Department of Energy
Additional Opportunities Exist for Reducing Laboratory Contractors' Support Costs
Gao ID: GAO-05-897 September 9, 2005
In fiscal year 2004, about two-thirds of the Department of Energy's (DOE) $26.9 billion in spending went to 28 major facilities--laboratories, production and test facilities, and nuclear waste cleanup and storage facilities. DOE spent about $2.9 billion in fiscal year 2004 to support the mission of its five largest laboratories. GAO was asked to examine (1) recent trends in indirect and functional support cost rates for these five laboratories, noting key differences in how contractors classify costs, and (2) the efforts of DOE and its contractors to reduce indirect and other support costs and identify additional opportunities for savings.
For fiscal years 2000 through 2004, laboratory-reported rates for indirect costs--those not charged directly to a specific program--increased at two laboratories and decreased at three. However, indirect cost rates cannot be compared across laboratories because contractors classify different portions of support costs as indirect. To facilitate analysis, DOE requires the laboratories to report what it called "functional support costs," or costs that support missions, regardless of whether they are classified as direct or indirect costs. Using this measure, three laboratories' rates--that is, functional support costs divided by total costs--increased and two laboratories' rates decreased over the 5-year period. While functional support cost rates improved comparability, several DOE and contractor officials said that the definitions for some categories of support costs, such as "facilities management," are unclear, leading to confusion and inconsistent reporting. DOE and its contractors have initiated several steps to reduce indirect and other support costs but can take additional actions to improve their implementation. First, DOE's laboratory contracts have increasingly included incentives to encourage cost reductions. In fiscal year 2004, for example, the National Nuclear Security Administration began an "award-term" pilot program that allows a contractor to earn extra contract years based on performance and cost-saving achievements. However, DOE is expanding use of this incentive without evaluating it. Second, DOE requires its contractors to benchmark employee benefits and to reduce benefits if they exceed the benchmark, but DOE did not promptly enforce these requirements at one laboratory and exempted two others. Third, DOE has begun to address a $1.9 billion backlog of deferred maintenance to reduce long-term costs. However, without a more rigorous approach, the backlog will persist well into future decades. Lastly, while some laboratories have used process improvement programs to streamline business processes and reduce costs, others do not have such programs, nor are they required to have them.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-05-897, Department of Energy: Additional Opportunities Exist for Reducing Laboratory Contractors' Support Costs
This is the accessible text file for GAO report number GAO-05-897
entitled 'Department of Energy: Additional Opportunities Exist for
Reducing Laboratory Contractors' Support Costs' which was released on
October 11, 2005.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to the Subcommittee on Energy and Water Development, Committee
on Appropriations, House of Representatives:
September 2005:
Department of Energy:
Additional Opportunities Exist for Reducing Laboratory Contractors'
Support Costs:
GAO-05-897:
GAO Highlights:
Highlights of GAO-05-897, a report to the Subcommittee on Energy and
Water Development, Committee on Appropriations, House of
Representatives:
Why GAO Did This Study:
In fiscal year 2004, about two-thirds of the Department of Energy‘s
(DOE) $26.9 billion in spending went to 28 major
facilities”laboratories, production and test facilities, and nuclear
waste cleanup and storage facilities. DOE spent about $2.9 billion in
fiscal year 2004 to support the mission of its five largest
laboratories (see table). GAO was asked to examine (1) recent trends in
indirect and functional support cost rates for these five laboratories,
noting key differences in how contractors classify costs, and (2) the
efforts of DOE and its contractors to reduce indirect and other support
costs and identify additional opportunities for savings.
What GAO Found:
For fiscal years 2000 through 2004, laboratory-reported rates for
indirect costs”those not charged directly to a specific
program”increased at two laboratories and decreased at three. However,
indirect cost rates cannot be compared across laboratories because
contractors classify different portions of support costs as indirect.
To facilitate analysis, DOE requires the laboratories to report what it
called ’functional support costs,“ or costs that support missions,
regardless of whether they are classified as direct or indirect costs.
Using this measure, three laboratories‘ rates”that is, functional
support costs divided by total costs”increased and two laboratories‘
rates decreased over the 5-year period. While functional support cost
rates improved comparability, several DOE and contractor officials said
that the definitions for some categories of support costs, such as
’facilities management,“ are unclear, leading to confusion and
inconsistent reporting.
DOE and its contractors have initiated several steps to reduce indirect
and other support costs but can take additional actions to improve
their implementation. First, DOE‘s laboratory contracts have
increasingly included incentives to encourage cost reductions. In
fiscal year 2004, for example, the National Nuclear Security
Administration began an ’award-term“ pilot program that allows a
contractor to earn extra contract years based on performance and cost-
saving achievements. However, DOE is expanding use of this incentive
without evaluating it. Second, DOE requires its contractors to
benchmark employee benefits and to reduce benefits if they exceed the
benchmark, but DOE did not promptly enforce these requirements at one
laboratory and exempted two others. Third, DOE has begun to address a
$1.9 billion backlog of deferred maintenance to reduce long-term costs.
However, without a more rigorous approach, the backlog will persist
well into future decades. Lastly, while some laboratories have used
process improvement programs to streamline business processes and
reduce costs, others do not have such programs, nor are they required
to have them.
Functional Support Costs for Five DOE Laboratories Reviewed, Fiscal
Year 2004:
Dollars in millions:
National laboratory: Idaho;
Contractor: Battelle Energy Alliance;
Functional support costs: $377.5.
National laboratory: Lawrence Livermore;
Contractor: University of California;
Functional support costs: $573.2.
National laboratory: Los Alamos;
Contractor: University of California;
Functional support costs: $889.1.
National laboratory: Oak Ridge;
Contractor: UT–Battelle, LLC;
Functional support costs: $292.9.
National laboratory: Sandia;
Contractor: Lockheed Martin Corporation;
Functional support costs: $718.0.
Source: DOE.
[End of table]
What GAO Recommends:
GAO is recommending that DOE take several actions to improve the
comparability of functional support cost data among laboratories and
reduce support costs by assessing the overall effectiveness of
initiatives and ensuring that DOE laboratories adopt important cost-
saving initiatives.
In commenting on the draft report, DOE generally concurred with GAO‘s
recommendations.
www.gao.gov/cgi-bin/getrpt?GAO-05-897.
To view the full product, including the scope and methodology, click on
the link above. For more information, contact Jim Wells at (202) 512-
3841 or wellsj@gao.gov.
[End of section]
Contents:
Letter:
Results in Brief:
Background:
Some Laboratories' Cost Rates Have Increased While Others Have
Decreased, but Not All Rates Are Comparable:
DOE and Its Contractors Have Taken Actions to Reduce Indirect and Other
Support Costs, but Opportunities Exist for Further Reductions:
Conclusions:
Recommendations for Executive Action:
Agency Comments:
Scope and Methodology:
Appendixes:
Appendix I: Award-Term Provisions at Four DOE Sites:
Appendix II: Comments from the Department of Energy:
Appendix III: GAO Contact and Staff Acknowledgments:
Tables:
Table 1: Functional Support Cost Rates for Five Laboratories, Fiscal
Years 2000-04:
Table 2: Results of the DOE-Funded Employee Benefit Value Studies for
Each of the Five Laboratories:
Table 3: Award-Term Provisions for Four DOE Facilities:
Abbreviations:
CFO: chief financial officer:
DOE: Department of Energy:
NNSA: National Nuclear Security Administration:
Letter September 9, 2005:
The Honorable David L. Hobson:
Chairman:
The Honorable Peter J. Visclosky:
Ranking Minority Member:
Subcommittee on Energy and Water Development:
Committee on Appropriations:
House of Representatives:
In fiscal year 2004, about two-thirds of the Department of Energy's
(DOE) $26.9 billion in spending went to 28 major facilities, including
laboratories, nuclear weapons test and production facilities, and
nuclear waste cleanup and storage facilities. DOE primarily uses
contractors--industrial firms and nonprofit organizations, including
educational institutions--to manage and operate these facilities. DOE
oversees these contractors' activities through its headquarters program
offices--primarily the National Nuclear Security Administration (NNSA),
the Office of Environmental Management, and the Office of Science--and
site offices located at each facility.
DOE reimburses its contractors for the costs incurred in carrying out
the department's missions. These include costs that can be directly
identified with a specific DOE program (known as direct costs) and
costs of activities that indirectly support a program (known as
indirect costs), such as administrative activities, utilities, and
building maintenance. To ensure that DOE programs are appropriately
charged for incurred costs, contractors' accounting systems assign the
direct costs associated with each program and collect similar types of
indirect costs into pools and allocate them proportionately among the
programs.
Historically, DOE obtained information on contractors' overall indirect
cost rates--the ratio of indirect costs to total operating costs--as a
basis for assessing contractors' efficiency in performing their
missions. However, the indirect cost rates of different facilities
cannot readily be compared (1) because cost accounting standards and
federal regulations provide contractors with flexibility regarding the
extent to which they identify incurred costs directly with a specific
program and how they collect similar costs into indirect cost pools and
allocate them among programs and (2) because of differences in the
facilities' missions, corporate structures, and accounting
systems.[Footnote 1] As a result, contractors' methods for accumulating
and allocating indirect costs vary--that is, a cost classified as an
indirect cost at one laboratory may be classified as a direct cost at
another. For example, electricity and other utility costs are usually
classified as indirect because they are not associated with a single
program; however, electricity costs could be charged directly if, for
example, a laboratory installs a meter to track the electricity
consumption in a building used solely by one program.
In the mid-1990s, DOE's chief financial officer (CFO) created 22
standard categories of "functional support costs" to obtain more
consistent information about the support costs at DOE's major
contractor-operated facilities. These categories include, for example,
executive direction, information services, procurement, maintenance,
and facilities management. Each of the 22 categories is defined to
cover all related costs, irrespective of whether contractors classify
them as direct or indirect. Beginning in fiscal year 1997, the CFO and
the Financial Management Systems Improvement Council, composed of DOE
and contractor financial officials, have required the department's
primary contractors to annually report these costs. To oversee the
quality of these data, contractors' financial personnel generally peer
review the data for each facility once every few years. In fiscal year
2004, functional support costs accounted for $7.2 billion, or nearly 40
percent, of the contractors' $18.1 billion total costs. The functional
support costs for the five largest DOE laboratories were $2.9 billion.
You asked us to examine (1) recent trends in reported indirect and
functional support cost rates at the largest DOE contractor-operated
laboratories, noting any key differences in how the contractors
determine which costs are indirect and how these rates compare with
those of similar laboratories in other federal agencies, and (2) the
efforts of DOE and its laboratory contractors to reduce indirect and
other support costs, identifying additional opportunities for potential
savings. In response, we reviewed DOE's five laboratories with the
greatest total operating costs--NNSA's Lawrence Livermore National
Laboratory, Los Alamos National Laboratory, and Sandia National
Laboratories; the Office of Science's Oak Ridge National Laboratory;
and the Office of Nuclear Energy's Idaho National Laboratory.[Footnote
2] The total costs of these five laboratories, $7.5 billion, accounted
for more than a quarter of DOE's total fiscal year 2004 budget. For
purposes of comparison with other federal laboratories, we identified
two similar large, contractor- operated laboratories--the Jet
Propulsion Laboratory, located in Pasadena, California, and operated by
the California Institute of Technology for the National Aeronautics and
Space Administration; and Lincoln Laboratory, located in Lexington,
Massachusetts, and operated by the Massachusetts Institute of
Technology for the Department of the Air Force. We determined that the
selection of these seven laboratories was appropriate for our design
and objectives and would generate valid and reliable evidence to
support our work.
To examine recent trends in the indirect cost rates of the five DOE
laboratories, we obtained indirect cost rates from each laboratory for
fiscal years 2000 through 2004 and identified cost-rate trends,
reviewed differences in what types of costs the laboratories included
in their indirect cost pools and how they allocated these costs, and
reviewed the laboratories' indirect cost rates and those of the Jet
Propulsion Laboratory and Lincoln Laboratory. We did not include
indirect cost rates in this report because some of these data are
proprietary. We also examined the fiscal years 2000 through 2004 data
that DOE's CFO published in its Fiscal Year 2004 Support Cost by
Functional Activity Report to compare these costs for the five DOE
laboratories. To examine the efforts of DOE and its laboratory
contractors to reduce indirect and other support costs, we reviewed
contractual provisions, key cost-saving initiatives, and audits.
Specifically, we reviewed the management and operating contracts for
each of the five laboratories, including clauses focused on reducing
functional support costs; analyzed several key initiatives that DOE and
its contractors have undertaken to reduce costs and the initiatives'
applicability to other DOE facilities; and examined reports of DOE's
Office of Inspector General and the contractors' internal audit teams.
We performed our work between January 2005 and August 2005, in
accordance with generally accepted government auditing standards.
Results in Brief:
For fiscal years 2000 through 2004, reported indirect cost rates
increased at two laboratories operated by DOE contractors and decreased
at three of them. Los Alamos had the largest reported increase, 10.4
percent, which it attributes to its July 2004 suspension of almost all
of the laboratory's operations in response to safety and security
concerns. Idaho had the largest decrease, 32.1 percent, primarily
because of changes in its accounting for indirect costs. Although a
contractor's overall indirect cost rates are generally comparable over
time, some rates, such as Idaho's fiscal year 2004 rate, are not
comparable. Specifically, in fiscal year 2004, the contractor at Idaho
reclassified a large portion of its indirect costs as direct to prepare
for a new environmental cleanup contract that is separate from its
laboratory operations contract. In addition, indirect costs cannot be
compared across laboratories because one contractor may classify a
greater portion of a particular support cost as an indirect cost than
another contractor. For example, from fiscal years 2000 through 2003,
Idaho classified all of its administrative support as indirect costs,
while other laboratories, such as Oak Ridge, classified administrative
support as both direct and indirect costs. In addition, Lawrence
Livermore and Oak Ridge treat maintenance for roads and grounds as
indirect expenses, while Idaho treats them as direct expenses.
Regarding functional support costs, three laboratories' rates increased
and two laboratories' rates decreased over the 5-year period we
examined. Again, Los Alamos had the largest increase, and Idaho had the
largest decrease. While functional support cost rates facilitate
greater comparability across laboratories, several DOE and contractor
officials told us that the definitions for some categories are unclear,
leading to confusion among categories. Notably, the "facilities
management" and "maintenance" categories are ambiguous and, hence, are
not fully comparable across laboratories. Because of the differences in
how DOE contractors categorize direct and indirect costs, and because
only DOE contractors report functional support costs, the rates at
DOE's laboratories cannot be compared with those of the Jet Propulsion
Laboratory or Lincoln Laboratory. For example, Jet Propulsion
Laboratory officials told us that they categorize all their costs as
direct in accordance with their contract with the National Aeronautics
and Space Administration.
DOE and its contractors have taken several actions to reduce indirect
and other support costs, but improved implementation could also produce
savings--particularly in the following areas of contract incentives,
contractors' employee benefits, deferred maintenance, and process
improvements:
* DOE's management and operating contracts have increasingly included
incentives to encourage cost reductions. For example, beginning in
fiscal year 2003, DOE contracts have placed greater emphasis on
performance objectives and fees based on the efficiency of
laboratories' business operations. In addition, in fiscal year 2004,
NNSA began a pilot "award-term" program that allows the contractor at
Sandia to earn up to 5 additional years on its 5-year contract if it
receives an overall rating of "outstanding" each year and achieves cost
savings sufficient to fund completion of projects that were approved
but did not receive full funding. In the first year of the pilot
program, Sandia's contractor earned a 1-year extension on its contract.
DOE has proposed to expand this pilot program to the Los Alamos
contract--and to allow contract extensions of up to 13 years beyond the
proposed 7-year contract term--even though the award-term program is
less than 2 years old and DOE has not yet evaluated its effectiveness.
For example, DOE has not evaluated whether the cost savings achieved
impaired the quality of work.
* DOE requires its contractors to benchmark the value of pension and
other benefit programs with those of industry and to reduce the value
of benefits if they exceed the overall benchmarked average by 5 percent
or more. However, DOE has exempted the University of California, which
manages Lawrence Livermore and Los Alamos, from benchmarking the value
of its benefits because those laboratories use the university's benefit
program. Of the three remaining laboratories, Idaho and Oak Ridge have
benefits whose values fall within the allowable range, while Sandia's
benefits have substantially exceeded the overall benchmarked average
since 2002, with current pension benefits being 68 percent higher. DOE
did not request that Sandia's contractor propose corrective actions
until May 2005, 3 years after discovering the benefits were too high.
While enforcing the limits on benefit values is a step in the right
direction, DOE has not set any limits on benefit costs. Because the
value of the benefits does not necessarily correlate with their costs,
controlling the benefits' value alone may not be the most effective
means to manage costs. Although DOE proposed in November 2003 to
require contractors to evaluate both the value and cost of their
benefits, it has not yet finalized this requirement, over 2 years
later.
* After decades of neglect, DOE has begun to address a backlog of
deferred maintenance at its facilities to reduce support costs in the
long term. As required by DOE, the five laboratories have 10-year plans
to reduce their maintenance backlog, which was valued at $1.9 billion
in fiscal year 2004. However, without a more rigorous approach, the
backlog will persist well beyond 10 years. To speed the backlog
reduction for NNSA facilities--including Lawrence Livermore, Los
Alamos, and Sandia--the Congress has funded the first 3 years of a 10-
year effort to "buy down" the backlog. However, only Lawrence Livermore
and Sandia have demonstrated success with long-term approaches to
further reduce their maintenance backlogs and minimize reaccumulation.
For example, Lawrence Livermore charges DOE and other agency programs
that use the laboratory about $8 per square foot for maintenance in an
effort to reduce the backlog.
* Idaho, Lawrence Livermore, and Sandia have used process improvement
programs to assess their operations and reduce costs. For example,
Idaho used process improvement methods to reduce the average cost of
each of 16 safety assessment reports, for a total 2-year savings of
$907,000. While it is generally recognized that using a process
improvement program is a good business practice, neither Los Alamos nor
Oak Ridge has one.
We are making several recommendations to the Secretary of Energy to
improve the comparability of functional support cost data among
laboratories and to reduce these costs by assessing the overall
effectiveness of initiatives and ensuring that other DOE laboratories
adopt important cost-saving initiatives. In commenting on a draft of
this report, DOE generally concurred with all of the recommendations.
Background:
The Federal Acquisition Regulation and Cost Accounting Standards
provide overall requirements for allocating incurred costs either
directly to a program or indirectly to pools of similar types of costs
that are allocated proportionately among the programs. For example, to
avoid double counting and ensure that DOE programs and other federal
agencies pay an appropriate share of indirect costs, the standards
require that a contractor use consistent methods for estimating costs
for each project or activity. That is, if the laboratory charges one
project $8 per square foot for maintenance, it must charge other
projects in the same manner. Contractors submit for DOE approval
accounting policy statements describing how they will classify costs as
direct or indirect.
DOE improved its ability to compare laboratories' costs in fiscal year
1997, when it began requiring contractors to report all functional
support costs, regardless of how they were classified. Functional
support cost data facilitate comparisons of laboratories' costs because
they are intended to include all costs that support laboratory
missions, regardless of whether a particular laboratory has classified
the support costs as direct or indirect. However, functional support
costs have limitations in that they cannot account for differences in
the mission, size, age, or location of DOE facilities. Facility
comparisons need to factor in the differences, for example, in (1)
maintenance costs for a 50-year-old manufacturing facility as compared
with those of a modern research facility or (2) safety and health costs
at a facility that uses nuclear materials as compared with a facility
with no nuclear materials.
Some Laboratories' Cost Rates Have Increased While Others Have
Decreased, but Not All Rates Are Comparable:
From fiscal years 2000 through 2004, indirect cost rates increased at
two of the five DOE laboratories we examined and decreased at the other
three laboratories. A laboratory's indirect cost rates are generally
comparable over time, but the indirect cost rates of different
laboratories are not comparable because contractors often categorize
costs differently. Regarding functional support costs, three of the
five laboratories' rates increased, while rates of two laboratories
decreased during the same 5-year period. While functional support cost
data help DOE to compare rates across laboratories, several DOE and
contractor officials told us that the definitions for some categories
are unclear, leading to confusion among categories. Finally, because of
the differences in how DOE contractors categorize direct and indirect
costs, and because other federal, non-DOE contractors do not collect
and report functional support costs, the rates at DOE's laboratories
cannot be compared with those of the Jet Propulsion Laboratory or
Lincoln Laboratory.
Two DOE Laboratories' Indirect Cost Rates Have Increased and Three Have
Decreased, but These Rates Are Not Comparable across Laboratories:
From fiscal years 2000 through 2004, indirect cost rates increased at
two laboratories operated by DOE contractors and decreased at
three.[Footnote 3] Los Alamos had the largest increase--10.4 percent.
Nearly all of this increase occurred during the 4TH quarter of fiscal
year 2004 and, according to Los Alamos officials, was attributable to
the "stand down" of activities that the laboratory director ordered in
July 2004 in response to a series of safety and security incidents. In
particular, the Los Alamos officials told us that the stand down
resulted in lower program costs without similarly lower indirect costs.
For example, $8 million in staff costs for the stand down's first 2
days was treated as indirect costs as laboratory managers developed
plans for assessing and resolving the safety and security issues. Once
risk assessment and mitigation activities began, stand-down costs were
charged directly to benefiting programs. Los Alamos officials stated
that general and administrative costs, especially costs in the
"executive direction" category, were higher than expected, while direct
program costs were lower. The indirect cost rate for Lawrence Livermore
increased as well by 2.9 percent from fiscal years 2000 through 2004
because of additional costs, such as those related to facilities
safety, maintenance, environmental protection, and hazard control.
In contrast, Idaho National Laboratory's indirect cost rate decreased
by 32.1 percent during the 5-year period, mainly because the contractor
reclassified a large portion of its costs associated with environmental
cleanup operations from indirect to direct in fiscal year 2004.
According to contractor officials, these costs were reclassified in
response to DOE's decision to split the management and operating
contract, which expired during fiscal year 2005, into two parts by
awarding separate contracts for laboratory operations and the
environmental restoration of the site. Laboratories can make changes in
how they account for indirect costs, and, when they do, they are
required to document these changes in their disclosure statement for
DOE approval. The indirect cost rates for Oak Ridge and Sandia
decreased by 7.3 percent and 2.2 percent, respectively, between fiscal
years 2000 and 2004. According to Oak Ridge contractor officials, the
decrease resulted from several factors, including management's decision
to limit the growth of indirect costs while the laboratory's total
spending grew--when total costs increase at a higher rate than indirect
costs, the indirect cost rate will decrease because the rate equals the
indirect costs divided by total costs.
Indirect cost rates cannot be meaningfully compared across laboratories
because one contractor may track costs more closely, allowing the
contractor to classify a higher proportion of the cost of a support
activity, such as administration, as a direct cost than another
contractor does. For example, from fiscal years 2000 through 2003, Oak
Ridge and Sandia classified administrative support costs as both
indirect and direct costs, while Idaho classified all administrative
support costs as indirect. Similarly, Idaho classified road and ground
maintenance as direct costs, while Lawrence Livermore and Oak Ridge
treated them as indirect costs. Two contractor officials provided other
examples of costs that laboratories are likely to classify differently:
subcontract administration, any type of fringe benefit, program
management, organizational management and administration, facility
management and maintenance, and information technology functions. A
Lawrence Livermore official noted, for example, that one contractor may
treat desktop software used by many programs as a direct cost, while
another contractor may bundle these software purchases into a common
site license that is paid from an indirect account. The indirect cost
rate may be higher in the latter case, but the goods may be obtained at
a lower cost. Thus, higher indirect costs do not necessarily equate
with less efficiency.
Further, the five DOE contractors use different methods to classify
support activities--that is, they differed in how indirect costs are
collected and distributed. For example, one contractor used 4 major
indirect cost pools while another contractor used 12 indirect cost
pools for distribution among programs. Similarly, the number of major
service centers at the five DOE laboratories ranged from 6 to 14.
Service centers are accounts where costs of specific services are
accumulated and charged on the basis of services rendered, either to a
program or to other indirect cost pools. Common service centers are
telecommunications and computing centers.
Functional Support Cost Rates Provide More Comparability than Indirect
Costs, Although the Definitions for Some Categories Are Unclear:
Table 1 shows that for fiscal years 2000 through 2004, three
laboratories' functional support cost rates increased and two
laboratories' decreased. These rates are the functional support costs
as a percentage of total costs without capital construction. Again, Los
Alamos had the largest increase, 8.1 percent, and Idaho had the largest
decrease, 11.8 percent.[Footnote 4]
Table 1: Functional Support Cost Rates for Five Laboratories, Fiscal
Years 2000-04:
Laboratory: Idaho;
FY 2000: 52.5%;
FY 2001: 52.1%;
FY 2002: 51.4%;
FY 2003: 51.7%;
FY 2004: 46.3%;
Percentage change for FYs 2000-04: (11.8)%.
Laboratory: Lawrence Livermore;
FY 2000: 32.4%;
FY 2001: 34.5%;
FY 2002: 35.1%;
FY 2003: 36.1%;
FY 2004: 34.0%;
Percentage change for FYs 2000-04: 4.9%.
Laboratory: Los Alamos;
FY 2000: 39.7%;
FY 2001: 41.0%;
FY 2002: 40.1%;
FY 2003: 39.5%;
FY 2004: 42.9%;
Percentage change for FYs 2000-04: 8.1%.
Laboratory: Oak Ridge;
FY 2000: 36.6%;
FY 2001: 34.6%;
FY 2002: 34.3%;
FY 2003: 36.2%;
FY 2004: 35.8%;
Percentage change for FYs 2000-04: (2.2%).
Laboratory: Sandia;
FY 2000: 33.5%;
FY 2001: 33.5%;
FY 2002: 32.5%;
FY 2003: 34.7%;
FY 2004: 33.7%;
Percentage change for FYs 2000-04: 0.6%.
Source: DOE's CFO, Fiscal Year 2004 Support Cost by Functional Activity
Report (Washington, D.C.).
Note: This table excludes the "safeguards and security" category from
the functional support costs because DOE and the laboratories have
treated them as direct costs after they began receiving line-item
funding. We also excluded "capital construction" from total costs.
While these rates are more comparable than indirect cost rates, they
are not entirely comparable, as discussed in this report.
[End of table]
Functional support costs were primarily developed to facilitate the
analysis of each facility's costs. While not intended for comparison
purposes, they provide more comparability across laboratories than
indirect costs because they are developed on the basis of standard,
defined cost categories. However, detailed analysis is required to
determine whether rate differences are the result of inefficiencies or
other factors, such as differences in each facility's mission,
activities, location, or size. For example, costs for safety and
health, maintenance, and utilities at Los Alamos are higher than costs
at other sites because, according to DOE officials, the laboratory has
2,224 facilities on 27,800 acres of mesas and canyons. Also, Los Alamos
uses plutonium and other hazardous materials, which require added
safety procedures, and accelerator facilities, which consume large
amounts of electricity.
While functional support cost rates facilitate improved analysis of
laboratory costs, several DOE and contractor officials told us that the
definitions for some categories are somewhat unclear, leading to
confusion in how to categorize certain costs. Notably, the "facilities
management" and "maintenance" categories are somewhat ambiguous and,
hence, are not fully comparable across laboratories. Peer reviewers
checking for accuracy of classification of costs have found that
several laboratories have misclassified costs between the two
categories. In July 2003, peer reviewers found that Sandia had
classified $1.1 million of facilities management costs as maintenance
and $8.8 million in maintenance costs as facilities management. In June
2004, peer reviewers found that Los Alamos had classified $550,000 in
maintenance costs as facilities management. In addition, in fiscal year
2003, a Lawrence Livermore internal review found that the laboratory
had categorized plant facility engineering costs as maintenance, while
other laboratories had categorized these costs as facilities
management. In 2004, after discussing the categories with DOE and
contractor officials involved in reviewing functional support cost
data, Lawrence Livermore moved $15 million from the fiscal years 2002
and 2003 maintenance category to the facilities management category.
Most of the peer reviews for the DOE laboratories and other facilities
found difficulties with which cost elements were placed in or omitted
from "facilities management" and "maintenance," according to our
analysis. In addition, peer reviews at Los Alamos and Oak Ridge found
over $2 million of legal or information services costs that was
misclassified in the "executive direction" category, another example of
a category whose definition may be unclear. Idaho officials reported
that discrepancies in executive direction cost data between Idaho and
other sites resulted from uncertainty about how many levels of
management or what type of site development and strategic planning
costs are to be included in the executive direction category.
Differences in interpretation result from insufficiently detailed
guidance for developing functional support costs. The guidance
primarily consists of 10 pages of 22 support category definitions.
DOE's Web site does not have more detailed instructions that
contractors can turn to when they are uncertain whether a cost should
be classified under one category or another. Contractor officials
developing cost data often turn to different DOE or contractor
officials with responsibility for these data for help, increasing the
likelihood of getting different advice, despite the fact that
consistency is key to data quality. Several DOE and contractor
officials with responsibility for these data agreed that more specific
guidance would cost little to develop and would increase consistency in
reporting. For example, some officials said they could post a list of
common laboratory errors on the Financial Management Systems
Improvement Council's Web site, based on peer review findings of the
past few years.
DOE Laboratories' Cost Rates Cannot Be Compared with Those of Other
Federal Laboratories:
Because comparisons of indirect cost rates are not very meaningful and
non-DOE contractors do not report functional support costs, the cost
rates for DOE's laboratories cannot be compared with those of the Jet
Propulsion Laboratory or Lincoln Laboratory. The Jet Propulsion
Laboratory, operated by the California Institute of Technology, is the
lead center for robotic exploration of space. Virtually all of the work
it performs is under a single National Aeronautics and Space
Administration agreement, which states that all of the laboratory's
costs are direct, according to laboratory officials.[Footnote 5]
Lincoln Laboratory, located on Hanscom Air Force Base, conducts applied
research to develop advanced technology in remote sensing, space
surveillance, missile defense, battlefield surveillance and
identification, communications, air traffic control, and biological and
chemical defense for the Department of Defense and other federal
agencies. The laboratory's indirect cost rate cannot be compared with
those of DOE laboratories without a detailed understanding of
differences in (1) contract provisions and other requirements; (2) how
contractors classify costs as direct or indirect; and (3) research
missions and activities, such as the added costs at the DOE
laboratories associated with safety requirements for handling
radioactive and other hazardous materials. Lincoln Laboratory's
indirect cost rate increased by 13.9 percent between fiscal years 2000
and 2004 because of a new enterprisewide accounting and management
reporting system and infrastructure improvements for laboratory test
facilities, according to laboratory officials.
DOE and Its Contractors Have Taken Actions to Reduce Indirect and Other
Support Costs, but Opportunities Exist for Further Reductions:
DOE and its contractors have numerous efforts under way to reduce
indirect and other support costs; however, we identified several
efforts that could be strengthened to further reduce costs. First, DOE
is including incentives in its contracts to encourage indirect cost
reductions. DOE officials stated that one of these incentives, a pilot
to award additional contract years for performance, had produced cost
savings. DOE is expanding this incentive to additional laboratories,
although it has not evaluated its effectiveness. Second, DOE generally
requires contractors to offer employee benefits that are similar in
value to those of comparable organizations, but the department has done
little to enforce this requirement. Third, DOE has begun requiring
contractors to address a backlog of maintenance projects while they
also manage current maintenance needs. Although this effort will
involve costs in the near term, it could reduce support costs in the
long term. However, only Lawrence Livermore and Sandia have programs
that have been shown to be sustainable over several years and appear to
be promising models. Finally, while DOE and some contractors have
reduced costs through process improvement programs, consolidated
procurement actions, and audits by DOE's Inspector General and DOE
contractor audit groups, opportunities exist for further cost savings
through these activities.
DOE Is Increasingly Using Contractual Incentives to Encourage Cost
Savings but Is Expanding a Key Program without Evaluating Its
Effectiveness:
Recently, NNSA has taken several actions to improve business operations
and achieve support cost savings through contractual incentives. For
example, Sandia's management and operating contract that NNSA extended
to the Sandia Corporation, a subsidiary of Lockheed Martin Corporation,
in October 2003 gives higher priority to improved performance and
greater efficiency in business operations. Specifically, 40 percent of
the contract's annual award fee in fiscal years 2004 and 2005 is based
on Sandia's performance in areas such as information technology,
procurement, human resources, and maintenance. Similarly, NNSA's
management and operating contracts for Lawrence Livermore and Los
Alamos have given greater emphasis to improved performance and greater
efficiency in business operations. For example, the Los Alamos
contract's performance measures that focused on business operations
increased from about 28 percent in fiscal year 2002 to 40 percent in
fiscal year 2005. NNSA also has added provisions to some of its
contracts to allow the laboratories to reinvest cost savings in other
activities considered to be indirect costs.[Footnote 6]
In addition, the Sandia contract initiated a pilot award-term program
under which an additional year may be awarded to the life of the
contract for each year the contractor achieves an overall outstanding
performance rating. A key performance target is finding sufficient cost
savings to be applied to unfunded projects.[Footnote 7] In fiscal year
2004, the first year of the pilot program, Lockheed Martin earned a 1-
year extension on its contract and documented $38 million in cost
savings, which it spent on agreed-upon projects, such as the following:
* $14 million for reprogramming security and safeguards to meet the new
design basis threat,
* $9.8 million for investing in computer clusters for defense projects,
* $3 million for purchasing equipment to refurbish the pulsed power
accelerator,
* $2 million for enhancing the classified network,
* $2 million for cleaning up beryllium contamination, and:
* $0.3 million for negotiating an agreement with Russia on polymer
research.
Although Sandia and NNSA officials stated that they believe the award-
term program emphasizes improved performance and cost savings better
than provisions in prior contracts, NNSA has not evaluated the nearly 2-
year-old pilot. Such an evaluation could compare the benefits of
redirecting funds for better mission uses with the costs of forgoing
recompetition of the contract and examine whether the cost savings
resulted in any negative effects on reduced work quality. The
evaluation also could determine whether award-term incentives need to
be revised in other contracts to improve their effectiveness and
sustainability, particularly since the mission and level of performance
among contractors vary. By expanding the incentive without evaluating
it, DOE does not know if it is receiving benefits commensurate with
awarding extra years to the contract term. Despite the lack of
evaluation, DOE's Office of Science extended the award-term incentive
to Lawrence Berkeley National Laboratory, and NNSA plans to extend it
to Los Alamos and the Nevada Test Site later this year when it awards
new contracts. As a result, Lawrence Berkeley's contractor, the
University of California, can potentially earn up to 15 additional
years on its recently awarded 5-year contract; the request for
proposals for the Nevada Test Site states that the contractor can
potentially earn up to 5 additional years on its 5-year contract; and
the request for proposals for Los Alamos states that the contractor can
potentially earn up to 13 additional years. (See app. I for more
information on this topic.)
DOE Has Not Always Enforced Its Requirement That Contractors' Employee
Benefits Be Comparable with Those of Similar Organizations:
To ensure that the value of each contractor's employee benefits are
comparable with its competitors and that costs are reasonable, DOE
Order 350.1 requires its management and operating contractors to
periodically benchmark the value of their employee benefit packages--
including retirement pensions, health care, death, and disability--with
those of organizations with whom the contractors compete in hiring
employees.[Footnote 8] The DOE order requires that if the value of a
contractor's benefits exceeds the average benchmarked value by more
than 5 percent, the contractor will provide DOE with a plan to adjust
the benefits so that they fall within 5 percent of the benchmarked
value. DOE must ensure that the contractor's proposed adjustments are
acceptable and reasonable. More specifically, the DOE order requires
that the contractors use a professionally recognized measure to compare
the value of their benefits with those of other organizations. The
contractors can use a nationally recognized consulting firm with
expertise in benefit value studies to perform such a study every 3
years or perform an annual employee benefit comparison survey through
the U.S. Chamber of Commerce. A benefit value study determines the
average of each benefit for 15 organizations with similar workforces.
The average value of the benefits becomes the benchmark against which
the contractor's benefits are assessed.
The benefit value studies conducted for Lawrence Livermore, Los Alamos,
and Sandia in 2004 show that the value of employee benefits for these
laboratories exceeded the benchmark by more than 5 percent in several
of the four primary categories of benefits. More importantly, the
studies showed that the overall benefits for those three laboratories
exceeded the allowable 5 percent variance for the overall benefits (see
table 2). Lawrence Livermore and Los Alamos both had benefit values
that far exceeded the benchmark and, in many categories, both
laboratories exceeded all comparators. For example, pension benefits
for both laboratories exceeded those of all 15 comparators and were
nearly twice those of the benchmarked value. Lawrence Livermore, Los
Alamos, and Sandia were highest or second highest in most benefit
categories. Sandia's defined benefit pension was second highest of all
15 comparators and exceeded the benchmarked value by 68 percent. In
contrast, the value of benefits for Idaho and Oak Ridge did not exceed
the 5 percent allowable range.
Table 2: Results of the DOE-Funded Employee Benefit Value Studies for
Each of the Five Laboratories:
Laboratory: Idaho;
Benefits exceeded benchmark by more than 5 percent: None.
Laboratory: Lawrence Livermore;
Benefits exceeded benchmark by more than 5 percent: Retirement, Health
care, Death, All benefits.
Laboratory: Los Alamos;
Benefits exceeded benchmark by more than 5 percent: Retirement, Health
care, Death, All benefits.
Laboratory: Oak Ridge;
Benefits exceeded benchmark by more than 5 percent: None.
Laboratory: Sandia;
Benefits exceeded benchmark by more than 5 percent: Retirement, Health
care, Death, Disability, All benefits.
Source: DOE.
Note: The health care and retirement values represent the benefits with
the highest average values, while the death and disability values
represent the benefits with the lowest values. All health care values
reflect both pre-and post-retirement health care values. We did not
independently verify the data used for the comparison studies.
[End of table]
DOE did not require prompt action to adjust benefits at the three
laboratories that exceeded the benchmarked value. Initially, DOE and,
later, NNSA exempted Lawrence Livermore and Los Alamos from the DOE
benchmark because the contract with the University of California, which
manages the laboratories, allowed the university to extend its own
benefits package to laboratory employees. When the DOE order was issued
in 1996, the existing contract with the university took precedence,
according to a university document. DOE did not request a benefit value
study until 2004, after it was determined that the Los Alamos and
Lawrence Livermore contracts were scheduled to be competed and DOE
became concerned about long-term liabilities for employees'
postretirement costs. DOE has no short-term liability for the pension
benefits because the pension plan is fully funded and is projected to
remain fully funded for at least the near term, according to university
officials. However, DOE's liability for long-term pension benefits for
these laboratories remains undetermined. In an effort to reduce this
liability, NNSA is requiring a stand-alone pension plan for the winning
bidder of the Los Alamos contract, which DOE plans to award at the end
of this year.
Similarly, after a benefit value study in 2001 showed that the value of
Sandia's benefits exceeded the benchmarked value, NNSA did not require
Sandia to adjust its benefits. In this case, an actuarial study showed
that NNSA had minimal risk that it would have to contribute to Sandia's
pension plan for at least 5 years. However, the amount of long-term
liability is again undetermined because the study could not reliably
determine the risk of NNSA having to contribute beyond 5 years. When a
new benefit value study was completed 3 years later, in May 2004, NNSA
required Sandia to submit a corrective action plan to adjust the
benefits. NNSA received Sandia's plan for making adjustments in June
2005, but officials are requiring modifications before approving the
plan.
Finally, while benchmarking the value of benefits is a step in the
right direction, DOE does not require contractors to benchmark the
costs of their benefits. NNSA officials stated that cost studies are
needed because the value of benefits may not be directly proportional
to their costs. For example, while value and cost are generally highly
correlated, it is possible that a contractor may negotiate high-value
benefits that have a low cost, or low-value benefits that have a high
cost. DOE has not yet finalized the revisions to DOE Order 350.1, which
includes a draft provision to require benchmarking of costs, in
addition to benefits. In commenting on this report, DOE officials
stated that, since late 2004, DOE solicitations and awards for
management and operating contracts required contractors to conduct
benefit value and cost studies. In addition, our April 2004 report (1)
noted that DOE should review postretirement costs because they have a
continuous and compounding effect as they are paid out for each year of
retirement and (2) recommended that DOE strengthen its oversight of
postretirement benefits by focusing more attention on long-term
costs.[Footnote 9]
DOE Has Begun to Focus on Deferred Maintenance, but Efforts at Some of
the Laboratories Are Not Sustainable:
For more than 2 decades, DOE orders and policies have required that
contractors' maintenance programs ensure the safe, reliable, and
efficient operation of buildings and equipment. They have also required
that these programs be adequately funded to ensure that the design
requirements of the buildings and equipment are met or exceeded for
their operating lives, and that industry standards for maintenance are
applied.[Footnote 10] Industry standards, for example, require that
maintenance budgets be developed using historical and other information
on the resources required to maintain the structure or equipment in
good repair. Industry standards and the National Academy of Sciences
have recommended that day-to-day maintenance requires continuous annual
funding of about 2 percent to 4 percent of the replacement plant
value.[Footnote 11]
Despite requirements, for many decades, DOE and its contractors have
neglected the routine maintenance of buildings and equipment--including
inspection of fire alarms, upgrades to electrical systems, and testing
of equipment critical to the nuclear weapons program. DOE and
contractor officials stated that the mission always took priority for
resource allocations. This practice has resulted in a maintenance
backlog that will cost an estimated $1.9 billion for the five
laboratories, excluding deferred maintenance for unused buildings.
Maintenance that continues to be deferred, particularly on older
structures and equipment, will contribute to an increasing growth in
deferred maintenance costs, including replacement costs for certain
equipment parts. For example, Lawrence Livermore reports that its
deferred maintenance costs continue to escalate each year because of
the higher probability of failure in the operability of aging
structures and equipment. In fiscal year 2004, Los Alamos reported that
it had the oldest structures of the three weapons laboratories, with an
average structure age of 33 years. Los Alamos also reported that it had
the highest level of deferred maintenance of the five laboratories,
accounting for about one-third, or $547 million, of the backlog for the
five laboratories.
The backlog could also jeopardize the safe, reliable, and efficient
operation of the buildings and equipment. At Los Alamos, for example,
the backlog put at risk the safety of some workers. Officials
inspecting the fire protection system in early fiscal year 2004
reported that the fire sprinklers were not properly winterized to
protect them from freezing, as required by fire codes and standards.
The inspectors reported that at least three fire sprinkler pipes had
frozen since November 2003, creating a safety concern in the event of a
fire. At Idaho, the backlog has placed reliable operation of the
Advanced Test Reactor at risk. Specifically, the deferral of
maintenance and recapitalization for several key systems--including the
waste control system and the digital monitoring system--has resulted in
the reliance on an outdated computer system for which technical support
is no longer available and replacement parts can only be found in used
parts markets. Loss of any these key systems could require Idaho to
temporarily shut down the Advanced Test Reactor, hindering test plans
and DOE's nuclear energy mission. Idaho plans to continue replacing
failing parts in the computer system until it can fund a full system
replacement.
DOE has begun to focus on deferred maintenance in an effort to reduce
the backlog and long-term costs. DOE's Defense Programs, the
predecessor to NNSA, first began to address the maintenance backlog in
fiscal year 2000. Defense Programs required the nuclear weapons
facilities to develop 10-year plans to evaluate short-and long-term
maintenance needs and develop long-term efforts to better manage the
maintenance backlog. At about the same time, the Congress began
providing funding for certain maintenance programs, such as NNSA's
Readiness in Technical Base and Facilities Program. Some DOE
laboratories also are using different types of indirect costs, such as
space charges, to help address maintenance. Additionally, in fiscal
year 2002, the Congress began funding the Facilities and Infrastructure
Recapitalization Program to reduce long-term deferred maintenance for
NNSA facilities. The program can also be used to demolish certain
structures. Demolishing or consolidating structures can help reduce
maintenance and other operating costs. Between fiscal years 2002 and
2005, the Congress provided about $1 billion for this program and, in
fiscal year 2005, NNSA requested an additional $1.7 billion for fiscal
years 2006 through 2009. When established, the program had two key
goals. First, contractors are to stabilize deferred maintenance by the
end of fiscal year 2005 so that there is no further growth in backlog.
NNSA informed the Congress that contractors have met this goal of
stabilizing deferred maintenance. The second goal is for contractors to
reduce the maintenance backlog so that the backlog for mission-critical
and nonmission-critical structures is less than 5 percent and less than
10 percent, respectively, of replacement plant value by fiscal year
2009. However, an NNSA official stated that most of NNSA's contractors
will not be able to meet this goal because the $1.7 billion budget
request for fiscal years 2006 through 2009 was reduced by $574 million.
Furthermore, in fiscal year 2003, DOE adopted NNSA's lead by addressing
maintenance in 10-year plans to better manage maintenance overall,
including deferred maintenance. As with NNSA's long-term planning
requirements, DOE Order 430.1B requires that all DOE facilities develop
10-year plans to assess, among other things, their short-term and long-
term maintenance needs. Although the order does not have specific time
lines associated with reducing deferred maintenance, DOE's headquarters
program offices are responsible for approving the 10-year plans and for
tracking the performance of the facilities against the plans. DOE's
Office of Engineering and Construction Management has general oversight
over DOE Order 430.1B, including the review of the 10-year plans and
the tracking of program office performance.
Despite all of these efforts, DOE contractors report that deferred
maintenance will continue to be a significant problem in the short term
and long term. Of the five laboratories, Lawrence Livermore has
demonstrated the most sophisticated and sustainable approach that fully
funds maintenance needs and reduces deferred maintenance over the long
term. Lawrence Livermore's plan, first implemented in 1998, relies on a
combination of funding, including two directly funded NNSA programs--
the Readiness in Technical Base and Facilities Program and the
Facilities and Infrastructure Recapitalization Program--and an indirect
cost pool established for its Maintenance Management Program. The
Maintenance Management Program collects funds ($8 per square foot) from
all users of its buildings--including NNSA and other DOE and non- DOE
programs. About 20 percent of the collected funds are spent on deferred
maintenance at the laboratory, in accordance with the program. The
program identifies the most critical needs for maintenance on the basis
of a matrix balancing "mission-essential" and "probability of failure"
criteria. In addition, the charge itself encourages more efficient use
of space and the return of unneeded space for use for other purposes or
demolition. Also, other Lawrence Livermore cost pools, such as the
Institutional General Plant Project, help fund capital improvements
that can help address maintenance by upgrading structures and
equipment. By managing the various elements of its maintenance effort,
Lawrence Livermore stopped the growth of its maintenance backlog by
fiscal year 2002. Despite the anticipated reductions in the Facilities
and Infrastructure Recapitalization Program, Lawrence Livermore
projects that it can reduce its deferred maintenance to within NNSA's
industry standards by 2011.
Sandia has an approach similar to Lawrence Livermore's, relying on a
combination of funds for addressing its maintenance and deferred
maintenance costs. Using an established methodology, a committee sets
maintenance priorities and determines how to spend funds collected from
an internal cost recovery pool. Sandia charges building users $12 per
square foot and expects to initiate increases to space charges over the
next 4 years to compensate for expected cuts in maintenance funding. As
a result, despite the anticipated reductions in the Facilities and
Infrastructure Recapitalization Program, Sandia projected in March 2005
that it would reduce its deferred maintenance to within NNSA's industry
standards by 2011.
Los Alamos officials acknowledge that they cannot achieve NNSA's goals
for reductions in deferred maintenance given the expected cuts in the
Facilities and Infrastructure Recapitalization Program in the
foreseeable future. Contractor and NNSA officials acknowledge that Los
Alamos' maintenance program is not sustainable, particularly given its
current level of funding for maintenance. Any reductions in backlog as
a result of the Facilities and Infrastructure Recapitalization Program
would reaccumulate when that funding ended. Similarly, even though Oak
Ridge provides additional support for maintenance by charging for space
used, officials report that without additional infrastructure renewal
or recapitalization funds to address aging facilities, the charge is
insufficient to fully fund its maintenance needs. Without this
additional funding, Oak Ridge reports that its maintenance backlog will
continue to grow. Finally, Idaho has passed many of its deferred
maintenance liabilities on to another contractor responsible for
cleaning up part of the laboratory site; nevertheless, Idaho reports
that without additional funding, its maintenance backlog will continue
to grow.
DOE and Some Contractors Have Reduced Support Costs through Process
Improvement Programs, Audits, and Procurement Consolidation:
Idaho, Lawrence Livermore, and Sandia have reduced support costs
through programs to improve business and other processes, while Los
Alamos and Oak Ridge do not have such programs. In addition, DOE and
some of the laboratories we reviewed have some efforts under way to
consolidate procurement actions. Finally, DOE's Inspector General and
contractors' internal audit groups have contributed to some cost
savings by auditing support functions.
Three Laboratories Have Reduced Costs through Process Improvement
Programs, While Two Laboratories Do Not Have Such Programs:
Process improvement is the practice of taking an analytical look at
different steps that go into developing a product or delivering a
service and assessing how those processes could be conducted better. In
a process improvement initiative, participants may define the process
and metrics, measure performance, analyze root causes of problems,
improve areas of low performance, and develop controls for the process.
Typically, the process improvement initiative involves iterative cycles
of identification and improvement, fueled by employee participation in
identifying problem areas and recommending steps to improve them. It is
generally recognized that process improvement is a good business
practice. Process improvement programs can increase product or service
quality, while decreasing costs. Public and private organizations have
reported significant returns on investment through process improvement
programs.
Several DOE laboratories and production facilities, including Idaho,
Sandia, and Lawrence Livermore, have used process improvement methods,
such as Six Sigma and Lean Six Sigma, to reduce costs.[Footnote 12] Six
Sigma and Lean Six Sigma are rigorous and disciplined methodologies
that use data and statistical analyses to measure and improve the
performance of a company's operations by identifying and eliminating
defects in manufacturing and service-related processes. Idaho used Six
Sigma to reduce the average cost of 16 Safety Assessment Reports for a
total savings of $907,000 from fiscal years 2002 through 2003. Sandia
used Lean Six Sigma to streamline its accounts payable purchase order
process, potentially leading to savings of more than $1 million over a
5-year period. Finally, Lawrence Livermore used Six Sigma and other
methods to improve processes in the areas of safety, security, resource
management, and property management. For example, the laboratory
reduced security staff overtime by increasing the workday to 12 hours
and reported a $2.3 million annual savings. The laboratory also
standardized the hours of the perimeter security gates and closure of
redundant gates in an effort to save $300,000 annually. Lawrence
Livermore plans to train 400 managers by the fall of 2006 in a new
process improvement method based on a combination of Lean Six Sigma and
a method used at the United Kingdom's Atomic Weapons Establishment,
which provides warheads for nuclear deterrence.
Neither Oak Ridge nor Los Alamos have process improvement programs,
although some DOE and laboratory officials agreed that such programs
can help reduce costs. When laboratories do not have some type of
process improvement program, DOE has little assurance that managers are
identifying and addressing inefficient or ineffective processes.
Many of the DOE Inspector General's Reports Have Reviewed Support
Activities:
Many of the DOE Inspector General's reports have examined support
activities at DOE laboratories and other facilities, including
security, procurement, property management, information resources,
financial management, and financial controls. The Inspector General has
found opportunities for reducing indirect and other support costs. For
example, in 2003, the Inspector General's audit of central office
expenses for the Thomas Jefferson National Accelerator Facility
questioned $4.6 million in costs claimed by and paid to the contractor
for central office expenses from November 1999 to September 2002. These
questioned expenses included costs that were not allowable, such as
alcoholic beverages, and costs that were not adequately supported or
documented. The audit resulted in $3.5 million in savings to DOE. In
2003, an audit of Los Alamos reported support and other costs of $14.6
million that were potentially unallowable, including meals, excessive
travel costs, and an internal audit function that did not meet DOE
requirements. DOE officials are in the process of determining
allowability of the questioned amount. In addition to the Inspector
General audits, contractors' internal auditors annually perform an
audit of the allowability of costs as claimed by contractors.[Footnote
13] This audit addresses both indirect and direct costs, identifying
whether or not costs are allowable under the terms of the contract. For
example, one such audit, conducted at Sandia in fiscal year 2003,
projected $112,000 in unallowable costs--DOE is in the process of
determining the precise amount.
DOE Has Consolidated Some Procurement Actions:
DOE and its management and operating contractors have reduced support
and other costs by consolidating their procurements of computer
equipment, office supplies, and other bulk items into single contracts
that result in volume discounts and the need for fewer purchasing
resources. In particular, DOE established an Integrated Contractor
Procurement Team that pursues buying opportunities and has negotiated
over 40 purchasing agreements with vendors to reduce procurement staff
time and obtain favorable prices, according to a DOE official. The
team, composed of contractor purchasing agents, surveys sites to
determine what contractors are paying for a product and whether they
can negotiate a better price. A contractor that wants to purchase goods
(e.g., paper) can review a list of agreements and supplier contact
information on the Integrated Contractor Procurement Team's Web site
and use its Basic Order Agreement. This saves contractors and suppliers
time because they do not need to renegotiate all the terms of the
contract. Contractors do not track savings resulting from the use of
Integrated Contractor Procurement Team, but they have collected some
examples of savings that total about $12 million to $15 million,
annually.
Other efforts to save time and money through consolidation of
procurement actions include the following:
* NNSA has required Lawrence Livermore, Los Alamos, and Sandia to begin
analyzing their spending using similar software so that opportunities
for consolidated purchases among the three laboratories can be
identified.
* Lawrence Livermore has hired a specialist who is focused full-time on
analyzing the laboratories' spending patterns and identifying
opportunities for consolidation. As a result of opportunities being
identified, the procurement office expects to reduce the number of
subcontracts by 10 percent, saving procurement staff time. The
laboratory also has developed 13 Electronic Ordering System agreements
through which suppliers provide electronic catalogs with over 2 million
commercial items (e.g., computers, electrical and plumbing supplies,
and chemicals) that laboratory employees can purchase online. The
purchases are automatically routed through an approval system.
* Oak Ridge consolidated its new radio system, which is used by
security and maintenance staff, with other DOE facilities in the area,
reportedly saving $900,000 on purchase prices plus $475,000 in annual
costs.
Laboratory officials told us that opportunities exist for further cost
savings through reduced staff time and better prices by consolidating
procurements with each contractor's parent organization, other DOE
facilities, or other federal agencies' facilities in the same region.
Idaho officials cited the potential for reducing costs for using
consolidated procurements with nearby military bases and other
facilities. An NNSA procurement official noted that laboratories could
save through increased use of Integrated Contractor Procurement Team
agreements, noting that some procurement officials may not be aware of
available opportunities.
Conclusions:
In an era of federal budget constraints, it is crucial to efficiently
manage support costs at DOE laboratories, thereby maximizing funds
available for laboratory missions. DOE and its contractors have taken
steps to reduce support costs, but additional opportunities exist. To
help decision makers analyze support costs across the laboratories,
several years ago DOE began to require laboratories to report
functional support costs. However, peer reviews have revealed some
problems with these data and challenges remain in comparing costs, in
part because of ambiguity in the definitions for some categories of
support costs. To encourage contractors to reduce support costs, DOE
also piloted a program to award contract years for performance
improvement and cost savings. However, by expanding the pilot incentive
program without evaluating it, DOE does not know if it is receiving
benefits commensurate with awarding extra years to the contract term.
In another effort to save money, DOE developed requirements to ensure
that contractors' employee benefits are comparable with those of
similar organizations with whom they compete for critically skilled
staff. However, DOE has not always required its contractors to reduce
employee benefits that substantially exceed the value of their
competitors' benefits and has not required contractors to benchmark the
costs of their benefits, potentially adding billions of dollars in long-
term costs. Furthermore, while DOE has begun to address the $1.9
billion backlog of deferred maintenance to reduce long-term costs and
improve the safe, efficient, and reliable operation of equipment and
buildings, only Lawrence Livermore and Sandia have demonstrated
sustainable approaches that successfully reduced their backlogs.
Lastly, process improvement programs are generally considered a good
business practice, and three laboratories have reduced costs through
their own programs. DOE, however, does not require laboratories to have
such programs, and some laboratories have not instituted one. Overall,
while DOE has made progress, without additional attention to these
initiatives, the department may miss the opportunity to produce
significant savings.
Recommendations for Executive Action:
To improve the quality and comparability of DOE facilities' support
cost data, we recommend that the Secretary of Energy direct the CFO to
work with the Financial Management Systems Improvement Council to
clarify definitions of functional support cost categories.
To determine whether the department receives benefits commensurate with
awarding 1 or more extra years to the contract term, we recommend that
the Secretary of Energy direct NNSA to evaluate the effectiveness of
its pilot award-term program at Sandia National Laboratories,
particularly the nature and extent of work quality improvements, prior
to extending the program to other laboratories.
To provide competitive but economical employee benefits, we recommend
that the Secretary of Energy complete the revision of DOE Order 350.1
and ensure that the order (1) extends the requirement to benchmark the
value of employee benefits to all contractors; (2) requires prompt
corrective action if the value of benefits exceeds the allowable range;
and (3) extends the benchmarking requirements to include the costs, as
well as the values, of the benefits.
To reduce long-term maintenance costs at contractor-operated
facilities, we recommend that the Secretary of Energy develop a long-
term sustainable approach that meets day-to-day maintenance
requirements, reduces the maintenance backlog, and minimizes its
reaccumulation.
To facilitate the further reduction of support costs, we recommend that
the Secretary of Energy require that each DOE management and operating
contractor implement a process improvement program that routinely
assesses the efficiency and effectiveness of business practices and
other operations.
Agency Comments:
We provided DOE with a draft of this report for its review and comment.
In written comments, DOE generally concurred with our recommendations.
(See app. II.) DOE also provided a number of technical comments, which
we incorporated in this report as appropriate.
Scope and Methodology:
To examine indirect cost-rate trends at each of the five largest DOE
laboratories, we analyzed each laboratory's indirect cost-rate data for
fiscal years 2000 through 2004. Specifically, we interviewed laboratory
financial officials and analyzed documents to determine how each
laboratory calculated its overall indirect costs rate by (1)
classifying costs as direct or indirect and (2) collecting indirect
costs into pools and distributing them among other cost pools or
directly to program sponsors. Furthermore, because DOE and its
management and operating contractors use functional support cost data
to help assess certain activities, we analyzed these rates for the five
laboratories for fiscal years 2000 through 2004, along with the results
of peer reviews performed at each laboratory.
We surveyed laboratory financial officials on the reliability of the
indirect and functional support cost data, covering issues such as data
entry access, quality control procedures, and the accuracy and
completeness of these data. Follow-up questions were added whenever
necessary. In addition, we reviewed all data provided by the
laboratories, investigated instances where we had questions regarding
issues such as categories or amounts, and made corrections as needed.
On the basis of this work, we determined that the financial data
provided were sufficiently reliable for the purposes of our report. We
presented percentage changes in the overall indirect cost rates for
fiscal years 2000 through 2004 that the five laboratories reported.
However, because of limitations discussed in this report, analyses of
increases or decreases in these rates mean little without a careful
analysis of how a contractor classifies costs, and one contractor's
rates cannot be compared with those of others. Moreover, we analyzed
changes in classification of costs or changes in mission over time to
determine if these data were comparable over several years at a single
laboratory. We noted in our report when we found changes in
classification that affected the comparability of data at a single
location over time.
To assess the efforts of DOE and its laboratory contractors to reduce
support costs and identify additional opportunities for savings, we
visited each of the five laboratories to interview senior managers and
obtain supporting documentation, interviewed DOE officials, and
examined prior GAO and DOE Inspector General reports. In the course of
this work, we identified opportunities for further potential cost
savings. We then interviewed cognizant laboratory and DOE officials
about actions taken to address each opportunity and reviewed supporting
documentation. Specifically, to review DOE's contract provisions, we
interviewed DOE contracting officers and obtained information about
recent contractual provisions that emphasized potential cost savings or
improved efficiency. To address DOE's liabilities related to employee
benefits, we analyzed benefit value studies for each of the
laboratories and compared the results of our analysis with the
department's requirements. We also interviewed DOE, NNSA, and
contractor officials to clarify the results of the studies and to
provide us with documentation on proposed resolutions, as appropriate.
It was not our intent to verify, nor would we have been able to
independently verify, the accuracy of actuarial calculations,
assumptions, or data used in the comparison studies due to the
proprietary nature of benefits that consulting firm databases used to
conduct the studies.
To address the maintenance backlog, we analyzed data from DOE's Office
of Engineering and Construction Management, which collects information
on deferred maintenance. We also analyzed each laboratory's 10-year
plan and related documents and compared the results of our analysis
with NNSA's and the department's requirements. We spoke with cognizant
officials at DOE headquarters and its site offices and with laboratory
managers to verify the results of our analysis and to determine the
actions being taken to address the backlog. To examine the
laboratories' use of process improvement programs, we reviewed examples
that the three laboratories provided of improved effectiveness and of
reduced costs for their business operations and interviewed senior
managers at the other two laboratories regarding what they had done to
improve business operations.
As agreed with your offices, unless you publicly announce the contents
of this report, we plan no further distribution of it until 30 days
from the date of this letter. At that time, we will send copies to the
Secretary of Energy; the Director, Office of Management and Budget; and
other interested parties. We will also make copies available to others
on request. In addition, the report will be available at no charge on
the GAO Web site at [Hyperlink, http://www.gao.gov].
If you or your staffs have any questions about the report, please
contact me at (202) 512-3841. Contact points for our Offices of
Congressional Relations and Public Affairs may be found on the last
page of this report. GAO staff who made key contributions to this
report are listed in appendix III.
Signed by:
Jim Wells:
Director, Natural Resources and Environment:
[End of section]
Appendixes:
Appendix I: Award-Term Provisions at Four DOE Sites:
The Department of Energy (DOE) introduced award-term incentives as a
pilot program to Sandia in fiscal year 2004, and then expanded the use
of the incentives to the Lawrence Berkeley contract and to the final
request for proposals for Los Alamos and the Nevada Test Site, as shown
in table 3. The language in the final request for proposals for Los
Alamos, if placed in the contract, would award additional years to the
contract term if the contractor (1) achieves a certain level of
performance to be determined by the DOE contracting officer and (2)
meets other conditions, such as finding cost savings and using these
savings to adequately perform approved work. As shown in table 3, Los
Alamos can earn 13 additional years on its 7-year contract.
Table 3: Award-Term Provisions for Four DOE Facilities:
Provisions: Duration of contract (years);
Final request for proposals: Los Alamos: 7;
Final request for proposals: Nevada Test Site: 5;
Existing contracts: Lawrence Berkeley: 5;
Existing contracts: Sandia: 5.
Provisions: Total number of years that can be added to contract;
Final request for proposals: Los Alamos: 13;
Final request for proposals: Nevada Test Site: 5;
Existing contracts: Lawrence Berkeley: 15;
Existing contracts: Sandia: 5.
Provisions: Possible total number of years of contract with award term;
Final request for proposals: Los Alamos: 20;
Final request for proposals: Nevada Test Site: 10;
Existing contracts: Lawrence Berkeley: 20;
Existing contracts: Sandia: 10.
Provisions: Level of performance needed to be assessed at to earn award
term;
Final request for proposals: Los Alamos: Annual determination by NNSA;
Final request for proposals: Nevada Test Site: Based on incentive fee
earned;
Existing contracts: Lawrence Berkeley: First 3 years: satisfactory;
Subsequent years: Outstanding;
Existing contracts: Sandia: Outstanding each year.
Provisions: Requires cost savings to earn award term;
Final request for proposals: Los Alamos: Yes;
Final request for proposals: Nevada Test Site: No;
Existing contracts: Lawrence Berkeley: No;
Existing contracts: Sandia: Yes.
Source: DOE.
[End of table]
Key differences between the Los Alamos final request for proposals and
the Sandia contract are as follows:
* The level of performance required to receive additional contract
years can be determined by the contracting officer for Los Alamos, but
Sandia's contract requires outstanding performance. NNSA officials
stated that the recent history of performance at Los Alamos may take
several years to reverse, and the contractor may not be able to achieve
overall "outstanding" ratings in the initial years of the contract. The
officials also noted that the flexibility may allow the contracting
officer to focus on certain areas for improvement, such as business
operations.
* The contract term for Los Alamos could be 20 years, rather than the
10 years allotted to Sandia. The 20-year term for Los Alamos requires a
deviation from DOE Acquisition Regulation 970.1706-1, which limits DOE
contracts to 10 years.
[End of section]
Appendix II: Comments from the Department of Energy:
Department of Energy:
Washington, DC 20585:
August 12, 2005:
Mr. Jim Wells:
Director, Natural Resources and Environment:
Government Accountability Office:
Washington, DC 20548:
Mr. Wells:
Thank you for the opportunity to comment on draft report GAO-05-897,
Department of Energy: Additional Opportunities Exist for Reducing
Laboratory Contractors' Support Costs. The Department of Energy's
official comments are enclosed for your consideration. While we
generally concur with the recommendations presented in the report, we
believe incorporation of the referenced comments is critical to ensure
the accuracy and clarity of the results. If you have any questions,
please contact John Newell, Director, Office of Program Liaison and
Financial Analysis, at 202-586-8921.
Sincerely,
Signed by:
Susan J. Grant:
Chief Financial Officer:
Enclosure:
[End of section]
Appendix III: GAO Contact and Staff Acknowledgments:
GAO Contact:
Jim Wells (202) 512-3841:
Staff Acknowledgments:
In addition to the contact named above, Richard Cheston, Beverly
Peterson, Robert Sanchez, James Espinoza, and Cynthia Norris made key
contributions to this report. Also contributing to this report were
Chuck Bausell, Virginia Chanley, Nancy Crothers, Alison O'Neill, and
Omari Norman.
(360536):
FOOTNOTES
[1] See the Cost Accounting Standards (48 C.F.R. Part 9904) for
detailed cost accounting requirements.
[2] Prior to February 2005, Idaho National Laboratory was known as
Idaho National Engineering and Environmental Laboratory. DOE's Office
of Nuclear Energy is responsible for the laboratory, while DOE's Office
of Environmental Management is responsible for the environmental
cleanup of the site.
[3] Because the Congress began providing funding specifically for
security in fiscal year 2001, we asked the laboratories to exclude
security from their prior indirect rates to provide consistent trend
data.
[4] Functional support costs accounted for about 40 percent of the 28
contractors' fiscal year 2004 operating costs of $17.4 billion.
[5] The Jet Propulsion Laboratory tracks "distributive costs," which
are similar to, but not comparable with, the DOE laboratories' indirect
costs. These distributive costs increased by 9.5 percent between fiscal
years 2000 and 2004.
[6] A January 2005 NNSA policy letter expanded the use of reinvested
savings to other approved areas. The final request for proposals for
the contract at Los Alamos allows a percentage of savings in indirect
costs to be applied to one of these approved areas--contractor-directed
research and development at universities and small technology companies
in northern New Mexico. Until recently, DOE and NNSA used a contract
provision that rewarded contractors for cost savings by allowing them
to keep up to 25 percent of documented cost savings that DOE or NNSA
officials had reviewed and approved. However, NNSA officials stated
that this provision was not effective because the claimed cost savings
could not be verified.
[7] Under the contract, Lockheed Martin shall apply cost efficiencies
achieved during a given fiscal year only to unfunded priority direct
mission work that NNSA and Lockheed Martin had agreed upon at the
beginning of the fiscal year, provided that this work is within the
same appropriation and budget and reporting category, unless NNSA
approves a formal reprogramming action.
[8] The value of the benefit packages varies by laboratory, and the
potential liability for DOE may be substantial. For example, DOE
estimates that, for the five laboratories, its long-term liabilities
for postretirement medical and pension benefits are at least $2.9
billion.
[9] GAO, Department of Energy: Certain Postretirement Benefits for
Contractor Employees Are Unfunded and Program Oversight Could Be
Improved, GAO-04-539 (Washington, D.C.: Apr. 15, 2004).
[10] For example, DOE Order 4330.4B, effective in 1994, specified that
sufficient resources should be budgeted to ensure the reliability,
safety, and operability of structures, systems, and components, and
that maintenance programs should meet equivalent industry guidelines.
[11] Building Research Board, Committing to the Cost of Ownership:
Maintenance and Repair of Public Buildings (Washington, D.C.: June
1990). NNSA determines replacement plant value by a formula that
estimates the value of replacing structures and equipment at each site.
[12] Other commonly used process improvement methods include Total
Quality Management and ISO 9000.
[13] The Inspector General, the cognizant auditor for DOE's management
and operating contractors, supplements its audit program with each
contractor's internal audit activities.
GAO's Mission:
The Government Accountability Office, the investigative arm of
Congress, exists to support Congress in meeting its constitutional
responsibilities and to help improve the performance and accountability
of the federal government for the American people. GAO examines the use
of public funds; evaluates federal programs and policies; and provides
analyses, recommendations, and other assistance to help Congress make
informed oversight, policy, and funding decisions. GAO's commitment to
good government is reflected in its core values of accountability,
integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains
abstracts and full-text files of current reports and testimony and an
expanding archive of older products. The Web site features a search
engine to help you locate documents using key words and phrases. You
can print these documents in their entirety, including charts and other
graphics.
Each day, GAO issues a list of newly released reports, testimony, and
correspondence. GAO posts this list, known as "Today's Reports," on its
Web site daily. The list contains links to the full-text document
files. To have GAO e-mail this list to you every afternoon, go to
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order
GAO Products" heading.
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office
441 G Street NW, Room LM
Washington, D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm
E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Public Affairs:
Jeff Nelligan, managing director,
NelliganJ@gao.gov
(202) 512-4800
U.S. Government Accountability Office,
441 G Street NW, Room 7149
Washington, D.C. 20548: