Maritime Security
Substantial Work Remains to Translate New Planning Requirements into Effective Port Security
Gao ID: GAO-04-838 June 30, 2004
The Maritime Transportation Security Act of 2002, as implemented by the Coast Guard, calls for owners and operators of about 3,150 port facilities (such as shipping terminals or factories with hazardous materials) and about 9,200 vessels (such as cargo ships, ferries, and tugs and barges) to develop and implement security plans by July 1, 2004. The Coast Guard intends to conduct on-site compliance inspections of all facilities by January 1, 2005, and all vessels by July 1, 2005, to ensure plans are adequately implemented. The Coast Guard estimated the act's security improvements would cost $7.3 billion over 10 years--most of it borne by facility and vessel owners and operators. GAO was asked to assess (1) the progress towards developing, reviewing, and approving plans by July 1, 2004, (2) the Coast Guard's monitoring and oversight strategy for ensuring that plans are implemented, and (3) the accuracy of the Coast Guard's cost estimate.
Owners and operators have made progress in developing security plans for their port facilities and vessels. However, the extent to which the Coast Guard will have reviewed and approved the approximately 12,300 individual plans by July 1, 2004, varies considerably. About 5,900 plans were being developed under an option allowing owners and operators to self-certify that they would develop and implement plans by July 1, using industry-developed, Coast Guard-approved standards and templates. These individual plans will not be reviewed before July 1 unless owners or operators choose to submit them for review. The remaining 6,400 plans went through a review process established by the Coast Guard. Every plan required revisions, some of which were significant. As of June 2004--1 month before the deadline for implementation--more than half of the 6,400 plans were still in process. The Coast Guard took steps to speed up the process and to allow facilities and vessels to continue operating with less than full plan approval after July 1, as long as the Coast Guard was satisfied with their progress. The Coast Guard's strategy for monitoring and overseeing security plan implementation will face numerous challenges. Whether the Coast Guard will be able to conduct timely on-site compliance inspections of all facilities and vessels is uncertain because questions remain about whether the Coast Guard will have enough inspectors; a training program sufficient to overcome major differences in experience levels; and adequate guidance to help inspectors conduct thorough, consistent reviews. Another challenge is to ensure inspections reflect assessments of the normal course of business at facilities and aboard vessels. The accuracy of the Coast Guard's $7.3 billion estimate for implementing security improvements is likewise uncertain. The estimate, while a goodfaith effort on the Coast Guard's part, is based on limited data and on assumptions that are subject to error. The estimate should be viewed more as a rough indicator than a precise measure of costs.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-04-838, Maritime Security: Substantial Work Remains to Translate New Planning Requirements into Effective Port Security
This is the accessible text file for GAO report number GAO-04-838
entitled 'Maritime Security: Substantial Work Remains to Translate New
Planning Requirements into Effective Port Security' which was released
on June 30, 2004.
This text file was formatted by the U.S. General Accounting Office
(GAO) to be accessible to users with visual impairments, as part of a
longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to Congressional Requesters:
United States General Accounting Office:
GAO:
June 2004:
Maritime Security:
Substantial Work Remains to Translate New Planning Requirements into
Effective Port Security:
GAO-04-838:
GAO Highlights:
Highlights of GAO-04-838, a report to congressional requesters
Why GAO Did This Study:
The Maritime Transportation Security Act of 2002, as implemented by the
Coast Guard, calls for owners and operators of about 3,150 port
facilities (such as shipping terminals or factories with hazardous
materials) and about 9,200 vessels (such as cargo ships, ferries, and
tugs and barges) to develop and implement security plans by July 1,
2004. The Coast Guard intends to conduct on-site compliance inspections
of all facilities by January 1, 2005, and all vessels by July 1, 2005,
to ensure plans are adequately implemented. The Coast Guard estimated
the act‘s security improvements would cost $7.3 billion over 10 years”
most of it borne by facility and vessel owners and operators. GAO was
asked to assess (1) the progress towards developing, reviewing, and
approving plans by July 1, 2004, (2) the Coast Guard‘s monitoring and
oversight strategy for ensuring that plans are implemented, and (3) the
accuracy of the Coast Guard‘s cost estimate.
What GAO Found:
Owners and operators have made progress in developing security plans
for their port facilities and vessels. However, the extent to which the
Coast Guard will have reviewed and approved the approximately 12,300
individual plans by July 1, 2004, varies considerably. About 5,900
plans were being developed under an option allowing owners and
operators to self-certify that they would develop and implement plans
by July 1, using industry-developed, Coast Guard-approved standards and
templates. These individual plans will not be reviewed before July 1
unless owners or operators choose to submit them for review. The
remaining 6,400 plans went through a review process established by the
Coast Guard. Every plan required revisions, some of which were
significant. As of June 2004”1 month before the deadline for
implementation”more than half of the 6,400 plans were still in process.
The Coast Guard took steps to speed up the process and to allow
facilities and vessels to continue operating with less than full plan
approval after July 1, as long as the Coast Guard was satisfied with
their progress.
The Coast Guard‘s strategy for monitoring and overseeing security plan
implementation will face numerous challenges. Whether the Coast Guard
will be able to conduct timely on-site compliance inspections of all
facilities and vessels is uncertain because questions remain about
whether the Coast Guard will have enough inspectors; a training program
sufficient to overcome major differences in experience levels; and
adequate guidance to help inspectors conduct thorough, consistent
reviews. Another challenge is to ensure inspections reflect assessments
of the normal course of business at facilities and aboard vessels.
The accuracy of the Coast Guard‘s $7.3 billion estimate for
implementing security improvements is likewise uncertain. The estimate,
while a good-faith effort on the Coast Guard‘s part, is based on
limited data and on assumptions that are subject to error. The estimate
should be viewed more as a rough indicator than a precise measure of
costs.
Port facilities pose many security concerns, given their size,
accessibility, and attractiveness as terrorist targets. Facilities like
these must have a security plan in place by July 1, 2004.
[See PDF for image]
[End of figure]
What GAO Recommends:
GAO recommends that the Coast Guard evaluate its initial compliance
efforts and use them to strengthen the compliance process for its long-
term strategy. As part of this strategy, the Coast Guard should clearly
define inspector qualifications and consider including unscheduled and
unannounced inspections and covert testing. The Coast Guard agreed.
www.gao.gov/cgi-bin/getrpt?GAO-04-838.
To view the full product, including the scope and methodology, click on
the link above. For more information, contact Margaret Wrightson at
(415) 904-2200 or wrightsonm@gao.gov.
[End of section]
Contents:
Letter:
Results in Brief:
Background:
Extent of Coast Guard Review and Approval of Individual Plans Varies
Widely:
Strategy for Monitoring and Oversight of Plan Implementation Faces
Numerous Challenges:
Cost to Comply with MTSA Is Uncertain:
Conclusions:
Recommendation for Executive Action:
Agency Comments:
Appendix I: Objectives, Scope, and Methodology:
Appendix II: Required Security Plan Items:
Appendix III: Analysis of Coast Guard's Compliance Cost Estimates:
Estimates Required Assumptions about Many Important Components:
Many Assumptions Carry Limitations:
Limited Time to Estimate Costs Precluded More Extensive Data Collection
and Analysis of Uncertainty:
Cost Estimate Spans Only 10 Years and Does Not Include All Costs:
Questions Remain about Adequacy of Public Comments to Validate Cost
Estimate:
Appendix IV: GAO Contacts and Staff Acknowledgments:
GAO Contacts:
Staff Acknowledgments:
Tables:
Table 1: Progress of Facility and Vessel Security Plan Review Under
Option A as of June 2004:
Table 2: Port Stakeholders GAO Contacted at Port Locations Reviewed:
Table 3: Coast Guard Assumptions about Extent of Prior Security
Preparation:
Figures:
Figure 1: Location of U.S. Ports:
Figure 2: Overview of the Two Options for Developing Security Plans:
Figure 3: Distribution of Individual Security Plans by Development
Option:
Figure 4: Projection of Estimated Costs, 2012-2022:
Abbreviations:
AMSC: Area Maritime Security Committee:
ASP: Alternative Security Program:
IMO: International Maritime Organization:
ISPS: International Ship and Port Facility Security Code:
MARSEC: Maritime Security Condition System:
MTSA: Maritime Transportation Security Act:
SOLAS: International Convention for Safety of Life at Sea:
United States General Accounting Office:
Washington, DC 20548:
June 30, 2004:
The Honorable Don Young:
Chairman, Committee on Transportation and Infrastructure:
House of Representatives:
The Honorable Frank A. LoBiondo:
Chairman, Subcommittee on Coast Guard and Maritime Transportation:
Committee on Transportation and Infrastructure:
House of Representatives:
Since the terrorist attacks of September 11, 2001, the nation's 361
ports have increasingly been viewed as potential targets for future
attacks for many reasons. For example, security experts remain
concerned about the potential for using the maritime transportation
system as a conduit for smuggling weapons of mass destruction or other
dangerous materials into the country. Further, cargo and cruise ships
present potentially desirable terrorist targets, given the potential
for loss of life, ecological destruction, or disruption of commerce.
And ports often are not only gateways for the movement of goods, but
also industrial hubs and close to population centers, presenting
additional opportunities for terrorists bent on urban destruction.
Coordinating a security response for this myriad of potential targets
is a daunting proposition, in part because so many different
stakeholders are involved. These stakeholders include law enforcement
and other government agencies at every level (federal, state, and
local); vessel owners and operators; railroads; port authorities;
factories and other businesses; and people who work in port areas or
live nearby. Although perspectives may vary, the specter of further
terrorist incidents has led to widespread agreement that port security
should be strengthened--and soon.
The Maritime Transportation Security Act (MTSA)[Footnote 1] contains
much of the federal government's approach to addressing these security
vulnerabilities. Enacted in November 2002 and largely administered by
the United States Coast Guard, an agency within the Department of
Homeland Security, MTSA is designed, in part, to help protect the
nation's ports and waterways from terrorist attacks through a wide
range of security improvements. One of its central maritime
transportation security provisions is a requirement that security plans
be developed and implemented for specific facilities (such as
factories, cargo terminals, and power plants); certain individual cargo
and passenger vessels; and entire ports.[Footnote 2] The basic aim of
such plans is to address potential vulnerabilities that could be
exploited to kill people, cause environmental damage, or disrupt
transportation systems and the economy, by developing measures to
mitigate these vulnerabilities. The Coast Guard established regulations
determining which facilities and vessels were to be covered by these
security planning requirements[Footnote 3] and consistent with MTSA,
set a deadline of July 1, 2004, for facility and vessel owners and
operators to operate under an approved or self-certified security plan.
Further, the Coast Guard intends to conduct on-site compliance
inspections of all facilities by January 1, 2005, and all vessels by
July 1, 2005, to ensure that they have satisfactorily implemented their
plans. This aggressive timeline for both developing and implementing
security plans reflects the seriousness of the port security issue.
However, the timeline also creates a substantial and immediate workload
for the Coast Guard and for owners and operators who collectively must
develop plans for thousands of facilities and vessels. The Coast Guard
estimated that the security improvements imposed by these requirements
would likely cost port stakeholders $7.3 billion over 10 years--most of
it borne by facility and vessel owners and operators.[Footnote 4]
You asked us to examine the efforts of stakeholders and the Coast Guard
in carrying out these security plan requirements. Our objectives were
to assess (1) the progress made to develop, review, and approve
facility and vessel security plans by July 1, 2004; (2) the Coast
Guard's monitoring and oversight strategy for ensuring that facility
and vessel security plans are implemented; and (3) the accuracy of the
Coast Guard's estimates of costs for complying with MTSA security
planning and implementation requirements.
To address the first two objectives, we analyzed Coast Guard documents
and spoke with officials at Coast Guard headquarters with
responsibilities for the security planning process. We also visited
seven port areas around the country, choosing locations that reflected
diversity in strategic importance, geographic location, and local
characteristics.[Footnote 5] During our visits, we spoke with Coast
Guard Captains of the Port;[Footnote 6] numerous local stakeholders in
the private sector; and government officials at the local, state, and
federal levels, to understand what progress had been made to develop
and implement security plans. We visited Coast Guard officials and
contractor staff responsible for reviewing and approving MTSA-required
security plans and examined the review and approval process used by the
Coast Guard to determine what internal controls were in place to
monitor the consistency of the process and ensure compliance with
pertinent MTSA requirements. Our work did not include reviewing ports
outside the United States or any "foreign-flagged" vessels--vessels
registered in countries other than the United States. To address the
third objective, we interviewed Coast Guard staff in charge of creating
estimates of compliance costs and performed economic simulations to
examine the impact of changing the assumptions the Coast Guard used in
making its estimates. We asked Coast Guard officials responsible for
these cost estimates what steps they took to ensure the reliability of
the underlying data on which the estimates were based. We also reviewed
the public comments provided to the Coast Guard on its estimates. Our
work, which was conducted from June 2003 through June 2004, was done in
accordance with generally accepted government auditing standards.
Results in Brief:
Although owners and operators have made progress in developing security
plans, the extent to which the Coast Guard will have reviewed and
approved the approximately 12,300 individual facility or vessel plans
by July 1, 2004, varies considerably. Owners and operators are
developing about 5,900 plans under an option allowing them to self-
certify that the plans will be developed and implemented by July 1. In
doing so, they are using standards and templates their trade
association had developed and the Coast Guard had approved. Owners and
operators who chose this option did not have to submit their plans for
review and approval. The Coast Guard's first look at many of these
plans will likely not come until after July 1, when inspectors begin
compliance inspections to ensure that plans have been implemented. The
remaining 6,400 plans, which were not developed through the self-
certification process, underwent a detailed review process for which
the Coast Guard hired contractors with security experience. The
contractors conducting much of the review found that all of these plans
needed to be revised, some extensively, and the Coast Guard concurred
with the contractors' findings. As of June 2004--1 month before the
deadline---more than half of these plans were still in process. To
speed up the process, the Coast Guard added more personnel and began
working more directly with owners and operators. Nonetheless, many of
these plans will not be approved by July 1. Under MTSA and Coast Guard
regulations, facilities and vessels without approved plans would have
to cease operations. However, MTSA and the regulations also allow the
Coast Guard to grant permission to such facilities and vessels to
continue operating for up to 1 year after the plans are submitted on
the condition that they continue to make sufficient progress through
the review process toward the approval of their plans. The Coast Guard
is currently allowing such facilities and vessels to operate through
October 31, 2004.
In late May 2004, the Coast Guard issued its strategy for ensuring that
facility and vessel owners and operators implement the security
activities identified in their plans. It is clear that this strategy
will face several challenges, both in the short and longer term. One
challenge is the sheer size of the immediate effort: between July and
December 2004, the Coast Guard plans to conduct on-site inspections of
every facility and as many vessels as possible to ensure that owners
and operators are complying with the actions called for in their
security plans. Inspectors will have to make decisions about whether
owners and operators have identified all vulnerabilities and adequately
addressed them. These decisions are complicated, in part because owners
and operators have considerable choice in how to mitigate
vulnerabilities and because the Coast Guard will be seeing many of
these plans for the first time. Other challenges include ensuring that
enough inspectors are available, training them adequately, and
equipping them with useful guidance for making on-site inspection
decisions. In the short term, these challenges are formidable, because
the Coast Guard expects to handle the added July-December inspection
load mainly by using reservists with widely varying degrees of training
and experience. In the longer term, when the Coast Guard plans to
conduct annual compliance inspections for the approximately 12,300
facilities and vessels, it faces the challenge of ensuring that owners
and operators continue implementing their plans. In this regard, our
work has shown that there are options the Coast Guard could consider
beyond regularly scheduled visits, such as unscheduled, unannounced
visits and covert testing to help ensure owners and operators do not
mask security problems in ways that do not represent the normal course
of business.
The accuracy of the Coast Guard's $7.3 billion estimate of maritime
industry costs for developing and implementing their security plans is
uncertain. An estimate's accuracy is often tied to such factors as the
complexity or straightforwardness of the issue, the quality of data and
validity of assumptions, and the length of time available to conduct
the work. The Coast Guard was heavily limited in all these factors.
First, the issue was complex: for example, facilities and vessels are
very diverse and they vary greatly in the degree to which they already
have security measures in place. Second, to account for such
differences, the Coast Guard was faced with having to develop many
assumptions, and while the Coast Guard used government and industry
expertise to help make these assumptions, it had limited data with
which to work, and the potential margin for error was considerable. Our
analysis found that changes in the Coast Guard's assumptions could
raise or lower the estimate by more than $1 billion. Third, the Coast
Guard had only a few months to develop the estimate. The Coast Guard
vetted the estimate with stakeholders as a way of testing its
reliability, but stakeholders were basically in no better position than
the Coast Guard to generalize from their own specific situations. The
Coast Guard appeared to make a good-faith effort to prepare an estimate
and seek review of it from port stakeholders, but the limiting factors
discussed here indicate the result can be viewed more as a rough
indicator of costs, not a precise measure.
We recommend that the Coast Guard evaluate the compliance inspection
efforts it takes during the initial 6-month period after July 1 and use
the results as a means to strengthen its long-term strategy for
ensuring compliance. As part of this strategy, the Coast Guard should
clearly define inspector qualifications, link these qualifications to a
certification process, and consider including unscheduled and
unannounced inspections and covert testing. The Coast Guard reviewed
our report and generally agreed with the facts and recommendation.
Background:
MTSA mandated major changes in the nation's approach to maritime
security. The act called for a comprehensive security framework--one
that included planning, personnel security, and careful monitoring of
vessels and cargo. Among its specific provisions were the development
of systems for tracking vessels, identifying maritime workers, and
assessing foreign ports for security risks they posed for the United
States. One of MTSA's central components is a systematic approach to
strengthening security throughout the nation's port areas--a difficult
task, given the tremendous size and variety of activities and user
groups involved. Ports present attractive targets: they are sprawling,
easily accessible by water and land, close to crowded metropolitan
areas, and interwoven with complex transportation networks designed to
move cargo and commerce as quickly as possible. They contain not only
terminals where goods bound for import or export are unloaded or loaded
onto vessels, but also other facilities critical to the nation's
economy, such as refineries, factories, and power plants.
Facilities and vessels can be vulnerable on many security-related
fronts. Facilities such as container terminals, where containers are
transferred between ships and railroad cars or trucks, must be able to
screen vehicles entering the facility and routinely check cargo for
evidence of tampering. Chemical factories and other installations where
hazardous materials are present must be able to control access to areas
containing dangerous goods or hazardous substances. Vessels, ranging
from oil tankers and freighters to tugboats and passenger ferries, must
be able to restrict access to areas on board the vessel such as the
bridge or other control stations critical to the vessel's operation. To
reduce the opportunity for terrorists to exploit these vulnerabilities,
as well as to help minimize the effects of accidents or natural
disasters, facilities and vessels need to take mitigation steps. For
example, fences, security guards, and monitoring cameras can all be
used to reduce the potential for unauthorized entry and help prevent
vulnerabilities from being exploited.
Dealing with such vulnerabilities involves a careful balance between
the benefits of added security and the potential economic impacts of
security enhancements. While there is broad support for greater
security, this task is a difficult one because the nation relies
heavily on a free and expeditious flow of goods. Particularly with
"just in time" deliveries, which require a smooth and expeditious flow
through the transportation system, delays or disruptions in the supply
chain could have serious economic impacts. Striking the right balance
between increasing security and protecting economic vitality of the
national economy and individual port stakeholders will remain an
important and difficult task. It is also important to keep in mind that
total security cannot be bought no matter how much is spent on it. It
is difficult if not impossible to successfully anticipate and thwart
all types of potential terrorist threats that highly motivated, well
skilled, and adequately funded terrorist groups could devise.
In this environment, MTSA required owners and operators of facilities
and vessels to conduct assessments that would identify their security
vulnerabilities and to develop security plans to mitigate these
vulnerabilities. Under the Coast Guard's implementing regulations,
these plans are to include such items as measures for access control,
responses to security threats, and drills and exercises to train staff
and test the plan. [Footnote 7] The plans are "performance-based,"
meaning that the security outcomes were specified, but the stakeholders
were free to identify and implement whatever measures they desired as
long as these measures achieved the specified outcomes. MTSA tasked the
Secretary of the Department of Homeland Security with responsibility
for reviewing, approving, and overseeing the implementation of these
plans, and the Secretary delegated this task to the Coast Guard.
MTSA imposed a specific date, July 1, 2004, for facilities and vessels
to begin operating in compliance with the plans. The Coast Guard
decided to adopt a schedule that would align the United States with
ongoing international improvements in maritime security as well as the
act. In December 2002, members of the International Maritime
Organization (IMO) adopted the International Ship and Port Facility
Security (ISPS) Code, an international agreement that called for
security plans to be in place by July 1, 2004.[Footnote 8] The Coast
Guard had to decide which facilities and vessels were subject to MTSA's
requirements and develop an approach for reviewing and approving the
plans. The categories of facilities and vessels were specified in
implementing regulations, issued in final form on October 22,
2003.[Footnote 9] Overall, approximately 3,150 facilities and 9,200
vessels operating in more than 300 ports around the nation were
required to comply with these requirements. The ports included not only
those on the Atlantic, Gulf, and Pacific coasts, but also ports in the
Great Lakes and various inland waterways like the Mississippi and Ohio
rivers. (See fig. 1.)
Figure 1: Location of U.S. Ports:
[See PDF for image]
[End of figure]
The key dates in the process established by the Coast Guard included
the following:
* By December 31, 2003, those facilities and vessels subject to MTSA's
security plan requirements had to submit security plans to the Coast
Guard for review or self-certify that their plans would be developed
and implemented by July 1.
* By July 1, 2004, the Coast Guard intends to complete its review and
approval of the security plan materials from all facilities and
vessels. On that date, facilities and vessels are to have their
security plans implemented.
* By January 1, 2005, the Coast Guard intends to conduct on-site
inspections of each facility subject to the security plan requirements,
along with as many vessels as possible, to ensure that the steps called
for in the security plan are actually in place.[Footnote 10]
* By July 1, 2005, the Coast Guard intends to complete the remaining
on-site compliance inspections for vessels it is not able to inspect by
January 1, 2005.
The Coast Guard took a number of steps to help stakeholders understand
and comply with requirements. The Coast Guard issued updated guidance
and established a "help desk" to provide stakeholders with a single
point of contact, both through the Internet and over the telephone. At
the local level, Coast Guard marine safety offices[Footnote 11] at the
ports provided stakeholders operating within their ports additional
information and assistance through forums, training sessions, e-mails,
letters, and telephone calls. The Coast Guard also hired two
contractors[Footnote 12] to provide expertise in reviewing the facility
and vessel security plans.
In issuing the final rules, the Coast Guard also developed an estimate
of the cost to implement MTSA's port security provisions. The Coast
Guard estimated that implementing the various port and vessel security
provisions, including the security plans, would cost $7.3 billion over
10 years.[Footnote 13] In fiscal years 2002-2004, the federal
government awarded $516 million in grant funds for improvements in port
security; in fiscal year 2005, the Department of Homeland Security
expects another $50 million to be made available through federal grants
to implement security improvements identified in the plans. However,
the bulk of the cost burden is likely to be borne by facility and
vessel owners and operators.
Extent of Coast Guard Review and Approval of Individual Plans Varies
Widely:
While the Coast Guard expects owners and operators to implement the
approximately 12,300 facility and vessel plans by July 1, 2004, the
extent it will have reviewed and approved these plans varies widely,
for two main reasons. First, about 5,900 of these plans were developed
under an option that essentially deferred Coast Guard review of
individual plans until after July 1. Under this option, owners and
operators self-certified that their plans would be based on industry-
developed, Coast Guard-approved standards and templates. Owners and
operators choosing this option did not have to submit their plans for
review. Second, while the remaining 6,400 plans did undergo detailed
review, all of them had deficiencies, and many are not likely to be
corrected and fully approved by July 1. Under MTSA and Coast Guard
regulations, facilities and vessels without fully approved plans would
have to cease operations on July 1. However, the Coast Guard has put
procedures in place to allow such facilities and vessels to continue
operating after the deadline, provided certain conditions are met.
Two Options for Developing Security Plans Varied in Key Respects:
The Coast Guard established two options, referred to in this report as
options A and B, which owners and operators could follow in developing
their plans. (See fig. 2.) These options differed in the documents that
had to be supplied to the Coast Guard and the extent of review that
would be applied to individual plans by July 1.
* Option A: Owners or operators who chose this option had to develop
their own security plans according to the requirements in the final
rules and submit them to the Coast Guard for review by December 31,
2003. These plans were then subject to detailed review by the Coast
Guard and its contractors.
* Option B: Owners or operators who were members of certain industry
groups could choose this option to develop plans by using Coast Guard
approved security programs established by their industry groups, such
as an association of chemical manufacturers or passenger vessel
operators. To accommodate widespread interest from owners and operators
in being able to use such standards to meet MTSA requirements, the
Coast Guard allowed trade organizations to submit security standards,
including templates[Footnote 14] for developing security plans, for
consideration as "alternative security programs" (ASP). The Coast Guard
then reviewed each organization's application and approved those it
determined would provide an equivalent level of security to the
standards being applied under option A at all threat levels within the
nation's Maritime Security Condition System. Members of the industry or
trade association then self-certified to the Coast Guard that they were
using the standards and templates to develop security plans for their
facilities or vessels.
Figure 2: Overview of the Two Options for Developing Security Plans:
[See PDF for image]
[End of figure]
These two options both involved review by the Coast Guard, but there
was considerable difference in what was being reviewed before the start
of the compliance phase on July 1, 2004. Under option A, the Coast
Guard and its contractors would review the individual plans themselves;
under option B, Coast Guard review would center on the organization's
standards and templates and would not extend to the individual
plans.[Footnote 15] These reviews were not the same, in that industry
standards and templates are a framework for developing a plan, but are
not analogous to individual vessel or facility security plans. To adapt
the standards and templates to specific facilities and vessels, owners
and operators still need to do considerable work.
Coast Guard records indicate that 90 percent of facilities and vessels
met the December 31, 2003, deadline for complying with one of the two
options. Most owners and operators who did not meet the December 31
deadline subsequently complied. However, the Coast Guard issued notices
of violation with a $10,000 penalty assessment against owners or
operators of 67 facilities and 90 vessels who had not responded by
February 1. Eight of these owners or operators received a subsequent
$25,000 penalty assessment for not responding by March 1.
Nearly Half of All Plans Will Be Developed under the Option with No
Review of Individual Plans:
In all, plans for 5,923 facilities or vessels are being prepared under
option B. Of these, 234 were facilities and 5,689 were vessels. The
Coast Guard granted approval to standards and templates submitted by
nine trade organizations, most of them vessel-related,[Footnote 16] and
the plans being developed under this option reflect the larger number
of vessel-related groups. Overall, about 7 percent of facility plans
are being developed under this option, compared with 62 percent of all
vessel plans. (See fig. 3.)
Figure 3: Distribution of Individual Security Plans by Development
Option:
[See PDF for image]
[End of figure]
The extensive use of option B meant that nearly half of the individual
plans were not directly reviewed by the Coast Guard before they were to
be implemented on July 1, 2004. Users of option B had to send the Coast
Guard a letter stating which alternative security program they planned
to use. The Coast Guard was to check to ensure that the owners or
operators were members of the organization that developed the program.
Inasmuch as option B reduced the number of individual plans to be
reviewed, it lessened the Coast Guard's review workload. However,
option B also had the effect of deferring review of these individual
plans into the next phase of the process--the on-site compliance
inspections to be conducted starting July 1. For these facilities and
vessels, the Coast Guard's first look at the plans will occur when
inspectors arrive to ensure that the plans have been
implemented.[Footnote 17]
All Plans Undergoing Individual Review Had Deficiencies that Affected
Final Approval:
For plans submitted under option A, the Coast Guard established a
comprehensive review and approval process that relies on contractors
with security planning expertise to review and evaluate the plans.
Plans move through a two-or three-stage process, depending on whether
they are for vessels or facilities. In stage I, at least two contract
personnel independently reviewed the plans to ensure they contain
material covering all required items such as measures for access
control, responses to security threats, and drills and exercises to
train staff and test the plan. Plans passing this stage move to stage
II, where comprehensive assessments are conducted as to whether the
plans address all of MTSA's requirements. Vessel plans are approved
once the Coast Guard determines they have passed this stage II review.
Facility plans continue on to a stage III review, in which the local
Coast Guard marine safety office verifies the information in the
security assessment against the facility's physical characteristics and
determines whether the plan is adequate to meet security needs. This
last stage may include an on-site visit, but if conducted, this
verification review is not the same as the post-July 1 compliance
inspection for determining whether the facility has implemented the
plan. Facility plans are approved once the Coast Guard determines they
have passed this stage III review.
This review and approval process flagged problems. Every one of the
more than 6,400 facility and vessel plans submitted under this option
had deficiencies that needed to be revised before the plan could be
approved. As table 1 shows, of the 2,913 facility plans and 3,505
vessel plans submitted under option A, more than half were still
undergoing the detailed review as of June 2004. Most of these plans
still in review were facility security plans.
Table 1: Progress of Facility and Vessel Security Plan Review Under
Option A as of June 2004:
Facility security plans;
Stage I: 80;
Stage II: 1,637;
Stage III: 1,076;
Approved: 120;
Totals: 2,913.
Vessel security plans;
Stage I: 23;
Stage II: 750;
Stage III: [A];
Approved: 2,732;
Totals: 3,505.
Source: GAO presentation of Coast Guard data.
Note: Facility security plan numbers are as of June 14, 2004; vessel
security plan numbers are as of June 4, 2004.
[A] Vessel security plans are approved once the Coast Guard determines
they have passed stage II.
[End of table]
The problems identified through this process resulted from a variety of
deficiencies in the plans developed under option A. The most common
deficiency identified for both facility and vessel plans during stage
I, according to the Coast Guard, was the failure to address or
inadequately address all of the required security plan sections
specified in regulations. For example, some owners and operators simply
restated the text in the regulations or excluded some plan elements
such as the security assessment. Common stage II deficiencies for
facility plans included providing insufficient detail describing steps
to be taken for elevated MARSEC threat levels or security measures to
be put in place for control of access to the facility. For vessel
security plans, common deficiencies identified at this level were
inadequate descriptions of the steps for conducting security drills and
exercises, insufficient measures for controlling access, or inadequate
descriptions of the qualifications and responsibilities of those in
charge of security programs.
Resolving such deficiencies has kept many plans at stage II of the
review. After reviewing the contactor's findings, the Coast Guard
notified the owner or operator about the deficiencies and any deadline
for submitting revisions.[Footnote 18] While owners and operators could
correct some deficiencies easily, such as adding a missing telephone
number or name of a security officer, other corrections required more
work, such as providing more detail about access control procedures or
measures. Plans could not proceed to the next stage until the Coast
Guard was satisfied they were complete--a process that has sometimes
required repeated revision. Correcting these deficiencies has taken
longer than the Coast Guard anticipated.[Footnote 19]
Process Exists to Allow Facilities and Vessels with Unapproved Plans to
Continue Operating:
Under MTSA and Coast Guard regulations, facilities and vessels can be
shut down if they have not complied with the requirements called for
under options A or B by July 1, 2004. Facilities and vessels with plans
still in revision under option A could thus face closure. To speed up
the overall process, the Coast Guard adopted a strategy called
"compliance through engagement." Instead of sending deficiency letters,
the Coast Guard began calling owners and operators directly to review
deficiencies, explain regulatory requirements, and answer questions.
The Coast Guard also advised Captains of the Port to encourage facility
owners or operators still in stage I to make needed revisions so the
plan could pass to stage II. Staffing was also increased at the center
reviewing facility security plans to help speed review.[Footnote 20]
According to the Coast Guard, this strategy significantly improved
turnaround time for receiving revised plans from owners and operators.
Anticipating that plans for some facilities and vessels would still be
in process on July 1, the Coast Guard also took steps to allow most of
them to continue operating as allowed by MTSA and the
regulations.[Footnote 21] The steps vary depending on whether the plan
covers a facility or vessel and how far along it is in the process.
* Facilities that have received an initial stage II review can receive
interim approval of their plan through October 31, 2004, pending final
approval of the security plan. Rather than waiting to conduct on-site
verification reviews until plans move to stage III, the Coast Guard
advised Captains of the Port to have their inspectors begin visiting
all facilities that had received a stage II review, regardless of
whether the facility had revised the deficiencies identified through
the review. During these visits, Coast Guard personnel are to verify
that (1) the plan accurately reflects the facility and its operations,
(2) the proposed security measures are realistic, and (3) deficiencies
will either be addressed by July 1 or satisfactory interim measures
will be in place. If these conditions are met and the changes to the
plan are administrative in nature, the Coast Guard may issue interim
approval allowing continued operations.
* Vessels that have received an initial stage II review can receive
similar interim approval of their plans through October 31, 2004. The
Coast Guard Marine Safety Center reviewing vessel plans can issue such
approvals provided they are satisfied that the plans are sufficiently
complete and any needed changes are administrative in nature.[Footnote
22]
* Facilities and vessels that are not far enough along to receive
interim approval of their plans--for example, still making substantial
revisions to their plans--can also receive permission to continue
operations. The process is much the same as that described earlier for
interim approval. For facilities, after an on-site visit the Captain of
the Port may issue a letter to the owner or operator, identifying the
areas of the plan requiring significant revision and allowing the
facility to continue operations through October 31, on the condition
that temporary security measures are implemented while the security
plan continues to be reviewed. For vessels, the Marine Safety Center
reviewing the plans may similarly issue a letter authorizing a vessel
to continue operating, as long as conditions specified in the letter
are met while review of the plan continues.
* These approaches do not extend to facilities or vessels that have not
completed stage I of the review process. The Coast Guard will not allow
those facilities and vessels to operate after June 30, 2004. Thus,
owners or operators who have not submitted a complete facility plan for
Coast Guard review are to be shut down. According to the Coast Guard,
MTSA provides the Coast Guard with the necessary legal authority to
shut down any facilities or vessels in this situation, if
necessary.[Footnote 23]
Strategy for Monitoring and Oversight of Plan Implementation Faces
Numerous Challenges:
In late May 2004, the Coast Guard issued its strategy for monitoring
and overseeing the implementation of security plans after July
1.[Footnote 24] It is clear that this strategy faces a number of
challenges both in the short and longer term. The first challenge is
the amount of work required to conduct the initial review of compliance
inspections. Between July and December, the Coast Guard plans to
inspect every one of the 3,147 facilities and as many of the 9,194
vessels as possible to ensure that owners and operators are complying
with the actions called for in their security plans.[Footnote 25] These
inspections will need to determine whether vessel and facility
operators have identified all vulnerabilities and adequately addressed
them--a task made more difficult by the fact that most of the 5,923
plans developed under option B will not have received detailed review.
Other challenges facing the Coast Guard include ensuring that enough
inspectors are available, training them appropriately, and equipping
them with sufficient guidance to make difficult judgments about whether
owners and operators have taken adequate steps to address
vulnerabilities. The Coast Guard's attention has been understandably
focused on how to meet these challenges in the immediate "surge" of
monitoring activity between July and December.[Footnote 26] However, in
the longer term, when the Coast Guard plans to conduct annual
compliance inspections for the more than 12,300 facilities and vessels,
it faces the challenge of developing a strategy to ensure that owners
and operators continue implementing their plans.
Workload for Compliance Inspections Is Substantial, Potential Exists
for Finding More Vulnerabilities, and Assessing the Adequacy of
Security Preparation Is Difficult:
The initial volume of compliance inspections to be done is large and
time is limited. The Coast Guard expects to complete the first round of
on-site inspections of all 3,147 facilities, as well as the inspection
of as many vessels as possible, by January 1, 2005. During these
compliance inspections, inspectors are to assess the steps that each
port stakeholder has taken to put a security plan into place, such as
the extent to which access controls like fences, guards, gates, and
cameras are in place, or the extent to which the security drills
written in the plan are actually being conducted.[Footnote 27] Since
most of the 5,923 plans developed under option B were not reviewed by
the Coast Guard or its contractors, inspectors will also have to
consider not only whether these plans have been implemented but also
whether they adequately identify relevant vulnerabilities and specify
sufficient steps to address them.
One reason for caution with regard to the adequacy of option B plans is
that there are indications that some owners and operators using option
B may not be fully aware of what they have to do to develop sufficient
plans, or, if they are aware of it, may be slow in complying. For
example:
* According to the Coast Guard's MTSA security plan program manager,
the agency's interactions with option B users showed that some of them
erroneously believed that membership in an industry or trade
organization with approved standards and templates satisfied their
obligation to implement a security plan.
* In some cases, the use of option B appeared to be a way of postponing
the completion of a security plan. For example, after being advised by
the Coast Guard that he missed the deadline for submitting a security
plan, one stakeholder joined an industry organization for the sole
purpose of using option B to avoid having to immediately write a
security plan. Another vessel operator we visited 2 weeks before the
deadline to submit security plans said he was using option B as a means
to gain an extra 6 months to complete the security plan.
Even among plans developed and reviewed under option A, there are
indications that the inspections may reveal additional vulnerabilities
or, for cost reasons, the disparity between actions prescribed in the
plans and actions actually implemented. For example:
* An official at a major port told us that more security
vulnerabilities were known than were included in the facility security
plan, these vulnerabilities were not included because money was not
available to address them. This port official said the port would await
the Coast Guard's review to see if the Coast Guard would identify any
of these vulnerabilities and require mitigating actions.
* Several owners and operators of facilities and vessels also told us
that funding was a major challenge. Although they did not indicate that
they omitted vulnerabilities from their plans, these owners and
operators told us that it would be difficult to obtain the financial
resources to fully mitigate their known vulnerabilities.
Compliance inspections will also be challenging because they involve
subjective evaluations about the adequacy of security measures. The
facility and vessel plans created by port stakeholders are performance-
based, meaning the Coast Guard has specified the outcomes it is seeking
to achieve and has given port stakeholders responsibility for
identifying and delivering the measures needed to achieve these
outcomes. While this approach provides flexibility to owners and
operators in designing and implementing their plans, it also places a
premium on the skills and experience of inspectors to identify
deficiencies and recommend corrective action. For example, inspectors
will have to determine if the security measures outlined in the
approved security plan adequately address the security vulnerabilities
identified in the security assessment, which the Coast Guard regards as
by far the most difficult step in the compliance inspection process.
Whether Sufficient Inspection Personnel Will Be Available Is Not Clear:
Another challenge the Coast Guard faces is ensuring that it has enough
qualified inspectors to complete all the inspections required during
the surge period. The Coast Guard estimated the need for and then
allocated an additional 282 positions, or "billets," to local marine
safety offices to supplement existing inspectors during this period.
The Coast Guard did not have a great deal of workload data to use in
making this estimate; as we have pointed out in other reports, the
agency does not have a system in place for determining how much time
its personnel are spending on specific duties.[Footnote 28] The Coast
Guard told us that it made its determination of how many additional
positions would be needed by using working groups, expert panels,
available data, and information about resources in port security
missions since the September 11, 2001, terrorist attacks.[Footnote 29]
While the Coast Guard thus had some basis for determining how many more
staff it should assign to complete the work on time, the approach stops
well short of providing demonstrable evidence of its validity. The
Coast Guard based its projection in part on past experiences with
environmental and safety inspections, but whether those types of
inspections are analogous is unclear. Further, the Coast Guard could
not provide documentation of the approach it used, limiting its ability
to assess the adequacy of its decision.
The Coast Guard also faces challenges in ensuring that it has the right
mix of skills and experience among these additional personnel. The
Coast Guard's staffing estimate does not specify what rank or type of
personnel are required to complete the surge inspections. According to
Coast Guard documents, none of the job functions for the additional 282
personnel working on compliance inspections have been detailed.
Further, of the additional 282 positions, about 75 percent are
reservists who are scheduled to be available for only a limited time.
Most are scheduled for deactivation in October 2004 - in the middle of
the surge period - though the Coast Guard has the ability to extend
their tour of duty. All of these challenges - the uncertainty of the
estimate, the lack of specificity about what personnel are needed, and
the reliance on personnel who may become unavailable --increase the
overall challenge of ensuring that the first round of compliance
inspections is effective, especially given the subjective evaluations
that are required.
Training Will Need to Overcome Disparity in Skills and Experience among
Inspectors:
The skills and prior inspection experience of the reservists who will
be assigned to supplement existing inspectors varies widely. Some have
graduate degrees in security management, while others have no formal
security training or prior experience. For example, in New Orleans, 1
of 7 reservists assigned to support local inspectors had previous
inspection experience, while in New York, at least 9 out of 19
reservists assigned to this task had previous inspection experience.
The disparity in experience levels raises the possibility that
personnel with little inspection experience will be less able or
equipped to identify deficiencies or assess the adequacy of security
efforts. This has implications for creating variation in the
rigorousness with which inspections are conducted from location to
location and port to port.
The Coast Guard has acknowledged this disparity and is taking steps to
address it, but these steps still carry challenges:
* The Coast Guard developed required training for all staff who would
be conducting port security compliance inspections. This training
lasted for 5 days and consisted of computer-based instruction,
classroom training from security experts, and other
coursework.[Footnote 30] It could be completed either by attending
program sessions at various locations or through tutoring from other
staff who had attended the training. As of mid-June, the Coast Guard
reported that more than 500 persons had completed this training.
Whether this training will be sufficient to overcome the skill and
experience disparities among inspection staff remains uncertain,
particularly since some inexperienced staff may receive the training
second-hand. Coast Guard officials said that one reservist with little
experience might be sent to the training, while another with similar
experience might be taught by a fellow reservist who attended. Thus, a
challenge the Coast Guard faces is to discern the extent to which each
inspector has mastery of the subject matter.
* To emphasize on-the-job-training and to try to improve the
consistency during the compliance inspection process, the Coast Guard
plans to pair inspectors with little previous experience with more
experienced inspectors. This will be especially critical when reviewing
the 234 facilities and 5,689 vessels using option B plans, since those
plans did not undergo a detailed review. However, the time that
reservists will need for such on-the-job experience before they can
contribute to the inspection process is unknown and could affect the
quality of the inspections and the Coast Guard's ability to complete
all of the inspections during this surge period.
Developing Inspection Guidance for a Performance-Based Inspection
Process Is Difficult:
A concern consistently raised by stakeholders is that if enforcement of
the security requirements varies from port to port, there will not be a
uniform standard of security across the nation. This inconsistency has
two main effects: First, it may create the potential for disparities in
stakeholder compliance and gaps in security. Second, aside from the
potential implications on security, stakeholders operating in a port
where enforcement is more rigorous could be put at a competitive
disadvantage, in that they may have to spend more money implementing
security measures than required of similar stakeholders in other
locations. Stakeholders are concerned that such disparities could
affect competitiveness among companies in the same industry or, on a
broad level, competition among ports themselves.
The Coast Guard is aware of this issue, and its preparations include
ways to make the security inspection process more uniform. In addition
to the training program, the Coast Guard issued an inspection guide
that all inspectors will use during on-site inspections.[Footnote 31]
The primary tool in the guide is a checklist that inspectors can use as
a "roadmap" to ensure that all areas of the security plans are covered
when inspecting a facility or vessel. The guide also provides
inspectors with scalable recommended penalty measures to consider,
given the severity and nature of the deficiencies found during an
inspection.
While a compliance guide is likely to provide some assistance to the
inspector, a key challenge to its usefulness during this surge
inspection period is the performance-based nature of the evaluation,
which makes it difficult to cover all the circumstances an inspector
may encounter. Inspectors will not check for compliance with a specific
procedure; instead, they will have to make a judgment about whether the
steps the owner or operator has taken, considered together, provide
adequate security. Although the security plans are required to contain
similar elements, they do not have to be identical, nor do they need to
address security vulnerabilities using the same mitigations. Facilities
and vessels may have different - yet reasonable - methods for
addressing the same vulnerability. This subjective nature of the
evaluation process has raised concerns among port stakeholders. Given
their experience with existing Coast Guard safety and environmental
inspection programs, several local port stakeholders we spoke with said
they did not think the Coast Guard had been consistent in its
administration of regulations across inspectors and offices. These port
stakeholders said they did not think the same standards had been
applied to other, similar operations as were applied to their own
organization. We did not assess the validity of these concerns, but the
Coast Guard regards this issue as the greatest implementation challenge
the agency faces.
Lessons Learned during Surge Period Should Help in the Development of
Strategy for Longer-Term Monitoring and Oversight Responsibilities:
While the Coast Guard is understandably focused on the initial surge
period for compliance inspections, it will soon need to decide how to
staff and conduct inspections on a longer-term basis. Accordingly, what
Coast Guard officials learn during the surge phase should help them
determine how to staff and conduct effective compliance inspections.
Many of the elements of this longer-term strategy will likely have to
deal with the same basic challenges faced during the surge period:
ensuring that enough personnel are available, training them well, and
equipping them with necessary guidance. These challenges will be
particularly important to overcome considering the frequency with which
Coast Guard personnel rotate to new positions within the Coast
Guard.[Footnote 32] Port stakeholders told us that the discontinuity
caused by these rotations creates gaps in expertise among personnel,
which ultimately leads to inconsistent application of the regulations.
According to Coast Guard officials, becoming a fully proficient
inspector takes time, and when inspectors do become proficient they
often face reassignment.
To address MTSA requirements and coordinate with its other annual
inspections, the Coast Guard plans to conduct security plan compliance
inspections annually for each of the more than 12,300 facilities and
vessels. MTSA requires that facility and vessel owners and operators
update and resubmit their security plans to the Coast Guard every 5
years or whenever a substantial change is made to their facility or
vessel. As another component of its longer-term compliance strategy,
the Coast Guard stated in its recently issued guidance that Captains of
the Port may verify continued compliance with the security plans at any
time through intervening inspections between the required annual
inspections. This critical responsibility of providing effective
national maritime security through monitoring and oversight emphasizes
the importance of a sound longer-term strategy.
While the strategy has yet to be implemented, it is important that
challenges be overcome in order to help ensure detection of
noncompliance with MTSA requirements. As the Coast Guard continues to
enhance its strategy, there are other options it can consider besides
regularly scheduled annual compliance inspections and the intervening
inspections. For example, our work assessing other areas such as
airport security and regulatory compliance[Footnote 33] has identified
approaches for ensuring compliance and improving and strengthening
security such as unscheduled and unannounced inspections, on weekends
or after normal working hours,[Footnote 34] and covert
testing.[Footnote 35] In fact, Coast Guard officials responsible for
facility and vessel inspections indicated that unscheduled inspections
would be a positive component of a longer-term strategy because
informing owners or operators of annual inspections can allow them to
mask security problems by preparing for inspections in ways that do not
represent the normal course of business.
Cost to Comply with MTSA Is Uncertain:
Although the Coast Guard made a good-faith effort in preparing its
estimate of $7.3 billion for maritime industry compliance with MTSA
security-related requirements, the estimate needs to be viewed with
some caution, because (1) the Coast Guard had to assume values for a
number of cost factors for which there was incomplete data and (2) it
had limited time to prepare the estimate. The Coast Guard was unable to
gather further information to ensure the accuracy of these values or to
determine how other values for these same factors would affect cost.
The $7.3 billion estimate covers a 10-year period of time (2003-2012)
and more than 90 percent of it is for the costs to be incurred by
vessel and facility owners to increase security. The Coast Guard
estimated the cost of securing facilities at $5.4 billion and the cost
of securing vessels at $1.4 billion. (The remaining portion of the
estimate was for outer continental shelf facility security, area
maritime security, and automatic identification system requirements.)
Appendix III explains how the Coast Guard developed these estimates.
The accuracy of an estimate is often tied to such factors as the
complexity or straightforwardness of the issue, the quality of data and
validity of the underlying assumptions, and the length of time
available to do the work. The Coast Guard faced a number of challenges
in dealing with each of these factors. Major challenges included the
following:
* Limited opportunity for expert involvement. Although the Coast Guard
worked with a panel of experts to develop the estimate, Coast Guard
officials said that time limitations precluded making the panel as
widely representative of industry and government as possible. They also
said that time limitations precluded an extensive set of meetings over
the course of many months, which would have allowed the expert panel to
make more useful contributions.
* Limited opportunity to analyze data or to test the uncertainty of
estimates. The Chief of the Standards Evaluation and Analysis Division,
who was the official responsible for developing the estimate, said that
if more time had been available, the Coast Guard would have analyzed
more data. Moreover, he said, the Coast Guard would have conducted a
sensitivity analysis of the estimate to determine how changes in the
underlying assumptions would affect the size of the estimate. Analyzing
uncertainty in this way is consistent with best practices for preparing
benefit-cost analysis of significant regulatory actions called for by
Executive Order No.12866, which applies to the Coast Guard's
analysis.[Footnote 36] For illustrative purposes, we conducted such an
analysis and found that the Coast Guard's cost estimate of $7.3 billion
could be more than $1 billion higher or lower, using generalized
assumptions about cost uncertainty. That is, the estimate of $5.4
billion for securing facilities could range from $4.5 billion to $6.4
billion, and the estimate of $1.4 billion for securing vessels could
range from $1.2 billion to $1.5 billion.
* Questionable validity of some key assumptions. The estimated $5.4
billion for securing facilities--the single biggest item--depends on
key assumptions, which the Coast Guard has acknowledged are of
questionable validity. For example, facilities are likely to vary in
the extent to which they already have adequate security measures in
place, and since no comprehensive data existed on the security
preparations in place, Coast Guard officials had to make an educated
guess about the extent of progress and the amount of additional
security steps that would need to be taken. This is significant because
the Coast Guard assumes facilities have already spent $17 billion on
these security measures before MTSA requirements take effect. Thus,
variation in these percentages can potentially have a sizable effect on
costs. Another example is the Coast Guard also assumed that one-third
of all facilities will have to spend about 60 percent more on security
equipment than the remaining two-thirds of facilities will have to
spend. However, some of the facilities in the lower-cost group will
expand in the future to handle additional cargo resulting from economic
growth, requiring more security and, therefore, placing more facilities
than currently assumed in the higher-cost group. This can also have a
substantial effect on costs. For example, assuming that 40 percent,
rather than 33 percent, of all facilities fit in the higher-cost
category, adds over $350 million to the costs of implementing these
rules.
* Limited span of time included in the analysis. The Coast Guard's
estimate covers a 10-year period beginning in 2003 and ending in 2012.
However, MTSA security-related requirements are not limited to a 10-
year period. Extending the period of analysis is also consistent with
best practices for preparing economic analysis of significant
regulatory actions called for by Executive Order No.12866.[Footnote 37]
Extending the Coast Guard's analysis by 10 years to 2022 raises the
estimate of total costs by nearly 50 percent to $10.7 billion. Total
costs continue to rise past 2012 because another $884 million in
operation and maintenance, equipment replacement, and security guard
costs are incurred with each additional year.[Footnote 38]
* Some potential costs not considered. The Coast Guard's estimate does
not include costs associated with possible delays in moving goods
through more secure facilities, or account for higher prices for goods
and services that could result if the maritime transportation industry
tries to pass along higher security costs to its customers. For
example, higher shipping rates could mean reduced water transportation
services and reduced consumption and production of goods dependent on
those services and associated economic losses.[Footnote 39]
In the absence of complete data, the Coast Guard relied on public and
stakeholder comments to determine if its estimate was valid. The Coast
Guard held seven public meetings to discuss its estimate and said it
received few negative comments. Given the limited time available,
relying on such comments to identify large errors makes practical
sense. There likely are limitations, however, in the extent to which
the various stakeholders were in a position to comment on the validity
of the estimate. For example, large cost differences between individual
facilities or vessels could make it difficult to judge the accuracy of
the Coast Guard's estimates of average facility or vessel costs.
The net effect of these limitations on the Coast Guard's estimate is
unknown. However, it should also be pointed out that enhancing security
could lower costs to society at large if implementing MTSA foils a
terrorist attack and thereby prevents a costly disruption. For example,
in 2002, U.S. ports handled $764 billion in international trade, or
more than $2 billion per day. An event that disrupts this trade could
have a substantial effect on the flow of goods, as well as a
substantial impact on the larger economy.
Conclusions:
The vulnerability of the nation's ports and the importance of
addressing these vulnerabilities cannot be overemphasized. Since MTSA's
enactment in November 2002, the Coast Guard has worked hard to address
these vulnerabilities by spurring the development of meaningful
security plans for thousands of facilities and vessels in the nation's
ports. Progress has been made, though the extent to which all
facilities and vessels will have adequate plans ready to implement as
of July 1, 2004, is still unclear. This is particularly true for the
thousands of self-certified plans. The Coast Guard has approved the
guidelines and templates for these plans, but in most instances it has
not seen the plans themselves.
As hard as the Coast Guard has worked to ensure that plans are
developed, the most important part of the process still lies ahead
because plans mean little if they do not actually produce better
security. Many challenges lie ahead as the Coast Guard attempts to
develop a complete picture of the security environment at the nation's
seaports and take whatever actions are needed, when they are needed to
protect those ports. The uncertainty about whether the Coast Guard will
be able to meet its timeframes for conducting on-site compliance
inspections of the more than 12,300 facilities and vessels and
questions about whether it will have enough staff and a sufficient
experience base to handle so many inspections will undoubtedly
challenge management and staff to effectively implement the strategy.
In addition, the complexity of compliance inspections that call for
sophisticated judgments about vulnerabilities and the actions taken to
address them will likely create the need for up-to-date training and
guidance to help ensure that such decisions are thorough and
consistent. During the initial surge period, these challenges make it
important for the Coast Guard to carefully evaluate its efforts, so
that problems or inadequacies can be identified. In the longer term,
the Coast Guard can benefit from the lessons learned from this
evaluation and use them to refine its long-term inspection strategy.
Several points stand out in particular as important in this evaluation
effort.
* First, the inspection program the Coast Guard has established is an
important feature of its strategy to improve port security. Having
qualified inspectors is key to this effort. While the training the
Coast Guard has adopted is an important step to build inspector skills
and compensate for differences in their skills and experience, training
alone does not provide assurance that those who conduct inspections are
qualified. Nor does it substitute for policies on the professional
development standards inspectors must meet. Filling these gaps takes on
added significance given the criticality of inspectors' roles and the
discretion they are anticipated to exercise.
* Second, the long-term strategy also needs to reflect a way to ensure
that the security inspections assess conditions that represent the
normal course of business at facilities and aboard vessels. One way to
do this is to include conducting unscheduled and unannounced
inspections and covert testing to provide additional information that,
taken together with the results of annual compliance inspections,
should provide better assurance that MTSA requirements are being
implemented effectively.
Recommendation for Executive Action:
To better ensure that MTSA requirements are being implemented
effectively, we recommend that the Secretary of Homeland Security
direct the Commandant of the Coast Guard to:
* conduct a formal evaluation of compliance inspection efforts taken
during the initial 6-month surge period, including the adequacy of
security inspection staffing, training, and guidance, and use this
evaluation as a means to strengthen the compliance process for the
longer term. As part of this strategy, the Coast Guard should clearly
define the minimum qualifications for inspectors and link these
qualifications to a certification process. The Coast Guard should also
consider including unscheduled and unannounced inspections and covert
testing as part of its inspection strategy to provide better assurance
that the security environment at the nation's seaports meets the
nation's expectations.
Agency Comments:
We provided a draft of this report to the Department of Homeland
Security and the Coast Guard for their review and comment. The Coast
Guard generally agreed with the facts presented in the report and with
the recommendation we made. The Coast Guard said our recommendation was
reasonable and that the Coast Guard should certainly study its progress
and make changes when necessary. Coast Guard officials also provided a
number of technical clarifications, which we incorporated to ensure the
accuracy of our report.
In its response, the Coast Guard raised one area where it disagreed
with our presentation. This disagreement focused on how to characterize
the Coast Guard's review of the Option B plans, which the Coast Guard
refers to as "alternative security programs." The Coast Guard contended
that its work on ASPs amounted to an approval of the plans themselves.
The Coast Guard's comments in this regard were as follows:
"GAO states ASPs provide a 'template' and 'framework' for a plan, but
not an actual plan. The ASPs were developed in the months leading up to
the 31 December 2003 plan submission deadline, and hundreds of
personnel-hours were spent working with the many industry associations
used to ensure the template, when properly completed with appropriate
details for a specific vessel/facility, would be a viable security plan
to mitigate vulnerabilities for the vessel or facility type identified
by the industry association. In fact, more hours were dedicated to each
ASP than any individual plan, and as a result, the ASP templates
produced a repeatable security plan precluding the need to have each
completed template individually review by 1 July. Indeed, the CG
considers them as approved security plans that must be implemented by 1
July. Primary burden is on the owners to comply with all applicable
regulations. Our role is to ensure it is being done; 'Trust, but
Verify'."
While we agree that the Coast Guard spent considerable time and effort
reviewing and approving the templates and that this approach was
understandable given the limited time available, we disagree with the
Coast Guard's view that its actions should be considered as reviewing
and approving the 5,900 individual Option B plans. The Coast Guard did
not individually review and approve these plans; it reviewed and
approved only the templates. The Coast Guard notes that Option B
security plans would be viable only when "properly completed with
appropriate details for a specific vessel/facility". Since the Coast
Guard did not individually review the Option B plans; it does not know
whether the plans have been properly completed.
This is more than a technical issue: We believe the distinction is
important because the missing reviews add to the challenges the Coast
Guard will face in its post-July 1 workload. The Coast Guard's
extensive review of the 6,400 individual Option A plans found
deficiencies in every single plan, raising concerns about how complete
the 5,900 individual Option B plans are likely to be when Coast Guard
inspectors arrive to conduct their inspections. Our discussions with
Coast Guard officials and our visits to seven ports around the country
provided indications that some owners and operators using Option B may
not be fully aware of what they have to do to develop sufficient plans,
or if they are aware of it, may be slow in complying. For example, the
Coast Guard program manager stated that interactions with Option B
users showed that some of them erroneously believed that membership in
an industry or trade organization with approved standards and templates
satisfied their obligation to implement a security plan. During our
site visits, some port stakeholders told us that they were using Option
B as a means to avoid preparing a security plan until July 1 while
remaining in compliance with Coast Guard requirements. For all of these
reasons, we chose not to change this aspect of our report.
If you or your staffs have any questions about this report, please
contact me at (415) 904-2200 or at wrightsonm@gao.gov or Steve Calvo,
Assistant Director, at (206) 287-4800 or at calvos@gao.gov. Key
contributors to this report are listed in appendix IV. This report will
also be available at no charge on the GAO Web site at http://
www.gao.gov.
Signed by:
Margaret T. Wrightson,
Director, Homeland Security and Justice Issues:
[End of section]
Appendix I: Objectives, Scope, and Methodology:
Our first two objectives involved the security plans being developed
for facilities and vessels. Specifically,
* assessing the progress made to develop, review, and approve the
security plans for facilities and vessels by July 1, 2004.
* assessing the U.S. Coast Guard's monitoring and oversight strategy
for ensuring that all necessary port security improvements are
implemented.
We conducted a variety of work to assess key steps in the Coast Guard
process for developing, reviewing, approving, and overseeing the
implementation of security plans. These key steps in the process
included the following:
* Identifying all the vessels and facilities that are subject to the
requirement to develop plans.
* Ensuring that all identified parties have submitted plans for Coast
Guard review.
* Reviewing all plans, identifying any deficiencies and ensuring their
correction, and approving the completed plan.
* Establishing resources and an action plan to monitor implementation
and compliance with requirements.
We carried out part of our work at Coast Guard headquarters or in
consultation with headquarters officials. In this regard, we reviewed
pertinent legislation, guidance, rules, and implementation documents to
identify the purpose, objectives, process, enforcement strategy, and
resources required to review and approve the security plans. We spoke
with headquarters officials and reviewed relevant documentation to
determine the management and methodology being used to address the
implementation of the Maritime Transportation Security Act (MTSA). We
met with MTSA's program manager and team to determine how they expected
to review and approve the security plans before the July 2004 deadline,
what resources and action plans are in place to oversee implementation
after July 2004, what training program was needed to produce capable
staff to perform inspections, how the staffing estimate for MTSA
implementation was made, and what guidance would be provided to local
inspectors and Captains of the Port to carry out MTSA implementation.
As part of our work in evaluating the process for reviewing security
plans, we visited the Coast Guard's contractors at the Marine Safety
Center in Washington, D.C., and the National Facility Security Plan
Review Center in Overland Park, Kansas. During these visits, we also
talked with contractor management and staff to determine how the review
process worked, what reviewers were finding in the plans during their
reviews, how deficient plans were dealt with, and what internal
controls and quality assurance mechanisms were in place to ensure
consistency during the review process. We also interviewed Coast Guard
staff with the contractor staff at the review centers to determine the
extent of their oversight roles and responsibilities in monitoring the
contractors' performance.
We reviewed more site-specific planning and implementation activity
through work conducted at seven specific maritime port areas. We
selected these seven ports to provide a diverse sample of security
environments and perspectives, basing our selections on such matters as
geographic location, varying levels of strategic importance, and unique
local characteristics. The seven ports and some of our reasons for
choosing them are as follows:
* Corpus Christi, Texas: a Gulf Coast port that is a major port for
military loadouts and important site for petroleum refining and
chemical production.
* Huntington, West Virginia: a major inland river port and has a
significant presence of critical chemical and petroleum producers.
* Los Angeles/Long Beach, California: the largest container port in the
country.
* San Diego, California: a port that includes many military facilities
and installations.
* Seattle/Tacoma, Washington: the third largest container traffic port
in the country, and the port with the country's largest passenger ferry
system.
* New Orleans, Louisiana: a large river port with many types of
industrial and other facilities.
* New York, New York: another of the nation's largest container ports,
and the site of the September 11th terrorist attacks.
During each of our visits to these seven ports we met with port
stakeholders, Coast Guard marine safety offices, and Captains of the
Port. The specific stakeholders we talked with at each port are listed
in table 3. When we met with these stakeholders, we discussed the
security assessments they had conducted, the facility or vessel
security plans they were developing, any problems they had in
developing those plans, and any assistance provided by the local Coast
Guard during the process. When we met with Captains of the Port and
marine safety offices, we discussed the extent to which they had
identified all facilities and vessels under MTSA regulations within
their port area, the outreach they provided to help stakeholders meet
the statutory deadlines and understand MTSA requirements, the process
they will use to ensure compliance after July 2004, and their general
perspectives on MTSA requirements. We also attended several meetings
put on by local marine safety offices, including a MTSA stakeholder
forum, Area Maritime Security Committee (AMSC) meetings, and AMSC
subcommittee meetings.
Table 2: Port Stakeholders GAO Contacted at Port Locations Reviewed:
Port area: Corpus Christi, Texas;
Stakeholders: United States Coast Guard Marine Safety Office Corpus
Christi.
Stakeholders: The Port of Corpus Christi.
Stakeholders: Occidental Chemical Corporation.
Stakeholders: Sherwin Alumina Company.
Stakeholders: Valero Refining-Texas, LP.
Stakeholders: Aransas-Corpus Christi Pilots.
Stakeholders: Kirby Inland Marine, LP.
Stakeholders: Union Pacific Railroad.
Stakeholders: United States Bureau of Immigration and Customs
Enforcement.
Stakeholders: Boyd-Campbell Company.
Stakeholders: Flint Hills Resources, LP.
Port area: Huntington, West Virginia;
Stakeholders: United States Coast Guard Marine Safety Office
Huntington.
Stakeholders: West Virginia Department of Transportation, Public Port
Authority.
Stakeholders: Union Carbide Corp.
Stakeholders: Sunoco, Inc. (Haverhill, OH).
Stakeholders: American Electric Power (Columbus, OH).
Stakeholders: Bayer CropScience.
Stakeholders: Marathon Ashland Petroleum, LLC (Catlettsburg, KY).
Stakeholders: United States Army Corps of Engineers.
Stakeholders: West Virginia Office of Emergency Services.
Stakeholders: Kirby Inland Marine, LP.
Port area: Los Angeles, California;
Stakeholders: United States Coast Guard Marine Safety Office Los
Angeles/Long Beach.
Stakeholders: The Port of Los Angeles.
Stakeholders: The Port of Long Beach.
Stakeholders: Marine Exchange of Southern California.
Stakeholders: Long Beach Container Terminal, Inc.
Stakeholders: Crowley Marine Services, Inc.
Stakeholders: APL Limited.
Stakeholders: Union Pacific Railroad.
Port area: San Diego, California;
Stakeholders: United States Coast Guard Marine Safety Office San Diego.
Stakeholders: Port of San Diego.
Stakeholders: United States Navy.
Stakeholders: California Highway Patrol.
Stakeholders: San Diego Harbor Police.
Stakeholders: National Steel and Shipbuilding Co.
Stakeholders: Continental Maritime.
Stakeholders: San Diego Harbor Excursion.
Stakeholders: United States Customs and Border Protection.
Port area: Puget Sound, Washington;
Stakeholders: United States Coast Guard Marine Safety Office Puget
Sound.
Stakeholders: Port of Seattle.
Stakeholders: Port of Tacoma.
Stakeholders: Washington State Ferries.
Stakeholders: Cruise Terminals of America.
Stakeholders: Husky Terminal & Stevedoring, Inc.
Port area: New Orleans, Louisiana;
Stakeholders: United States Coast Guard Marine Safety Office New
Orleans.
Stakeholders: Port of New Orleans.
Stakeholders: Port of South Louisiana.
Stakeholders: Union Carbide Corporation.
Stakeholders: Upper St. Rose Fleeting Co.
Stakeholders: Plaquemine Parish Ferry Department.
Stakeholders: Zen-Noh Grain Corporation.
Stakeholders: Chalmette Refining, L.L.C.
Stakeholders: Shell Exploration and Production Company.
Stakeholders: P & O Ports North America, Inc.
Stakeholders: United States Bureau of Immigration and Customs
Enforcement.
Port area: New York/New Jersey;
Stakeholders: United States Coast Guard Activities New York.
Stakeholders: The Port Authority of New York & New Jersey.
Stakeholders: General Chemical.
Stakeholders: Staten Island Ferry System.
Stakeholders: Lincoln Harbor Yacht Club.
Stakeholders: Maersk, Inc.
Stakeholders: Howland Hook Container Terminal, Inc.
Stakeholders: Maher Terminals, Inc.
Source: GAO.
[End of table]
We also met with officials from industry trade groups such as the
American Chemistry Council, American Association of Port Authorities,
and the Association of American Railroads to determine their perception
of MTSA requirements and the extent of interaction between port
stakeholders and Coast Guard nationwide.
Finally, we followed-up with all the ports we visited to collect
updated information on their respective progress in regard to our
objectives. We then compared the information gathered through
interviews and document analysis against pertinent criteria specified
in MTSA, the final rule, and other Coast Guard guidance to determine
the progress being made to develop vessel and facility maritime
security plans and determine the sufficiency of Coast Guard resources
and action plan to ensure that security plans are completed, reviewed,
approved, and implemented in a timely manner.
Our third report objective was to determine the accuracy of the Coast
Guard's estimates of the cost to comply with MTSA security planning and
implementation requirements. To address this objective, we reviewed
cost spreadsheets prepared by the Coast Guard documenting how cost
estimates were developed. We identified key cost assumptions and the
basis for the values assumed. Based on information about the basis for
these assumed values, we conducted Monte Carlo simulations to determine
the sensitivity of costs for facilities and vessels to generalized
assumptions about cost uncertainty. As part of this review, we
interviewed Coast Guard analysts responsible for these cost estimates.
Besides reviewing the cost spreadsheets, we reviewed documentation
provided by the Coast Guard to support its choice of assumed values. We
also asked Coast Guard officials responsible for these cost estimates
what steps they took to ensure the reliability of the underlying data
on which the estimates were based.
Our review was limited to security plans for facilities and vessels
operating in domestic ports and did not include foreign ports, foreign
flagged vessels, or the other security programs called for under MTSA.
We conducted our work from June 2003 to June 2004 in accordance with
generally accepted government auditing standards.
[End of section]
Appendix II: Required Security Plan Items:
Vessel security plans: A vessel owner or operator must ensure that his
or her plan consists of the individual sections listed below:
(1) Security organization of the vessel;
(2) Personnel training;
(3) Drills and exercises;
(4) Records and documentation;
(5) Response to change in MARSEC level;
(6) Procedures for interfacing with facilities and other vessels;
(7) Declarations of Security;
(8) Communications;
(9) Security systems and equipment maintenance;
(10) Security measures for access control;
(11) Security measures for restricted areas;
(12) Security measures for handling cargo;
(13) Security measures for delivery of vessel stores and bunkers;
(14) Security measures for monitoring;
(15) Security incident procedures;
(16) Audits and Vessel Security Plan amendments;
(17) Vessel Security Assessment Report;
Facility security plans: A facility owner or operator must ensure that
his or her plan consists of the individual sections listed below:
(1) Security administration and organization of the facility;
(2) Personnel training;
(3) Drills and exercises;
(4) Records and documentation;
(5) Response to change in MARSEC level;
(6) Procedures for interfacing with vessels;
(7) Declaration of Security;
(8) Communications;
(9) Security systems and equipment maintenance;
(10) Security measures for access control, including designated public
access areas;
(11) Security measures for restricted areas;
(12) Security measures for handling cargo;
(13) Security measures for delivery of vessel stores and bunkers;
(14) Security measures for monitoring;
(15) Security incident procedures;
(16) Audits and security plan amendments;
(17) Facility Security Assessment Report;
(18) Facility Vulnerability and Security Measures Summary (Form CG-
6025).
Source: 33 C.F.R. 104.405 and 33 C.F.R. 105.405.
[End of table]
[End of section]
Appendix III: Analysis of Coast Guard's Compliance Cost Estimates:
The Coast Guard estimated the maritime transportation industry will
spend $7.3 billion to develop and implement security plans through the
year 2012.[Footnote 40] Of this amount, the estimate for owners and
operators of facilities was $5.4 billion, and the estimate for owners
and operators of vessels was $1.4 billion. The remainder--about $500
million--was for outer continental shelf facility and area maritime
security and automatic identification system requirements. This
appendix focuses on how the estimates for facilities and vessels were
derived.
To make these estimates, the Coast Guard had to make a variety of
assumptions about such matters as how many facilities and vessels would
be affected, how extensive the planning and implementation efforts
would have to be, and how much of a security framework was already in
place that would go towards meeting MTSA requirements. The Coast Guard
had to develop its estimates within a relatively short time, and it had
limited amounts of data on which to base many of these assumptions.
Factors that need to be kept in mind in considering the estimates
include the uncertainties inherent in many of these assumptions, over
what time period the costs were calculated, and the extent to which
industry stakeholders had sufficient knowledge of their own to comment
meaningfully on the Coast Guard's results.
Estimates Required Assumptions about Many Important Components:
Several basic pieces of information were needed to compute the cost of
developing and implementing security plans for facilities and vessels,
and deriving these basic pieces of information involved making a
variety of assumptions. The nation's ports and waterways are sprawling
and diverse, and the facilities and vessels that are affected by MTSA
requirements vary greatly in size and complexity. Facilities, for
example, include not only port-operated docks and intermodal transfer
stations, but also petrochemical facilities, power plants, and
factories with hazardous materials. Developing the estimates involved
making educated guesses about such things as how much effort they would
have to expend on developing plans, what equipment and manpower would
be called for in their plans, and how far along they already were.
Number of Facilities and Vessels:
The Coast Guard first needed information on how many facilities and
vessels would be affected by the regulation. The Coast Guard counted
4,965 facilities and 10,234 vessels affected by the regulation and
assumed this tally would remain constant during the 10-year period of
analysis from 2003 to 2012. According to the Coast Guard, these numbers
were based on its Marine Safety Management System database, U.S. Army
Corps of Engineer's waterborne statistics data, and a Department of
Transportation database on ferries and terminals. The Coast Guard cited
two previous studies to support its assumption that the number of
facilities and vessels remain constant. First, in studying response
plans for oil spills, the Coast Guard said it had found little yearly
variation in facility numbers, because purchasing land and negotiating
permits is time-consuming and prohibits significant numbers of
facilities from entering and leaving the population. Second, in
analyzing fire suppression on towing vessels, the Coast Guard reported
very few vessels entering the domestic fleet, with the limited numbers
largely being offset by vessels exiting the fleet.
Extent of Security Planning and Implementation Efforts:
The Coast Guard next needed to determine how long it would take for
facilities and vessels to complete security plans and what types of
security measures they would need to take. Given the diversity of
facilities and vessels, the Coast Guard assumed that some would require
much more planning time and security measures than others. For
facilities, the Coast Guard assumed that one-third of the total (1,638
of the 4,965 facilities) would require more time to draft security
assessments and plans and would implement more security measures than
the remaining 3,327 facilities. For example, the Coast Guard assumed
that the 1,638 facilities would take 160 hours, on average, to draft
security assessments and plans, compared with 80 hours for 3,327 other
facilities.[Footnote 41] Regarding the security measures that would
need to be taken, the largest differences were in assumptions about the
number of security guards. The Coast Guard tailored requirements for
eight different facility types, such as container or break bulk
facilities, hazardous substance facilities, and ferry and passenger
terminals. For container or break bulk facilities, for example, the
Coast Guard assumed that those facilities that had greater security
needs would have 15 security guards, on average, compared with 4
security guards for those facilities with less extensive security
needs.
Similarly, the Coast Guard assumed different types of vessels will
require varying amounts of time to draft security assessments and plans
and varying amounts of security measures. All told, the Coast Guard
tailored security requirements by 26 vessel types. For these various
types of vessels, the Coast Guard established estimates for the amount
of planning time involved, the number of security personnel that would
be needed, and average requirements for such security equipment as
metal detectors, intrusion alarms, hand-held radios, locks, and lights.
The Coast Guard also assumed nontowing vessels will need more security
than towboats and barges and that companies with more than 10 vessels
will need more security than companies with 10 or fewer vessels.
To establish many of these facility and vessel security requirements,
the Coast Guard convened a self-described informal expert panel of
economists, program managers, and other Coast Guard personnel with
extensive field experience, including personnel currently stationed in
field units. This group estimated the type and number of pieces of
equipment and number of personnel required to comply with the
requirements based on the type and configuration of a vessel or
facility, locations of facilities, the average crew size aboard
vessels, and how the Coast Guard envisioned vessels and facilities
complying with the requirements. Because its requirements do not
mandate specific equipment or personnel but set performance standards,
the Coast Guard reported that it had to make broad assumptions about
how industry would comply with these regulations.
Costs for Security Planning and Implementation:
To translate the planning and implementation steps into a cost
estimate, the Coast Guard also needed to establish assumptions about
labor costs for each hour spent on security assessments and plans and
costs per unit for each type of security measure. According to the
Coast Guard, salaries for some personnel were based on previous
analyses for salvage and marine firefighting and requirements for
mechanical recovery and dispersants. Costs for security guards and
other security personnel for facilities were based on national data
from the Bureau of Labor Statistics along with a "loaded" labor factor
to account for fringe benefits to these personnel. Equipment costs were
based on product research and limited data received from industry
during comment periods.
When these cost factors were applied, the results indicated that the
one-third of facilities assumed to have more extensive planning and
security needs would spend about 60 percent more on security equipment
than the lower-cost group. Similarly, spending for security equipment
varied considerably between vessel types.
Extent to Which Adequate Security Measures Were Already in Place:
Another important assumption deals with the extent to which facilities
would already have security measures in place and, therefore, would not
incur additional costs to comply with MTSA requirements. Among
facilities, the Coast Guard assumed the level of prior investment
varied substantially, both by type of facility and by type of
equipment. According to the Coast Guard, many facilities, such as oil
terminals, cruise terminals, and those dealing with hazardous
materials, were already required to implement security measures under
preexisting regulation by states or various federal agencies. Table 3
presents the Coast Guard's assumptions about the percentage of
facilities that would need to purchase or enhance their security
measures. For example, the Coast Guard assumed that most ferry
terminals would need improvements with regard to gates, fencing, and
number of security guards, but that no ferry terminals would need to
improve their communications system.
Table 3: Coast Guard Assumptions about Extent of Prior Security
Preparation:
Type of facility: Container or break bulk;
Percentage of facilities needing to purchase or enhance security
measures: Communications system: 5%;
Gates: 30%;
Radio: 5%;
CCTV: 5%;
Lights: 5%;
Fencing: 5%;
Guards: 30%.
Type of facility: Dry bulk;
Percentage of facilities needing to purchase or enhance security
measures: Communications system: 0%;
Gates: 70%;
Radio: 70%;
CCTV: 10%;
Lights: 60%;
Fencing: 20%;
Guards: 70%.
Type of facility: Hazardous bulk liquid;
Percentage of facilities needing to purchase or enhance security
measures: Communications system: 5%;
Gates: 10%;
Radio: 5%;
CCTV: 5%;
Lights: 5%;
Fencing: 5%;
Guards: 10%.
Type of facility: Hazardous substance (other);
Percentage of facilities needing to purchase or enhance security
measures: Communications system: 5%;
Gates: 5%;
Radio: 5%;
CCTV: 5%;
Lights: 5%;
Fencing: 5%;
Guards: 5%.
Type of facility: Nonhazardous bulk liquid;
Percentage of facilities needing to purchase or enhance security
measures: Communications system: 10%;
Gates: 10%;
Radio: 10%;
CCTV: 10%;
Lights: 10%;
Fencing: 10%;
Guards: 10%.
Type of facility: Fleeting areas;
Percentage of facilities needing to purchase or enhance security
measures: Communications system: 5%;
Gates: 0%;
Radio: 5%;
CCTV: 10%;
Lights: 0%;
Fencing: 0%;
Guards: 10%.
Type of facility: Ferry terminals Group A;
Percentage of facilities needing to purchase or enhance security
measures: Communications system: 0%;
Gates: 60%;
Radio: 5%;
CCTV: 10%;
Lights: 10%;
Fencing: 50%;
Guards: 60%.
Type of facility: Ferry terminals Group B;
Percentage of facilities needing to purchase or enhance security
measures: Communications system: 0%;
Gates: 80%;
Radio: 5%;
CCTV: 10%;
Lights: 10%;
Fencing: 50%;
Guards: 80%.
Type of facility: Passenger terminals;
Percentage of facilities needing to purchase or enhance security
measures: Communications system: 5%;
Gates: 5%;
Radio: 5%;
CCTV: 5%;
Lights: 5%;
Fencing: 5%;
Guards: 5%.
Source: GAO analysis of Coast Guard data.
[End of table]
Many Assumptions Carry Limitations:
Many of these assumptions carry limitations that need to be kept in
mind in assessing the reliability of the estimate. For example, the
assumptions reflected in table 3 above are based on incomplete data and
a response rate from Coast Guard field units that the Coast Guard
acknowledges seriously limit the reliability of any results. This is
significant because the Coast Guard assumes facilities have already
spent $17 billion on these security measures before MTSA requirements
take effect. Thus, variations in the percentages shown in table 3 can
have a potentially huge effect on costs. Actual costs to comply with
the final rules could thus differ substantially from what the Coast
Guard estimated because of simplifying assumptions that had to be made
in the absence of complete data. In a number of cases, the Coast Guard
cannot say if the value it assumed for a particular cost factor is the
most likely one to occur, or likely to be too low or high.
Even relatively small changes in some of these assumptions can have a
substantial effect on results. One example can be seen in changing the
assumption about the percentage of facilities needing more extensive
security measures. The Chief of the Standards Evaluation and Analysis
Division said that some facilities would likely expand in the future to
handle additional cargo resulting from economic growth. This expansion,
in turn, could require more security and potentially place more
facilities than currently assumed in this higher-need group. For
example, assuming that 40 percent of facilities should be in this
higher-need group rather than the current 33 percent increases the cost
estimate by over $350 million.
Limited Time to Estimate Costs Precluded More Extensive Data Collection
and Analysis of Uncertainty:
According to Coast Guard officials, the agency had only a matter of
weeks to prepare its cost estimate, and the estimate had to be prepared
without the benefit of extensive background research, vendor surveys,
and field inventories. The Chief of the Standards Evaluation and
Analysis Division, the Coast Guard official responsible for estimating
costs, explained that had the Coast Guard more time they would have
analyzed more data. Likewise, while the Coast Guard took the step of
working with an expert panel, Coast Guard officials said this effort
was not as extensive or sustained as under ideal circumstances. Time
permitting, Coast Guard officials said, they would have convened an
expert panel that included members of industry, nongovernmental
organizations, and other government agencies, and this panel would have
met multiple times over the course of many months, if not years.
Coast Guard officials also said that if time had permitted, they would
have analyzed uncertainty in their estimate by conducting sensitivity
or other analyses to determine how variations in these assumptions
would change the cost estimate. Analyzing uncertainty in this way is
consistent with best practices for preparing economic analysis of
significant regulatory actions called for by Executive Order 12866,
which applies to the Coast guard's analysis.[Footnote 42] For
illustrative purposes, we conducted a Monte Carlo analysis using the
Coast Guard's cost models for facilities and vessels.[Footnote 43] We
found that the Coast Guard's cost estimate of $7.3 billion could be
more than $1 billion higher or lower using generalized assumptions
about cost uncertainty. This results from finding that the Coast Guard
estimate of $5.4 billion to secure facilities could range from $4.5
billion to $6.4 billion, and its estimate of $1.4 billion to secure
vessels could range from $1.2 billion to $1.5 billion.
Cost Estimate Spans Only 10 Years and Does Not Include All Costs:
The Coast Guard has estimated it will cost $7.3 billion to develop and
implement security plans from 2003 to 2012, but MTSA security related
requirements are not limited to a 10-year period. Extending Coast
Guard's analysis by 10 years to 2022 raises total costs by nearly 50
percent to $10.7 billion. Extending the period of analysis is
consistent with best practices for preparing economic analysis of
significant regulatory actions called for by Executive Order
12866.[Footnote 44]
Figure 4 shows the trajectory of total costs as the time period of
analysis is extended, holding the number of facilities and vessels
constant. Total costs continue to rise past 2012 because another $884
million in operation and maintenance, equipment replacement, and
security guard costs are incurred with each additional year.[Footnote
45]
Figure 4: Projection of Estimated Costs, 2012-2022:
[See PDF for image]
[End of figure]
The Coast Guard's estimate also does not include several types of
costs:
* The estimate does not extend to costs beyond the maritime
transportation industry. For example, it does not include costs
associated with possible delays experienced by users in gaining access
to more secure port facilities and the services they provide. It also
does not include incremental costs borne by the Coast Guard to develop
and enforce these new requirements.
* The estimate does not address higher prices for goods and services as
the maritime transportation industry tries to pass along higher
security costs to its customers. For example, higher shipping rates
could mean reduced water transportation services and reduced
consumption and production of goods and services dependent on those
transportation services and associated economic losses.[Footnote 46]
* The Coast Guard has also estimated an additional $5 billion to meet
an elevated threat level, which is not included in its $7.3 billion
estimate.[Footnote 47] It assumed a code orange alert occurs twice a
year, with each elevated alert lasting 21 days. Increased personnel
time is the primary cost. For example, vessel security officers and key
crewmembers are assumed to work 16 hours per day during each elevation.
For facilities, the number of security guards is doubled.
While the points noted above would add to the cost estimate, it should
also be noted that other considerations could have the opposite effect.
For example:
* Some facility and vessel owners may take steps to exempt themselves
from the requirements, thereby lowering total costs. For example, some
passenger vessel operators could elect to transport fewer people,
placing their vessels into categories that do not have to comply with
MTSA requirements. Other vessel operators could choose to no longer
transport certain types of cargo and thus similarly become exempt.
However, these mitigating actions on the part of vessel and facility
owners may not be costless. For example, restrictive actions like those
described may result in added costs to users of these transportation
services.
* On the facilities side, companies will have an incentive to
collaborate in designing collective security systems where
opportunities exist to enhance security at less cost than if each
company acted alone. For example, adjoining facilities may have
opportunities to exploit possible cost economies in surveillance,
access control, and communications. Moreover, because requirements to
develop and implement security plans incorporate a performance-standard
approach, there is flexibility in how a facility or vessel can comply,
which could encourage lower-cost solutions than assumed by the Coast
Guard. In addition, re-examining existing security arrangements as a
result of the new requirements could lead to replacing some older, less
cost-effective measures.
* Steps to enhance security could also lower costs to society at large
if implementing security plans foils a security incident and prevents
much larger costs. For example, in 2002, $764 billion in international
trade was handled by U.S. ports, or more than $2 billion per day.
Disruptions to this trade could have a large impact on the economy. In
addition, security improvements from implementing security plans could
have collateral benefits such as reducing nonsecurity related risks
from theft and fire. Finally, if better security enhances demand for
maritime transportation services, facility and vessel owners have
positive incentives to comply.
Questions Remain about Adequacy of Public Comments to Validate Cost
Estimate:
In the absence of complete data, the Coast Guard relied on public
comments to validate its cost estimate of $7.3 billion and ensure
reliability of data used in that estimate. The extent to which the
public comment process was up to this task is debatable. For instance,
the Coast Guard acknowledged that on a vessel-by-vessel or facility-by-
facility basis, its cost assumptions probably carry a large margin of
error. Coast Guard analysts said the problem in estimating costs for
facilities is that there is no typical facility. In turn, large cost
differences for individual vessels and facilities could make it
difficult for individual stakeholders to judge the accuracy of Coast
Guard's estimates of average facility and vessel costs. In addition,
the Coast Guard acknowledged that a key cost driver in the facility
estimate--the national percentage of facilities requiring higher rather
than lower costs to ensure security--is likely to rise over time. These
issues call into question the adequacy of public comments to validate
the estimate and ensure data reliability. However, given the limited
time the Coast Guard had to gather data and make an estimate, relying
on public comments to identify large errors made practical sense.
The Coast Guard vetted its cost estimate in seven public meetings and
said it received few negative comments. For instance, some stakeholders
commented that foreign-flag vessels should be included in the cost
analysis, but, according to the Coast Guard, foreign-flag vessels are
already required by the International Ship & Port Facility Security
Code to meet these security requirements. On the other hand, the Coast
Guard revised its cost values for portable vapor detectors and
operations and maintenance for equipment after receiving comments that
these values were too low. To help validate cost assumptions, the Coast
Guard also established a proprietary docket where industry could
provide it with cost data without worrying about disclosure in the
public domain. However, not much data were submitted.
[End of section]
Appendix IV: GAO Contacts and Staff Acknowledgments:
GAO Contacts:
Margaret Wrightson (415) 904-2200 Steven Calvo (206) 287-4800:
Staff Acknowledgments:
In addition to those named above, Chuck Bausell, Jason Berman, Geoffrey
Hamilton, Christopher Hatscher, Nicholas Larson, and Stan Stenersen
made key contributions to this report.
FOOTNOTES
[1] P.L. 107-295, 116 Stat. 2064, 2066 (2002).
[2] The portwide security plan, called an Area Maritime Security Plan,
is to be developed by the Coast Guard's local Captains of the Port and
a committee comprised of federal, state, and local agencies; law
enforcement and security agencies; and other port stakeholders such as
owners and operators of facilities and vessels, trade and labor
organizations, and railroad and trucking companies among others. The
plan is designed to provide a framework for communication and
coordination among port stakeholders and law enforcement officials. Our
review focused on plans being developed by entities other than the
Coast Guard, and we, therefore, do not discuss these area plans in this
report. We will, however, be addressing aspects of these plans in a
subsequent report.
[3] See generally 33 C.F.R. Parts 101, 104, and 105. Motorboats and
other pleasure craft, for example, are generally, not subject to
security plan requirements, as are a variety of other types of vessels
below certain prescribed lengths or weights.
[4] This is the present value of costs incurred from 2003 to 2012.
Unless otherwise noted, all cost figures cited are present values.
[5] Appendix I describes our scope and methodology in more detail and
contains a list of ports we visited and port stakeholders we
interviewed.
[6] The Captain of the Port is a Coast Guard officer who provides
direction to Coast Guard law enforcement activities within the general
proximity of the port in which assigned. Captains of the Port enforce,
within their respective areas, port safety and security and marine
environmental protection regulations. There are 45 Captains of the Port
nationwide.
[7] The requirements for security plans are found in 33 C.F.R. Part
104, Subpart D for vessels and 33 C.F.R. Part 105, Subpart D for
facilities. See appendix II for a listing of required security plan
contents.
[8] IMO is responsible for improving maritime safety, including
combating acts of violence or crime at sea. The United States is a
member. In November 2001, the Commandant of the Coast Guard addressed
IMO's General Assembly, urging that body to consider an international
scheme for port and shipping security. Recommendations and proposals
for comprehensive security requirements, including amendments to
International Convention for Safety of Life at Sea, 1974, (SOLAS) and
the new ISPS Code, were developed at a series of intersessional
maritime security work group meetings held at the direction of IMO's
Maritime Safety Committee.
[9] Prior to issuing the final regulation, the Coast Guard issued an
interim final rule on July 1, 2003.
[10] The Coast Guard also intends to complete on-site inspections of
"uninspected vessels" by December 31, 2004. These "uninspected vessels"
include some towing vessels, most fishing industry vessels, some
freight barges, and certain passenger vessels, among others that were
not required to submit a security plan but did so voluntarily.
[11] Marine safety offices are located at coastal ports and on inland
waterways and are responsible for the overall safety and security of
maritime activities and for environmental protection in their
geographic areas.
[12] The Coast Guard hired Black and Veatch Corporation, an engineering
consulting and construction company with expertise in facility
security, to conduct the facility security plan reviews. The Coast
Guard also hired George G. Sharp, Inc., a maritime engineering, safety,
and security company with expertise in vessel security, to conduct the
vessel security plan reviews. The Coast Guard is reviewing the security
plans with the contractors in two locations: The National Facility
Security Plan Review Center in Overland Park, Kansas, and the Marine
Safety Center (for vessels) in Washington, D.C.
[13] The estimate of $7.3 billion applies to compliance costs at
Maritime Security Condition System (MARSEC) Level 1. MARSEC is a three-
tiered system developed by the Coast Guard to communicate the
prevailing threat environment to the marine elements of the national
transportation system, including ports, vessels, facilities, and
critical assets and infrastructure. The levels align closely with DHS's
color-coded Homeland Security Alert System in the following way: MARSEC
Level 1 applies when threat conditions Green, Blue, or Yellow are set;
MARSEC Level 2 applies when threat condition Orange is set; and MARSEC
Level 3 applies when threat condition Red is set.
[14] A template is a document that owners or operators can use to
develop and implement security plans by tailoring it to the specific
circumstances of their operation.
[15] Under both options, facilities also had to submit a "Vulnerability
and Security Measures Summary" (Form CG-6025), which lists the
vulnerabilities and specific security measures to be taken. Owners and
operators submitting plans under option A also had to submit a security
assessment report, a document based on background information and an
on-scene survey, identifying possible threats, vulnerabilities,
consequences, and existing protective measures. Those who chose option
B did not have to submit this report.
[16] Trade or industry organizations with approved "alternative
security programs" include: American Chemistry Council, American Gaming
Association, American Waterways Operators, Lake Carriers' Association,
Offshore Marine Service Association, and the Passenger Vessel
Association. Other organizations that received interim approval: the
North American Grain Export Association & National Grain and Feed
Association, Greater New Orleans Barge Fleeting Association, and
Washington State Ferries.
[17] The Coast Guard has issued guidance to Captains of the Port to
encourage them to "engage" with users of option B to review their
progress prior to July 1, 2004. However, these users are not required
to agree to these reviews.
[18] For revisions to facility security plans, 30 calendar days were
allowed for revisions to be made and resubmitted to the Coast Guard. No
time limit was specified for revisions to vessel security plans.
[19] Some owners or operators with plans undergoing the review process
have commented that the Coast Guard's contractors have been
unnecessarily "nitpicky" or have gone beyond regulations, resulting in
what the owners or operators consider to be excessive deficiencies.
While we did not evaluate the validity of these comments, Coast Guard
officials have publicly defended the quality of the contractors'
performance.
[20] The Coast Guard is reviewing the facility security plans with the
contractor at the National Facility Security Plan Review Center in
Overland Park, Kansas.
[21] MTSA allows the Coast Guard, under certain circumstances, to grant
permission to facilities and vessels with plans still in process to
continue operating for up to 1 year after the plans were submitted.
[22] Vessels in international trade were given priority since all
vessels subject to the SOLAS/ISPS codes must be in compliance with an
approved security plan by July 1, 2004.
[23] In addition, the Captain of the Port has the authority under 33
C.F.R. Part 6 to establish security zones and prevent access to any
vessel or facility whenever he or she believes such action may be
necessary to prevent damage or injury.
[24] The guidelines for this strategy were contained in Navigation and
Vessel Inspection Circulars (NVIC), an approach the Coast Guard uses to
provide detailed guidance about enforcement or compliance with certain
federal marine safety regulations and Coast Guard marine safety
programs.
[25] The Coast Guard plans to complete all vessel inspections by July
1, 2005, and as soon after July 1, 2004, as possible. Each vessel will
receive a security compliance inspection concurrently with its annual
Certificate of Inspection visit conducted by the Coast Guard between
July 1, 2004, and July 1, 2005. However, under three situations vessels
will receive inspections earlier. First, all inspections for SOLAS
vessels (i.e., U.S. registered vessels operating internationally) must
be completed by July 1, 2004. Second, at the discretion of the Captain
of the Port, certain vessels of interest will be inspected shortly
after July 1, 2004. Finally, the Coast Guard will inspect any vessel
whose owners or operators request an early security compliance
inspection.
[26] The Coast Guard refers to this initial 6-month period as a surge
effort because of the amount of work demanded in a short time frame.
The Coast Guard regards the facility compliance inspections, which must
be completed in full within this period, as particularly time-
consuming.
[27] A drill is a training event that tests at least one component of
the vessel or facility security plan and is used to maintain a high-
level of security readiness. According to the Coast Guard regulations,
at least one security drill is to be conducted by owners and operators
every 3 months.
[28] U.S. General Accounting Office, Coast Guard: Relationship Between
Resources Used and Results Achieved Needs to Be Clearer, GAO-04-432
(Washington, D.C.: March 22, 2004).
[29] The working groups were comprised of Coast Guard headquarters,
area, district, and field office staff. The historical information came
from the Coast Guard's implementation of the Oil Pollution Act of 1990,
Public Law 101-380, 104 Stat. 484 (1990).
[30] The first 2 days of the 5-day training were not required for those
personnel with prior inspection experience because the first 2 days
covered "basic" elements of conducting inspections.
[31] The inspection guide, checklists, and other enforcement guidance
were included in a series of NVICs issued by the Coast Guard. The NVICs
that included the inspection guides were issued in May 2004.
[32] Every 2 to 4 years, the Coast Guard rotates its staff among
various duty stations, such as search and rescue, high-and medium-
endurance cutters, and buoy tenders. The Coast Guard also rotates its
staff within duty stations, such as moving facility security inspectors
to noninspection duties within a marine safety office.
[33] U.S. General Accounting Office, Aviation Security: Further Steps
Needed to Strengthen the Security of Commercial Airport Perimeters and
Access Controls, GAO-04-728 (Washington, D.C.: June 4, 2004).
[34] Since facilities and vessels are often staffed differently on
weekends, evenings, and nights, this approach is intended to allow
inspectors a better opportunity to identify the actual operating
conditions of facilities and vessels.
[35] Covert testing would involve Coast Guard agents working undercover
to evaluate, among other things, the effectiveness of security
processes and procedures.
[36] A significant regulatory action is defined as likely to result in,
among other things, a rule having an annual effect on the economy of
$100 million or more or other serious effects. The Coast Guard has
estimated that its rule for facilities and vessels will have an annual
cost of $832 million in real, undiscounted dollars.
[37] Guidance on implementing this executive order notes that the
ending point of the analysis should be far enough in the future to
encompass all the significant benefits and costs likely to result from
the rule.
[38] The $884 million is in real, undiscounted dollars.
[39] The net effect of these considerations on overall costs is
unclear.
[40] This estimate is based on costs to maintain security at MARSEC
Level 1, which encompasses the Low (Green), Guarded (Blue), and
Elevated (Yellow) designations of the Homeland Security Advisory
System. The Coast Guard estimated that meeting a more extensive threat
level, which the Coast Guard defined as two 21-day periods at MARSEC
Level 2, the equivalent to the Department of Homeland Security's
Advisory System's orange threat level (high risk of terrorist attack)
each year, would cost an additional $5 billion.
[41] Not counting the number of hours spent annually on these
documents.
[42] A significant regulatory action is defined as likely to result in,
among other things, a rule having an annual effect on the economy of
$100 million or more or other serious effects. The Coast Guard has
estimated that its rule for facilities and vessels will have an annual
cost of $832 million in real, undiscounted dollars.
[43] Our analysis was conducted using what is called Monte Carlo
simulation, which uses random numbers to measure the effects of
uncertainty. Because the Coast Guard was unable to provide additional
information, our simulation is based on some general assumptions about
the probability distributions characterizing values used by the Coast
Guard for cost factors.
[44] Guidance on implementing this executive order notes that the
ending point of the analysis should be far enough in the future to
encompass all the significant benefits and costs likely to result from
the rule.
[45] The $884 million is in real, undiscounted dollars.
[46] The net effect of these considerations on overall costs is
unclear.
[47] At MARSEC Level 2, which is the equivalent to the Department of
Homeland Security's Advisory System orange level.
GAO's Mission:
The General Accounting Office, the investigative arm of Congress,
exists to support Congress in meeting its constitutional
responsibilities and to help improve the performance and accountability
of the federal government for the American people. GAO examines the use
of public funds; evaluates federal programs and policies; and provides
analyses, recommendations, and other assistance to help Congress make
informed oversight, policy, and funding decisions. GAO's commitment to
good government is reflected in its core values of accountability,
integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains
abstracts and full-text files of current reports and testimony and an
expanding archive of older products. The Web site features a search
engine to help you locate documents using key words and phrases. You
can print these documents in their entirety, including charts and other
graphics.
Each day, GAO issues a list of newly released reports, testimony, and
correspondence. GAO posts this list, known as "Today's Reports," on its
Web site daily. The list contains links to the full-text document
files. To have GAO e-mail this list to you every afternoon, go to
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order
GAO Products" heading.
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. General Accounting Office
441 G Street NW,
Room LM Washington,
D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Public Affairs:
Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.
General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.
20548: