Nuclear Weapons
National Nuclear Security Administration Needs to Better Manage Risks Associated with Modernization of Its Kansas City Plant
Gao ID: GAO-10-115 October 23, 2009
Built in 1943, the Kansas City Plant (KCP)--the National Nuclear Security Administration's (NNSA) primary production plant for manufacturing nonnuclear components of nuclear warheads and bombs--is to be modernized because of its age and the high cost of maintenance and operation. Among other changes, NNSA plans to relocate KCP to a new facility and increase components obtained from external suppliers from about 54 to 70 percent. KCP's continued supply of these components is essential for maintaining a reliable nuclear weapons stockpile. GAO was asked to determine (1) how KCP developed plans for modernization, (2) actions KCP has taken to ensure uninterrupted production of components, and (3) actions KCP has taken to address the risks of outsourcing. GAO reviewed planning documents and met with officials from NNSA, KCP, and Sandia National Laboratories, which designs many of the components produced at KCP.
KCP evaluated several alternatives on behalf of NNSA to modernize its facility based on whether the alternative (1) was consistent with NNSA's goals for maintaining a smaller facility for producing nuclear weapons and one that could quickly adapt to change, (2) met NNSA's commitments to Congress to operate a new facility by 2012, and (3) minimized costs and implementation risks. Based on KCP's analyses of alternatives, NNSA chose to have a private developer build a new building in Kansas City 8 miles from the current facility, which NNSA would then lease through the General Services Administration (GSA) for a period of 20 years. However, in evaluating a financing method, KCP compared alternatives using cost estimates limited to 20 years. Twenty years is far shorter than the useful life of a production facility that is properly maintained; the current facility has operated for more than 60 years. NNSA and KCP officials acknowledge that while leasing a facility through GSA under a 20-year scenario is less costly than purchasing, it can be more costly over the longer term. Because KCP's analysis did not consider costs beyond 20 years, NNSA cannot be certain if other alternatives, such as purchasing the facility, might have offered lower costs over the longer term. KCP officials developed extensive plans to ensure that the production of components is not interrupted because of the transition to the new facility. However, its schedule--which is critical to ensuring that the move does not disrupt production--does not fully adhere to best practices GAO identified for schedule development and related DOE scheduling guidance. In February 2009, GAO assessed KCP's schedule and found that, among other things, KCP had not adequately sequenced all activities in its schedule in the order in which they are to be carried out. GAO followed up in July 2009 and found that although KCP officials have made progress in addressing several of these problems, the schedule still has some shortcomings. KCP has taken steps to mitigate some risks of increased outsourcing, but NNSA has not provided adequate oversight or clear and up-to-date export control guidance tailored for NNSA production and laboratory sites to effectively manage associated nuclear weapons proliferation risks. As such, KCP has not implemented a formal, risk-based approach to identify specific components and technologies that may be used by potential adversaries to develop or advance their nuclear capabilities. Lacking effective NNSA-specific guidance and a risk-based approach, KCP instead treats all components as if they pose equal proliferation risks. As such, items such as a common, commercially available screw are considered to be at the same level of proliferation risk as a complex mechanism designed to arm nuclear weapons. Further, KCP's primary means of addressing this issue rests on its suppliers' self-enforced compliance with a contract clause that outlines the suppliers' responsibility to abide by applicable export control laws. Under this broadly applied approach to managing export control--where all components are treated as equal risks--NNSA may be missing opportunities at KCP to systematically identify and more effectively mitigate those risks that pose the greatest threats.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-10-115, Nuclear Weapons: National Nuclear Security Administration Needs to Better Manage Risks Associated with Modernization of Its Kansas City Plant
This is the accessible text file for GAO report number GAO-10-115
entitled 'Nuclear Weapons: National Nuclear Security Administration
Needs to Better Manage Risks Associated with Modernization of Its
Kansas City Plant' which was released on November 23, 2009.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to the Subcommittee on Energy and Water Development, Committee
on Appropriations, U.S. Senate:
United States Government Accountability Office:
GAO:
October 2009:
Nuclear Weapons:
National Nuclear Security Administration Needs to Better Manage Risks
Associated with Modernization of Its Kansas City Plant:
GAO-10-115:
GAO Highlights:
Highlights of GAO-10-115, a report to the Subcommittee on Energy and
Water Development, Committee on Appropriations, U.S. Senate.
Why GAO Did This Study:
Built in 1943, the Kansas City Plant (KCP)––the National Nuclear
Security Administration‘s (NNSA) primary production plant for
manufacturing nonnuclear components of nuclear warheads and bombs––is
to be modernized because of its age and the high cost of maintenance
and operation. Among other changes, NNSA plans to relocate KCP to a new
facility and increase components obtained from external suppliers from
about 54 to 70 percent. KCP‘s continued supply of these components is
essential for maintaining a reliable nuclear weapons stockpile.
GAO was asked to determine (1) how KCP developed plans for
modernization, (2) actions KCP has taken to ensure uninterrupted
production of components, and (3) actions KCP has taken to address the
risks of outsourcing. GAO reviewed planning documents and met with
officials from NNSA, KCP, and Sandia National Laboratories, which
designs many of the components produced at KCP.
What GAO Found:
KCP evaluated several alternatives on behalf of NNSA to modernize its
facility based on whether the alternative (1) was consistent with NNSA‘
s goals for maintaining a smaller facility for producing nuclear
weapons and one that could quickly adapt to change, (2) met NNSA‘s
commitments to Congress to operate a new facility by 2012, and (3)
minimized costs and implementation risks. Based on KCP‘s analyses of
alternatives, NNSA chose to have a private developer build a new
building in Kansas City 8 miles from the current facility, which NNSA
would then lease through the General Services Administration (GSA) for
a period of 20 years. However, in evaluating a financing method, KCP
compared alternatives using cost estimates limited to 20 years. Twenty
years is far shorter than the useful life of a production facility that
is properly maintained; the current facility has operated for more than
60 years. NNSA and KCP officials acknowledge that while leasing a
facility through GSA under a 20-year scenario is less costly than
purchasing, it can be more costly over the longer term. Because KCP‘s
analysis did not consider costs beyond 20 years, NNSA cannot be certain
if other alternatives, such as purchasing the facility, might have
offered lower costs over the longer term.
KCP officials developed extensive plans to ensure that the production
of components is not interrupted because of the transition to the new
facility. However, its schedule”which is critical to ensuring that the
move does not disrupt production”does not fully adhere to best
practices GAO identified for schedule development and related DOE
scheduling guidance. In February 2009, GAO assessed KCP‘s schedule and
found that, among other things, KCP had not adequately sequenced all
activities in its schedule in the order in which they are to be carried
out. GAO followed up in July 2009 and found that although KCP officials
have made progress in addressing several of these problems, the
schedule still has some shortcomings.
KCP has taken steps to mitigate some risks of increased outsourcing,
but NNSA has not provided adequate oversight or clear and up-to-date
export control guidance tailored for NNSA production and laboratory
sites to effectively manage associated nuclear weapons proliferation
risks. As such, KCP has not implemented a formal, risk-based approach
to identify specific components and technologies that may be used by
potential adversaries to develop or advance their nuclear capabilities.
Lacking effective NNSA-specific guidance and a risk-based approach, KCP
instead treats all components as if they pose equal proliferation
risks. As such, items such as a common, commercially available screw
are considered to be at the same level of proliferation risk as a
complex mechanism designed to arm nuclear weapons. Further, KCP‘s
primary means of addressing this issue rests on its suppliers‘ self-
enforced compliance with a contract clause that outlines the suppliers‘
responsibility to abide by applicable export control laws. Under this
broadly applied approach to managing export control––where all
components are treated as equal risks––NNSA may be missing
opportunities at KCP to systematically identify and more effectively
mitigate those risks that pose the greatest threats.
What GAO Recommends:
GAO is recommending, among other things, that NNSA ensure that future
cost analyses consider the full useful life of the facility, revise the
KCP relocation schedule to be consistent with Department of Energy
(DOE) guidance and GAO-identified best practices, and develop a risk-
based approach for managing technologies that could advance
adversaries‘ nuclear capabilities. In commenting on a draft of this
report, NNSA generally agreed with our recommendations.
View [hyperlink, http://www.gao.gov/products/GAO-10-115] or key
components. For more information, contact Gene Aloise at (202) 512-3841
or aloisee@gao.gov.
[End of section]
Contents:
Letter:
Background and Overview of Plans for Modernizing NNSA's KCP Facility:
KCP Evaluated Several Alternatives for Modernizing Its Facility but Did
Not Fully Analyze the Long-Term Impact of Some Financing Options:
KCP Is Taking Steps to Ensure Uninterrupted Production, Including
Efforts to Address Scheduling Problems We Identified:
KCP Has Begun Taking Steps to Mitigate Some Outsourcing Risks but Could
Better Safeguard Technologies That Pose Nuclear Proliferation Risks:
Conclusions:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Objectives, Scope, and Methodology:
Appendix II: GAO Assessment of KCP's Relocation Schedule:
Appendix III: Comments from the National Nuclear Security
Administration:
Appendix IV: GAO Contact and Staff Acknowledgments:
Tables:
Table 1: KCP's Comparison of Financing Options:
Table 2: KCP's Progress in Meeting GAO-Identified Best Practices for
Scheduling:
Figure:
Figure 1: Production of Nonnuclear Components in the U.S. Nuclear
Weapons Complex:
Abbreviations:
DOD: Department of Defense:
DOE: Department of Energy:
DOJ: Department of Justice:
GSA: General Services Administration:
KCP: Kansas City Plant:
NNSA: National Nuclear Security Administration:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
October 23, 2009:
The Honorable Byron L. Dorgan:
Chairman:
The Honorable Robert Bennett:
Ranking Member:
Subcommittee on Energy and Water Development:
Committee on Appropriations:
United States Senate:
Built in 1943, the Kansas City Plant (KCP)--the National Nuclear
Security Administration's (NNSA) primary production plant for
manufacturing nonnuclear components of nuclear warheads and bombs--is
being modernized because of its age and the high cost of maintenance
and operation. KCP produces or procures more than 100,000 parts
annually--ranging from nuts and bolts to complex radars--comprising
about 85 percent of the components that go into a typical nuclear
weapon. NNSA, a separately organized agency within the Department of
Energy (DOE), owns the building, equipment, and components produced at
KCP, and NNSA's Kansas City Site Office provides local oversight of all
activity. Honeywell Federal Manufacturing and Technologies (Honeywell)
manages and operates the KCP facility for NNSA. In response to a July
2005 report of the Secretary of Energy Advisory Board's infrastructure
task force,[Footnote 1] and NNSA's 2006 strategic plan on
infrastructure,[Footnote 2] which proposed ways to transform the
nuclear weapons complex, NNSA directed KCP to develop plans for
modernizing its production facilities based on its goals of developing
a smaller, more responsive production infrastructure--one that will
ultimately support a smaller nuclear weapons stockpile--while
continuing to maintain and refurbish the weapons currently in the
stockpile. KCP outlined three key avenues for achieving NNSA's goals,
including (1) purchasing more components from external suppliers; (2)
implementing a more commercial-like business process; and (3) building
a smaller, modern, state-of-the-art, and more flexible manufacturing
facility by 2012. KCP's current plans are expected to result in an 18-
month relocation to a new facility, an increase in outsourcing of
components from 54 to 70 percent, and a reduction in KCP's
manufacturing footprint from about 3 million to 1 million square feet.
KCP estimates that these measures will save about $100 million
annually.
Because KCP produces or procures components that are used to maintain
the nation's nuclear weapons stockpile, any disruptions in production
at KCP could negatively affect the nuclear weapons stockpile. Another
important consideration--particularly as KCP increases purchases of
components from external suppliers, or outsourcing--is ensuring that
NNSA protects components and technologies, including weapons-related
design drawings, unique production processes, and information that,
although mostly unclassified, could be used by potential adversaries to
develop or advance their nuclear capabilities. Recent GAO testimonies
and a grand jury indictment have described events where foreign
entities sought dual-use items--items that can be used for both
commercial and military applications. In fact, we covertly purchased
two such items--a triggered spark gap and an accelerometer--and shipped
dummy copies overseas to demonstrate the ease with which real, illegal
shipments could be affected.[Footnote 3] These events also demonstrate
potential nuclear proliferation risks and gaps in the nation's system
for controlling the export of these items.[Footnote 4] KCP regularly
outsources the production of these types of dual-use items--which may
have been designed at the nuclear weapons laboratories with unique
weapons design characteristics, such as very high tolerances to extreme
environments--raising questions as to whether these items may be more
vulnerable to export.
In this context, you asked us to determine (1) how KCP developed plans
for modernizing the facility, (2) actions KCP has taken to ensure
uninterrupted production of components needed to support the weapons
stockpile during and after the transition to the new facility, and (3)
actions KCP has taken to address the risks and potential consequences
of increased outsourcing of nonnuclear components.
To determine how KCP developed plans for modernizing the current
facility, we reviewed NNSA and Honeywell documents describing the
project's goals, approach, and rationale for key decisions on what
actions to take, where to locate the facility, and how to finance it.
We also interviewed officials at NNSA's Kansas City Site Office,
Honeywell, and relevant subcontractors. Under our long-standing policy
of not addressing issues in ongoing litigation, we did not evaluate
KCP's analysis of location alternatives because a lawsuit was filed in
October 2008 that among other things challenged the extent and adequacy
of DOE's consideration of alternatives to its plans for replacing the
KCP facility.[Footnote 5] To determine the actions KCP has taken to
ensure uninterrupted production of components, we reviewed agency and
contractor documents describing transition plans and talked to
officials at Sandia National Laboratories (Sandia) in New Mexico, which
designs many of the nonnuclear components that are produced at KCP. We
also evaluated the reliability of KCP's relocation schedule using GAO-
identified best practices for effective scheduling,[Footnote 6] many of
which are also identified by DOE in its guidance on establishing
performance baselines.[Footnote 7] To determine the actions KCP has
taken to address the risks associated with outsourcing, we reviewed
agency and contractor documents, including KCP's outsourcing strategy
and export control process and relevant export control laws and
regulations, and interviewed key KCP, Sandia, and NNSA officials
responsible for overseeing nuclear nonproliferation activities.
We conducted this performance audit from November 2008 through October
2009 in accordance with generally accepted government auditing
standards. Those standards require that we plan and perform the audit
to obtain sufficient, appropriate evidence to provide a reasonable
basis for our findings and conclusions based on our audit objectives.
We believe that the evidence obtained provides a reasonable basis for
our findings and conclusions based on our audit objectives. Appendix I
contains a detailed description of our scope and methodology.
Background and Overview of Plans for Modernizing NNSA's KCP Facility:
The KCP facility, NNSA's primary site for producing or procuring
nonnuclear components, is the first site within the nuclear weapons
complex scheduled for significant modernization. KCP does not possess
weapons-grade nuclear materials, but it supplies approximately 85
percent of the nonnuclear components that compose a typical nuclear
weapon--ranging from simple items like nuts and bolts to more complex
components, such as radars, arming and firing mechanisms, and critical
nuclear safety devices meant to prevent accidental detonation. The
facility has a footprint of nearly 3 million square feet and costs
about $400 million per year to operate. Currently, about 127,000 square
feet of this space is devoted to stored inventory, including production
equipment, tooling, gauges, and testers.
Modernizing the KCP Facility:
The production infrastructure of the nuclear weapons complex is aging
and becoming increasingly outdated. A 2001 Department of Defense (DOD)
review of the nation's nuclear policy found that the nuclear weapons
production infrastructure needed to be repaired and made more flexible
so that it could adapt to the changing needs of the nuclear weapons
stockpile.[Footnote 8] Subsequently, NNSA developed the strategic
Complex Transformation Plan, which seeks to develop a smaller, more
responsive production infrastructure--one that will ultimately support
a smaller nuclear weapons stockpile--while continuing to maintain and
refurbish the weapons currently in the stockpile.
As part of its Complex Transformation Plan, in 2006 NNSA directed KCP
to develop plans for modernizing its production facilities. In its
plans, KCP identified three key avenues for achieving NNSA's goals:
Increasing outsourcing. KCP is increasing the percentage of nonnuclear
components purchased from external suppliers from about 54 to 70
percent. At the same time, it is consolidating and reducing its
external suppliers from about 412 in May 2008 to 320 in September 2009
to reduce the costs of working with and certifying multiple suppliers.
As more components are acquired from external suppliers, KCP expects
the equipment and infrastructure necessary for the production of many
of those components to be eliminated, reducing the need for the large
size and associated operating costs of the facility. KCP currently uses
domestic-based suppliers, with the exception of those components that
are acquired from Malaysia and Mexico. Nearly all of the components and
processes that KCP outsources are unclassified; KCP officials told us
that they have only certified one supplier that is approved for
classified processing, production, and storage.
Transforming its business processes. Honeywell, the contractor that
manages KCP, is implementing more commercial-like business practices.
In particular, KCP officials note that they have recently been granted
relief from some DOE and NNSA oversight, such as NNSA nuclear security
orders, because it does not possess weapons-grade nuclear material and
because commercial standards are being used. KCP officials believe that
these changes will lead to more streamlined business processes with
lower administrative costs. According to KCP officials, an independent
review estimated that these lower costs will amount to $37 million each
year--more than one-third of the $100 million annual cost savings KCP
projects will result from its modernization plans.
Building a modern, more flexible facility. NNSA plans to have a new KCP
facility built on an undeveloped site in Kansas City, Missouri. KCP's
new facility is designed to be smaller and more adaptable than the
current facility, allowing quick and economical changes to the
capability and capacity of the facility, such as using more open
manufacturing space and modular utility systems so that it can be
quickly and inexpensively reconfigured to adapt to changing production
needs. NNSA committed to Congress that the new KCP facility would be
operating by 2012 but now expects a delay of about 1 year.
Financing the New Facility:
To construct this new facility, NNSA identified three financing
options. The traditional approach for financing construction projects
is to request funding from Congress using a budget line item in the
President's annual request for appropriations. If the requested funds
are appropriated, a federal manager directly controls the scope, cost,
and schedule of the design and construction of the facility. These
projects usually require significant funding up front when the facility
is being designed and constructed. However, as we have reported, large
amounts of funding have become more difficult to obtain, and agencies
are increasingly interested in financing alternatives that distribute
costs over longer periods of time.[Footnote 9] One alternative is to
acquire facilities using the General Services Administration's (GSA)
leasing authority, which allows GSA to lease space from a private
developer on behalf of many government agencies. For a lease on
privately owned land, the process culminates with a lease agreement of
up to 20 years.[Footnote 10] Another alternative, according to KCP
officials, allows NNSA to secure financing directly through private
developers for the construction of facilities, but this alternative
allows only for a maximum 5-year lease term.[Footnote 11]
We have considered federal leasing, in general, to be a challenge for
almost 20 years. In January 2003 we designated federal real property as
a high-risk area, citing the government's overreliance on costly, long-
term leasing as one of the major reasons.[Footnote 12] Our work has
also shown that building ownership often costs less than operating
leases, especially for long-term space needs.[Footnote 13] Based on
this work, we made recommendations in 2008 that agencies develop
strategies to reduce reliance on leased space for long-term needs when
ownership would be less costly.[Footnote 14]
Avoiding Interruptions in the Supply of Components:
Another important consideration in KCP's modernization plans is
avoiding interruptions in the supply of components it produces. Such
interruptions could negatively affect the nuclear weapons stockpile and
weaken national security. For example, as nuclear weapons components
age, they may need to be replaced to avoid undermining the reliability
and performance of the weapon that they occupy. KCP produces or
procures these replacement components. Much of KCP's current workload
supports the life extension program for the W76 warhead--carried on the
Navy's Trident II submarine-launched ballistic missile--which is a
significant part of the U.S. nuclear weapons stockpile. Life extensions
lengthen weapons' operational life for an additional 20 to 30 years and
allow NNSA to certify that the weapons continue to meet military
performance requirements without underground nuclear testing. In
addition, KCP currently produces or procures nonnuclear components
needed to maintain the W88 submarine-launched ballistic missile
warheads, the W78 and W87 intercontinental ballistic missile warheads,
the W80 cruise missile warhead, and the B61 and B83 nuclear bombs.
Managing Outsourced Technologies:
Another important consideration in KCP's modernization plans,
particularly as it begins to increase outsourcing, is that KCP manages
components and technologies that might be attractive to terrorists or
other potential adversaries. Passing components and technologies to
external suppliers may put them at greater risk of being obtained and
used by potential adversaries to develop or advance their own nuclear
capabilities. Recently, the Department of Justice (DOJ) reported that
on a daily basis, foreign states as well as criminal and terrorist
groups seek arms, technology, and other material to advance their
technological capacity, and the United States is a primary target
because it produces advanced technologies. For fiscal year 2008, DOJ
reported that more than 145 defendants faced criminal charges for
attempting to illegally transfer these items and technologies, with
roughly 43 percent of these defendants charged with attempting to
transfer them to Iran or China.
Some of the components KCP produces or procures, as well as
technologies that can be developed from obtaining weapons-related
design drawings and unique production processes, among other things,
may be subject to laws and regulations controlling their export. Export
control is primarily managed by the Departments of Commerce and State.
The Department of Commerce, through the Export Administration
Regulations, controls exports of most dual-use items and technologies.
The Department of Commerce maintains the Commerce Control List, which
describes the characteristics and capabilities of dual-use items that
may require export licenses. The list is divided into 10 general
categories of controlled technologies, such as sensors or electronics,
which could include components that KCP produces or outsources. The
Department of State, under the authority of the Arms Export Control Act
and the International Traffic in Arms Regulations, controls exports of
munitions items and technologies--those designed, developed,
configured, adapted, or modified solely for military applications.
These items are identified on the U.S. Munitions List, requiring most
to be licensed for export. While these two departments are responsible
for limiting the possibility of export-controlled items and
technologies falling into the wrong hands, NNSA asserts that it is also
generally responsible for the management and security of the nation's
nuclear weapons, including ensuring that nuclear weapons components or
related information about these technologies are not used to advance
the nuclear capabilities of potential adversaries.
Collaborating with NNSA's National Laboratories:
Many of the actions needed to successfully relocate the KCP facility
require the ongoing cooperation of and collaboration with other NNSA
laboratory sites. Design engineers at Lawrence Livermore, Los Alamos,
and Sandia National Laboratories design the nonnuclear components
produced or procured by KCP and determine whether the designs are
classified, among other things. KCP produces or procures the components
according to laboratory design specifications, but quality and
production engineers from KCP continue to periodically collaborate with
laboratory design engineers to oversee production, mitigate production
risks, and integrate competing priorities, such as cost, schedule,
design requirements, and quality. Before KCP begins full procurement or
production of some components, laboratory design engineers must
formulate a plan to qualify the component and assist in executing the
qualification plan, which involves testing a sample of components to
ensure that they meet quality, safety, and security standards. Such
tests may include visual, environmental, mechanical, and electric
tests, among others. In addition, if KCP decides to make major
production changes or move the production process, components may have
to be requalified to ensure that they still meet quality, safety, and
security standards. Requalification can take from 1 month to more than
1 year, depending on the significance or complexity of the part and the
extent of the planned production change. Requalification may also be
required when a product is outsourced or moved from one supplier to
another. As such, many components will have to be requalified before
they can be produced at KCP's new facility or by an external supplier.
KCP is NNSA's primary site within the nuclear weapons complex for
producing nonnuclear components of nuclear warheads and bombs. Figure 1
illustrates how sites in the nuclear weapons complex interact with each
other to design, produce, procure, and assemble nonnuclear components.
Figure 1: Production of Nonnuclear Components in the U.S. Nuclear
Weapons Complex:
[Refer to PDF for image: illustration]
Design laboratories:
Lawrence Livermore National Laboratory:
Designs nuclear and nonnuclear components.
Sandia National Laboratories:
Primary designer of nonnuclear components.
Los Alamos National Laboratory:
Designs nuclear and nonnuclear components.
Production plants:
Private suppliers:
KCP outsources the production of select nonnuclear parts and
components to private suppliers:
May 2006:
Produced at KCP: 46%;
Outsourced: 54%.
September 2011:
Produced at KCP: 30%;
Outsourced: 70%.
Kansas City Plant:
Produces or procures nonnuclear components.
Pantex Plant:
Assembles nuclear weapons using nonnuclear components from KCP and
nuclear components from other NNSA sites.
Other production sites within the nuclear weapons complex:
Savannah River Site;
Y-12 Plant.
Nuclear weapons stockpile:
Department of Defense.
Source: GAO analysis of NNSA and KCP data.
[End of figure]
KCP Evaluated Several Alternatives for Modernizing Its Facility but Did
Not Fully Analyze the Long-Term Impact of Some Financing Options:
KCP officials told us that they evaluated several locations and
financing alternatives based on their potential for satisfying NNSA's
key goals outlined in its strategic plans for modernizing the overall
infrastructure of the nuclear weapons complex. Based on analyses
conducted by KCP, NNSA chose to lease a new facility for 20 years.
However, KCP compared financing alternatives using cost estimates
limited to 20 years rather than the full expected life of the proposed
facility; therefore, NNSA cannot be certain whether other financing
alternatives might have offered lower costs over the longer term.
KCP Evaluated Several Alternatives for Modernizing the Facility:
KCP evaluated several alternatives on behalf of NNSA for modernizing
its facility based on each alternative's potential to satisfy key goals
outlined in NNSA's strategic plans for modernizing the nuclear weapons
complex, among other things.[Footnote 15] Specifically, KCP officials
told us that they sought an option that (1) was consistent with NNSA's
goals for maintaining a smaller facility for producing nuclear weapons
and that could quickly adapt to change; (2) met schedule commitments to
Congress; (3) minimized costs of constructing and annually operating
and maintaining the facility; and, (4) maximized chances of completing
the relocation within the established scope, cost, and schedule.
Although KCP conducted the analyses of alternatives for modernizing its
facility under the direction of NNSA, NNSA ultimately made its final
decisions on how best to proceed using these analyses.
To determine how to proceed with the modernization of its facility, KCP
officials stated that they considered (1) taking no action--essentially
continuing operations at the current KCP location; (2) renovating
adjacent GSA facilities; (3) purchasing or leasing other facilities
that were already available in the Kansas City area; or (4) building a
new facility on the existing KCP site, on other vacant land within
Kansas City, or at another location. KCP officials explained that
several of these options proved undesirable for a variety of reasons.
* Taking no action. KCP determined that taking no action did not align
with NNSA's overall Complex Transformation goals or commitments that
NNSA's Deputy Administrator made to Congress to modernize the facility.
According to KCP officials, taking no action would also result in
annual operating costs that are about $100 million higher than
necessary beyond fiscal year 2013, over half of which would be related
to facility maintenance.
* Renovating adjacent GSA facilities. KCP determined that renovating
adjacent GSA facilities was feasible and the least costly alternative
in terms of construction costs, but it posed several problems. For
example, renovating the 70-year-old facility would require extensive
modification of electrical, heating, and cooling systems, which would
require moving, penetrating, or bypassing concrete walls, floors, and
ceilings. KCP officials stated that this would be difficult and time-
consuming, and the considerable expense would be of questionable worth
for such an old facility. Also, the adjacent facility is located in an
area susceptible to flooding. Further, KCP officials stated that this
option presented schedule risks. For example, multiple tenants in the
GSA facility would need to relocate, and any delays in their
relocations could cascade to the renovation process.
* Purchasing or leasing other available facilities in the Kansas City
area. KCP officials stated that they could not identify any other
facilities in the region that were adequate for the KCP mission.
In light of these constraints, NNSA officials determined that building
a new facility was the best option.
To identify a specific location for the new facility, KCP officials
also told us that they considered nearby sites as well as sites outside
of the Kansas City area. In particular, NNSA's Office of Transformation
asked Science Applications International Corporation--a support
contactor--to prepare an independent assessment of moving the
nonnuclear production facilities from KCP to another site in the
nuclear weapons complex.[Footnote 16] In examining seven other active
NNSA sites in the nuclear weapons complex, the study determined that
Albuquerque, New Mexico, presented the highest potential for cost
savings because Sandia--the primary design laboratory for nonnuclear
components--has a location there. However, the study concluded that
constructing the new facility in Albuquerque would not allow NNSA to
recover the cost of moving the operation--reaching a "break even"
point--by the end of the period considered in the study--about 20
years. The study also determined that relocating operations away from
Kansas City would be expensive because staff would have to relocate,
new staff would have to be trained, and critical expertise would be
lost. Ultimately, based on KCP's analysis, NNSA decided to build its
new facility on an available site in Kansas City about 8 miles from the
existing facility that is not on a flood plain.
KCP's Cost Evaluation Did Not Consider the Full Life Cycle Costs of the
Proposed Facility:
To determine how to finance the construction of the new facility, KCP
analyzed options to determine which best met NNSA's goals and presented
acceptably low risks. According to KCP officials, these options
included (1) using congressional line item capital project funding,
which is DOE's traditional approach; (2) using a DOE lease process,
which secures financing directly through private developers for the
construction of facilities, but allows for a maximum 5-year lease term;
and (3) using GSA's leasing process. According to KCP officials, GSA's
leasing process was the best available financing alternative because it
was the only financing option that could meet the NNSA Administrator's
commitment to Congress to operate the facility by 2012. GSA's leasing
process also led to the lowest overall total cost over a 20-year period
and eliminated the need for large up-front capital outlays that Office
of Management and Budget officials said would likely not be available
for modernizing KCP. According to KCP officials, a 20-year lease
through GSA would cost less annually than a lease undertaken through
DOE's lease process, which allows only a maximum 5-year lease.
The GSA lease process defines, among other things, (1) facility
requirements; (2) how the facility should be built, such as security
during construction; and (3) developer responsibilities for providing
facility maintenance services over the life of the lease. For a lease
on privately owned land, the process results in an operating lease
agreement of up to 20 years--a legal and binding contract between GSA
and a developer, with ownership remaining with the developer. KCP
estimated that the GSA lease option would cost about $4.762 billion,
which includes estimated annual operating costs, onetime relocation
costs, capital equipment, and annual lease payments of about $43
million beginning in fiscal year 2011 and continuing through fiscal
year 2030. In contrast, KCP's total estimated cost for constructing the
facility using congressional line item capital project funding is about
$4.875 billion, which includes the same types of costs plus
construction costs, but excludes annual lease payments because NNSA
would own the facility.[Footnote 17] KCP determined that DOE third-
party financing was not viable because the process was new and unproven
and offered only a short-term lease of 5 years, which KCP officials
believed would likely result in higher annual lease costs because
potential developers would have difficulty obtaining financing for such
a short-term lease at a reasonable cost. As a result, KCP did not
develop a total estimated cost based on a 5-year lease using DOE's
process of obtaining third-party financing. Table 1 shows KCP's
comparison of the two KCP options it determined would pose the lowest
risk to implement--the GSA lease and DOE line-item project--revealing
that the GSA lease is less costly than line-item funding by over $100
million.
Table 1: KCP's Comparison of Financing Options (Dollars in billions):
Financing option: GSA lease;
Meets NNSA's complex transformation goals: Yes;
Meets NNSA's schedule commitments to Congress: Yes;
Total estimated cost[A]: $4.762.
Financing option: Congressional line item capital project funding;
Meets NNSA's complex transformation goals: Yes;
Meets NNSA's schedule commitments to Congress: No;
Total estimated cost[A]: $4.875.
Source: GAO analysis of KCP data.
[A] KCP's total estimated cost is presented as the net present value in
fiscal year 2006 dollars, with GSA lease payments beginning in fiscal
year 2011 and ending in fiscal year 2030--a 20-year period. KCP's
estimate also includes costs for the 5 years preceding commencement of
the lease payments.
[End of table]
However, KCP did not compare alternatives using the total costs over
the expected life of the proposed KCP facility--the full life cycle
costs; therefore, NNSA cannot be certain whether other alternatives
might result in lower longer-term costs. KCP limited its analysis of
future costs to 20 years after lease payments begin, consistent with
the longest lease term allowed under the GSA option and the longest
period for which NNSA was willing to commit to under its current KCP
relocation approach. However, 20 years is far shorter than the useful
life of a production facility that is properly maintained; the current
KCP facility has operated for more than 60 years. In addition, although
requirements may change in the future, current nuclear weapons
production requirements justify the need for KCP manufacturing
capabilities for at least another 32 years. Although leasing a facility
for 20 years through GSA is less costly than leasing over shorter-term
periods, leasing is usually more costly over the long term than
constructing and owning a facility. NNSA and KCP officials acknowledged
that while leasing a facility through GSA under a 20-year scenario is
less costly than a line item project, it can be more costly over a
longer-term scenario--possibly even beginning at about 22 years into
the lease.
In early 2009, DOE's Office of Cost Analysis reviewed KCP's relocation
project. Although ultimately supporting NNSA's decision to lease a new
facility, DOE's review found KCP's cost analysis to be biased toward
the leasing option. DOE's review noted that while leasing is more
affordable up front, it is more costly over time, particularly since
the government tends to occupy facilities for long periods of time and
must pay relocation costs when the lease terms expire or negotiate new
leases and continue making lease payments. KCP's cost analysis, being
limited to 20 years, precludes including either of these costs, whereas
a full life cycle cost analysis would have included both relocation and
continuing lease costs.
KCP officials stated that limiting their analyses to 20 years is
appropriate and is consistent with NNSA's overall approach for KCP's
transformation. As part of its goals to develop a more adaptable
nuclear infrastructure, NNSA determined that 20 years is the longest
period for which it would be willing to commit under the current KCP
relocation approach. NNSA officials stated that it is conceivable that
the nation's entire nuclear stockpile, its nuclear strategy, or both
could be obsolete by 2030 and a new strategy would apply. However,
NNSA's weapons program manager for the W76 and W88 told us that current
nuclear weapons production requirements for these two warhead types
justify the need for KCP manufacturing capabilities until at least
2042. He added that since some threat to the United States will always
exist, a new project will likely replace the W76 and W88 if they are
ever taken out of service, thus justifying the need for KCP's
manufacturing capabilities even beyond 2042.
KCP Is Taking Steps to Ensure Uninterrupted Production, Including
Efforts to Address Scheduling Problems We Identified:
KCP is initiating several key actions to help ensure that components
are produced without delay or interruption, such as producing
components before the move to compensate for periods of time when
production will be halted and coordinating with design laboratories
that will help to requalify equipment after the move. However, KCP's
relocation schedule--which is critical to ensuring that the move does
not disrupt production--did not initially adhere to all of GAO's best
practices for schedule development. While KCP officials have taken
steps to address some of these problems, the schedule still has some
shortcomings.
KCP Is Initiating Several Key Actions to Help Ensure That Components
Are Produced without Delay or Interruption:
In preparation for KCP's 18-month move to its new facility, KCP
officials have developed plans to ensure that it can continue to
provide components for the nuclear weapons stockpile as scheduled. In
2007, KCP hired a professional moving company to develop a high-level
strategy to minimize the duration, costs, and disruptions associated
with the move. This strategy included major milestones and estimated
time frames for moving each department within KCP. Based on these
estimates, KCP has begun to produce components that it will store or
deliver before and during the move to ensure that it can meet delivery
requirements when production is halted to move, set up, and requalify
equipment at the new facility. KCP officials conducted long-range
planning to determine the demand for components through 2016, which
helped officials estimate the number of components to produce in
advance. As of June 2009, KCP officials stated that they are largely on
schedule for producing these additional components.
Moreover, KCP has established a formal program to capture and preserve
information about certain production processes and ensure that
production capabilities are not lost. While KCP does not plan to record
information about all processes, officials developed more than 60 step-
by-step videos, overview videos, and notes from subject matter experts.
This knowledge preservation program focuses on processes that are
difficult to develop or involve key personnel who are retiring or
otherwise leaving through other forms of attrition, as well as
processes that KCP uses infrequently or plans to outsource. These
efforts are designed to allow KCP to transfer knowledge and resume
internal production of outsourced components, if necessary. Our March
2009 report on NNSA's stockpile life extension program illustrates the
importance of maintaining such information.[Footnote 18] Specifically,
at another NNSA site, we found that officials no longer knew how to
manufacture a key material needed to refurbish the W76 warhead because
the site had kept few records of the process when the material was made
in the 1980s, and almost all staff with expertise on its production had
retired or left the agency. NNSA's efforts to address this information
gap resulted in $69 million in cost overruns and a schedule delay of at
least 1 year that presented significant logistical challenges for the
Navy. KCP's knowledge preservation program should help avoid similar
problems.
In addition, KCP has developed a strategy to estimate the cost and time
needed to requalify production and testing equipment after the move,
which will help to ensure that the equipment continues to produce
components of the same quality as before the move. In particular, KCP
officials have identified all equipment that they believe will need to
be requalified and determined how the move will affect this equipment,
which in turn will affect how extensive requalification efforts will
need to be. For example, officials assessed how the production process
will change as a result of KCP purchasing new equipment or outsourcing
production. Changes in environment, such as temperature and humidity
levels, could also affect equipment and production. KCP officials also
estimated how long requalification will likely take, based on previous
requalification efforts, and have been meeting with design laboratories
since July 2006 to plan and budget requalification efforts and to
communicate overall plans for KCP's transition.
However, officials at Sandia stated that they are concerned that they
may not have sufficient funds to assist with requalification activities
within KCP's scheduled time frames. KCP officials estimate that
requalification activities will cost KCP about $20 million, while
Sandia estimates that their support of requalification activities will
cost Sandia an additional $40 million for fiscal years 2008 through
2013.[Footnote 19] In fiscal year 2009, the design laboratories'
budgets did not include funding for requalification at KCP; the
laboratories have requested funding for fiscal year 2010. KCP officials
acknowledge that if funding is not available, requalification efforts
will be delayed, which will significantly delay its production
schedule. Nevertheless, KCP believes that NNSA is committed to the KCP
transition and will provide adequate funding to the design laboratories
to support requalification. Accordingly, KCP is continuing to
coordinate with the laboratories to estimate requalification needs.
KCP officials have also made plans to provide additional capability and
capacity at the new facility to produce components that implement new
technology or to reestablish the production of outsourced components if
necessary. Specifically, KCP designed the facility so that it can add
second and third work shifts, which may allow it to increase production
of some components if needed. KCP has also dedicated about 10 percent
of the facility's total square footage--about 100,000 square feet out
of the facility's 1 million total square feet--to unused space that can
be quickly and cost effectively converted for new capabilities or
expansion of existing ones. KCP officials stated that they designed the
new facility with a more open manufacturing space and modular utility
systems so that it can be quickly and inexpensively reconfigured to
adapt to changing production needs. In contrast, reconfiguring KCP's
current facility would require extensive modification of electrical,
heating, and cooling systems, including moving, penetrating, or
bypassing concrete walls, floors, and ceilings. KCP has also retained
the capability to produce certain components that it currently
outsources, which will allow it to reverse the decision to outsource
those components and more quickly resume production internally if
necessary. For other components, however, KCP officials have determined
that there are many private suppliers with similar production
capabilities. As a result, KCP will not retain the ability to produce
these components or execute such processes.
KCP plans to reduce the size of its available stored inventory space
from nearly 300,000 square feet to 60,000 square feet--a total
reduction of about 240,000 square feet, or about 80 percent. This will
be accomplished by higher-density storage and disposition of obsolete
and surplus inventory. KCP officials are currently in the process of
identifying surplus inventory, which they define as items that have not
been used in the last 2 years or have no demand anticipated in the next
10 years. As of February 2009, KCP had identified from 8,000 to 9,000
parts as surplus inventory. Sandia design engineers are concerned that
KCP may discard critical equipment that could be expensive and
difficult to re-create if it were needed again in the future. However,
according to KCP officials, most equipment stored at KCP is so outdated
that it would cost more to repair the equipment than the equipment is
worth. Moreover, KCP officials said that they have consulted
periodically with design engineers as part of the review process and
that before disposal of items is authorized, NNSA will distribute a
list of excess items to all nuclear weapons complex sites to confirm
that KCP does not need to retain these items. KCP officials said that
they plan to continue to coordinate with the design laboratories as
they reduce inventory.
KCP Has Begun Taking Steps to Address Some Scheduling Problems We
Identified:
As part of KCP's plans to ensure a smooth transition to its new
facility, KCP officials are working to develop a comprehensive project
schedule that details when relocation activities will occur, how long
they will take, and how they are interrelated. The schedule provides a
road map for the move and a means for gauging progress and identifying
potential problems. KCP officials stated that they have not established
a formal baseline of the schedule because the construction portion of
the schedule is not firm.[Footnote 20] We assessed KCP's initial
schedule in February 2009 and found that KCP did not fully adhere to
GAO-identified best practices for schedule development. We assessed its
revised schedule in July 2009 and found that KCP officials have taken
steps to address some of the problems identified in our initial review,
but that the schedule still has some shortcomings.
We assessed KCP's relocation schedule based on the nine best practices
we have identified for effective schedule estimating: (1) capturing key
activities, (2) sequencing key activities, (3) assigning resources to
key activities, (4) establishing the duration of key activities, (5)
integrating key activities horizontally and vertically, (6)
establishing the critical path for key activities, (7) identifying
"float time"--the time that activities can slip before the delay
affects the completion date, (8) performing a risk analysis of the
schedule, and (9) updating the schedule using logic and durations to
determine dates.[Footnote 21] Most of these practices are also
identified by DOE in recent guidance on establishing performance
baselines.[Footnote 22] Appendix II contains more details on GAO's best
practices for scheduling and a description of our assessments.
Our assessment of KCP's February 2009 schedule revealed that KCP did
not meet three of these best practices and only partially met five.
[Footnote 23] For example, we found that KCP's schedule did not reflect
resources--such as labor, material, or overhead--required to complete
each activity, which is important to determine the feasibility of the
schedule based on available resources. Further, KCP officials told us
that they did not intend to conduct a risk analysis of the schedule,
which, according to best practices, is important to predict the level
of confidence in meeting a program's completion date and to identify
high-priority risks. In addition, our assessment revealed that KCP
established excessively long time frames for some very broad
activities--275 activities had time frames of over 200 days in length.
According to best practices, activity durations should be as short as
possible.
In April 2009, we provided KCP and NNSA officials with our assessment
of the February schedule. Although KCP officials provided additional
context about their particular schedule situation, they acknowledged
that the pre-baselined schedule was not yet complete and expressed an
intention to work toward ensuring that the relocation schedule better
conforms to GAO-identified best scheduling practices. For example, KCP
officials acknowledged that they did not assign resources to activities
in the schedule as suggested by GAO best practices, but explained that
they planned to assign resources to certain activities in the schedule
as well as track resources using other management systems as they
complete a more detailed relocation plan in fiscal year 2011. KCP
officials also explained that scheduling is time-intensive, and that
the schedule is updated and improved daily. For example, KCP officials
told us that they are in the process of reducing the number of
activities with excessively long durations by, among other things,
splitting longer duration activities into more detailed and shorter
tasks as more information becomes available. KCP officials further
explained that most of the activities with long durations are well into
the future and cannot be accurately broken into smaller segments until
some near-term activities are completed. In addition, KCP officials
explained that although they have not performed a formal risk analysis
on the schedule, they use alternative methods to identify and reduce
scheduling risks. For example, KCP officials told us that scheduling
officials consult subject matter experts to provide estimates for the
duration of activities, which they believe will be successfully
executed within those time frames. Further, KCP officials asserted that
they are monitoring schedule risks at the project and program levels
through a separate database.
In our review of KCP's revised schedule in July, we found that KCP had
taken steps to address some of the problems we identified; however, the
schedule still does not fully adhere to GAO's best practices.
Specifically, KCP improved the schedule in several areas. For example,
KCP's February schedule did not fully resolve some key activities on
the critical path--the path of work that must be completed as planned
if the projected completion date is to be met. To correct this, KCP's
July schedule included additional information on the lease award and
other activities in the critical path that more realistically depicts
KCP's overall expected completion date for relocation--October 2013,
about a 1-year delay from NNSA's original commitment to Congress.
However, a few practices that KCP's initial schedule either did not
meet or only partially met did not significantly improve. For example,
although KCP officials monitor schedule risks in a separate database,
they do not plan to conduct a risk analysis using statistical analysis
techniques as suggested by GAO-identified best practices. Table 2
summarizes the progress KCP made from February through July 2009.
Table 2: KCP's Progress in Meeting GAO-Identified Best Practices for
Scheduling:
Criterion: Capturing all activities;
February 2009: [A];
July 2009: Partially meets.
Criterion: Sequencing all activities;
February 2009: Does not meet;
July 2009: Partially meets.
Criterion: Assigning resources to all activities;
February 2009: Does not meet;
July 2009: Does not meet.
Criterion: Establishing the duration of all activities;
February 2009: Partially meets;
July 2009: Mostly meets.
Criterion: Integrating schedule activities horizontally and vertically;
February 2009: Partially meets;
July 2009: Mostly meets.
Criterion: Establishing the critical path for all activities;
February 2009: Partially meets;
July 2009: Mostly meets.
Criterion: Identifying float between activities;
February 2009: Partially meets;
July 2009: Partially meets.
Criterion: Conducting a schedule risk analysis;
February 2009: Does not meet;
July 2009: Does not meet.
Criterion: Updating the schedule using logic and durations to determine
the dates;
February 2009: Partially meets;
July 2009: Mostly meets.
Source: GAO assessment of KCP's relocation schedule plan as of February
and July 2009.
[A] We did not assess this best practice in February 2009 because we
needed KCP to first clarify details on the data we received. We
obtained additional data and clarification for the July 2009
assessment.
[End of table]
The timely implementation of KCP's relocation schedule is critical to
ensure that the relocation occurs on time and does not risk disruption
of component production. In particular, the relocation is scheduled to
occur during a large production run for the W76 life extension program,
which began 2 years ago and is scheduled to last at least 10 more
years. An NNSA W76 program manager stated that the relocation was
planned without substantial input from him and that KCP may have missed
opportunities to reduce risks associated with the relocation. For
example, if officials had delayed the relocation by 2 years as he would
have recommended, KCP could have reduced potential disruptions to the
life extension program for the W76 nuclear warhead. Moreover, the
program manager stated that any schedule delays during the relocation
will likely cascade to an already tight production and delivery
schedule.
KCP Has Begun Taking Steps to Mitigate Some Outsourcing Risks but Could
Better Safeguard Technologies That Pose Nuclear Proliferation Risks:
KCP has begun taking steps to address outsourcing risks, such as
potential interruptions to supply sources; unanticipated price
increases; and quality assurance problems, including counterfeiting and
sabotage. However, KCP lacks a formal, risk-based approach to
identifying and mitigating risks posed by components and technologies,
including weapons-related design drawings; unique production processes;
and information that although mostly unclassified, could be used by
adversaries to develop or advance their nuclear capabilities.
KCP Has Begun Taking Steps to Mitigate Many Risks of Outsourcing:
Sandia design engineers that we interviewed identified several general
risks of outsourcing that could jeopardize the quality or safety of
nuclear weapons or affect KCP's schedule or costs, and KCP has begun
taking steps that seek to mitigate many of those risks. Specifically:
* Loss of a supplier. Sandia officials stated that relying on one
supplier to produce a particular component can be risky because if a
supplier can no longer produce components for KCP because of business
failures, loss of interest in working with KCP, a natural disaster, or
other reasons, production may be delayed while KCP identifies an
alternative supplier or reestablishes production capabilities on-site.
To mitigate this risk, KCP is developing a pool of capable suppliers
for outsourced components so that it can quickly move production to
another qualified supplier, if necessary. For example, when KCP
officials decided to outsource a plating process--the process of
coating electrical and mechanical products to improve their mechanical
properties and protect against corrosion--they identified 1 primary
supplier and 4 backup suppliers out of a potential pool of more than
2,000 suppliers that could be called upon if the primary supplier could
no longer meet KCP's needs. KCP officials told us that they also review
potential suppliers' financial stability and eliminate those companies
with financial concerns from consideration.
* Price increases. According to Sandia officials, suppliers could
increase their prices, which could cause an unanticipated increase in
KCP's manufacturing costs. To mitigate this risk, KCP officials told us
that they include cost thresholds in their long-term purchase
agreements and validate the reasonableness of the component price by
comparing it with those of direct competition.
* Quality assurance problems--including counterfeiting and sabotage.
Sandia officials stated that KCP is likely to have less direct control
over outsourced production processes, which could lead to quality
assurance problems, including an increased risk of counterfeiting and
sabotage. KCP has, on occasion, experienced poor quality results from
suppliers, which has required rework or changes in suppliers. Sandia
officials also stated that they are increasingly concerned about the
potential for KCP to unintentionally purchase counterfeit parts. For
example, an expansive black market exists for some microelectronics,
particularly in Southeast Asia. Sandia officials stated that
counterfeit parts are becoming increasingly more sophisticated, thereby
requiring more expertise to detect. Sandia officials also stated that
suppliers may sabotage a component to undermine the reliability of a
nuclear weapon. To mitigate these risks, KCP officials, sometimes
accompanied by design engineers, have conducted periodic quality
reviews, including scheduled and unannounced visits to some suppliers'
production sites. According to KCP officials, the frequency and type of
these reviews depends on, among other things, the components' degree of
customization and the ease of inspection--in some cases, components
must be destroyed while undergoing inspection, which is known as
destructive testing. KCP officials have reportedly observed some
suppliers' production processes and overall quality of operations to
verify that suppliers adhere to industry standards and follow proper
production techniques, such as using appropriate levels of electrical
voltage when manufacturing certain components. KCP officials also have
tested components for problems with quality, including counterfeiting
and sabotage. However, Sandia officials stated that testing might not
always effectively reveal counterfeit parts or attempted sabotage.
Although KCP officials said they do not outsource components that have
the potential for sabotage that their tests cannot detect, KCP's
efforts to restrict outsourcing of these components is not infallible.
Although KCP's outsourcing process considers the security of a
component and there is no evidence that sabotage has occurred in any
components KCP has procured, KCP's outsourcing process lacks criteria
and steps for determining and mitigating the risk of a component being
counterfeited or sabotaged--a crucial feature of an effective risk-
based approach. KCP officials have previously outsourced highly
customized and preassembled components that cannot be easily inspected,
potentially increasing the chance of counterfeited or sabotaged
components going undetected.
KCP Has Not Conducted a Systematic Review to Identify Outsourced
Technologies That Pose Nuclear Proliferation Risks:
KCP has not implemented a systematic review process to identify
specific components, technologies, and information that although not
considered to be classified national security information, are subject
to export controls and could be used to advance the nuclear
capabilities of adversaries. Although DOE guidance states that KCP
should conduct a review to identify the components, technology, and
information that could potentially advance the nuclear capabilities of
potential adversaries, KCP and NNSA's site office have not conducted
such a review. KCP and NNSA officials stated that they have not
conducted such a review because NNSA's current interpretation of export
control regulations is that all components used in nuclear weapons
should be considered subject to the regulations. If this were not the
case, the officials stated that it would be both difficult and time-
consuming to make individual export control determinations for each of
the many components produced or outsourced at KCP given the officials'
perception of the lack of clarity in the regulations and would add
little value to their current approach. Specifically, DOE issued
guidance in 1999 to help DOE and its contractors to implement a
consistent policy regarding transfers of unclassified equipment,
materials, and technology that could adversely affect U.S. security or
lead to the proliferation of weapons of mass destruction. This guidance
specifies the need for an export control review to identify such
equipment, materials, and technology, among other things, that could
pose proliferation risks.[Footnote 24] NNSA officials stated that
although these guidelines are not requirements, they would be
appropriate for KCP to use in its outsourcing decisions. Furthermore,
the DOE guidance states that the NNSA site office manager at KCP is
responsible for ensuring that KCP performs export control reviews.
As outsourcing increases and additional individuals gain access to
nuclear weapons design and production information, potential
adversaries could gain access to information that could be used to
advance their own nuclear capabilities. KCP officials estimate that
about 10 percent of the components KCP produces or procures would
likely be considered high risk if a program of review existed, and
acknowledged that they have not conducted a review to systematically
evaluate the level of risk for each component. Instead, KCP officials
stated that they treat each component and the associated design
information as if they pose equal proliferation risks and are subject
to International Traffic in Arms Regulations--the regulations
controlling the exports of munitions items and technologies.[Footnote
25] As such, items that pose little apparent risk of contributing to
potential adversaries' development of nuclear weapons, such as a
commercially available screw, are considered to be the same level of
risk as complex components, such as a mechanism designed to arm nuclear
weapons.
As a precautionary measure, KCP officials stated that they produce and
assemble most of the more complex and higher-level components in-house,
reserving outsourcing for components that are more commercially
available, less complex, and at lower stages of assembly. Nevertheless,
we observed that KCP officials currently outsource the production and
assembly of several components that they determined to be of higher
complexity and assumed the components were subject to export control
requirements but did not conduct a systematic assessment of the
components' actual proliferation risk. Without a systematic review
process to identify which components and technologies--including
weapons-related design drawings, unique production processes, and other
information--pose greater threats, KCP may be missing opportunities to
restrict certain outsourcing activities and mitigate the risk
associated with sharing critical information that could be used use to
develop or enhance an adversary's nuclear weapon capabilities.
Furthermore, KCP's primary export control measure rests on its
suppliers' compliance with a contract clause outlining their
responsibility to abide by export control laws and safeguard nuclear
weapon component production and design information. The contract clause
informs external suppliers of the potential applicability of export
regulations and notifies suppliers that they must report any
information that may require an export license or other forms of
approval. For example, KCP outlines expectations for its suppliers,
including to (1) disclose their intent to export a component or hire
foreign nationals that might be exposed to the component or its design-
related information and (2) fully comply with all export control laws
and regulations. In some instances, self-reporting has allowed KCP to
identify and mitigate a risk. For example, when one of KCP's domestic
suppliers moved its operations to Mexico, KCP officials were faced with
the decision whether to switch suppliers or retain the now foreign-
based supplier. To mitigate concerns about working with a foreign-based
company, KCP officials told us that they reevaluated the design of the
component and decided to continue purchasing less-sensitive parts of
the component--such as a type of connector--from that supplier, but
found another domestic-based supplier to produce other more sensitive
parts of the component--such as a particular type of cable. KCP
officials told us that they took these actions after the supplier
reported its relocation plans to KCP, as required in its contract.
However, according to Sandia officials, supplier self-reporting has not
always been a reliable approach. In another recent case, Sandia learned
that a supplier was foreign owned only after it had already procured
parts from that supplier, which led to additional costs, schedule
delays, and other problems that eventually forced Sandia to produce the
component in-house.
DOE and NNSA lack clear and up-to-date export control guidance. As a
result, NNSA has not clearly communicated to KCP its expectations of
what a systematic and consistent export control review process should
include, or ensured that the specific components, technologies, and
information that could be used to advance the nuclear capabilities of
potential adversaries are identified. For example, NNSA officials that
we spoke with noted that DOE's 1999 export control guidance is
outdated. In 2005, NNSA officials determined that DOE's guidance needed
to be updated, but the guidance revision was never completed. In
addition, because the export control guidance is not tailored for NNSA
production and laboratory sites, NNSA lacks firm criteria for
conducting oversight of export control activities. KCP officials
further explained that DOE's guidance is not helpful in interpreting
the Commerce Control List, which is made up of broad categories that
are not always specific to nuclear weapons technologies. For example,
the Commerce Control List identifies sensors as a controlled
technology; however, according to KCP officials, several items may fit
that category, including items that could be used by potential
adversaries to advance their own nuclear weapon capabilities as well as
those that would not pose such a threat, such as a simple thermometer
or rain gauge. Further, KCP officials stated that DOE's guidance does
not clearly define laboratories' and production sites' responsibilities
or provide a clear determination of who is responsible for identifying
the components that are subject to export control. In particular, both
KCP officials and design engineers told us that it is unclear whether
KCP or the laboratories should determine the level of risk and how that
risk should be communicated, such as how each design drawing should be
labeled. KCP officials suggested that if design engineers identified
the portions of the design drawing that may require more careful export
control consideration, it would help them determine effective export
risk mitigation steps. One KCP official stated that there is also
considerable risk in asserting that a component is not subject to
International Traffic in Arms Regulations, especially given the
sensitivity and risk-averse nature of the nuclear weapons community. As
a result, KCP has defaulted to treating all components as being of
equal risk and subject to these regulations and has taken no specific
actions to identify and mitigate the greatest risks.
Conclusions:
KCP has made substantial progress toward achieving NNSA's overall goals
to modernize its nonnuclear production facility and ensure continued
production of quality components essential to maintaining the U.S.
nuclear weapons stockpile. However, shortcomings in NNSA's oversight of
KCP's relocation may offer lessons for future modernization efforts at
its nuclear weapons facilities. In particular, NNSA allowed KCP to
limit its cost analysis to a 20-year life cycle that has no
relationship with known requirements of the nuclear weapons stockpile
or the useful life of a production facility that is properly
maintained, and did not require that KCP consider the full useful life
of the facility in its analysis. As a result, NNSA's financing
decisions were not as fully informed and transparent as they could have
been. If KCP had quantified potential cost savings to be realized over
the longer useful life of the facility, NNSA may have made a different
decision. Further, because NNSA has not ensured that KCP's relocation
schedule fully complies with DOE schedule development guidance and GAO-
identified scheduling best practices, there is a potential for delays.
A delay in KCP's relocation could affect the timely delivery of
replacement components needed to maintain a reliable nuclear weapons
stockpile, which, in turn, could have a detrimental effect on national
security. Moreover, DOE and NNSA lack clear and up-to-date export
control guidance that articulates NNSA's expectations of what a
systematic and consistent export control review process should include.
Because of this, KCP is not required to take--and therefore has not
taken--proactive steps to identify specific components, technologies,
and information that could be used to advance the nuclear capabilities
of potential adversaries. Furthermore, without export control
requirements that are designed specifically to meet NNSA production and
nuclear weapons design laboratory needs, and an effective mechanism for
ensuring enforcement of these requirements within NNSA, NNSA site
offices are less able to (1) mitigate the risks associated with
outsourcing components and (2) exercise effective oversight.
Recommendations for Executive Action:
We recommend that the Secretary of Energy take the following five
actions to strengthen NNSA's oversight practices and current and future
facility modernization efforts.
To improve the transparency and usefulness of cost analyses prepared
for future NNSA nuclear facilities modernization projects, we recommend
that the Secretary of Energy direct the Administrator of NNSA to ensure
that life cycle cost analyses include a thorough and balanced
evaluation of short-and long-term construction and financing
alternatives. Such analyses should consider the full useful life of the
facility rather than the 20-year requirement for GSA leases or any
predetermined length of time that might produce results that favor one
option over another.
To better manage the KCP relocation schedule, we recommend that the
Secretary of Energy direct the Administrator of NNSA to ensure that
KCP's operating contractor revise the KCP relocation schedule so that
it is consistent with DOE schedule development guidance and GAO-
identified scheduling best practices, as outlined in appendix II.
Because of the importance of mitigating the risks of outsourcing
nuclear weapons components and other information that if exported,
might allow potential adversaries to develop or advance their nuclear
capabilities, we also recommend that the Secretary of Energy direct the
Administrator of NNSA to take immediate action to:
* Assess the effectiveness of NNSA's oversight of KCP's current export
control and nonproliferation practices and, if appropriate, initiate
corrective actions to strengthen that oversight.
* In collaboration with the Departments of State and Commerce, replace
or supplement DOE's July 1999 Guidelines on Export Control and
Nonproliferation with guidelines, or another form of directive as
deemed appropriate by the agencies, that (1) clarify expectations for
export control reviews to specifically meet NNSA production and nuclear
weapon design laboratory needs and (2) contain an effective mechanism
for ensuring enforcement of these export control guidelines within
NNSA.
* Direct the KCP operating contractor to develop and implement a formal
risk-based review process in cooperation with the nuclear weapons
design laboratories that (1) identifies specific components,
technologies, production processes, and related information that if
exported, might allow potential adversaries to develop or advance their
nuclear capabilities and (2) includes steps for mitigating these risks,
particularly for considering whether or how to outsource these items.
Agency Comments and Our Evaluation:
We provided NNSA with a draft of this report for its review and
comment. In its written comments, NNSA states that our review was
thorough and that we appropriately recognized NNSA's progress toward
achieving the overall goals to modernize its production facility. NNSA
also provided additional information on its overall approach for
modernizing the KCP facility. NNSA generally agreed with our five
recommendations and outlined some initial actions that it expects to
take to address each of them.
NNSA provided its most substantive comments on our findings and
recommendations concerning export control. Specifically, although
agreeing with our three export control recommendations, NNSA stated
that it will delay action on them until an export control working group
that it created in July 2009 completes its analysis of export licensing
and other related issues. While we believe NNSA's formation of a
working group to study these export control issues is a positive first
step toward improving its export control practices, it is important
that NNSA not unduly delay taking action to mitigate nuclear
proliferation risks associated with outsourcing nuclear weapons
components and information.
Regarding our finding that KCP lacks a formal, risk-based approach to
safeguard components and technology that could be used by potential
adversaries, NNSA commented that KCP officials do not feel that
additional outsourcing increases risk or that a more rigorous review
would necessarily lead to different outsourcing decisions. However, as
our draft report noted, without knowing which components pose the
greatest risks, NNSA cannot be certain that it is focusing its efforts
to safeguard the highest-risk components and technologies in the most
effective manner.
With regard to our recommendation that NNSA assess the effectiveness of
its oversight of KCP's current export control and nonproliferation
practices, NNSA responded that the correct export control requirements
are being applied through its management and operating contract for
KCP. Specifically, the management and operating contractor (Honeywell)
uses standard export compliance clauses in supplier purchasing
agreements to put suppliers on notice as to the requirements applicable
to them. However, in our view, simply relying on the use of such
clauses is not oversight. Because NNSA has the primary responsibility
of preventing the proliferation of nuclear weapons, it is important
that NNSA consider adopting a risk-based approach that could enhance
existing export control requirements.
NNSA's comments are reprinted in appendix III.
As agreed with your offices, unless you publicly announce the contents
of this report earlier, we plan no further distribution until 30 days
from the report date. At that time, we will send copies to the
appropriate congressional committees; the Secretaries of Energy, State,
and Commerce; the Administrator of NNSA; and the Director, Office of
Management and Budget. The report also will be available at no charge
on the GAO Web site at [hyperlink, http://www.gao.gov].
If you or your staffs have any questions about this report, please
contact me at (202) 512-3841 or aloisee@gao.gov. Contact points for our
Offices of Congressional Relations and Public Affairs may be found on
the last page of this report. GAO staff who made major contributions to
this report are listed in appendix IV.
Signed by:
Gene Aloise:
Director, Natural Resources and Environment:
[End of section]
Appendix I: Objectives, Scope, and Methodology:
Our objectives were to determine (1) how the Kansas City Plant (KCP)
developed plans for modernizing its facility, (2) actions KCP has taken
actions to ensure uninterrupted production of components needed to
support the nuclear weapons stockpile during and after the transition
to the new facility, and (3) actions KCP has taken to address the risks
and potential consequences of increased outsourcing of nonnuclear
components.
To determine how KCP developed plans for modernizing the facility, we
reviewed documents from the National Nuclear Security Administration
(NNSA) and Honeywell Federal Manufacturing and Technologies
(Honeywell), which manages and operates the KCP facility for NNSA, that
describe the project's goals, approach, and rationale for key decisions
on relocating and outsourcing the production of nonnuclear components.
We also interviewed officials at NNSA's Kansas City Site Office,
Honeywell, relevant subcontractors, and component design laboratories
about KCP's relocation plans, approach, and time frames, including how
the relocation might affect continued production of high-quality
components and the risks posed by the current approach. Under our long-
standing policy of not addressing issues in ongoing litigation, we did
not evaluate KCP's analysis of relocation alternatives because a
lawsuit was filed in October 2008 that, among other things, challenged
the extent and adequacy of the Department of Energy's (DOE)
consideration of alternatives to its plans for replacing the KCP
facility.[Footnote 26]
To determine the actions KCP has taken to ensure uninterrupted
production of components needed to support the nuclear weapons
stockpile during and after the transition to the new facility, we
reviewed agency and contractor documents describing transition plans.
We talked to officials at Sandia National Laboratories (Sandia) in New
Mexico--which designs the nonnuclear components that are produced at
KCP--about the impact of KCP's plans on the quality, reliability, and
future support of the nuclear weapons stockpile. We evaluated the
reliability of KCP's relocation schedule to determine the extent to
which it captures key activities, is correctly sequenced, establishes
the duration of key activities, is integrated, and has an established
reliable critical path, among other things. We conducted an initial
assessment in February 2009, and conducted a second assessment in July
2009 to evaluate the extent to which the schedule improved over time.
We based our assessment on GAO-identified best practices associated
with effective schedule estimating,[Footnote 27] many of which are also
identified by DOE in its guidance on establishing performance
baselines.[Footnote 28] To assess KCP's schedule, we consulted with a
scheduling expert and interviewed key program officials responsible for
developing this schedule.
To determine the actions KCP has taken to address the risks and
potential consequences of increased outsourcing of nonnuclear
components, we reviewed agency and contractor documents, including
KCP's outsourcing strategy and export control process. We also reviewed
DOE's Export Control and Nonproliferation Guidelines, as well as
relevant export control laws and regulations. In addition, we
interviewed key KCP and Sandia officials to understand potential risks
associated with outsourcing and KCP's approach for mitigating these
risks, including nuclear proliferation risks. We met with NNSA site
office officials responsible for overseeing KCP nuclear
nonproliferation activities, and headquarters officials that provide
guidance and nonproliferation expertise to site offices across NNSA.
We conducted this performance audit from November 2008 through October
2009 in accordance with generally accepted government auditing
standards. Those standards require that we plan and perform the audit
to obtain sufficient, appropriate evidence to provide a reasonable
basis for our findings and conclusions based on our audit objectives.
We believe that the evidence obtained provides a reasonable basis for
our findings and conclusions based on our audit objectives.
[End of section]
Appendix II: GAO Assessment of KCP's Relocation Schedule:
Criterion: Capturing all activities;
Explanation: The schedule should reflect all activities as defined in
the program's work breakdown structure, to include activities to be
performed by both the government and its contractors;
GAO analysis - February 2009: Criteria not evaluated: The schedule
appears to contain most necessary activities; however, we were unable
to verify whether all activities were included because of incomplete
data and the need to clarify details on the data we received;
GAO follow-up analysis - July 2009: Criteria partially met: The
schedule appears to contain most necessary activities; however, a
supplemental dictionary that defines activities did not include
sufficient detail for us to conclude that the schedule includes all the
activities to be performed. The July schedule has a total of 5,592
activities.
Criterion: Sequencing all activities;
Explanation: The schedule should be planned so that it can meet
critical program dates. To meet this objective, key activities need to
be logically sequenced in the order that they are to be carried out. In
particular, activities that must finish before the start of other
activities (i.e., predecessor activities) as well as activities that
cannot begin until other activities are completed (i.e., successor
activities) should be identified. By doing so, interdependencies among
activities that collectively lead to the accomplishment of events or
milestones can be established and used as a basis for guiding work and
Sequencing all activities measuring progress;
GAO analysis - February 2009: Criteria not met: The schedule has an
excessive amount of incomplete logic-- where successor activities start
before predecessor activities have completed--and an excessive amount
of constrained tasks--which are tasks that have a specific start to
finish date. According to best scheduling practices, the schedule
should use logic and durations to reflect realistic start and
completion dates for program activities. Specifically, we found;
* 212 tasks with early start constraints--that is, a "start no earlier
than" date;
* 2,121 activities with no successor activities;
* 352 activities with no predecessor activities;
* 102 lags--which are the duration between activities that delay
successor activities; and;
* 850 negative lags--which allow the start or finish of a successor
activity to occur earlier than the start or finish of a predecessor
activity;
GAO follow-up analysis - July 2009: Criteria partially met: KCP's use
of constrained tasks has been reduced but not eliminated. Specifically,
we found that since February 2009 KCP reduced the extent to which the
following tasks were constrained:
* the number of tasks with early start constraints was reduced from 212
in February to 144 in the July schedule;
* the number of tasks with no successors was reduced from 2,121 in
February to 200;
* the number of tasks with no predecessor activities was reduced from
352 in February to 21;
* the number of lags was reduced from 102 in February to 21, although
some lags are still excessively long--from 240 to 422 days; and;
* the number of tasks with negative lags was reduced from 850 in
February to 20.
Criterion: Assigning resources to all activities;
Explanation: The schedule should reflect what resources (i.e., labor,
material, and overhead) are needed to do the work, whether all required
resources will be available when they are needed, and whether any
funding or time constraints exist;
GAO analysis - February 2009: Criteria not met: The schedule did not
include resources;
therefore, it is not clear that this schedule is feasible;
GAO follow-up analysis - July 2009: Criteria not met: KCP's July
schedule still does not include resources. Although the agency asserted
that it has other systems to track resource use and to determine future
resource needs, according to scheduling best practices, resources
should be included in the schedule.
Criterion: Establishing the duration of all activities;
Explanation: The schedule should realistically reflect how long each
activity will take to execute. In determining the duration of each
activity, the same rationale, data, and assumptions used for cost
estimating should be used. Further, these durations should be as short
as possible and they should have specific start and end dates.
Excessively long periods needed to execute an activity should prompt
further decomposition of the activity so that shorter execution
durations will result;
GAO analysis - February 2009: Criteria partially met: The schedule
included 138 activities with over 260 days' duration, which is
approximately 1 year given a 5-day calendar. In addition, we found that
KCP included 275 activities over 200 days in length. It is difficult to
manage activities of this length and to know if these are realistic
durations or how they were determined. According to best scheduling
practices, durations should be as short as possible;
GAO follow-up analysis - July 2009: Criteria mostly met: Activity
durations have been reduced, although some still remain long. For
example, KCP has since reduced the number of activities with over 260
days duration from 138 in February to 57 activities in its July
schedule. In addition, KCP has reduced the number of activities over
200 days in length from 275 in February to 204 in its July schedule.
According to KCP officials, most of the long duration activities are
well into the future and cannot be accurately decomposed until some
near-term planning activities are completed. .
Criterion: Integrating schedule activities horizontally and vertically;
Explanation: The schedule should be horizontally integrated, meaning
that it should link the products and outcomes associated with already
sequenced activities. These links are commonly referred to as handoffs
and serve to verify that activities are arranged in the right order to
achieve aggregated products or outcomes. The schedule should also be
vertically integrated, meaning that traceability exists among varying
levels of activities and supporting tasks and subtasks. Such mapping or
alignment among levels enables different groups to work to the same
master schedule;
GAO analysis - February 2009: Criteria partially met: The schedule is
not horizontally integrated. There are excessive instances of
incomplete logic where activities have no successors. In addition,
there is no evidence that the schedule is vertically traceable to other
levels of activities, supporting tasks, or subtasks;
GAO follow-up analysis - July 2009: Criteria mostly met: KCP has made
significant progress; however, because of the continued use of
constraints, lags, and incomplete logic, the schedule is still not
fully horizontally integrated. KCP has demonstrated that the schedule
is vertically integrated with supporting tasks and subtasks through an
external document.
Criterion: Establishing the critical path for all activities;
Explanation: Using scheduling software, the critical path--the longest
duration path through the sequenced list of key activities--should be
identified. The establishment of a program's critical path is necessary
for examining the effects of any activity slipping along this path.
Potential problems that may occur on or near the critical path should
also be identified and reflected in the scheduling of the time for high-
risk activities;
GAO analysis - February 2009: Criteria partially met: The critical path
appears to be logical; however, with all of the other incomplete logic,
as well as a large float value--the time that a predecessor activity
can slip before the delay affects successor activities--the critical
path is not reliable. In addition, in the February schedule, the
critical path extended to September 27, 2010, and the lease award task
was not on the critical path;
GAO follow-up analysis - July 2009: Criteria mostly met: KCP has made
progress on the critical path. In KCP's July schedule, the critical
path was extended to October 5, 2013, and the lease award task was
added, as appropriate. However, the continued incomplete logic and
large float value continue to affect the validity of the critical path.
Criterion: Identifying float between activities;
Explanation: The schedule should identify float, so that schedule
flexibility can be determined. As a general rule, activities along the
critical path typically have the least amount of float;
GAO analysis - February 2009: Criteria partially met: The schedule
calculates total float values--the time that activities can slip before
the delay affects the end date--automatically. However, there are more
than 4,800 activities with total float over 200 days. In addition, in
the February schedule, there were 390 activities with over 1,000 days
of total float. These values do not seem reasonable for a project
schedule and probably are due to the excessive use of constraints and
incomplete logic;
GAO follow-up analysis - July 2009: Criteria partially met: Progress
has been made on reducing total float values, although they remain
higher than expected. For example, KCP reduced the number of activities
with over 200 days of total float from 4,800 in February to 2,964 in
the July schedule. In addition, KCP has since reduced the number of
activities with over 1,000 days of total float from 390 to 147.
Criterion: Conducting a schedule risk analysis;
Explanation: A schedule risk analysis should be performed using a good
critical path method schedule and data about project schedule risks, as
well as statistical analysis techniques (such as Monte Carlo) to
predict the level of confidence in meeting a program's completion date.
This analysis focuses not only on critical path activities but also on
activities near the critical path, since they can potentially affect
program status;
GAO analysis - February 2009: Criteria not met: KCP has not performed a
schedule risk analysis using statistical techniques. KCP officials
reported that they have no plans to address this issue;
GAO follow-up analysis - July 2009: Criteria not met: KCP's schedule
has not been subjected to a statistical risk analysis. KCP's scheduling
team also indicated that it does not have plans to conduct statistical
analyses on the schedule. Although KCP officials stated that they have
conducted an analysis on a separate spreadsheet, it does not provide
sufficient confidence in meeting a program's completion date.
Criterion: Updating the schedule using logic and durations to determine
the start and completion dates;
Explanation: The schedule should use logic and durations in order to
reflect realistic start and completion dates for program activities.
The schedule should be continually monitored to determine when
forecasted completion dates differ from the planned dates, which can be
used to determine whether schedule variances will affect downstream
work. Maintaining the integrity of the schedule logic is not only
necessary to reflect true status, but is also required before
conducting a schedule risk analysis;
GAO analysis - February 2009: Criteria partially met: The schedule
appears to have been updated recently; however, because of the
incomplete logic and reliance on lags, the dates for future activities
are not reliable. Because the dates are not all calculated
automatically, the schedule cannot be used to monitor changes in
forecasted completion. Therefore, we could not determine with
confidence whether schedule variances will affect downstream work;
GAO follow-up analysis - July 2009: Criteria mostly met: There are
still 14 instances of incomplete logic--where successor activities
start before predecessor activities have been completed.
Source: GAO assessment of KCP's relocation schedule based on GAO-
identified best scheduling practices.
Note: During our July 2009 assessment, we learned that the software
used to conduct our February assessment had produced inaccurate
statistics. To correct this, we obtained new statistics for both
February's and July's assessments using a more reliable method.
However, the statistics shown in the February analysis have not been
verified with KCP officials. Nevertheless, KCP officials agree that the
general conclusions of our February assessment are still considered to
be valid.
[End of table]
[End of section]
Appendix III: Comments from the National Nuclear Security
Administration:
Department of Energy:
National Nuclear Security Administration:
Washington, DC 20585:
October 15, 2009
Mr. Gene Aloise:
Director, National Resources and Environment:
Governmental Accountability Office:
Washington, D.C. 20548:
Dear Mr. Aloise:
The National Nuclear Security Administration (NNSA) appreciates the
opportunity to review the Government Accountability Office's (GAO)
draft report, GAO-10-115, Nuclear Weapons: National Nuclear Security
Administration Needs to Better Manage Risks Associated with
Modernization of Its Kansas City Plant. We understand that this work
was done at the request of the Senate's Subcommittee on Energy and
Water Development, Committee on Appropriations. GAO was asked to
determine (1) how the Kansas City Plant (KCP) developed plans for
modernization; (2) the extent the plans ensure continuity of operations
in support of the stockpile during and after transition to the new
facility; (3) the extent the plans consider the consequences of
increased outsourcing of the nonnuclear components (e.g., security,
nonproliferation); and (4) the alternatives considered prior to
deciding to replace the KCP facility.
NNSA appreciates GAO recognizing that substantial progress has been
made toward achieving the overall goals to modernize its nonnuclear
production facility and ensuring that continued production of quality
components essential to maintaining the U.S. nuclear weapons stockpile.
In addition, we appreciate the thorough investigative approach taken by
GAO on this project and the professionalism of the GAO staff.
The transformation of the nonnuclear production infrastructure is a
significant first step in NNSA's overall plan to transform the Cold War-
era Nuclear Weapons Complex to a more cost effective, integrated and
interdependent Nuclear Security Enterprise. The goals of the nonnuclear
transformation are to reduce the operating footprint by more than half
(from 3.IM to 1.4M ft2) and reduce NNSA's annual operating costs for
KCP by about 25% ($100M per year). NNSA directed and endorsed a plan
with three major characteristics:
1. Strategic Sourcing and Sizing:
While KCP was already outsourcing over half of the active components,
additional outsourcing had the potential to enable reductions in
footprint, capital expenditures, operating costs, and environmental
hazards It was appropriate to examine what additional technologies
could be outsourced with acceptable risk. This analysis resulted in
decisions to increase the total number of outsourced components by
about 9% and suppliers by about 3%.
A much more significant impact on future plant size was enabled by the
planned consolidation of major manufacturing processing areas. Through
the elimination of excess capacity and redundancy of capabilities that
are no longer necessary given the full range of future stockpile
scenarios, the manufacturing footprint will be reduced from about 1.3M
square feet to just over 0.6M square feet.
2. Business Process Transformation:
NNSA recognized the unique nonnuclear production mission of KCP in 2005
and implemented a new oversight model for the facility in early 2007.
This new oversight model implemented industrial standards in lieu of
the Department of Energy (DOE) and NNSA directives, revised government
oversight, and established a new contractor relationship based on
commercial practices. These changes enabled the Maintenance &
Operations (M&O) contractor to begin aligning the indirect and fixed
costs of site operation to a more commercial model.
After benchmarking comparable operations, KCP officials set future cost
targets and implemented business process transformation plans for each
division that will achieve a $100M annual savings in operations ”
predominantly from indirect and support functions.
The business transformation is already about halfway to this goal and
will exceed the forecasted savings rate when the transformation to the
new facility is completed in Fiscal Year (FY) 2014.
3. Smaller, Modern, Adaptable Facility:
After analyzing multiple physical alternatives and funding options, and
in conjunction with the National Environmental Policy Act (NEPA)
process, NNSA selected a General Services Administration (GSA) lease as
the most appropriate means to acquire a smaller, modern, adaptable
facility to be built on an undeveloped site in south Kansas City. The
facility is being designed to have an administrative to manufacturing
space ratio equivalent to a commercial facility. It is also being
designed to enable timely and cost effective reconfigurations as
required capabilities and capacities change in the future. The facility
will be environmentally sustainable with Leadership in Energy and
Environmental Design (LEED) Gold certification and less than half the
energy consumption of the legacy building.
The buildings on the new campus have also been designed to yield high
commercial value if the future NNSA mission strategy no longer requires
the site. The choice of the GSA lease gives NNSA a wide range of future
mission options without delays, lost opportunity savings, and long-term
financial commitment associated with line item capitalization.
GAO examined all major aspects of the nonnuclear production
transformation, known as the Kansas City Responsive Infrastructure
Manufacturing & Sourcing (KCRIMS) project. Included in the scope of the
project is related work for other government agencies that is performed
in the National Secure Manufacturing Center (NSMC). The GAO report
credits KCP officials with developing extensive plans and initiating
several key actions to help ensure that the delivery of nonnuclear
components is not interrupted during the transition to the new
facility.
NNSA Response to GAO Observations:
After extensive review, GAO had no significant criticisms of the
nonnuclear transformation project itself, but did recommend three areas
for improvement. In summary, they are as follows:
1. Lease vs. Buy Life Cycle Cost Analysis: The GAO notes that the
facility cost analysis for the lease/buy decision was limited to 20
years rather than the full life expectancy of a new manufacturing
facility. A full life cycle analysis may have resulted in a decision
for federal ownership.
We acknowledge that leases can be more expensive than ownership at some
point in the life-span of a robust facility. The DOE's Office of Cost
Analysis (DOE/OCA) examined the same concern by performing an
independent review of the decision earlier this year. As
noted in the GAO report, DOE/OCA ultimately supported the lease
decision. The lease strategy requires no upfront capital which would
likely require 3-5 years to obtain through the conventional
Congressional line item funding process. This delay would result in
lost savings of $300M to $500M. It should also be noted that the
project met all criteria under OMB A-11 and A-94 for a government
operating lease.
Furthermore, NNSA does not want to commit to maintaining a nonnuclear
production facility within the Nuclear Security Enterprise for a period
beyond 20 years because the overall stockpile and enterprise strategy
could change significantly during that period.
Finally, if a longer term commitment is deemed appropriate, the
government retains the flexibility to purchase the facility at fair
market value at any time in the future. During the first site visit to
KCP, the GAO auditor even noted that using a professional developer to
manage the construction schedule and cost risk for a fixed price and
then buying the facility may be a superior business practice since the
developer rather than the government assumes the construction risks. In
summary, NNSA believes that a lease with a good financial return is
preferable to a federal ownership model that cannot be executed in the
short term, especially when federal ownership could still be enabled at
a later date.
2. Project Schedule Maturity: The GAO sponsored two assessments of the
KCRIMS integrated project plan (IPP) and concludes that the project
schedule does not fully comply with GAO and DOE best practices and
guidance for schedule development.
We acknowledge that the project schedule does not yet comply with all
of the GAO/DOE best practices, but we expect full compliance by the
time the schedule is actually baselined. The baseline will be set
within 30 days of receipt of a firm construction schedule from the
developer. For the record, the GAO and DOE guidelines are excellent
criteria for assessing the integrity of a baselined schedule. However,
such assessments should not imply an end state during the period when
the schedule is being developed.
NNSA would like to highlight the improvement in the schedule maturity
between the February and July assessments, as evidenced by Appendix II
in the report, which shows that only a small percentage of tasks do not
pass the recommended criteria. Many of these tasks are far into the
future and still lack enough resolution to comprehensively meet the
guideline criteria. As noted in the report, KCP officials are using
different management systems to allocate resources and manage risks and
they will not be included in the schedule files. The best practice
guidance does not preclude these attributes from being managed in other
ways.
The Program Management Institute recognizes that scheduling is both an
art and a science and the KCP scheduling team is following these
professional best practices. The Project Management Body of Knowledge
(PMBOK) states, "Good practice does not mean that the knowledge
described should always be applied uniformly on all projects; the
project management team is responsible for determining what is
appropriate for any given project." The KCP team believes that placing
too much emphasis on a purely mathematical approach does not yield the
most cost effective path to a viable schedule. Therefore, the team
embraces the fundamental PMBOK concept of progressive elaboration to
develop the schedule in systematic incremental steps leading to the
baselined schedule.
3. Export Control: DOE and NNSA lack clear and up-to-date export
control guidance with expectations for a systematic and consistent
export control review process. Without such, KCP may be taking
additional risks in outsourcing additional products.
NNSA contractors are required to comply with federal, state and local
regulations as part of their prime contract agreements. The
International Traffic in Arms Regulations (ITAR) and Export
Administration Regulations (EAR) are included in the federal regulation
compliance requirement. The ITAR and the EAR contain the regulatory
requirements associated with export activities related to nuclear
weapons production. The DOE Guidelines on Export Control and
Nonproliferation were developed to serve as complementary compliance
"guidelines" in support of these regulations.
In order to comply with ITAR and EAR regulatory requirements, KCP M&O
contractor utilizes export compliance clauses in supplier purchasing
agreements, which place the suppliers on notice as to the ITAR and EAR
regulatory requirements. The ITAR and EAR regulations currently do not
require that NNSA M&O contractors go beyond the export compliance
contract clause to transfer technical data to a domestic supplier
(qualifying as a U.S. person). This clause, included in all product-
related lower-tier KCP subcontracts, requires suppliers to notify KCP
for concurrence prior to applying for an export license if the supplier
deems one necessary. The KCP M&O contractor receives two to three such
requests per year.
The ITAR regulations require companies to obtain an export license when
sharing technical data with a foreign supplier or a domestic supplier
allowing foreign national access. The KCP M&O contractor submits ITAR
export license applications to the Directorate Defense Trade Controls
when an export license is required to transfer technical data. The
NNSA's Office of International Regimes & Agreements organization has
visibility to these license applications as part of the governments
interagency review process.
The export control concerns are consistent with the national theme of
recent GAO audits. The KCP M&O contractor does review security issues
prior to outsourcing decisions, of which export control is one subset.
Based on the current interpretation of State Department regulations,
all production items outsourced by KCP are considered export controlled
and treated as high risk. KCP officials do not feel that the additional
outsourcing under KCRIMS (a 9% increase in components outsourced and a
3% increase in suppliers) adds significantly to the Nation's risk
profile and also does not believe that a more rigorous review would
lead to different sourcing decisions.
The NNSA Nuclear Security Enterprise Senior Management Team created an
Export Control Working Group in July 2009 to address export licensing
and due diligence factors, e.g. marking technical data, registration,
supplier contract language, supplier control plan and training.
Recommendations from the Export Control Working Group will be shared
with the GAO upon completion.
NNSA Response to GAO Recommendations: NNSA generally agrees with the
recommendations and will take the following action:
Recommendation 1: Ensure that life cycle cost analyses include a
thorough and balanced evaluation of short and long term construction
and financing alternatives.
Response: Future NNSA projects will have the opportunity to take
advantage of the DOE/OCA to perform reviews on major facility
acquisition projects.
Recommendation 2: Ensure that KCP's operating contractor revises the
KCP relocation schedule so that it is consistent with DOE schedule
development guidance and GAO-identified scheduling best practices.
Response: NNSA concurs with the recommendation and will execute its
existing plan for the initial baselined schedule to incorporate
recognized best practices.
Recommendation 3: Assess the effectiveness of NNSA's oversight of KCP's
current export control and nonproliferation practices.
Response: NNSA asserts that the correct export control requirements are
being applied through the M&O contract. The recommendation will be
taken under advisement for potential future action following
recommendation 4 consideration.
Recommendation 4: Replace or supplement DOE's July 1999 Guidelines on
Export Control and Nonproliferation to clarify expectations for export
control reviews and develop an effective mechanism for ensuring
enforcement.
Response: NNSA will take this recommendation under advisement. The NNSA
ECWG (formed July 2009) is currently examining different aspects of
export control. Their conclusions and recommendations will impact
NNSA's actions concerning this GAO recommendation.
Recommendation 5: Direct the KCP operating contractor to develop and
implement a formal risk-based review process to assess nuclear
proliferation risks and mitigate these risks relative to component
outsourcing decisions.
Response: NNSA will take this recommendation under advisement awaiting
the analysis of the ECWG team referenced in our actions to
recommendation 4.
Again, NNSA appreciates the opportunity to provide these comments to
the GAO's draft report. Should you have any questions about this
response, please contact JoAnne Parker, Acting Director, Policy and
Internal Controls Management, at 202-586-1913.
Sincerely,
Signed by:
Michael C. Kane:
Associate Administrator for Management and Administration
[End of section]
Appendix IV: GAO Contact and Staff Acknowledgments:
GAO Contact:
Gene Aloise, (202) 512-3841 or aloisee@gao.gov:
Acknowledgments:
In addition to the contact named above, Ryan T. Coles, Assistant
Director; Antoinette Capaccio; Tisha Derricotte; Terry Dorn; David T.
Hulett; Sandra Kerr; Amanda Krause; Alison O'Neill; Christopher
Pacheco; Tim Persons; Jeff Phillips; and John Smale made key
contributions to this report.
[End of section]
Footnotes:
[1] Secretary of Energy Advisory Board, Report of the Nuclear Weapons
Complex Infrastructure Task Force: Recommendations for the Nuclear
Weapons Complex of the Future (Washington, D.C., July 13, 2005).
Although not formally part of the nuclear weapons complex
transformation, KCP aligned its modernization goals with NNSA's overall
transformation goals for the nuclear weapons complex.
[2] National Nuclear Security Administration, Complex 2030: An
Infrastructure Planning Scenario for a Nuclear Weapons Complex Able to
Meet the Threats of the 21st Century (Washington, D.C., Oct. 23, 2006).
[3] Triggered spark gaps are versatile high-voltage switches used for
medical applications that can also be used as nuclear weapons
detonators. Accelerometers are sensors and instruments used for
measuring, displaying, and analyzing acceleration and vibration.
[4] GAO, Export Controls: Fundamental Reexamination of System Is Needed
to Help Protect Critical Technologies, [hyperlink,
http://www.gao.gov/products/GAO-09-767T] (Washington, D.C.: June 4,
2009), and Military and Dual-Use Technology: Covert Testing Shows
Continuing Vulnerabilities of Domestic Sales for Illegal Export, GAO-09-
725T (Washington, D.C.: June 4, 2009).
[5] Natural Resources Defense Council v. Samuel W. Bodman, No. 1:08-cv-
01709 (D. D.C. filed Oct. 8, 2008).
[6] GAO, GAO Cost Estimating and Assessment Guide: Best Practices for
Developing and Managing Capital Program Costs, [hyperlink,
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: March 2009).
[7] Department of Energy, Performance Baseline Guide, G 413.3-5
(Washington, D.C., Sept. 12, 2008).
[8] Department of Defense, Nuclear Posture Review (Washington, D.C.,
Dec. 31, 2001). This review was required by the Floyd D. Spence
National Defense Authorization Act for Fiscal Year 2001, Pub. L. No.
106-398, § 1041, 114 Stat. 1654, 1654A-262 (2000), which directed the
Secretary of Defense, in consultation with the Secretary of Energy, to
"conduct a comprehensive review of the nuclear posture of the United
States for the next 5 to 10 years." The result of this review was DOD's
proposal for the New Triad, which significantly expanded the range of
strategic capabilities. A new Nuclear Posture Review is currently in
progress--as required by the National Defense Authorization Act for
Fiscal Year 2008, Pub. L. No. 110-181 § 1070, 122 Stat. 3, 327 (2008)-
-and a report on the results of this review is required to be submitted
to Congress in 2009.
[9] GAO, Federal Real Property: Strategy Needed to Address Agencies'
Long-standing Reliance on Costly Leasing, [hyperlink,
http://www.gao.gov/products/GAO-08-197] (Washington, D.C.: Jan. 24,
2008).
[10] The lease term may be for up to 30 years if the government owns
the underlying land.
[11] Current NNSA policy permits potentially three additional 5-year
options under this financing alternative--a total of 20 years.
[12] GAO, High-Risk Series: An Update, [hyperlink,
http://www.gao.gov/products/GAO-03-119] (Washington, D.C.: January
2003).
[13] An operating lease is a lease that meets six criteria listed in
the scorekeeping guidelines in OMB Circular A-11, app. A. Specifically,
(1) ownership of the asset remains with the lessor during the term of
the lease and is not transferred to the government at or shortly after
the end of the lease term; (2) the lease does not contain a bargain-
price purchase option; (3) the lease term does not exceed 75 percent of
the estimated economic life of the asset; (4) the asset is a general
purpose asset, it is not for a special purpose of the government, and
it is not built to the unique specifications of the government lessee;
(5) there is a private sector market for the asset; and (6) the present
value of the minimum lease payments over the life of the lease does not
exceed 90 percent of the fair market value of the asset at the
beginning of the lease term.
[14] [hyperlink, http://www.gao.gov/products/GAO-08-197].
[15] A lawsuit was filed in October 2008 that, among other things,
challenged the extent and adequacy of DOE's consideration of
alternatives to its plans for replacing the KCP facility. Natural
Resources Defense Council v. Samuel W. Bodman, No. 1:08-cv-01709 (D. D.
C. filed Oct. 8, 2008). Pursuant to its long-standing policy of not
addressing issues in ongoing litigation, GAO has not evaluated DOE's
consideration of these alternatives.
[16] Science Applications International Corporation, Relocation of Non-
Nuclear Production to an Alternate Location Business Case, prepared for
the National Nuclear Security Administration (Washington, D.C., Apr.
25, 2008).
[17] The congressional line item capital project costs were adjusted to
account for the estimated residual value of the facility after 20
years--about $130 million.
[18] GAO, Nuclear Weapons: NNSA and DOD Need to More Effectively Manage
the Stockpile Life Extension Program, [hyperlink,
http://www.gao.gov/products/GAO-09-385] (Washington, D.C.: Mar. 2,
2009).
[19] Lawrence Livermore and Los Alamos National Laboratories will also
conduct requalification activities; however, Sandia maintains a primary
role in conducting these activities.
[20] KCP officials initially expected to establish a formal baseline
for the schedule in April 2009, in conjunction with the lease award,
which did not occur at that time. Subsequently, KCP officials have
delayed establishing the schedule baseline and currently expect to have
one established by fall 2009.
[21] [hyperlink, http://www.gao.gov/products/GAO-09-3SP].
[22] Department of Energy, Performance Baseline Guide. Although there
is not a one-to-one correlation, many of the GAO-identified best
practices, are also suggested schedule development practices in DOE's
Performance Baseline Guide.
[23] In our February 2009 review, we had not completed our assessment
of whether KCP's schedule had captured all key activities because we
were missing key information and needed additional clarification. KCP
supplied additional information and clarification for our July 2009
review.
[24] Department of Energy, Office of Nonproliferation and National
Security, Office of Arms Control and Nonproliferation, Nuclear Transfer
and Supplier Policy Division, Guidelines on Export Control and
Nonproliferation, July 1999.
[25] The International Traffic in Arms Regulations appear at 22 C.F.R.
§§ 120-130 (2009).
[26] Natural Resources Defense Council v. Samuel W. Bodman, No. 1:08-
cv-01709 (D. D.C. filed Oct. 8, 2008).
[27] [hyperlink, http://www.gao.gov/products/GAO-09-3SP].
[28] Department of Energy, Performance Baseline Guide.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: