Nuclear Weapons
Views on NNSA's Proposal to Transform the Nuclear Weapons Complex
Gao ID: GAO-08-1032T July 17, 2008
Over the past several years, a serious effort has begun to comprehensively reevaluate how the United States maintains its nuclear deterrent and what the nation's approach should be for transforming its aging nuclear weapons complex. The National Nuclear Security Administration (NNSA), a separately organized agency within the Department of Energy (DOE), is responsible for overseeing this weapons complex, which comprises three nuclear weapons design laboratories, four production plants, and the Nevada Test Site. In December 2007, NNSA issued a draft report on potential environmental impacts of alternative actions to transform the nuclear weapons complex, which NNSA refers to as Complex Transformation. NNSA's preferred action is to establish a number of "distributed centers of excellence" at sites within the existing nuclear weapons complex, including the Los Alamos National Laboratory for plutonium capabilities, the Y-12 Plant for uranium capabilities, and the Pantex Plant for weapons assembly, disassembly, and high explosives manufacturing. NNSA would continue to operate these facilities to maintain and refurbish the existing nuclear weapons stockpile as it makes the transition to a smaller, more responsive infrastructure. GAO was asked to discuss NNSA's Complex Transformation proposal. This testimony is based on previous GAO work.
Transforming the nuclear weapons complex will be a daunting task. In April 2006 testimony before the Subcommittee on Energy and Water Development, House Committee on Appropriations, GAO identified four actions that, in its view, were critical to successfully achieving the transformation of the complex. On the basis of completed and ongoing GAO work on NNSA's management of the nuclear weapons complex, GAO remains concerned about NNSA's and the Department of Defense's (DOD) ability to carefully and fully implement these four actions. For this reason, GAO believes that the Congress must remain vigilant in its oversight of Complex Transformation. Specifically, NNSA and DOD have not established clear, long-term requirements for the nuclear weapons stockpile. While NNSA and DOD have considered a variety of scenarios for the future composition of the nuclear weapons stockpile, no requirements have been issued. It is GAO's view that NNSA will not be able to develop accurate cost estimates or plans for Complex Transformation until stockpile requirements are known. Further, recent GAO work found that the absence of stockpile requirements is affecting NNSA's plans for manufacturing a critical nuclear weapon component. NNSA has had difficulty developing realistic cost estimates for large, complex projects. In September 2007, a contractor provided NNSA with a range of cost estimates for over 10 different Complex Transformation alternatives. However, the contractor stated that (1) its analysis was based on rough order-of-magnitude estimates and (2) NNSA should not use its cost estimates to predict budget-level project costs. In addition, in March 2007 GAO reported that 8 of 12 major construction projects being managed by DOE and NNSA had exceeded their initial cost estimates. NNSA will need to develop a transformation plan with clear, realistic milestones. GAO expects that once NNSA decides the path forward for Complex Transformation later this year, NNSA will put forward such a plan. However, GAO has repeatedly documented problems with NNSA's ability to implement its plans. For example, in February 2006 GAO reported problems with the planning documents that NNSA was using to manage the implementation of its new approach for assessing and certifying the safety and reliability of the nuclear stockpile. Successful transformation requires strong leadership. In 2006, NNSA created an Office of Transformation to oversee its Complex Transformation activities. However, GAO is concerned that the Office of Transformation may not have sufficient authority to set transformation priorities for all of NNSA, specifically as they affect nuclear nonproliferation programs.
GAO-08-1032T, Nuclear Weapons: Views on NNSA's Proposal to Transform the Nuclear Weapons Complex
This is the accessible text file for GAO report number GAO-08-1032T
entitled 'Nuclear Weapons: Views on NNSA's Proposal to Transform the
Nuclear Weapons Complex' which was released on July 17, 2008.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the Subcommittee on Strategic Forces, Committee on Armed
Services, House of Representatives:
United States Government Accountability Office:
GAO:
For Release on Delivery:
Expected at 10:00 a.m. EDT:
Thursday, July 17, 2008:
Nuclear Weapons:
Views on NNSA's Proposal to Transform the Nuclear Weapons Complex:
Statement of Gene Aloise, Director:
Natural Resources and Environment:
GAO-08-1032T:
GAO Highlights:
Highlights of GAO-08-1032T, a testimony before the Subcommittee on
Strategic Forces, Committee on Armed Services, House of
Representatives.
Why GAO Did This Study:
Over the past several years, a serious effort has begun to
comprehensively reevaluate how the United States maintains its nuclear
deterrent and what the nation‘s approach should be for transforming its
aging nuclear weapons complex. The National Nuclear Security
Administration (NNSA), a separately organized agency within the
Department of Energy (DOE), is responsible for overseeing this weapons
complex, which comprises three nuclear weapons design laboratories,
four production plants, and the Nevada Test Site.
In December 2007, NNSA issued a draft report on potential environmental
impacts of alternative actions to transform the nuclear weapons
complex, which NNSA refers to as Complex Transformation. NNSA‘s
preferred action is to establish a number of ’distributed centers of
excellence“ at sites within the existing nuclear weapons complex,
including the Los Alamos National Laboratory for plutonium
capabilities, the Y-12 Plant for uranium capabilities, and the Pantex
Plant for weapons assembly, disassembly, and high explosives
manufacturing. NNSA would continue to operate these facilities to
maintain and refurbish the existing nuclear weapons stockpile as it
makes the transition to a smaller, more responsive infrastructure.
GAO was asked to discuss NNSA‘s Complex Transformation proposal. This
testimony is based on previous GAO work.
What GAO Found:
Transforming the nuclear weapons complex will be a daunting task. In
April 2006 testimony before the Subcommittee on Energy and Water
Development, House Committee on Appropriations, GAO identified four
actions that, in its view, were critical to successfully achieving the
transformation of the complex. On the basis of completed and ongoing
GAO work on NNSA‘s management of the nuclear weapons complex, GAO
remains concerned about NNSA‘s and the Department of Defense‘s (DOD)
ability to carefully and fully implement these four actions. For this
reason, GAO believes that the Congress must remain vigilant in its
oversight of Complex Transformation. Specifically:
* NNSA and DOD have not established clear, long-term requirements for
the nuclear weapons stockpile. While NNSA and DOD have considered a
variety of scenarios for the future composition of the nuclear weapons
stockpile, no requirements have been issued. It is GAO‘s view that NNSA
will not be able to develop accurate cost estimates or plans for
Complex Transformation until stockpile requirements are known. Further,
recent GAO work found that the absence of stockpile requirements is
affecting NNSA‘s plans for manufacturing a critical nuclear weapon
component.
* NNSA has had difficulty developing realistic cost estimates for
large, complex projects. In September 2007, a contractor provided NNSA
with a range of cost estimates for over 10 different Complex
Transformation alternatives. However, the contractor stated that (1)
its analysis was based on rough order-of-magnitude estimates and (2)
NNSA should not use its cost estimates to predict budget-level project
costs. In addition, in March 2007 GAO reported that 8 of 12 major
construction projects being managed by DOE and NNSA had exceeded their
initial cost estimates.
* NNSA will need to develop a transformation plan with clear, realistic
milestones. GAO expects that once NNSA decides the path forward for
Complex Transformation later this year, NNSA will put forward such a
plan. However, GAO has repeatedly documented problems with NNSA‘s
ability to implement its plans. For example, in February 2006 GAO
reported problems with the planning documents that NNSA was using to
manage the implementation of its new approach for assessing and
certifying the safety and reliability of the nuclear stockpile.
* Successful transformation requires strong leadership. In 2006, NNSA
created an Office of Transformation to oversee its Complex
Transformation activities. However, GAO is concerned that the Office of
Transformation may not have sufficient authority to set transformation
priorities for all of NNSA, specifically as they affect nuclear
nonproliferation programs.
To view the full product, including the scope and methodology, click on
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-1032T]. For more
information, contact Gene Aloise at (202) 512-3841 or aloisee@gao.gov.
[End of section]
Madam Chairman and Members of the Subcommittee:
We are pleased to be here today to provide our observations on the
National Nuclear Security Administration's (NNSA) proposal, known as
Complex Transformation, to modernize the nuclear weapons complex. As
you know, NNSA, a separately organized agency within the Department of
Energy (DOE), is responsible for conducting nuclear weapon and
nonproliferation-related national security activities in research and
development laboratories, production plants, and other facilities.
[Footnote 1] With the moratorium on underground nuclear testing that
began in 1992 and the subsequent creation of the Stockpile Stewardship
Program, the mission of the nuclear weapons complex changed from
"designing, building, and testing" successive generations of weapons to
extending the life of the existing nuclear weapons stockpile through
"scientific study, computer simulation, and refurbishment." To carry
out its weapons activities, NNSA received about $6.3 billion for fiscal
year 2008 and has requested about $6.6 billion for fiscal year 2009.
Between fiscal years 2010 and 2013, NNSA is proposing to spend almost
$29 billion for these programs.
Over the past decade, NNSA has invested billions of dollars in
sustaining the Cold War-era stockpile and upgrading the three nuclear
weapons design laboratories with new, state-of-the-art experimental and
computing facilities. In contrast, the production infrastructure of the
nuclear weapons complex is aging and increasingly outdated. The 2001
Nuclear Posture Review found that the nuclear weapons manufacturing
infrastructure had atrophied and needed to be repaired[Footnote 2].
NNSA estimates that it will cost $2.4 billion to reduce the backlog of
deferred maintenance at these facilities to an appropriate level
consistent with industry best practices. The 2001 Nuclear Posture
Review also called for the development of a "responsive infrastructure"
that would support a smaller nuclear deterrent. The United States
subsequently committed to stockpile reductions in the Moscow Treaty
with Russia, which was ratified in 2003.
NNSA's Complex Transformation effort seeks to address these issues by
transforming to a smaller, more responsive infrastructure--one that
will ultimately support a smaller nuclear weapons stockpile--while
continuing to maintain and refurbish the existing nuclear weapons
stockpile in the interim. In recent years, NNSA and the Department of
Defense (DOD) have advocated replacing the existing stockpile with one
composed of reliable replacement warheads (RRW), which could
potentially be easier to manufacture, maintain, and certify without the
need for underground nuclear tests. They believe the RRW program would
help transform the complex. In addition, in January 2008 the Congress
established the Congressional Commission on the Strategic Posture of
the United States, which must conduct a review of nuclear weapons
policies and requirements.[Footnote 3] NNSA and DOD must cooperate with
the Commission as it conducts its review.[Footnote 4]
In December 2007, NNSA issued a draft report on the potential
environmental impacts of alternative Complex Transformation actions.
[Footnote 5] NNSA's preferred action is to establish a number of
"distributed centers of excellence" at sites within the existing
nuclear weapons complex.[Footnote 6] The individual centers of
excellence proposed include the Los Alamos National Laboratory (LANL)
for plutonium capabilities, the Y-12 Plant for uranium capabilities,
and the Pantex Plant for weapons assembly and disassembly as well as
for high explosives manufacturing. In addition, NNSA's preferred action
includes the consolidation of significant quantities of special nuclear
material. Implementation of the preferred action is supported by two
major construction projects: (1) the Chemistry and Metallurgy Research
Replacement Facility at LANL, which would provide upgraded analytical
chemistry capabilities to support manufacturing of "pits"--a key
nuclear weapons component that contains plutonium; and (2) the Uranium
Processing Facility at Y-12, which would provide upgraded capabilities
to support manufacturing and processing of weapons components
containing uranium. The total costs of these two projects are currently
estimated to be as high as $5.5 billion.
Our testimony discusses our concerns with NNSA's Complex Transformation
proposal and is based on completed and ongoing GAO work. To carry out
our objective, we relied on previous GAO work, including our April 2006
testimony before the Subcommittee on Energy and Water Development,
Committee on Appropriations, House of Representatives;[Footnote 7] a
May 2008 report on nuclear weapon pit manufacturing;[Footnote 8] and
our March 2007 report on DOE's management of major construction
projects.[Footnote 9] We conducted the performance audit work that
supports this statement in accordance with generally accepted
government auditing standards. Those standards require that we plan and
perform the audit to obtain sufficient, appropriate evidence to produce
a reasonable basis for our findings and conclusions based on our audit
objectives. We believe that the evidence obtained provides a reasonable
basis for our statements today.
In summary:
Transforming the nuclear weapons complex will be a daunting task. The
facilities that maintain and refurbish the legacy nuclear weapons
stockpile must remain operational during the transition to a smaller,
more responsive infrastructure while minimizing the potential safety,
security, and environmental impacts of relocating and constructing this
infrastructure. In our April 2006 testimony, we identified four actions
that, in our view, are critical to successfully achieving the
transformation of the complex. We continue to believe these actions
must be addressed. Specifically:
* NNSA and DOD will need to establish clear, long-term requirements for
the stockpile by determining the types and quantities of nuclear
weapons needed;
* After stockpile requirements are developed, NNSA will need to provide
accurate estimates of the costs of transformation;
* NNSA will need to develop and implement a plan with clear milestones
for measuring progress; and:
* NNSA's Office of Transformation must have the authority to make and
enforce its decisions on transformation and be held accountable by the
Congress for achieving timely and cost-effective results.
On the basis of our review of recent and ongoing GAO work on NNSA's
management of the nuclear weapons complex, we remain concerned about
NNSA's and DOD's ability to carefully and fully implement these four
actions. For this reason, we believe that the Congress must remain
vigilant in its oversight of Complex Transformation.
NNSA and DOD Have Not Established Clear, Long-Term Requirements for the
Nuclear Weapons Stockpile:
The United States' nuclear weapons stockpile comprises nine nuclear
weapons types, all of which were designed during the Cold War. Two of
these systems--the B61 and the W76--are currently being refurbished to
extend their useful lives for up to 30 years through NNSA's Life
Extension Program.[Footnote 10] In May 2008, we reported that, over the
past few years, NNSA and DOD have considered a variety of scenarios for
the future composition of the nuclear stockpile that would be based on
different stockpile sizes and the degree to which the stockpile would
incorporate new RRW designs.[Footnote 11] For example, NNSA and DOD
have considered how large the stockpile needs to be in order to
maintain a sufficiently robust and responsive manufacturing
infrastructure to respond to future global geopolitical events. In
addition, NNSA and DOD have considered the number of warheads that will
need to be either refurbished or replaced in the coming decades.
However, NNSA and DOD have not issued requirements defining the size
and composition of the future stockpile.[Footnote 12]
We discussed one effect of this lack of clear stockpile requirements in
our May 2008 report on plutonium pit manufacturing. Specifically, we
found that in October 2006, NNSA proposed building a new, consolidated
plutonium center at an existing DOE site that would be able to
manufacture pits at a production capacity of 125 pits per year.
However, by December 2007, NNSA stated that instead of building a new,
consolidated plutonium center, its preferred action was to upgrade the
existing pit production building at LANL to produce up to 80 pits per
year.[Footnote 13] Although DOD officials agreed to support NNSA's
plan, these officials also stated that future changes to stockpile
size, military requirements, and risk factors may ultimately lead to a
revised, larger rate of production. This uncertainty has delayed NNSA
in issuing final plans for its future pit manufacturing capability.
NNSA Has Had Difficulty Developing Realistic Cost Estimates for Large,
Complex Projects:
Once a decision is made about the size and composition of the
stockpile, NNSA should develop accurate estimates of the costs of
transforming the nuclear weapons complex. In September 2007, a
contractor provided NNSA with a range of cost estimates for over 10
different Complex Transformation alternatives.[Footnote 14] For
example, the contractor estimated that the cost of NNSA's preferred
action would be approximately $79 billion over the period 2007 through
2060.[Footnote 15] This option was also determined to be the least
expensive. In contrast, the contractor's estimate for a consolidated
nuclear production center--another alternative that would consolidate
plutonium, uranium, and weapons assembly and disassembly at one site--
totaled $80 billion over the same period.[Footnote 16] Although these
estimates differ by only $1 billion over 53 years, they are based on
significantly different assumptions. Specifically, NNSA's preferred
action assumes a manufacturing capacity of up to 80 pits per year, and
the alternative for a consolidated nuclear production center assumes a
capacity of 125 pits per year. In addition, the contractor cautioned
that because its cost analysis was not based on any specific conceptual
designs for facilities such as the consolidated nuclear production
center, it had not developed cost estimates for specific projects. As a
result, the contractor stated that its estimates should not be used to
predict a budget-level project cost.
Historically, NNSA has had difficulty developing realistic, defensible
cost estimates, especially for large, complex projects. For example, in
March 2007,[Footnote 17] we found that 8 of the 12 major construction
projects that DOE and NNSA were managing had exceeded their initial
cost estimates. One project, the Highly Enriched Uranium Materials
Facility nearing completion at the Y-12 Plant, has exceeded its
original cost estimate by over 100 percent, or almost $300 million. We
reported that the reasons for this cost increase included poor
management and contractor oversight. In addition, NNSA's cost estimate
for constructing the Chemistry and Metallurgy Research Replacement
Facility has more than doubled--from $838 million to over $2 billion--
since our April 2006 testimony. This revised cost estimate is so
uncertain that NNSA did not include any annual cost estimates beyond
fiscal year 2009 in its fiscal year 2009 budget request to the
Congress. Finally, the preliminary results of our ongoing review of
NNSA's Life Extension Program for this Subcommittee show that NNSA's
cost estimate for refurbishing each B61 nuclear bomb has doubled since
2002.[Footnote 18]
NNSA Will Need to Develop a Transformation Plan with Clear, Realistic
Milestones:
NNSA does not expect to issue a record of decision on Complex
Transformation until later this year. As a result, we do not know the
ultimate decision that NNSA will make--whether to modernize existing
sites in the weapons complex or consolidate operations at new
facilities. We expect that once NNSA makes this decision, NNSA will put
forward a transformation plan with specific milestones to implement its
decision. Without such a plan, NNSA will have no way to evaluate its
progress, and the Congress will have no way to hold NNSA accountable.
However, over the past decade, we have repeatedly documented problems
with NNSA's process for planning and managing its activities. For
example, in a December 2000 report, we found that NNSA needed to
improve its planning process so that there were linkages between
individual plans across the Stockpile Stewardship Program and that the
milestones contained in NNSA's plans were reflected in contractors'
performance criteria and evaluations.[Footnote 19] However, in February
2006, we reported similar problems with how NNSA is managing the
implementation and reliability of the nuclear stockpile.[Footnote 20]
Specifically, we found that NNSA planning documents did not contain
clear, consistent milestones or a comprehensive list of the scientific
research being conducted across the weapons complex in support of
NNSA's Primary and Secondary Assessment Technologies programs. These
programs are responsible for setting the requirements for the computer
codes and experimental data needed to assess and certify the safety and
reliability of nuclear warheads. We also found that NNSA had not
established adequate performance measures to determine the progress of
the weapons laboratories in developing and implementing this new
methodology.
Successful Transformation Requires a Strong Office of Transformation:
As we noted in July 2003, one of the key practices for successfully
transforming an organization is to ensure that top leadership sets the
direction, pace, and tone for the transformation.[Footnote 21] One of
the key problems that NNSA has experienced has been its inability to
build an organization with clear lines of authority and responsibility.
We also reported in January 2004 that NNSA, as a result of
reorganizations, has shown that it can move from what was often called
a "dysfunctional bureaucracy" to an organization with clearer lines of
authority and responsibility.[Footnote 22] In this regard, we stated in
our April 2006 testimony that NNSA's proposed Office of Transformation
needed to be vested with the necessary authority and resources to set
priorities, make timely decisions, and move quickly to implement those
decisions.[Footnote 23] It was our view that the Office of
Transformation should (1) report directly to the Administrator of NNSA;
(2) be given sufficient authority to conduct its studies and implement
its recommendations; and (3) be held accountable for creating real
change within the weapons complex.
In 2006, NNSA created an Office of Transformation to oversee its
Complex Transformation efforts. This office has been involved in
overseeing early activities associated with Complex Transformation,
such as the issuance of the December 2007 draft report on the potential
environmental impacts of alternative Complex Transformation actions.
However, the Office of Transformation does not report directly to the
Administrator of NNSA. Rather, the Office reports to the head of NNSA's
Office of Defense Programs. In this respect, we are concerned that the
Office of Transformation may not have sufficient authority to set
transformation priorities for all of NNSA, specifically as they affect
nuclear nonproliferation programs. Because NNSA's ultimate decision on
the path forward for Complex Transformation has not yet been made, it
remains to be seen whether the office has sufficient authority to
enforce transformation decisions or whether it will be held accountable
within NNSA for these decisions.
Madam Chairman, this concludes my prepared statement. I would be happy
to respond to any questions that you or Members of the Subcommittee may
have at this time.
GAO Contacts and Staff Acknowledgements:
For further information on this testimony, please contact me at (202)
512-3841 or aloisee@gao.gov. Contact points for our Offices of
Congressional Relations and Public Affairs may be found on the last
page of this statement. Ryan T. Coles, Assistant Director; Allison
Bawden; Jason Holliday; Leland Cogliani; Marc Castellano; and Carol
Herrnstadt Shulman made key contributions to this testimony.
[End of section]
Footnotes:
[1] Specifically, NNSA operates three national nuclear weapon design
laboratories--Lawrence Livermore National Laboratory, California; Los
Alamos National Laboratory, New Mexico; and the Sandia National
Laboratories, New Mexico and California--four nuclear weapons
production sites--the Pantex Plant, Texas; theY-12 Plant, Tennessee;
the Kansas City Plant, Missouri; and a portion of the Savannah River
Site, South Carolina--and the Nevada Test Site.
[2] In section 1401 of the Floyd D. Spence Defense Authorization Act
for Fiscal Year 2001 (Pub. L. No. 106-398), the Congress required the
Secretary of Defense, in consultation with the Secretary of Energy, to
"conduct a comprehensive review of the nuclear posture of the United
States for the next 5 to 10 years." The 2001 Nuclear Posture Review was
the second post-Cold War review of U.S. strategic nuclear forces. The
first one was conducted in 1994.
[3] Commissioners include William Perry, James Schlesinger, John
Foster, Lee Hamilton, Keith Payne, Ellen Williams, Harry Cartland, John
Glenn, Fred Ikle, Morton Halperin, James Woolsey, and Bruce Tarter.
[4] National Defense Authorization Act for Fiscal Year 2008 (Pub. L.
No. 110-181) §1062.
[5] NNSA, Draft Complex Transformation Supplemental Programmatic
Environmental Impact Statement (Washington, D.C., Dec. 2007).
[6] According to NNSA, this preferred action is based on the
consideration of environmental impacts, as well as consideration of
other factors such as mission and infrastructure compatibility,
economic analysis, safety, safeguards and security, and workforce
training and retention.
[7] GAO, Nuclear Weapons: Views on Proposals to Transform the Nuclear
Weapons Complex, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-
606T] (Washington, D.C.: April 26, 2006).
[8] GAO, Nuclear Weapons: NNSA Needs to Establish a Cost and Schedule
Baseline for Manufacturing a Critical Nuclear Weapon Component,
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-593] (Washington,
D.C.: May 23, 2008).
[9] GAO, Department of Energy: Major Construction Projects Need a
Consistent Approach for Assessing Technology Readiness to Help Avoid
Cost Increases and Schedule Delays, [hyperlink, http://www.gao.gov/cgi-
bin/getrpt?GAO-07-336] (Washington, D.C.: Mar. 27, 2007).
[10] NNSA has already refurbished the W87. However, as we reported in
December 2000--GAO, Nuclear Weapons: Improved Management Needed to
Implement Stockpile Stewardship Program Effectively, GAO-01-48
(Washington, D.C.: Dec. 14, 2000)--the W87 life extension experienced
significant design and production problems that raised its costs by
over $300 million and caused schedule delays of about 2 years. We found
that one of the main causes for these problems was an inadequate
management structure and unclear leadership.
[11] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-593].
[12] NNSA had planned to complete a detailed design definition and cost
study of the RRW during 2008. However, the explanatory statement
accompanying the fiscal year 2008 NNSA appropriation stated that the
bill provided no funding for the RRW program.
[13] At LANL, pit manufacturing currently takes place within the
Plutonium Facility-4 building, which was constructed in 1978 as a
multiuse research and development facility. As of September 1, 2007,
pit manufacturing and certification operations occupied about 35
percent of this building.
[14] TechSource, Inc., LMI Government Consulting, Independent Business
Case Analysis of Consolidation Options for the Defense Programs SNM and
Weapons Production Missions, preliminary draft, September 2007.
[15] This cost estimate is reported using net present value, base year
2007.
[16] The contractor assumed this consolidated nuclear production center
would be constructed at LANL.
[17] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-336].
[18] NNSA is currently refurbishing two types of B61 nuclear bombs: the
B61-7 and the B61-11.
[19] GAO, Nuclear Weapons: Improved Management Needed to Implement
Stockpile Stewardship Program Effectively, [hyperlink,
http://www.gao.gov/cgi-bin/getrpt?GAO-01-48] (Washington, D.C.: Dec.
14, 2000).
[20] GAO, Nuclear Weapons: NNSA Needs to Refine and More Effectively
Manage Its New Approach for Assessing and Certifying Nuclear Weapons,
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-261] (Washington,
D.C.: Feb. 3, 2006).
[21] GAO, Results-Oriented Cultures: Implementation Steps to Assist
Mergers and Organizational Transformations, [hyperlink,
http://www.gao.gov/cgi-bin/getrpt?GAO-03-669] (Washington, D.C.: July
2, 2003).
[22] GAO, National Nuclear Security Administration: Key Management
Structure and Workforce Planning Issues Remain as NNSA Conducts
Downsizing, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-04-545]
(Washington, D.C.: June 25, 2004).
[23] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-606T].
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office:
441 G Street NW, Room LM:
Washington, D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548: