Nuclear Regulation
Emergency Preparedness Issues at the Indian Point 2 Nuclear Power Plant
Gao ID: GAO-03-528T March 10, 2003
After the September 11, 2001, terrorist attacks, emergency preparedness at nuclear power plants has become of heightened concern. Currently, 104 commercial nuclear power plants operate at 64 sites in 32 states and provide about 20 percent of the nation's electricity. In July 2001, GAO reported on emergency preparedness at the Indian Point 2 nuclear power plant in New York State. This testimony discusses GAO's findings and recommendations in that report and the progress the plant, the Nuclear Regulatory Commission (NRC), and the Federal Emergency Management Agency (FEMA) have made in addressing these problems. GAO also provides its thoughts on the findings of a soon-to-be-issued report (the Witt report) on emergency preparedness at Indian Point and the Millstone nuclear power plant in Connecticut, and the implications of that report for plants nationwide. Since 2001, the Entergy Corporation has assumed ownership of the Indian Point 2 plant from the Consolidated Edison Company of New York (ConEd).
In 2001, GAO reported that, over the years, NRC had identified a number of emergency preparedness weaknesses at Indian Point 2 that had gone largely uncorrected. ConEd had some corrective actions underway before a 2000 event raised the possibility of a leak of radioactively contaminated water into the environment. ConEd took other actions to address problems during this event. According to NRC, more than a year later, the plant still had problems similar to those previously identified--particularly in the pager system for activating emergency personnel. However, NRC, in commenting on a draft of GAO's report, stated that ConEd's emergency preparedness program could protect the public. Four counties responsible for responding to a radiological emergency at Indian Point 2 had, with the state and ConEd, developed a new form to better document the nature and seriousness of any radioactive release and thus avoid the confusion that occurred during the February 2000 event. Because they are the first responders in any radiological emergency, county officials wanted NRC and FEMA to communicate more with them in nonemergency situations, in addition to communicating through the states. However, NRC and FEMA primarily rely on the states to communicate with local jurisdictions. Since GAO's 2001 report, NRC has found that emergency preparedness weaknesses have continued. For example, NRC reported that, during an emergency exercise in the fall of 2002, the facility gave out unclear information about the release of radioactive materials, which had also happened during the February 2000 event. Similarly, in terms of communicating with the surrounding jurisdictions, little has changed, according to county officials. County officials told GAO that a videoconference system--promised to ensure prompt meetings and better communication between the plant's technical representatives and the counties--had not been installed. In addition, NRC and FEMA continue to work primarily with the states in nonemergency situations. Although they note that there are avenues for public participation, none of these is exclusively for the county governments. GAO did not evaluate the draft Witt report or verify the accuracy of its findings. The draft Witt report is a much larger, more technical assessment than the 2001 GAO report. While both reports point out difficulties in communications and planning inadequacies, the draft Witt report concludes that the current radiological response system and capabilities are not adequate to protect the public from an unacceptable dose of radiation in the event of a release from Indian Point, especially if the release is faster or larger than the release for which the programs are typically designed. GAO is aware that, in commenting on a draft of the Witt report, FEMA disagreed with some of the issues raised but said the report highlights several issues worth considering to improve emergency preparedness in the communities around Indian Point and nationwide. NRC concluded that the draft report gives "undue weight" to the impact of a terrorist attack.
GAO-03-528T, Nuclear Regulation: Emergency Preparedness Issues at the Indian Point 2 Nuclear Power Plant
This is the accessible text file for GAO report number GAO-03-528T
entitled 'Nuclear Regulation: Emergency Preparedness Issues at the
Indian Point 2 Nuclear Power Plant' which was released on March 10,
2003.
This text file was formatted by the U.S. General Accounting Office
(GAO) to be accessible to users with visual impairments, as part of a
longer term project to improve GAO products‘ accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
United States General Accounting Office:
GAO:
Testimony:
Before the Subcommittee on National Security, Emerging Threats and
International Relations, Committee on Government Reform, House of
Representatives:
For Release on Delivery:
Expected at 2:00 p.m.
Monday, March 10, 2003:
NUCLEAR REGULATION:
Emergency Preparedness Issues at the Indian Point 2 Nuclear Power
Plant:
Statement of Jim Wells, Director:
Natural Resources and Environment:
GAO-03-528T:
GAO Highlights:
Highlights of GAO-03-528T, a report to the Subcommittee on National
Security, Emerging Threats and International Relations, Committee on
Government Reform, House of Representatives
Why GAO Did This Study:
After the September 11, 2001, terrorist attacks, emergency
preparedness at nuclear power plants has become of heightened
concern. Currently, 104 commercial nuclear power plants operate at
64 sites in 32 states and provide about 20 percent of the nation‘s
electricity. In July 2001, GAO reported on emergency preparedness
at the Indian Point 2 nuclear power plant in New York State (Nuclear
Regulation: Progress Made in Emergency Preparedness at Indian Point
2, but Additional Improvements Needed [GAO-01-605, July 30, 2001]).
This testimony discusses GAO‘s findings and recommendations in that
report and the progress the plant, the Nuclear Regulatory Commission
(NRC), and the Federal Emergency Management Agency (FEMA) have made
in addressing these problems. GAO also provides its thoughts on the
findings of a soon-to-be-issued report (the Witt report) on
emergency preparedness at Indian Point and the Millstone nuclear
power plant in Connecticut, and the implications of that report for
plants nationwide.
Since 2001, the Entergy Corporation has assumed ownership of the
Indian Point 2 plant from the Consolidated Edison Company of New
York (ConEd).
What GAO Found:
In 2001, GAO reported that, over the years, NRC had identified a
number of emergency preparedness weaknesses at Indian Point 2 that
had gone largely uncorrected. ConEd had some corrective actions
underway before a 2000 event raised the possibility of a leak of
radioactively contaminated water into the environment. ConEd took
other actions to address problems during this event. According to
NRC, more than a year later, the plant still had problems similar to
those previously identified”particularly in the pager system for
activating emergency personnel. However, NRC, in commenting on a
draft of GAO‘s report, stated that ConEd‘s emergency preparedness
program could protect the public. Four counties responsible for
responding to a radiological emergency at Indian Point 2 had, with
the state and ConEd, developed a new form to better document the
nature and seriousness of any radioactive release and thus avoid the
confusion that occurred during the February 2000 event. Because they
are the first responders in any radiological emergency, county
officials wanted NRC and FEMA to communicate more with them in
nonemergency situations, in addition to communicating through the
states. However, NRC and FEMA primarily rely on the states to
communicate with local jurisdictions.
Since GAO‘s 2001 report, NRC has found that emergency preparedness
weaknesses have continued. For example, NRC reported that, during
an emergency exercise in the fall of 2002, the facility gave out
unclear information about the release of radioactive materials,
which had also happened during the February 2000 event. Similarly,
in terms of communicating with the surrounding jurisdictions,
little has changed, according to county officials. County officials
told GAO that a videoconference system”promised to ensure prompt
meetings and better communication between the plant‘s technical
representatives and the counties”had not been installed. In
addition, NRC and FEMA continue to work primarily with the states
in nonemergency situations. Although they note that there are
avenues for public participation, none of these is exclusively for
the county governments.
GAO did not evaluate the draft Witt report or verify the accuracy
of its findings. The draft Witt report is a much larger, more
technical assessment than the 2001 GAO report. While both reports
point out difficulties in communications and planning inadequacies,
the draft Witt report concludes that the current radiological
response system and capabilities are not adequate to protect the
public from an unacceptable dose of radiation in the event of a
release from Indian Point, especially if the release is faster or
larger than the release for which the programs are typically
designed. GAO is aware that, in commenting on a draft of the Witt
report, FEMA disagreed with some of the issues raised but said the
report highlights several issues worth considering to improve
emergency preparedness in the communities around Indian Point and
nationwide. NRC concluded that the draft report gives ’undue
weight“ to the impact of a terrorist attack.
www.gao.gov/cgi-bin/getrpt?GAO-03-528.
To view the full report, including the scope
and methodology, click on the link above.
For more information, contact Jim Wells at (202) 512-3841 or
wellsj@gao.gov.
Mr. Chairman and Members of the Subcommittee:
We are pleased to be here today to discuss emergency preparedness at
operating commercial nuclear power plants. Twenty-four years ago, in
March 1979, the accident at the Three Mile Island nuclear power plant
in Pennsylvania created considerable alarm and uncertainty in the
surrounding areas about the plant‘s safety and the adequacy of
emergency planning. On the broader front, the American public focused
not only on Three Mile Island but also on safety and emergency
preparedness at nuclear power plants nationwide. With the September 11,
2001, terrorist attacks, public concern about the plants has increased
again. Concerns have focused principally on ensuring the plants‘
physical security and then on emergency preparedness in case terrorists
are successful in their attacks. The nation currently has 104
commercial nuclear power plants licensed to operate at 64 sites in 32
states. These plants provide about 20 percent of the nation‘s
electricity.
To protect the public should a commercial nuclear power plant
accidentally release radiation to the environment, the Nuclear
Regulatory Commission (NRC) requires the plant owner/operator to
prepare for NRC‘s approval a radiological emergency preparedness plan.
This on-site plan describes what is to be done in an emergency, how it
is to be done, and who is to do it. Among other things, the plan
identifies the process for notifying and communicating with the
operator‘s own personnel as well as with federal, state, and local
agencies and the media during an emergency. The plan also identifies
the circumstances and the actions--such as evacuating the local
population--the plant owner would recommend that off-site officials
take to protect the public. NRC conducts inspections to ensure that the
plant owner can effectively implement the on-site plan. In addition,
the Federal Emergency Management Agency (FEMA) is responsible for
ensuring that state and local communities develop emergency
preparedness plans to address the off-site effects of a radiological
emergency. FEMA oversees the conduct of periodic exercises to determine
whether the off-site response would adequately protect public health
and safety.
My testimony today is grounded in a report we issued in July 2001 to
the Chairman of the House Committee on Government Reform and to
Representatives Gilman, Kelly, and Lowey on emergency preparedness at
the Indian Point 2 plant in New York State.[Footnote 1] The Indian
Point facility is located within the Village of Buchanan in upper
Westchester County, approximately 24 miles north of New York City along
the east bank of the Hudson River. About 300,000 people live within 10
miles of the plant and millions more live in New York City and within
50 miles in Connecticut, New Jersey, New York, and Pennsylvania.
Concerns that nuclear power plants may be targets for terrorists and
Indian Point‘s close proximity to these large populations have
increased public interest in the adequacy of the plant‘s security and
emergency preparedness--leading some to call for closing the plant. A
draft report (the Witt report) commissioned by the Governor of New York
questions the adequacy of emergency preparedness at Indian Point and
raises broader issues about emergency preparedness at other nuclear
power plants.[Footnote 2]
In my testimony today, I will discuss the (1) findings and
recommendations of our 2001 report on emergency preparedness at the
Indian Point 2 plant and (2) subsequent progress made by the plant,
NRC, and FEMA in addressing problems noted in our report. You also
asked for our thoughts on the findings of the draft Witt report and its
potential implications for emergency planning at other facilities. To
follow up on the progress made to address the problems we identified in
2001, we reviewed relevant NRC inspection reports prepared since our
2001 report and held discussions with officials of NRC, FEMA, and the
four counties responsible for emergency preparedness in the surrounding
areas. We did not conduct a comprehensive update of emergency
preparedness at the Indian Point 2 plant nor verify the accuracy of the
draft Witt report‘s findings and conclusions. We should also note that,
since our 2001 report, the Entergy Corporation has assumed ownership of
the facility from the Consolidated Edison Company of New York.
In summary:
In 2001, we reported that, over the years, NRC had identified a number
of emergency preparedness weaknesses at Indian Point 2 that had gone
largely uncorrected. For example, in 1998 and again in 1999, NRC
identified several communication weaknesses, including delays in
activating the pagers used to alert the plant‘s staff about an
emergency. Consolidated Edison had some corrective actions under way
before a February 2000 event raised the possibility that radioactively
contaminated water would leak into the environment.[Footnote 3]
Consolidated Edison initiated other actions to address problems that
occurred during this event. However, according to an April 2001 NRC
inspection report, the actions were not fully effective. In evaluating
Consolidated Edison‘s response to the February 2000 event, NRC found
that critical emergency response personnel were not notified in a
timely manner, which delayed the staffing and operation of the on-site
emergency response facility. According to NRC, this delay occurred
because the process to activate the pagers was complex and not well
understood and Consolidated Edison had responded to the earlier
problems identified without diagnosing their underlying causes. As a
result, NRC found emergency preparedness problems similar to those it
had identified before and during the event. Despite these weaknesses,
NRC, in commenting on a draft of our report, expressed its view that
Consolidated Edison‘s emergency preparedness program could protect the
public.
We reported in 2001 that the four New York counties responsible for
responding to a radiological emergency at Indian Point 2 had
strengthened their emergency preparedness programs as a result of the
lessons learned from the February 2000 event. These lessons included
the need for better coordination and communications (1) between the
counties in responding to a radiological emergency and in providing the
media with information and (2) between Consolidated Edison and the
counties about the emergency and its potential impact on the public. We
reported that Consolidated Edison had not clearly communicated with the
state and counties about whether a radioactive release had occurred
and, if so, its magnitude. Consolidated Edison reported that a release
had occurred but posed no threat to the public, while county officials
reported that no release had occurred. This contradictory information
led to credibility problems with the media and the public. Consolidated
Edison, the state, and the counties revised the plant‘s radiological
emergency data form to more clearly show whether a release had
occurred.
As we also reported, county officials suggested changes to improve
communications among NRC, FEMA, and nonstate entities. In particular,
county officials said that since they are responsible for radiological
emergency preparedness for Indian Point 2, NRC and FEMA should
communicate directly with them during nonemergency situations. In New
York and 16 other states--where more than half of the nation‘s
operating nuclear power plants are located--counties or other local
governments are responsible for radiological preparedness, but NRC and
FEMA communicated primarily with the states and relied on the states to
communicate with local jurisdictions. In response, NRC said that
meeting with local officials would require considerable resources, and
FEMA said that some states limit its communications with local
officials. However, NRC had not assessed the costs and benefits of
routinely meeting with local officials, and FEMA‘s method of
communicating with the states had not effectively provided the four
counties with information on various initiatives that would affect
their programs. Since effective communication is critical to prepare
for and respond to a radiological emergency, we therefore recommended
that NRC and FEMA reassess their policies for communicating primarily
with the state in those instances where other entities have a major
role for responding to a radiological emergency.
Since our 2001 report, NRC inspection reports have continued to show
emergency preparedness weaknesses. For example, NRC reported that,
during an emergency exercise in the fall of 2002, the facility gave out
unclear information about the release of radioactive materials, as it
did during the February 2000 event. Similarly, in terms of NRC and FEMA
communicating with the surrounding jurisdictions, little has changed,
according to county officials. County officials told us that a
videoconference system--promised to ensure prompt meetings and better
communication between the plant‘s technical representatives and the
counties--had not been installed. During the February 2000 event, these
representatives had arrived late at the counties‘ emergency operations
centers. NRC officials said that they meet with state officials
concerning emergency preparedness and have instituted various
initiatives to improve public communication, in which local officials
can participate. FEMA officials told us that it would continue to work
with state and local governments on emergency preparedness.
The draft Witt report is a much larger, more technical assessment than
our 2001 report. While both reports talk to difficulties in
communications and planning inadequacies, the draft Witt report
concludes that the current radiological response system and
capabilities are not adequate to protect the public from an
unacceptable dose of radiation in the event of a release from Indian
Point, especially if the release is faster or larger than the release
for which the programs are typically designed. We are aware that, in
commenting on the draft of the Witt report, FEMA disagreed with some of
the issues raised but said that the report does highlight several
issues worth considering in order to improve preparedness levels in the
communities around Indian Point and nationwide. NRC concluded that the
report gives ’undue weight“ to the impact of a terrorist attack. The
agency said that it saw no difference between emergency plans for
releases caused by terrorist acts and those caused by equipment
malfunctions.
Background:
Emergency plans for commercial nuclear power plants are intended to
protect public health and safety whenever plant accidents cause
radiation to be released to the environment. Since the 1979 accident at
the Three Mile Island nuclear power plant, significantly more attention
has been focused on emergency preparedness. For example, the NRC
Authorization Act for fiscal year 1980 established a requirement for
off-site emergency planning around nuclear power plants and allowed NRC
to issue a nuclear plant operating license only if it determines that
there is either a
related state or local emergency preparedness plan that provides for
responding to accidents at the specific plant and complies with NRC‘s
emergency planning guidelines or
state, local, or facility plan that provides reasonable assurance that
public health and safety are not endangered by the plants‘ operation in
the absence of a related state or local emergency preparedness plan.
In November 1980, NRC and FEMA published regulations that provided the
criteria for radiological emergency plans. The regulations include
emergency standards for on-and off-site safety and require that
emergency plans be prepared to cover the population within a 10-mile
radius of a commercial nuclear power plant. In addition, state plans
must address measures necessary to deal with the potential for the
ingestion of radioactively contaminated foods and water within a 50-
mile radius. NRC and FEMA have supplemented the criteria several times
since 1980. For example in July 1996, the agencies endorsed the prompt
evacuation of the public within a 2-mile radius and about 5 miles
downwind of the plant, rather than sheltering the public, in the event
of a severe accident.
FEMA and the affected state and local governments within the 10-mile
emergency planning zone conduct exercises at least every 2 years at
each nuclear power plant site. In addition, each state with a nuclear
power plant must conduct an exercise within the 50-mile zone at least
every 6 years. The exercises are to test the integrated capabilities of
appropriate state and local government agencies, facility emergency
personnel, and others to verify their capability to mobilize and
respond if an accident occurs. Before the exercises, generally, FEMA
and state officials not involved in them agree to the accident
scenarios and the aspects of emergency preparedness that will be
tested. In addition, NRC requires plants to conduct exercises of their
on-site plans. According to NRC staff, the plants usually conduct their
exercises as part of FEMA‘s biennial exercises.
Indian Point 2 is one of the 104 commercial nuclear power plants
nationwide licensed to operate. The Indian Point site, which is called
the Indian Point Energy Center, has one closed and two operating
plants. The other operating plant is referred to as Indian Point 3.
In 2001, We Noted That Indian Point 2 Had Struggled:
to Resolve Emergency Preparedness Weaknesses:
Over the years, Consolidated Edison‘s efforts to improve emergency
preparedness at Indian Point 2 were not completely successful, and the
company experienced recurring weaknesses in its program, as we reported
in July 2001. The four New York counties surrounding the plant made
improvements in their emergency response programs but suggested better
communication among NRC, FEMA, and nonstate entities in nonemergency
situations.
Consolidated Edison Acted to Resolve Emergency Preparedness:
Weaknesses, but Its Actions Were Incomplete:
Beginning in 1996, NRC identified numerous weaknesses with the
emergency preparedness program at Indian Point 2. NRC found, for
example, that Consolidated Edison was not training its emergency
response staff in accordance with required procedures, and some
individuals had not taken the annual examination and/or participated in
a drill or exercise within a 2-year period, as required. In response,
Consolidated Edison disciplined the individuals responsible, developed
an improved computer-based roster containing the current status of the
training requirements for emergency response personnel, and began a
process to distribute training modules to those employees before their
qualifications expired.
NRC relied on Consolidated Edison to take corrective actions for other
emergency preparedness problems and weaknesses. However, the company
did not correct the weaknesses identified. For example, in 1998 and
again in 1999, NRC identified problems with activating the pagers used
to alert the plant‘s staff about an emergency, as well as other
communication weaknesses. In 1999, NRC concluded that Consolidated
Edison lacked the ability to detect and correct problems and determine
their causes, resulting in weak oversight of the emergency preparedness
program. In response, NRC staff said that they met with the company‘s
managers to specifically discuss and express NRC‘s concerns.
Similarly, NRC identified emergency preparedness weaknesses when
evaluating Indian Point 2‘s response to the February 2000 event. For
example, NRC found that Consolidated Edison did not activate its
emergency operations facilities within the required 60 minutes,
primarily because of the complex process used to page the emergency
response staff. This problem delayed the on-site response. NRC‘s Office
of the Inspector General also identified emergency preparedness issues,
including the state‘s difficulties getting information about the
emergency from Consolidated Edison and the fact that English is a
second language for many who lived within 10 miles of the plant. The
Office of the Inspector General concluded, and NRC agreed, that
recurring uncorrected weaknesses at Indian Point 2 had played a role in
the company‘s response during the February 2000 event. However, NRC
concluded that Consolidated Edison had taken the necessary steps to
protect public health and safety.
Consolidated Edison subsequently evaluated its entire emergency
preparedness program to determine the causes of the deficiencies and to
develop corrective actions. Consolidated Edison concluded that senior
management did not pay sufficient attention to the emergency
preparedness program or problems at Indian Point 2 because these
problems were not viewed as a high priority warranting close attention
and improvement. As a result, emergency preparedness had relatively low
visibility, minimal direction, and inadequate resources. The company
also found that (1) the emergency response organization had been
stagnant, understaffed, poorly equipped, and consistently ineffective;
(2) the emergency manager performed collateral and competing duties;
and (3) for a time, a contractor held the manager‘s position.
Furthermore, the professional development and continuing training of
the emergency planning staff had been minimal. The company undertook
initiatives to address the deficiencies noted.
Despite these initiatives, in April 2001, NRC reported that it had
found problems similar to those previously identified at Indian Point
2. NRC again found weaknesses in communication and information
dissemination. It also found that the utility‘s training program had
not prevented the recurrence of these issues during on-site drills and
that its actions to resolve other weaknesses had not been fully
effective. NRC said that Consolidated Edison had identified the major
issues in its business plan, which, if properly implemented, should
improve emergency preparedness at the plant. In commenting on a draft
of our July 2001 report, NRC noted that its April 2001 inspection
report concluded that Consolidated Edison‘s emergency preparedness
program would provide reasonable assurance of protecting the public.
The Four Counties Strengthened Their Emergency:
Preparedness Programs but Suggested Better:
Communication Among NRC, FEMA, and Nonstate Entities:
The need to improve communication between Consolidated Edison and the
counties about the extent of the emergency and the potential impact on
the public was highlighted during the February 2000 event. At that
time, Consolidated Edison reported that a radioactive release had
occurred but that it posed no danger to the public. County officials,
on the other hand, reported that no release had occurred. This
contradictory information led to credibility problems with the media
and the public.
Before the emergency, the counties did not have a defined process to
determine what information they needed and how they would present the
information to the public. At the time of the February 2000 event, the
Radiological Emergency Data Form that Consolidated Edison used to
inform local jurisdictions provided for one of three choices about a
release of radioactive materials: (1) no release (above technical
specification limits), (2) a release to the atmosphere above technical
specification limits, and (3) a release to a body of water (above
technical specification limits). In April 2000, Consolidated Edison, in
partnership with the state and counties, revised the form to ensure
that all affected parties were ’speaking with one voice“ when providing
the media and the public with information. The change to the form
provided for one of four choices: (1) no release, (2) a release below
federally approved operating limits (technical specifications) and
whether it was to the atmosphere or to water, (3) a release above
federally approved operating limits and whether to the atmosphere or to
water, and (4) an unmonitored release requiring evaluation.
The counties had also taken some other actions to improve their
radiological emergency programs. For example, all four counties agreed
to activate their emergency operation centers at the ’alert“ level (the
second lowest of four NRC classifications). Before the February 2000
event, the counties differed on when they would activate their centers,
with one county activating its center at the alert level and the other
three counties at the site-area emergency level (the next level above
an alert). As a result, once the first county activated its center
during the event, the media questioned why the other three counties had
not done so. The counties also connected the ’Executive Hot Line,“
which linked the state, four counties, and governor, to the emergency
operations facility at Indian Point 2 to establish and maintain real-
time communications during an emergency.
In addition to these actions, county officials suggested to us in 2001
that other changes to improve communications among NRC, FEMA, and
nonstate entities could be taken. In particular, county officials said
that since they are responsible for radiological emergency preparedness
for Indian Point 2, NRC and FEMA should communicate directly with them
during nonemergency situations. Absent these direct communications, the
counties were not privy to issues or initiatives that could affect
their emergency preparedness programs.
NRC staff tried to meet every 5 years with officials from all states
that have operating nuclear power plants. NRC staff told us that they
met with some states more frequently and that the requests to meet
exceeded the agency‘s capability. Although NRC‘s policy was to meet at
the state level, its staff believed that local officials had various
options for meeting with NRC. For example, local officials could
participate in the meetings held at least every 5 years with the states
and could interact with NRC staff during public meetings, including
those held annually for all plants. Emergency preparedness officials
from the four counties around Indian Point 2 said that they did not
believe that public meetings were the appropriate forums for
government-to-government interactions. Therefore, the counties
suggested that NRC should meet with them at least annually. According
to NRC staff, routinely communicating with local officials has resource
implications and involves tradeoffs with its other efforts, such as
maintaining safety and enhancing the effectiveness and efficiency of
operations. However, NRC, at the time of our review, had not assessed
the costs and benefits of meeting with local officials nor the impact
that such meetings might have.
FEMA generally implements its programs through the states and relies on
the states to communicate relevant information to local jurisdictions.
County officials responsible for emergency preparedness at Indian Point
2 identified instances in which this method of communicating with local
jurisdictions had not been effective. For example, both New York State
and county officials told us that the February 2000 event identified
the need for flexibility in FEMA‘s off-site exercises. County officials
said they responded to the 2000 event as they would have responded
during FEMA‘s exercises, which are conducted to the general emergency
level (the highest of NRC‘s action level classifications). Yet, they
noted, the response for an alert like the one that occurred in 2000 is
significantly different from the response needed during a general
emergency, when a significant amount of radiation would be released
from the plant site. State and county officials suggested that it would
be more realistic to periodically conduct biennial exercises at the
lower alert level, which, they noted (and NRC data confirmed), occur
more frequently than a general emergency. In commenting on a draft of
our report, FEMA said that the emergency plans for the four New York
counties require them to conduct off-site monitoring and dose
calculations at the alert level.
FEMA officials also noted that the agency‘s regulations allow state and
local jurisdictions the flexibility to structure the exercise scenarios
to spend more time at the alert level and less at the general emergency
level. Nevertheless, county officials who participated in the exercises
were not aware of the flexibility allowed by FEMA‘s regulations, in
part because they did not participate in developing the exercise
scenarios.
Emergency Preparedness Weaknesses at Indian Point 2 Have Continued:
In reviewing NRC‘s reports on its on-site inspections and evaluations
of the plant‘s emergency preparedness exercises or drills completed
since we issued our 2001 report, we found that the facility‘s emergency
preparedness program has continued to experience problems or
weaknesses. For example, NRC reported that, in an emergency exercise
conducted last fall, the facility gave out unclear information about
the release of radioactive materials, which also happened during the
February 2000 event. In addition, NRC reported that several actions to
correct previously identified weaknesses had not been completed. For
example, NRC noted that the timely and accurate dissemination of
information was identified as a weakness in the fall 2002 exercise and
had been documented previously in drill critique and condition reports.
In addition, in our 2001 report, we noted that NRC‘s Office of the
Inspector General found that, during the February 2000 event, the
Indian Point plant‘s technical representatives did not arrive on time
at the local counties‘ emergency operations centers. To help address
this problem, Consolidated Edison said that it would install a
videoconferencing system in the centers to enhance communications
between the plant and the off-site officials. According to county
officials, the videoconferencing system had not been installed as of
February 2003.
With respect to our 2001 recommendation that NRC and FEMA reassess
their practices of primarily communicating with state officials during
nonemergency situations, federal and local officials indicated that
little has changed since our report. NRC officials told us that they
did reassess their policy since our report was issued and determined
that no changes were needed. According to FEMA officials, the agency
will continue to work with state and local officials to carry out its
emergency preparedness program but has not made any changes regarding
nonemergency communication with state and local officials.
Given this history of inadequate efforts to address weaknesses in
Indian Point 2‘s emergency preparedness program, we continue to believe
that both NRC and the plant owner could benefit from being more
vigilant in correcting problems as they are identified. In addition to
improving the plant‘s program, a better track record in addressing
these problems could go a long way in helping alleviate the heightened
concerns in the surrounding communities about the plant‘s safety and
preparedness for an emergency. Similarly, more frequent, direct
communication by NRC and FEMA with officials of the surrounding
counties could improve local emergency preparedness programs and, in
turn, help local officials better communicate with their constituents
about the plant‘s safety and preparedness for an emergency.
The Witt Report Raises Emergency Preparedness
Issues at Indian Point and Other Nuclear Power Plants:
On August 1, 2002, the Governor of New York announced that James Lee
Witt Associates would conduct a comprehensive and independent review of
emergency preparedness around the Indian Point facility and for that
portion of New York State in proximity to the Millstone nuclear power
plant in Waterford, Connecticut.[Footnote 4] According to Witt
Associates, the review encompassed many related activities that were
designed, when taken together, to shed light on whether the
jurisdictions‘ existing plans and capabilities are sufficient to ensure
the safety of the people of the state in the event of an accident at
one of the plants, and how the existing plans and capabilities might be
improved. According to Witt Associates, it has considered and
incorporated public comments on a January 2003 draft of its report and
plans to issue the final report this month.
We have not evaluated the Witt report or verified the accuracy of its
findings and conclusions. We did note that the draft report identifies
various issues--such as planning inadequacies; expected parental
behavior that would compromise school evacuation; difficulties in
communications; the use of outdated technologies; problems caused by
spontaneous evacuation in a post September 11, 2001, environment; and a
limited public education effort--that may warrant consideration at
Indian Point and nationwide. The draft Witt report concludes that NRC
and FEMA regulations need to be revised and updated. We understand that
FEMA agreed, to an extent, in its review of the draft report. According
to the agency, the draft report raises a number of issues that should
be considered for enhancing the level of preparedness in the
communities surrounding the Indian Point facility, such as better
public education, more training of off-site responders, and improved
emergency communications. In addition, FEMA stated that some of these
issues should be evaluated for their applicability nationwide. However,
FEMA also said that a number of the issues raised in the draft report
were not supported by its own exercise evaluations, plan reviews, and
knowledge of the emergency preparedness program. According to NRC, the
draft report gives ’undue weight“ to the impact of a terrorist attack.
The agency said that it saw no difference between emergency plans for
releases caused by terrorist acts and those caused by equipment
malfunctions.
In summary, Mr. Chairman, the post September 11, 2001, environment
clearly presents new challenges for NRC and FEMA. While the public has
always had considerable interest in the safety of nuclear power plants,
the terrorist attacks have brought a level of focus and anxiety that
may rival or exceed that caused by the Three Mile Island accident in
1979. NRC and the nuclear industry deserve credit for taking action to
strengthen physical security as the result of a changing world, but we
are still concerned that, as shown in this hearing today, problems in
emergency preparedness remain after being repeatedly identified as
needing attention. Mr. Chairman, GAO is currently conducting reviews of
physical security at selected nuclear power plants and is looking in-
depth at safety issues at the Davis-Besse plant in Ohio. We plan to
report the results of our work later this year.
Mr. Chairman, this concludes our prepared statement. We would be happy
to respond to any questions that you or Members of the Subcommittee may
have.
Contacts and Acknowledgments:
For further information about this testimony, please contact me at
(202) 512-3841. Raymond Smith, William Fenzel, Kenneth Lightner,
William Lanouette, Jill Edelson, Heather Barker, and Addison Ricks also
made key contributions to this statement.
(360317):
FOOTNOTES
[1] NUCLEAR REGULATION: Progress Made in Emergency Preparedness at
Indian Point 2, but Additional Improvements Needed, GAO-01-605
(Washington, D.C., July 30, 2001).
[2] James Lee Witt Associates, LLC, Review of Emergency Preparedness at
Indian Point and Millstone [Draft] (Washington, D.C., Jan. 10, 2003).
The Witt report was commissioned by Governor Pataki to be a
comprehensive and independent review of emergency preparedness in the
areas around Indian Point and for that portion of New York State in
proximity to the Millstone nuclear power plant in Connecticut.
[3] In February 2000, a tube ruptured in a steam generator and
Consolidated Edison temporarily shut down the plant because of the
possibility that radioactively contaminated water could leak into the
environment. According to Consolidated Edison and NRC, the total amount
of radioactivity released posed no threat.
[4] Mr. Witt is a former FEMA Director.