Centers for Medicare and Medicaid Services
Pervasive Internal Control Weaknesses Hindered Effective Contract Management
Gao ID: GAO-10-637T April 28, 2010
In November 2007, GAO reported significant deficiencies in internal control over certain contracts the Centers for Medicare and Medicaid Services (CMS) awarded under the Federal Acquisition Regulation (FAR). This Subcommittee and others in Congress asked GAO to perform an in-depth review of CMS's contract management practices. This testimony is based on GAO's October 2009 report on these issues and summarizes GAO's findings on the extent to which CMS (1) implemented effective control procedures over contract actions, (2) established a strong contract management control environment, and (3) implemented GAO's 2007 recommendations. GAO used a statistical random sample of 2008 CMS contract actions to assess CMS internal control procedures. The results were projected to the population of 2008 CMS contract actions. GAO reviewed contract file documentation and interviewed senior acquisition management officials.
GAO reported in October 2009 that pervasive deficiencies in CMS contract management internal control increased the risk of improper payments or waste. Specifically, based on a statistical random sample of 2008 CMS contract actions, GAO estimated that at least 84.3 percent of fiscal year 2008 contract actions contained at least one instance where a key control was not adequately implemented. For example, CMS used cost reimbursement contracts without first ensuring that the contractor had an adequate accounting system, as required by the FAR. These deficiencies were due in part to a lack of agency-specific policies and procedures to help ensure proper contracting expenditures. These control deficiencies stemmed from a weak overall control environment characterized primarily by inadequate strategic planning for staffing and funding resources. CMS also did not accurately capture data on the nature and extent of its contracting, hindering CMS's ability to manage its acquisition function by identifying areas of risk. Finally, CMS did not track, investigate, and resolve contract audit and evaluation findings for purposes of cost recovery and future award decisions. A positive control environment sets the tone for the overall quality of internal control and provides the foundation for effective contract management. Without a strong control environment, the specific control deficiencies GAO identified will likely persist. As of the date of GAO's October 2009 report, CMS had not substantially addressed seven of the nine recommendations made by GAO in 2007 to improve internal control over contracting and payments to contractors. To the extent that CMS has continuing weaknesses in contracting activities, it will continue to put billions of taxpayer dollars at risk of improper payments or waste.
GAO-10-637T, Centers for Medicare and Medicaid Services: Pervasive Internal Control Weaknesses Hindered Effective Contract Management
This is the accessible text file for GAO report number GAO-10-637T
entitled 'Centers For Medicare And Medicaid Services: Pervasive
Internal Control Weaknesses Hindered Effective Contract Management'
which was released on April 28, 2010.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the Ad Hoc Subcommittee on Contracting Oversight, Committee on
Homeland Security and Governmental Affairs, U.S. Senate:
United States Government Accountability Office:
GAO:
For Release on Delivery:
Expected at 2:30 p.m. EDT:
Wednesday, April 28, 2010:
Centers For Medicare And Medicaid Services:
Pervasive Internal Control Weaknesses Hindered Effective Contract
Management:
Statement of Kay L. Daly:
Director:
Financial Management and Assurance:
GAO-10-637T:
GAO Highlights:
Highlights of GAO-10-637T, a testimony before the Ad Hoc Subcommittee
on Contracting Oversight, Committee on Homeland Security and
Governmental Affairs, U.S. Senate.
Why GAO Did This Study:
In November 2007, GAO reported significant deficiencies in internal
control over certain contracts the Centers for Medicare and Medicaid
Services (CMS) awarded under the Federal Acquisition Regulation (FAR).
This Subcommittee and others in Congress asked GAO to perform an in-
depth review of CMS‘s contract management practices. This testimony is
based on GAO‘s October 2009 report on these issues and summarizes
GAO‘s findings on the extent to which CMS (1) implemented effective
control procedures over contract actions, (2) established a strong
contract management control environment, and (3) implemented GAO‘s
2007 recommendations.
GAO used a statistical random sample of 2008 CMS contract actions to
assess CMS internal control procedures. The results were projected to
the population of 2008 CMS contract actions. GAO reviewed contract
file documentation and interviewed senior acquisition management
officials.
What GAO Found:
GAO reported in October 2009 that pervasive deficiencies in CMS
contract management internal control increased the risk of improper
payments or waste. Specifically, based on a statistical random sample
of 2008 CMS contract actions, GAO estimated that at least 84.3 percent
of fiscal year 2008 contract actions contained at least one instance
where a key control was not adequately implemented. For example, CMS
used cost reimbursement contracts without first ensuring that the
contractor had an adequate accounting system, as required by the FAR.
These deficiencies were due in part to a lack of agency-specific
policies and procedures to help ensure proper contracting expenditures.
These control deficiencies stemmed from a weak overall control
environment characterized primarily by inadequate strategic planning
for staffing and funding resources. CMS also did not accurately
capture data on the nature and extent of its contracting, hindering
CMS‘s ability to manage its acquisition function by identifying areas
of risk. Finally, CMS did not track, investigate, and resolve contract
audit and evaluation findings for purposes of cost recovery and future
award decisions. A positive control environment sets the tone for the
overall quality of internal control and provides the foundation for
effective contract management. Without a strong control environment,
the specific control deficiencies GAO identified will likely persist.
As of the date of GAO‘s October 2009 report, CMS had not substantially
addressed seven of the nine recommendations made by GAO in 2007 to
improve internal control over contracting and payments to contractors.
Table: GAO‘s 2009 Assessment of CMS Actions to Address Prior
Recommendations:
GAO recommendation: 1. Develop policies for pre-award contract
activities;
GAO assessment: No action taken.
GAO recommendation: 2. Develop policies regarding cognizant federal
agency responsibilities;
GAO assessment: Actions insufficient.
GAO recommendation: 3. Develop policies that clarify roles and
responsibilities during the invoice review process;
GAO assessment: Completed.
GAO recommendation: 4. Develop guidelines regarding sufficient detail
to support contractor invoices;
GAO assessment: No action taken.
GAO recommendation: 5. Establish criteria for negative certification
for payment of invoices;
GAO assessment: No action taken.
GAO recommendation: 6. Provide training on the invoice review policies;
GAO assessment: Actions insufficient.
GAO recommendation: 7. Develop a centralized tracking mechanism for
employee training;
GAO assessment: Completed.
GAO recommendation: 8. Develop a plan to reduce the backlog of
contracts eligible for closeout;
GAO assessment: Actions insufficient.
GAO recommendation: 9. Review the questionable payments identified in
GAO‘s 2007 report;
GAO assessment: Actions insufficient.
Source: GAO. See GAO-10-60 for further details.
[End of table]
To the extent that CMS has continuing weaknesses in contracting
activities, it will continue to put billions of taxpayer dollars at
risk of improper payments or waste.
What GAO Recommends:
GAO‘s October 2009 report included 10 recommendations to improve
oversight and strengthen CMS‘s control environment and reaffirmed 7
recommendations from our November 2007 report. CMS concurred with the
new recommendations, but generally disagreed with GAO‘s assessment of
progress on the 2007 recommendations. GAO‘s analysis confirmed only
limited progress at that time.
View [hyperlink, http://www.gao.gov/products/GAO-10-637T] or key
components. For more information, contact Kay L. Daly at (202) 512-
9095 or dalykl@gao.gov.
[End of section]
Madam Chairman and Members of the Subcommittee:
I am pleased to be here today to discuss contract management at the
Centers for Medicare and Medicaid Services (CMS), a component of the
Department of Health and Human Services (HHS). CMS administers
Medicare and Medicaid, two programs included on our high-risk list,
[Footnote 1] and other programs such as the State Children's Health
Insurance Program. CMS relies extensively on contractors to assist in
carrying out its basic mission, including program administration,
management, and oversight of its health programs. In fiscal year 2008,
the most recent fiscal year for which data were available at the time
we completed our work, CMS reported that it obligated $3.6 billion
under contracts for a variety of goods and services. CMS's
acquisitions include contracts to administer, oversee, and audit
claims made under the Medicare program; provide information technology
systems; provide program management and consulting services; and
operate the 1-800 Medicare help line.
In November 2007, we reported[Footnote 2] pervasive deficiencies in
internal control over certain contracts used by CMS for start-up
administrative services to implement programs enacted under the
Medicare Prescription Drug, Improvement, and Modernization Act of 2003
(MMA).[Footnote 3] We reported that CMS's internal control
deficiencies resulted in millions of dollars of questionable payments
to certain contractors, primarily because CMS did not obtain adequate
support for billed costs. Internal control--the plans, methods, and
procedures used to meet missions, goals, and objectives--is the first
line of defense in safeguarding assets and preventing and detecting
fraud and errors and helps government program managers achieve desired
results through effective stewardship of public resources.
Because of concerns about the implications that these weaknesses may
have on all CMS contracts generally subject to the requirements of the
Federal Acquisition Regulation (FAR),[Footnote 4] we were asked to
perform a comprehensive, in-depth review of internal controls over
CMS's contract management practices. My remarks today are based on the
findings and recommendations included in our subsequent report issued
in October 2009.[Footnote 5] That report addressed the extent to which
(1) CMS implemented effective internal control procedures over
contract actions to help ensure proper contracting expenditures and
(2) CMS established a strong control environment for contract
management. Our report also discussed the extent to which CMS
implemented the recommendations we made in 2007 to improve internal
control over contracting and payments to contractors. For this
testimony, because of the relatively short time between the request to
testify and the hearing date, we did not have sufficient time to
update the status of CMS's actions to implement our prior
recommendations.
Scope and Methodology:
To address the extent to which CMS implemented control procedures over
contract actions, we focused on contracts that were generally subject
to the FAR (i.e., FAR-based),[Footnote 6] which represented about $2.5
billion, or about 70 percent, of total obligations awarded in fiscal
year 2008. The FAR is the governmentwide regulation containing the
rules, standards, and requirements for the award, administration, and
termination of government contracts. Based on the standards for
internal control,[Footnote 7] FAR requirements, and agency policies,
we identified and evaluated 11 key internal control procedures
[Footnote 8] over contract actions, ranging from ensuring contractors
had adequate accounting systems prior to the use of a cost
reimbursement contract to certifying invoices for payment. Contract
actions include new contract awards and modifications to existing
contracts. We conducted our tests on a statistically random sample
[Footnote 9] of 102 FAR-based contract actions CMS made in fiscal year
2008 and projected the results of our statistical sample
conservatively by reporting the lower bound of our two-sided, 95
percent confidence interval. We tested a variety of contract actions
including a range of dollars obligated, different contract types
(fixed price, cost reimbursement, etc.), and the types of goods and
services procured. The actions in the sample ranged from a $1,000 firm-
fixed price contract for newspapers to a $17.5 million modification of
an information technology contract valued at over $500 million. For
each contract action in the sample, we determined if the 11 key
internal control procedures were implemented by reviewing the contract
file supporting the action and, where applicable, by obtaining
additional information from the contracting officer or specialist or
senior acquisition management. We also tested the reliability of the
data contained in CMS's two acquisition databases.
To address the extent to which CMS established a strong control
environment for contract management, we obtained and reviewed
documentation regarding contract closeout, acquisition planning, and
other management information and interviewed officials in the Office
of Acquisition and Grants Management (OAGM) about its contract
management processes. We also evaluated the extent to which CMS had
addressed recommendations we made in our 2007 report.[Footnote 10] We
used the internal control standards as a basis for our evaluation of
CMS's contract management control environment. Appendix I of our
October 2009 report provides additional details of our scope and
methodology.
This testimony is based on our October 2009 performance audit, which
was conducted from July 2008 to September 2009 in accordance with
generally accepted government auditing standards. Those standards
require that we plan and perform the audit to obtain sufficient,
appropriate evidence to provide a reasonable basis for our findings
and conclusions based on our audit objectives. We believe that the
evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives.
Background:
Except for certain Medicare claims processing contracts, CMS contracts
are generally required to be awarded and administered in accordance
with general government procurement laws[Footnote 11] and regulations
such as the FAR; the Health and Human Services Acquisition Regulations
(HHSAR);[Footnote 12] the Cost Accounting Standards (CAS);[Footnote
13] and the terms of the contract.
Since 1998, CMS's obligations to fiscal intermediaries, carriers, and
Medicare Administrative Contractors (contractors that primarily
process Medicare claims) have decreased approximately 16 percent. In
contrast, obligations for other-than-claims processing contract
activities, such as the 1-800 help line, information technology and
financial management initiatives, and program management and
consulting services, have increased 466 percent. These trends may be
explained in part by recent changes to the Medicare program, including
the movement of functions, such as the help line, data centers, and
certain financial management activities, from the fiscal
intermediaries and carriers to specialized contractors.
MMA required CMS to transition its Medicare claims processing
contracts, which generally did not follow the FAR, to the FAR
environment through the award of contracts to Medicare Administrative
Contractors. CMS projected that the transition, referred to as
Medicare contracting reform, would produce administrative cost savings
due to the effects of competition and contract consolidation as well
as produce Medicare trust fund savings due to a reduction in the
amount of improper benefit payments. Additionally, the transition
would subject millions of dollars of CMS acquisitions to the rules,
standards, and requirements for the award, administration, and
termination of government contracts in the FAR. Obligations to the new
Medicare Administrative Contractors were first made in fiscal year
2007. CMS is required to complete Medicare contracting reform by 2011.
As of September 1, 2009, 19 contracts had been awarded[Footnote 14] to
Medicare Administrative Contractors, totaling about $1 billion in
obligations.
The Standards for Internal Control in the Federal Government[Footnote
15] provide the overall framework for establishing and maintaining
internal control and for identifying and addressing areas at greatest
risk of fraud, waste, abuse, and mismanagement. These standards
provide that--to be effective--an entity's management should establish
both a supportive overall control environment and specific control
activities directed at carrying out its objectives. As such, an
entity's management should establish and maintain an environment that
sets a positive and supportive attitude towards control and
conscientious management. A positive control environment provides
discipline and structure as well as the climate supportive of quality
internal control, and includes an assessment of the risks the agency
faces from both external and internal sources. Control activities are
the policies, procedures, techniques, and mechanisms that enforce
management's directives and help ensure that actions are taken to
address risks. The standards further provide that information should
be recorded and communicated to management and oversight officials in
a form and within a time frame that enables them to carry out their
responsibilities. Finally, an entity should have internal control
monitoring activities in place to assess the quality of performance
over time and ensure that the findings of audits and other reviews are
promptly resolved.
Control activities include both preventive and detective controls.
Preventive controls--such as invoice review prior to payment--are
controls designed to prevent errors, improper payments, or waste,
while detective controls--such as incurred cost audits--are designed
to identify errors or improper payments after the payment is made. A
sound system of internal control contains a balance of both preventive
and detective controls that is appropriate for the agency's
operations. While detective controls are beneficial in that they
identify funds that may have been inappropriately paid and should be
returned to the government, preventive controls such as accounting
system reviews[Footnote 16] and invoice reviews help to reduce the
risk of improper payments or waste before they occur. A key concept in
the standards is that control activities selected for implementation
be cost beneficial. Generally it is more effective and efficient to
prevent improper payments. A control activity can be preventive,
detective, or both based on when the control occurs in the contract
life cycle.
Additional, detailed background information is available in our
related report, GAO-10-60.
Pervasive Deficiencies in Control Procedures at the Contract Level
Increase the Risk of Improper Payments or Waste:
Our October 2009 report identified pervasive deficiencies in internal
control over contracting and payments to contractors. Specifically, as
a result of our work, we estimated that at least 84.3 percent[Footnote
17] of FAR-based contract actions made by CMS in fiscal year 2008
contained at least one instance in which 1 of 11 key controls was not
adequately implemented. Not only was the number of internal control
deficiencies widespread, but also many contract actions had more than
one deficiency. We estimated that at least 37.2 percent[Footnote 18]
of FAR-based contract actions made in fiscal year 2008 had three or
more instances in which a key control was not adequately implemented.
The internal control deficiencies occurred throughout the contracting
process and increased the risk of improper payments or waste. These
deficiencies were due in part to a lack of agency-specific policies
and procedures to ensure that FAR requirements and other control
objectives were met. CMS also did not take appropriate steps to ensure
that existing policies were properly implemented or maintain adequate
documentation in its contract files. Further, CMS's Contract Review
Board process had not been properly or effectively implemented to help
ensure proper contract award actions.[Footnote 19] These internal
control deficiencies are a manifestation of CMS's weak overall control
environment, which is discussed later. Additional, detailed
information on our testing of key internal controls is available in
our October 2009 report.
The high percentage of deficiencies indicates a serious failure of
control procedures over FAR-based acquisitions, thereby creating a
heightened risk of improper payments or waste. Highlights of the
control deficiencies we noted included the following.
* We estimated that at least 46.0 percent of fiscal year 2008 CMS
contract actions did not meet the FAR requirements applicable to the
specific contract type awarded.[Footnote 20] For example, we found
that CMS used cost reimbursement contracts without first ensuring that
the contractor had an adequate accounting system. According to the
FAR, a cost reimbursement contract may be used only when the
contractor's accounting system is adequate for determining costs
applicable to the contract.[Footnote 21] To illustrate, of the
contract awards in our sample, we found nine cases in which cost
reimbursement contracts were used without first ensuring that the
contractor had an adequate accounting system. In addition to these
nine cases, during our review of contract modifications we observed
another six cases in which cost reimbursement contracts were used even
though CMS was aware that the contractor's accounting system was
inadequate at the time of award. In one instance, the contracting
officer was aware that a contractor had an inadequate accounting
system resulting from numerous instances of noncompliance with
applicable Cost Accounting Standards. Using a cost reimbursement
contract when a contractor does not have an adequate accounting system
hinders the government's ability to fulfill its oversight duties
throughout the contract life cycle and increases risk of improper
payments and the risk that costs billed cannot be substantiated during
an audit.
* We estimated that for at least 40.4 percent of fiscal year 2008
contract actions, CMS did not have sufficient support for provisional
indirect cost rates[Footnote 22] nor did it identify instances when a
contractor billed rates higher than the rates that were approved for
use.[Footnote 23] Provisional indirect cost rates provide agencies
with a mechanism by which to determine if the indirect costs billed on
invoices are reasonable for the services provided until such time that
final indirect cost rates can be established, generally at the end of
the contractor's fiscal year. When the agency does not maintain
adequate support for provisional indirect rates, it increases its risk
of making improper payments.
* We estimated that for at least 52.6 percent of fiscal year 2008
contract actions, CMS did not have support for final indirect cost
rates or support for the prompt request of an audit of indirect costs.
[Footnote 24] The FAR states that final indirect cost rates, which are
based on a contactor's actual indirect costs incurred during a given
fiscal year, shall be used in reimbursing indirect costs under cost
reimbursement contracts.[Footnote 25] The amounts a contractor billed
using provisional indirect cost rates are adjusted annually for final
indirect cost rates, thereby providing a mechanism for the government
to timely ensure that indirect costs are allowable and allocable to
the contract. CMS officials told us that they generally adjust for
final indirect cost rates during contract closeout at the end of the
contract performance rather than annually mainly due to the cost and
effort the adjustment takes. However, CMS did not promptly close out
its contracts and had not made progress in reducing the backlog of
contracts eligible for closeout. Specifically, in 2007, we reported
that CMS's backlog was 1,300 contracts, of which 407 were overdue for
closeout as of September 30, 2007. This backlog continued to increase,
and CMS officials stated that as of July 29, 2009, the total backlog
of contracts eligible for closeout was 1,611, with 594 overdue based
on FAR timing standards.[Footnote 26] Not annually adjusting for final
indirect cost rates increases the risk that CMS is paying for costs
that are not allowable or allocable to the contract. Furthermore,
putting off the control activity until the end of contract performance
increases the risk of overpaying for indirect costs during contract
performance and may make identification or recovery of any unallowable
costs during contract closeout more difficult due to the passage of
time.
* We estimated that for at least 54.9 percent of fiscal year 2008
contract actions, CMS did not promptly perform or request an audit of
direct costs.[Footnote 27] Similar to the audit of indirect costs,
audits of direct costs allow the government to verify that the costs
billed by the contractor were allowable, reasonable, and allocable to
the contract. Not annually auditing direct costs increases the risk
that CMS is paying for costs that are not allowable or allocable to
the contract.
* We estimated that for at least 59.0 percent of fiscal year 2008
contract actions, the project officer did not always certify the
invoices.[Footnote 28] CMS's Acquisition Policy Notice 16-01 requires
the project officer to review each contractor invoice and recommend
payment approval or disapproval to the contracting officer. This
review is to determine, among other things, if the expenditure rate is
commensurate with technical progress and whether all direct cost
elements are appropriate, including subcontracts, travel, and
equipment. We noted in our 2007 report[Footnote 29] that CMS used
negative certification--a process whereby it paid contractor invoices
without knowing whether they were reviewed and approved--in order to
ensure invoices were paid in a timely fashion. In October 2009 we
reported that negative certification continued to be CMS's policy to
process contractor invoices for payment. This approach, however,
significantly reduces the incentive for contracting officers,
specialists, and project officers to review the invoice prior to
payment. For example, in one case, although a contractor submitted
over 100 invoices for fiscal year 2008,[Footnote 30] only 8 were
certified by the project officer. The total value of the contract
through January 2009 was about $64 million. In addition, based on a
cursory review of the fiscal year 2008 invoices submitted for payment,
we found instances in which the contracting officer or specialist did
not identify items that were inconsistent with the terms of the
contract or acquisition regulations. For example, we found two
instances where the contractor billed, and CMS paid, for items
generally disallowed by HHSAR.[Footnote 31] Reviewing invoices prior
to payment is a preventive control that may result in the
identification of unallowable billings, especially on cost
reimbursement and time and materials invoices, before the invoices are
paid. CMS increases its risk of improper payments when it does not
properly review and approve invoices prior to payment.
Weak Control Environment Hindered CMS's Ability to Manage Its FAR-
based Acquisition Process:
The control deficiencies we identified in the statistical sample
discussed in our October 2009 report stemmed from a weak overall
control environment. CMS's control environment was characterized by
the lack of (1) strategic planning to identify necessary staffing and
funding; (2) reliable data for effectively carrying out contract
management responsibilities; and (3) follow-up to track, investigate,
and resolve contract audit and evaluation findings for purposes of
cost recovery and future award decisions. A positive control
environment sets the tone for the overall quality of an entity's
internal control, and provides the foundation for an entity to
effectively manage contracts and payments to contractors. Without a
strong control environment, the control deficiencies we identified
will likely persist. Following is a summary of the weaknesses we found
in CMS's overall control environment:
* Limited analysis of contract management workforce and related
funding needs. OAGM management had not analyzed its contract
management workforce and related funding needs through a
comprehensive, strategic acquisition workforce plan. Such a plan is
critical to help manage the increasing acquisition workload and meet
its contracting oversight needs. We reported in November 2007[Footnote
32] that staff resources allocated to contract oversight had not kept
pace with the increase in CMS contract awards. In our 2009 report, we
found a similar trend continued into 2008. While the obligated amount
of contract awards had increased 71 percent since 1998, OAGM staffing
resources--its number of full time equivalents (FTE)--had increased 26
percent. This trend presents a major challenge to contract award and
administration personnel who must deal with a significantly increased
workload without additional support and resources. In addition,
according to its staff and management, OAGM faced challenges in
meeting the various audit requirements necessary to ensure adequate
oversight of contracts that pose more risk to the government,
specifically cost reimbursement contracts, as well as in performing
the activities required of a cognizant federal agency (CFA).[Footnote
33]
Although officials told us they could use more audit funding, we found
that OAGM management had yet to determine what an appropriate funding
level should be. Without knowing for which contractors additional CFA
oversight was needed, CMS did not have reliable information on the
number of audits and reviews that must be performed annually or the
depth and complexity of those audits. Without this key information,
CMS could not estimate an adequate level of needed audit funding. The
risks of not performing CFA duties are increased by the fact that
other federal agencies that use the same contractors rely on the
oversight and monitoring work of the CFA. A shortage of financial and
human resources creates an environment that introduces vulnerabilities
to the contracting process, hinders management's ability to sustain an
effective overall control environment, and ultimately increases risk
in the contracting process.
* Lack of reliable contract management data. Although CMS had
generally reliable information on the basic attributes of each
contract action, such as vendor name and obligation amount, CMS lacked
reliable management information on other key aspects of its FAR-based
contracting operations. For example, in our October 2009 report we
identified acquisition data errors related to the number of certain
contract types awarded, the extent of competition achieved, and total
contract value. Standards for internal control provide that for an
agency to manage its operations, it must have relevant, reliable, and
timely information relating to the extent and nature of its
operations, including both operational and financial data, and such
information should be recorded and communicated to management and
others within the agency who need it and in a form and within a time
frame that enables them to carry out their internal control and
operational responsibilities. The acquisition data errors were due in
part to a lack of sufficient quality assurance activities over the
data entered into the acquisition databases. Without accurate data,
CMS program managers did not have adequate information to identify,
monitor, and correct or mitigate areas that posed a high risk of
improper payments or waste.
* Lack of follow-up to resolve contract audit and evaluation findings.
CMS did not track, investigate, and resolve contract audit and
evaluation findings for purposes of cost recovery and future award
decisions. Tracking audit and evaluation findings strengthens the
control environment in part because it can help assure management that
the agency's objectives are being met through the efficient and
effective use of the agency's resources. It can also help management
determine whether the entity is complying with applicable acquisition
laws and regulations. Contract audits and evaluations can add
significant value to an organization's oversight and accountability
structure, but only if management ensures that the results of these
audits and evaluations are promptly investigated and resolved. For
example, in an audit report dated September 30, 2008, the Defense
Contract Audit Agency[Footnote 34] questioned approximately $2.1
million of costs that CMS paid to a contractor in fiscal year 2006. As
discussed in our October 2009 report, OAGM management confirmed that
no action had been taken at that time to investigate and recover the
challenged costs.
GAO Has Made Numerous Recommendations to Improve CMS's Contract
Management Controls:
Seven of Nine GAO 2007 Recommendations Were Substantially Unresolved:
As we reported in October 2009, CMS management had not taken
substantial actions to address our 2007 recommendations to improve
internal control in the contracting process. Only two of GAO's nine
2007 recommendations had been fully addressed. Table 1 summarizes our
assessment of the status of CMS's actions to address our
recommendations.
Table 1: GAO's October 2009 Assessment of Status of CMS Actions Taken
to Address 2007 Recommendations:
GAO recommendation: 1. Develop policies for pre-award contract
activities;
GAO assessment: No action taken.
GAO recommendation: 2. Develop policies regarding cognizant federal
agency responsibilities;
GAO assessment: Actions insufficient.
GAO recommendation: 3. Develop policies that clarify roles and
responsibilities during the invoice review process;
GAO assessment: Completed.
GAO recommendation: 4. Develop guidelines regarding sufficient detail
to support contractor invoices;
GAO assessment: No action taken.
GAO recommendation: 5. Establish criteria for negative certification
for payment of invoices;
GAO assessment: No action taken.
GAO recommendation: 6. Provide training on the invoice review policies;
GAO assessment: Actions insufficient.
GAO recommendation: 7. Develop a centralized tracking mechanism for
employee training;
GAO assessment: Completed.
GAO recommendation: 8. Develop a plan to reduce the backlog of
contracts eligible for closeout;
GAO assessment: Actions insufficient.
GAO recommendation: 9. Review the questionable payments identified in
GAO‘s 2007 report;
GAO assessment: Actions insufficient.
Source: GAO. See GAO-10-60 for further details.
[End of table]
GAO Made 10 Additional Recommendations in October 2009 to Further
Improve CMS Contract Management:
In addition to reaffirming the 7 substantially unresolved 2007
recommendations, our October 2009 report included 10 recommendations
to further improve oversight and strengthen CMS's control environment.
Specifically, we made recommendations for additional procedures or
plans to address the following 10 areas:
* document compliance with FAR requirements for different contract
types;
* document provisional indirect cost rates in the contract file;
* specify what constitutes timely performance of (or request for)
audits of contractors' billed costs;
* specify circumstances for the use and content of negotiation
memorandums, including any required secondary reviews;
* specify Contract Review Board documentation, including resolution of
issues identified during the CRB reviews;
* conduct periodic reviews of contract files to ensure invoices were
properly reviewed by both the project officer and contracting officer
or specialist;
* develop a comprehensive strategic acquisition workforce plan, with
resource needs to fulfill FAR requirements for comprehensive
oversight, including CFA duties;
* revise the verification and validation plan to require all relevant
acquisition data errors be corrected and their resolution documented;
* develop procedures for tracking contract audit requests and the
resolution of audit findings; and:
* develop procedures that clearly assign roles and responsibilities
for the timely fulfillment of CFA duties.
In commenting on a draft of our October 2009 report, CMS and HHS
agreed with each of our 10 new recommendations and described steps
planned to address them. CMS also stated that the recommendations will
serve as a catalyst for improvements to the internal controls for its
contracting function. CMS also expressed concerns about our assessment
of key internal controls and disagreed with our conclusions on the
status of CMS's actions to address our November 2007 recommendations.
CMS stated its belief that "virtually all" of the errors we identified
in our statistical sample related to "perceived documentation
deficiencies." CMS also expressed concern that a reasonable amount of
time had not yet elapsed since the issuance of our November 2007
report to allow for corrective actions to have taken place.
However, as discussed in greater detail in our October 2009 report
response to agency comments, nearly 2 years had elapsed between our
November 2007 and October 2009 reports and CMS had made little
progress in addressing the recommendations from our November 2007
report. Further, a significant number of our October 2009 report
findings, including weaknesses in the control environment, were based
on observations and interviews with OAGM officials and reviews of
related documentation such as policies and strategic plans. Finally,
the deficiencies we identified negatively impact the key controls
intended to help ensure compliance with agency acquisition regulations
and the FAR.
In conclusion, Madam Chairman, while we have not updated the status of
any CMS actions to address our October 2009 findings and
recommendations, the extent to which control weaknesses in CMS's
contracting activities continue, raises questions concerning whether
CMS management has established an appropriate "tone at the top" to
effectively manage these key activities. Until CMS management
addresses our previous recommendations in this area, along with taking
action to address the additional deficiencies identified in our
October 2009 report, its contracting activities will continue to pose
significant risk of improper payments, waste, and mismanagement.
Further, the deficiencies we identified are likely to be exacerbated
by the rise in obligations for non-claims processing contract awards
as well as CMS's extensive reliance on contractors to help achieve its
mission objectives. It is imperative that CMS address its serious
contract-level control deficiencies and take action on our
recommendations to improve overall environment controls or CMS will
continue to place billions of taxpayer dollars at risk of fraud, or
otherwise improper contract payments. We commend the Subcommittee for
its continuing oversight and leadership in this important area and
believe that hearings such as the one being held today will be
critical to ensuring that CMS's continuing contract management
weaknesses are resolved without further delay and that overall risks
to the government are substantially reduced.
Madam Chairman and Members of the Subcommittee, this concludes my
prepared statement. I would be happy to answer any questions that you
may have at this time.
GAO Contacts and Acknowledgments:
For further information regarding this testimony, please contact Kay
L. Daly at (202) 512-9095 or dalykl@gao.gov. In addition, contact
points for our Offices of Congressional Relations and Public Affairs
may be found on the last page of this statement. Individuals who made
key contributions to this testimony are Marcia Carlsen and Phil
McIntyre (Assistant Directors), Sharon Byrd, Richard Cambosos,
Francine DelVecchio, Abe Dymond, John Lopez, Ron Schwenn, Omar Torres,
Ruth Walk, and Danietta Williams.
[End of section]
Footnotes:
[1] GAO, High Risk Series: An Update, [hyperlink,
http://www.gao.gov/products/GAO-09-271] (Washington, D.C.: Jan. 22,
2009).
[2] GAO, Centers for Medicare and Medicaid Services: Internal Control
Deficiencies Resulted in Millions of Dollars of Questionable Contract
Payments, [hyperlink, http://www.gao.gov/products/GAO-08-54]
(Washington, D.C.: Nov. 15, 2007).
[3] Pub. L. No. 108-173, 117 Stat. 2066 (Dec. 8, 2003).
[4] 48 C.F.R. ch. 1.
[5] GAO, Centers for Medicare and Medicaid Services: Deficiencies in
Contract Management Internal Control Are Pervasive, [hyperlink,
http://www.gao.gov/products/GAO-10-60] (Washington, D.C.: Oct. 23,
2009).
[6] Certain CMS contracts, such as the claims administration contracts
referred to as fiscal intermediaries and carriers, generally are not
subject to FAR requirements.
[7] GAO, Standards for Internal Control in the Federal Government,
[hyperlink, http://www.gao.gov/products/GAO/AIMD-00-21.3.1]
(Washington, D.C.: November 1999).
[8] We determined a control to be "key" based on our review of the
standards for internal control as well as the FAR, Health and Human
Services Acquisition Regulations, and agency policies and whether
inadequate implementation would significantly increase the risk of
improper payments or waste.
[9] We selected a stratified random sample of 102 contract actions
from a population of 2,441 total contract actions recorded in CMS's
procurement system, PRISM, during fiscal year 2008.
[10] [hyperlink, http://www.gao.gov/products/GAO-08-54].
[11] Title 41, United States Code.
[12] 48 C.F.R. ch. 3.
[13] 48 C.F.R. ch. 99. These standards are mandatory for use by all
executive agencies and by contractors and subcontractors in
estimating, accumulating, and reporting costs in connection with
pricing and administration of, and settlement of disputes concerning,
all negotiated prime contract and subcontract procurements with the
U.S. government in excess of $500,000. Certain contracts or
subcontracts are exempt from CAS, such as those that are fixed price
or those with a small business. Additionally, contractors that
received less than $50 million in net awards in the prior accounting
period are subject to only certain CAS standards, known as modified
coverage. The FAR incorporates the CAS, see 48 C.F.R. §30.101(b).
[14] Of the 19 contracts awarded, 6 were under protest and were not
yet operational as of September 1, 2009.
[15] [hyperlink, http://www.gao.gov/products/GAO/AIMD-00-21.3.1].
[16] An accounting system review is used to determine whether a
contractor's accounting system is adequate for determining costs
applicable to a contract.
[17] Based on the results of our work, we are 95 percent confident
that the percentage of contract actions that did not meet at least one
control test is at least 84.3 percent.
[18] Based on the results of our work, we are 95 percent confident
that the percentage of contract actions that did not meet three or
more control tests is at least 37.2 percent.
[19] CMS's OAGM established the Contract Review Board as a key control
procedure to help ensure contract award actions are in conformance
with law, established policies and procedures, and sound business
practices.
[20] We identified 25 contract actions to which FAR requirements
specific to the contract type awarded applied, of which 16 contract
actions did not meet the control test. Based on the results of our
work, we are 95 percent confident that the total percentage of
contract actions that did not meet the control test is at least 46.0
percent.
[21] 48 C.F.R. §§ 16.104(h), 16.301-3.
[22] The FAR states that provisional indirect cost rates shall be used
in reimbursing indirect costs such as fringe benefits or overhead
costs under cost reimbursement contracts and are used to prevent
substantial overpayment or underpayment of indirect costs. 48 C.F.R. §
42.703-1(b). Provisional indirect cost rates, sometimes called a
materials handling rate, may also be used on some time and materials
(T&M) contracts. 48 C.F.R. §§ 16.307(a)(1), 52.216-7.
[23] We identified 62 contract actions to which provisional indirect
cost rates applied, of which 36 contract actions did not meet the
control test. Based on the results of our work, we are 95 percent
confident that the total percentage of contract actions that did not
meet the control test is at least 40.4 percent.
[24] We identified 34 contract actions to which final indirect cost
rates applied, of which 23 contract actions did not meet the control
test. Based on the results of our work, we are 95 percent confident
that the total percentage of contract actions that did not meet the
control test is at least 52.6 percent.
[25] 48 C.F.R. § 42.703-1(b).
[26] 48 C.F.R. § 4.804 states that firm fixed price contracts should
be closed within 6 months; contracts requiring the settlement of
indirect costs rates, such as cost reimbursement contracts, should be
closed within 36 months; and all other contracts should be closed
within 20 months. These time frames begin in the month in which the
contracting official receives evidence of physical completion of the
contract. Generally, files for contracts using simplified acquisition
procedures should be considered closed when the contracting officer
receives evidence of receipt of property and final payment.
[27] We identified 36 contract actions to which an audit of direct
costs applied, of which 25 contract actions did not meet the control
test. Based on the results of our work, we are 95 percent confident
that the total percentage of contract actions that did not meet the
control test is at least 54.9 percent.
[28] We identified 90 contract actions to which certification of
invoices applied, of which 61 contract actions did not meet the
control test. Based on the results of our work, we are 95 percent
confident that the total percentage of contract actions that did not
meet the control test is at least 59.0 percent.
[29] [hyperlink, http://www.gao.gov/products/GAO-08-54].
[30] The contractor submitted separate invoices for different contract
line items, which resulted in the high number of invoices in 1 fiscal
year.
[31] 48 C.F.R. § 315.404-4(d)(4). The HHSAR generally disallows
facilities capital cost of money. In cases when the contractor
includes the cost in its proposal, the agency is required to reduce
the amount of the profit objective by an equivalent amount. In the two
instances where CMS paid facilities capital cost of money, the cost
was either expressly disallowed by 48 C.F.R. § 52.215-17 or the profit
objective was not reduced.
[32] [hyperlink, http://www.gao.gov/products/GAO-08-54], p. 18.
[33] A CFA is a contracting role established in the FAR. The FAR
defines the CFA as the agency responsible for establishing forward
pricing rates, final indirect cost rates (when not accomplished by a
designated contract auditor), and administering cost accounting
standards for all contracts in a business unit. 48 C.F.R. §§ 2.101.
See 48 C.F.R. §§ 42.302(a), 42.703-1, 30.601. Generally, the CFA is
the agency with the largest dollar amount of negotiated contracts,
including options, with the contractor. The CFA concept provides an
efficient way for contractors to receive a streamlined set of audits
and reviews, thereby enabling them to receive and perform government
contracts.
[34] Within the Department of Defense (DOD), the Defense Contract
Audit Agency (DCAA) performs contract audits, including those required
to fulfill DOD's responsibilities as a cognizant federal agency. When
requested and for a fee, DCAA will perform contract audits for other
agencies.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: