and DOE's Lengthy Review and Comment
Process:
Under DOE Order 470.1, the DBT is intended to provide the foundation
for all of DOE's protective strategies. For example, DOE Order 473.2
states that protective forces must be trained and equipped to defeat
the terrorist groups contained in the DBT. In the immediate aftermath
of September 11, 2001, DOE officials realized that the then current
DBT, issued in April 1999 and based on a 1998 intelligence community
assessment, was obsolete. The September 11, 2001, terrorist attacks
suggested larger groups of terrorists, larger vehicle bombs, and
broader terrorist aspirations to cause mass casualties and panic than
were envisioned in the 1999 DOE DBT. However, formally recognizing
these new threats by updating the DBT was difficult because of debates
over the size of the future threat, the cost to meet it, and the DOE
policy process.
The traditional basis for the DBT has been the Postulated Threat, which
is conducted by the U.S. intelligence community, principally DOD's
Defense Intelligence Agency, and the security organizations of a number
of different agencies, including DOE. For example, DOE closely based
its 1999 DBT on the 1998 Postulated Threat assessment and adopted the
same number of terrorists as identified by the 1998 Postulated Threat
as its highest threat to its facilities. Efforts to revise the
Postulated Threat began soon after the terrorist attacks of September
11, 2001. The intelligence community originally planned to complete the
Postulated Threat by April 2002; however, the document was not
completed and officially released until January 2003, about 9 months
behind the original schedule. According to DOE and DOD officials, this
delay was the result of other post September 11, 2001, demands placed
on the intelligence community, as well as sharp debates among the
organizations involved with developing the Postulated Threat over the
size and capabilities of future terrorist threats and the resources
needed to meet these projected threats.
While waiting for the new Postulated Threat, DOE developed a number of
draft documents that culminated in the final May 20, 2003, DBT. These
documents included the following:
* December 2001-Interim Joint Threat Policy Statement. DOE and DOD
worked on this joint draft document but abandoned this effort later in
2002 because neither agency wanted to act without the benefit of the
Postulated Threat.
* January 2002-Interim Implementing Guidance. DOE's Office of Security
issued this guidance so that DOE programs could begin to plan and
budget for eventual increases in the DBT. This interim guidance
suggested that sites begin planning for an increased number of
adversaries over the 1999 DBT.
* May 2002-Draft DBT. DOE produced its first official draft DBT and
labeled it an interim product pending the release of the Postulated
Threat.
* August 2002-Second Draft DBT. This draft introduced the graded threat
approach, which is an important feature in the final DBT.
* December 2002-Third Draft DBT.
* April 2003-Fourth Draft DBT. This draft was the first to consider the
final January 2003 Postulated Threat.
* May 2003-Final DBT.
Like the participants responsible for developing the Postulated Threat,
during the development of the DBT, DOE officials debated the size of
the future terrorist threat and the costs to meet it. DOE officials at
all levels told us that concern over resources played a large role in
developing the 2003 DBT, with some officials calling the DBT the
’funding basis threat," or the maximum threat the department could
afford. This tension between threat size and resources is not a new
development. According to a DOE analysis of the development of prior
DBTs, political and budgetary pressures and the apparent desire to
reduce the requirements for the size of protective forces appear to
have played a significant role in determining the terrorist group
numbers contained in prior DBTs.
Finally, DOE developed the DBT through the standard DOE review and
comment process for developing policy as outlined in DOE Order 251.1A
and DOE Manual 251.1-1A. This process emphasizes developing consensus
and resolving conflicts and involving a wide number of DOE
organizations and affected contractors. Once DOE formulates a proposed
policy, it typically allows 60 days for review and comment and 60 days
for issue resolution. While developing the 2003 DBT, DOE's Office of
Security distributed the draft DBTs to DOE program and field offices
and invited them to provide comments. Field offices distributed the
drafts to contractors, who were also invited to provide comments. DOE's
Office of Security considered these comments and often incorporated
them into the next version of the DBT. DOE's Office of Security also
continued to coordinate with the other federal organizations that have
similar assets, chiefly DOD and the Nuclear Regulatory Commission.
Having followed this process for 21 months, the Deputy Secretary of
Energy signed the revised DBT in May 2003. According to the Director of
Policy in DOE's Office of Security, the DBT was developed as fast as
possible, given delays in completing the Postulated Threat and the
constraints of the DOE policy system. He added that using the DOE
policy process was difficult and time-consuming and inevitably added to
delays in issuing the new DBT. Many officials in DOE's program offices
and sites, as well as contractor officials, also found the process to
be laborious and not timely, especially given the more dangerous threat
environment that existed after the September 11, 2001, terrorist
attacks.
During the 21 months it took to develop the DBT, DOE sites still
officially followed the 1999 DBT, although their protective posture was
augmented by implementing SECON level 2 and 3 measures. EM sites
continued to conduct vulnerability assessments and develop Site
Safeguards and Security Plans based on the 1999 DBT. In contrast, NNSA
largely suspended the development of Site Safeguards and Security Plans
pending the issuance of the new DBT, although NNSA did embark on a new
vulnerability assessment process, called Iterative Site Analysis. NNSA
performed Iterative Site Analysis exercises at a number of its sites.
EM also conducted an Iterative Site Analysis at one site. Also during
this period, DOE's Office of Independent Oversight and Performance
Assurance continued its inspections; however, it initially reduced the
amount of force-on-force performance testing it conducted because of
the high levels of protective force overtime caused by implementation
of SECON level 2 and 3 measures. This office also planned to begin
performance testing at levels higher than the 1999 DBT, but it had done
so only once before the 2003 DBT was issued.
The May 2003 DBT Identifies a Larger Terrorist Threat, but in Most
Cases is Less Than the Terrorist Threat Identified by an Important
Intelligence Community Assessment:
Reflecting the post-September 11, 2001, environment, the May 2003 DBT,
among other things, identifies a larger terrorist threat than did the
previous DBT. It also mandates specific protection strategies and
expands the range of terrorist objectives to include radiological,
biological, and chemical sabotage. However, the threat identified in
the new DBT, in most cases, is less than the terrorist threat
identified in the intelligence community's Postulated Threat. Key
features of the 2003 DBT include the following:
* Expanded terrorist characteristics and goals. The 2003 DBT assumes
that terrorist groups are the following: well armed and equipped;
trained in paramilitary and guerrilla warfare skills and small unit
tactics; highly motivated; willing to kill, risk death, or commit
suicide; and capable of attacking without warning. Furthermore,
according to the 2003 DBT, terrorists might attack a DOE or NNSA
facility for a variety of goals, including the theft of a nuclear
weapon, nuclear test device, or special nuclear material; radiological,
chemical, or biological sabotage; and the on-site detonation of a
nuclear weapon, nuclear test device, or special nuclear material that
results in a significant nuclear yield. DOE refers to such a detonation
as an improvised nuclear device.
* Increased size of the terrorist group threat. The 2003 DBT increases
the terrorist threat levels for the theft of the department's highest
value assets-Category I special nuclear materials-although not in a
uniform way. Previously, under the 1999 DBT, all DOE sites that
possessed any type of Category I special nuclear material were required
to defend against a uniform terrorist group composed of a relatively
small number of individuals. Under the 2003 DBT, however, the
department judges the theft of a nuclear weapon or test device to be
more attractive to terrorists, and sites that have these assets are
required to defend against a substantially higher number of terrorists
than are other sites. For example, an NNSA site that, among other
things, assembles and disassembles nuclear weapons, is required to
defend against a larger terrorist group. Other NNSA sites, some of
which fabricate nuclear weapons components, or EM sites that store
excess plutonium, only have to defend against a smaller group of
terrorists. However, the number of terrorists in the 2003 DBT is larger
than the 1999 DBT number. DOE calls this a graded threat approach.
* Mandated specific protection strategies. In line with the graded
threat approach and depending on the type of materials they possess and
the likely mission of the terrorist group, sites must now implement
specific protection strategies, such as denial of access, denial of
task, or containment with recapture for their most sensitive facilities
and assets. For example, one NNSA site is required under the new DBT to
implement a denial of task strategy to prevent terrorists from stealing
a nuclear weapon or test device. In contrast, other DOE sites are
required to implement a containment with recapture strategy to prevent
the theft of special nuclear material. However, if these sites have an
improvised nuclear device concern, they will have to implement denial
of access or denial of task strategies. Finally, sites will have to
develop, for the first time, specific protection strategies for
facilities, such as radioactive waste storage areas, wastewater
treatment, and science laboratories, against the threat of
radiological, chemical, or biological sabotage. Previously, in an April
1998 policy clarification, DOE's Office of Security had stated that,
assuming that baseline security requirements were met, radiological
dispersal sabotage events were not considered attractive to terrorists.
* Addressed the potential for improvised nuclear device concerns. The
new DBT establishes a team to report to the Secretary of Energy on each
site's potential for improvised nuclear devices. Based on the teams'
advice, the Secretary of Energy will have to designate whether a site
has such a concern. This official designation should help address the
general dissatisfaction with previous DOE policies for improvised
nuclear devices, knowledge of which is carefully controlled and not
shared widely with security officials. For example, some EM sites have
had no information at all on their potential for this risk, and at
least one NNSA site official believed that scenarios for such risks
have not been fully characterized.
* Introduced aircraft threats and mitigation measures. In the 1999 DBT,
DOE only acknowledged the risk for unspecified air attacks but did not
lay out any protective measures to mitigate this risk. In the 2003 DBT,
DOE considers aircraft as airborne improvised explosive devices. DOE's
new policy is to rely on other federal government agencies, such as the
Departments of Homeland Security and Defense, to defeat such a threat.
DOE sites are expected, however, to consider measures, such as how they
handle and store their materials, to mitigate the consequences of an
aircraft attack on existing facilities, and new DOE facility designs
are expected to include features to mitigate the consequences of an
attack.
While DOE's 2003 DBT makes some important advances, aspects of the DBT
raise several important issues.
First, while the May 2003 DBT identifies a larger terrorist group than
did the previous DBT, the threat identified in the new DBT in most
cases is less than the terrorist threat identified in the intelligence
community's Postulated Threat. The Postulated Threat applies to nuclear
weapons sites, which the Postulated Threat defines as research and
development facilities with nuclear weapons, components, or special
nuclear material; weapons production facilities; sites for long-term
storage of nuclear weapons; and nuclear weapons in transport. With
respect to these sites, the Postulated Threat specified the following:
* There is a credible threat to U.S. facilities with nuclear or
chemical weapons or biological agents.
* A well-organized terrorist group presents the greatest and most
likely threat in most circumstances.
* Terrorists may use aircraft as weapons.
* Terrorists may use multiple vehicle bombs loaded with explosives.
* Terrorist groups would probably consist of a small to medium sized
group of well-armed and trained members. A larger force is possible if
the group thought this was necessary to attain an important strategic
goal.
* Terrorist objectives include the theft of a weapon, detonation of a
nuclear weapon in place, radiological sabotage, mass casualties, and/or
public panic.
In contrast to the Postulated Threat, DOE is preparing to defend
against a significantly smaller group of terrorists attacking most of
its facilities. Specifically, only for its sites and operations that
handle nuclear weapons, is DOE currently preparing to defend against an
attacking force that approximates the lower range of the threat
identified in the Postulated Threat. For the other DOE sites that have
Category I special nuclear material-all of which fall under the
Postulated Threat's definition of a nuclear weapons site-DOE is
currently only preparing to defend against a smaller number
terrorists-or approximately the same number contained in its DBT in the
early 1980s.
Second, and more critically, some of these sites may have improvised
nuclear device concerns that, if successfully exploited by terrorists,
could result in a nuclear detonation. Nevertheless, under the graded
threat approach, DOE requires these sites only to be prepared to defend
against a smaller force of terrorists than was identified by the
Postulated Threat. DOE's Office of Security cited subject matter expert
opinion as support for this distinction. However, according to
officials in DOE's Office of Independent Oversight and Performance
Assurance, sites with improvised nuclear device concerns should be held
to the same requirements as facilities that possess nuclear weapons and
test devices since the potential worst-case consequence at both types
of facilities would be the same-a nuclear detonation. Some DOE
officials and an official in DOD's Office of the Assistant Secretary of
Defense for Command, Control, Communications, and Intelligence
disagreed with the overall graded threat approach, believing that the
threat should not be embedded in the DBT by adjusting the number of
terrorists that might attack a particular target.
DOE Office of Security officials cited three reasons for why the
department departed from the Postulated Threat's assessment of the
potential size of terrorist forces. First, these officials stated that
they believed that the Postulated Threat only applied to sites that
handled completed nuclear weapons and test devices. However, both the
2003 Postulated Threat, as well as the preceding 1998 Postulated
Threat, state that the threat applies to nuclear weapons and special
nuclear material without making any distinction between them. Second,
DOE Office of Security officials believed that the higher threat levels
contained in the 2003 Postulated Threat represented the worst potential
worldwide terrorist case over a 10-year period. These officials noted
that while some U.S. assets, such as military bases, are located in
parts of the world where terrorist groups receive some support from
local governments and societies, thereby allowing for an expanded range
of capabilities, DOE facilities are located within the United States,
where terrorists would have a more difficult time operating.
Furthermore, DOE Office of Security officials stated that the DBT
focuses on a nearer-term threat of 5 years. As such, DOE Office of
Security officials said that they chose to focus on what their subject
matter experts believed was the maximum, credible, near-term threat to
their facilities. However, while the 1998 Postulated Threat made a
distinction between the size of terrorist threats abroad and those
within the United States, the 2003 Postulated Threat, reflecting the
potential implications of the September 2001 terrorist attacks, did not
make this distinction. Finally, DOE Office of Security officials stated
that the Postulated Threat document represented a reference guide
instead of a policy document that had to be rigidly followed. The
Postulated Threat does acknowledge that it should not be used as the
sole consideration to dictate specific security requirements and that
decisions regarding security risks should be made and managed by
decision makers in policy offices. However, DOE has traditionally based
its DBT on the Postulated Threat. For example, the prior DBT, issued in
1999, adopted exactly the same terrorist threat size as was identified
by the 1998 Postulated Threat.
Finally, the department's criteria for determining the severity of
radiological, chemical, and biological sabotage may be insufficient.
For example, the criterion used for protection against radiological
sabotage is based on acute radiation dosages received by individuals.
However, this criterion may not fully capture or characterize the
damage that a major radiological dispersal at a DOE site might cause.
For example, according to a March 2002, DOE response to a January 23,
2002, letter from Representative Edward J. Markey, a worst-case
analysis at one DOE site showed that while a radiological dispersal
would not pose immediate, acute health problems for the general public,
the public could experience measurable increases in cancer mortality
over a period of decades after an event. Moreover, releases at the site
could also have environmental consequences requiring hundreds of
millions to billions of dollars to clean up. Contamination could also
affect habitability for tens of miles from the site, possibly affecting
hundreds of thousands of residents for many years. Likewise, the same
response showed that a similar event at a NNSA site could result in a
dispersal of plutonium that could contaminate several hundred square
miles and ultimately cause thousands of cancer deaths. For chemical
sabotage standards, the 2003 DBT requires sites to protect to industry
standards. However, we reported last year that such standards currently
do not exist. Specifically, we found that no federal laws explicitly
require chemical facilities to assess vulnerabilities or take security
actions to safeguard their facilities against terrorist attack.
Finally, the protection criteria for biological sabotage are based on
laboratory safety standards developed by the U.S. Centers for Disease
Control, not physical security standards.
DOE Has Been Slow to Resolve a Number of Significant Issues That May
Affect the Ability of its Sites to Fully Meet the Threat Contained in
the New DBT:
While DOE issued the final DBT in May 2003, it has been slow to resolve
a number of significant issues that may affect the ability of its sites
to fully meet the threat contained in the new DBT in a timely fashion.
Fully resolving these issues may take several years and the total cost
of meeting the new threats is currently unknown. Because some sites
will be unable to effectively counter the higher threat contained in
the new DBT for up to several years, these sites should be considered
to be at higher risk under the new DBT than they were under the old
DBT.
In order to undertake the necessary range of vulnerability assessments
to accurately evaluate their level of risk under the new DBT and
implement necessary protective measures, DOE recognized that it had to
complete a number of key activities. DOE only recently completed two of
these key activities. First, in February 2004, DOE issued its Adversary
Capabilities List, which is a classified companion document to the DBT,
that lists the potential weaponry, tactics, and capabilities of the
terrorist group described in the DBT. This document has been amended to
include, among other things, heavier weaponry and other capabilities
that are potentially available to terrorists who might attack DOE
facilities. DOE is continuing to review relevant intelligence
information for possible incorporation into future revisions of the
Adversary Capabilities List.
Second, DOE also only recently provided additional DBT implementation
guidance. In a July 2003 report, DOE's Office of Independent Oversight
and Performance Assurance noted that DOE sites had found initial DBT
implementation guidance confusing. For example, when the Deputy
Secretary of Energy issued the new DBT in May 2003, the cover memo said
the new DBT was effective immediately but that much of the DBT would be
implemented in fiscal years 2005 and 2006. According to a 2003 report
by the Office of Independent Oversight and Performance Assurance, many
DOE sites interpreted this implementation period to mean that they
should, through fiscal year 2006, only be measured against the
previous, less demanding 1999 DBT. In particular, the 2003 report found
that one NNSA site was planning to conduct certain operations starting
in 2003 that involved special nuclear material using security plans
that did not comply with even the 1999 DBT. Consequently, the Office of
Independent Oversight and Performance Assurance recommended that the
site suspend these planned operations until it had adequate security
plans that reflected the new DBT. NNSA security officials concurred
with this recommendation and postponed the site's proposed operations.
In response to this confusion, the Deputy Secretary issued further
guidance in September 2003 that called for the following, among other
things:
* DOE's Office of Security to issue more specific guidance by October
22, 2003, regarding DBT implementation expectations, schedules, and
requirements. DOE issued this guidance January 30, 2004.
* Quarterly reports showing sites' incremental progress in meeting the
new DBT for ongoing activities.
* Immediate compliance with the new DBT for new and reactivated
operations.
Other important DBT-related issues remain unresolved. First, as noted
earlier, a special team created in the 2003 DBT, composed of weapons
designers and security specialists, finalized its report on each site's
improvised nuclear device vulnerabilities. The results of this report
were briefed to senior DOE officials in March 2004. Based on this
team's report, the Secretary may officially designate some sites as
having an improvised nuclear device concern. If this designation is
made, some sites may be required under the 2003 DBT to shift to a
denial of access or denial of task protection strategy, which could be
very costly. This special team's report may most affect EM sites
because their improvised nuclear device potential had not been explored
until this review, and their formal protection strategy remains at the
less demanding containment with recapture and recovery level. DOE
officials have not identified when the Secretary will make these
designations.
Second, DOE's Office of Security has not completed all of the
activities associated with the new vulnerability assessment methodology
it has been developing for over a year. DOE's Office of Security
believes this methodology, which uses a new mathematical equation for
determining levels of risk, will result in a more sensitive and
accurate portrayal of each site's defenses-in-depth and the
effectiveness of sites' protective systems (i.e., physical security
systems and protective forces) when compared with the new DBT. DOE's
Office of Security decided to develop this new equation because its old
mathematical equation had been challenged on technical grounds and did
not give sites credit for the full range of their defenses-in-depth.
While DOE's Office of Security completed this equation in December
2002, officials from this office believe it will probably not be
completely implemented at the sites for at least another year for two
reasons. First, site personnel who implement this methodology will
require additional training to ensure they are employing it properly.
DOE's Office of Security conducted initial training in December 2003,
as well as a prototype course in February 2004, and has developed a
nine-course vulnerability assessment certification program. Second,
sites will have to collect additional data to support the broader
evaluation of their protective systems against the new DBT. Collecting
these data will require additional computer modeling and force-on-force
performance testing.
Because of the slow resolution of some of these issues, DOE has not
developed any official long-range cost estimates or developed any
integrated, long-range implementation plans for the May 2003 DBT.
Specifically, neither the fiscal year 2003 nor 2004 budgets contained
any provisions for DBT implementation costs. However, during this
period, DOE did receive additional safeguards and security funding
through budget reprogramming and supplemental appropriations. DOE used
most of these additional funds to cover the higher operational costs
associated with the increased SECON measures. DOE has gathered initial
DBT implementation budget data and has requested additional DBT
implementation funding in the fiscal year 2005 budget: $90 million for
NNSA, $18 million for the Secure Transportation Asset within the Office
of Secure Transportation, and $26 million for EM. However, DOE
officials believe the budget data collected so far has been of
generally poor quality because most sites have not yet completed the
necessary vulnerability assessments to determine their resource
requirements. Consequently, the fiscal year 2006 budget may be the
first budget to begin to accurately reflect the safeguards and security
costs of meeting the requirements of the new DBT. Reflecting these
various delays and uncertainties, in September 2003, the Deputy
Secretary changed the deadline for DOE program offices, such as EM and
NNSA, to submit DBT implementation plans from the original target of
October 2003 to the end of January 2004. NNSA and EM approved these
plans in February 2004.
A DOE Office of Budget official told us that current DBT implementation
cost estimates do not include items such as closing unneeded
facilities, transporting and consolidating materials, completing line
item construction projects, and other important activities that are
outside of the responsibility of the safeguards and security program.
For example, EM's Security Director told us that, for EM to fully
comply with the DBT requirements in fiscal year 2006 at one of its
sites, it will have to:
* close and de-inventory two facilities,
* consolidate excess materials into remaining special nuclear materials
facilities, and:
* move consolidated Category I special nuclear material, which NNSA's
Office of Secure Transportation will transport, to another site.
Likewise, the EM Security Director told us that to meet the DBT
requirements at another site, EM will have to accelerate the closure of
one facility and transfer special nuclear material to another facility
on the site. The costs to close these facilities and to move materials
within a site are borne by the EM program budget and not by the EM
safeguards and security budget. Similarly, the costs to transport the
material between sites are borne by NNSA's Office of Secure
Transportation budget and not by EM's safeguards and security budget. A
DOE Office of Budget official told us that a comprehensive, department-
wide approach to budgeting for DBT implementation that includes such
important program activities as described above is needed; however,
such an approach does not currently exist.
The department plans to complete DBT implementation by the end of
fiscal year 2006. However, most sites estimate that it will take 2 to 5
years, if they receive adequate funding, to fully meet the requirements
of the new DBT. During this time, sites will have to conduct
vulnerability assessments, undertake performance testing, and develop
Site Safeguards and Security Plans. Consequently, full DBT
implementation could occur anywhere from fiscal year 2005 to fiscal
year 2008. Some sites may be able to move more quickly and meet the
department's deadline of the end of fiscal year 2006. For example, one
NNSA site already has developed detailed plans and budgets to meet the
new DBT requirements.
While this site may be already close to meeting the new DBT
requirements, other DOE sites are at higher risk to the threats
specified under the 2003 DBT than they were under the old 1999 DBT. For
example, the Office of Independent Oversight and Performance Assurance
has concluded in recent inspections that at least two DOE sites face
fundamental and not easily resolved security problems that will make
meeting the requirements of the new DBT difficult. For other DOE sites,
their level of risk under the new DBT remains largely unknown until
they can conduct the necessary vulnerability assessments. Because some
sites will be unable to effectively counter the threat contained in the
new DBT for a period of up to several years, these sites should be
considered to be at higher risk under the new DBT than they were under
the old DBT.
Conclusions:
DOE took a series of immediate actions in response to the terrorist
attacks of September 11, 2001. While each of these actions have been
important, in and of themselves, we believe they are not sufficient to
ensure that all of DOE's sites are adequately prepared to defend
themselves against the higher terrorist threat present in a post
September 11, 2001 world. Rather, DOE must press forward with a series
of actions to ensure that it is fully prepared to provide a timely and
cost effective defense.
First, DOE needs to know the effectiveness of its most immediate
response to September 11, 2001-the move to higher SECON levels. The
higher SECON levels, while increasing the level of visible deterrence,
have come at a significant cost in budget dollars and protective force
readiness. We believe that DOE needs to follow its own policies and use
its well-established vulnerability assessment methodology to evaluate
the effectiveness of these additional security measures.
Second, because the September 11, 2001, terrorist attacks suggested
larger groups of terrorists with broader aspirations of causing mass
casualties and panic, we believe that the DBT development process that
was used requires reexamination. While DOE may point to delays in the
development of the Postulated Threat as the primary reason for the
almost 2 years it took to develop a new DBT, DOE was also working on
the DBT itself for most of that time. We believe the difficulty
associated with developing a consensus using DOE's traditional policy-
making process was a key factor in the time it took to develop a new
DBT. During this extended period, DOE's sites were only being defended
against what was widely recognized as an obsolete terrorist threat
level.
Third, we are concerned about two aspects of the resulting DBT. We are
not persuaded that there is sufficient difference, in its ability to
achieve the objective of causing mass casualties or creating public
panic, between the detonation of an improvised nuclear device and the
detonation of a nuclear weapon or test device at or near design yield
that warrants setting the threat level at a lower number of terrorists.
Furthermore, while we applaud DOE for adding additional requirements to
the DBT such as protection strategies to guard against radiological,
chemical, and biological sabotage, we believe that DOE needs to
reevaluate its criteria for terrorist acts of sabotage, especially in
the chemical area, to make it more defensible from a physical security
perspective.
Finally, because some sites will be unable to effectively counter the
threat contained in the new DBT for a period of up to several years,
these sites should be considered to be at higher risk under the new DBT
than they were under the old DBT. Consequently, DOE needs to take a
series of actions to mitigate these risks to an acceptable level as
quickly as possible. To accomplish this, it is important for DOE to
resolve a number of DBT and DBT-related issues and go about the hard
business of a comprehensive department-wide approach to implementing
needed changes in its protective strategy. Because the consequences of
a successful terrorist attack on a DOE site could be so devastating, we
believe it is important for DOE to inform the Congress about what sites
are at high risk and what progress is being made to reduce these risks
to acceptable levels.
Recommendations for Executive Action:
In order to strengthen DOE's ability to meet the requirements of the
new DBT, as well as to strengthen the department's ability to deal with
future terrorist threats, we are making the following seven
recommendations to the Secretary of Energy:
* Evaluate the cost and effectiveness of existing SECONs and how they
are implemented using DOE's vulnerability assessment methodology.
* Review how the DBT is developed to determine if using the current
policy-making approach is appropriate given the dynamic post-September
11, 2001, security environment.
* Reexamine the current application of the graded threat approach to
sites that may have improvised nuclear device concerns.
* Reexamine the criteria established in the May 2003 DBT to determine
levels of risk from radiological, biological, and chemical sabotage to
ensure that they are appropriate from a security standpoint.
* Ensure that all remaining DBT and DBT related-issues, such as the
designation of improvised nuclear device concerns and the new
vulnerability assessment methodology, are completed on an expedited
schedule.
* Develop and implement a department-wide, multiyear, fully resourced
implementation plan for meeting the new DBT requirements that includes
important programmatic activities such as the closure of facilities and
the transportation of special nuclear materials.
* Report regularly to relevant congressional oversight committees on:
(1) the status of DBT implementation as reflected by the required
quarterly DBT implementation progress reports and (2) which sites and
facilities are currently considered to be at high risk under the new
DBT and what steps are being taken to mitigate these risks to
acceptable levels.
Agency Comments and Our Evaluation:
We provided DOE with a draft of the classified version of this report
for review and comment. In its written comments, DOE said it was
committed to the development and promulgation of an accurate and
comprehensive DBT policy. DOE did not comment specifically on our
recommendations other than to say that the department would consider
them as part of its Departmental Management Challenges for 2004. DOE
has identified the DBT as a major departmental initiative within the
National Security Management Challenge. In an enclosure attached to its
comments, DOE also provided some additional technical information that
we incorporated where appropriate. DOE's letter commenting on our draft
report is presented in appendix I.
We are sending copies of this report to the Secretary of Energy, the
Director of the Office of Management and Budget, and appropriate
congressional committees. We also will make copies available to others
upon request. In addition, the report will be available at no charge on
the GAO Web site at http://www.gao.gov.
If you or your staff have any questions about this report, please call
me at (202) 512-3841. Major contributors to this report are listed in
appendix II.
Sincerely yours,
Signed by:
Robin M. Nazzaro,
Director, Natural Resources and Environment:
[End of section]
Appendix I: Comments from the Department of Energy:
Department of Energy
Washington, DC 20585:
February 9, 2004:
Ms. Robin Nazzaro:
Director, Natural Resources and Environment
United States General Accounting Office
441 G Street, NW:
Washington, DC 20548:
Dear Ms. Nazzaro:
The Department of Energy (DOE) appreciates the opportunity to review
and comment on the General Accounting Office (GAO) draft report, "DOE
Needs to Resolve Significant Issues Before it Fully Meets the New
Design Basis Threat (U)," transmitted by your letter dated January 23,
2004, GAO-04-273C.
DOE is committed to the development and promulgation of an accurate and
comprehensive Design Basis Threat (DBT) policy. The DBT is developed by
the Office of Security and Safety Performance Assurance based on
information from the intelligence organizations, both internal and
external to DOE, national security information, and technical exchanges
with the Department of Defense (DoD) and the Nuclear Regulatory
Commission (NRC). The DBT is developed to consider all Departmental
nuclear assets and the potential consequences of the loss or compromise
of those assets.
With respect to the recommendations in the draft report, we will
consider each of them as part of the Departmental Management Challenges
for 2004. For the National Security Management Challenge, the DBT has
already been identified as a major Departmental initiative.
Our specific comments are included in Enclosure 1. The comments provide
additional information for consideration in the report and a suggested
correction to one minor inaccuracy. Please contact Marshall Combs,
Director, Office of Security, at 202-586-3345 if you have any
additional questions.
Sincerely,
Signed by:
Glenn S. Podonsky, Director
Office of Security and Safety Performance Assurance:
Enclosure (as stated):
cc:
K. McSlarrow, DS L. Brooks, NA-1 R. Card, US:
T. Johnson, NA-1 B. Desmond, NA-55 M. Combs, SO-1 M. Kilpatrick, OA-1:
[End of section]
Appendix II: GAO Contact and Staff Acknowledgments:
GAO Contact:
James Noel (202) 512-3591:
Staff Acknowledgments:
In addition to the individuals named above, Jonathan Gill, Chris
Pacheco, Andrea Miller, Chris Abraham, Jill Berman, Carol Hernstadt
Shulman, Joyce Evans, and Gail Traynham also made key contributions to
this report.
FOOTNOTES
[1] NNSA is responsible for the nation's nuclear weapons,
nonproliferation, and naval reactors programs. We did not include Naval
Reactors in our review because that office is a semiautonomous entity
with a unique security structure and program.
[2] At the time of our review, the Rocky Flats Environmental Technology
Site in Rocky Flats, Colorado, was in the process of shipping its
remaining Category I special nuclear material primarily to the Savannah
River Site. This has now been completed. In addition, responsibility
for the Idaho National Engineering and Environmental Laboratory, in
Idaho Falls, Idaho, which is also a Category I special nuclear material
site, was transferred from DOE's EM to DOE's Office of Nuclear Energy
in May 2003.
[3] Federal employees instead of contractors operate the assets of the
Office of Secure Transportation.
[4] See U.S. General Accounting Office, Nuclear Security: NNSA Needs to
Better Manage Its Safeguards and Security Program, GAO-03-471
(Washington, D.C.: May 30, 2003).
[5] We testified on these issues before the Subcommittee on National
Security, Emerging Threats, and International Relations, House
Committee on Government Reform, on June 24, 2003. See U.S. General
Accounting Office, Nuclear Security: DOE's Response to the September
11, 2001 Terrorist Attacks, GAO-03-898TC (Washington, D.C.: June 24,
2003).
[6] See U.S. General Accounting Office, Homeland Security: Voluntary
Initiatives Are Under Way at Chemical Facilities, but the Extent of
Security Preparedness Is Unknown, GAO-03-439 (Washington, D.C.: Mar.
14, 2003).
[7] Audit Report: Management of the Department's Protective Forces,
DOE/IG-0602, Department of Energy, Office of the Inspector General,
June 2003.
GAO's Mission:
The General Accounting Office, the investigative arm of Congress,
exists to support Congress in meeting its constitutional
responsibilities and to help improve the performance and accountability
of the federal government for the American people. GAO examines the use
of public funds; evaluates federal programs and policies; and provides
analyses, recommendations, and other assistance to help Congress make
informed oversight, policy, and funding decisions. GAO's commitment to
good government is reflected in its core values of accountability,
integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains
abstracts and full-text files of current reports and testimony and an
expanding archive of older products. The Web site features a search
engine to help you locate documents using key words and phrases. You
can print these documents in their entirety, including charts and other
graphics.
Each day, GAO issues a list of newly released reports, testimony, and
correspondence. GAO posts this list, known as "Today's Reports," on its
Web site daily. The list contains links to the full-text document
files. To have GAO e-mail this list to you every afternoon, go to
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order
GAO Products" heading.
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. General Accounting Office
441 G Street NW,
Room LM Washington,
D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Public Affairs:
Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.
General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.
20548: