Coast Guard
Preliminary Observations on Deepwater Program Assets and Management Challenges
Gao ID: GAO-07-446T February 15, 2007
The U.S. Coast Guard's Deepwater program was designed to upgrade or replace its aging legacy aircraft and vessels with assets focusing on the Coast Guard's traditional at-sea roles. After the September 11, 2001 terrorist attacks, the Coast Guard took on additional security missions, resulting in revisions to the Deepwater plan. GAO's prior work raised concerns about Coast Guard's efforts to upgrade or acquire assets on schedule, and manage and effectively monitor the system integrator. This testimony provides GAO's preliminary observations on (1) events and issues surrounding the Coast Guard's bridging strategy to convert the legacy 110-foot patrol boats to 123-foot patrol boats; (2) the status of the Coast Guard's efforts to acquire new or upgraded Deepwater assets; and (3) the Coast Guard's ability to effectively manage the Deepwater program, hold contractors accountable, and control costs through competition. GAO's preliminary observations are based on audit work performed from August 2006 to February 2007.
Numerous events since January 2001 led up to the failure of the Coast Guard's bridging strategy to convert its legacy 110-foot patrol boats into 123-foot patrol boats. These converted boats were removed from service on November 30, 2006 because of operational and safety concerns. According to the Coast Guard Commandant, actions are being taken to mitigate the impact of the removal of these patrol boats on mission activities. For example, patrol hours of some 110-foot patrol boats have been increased through the addition of crews from the 123-foot patrol boats, and other Coast Guard vessels have been deployed to assist in carrying out missions. The delivery record for the 10 classes of upgraded or new Deepwater aircraft and vessels is mixed. Specifically, 7 of the 10 asset classes are on or ahead of schedule. Among these, 5 first-in-class assets have been delivered on or ahead of schedule; 2 others remain on time but their planned delivery dates are in 2009 or beyond; therefore, delays could still potentially occur. Three Deepwater asset classes are currently behind schedule due to various problems related to designs, technology, or funding. For example, the Fast Response Cutter (a new vessel), which had been scheduled for first-in-class delivery in 2007, has been delayed by at least 2 years in part because work on its design was suspended until technical problems can be addressed. From the program's outset, GAO has raised concerns about the risks involved with the Coast Guard's acquisition strategy. In 2004, GAO reported that program management, contractor accountability, and cost control were all challenges, and made recommendations in these areas. Insufficient staffing, ineffective performance measures, and the Coast Guard's lack of knowledge about the extent to which the contractor was using competition have contributed to program risk. The Coast Guard has taken some actions to address these issues. GAO plans to continue to assess the Coast Guard's Deepwater program, including its efforts to address GAO recommendations, and will report the findings later this year.
GAO-07-446T, Coast Guard: Preliminary Observations on Deepwater Program Assets and Management Challenges
This is the accessible text file for GAO report number GAO-07-446T
entitled 'Coast Guard: Preliminary Observations on Deepwater Program
Assets and Management Challenges' which was released on February 15,
2007.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony Before the Subcommittee on Homeland Security, Committee on
Appropriations, House of Representatives:
United States Government Accountability Office:
GAO:
For Release on Delivery Expected at 10:00 a.m. EST:
Thursday, February 15, 2007:
Coast Guard:
Preliminary Observations on Deepwater Program Assets and Management
Challenges:
Statement of John P. Hutton, Acting Director:
Acquisition and Sourcing Management:
GAO-07-446T:
GAO Highlights:
Highlights of GAO-07-446T, a testimony for the Subcommittee on Homeland
Security, Committee on Appropriations, House of Representatives
Why GAO Did This Study:
The U.S. Coast Guard‘s Deepwater program was designed to upgrade or
replace its aging legacy aircraft and vessels with assets focusing on
the Coast Guard‘s traditional at-sea roles. After the September 11,
2001 terrorist attacks, the Coast Guard took on additional security
missions, resulting in revisions to the Deepwater plan. GAO‘s prior
work raised concerns about Coast Guard‘s efforts to upgrade or acquire
assets on schedule, and manage and effectively monitor the system
integrator.
This testimony provides GAO‘s preliminary observations on (1) events
and issues surrounding the Coast Guard‘s bridging strategy to convert
the legacy 110-foot patrol boats to 123-foot patrol boats; (2) the
status of the Coast Guard‘s efforts to acquire new or upgraded
Deepwater assets; and (3) the Coast Guard‘s ability to effectively
manage the Deepwater program, hold contractors accountable, and control
costs through competition. GAO‘s preliminary observations are based on
audit work performed from August 2006 to February 2007.
What GAO Found:
Numerous events since January 2001 led up to the failure of the Coast
Guard‘s bridging strategy to convert its legacy 110-foot patrol boats
into 123-foot patrol boats. These converted boats were removed from
service on November 30, 2006 because of operational and safety
concerns. According to the Coast Guard Commandant, actions are being
taken to mitigate the impact of the removal of these patrol boats on
mission activities. For example, patrol hours of some 110-foot patrol
boats have been increased through the addition of crews from the 123-
foot patrol boats, and other Coast Guard vessels have been deployed to
assist in carrying out missions.
The delivery record for the 10 classes of upgraded or new Deepwater
aircraft and vessels is mixed. Specifically, 7 of the 10 asset classes
are on or ahead of schedule. Among these, 5 first-in-class assets have
been delivered on or ahead of schedule; 2 others remain on time but
their planned delivery dates are in 2009 or beyond; therefore, delays
could still potentially occur. Three Deepwater asset classes are
currently behind schedule due to various problems related to designs,
technology, or funding. For example, the Fast Response Cutter (a new
vessel), which had been scheduled for first-in-class delivery in 2007,
has been delayed by at least 2 years in part because work on its design
was suspended until technical problems can be addressed.
From the program‘s outset, GAO has raised concerns about the risks
involved with the Coast Guard‘s acquisition strategy. In 2004, GAO
reported that program management, contractor accountability, and cost
control were all challenges, and made recommendations in these areas.
Insufficient staffing, ineffective performance measures, and the Coast
Guard‘s lack of knowledge about the extent to which the contractor was
using competition have contributed to program risk. The Coast Guard has
taken some actions to address these issues. GAO plans to continue to
assess the Coast Guard‘s Deepwater program, including its efforts to
address GAO recommendations, and will report the findings later this
year.
Figure: Deepwater Vessel and Aircraft Classes:
[See PDF for Image]
Source: U.S. Coast Guard.
[End of Figure]
What GAO Recommends:
This testimony contains no recommendations. In 2004, GAO made 11
recommendations on management and oversight, contractor accountability,
and cost control through competition, and reported in April 2006 that
progress had been made but continued monitoring was warranted.
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-446T].
To view the full product, including the scope and methodology, click on
the link above. For more information, contact John P. Hutton at (202)
512-4841 or huttonj@gao.gov.
[end of section]
Mr. Chairman and Members of the Subcommittee:
I appreciate the opportunity to participate in today's hearing to
discuss our preliminary observations on the status of the United States
Coast Guard's Integrated Deepwater System program. These observations
are based upon our ongoing analysis for this Committee and the Senate
Appropriations Committee, and we plan to provide a more complete
analysis when we issue our report later this year.
Deepwater is a 25-year, $24-billion effort to upgrade or replace
existing Coast Guard aircraft and vessels in order to carry out its
missions along our coastlines and farther out at sea. An initial
emphasis of the Deepwater program was to improve existing assets, known
as "legacy" assets, as a bridging strategy until new assets could be
delivered and begin operating. One of the key legacy assets to be
improved was the 110-foot patrol boat, which was to be converted to a
123-foot patrol boat by lengthening the hull and modernizing various
components. While the Coast Guard originally planned to convert all 49
of its 110-foot patrol boats to 123-foot patrol boats, it halted the
patrol boat conversion program after 8 boats because of hull buckling
and the inability of these converted patrol boats to meet post-
September 11, 2001 mission requirements.
The Deepwater program is eventually to include 10 major classes of new
or upgraded assets--5 major classes each of aircraft and vessels. By
2027, under these 10 asset classes, a total of 215 vessels and 240
aircraft are to be acquired or upgraded. To carry out this effort, the
Coast Guard has relied on an acquisition strategy that allows a prime
contractor (system integrator) to manage the acquisition process,
including identifying the assets needed, and then using tiers of
subcontractors to design and build the assets.
Since 2001, we have reviewed the Deepwater program and have informed
Congress, the Department of Homeland Security (DHS), and the Coast
Guard of the problems, risks, and uncertainties inherent with such a
large acquisition. In March 2004, we made recommendations to the Coast
Guard to address three broad areas of concern: improving program
management, strengthening contractor accountability, and promoting cost
control through greater competition among potential
subcontractors.[Footnote 1] In April 2006, we issued a follow-on report
describing efforts the Coast Guard had taken to address the outstanding
recommendations.[Footnote 2]
This statement offers preliminary observations on the Coast Guard's
management of the Deepwater program. Specifically, it discusses:
* events and issues surrounding the problems encountered with the Coast
Guard's bridging strategy to convert the legacy 110-foot patrol boats
to 123-foot patrol boats;
* the status of the Coast Guard's efforts to acquire new or upgraded
Deepwater assets; and:
* the Coast Guard's ability to effectively manage the Deepwater
program, hold contractors accountable, and control costs through
competition.
The preliminary findings and observations noted in this testimony are
based on our review of key documents, including the 2005 Deepwater
Acquisition Program Baseline; schedule information provided by the
Coast Guard; Coast Guard memoranda regarding the 123-foot patrol boat
conversion; and Coast Guard's human capital plan, its award fee and
award term documentation, and its competition monitoring plan. We
conducted interviews with Coast Guard officials at agency headquarters
in Washington, D.C; officials in Coast Guard's System Integration
Program Office in Arlington, VA; and Coast Guard contractor staff. In
addition, we interviewed Coast Guard officials during visits to the
Pacific and Atlantic Area Commands and their associated Maintenance and
Logistics Commands and at the Coast Guard's Aircraft Repair and Supply
Center. Our work was conducted from August 2006 to February 2007 in
accordance with generally accepted government auditing standards.
Appendix I contains a list of related GAO products.
Summary:
Numerous events, dating back to January 2001, resulted in the failure
of the Coast Guard's bridging strategy to convert its legacy 110-foot
patrol boats into 123-foot patrol boats. These converted boats were
removed from service on November 30, 2006 because of operational and
safety concerns. Specifically, the Coast Guard cited that the 123-foot
patrol boats in service in Key West, Florida displayed deck cracking,
hull buckling, and shaft alignment problems related to other structural
issues. The mission of these boats involved, among other things, drug
interdiction, intercepting illegal aliens, and providing support for
antiterrorist activities. According to the Commandant of the Coast
Guard, actions are being taken to mitigate the impact of the removal of
these patrol boats on mission activities. For example, patrol hours of
some 110-foot patrol boats have been increased through the addition of
crews from the 123-foot patrol boats; other Coast Guard vessels have
been deployed to assist in missions formerly performed by the 123-foot
patrol boats; and permission has been secured from the U.S. Navy to
continue using 179-foot cutters on loan for an additional 5 years. We
will continue to review the actions the Coast Guard is taking to
mitigate the removal from service of the 123-foot patrol boats.
Of the 10 classes of upgraded or new Deepwater aircraft and vessels,
the delivery record for first-in-class assets (that is, the first of
multiple aircraft or vessels to be delivered within each class) is
mixed. Specifically, 7 of the 10 asset classes are on or ahead of
schedule. Among these, 5 first-in-class assets have been delivered on
or ahead of schedule; and 2 others remain on schedule but their planned
delivery dates are in 2009 or beyond. Three Deepwater asset classes are
currently behind schedule due to various problems related to designs,
technology, or funding. For example, the Fast Response Cutter (a new
vessel), which had been scheduled for first-in-class delivery in 2007,
has been delayed by at least 2 years in part because work on its design
was suspended until technical problems related to its hull and other
issues can be addressed. The Vertical Unmanned Aerial Vehicle (a new
aircraft), which had also been scheduled for delivery in 2007, has been
delayed by 6 years due to evolving technological developments, among
other things. In addition, the Offshore Patrol Cutter, which had a
planned delivery date in 2010, has now been delayed by 5 years.
In 2001, we described the Deepwater project as risky due to the unique,
untried acquisition strategy for a project of this magnitude within the
Coast Guard--a "systems of systems" approach with a contractor as the
integrator. In 2004, we reported that there were significant risks
related to program management, contractor accountability, and cost
control, and we made recommendations in all these areas. The Coast
Guard's ability to effectively manage the program has been challenged
by staffing shortfalls and poor communication and collaboration among
Deepwater program staff, contractors, and field personnel. Despite
documented problems in schedule, performance, cost control, and
contract administration, measures for holding the contractor
accountable resulted in an award fee of $4 million (of the maximum $4.6
million) for the first year. Through the first 4 years of the Deepwater
contract, the system integrator received award fees that ranged from 87
percent to 92 percent of the total possible award fee (scores that
ranged from "very good" to "excellent" based on Coast Guard criteria),
for a total of over $16 million. Further, the program's ability to
control Deepwater costs is uncertain given the Coast Guard's lack of
detailed information on the contractor's competition decisions. While
the Coast Guard has taken some actions to improve program outcomes, our
assessment of the program and its efforts to address our
recommendations continues, and we plan to report on our findings later
this year.
Background:
The Coast Guard is the lead federal agency for maritime security within
DHS. The Coast Guard is responsible for a variety of missions,
including ensuring ports, waterways, and coastline security; conducting
search and rescue missions; interdicting illicit drug shipments and
illegal aliens; and enforcing fisheries laws. In 1996, in order to
continue carrying out its responsibilities and operations, the Coast
Guard initiated the Deepwater program to replace or upgrade its aging
vessels, aircraft, and other essential equipment.
As originally conceived, Deepwater was designed around producing
aircraft and vessels that would function in the Coast Guard's
traditional at-sea roles--such as interdicting illicit drug shipments
or rescuing mariners from difficulty at sea--and the original 2002
Deepwater program was focused on those traditional missions. After the
terrorist attacks on September 11, 2001, the Coast Guard was also
assigned homeland security missions related to protection of ports,
waterways, and coastal areas. Based on its revised mission
responsibilities, the Coast Guard updated its Deepwater Acquisition
Program Baseline in November 2005. The new baseline contained changes
in the balance between new assets to be acquired and legacy assets to
be upgraded and adjusted the delivery schedule and costs for many of
these assets. Overall, the Deepwater acquisition schedule was
lengthened by 5 years, with the final assets now scheduled for delivery
in 2027.
Upon its completion, the Deepwater program is to consist of 5 new
classes of vessels, 1 new class of fixed-wing aircraft, 1 new class of
unmanned aerial vehicles, 2 classes of upgraded helicopters, and 1
class of upgraded fixed-wing aircraft.[Footnote 3] The 215 new vessels
consist of five new asset classes--the National Security Cutter (NSC),
Offshore Patrol Cutter (OPC), Fast Response Cutter (FRC), Long-Range
Interceptor (LRI), and Short-Range Prosecutor (SRP). The 240 aircraft
are composed of two new aircraft classes, the Vertical Unmanned Aerial
Vehicle (VUAV) and the Maritime Patrol Aircraft (MPA); and three
upgraded asset classes--the Long-Range Surveillance Aircraft (LRS),
Medium-Range Recovery Helicopter (MRR), and the Multi-Mission Cutter
Helicopter (MCH).
Table 1 provides an overview, by asset class, of the Deepwater vessels
to be acquired and table 2 provides an overview of the Deepwater
aircraft to be acquired or upgraded. As noted in Table 1, the 140-foot
FRC was designated as a replacement vessel for the 110-foot and 123-
foot patrol boats.
Figure 1: Deepwater Vessels to be Acquired:
[See PDF for image]
Source: GAO analysis of Coast Guard documentation.
[End of figure]
Figure 2: Deepwater Aircraft to be Upgraded or Acquired:
[See PDF for image]
Source: GAO analysis of Coast Guard documentation.
[End of figure]
Since 2001, we have reviewed the Deepwater program and have informed
Congress, DHS, and Coast Guard of the problems, risks, and
uncertainties inherent with such a large acquisition that relies on a
system integrator to identify the assets needed and then using tiers of
subcontractors to design and build the assets. In March 2004, we made
recommendations to the Coast Guard to address three broad areas of
concern: improving program management, strengthening contractor
accountability, and promoting cost control through greater competition
among potential subcontractors (see table 3).[Footnote 4] We have
issued a number of follow-on reports describing efforts the Coast Guard
has taken to address these recommendations. (See app. I for a list of
related GAO products.)
Table 1: Status of GAO Recommendations to the U.S. Coast Guard
Regarding Management of the Deepwater Program, as of April 28, 2006:
Areas of concern; Recommendations to the U.S. Coast Guard;
Recommendation status.
Areas of concern: Key components of management and oversight;
Recommendations to the Coast Guard: Put in place a human capital plan
to ensure adequate staffing of the Deepwater program;
Recommendation status: Implemented (human capital plan was
implemented).
Areas of concern: Key components of management and oversight;
Recommendations to the Coast Guard: Improve integrated product teams
(IPTs) responsible for managing the program by providing better
training, approving charters for sub-IPTs, and improving systems for
sharing information between teams;
Recommendation status: Partially implemented.
Areas of concern: Key components of management and oversight;
Recommendations to the U.S. Coast Guard: Provide field operators and
maintenance personnel with timely information and training on how the
transition to Deepwater assets will occur and how maintenance
responsibilities are to be divided between the system integrator and
Coast Guard personnel;
Recommendation status: Partially implemented.
Areas of concern: Procedures for ensuring contractor accountability;
Recommendations to the U.S. Coast Guard: Develop measurable award fee
criteria consistent with guidance from the Office of Federal
Procurement Policy;
Recommendation Status: Implemented.
Areas of concern: Procedures for ensuring contractor accountability;
Recommendations to the U.S. Coast Guard: Provide for better input from
U.S. Coast Guard performance monitors;
Recommendation Status: Implemented.
Areas of concern: Procedures for ensuring contractor accountability;
Recommendations to the U.S. Coast Guard: Hold the system integrator
accountable in future award fee determinations for improving
effectiveness of the IPTs;
Recommendation Status: Implemented.
Areas of concern: Procedures for ensuring contractor accountability;
Recommendations to the U.S. Coast Guard: Establish a baseline for
determining whether the acquisition approach is costing the government
more than the traditional asset replacement approach;
Recommendation Status: Will not be implemented.
Areas of concern: Procedures for ensuring contractor accountability;
Recommendations to the U.S. Coast Guard: Establish a time frame for
when the models and metrics will be in place with the appropriate
degree of fidelity to be able to measure contractor's progress toward
improving operational effectiveness;
Recommendation status: Partially implemented.
Areas of concern: Procedures for ensuring contractor accountability;
Recommendations to the U.S. Coast Guard: Establish criteria to
determine when to adjust the project baseline and document the reasons
for change;
Recommendation status: Partially implemented.
Areas of concern: Control of future costs through competition;
Recommendations for the U.S. Coast Guard: For subcontracts over $5
million awarded by the system integrator to the two major
subcontractors, require notification to the Coast Guard about decision
to perform the work in-house rather than contracting it out;
Recommendation status: Implemented.
Areas of concern: Control of future costs through competition;
Recommendations for the U.S. Coast Guard: Develop a comprehensive plan
for holding the system integrator accountable for ensuring adequate
competition among suppliers;
Recommendation status: Partially implemented.
Source: GAO-04-380 and GAO-06-546.
[End of table]
Coast Guard Removed 123-foot Patrol Boats from Service for Operational
and Safety Reasons, and is Acting to Mitigate Operational Impacts:
Between January 2001 and November 2006, numerous events led up to the
failure of the Coast Guard's bridging strategy to convert the legacy
110-foot patrol boats into 123-foot patrol boats. In January 2001, an
independent study found that the 110-foot patrol boats based in south
Florida and Puerto Rico were experiencing severe hull corrosion and
that their structural integrity was deteriorating rapidly.[Footnote 5]
To address these issues, the Coast Guard's original (2002) Deepwater
plan included a strategy to convert all 49 of the 110-foot patrol boats
into 123-foot patrol boats to strengthen the hulls. Also, the plan was
to provide additional capabilities, such as stern launch and recovery
capabilities and enhanced and improved command, control,
communications, computers, intelligence, surveillance, and
reconnaissance (C4ISR). While Coast Guard originally planned to convert
all 49 of its 110-foot patrol boats to 123-foot patrol boats, it halted
the patrol boat conversion program after 8 boats because of continued
hull buckling and the inability of these converted patrol boats to meet
post-September 11, 2001 mission requirements. These 8 converted boats
were removed from service on November 30, 2006 because of operational
and safety concerns.
The first patrol boat conversion was completed in March 2004, on the
Matagorda. Between March 2004 and late August 2004, the Matagorda
underwent additional maintenance that was not included in the contract
to convert it to 123 feet, according to Coast Guard officials. On
September 10, 2004, while en route to its home port in Key West, the
Matagorda experienced hull and deck buckling, while transiting the Gulf
of Mexico.
By March 2005, 2 other converted 123-foot patrol boats, the Nunivak and
the Padre, also began experiencing problems with hull buckling. That
same month, similar hull deformations were discovered in 3 other 123-
foot patrol boats--the Metompkin, Vashon, and Monhegan. As a result of
the deteriorating hull conditions, Coast Guard imposed operational
restrictions in April 2005 on the 123-foot patrol boats. These
restrictions specified that the converted patrol boats could not
operate in seas with wave heights exceeding 8 feet (they were
originally intended to operate in seas up to roughly 13 feet) and that
they had to operate at reduced speeds. Figure 1 provides a timeline of
key events that led to the eventual removal from service of the 123-
foot patrol boats.
Figure 3: Timeline of Key Events Leading to Removal from Service of 123-
foot Patrol Boats:
[See PDF for image]
Source: GAO analysis of Coast Guard data.
[End of figure]
The Coast Guard is taking actions to mitigate the operational impacts
resulting from the removal of the 123-foot patrol boats from service.
Specifically, in recent testimony, the Commandant of the Coast Guard
stated that Coast Guard has taken the following actions:
* multi-crewing certain 110-foot patrol boats with crews from the 123-
foot patrol boats that have been removed from service so that patrol
hours for these vessels can be increased;
* deploying other Coast Guard vessels to assist in missions formerly
performed by the 123-foot patrol boats; and:
* securing permission from the U.S. Navy to continue using 179-foot
cutters on loan from the Navy for an additional 5 years (these were
originally to be returned to the Navy in 2008) to supplement the Coast
Guard's patrol craft.
We will continue to review the actions the Coast Guard is taking to
mitigate the removal from service of the 123-foot patrol boats as part
of our ongoing work.
Deepwater Asset Delivery Schedule is Mixed, with 7 of 10 on or Ahead of
Schedule and 3 Behind Due to Various Factors:
Our review of available data show that as of January 2007, of the 10
classes of Deepwater assets to be acquired or upgraded, 4 are ahead of
schedule; 3 remain on schedule (and for 1 of these, design problems
have arisen); and 3 are behind scheduled delivery and face design,
funding, or technology challenges. Using the 2005 Deepwater Acquisition
Program Baseline as the baseline, figure 2 indicates, for each asset
class, whether delivery of the first-in-class (that is, the first of
several to be produced in its class) is ahead of schedule, on schedule,
or behind schedule, as of January 2007.
Figure 4: Comparison of the Estimated Delivery Dates for the First-in-
Class Deepwater Assets from the 2005 Deepwater Acquisition Baseline and
as of January 2007:
[See PDF for image]
Source: GAO analysis of documentation provided by U.S. Coast Guard.
[End of figure]
Among the Deepwater assets, 3 of the 5 aircraft classes are upgrades to
existing legacy systems, and these are all on or ahead of schedule; 1
new aircraft class is ahead of schedule; and the remaining new aircraft
class is 6 years behind schedule. With respect to Deepwater vessels,
all 5 asset classes are new, and of these, 2 are behind schedule, and a
third, while on schedule, faces structural modifications. The remaining
2 new maritime assets are small vessels that are on or ahead of
schedule at this time. Table 4 provides an overview of schedule status
for the Deepwater aircraft and vessel classes.
Table 2: Delivery Status of the Deepwater Aircraft and Vessels, as of
January 2007:
Asset category: Upgraded legacy aircraft;
Behind schedule: N/A[A];
On schedule: MCH;
Ahead of schedule: LRS, MRR.
Asset category: New aircraft;
Behind schedule: VUAV;
On schedule: N/ A[A];
Ahead of schedule: MPA.
Asset category: New vessels;
Behind schedule: OPC, FRC[B];
On schedule: NSC, LRI;
Ahead of schedule: SRP.
Source: GAO analysis of Coast Guard data.
[A] There are no such assets in this category.
[B] The FRC will replace the 110-foot and 123-foot patrol boats.
[End of table]
Assets That Are on Schedule as of January 2007:
The status of each asset class, and our preliminary observations on the
factors affecting their status, is discussed below.
Long-Range Interceptor:
The LRI is a 36-foot small boat that is to be carried and deployed on
each NSC and OPC. Coast Guard has one LRI on contract for delivery in
August 2007, to match delivery of the first NSC.
Short-Range Prosecutor:
According to the Coast Guard, the SRP is on schedule at this time and 8
have been delivered to date. Coast Guard is currently planning to
pursue construction and delivery of the remaining SRPs outside of the
system integrator contract. By doing so, the Coast Guard expects to
achieve a cost savings.
Maritime Patrol Aircraft:
The MPA is a commercial aircraft produced in Spain that is being
acquired to replace the legacy HU-25 aircraft and will permit the Coast
Guard to carry out missions, such as search and rescue, marine
environmental protection, and maritime security. The first MPA was
delivered to the Coast Guard in December 2006, and the second and third
are due for delivery by April 2007. Pilots and aircrew participated in
training classes in Spain, and Coast Guard is to take responsibility
for the development and implementation of MPA's maintenance and
logistics.
Long-Range Surveillance Aircraft:
The LRS is an upgraded legacy fixed-wing aircraft that includes 6 C-
130Js and 16 C-130Hs. The first aircraft entered the modification
process in January 2007, and five additional aircraft are to be
modified by July 2008. In fiscal year 2008, funding has been requested
to upgrade the C-130H radar and avionics, and for the C-130J fleet
introduction.
Medium-Range Recovery Helicopter:
The MRR is an upgraded legacy HH-60 helicopter. It began receiving a
series of upgrades beginning in fiscal year 2006, which will continue
into fiscal year 2012, including the service life extension program and
radar upgrades.
Multi-Mission Cutter Helicopter:
The MCH is an upgraded legacy HH-65 helicopter. According to Coast
Guard officials, the MCH assets will not have a single delivery date,
as the process involves three phases of upgrades. Phase I is the
purchase and delivery of new engines and engine control systems, Phase
II is a service-life extension program, and Phase III includes
communications upgrades. A Coast Guard official stated that 84 of the
95 HH-65s should be re-engined by June 2007, and all 95 should be
finished by October 2007. The fiscal year 2008 congressional
justification states that Phase II began in fiscal year 2007 and will
end in fiscal year 2014, and that Phase III is to begin in fiscal year
2008 and is to end in fiscal year 2014.
Deepwater Asset Reported to Be on Schedule as of January 2007, Despite
Design Issues:
National Security Cutter:
According to Coast Guard documentation, the NSC is on schedule for
delivery despite required modifications regarding its structural
integrity. In particular, the Coast Guard Commandant recently stated
that internal reviews by Coast Guard engineers, as well as by
independent analysts, have concluded that the NSC, as designed, will
need structural reinforcement to meet its expected 30-year service
life. In addition, the DHS Office of Inspector General recently
reported that the NSC design will not achieve a 30-year service life
based on an operating profile of 230 days underway per year in general
Atlantic and North Pacific sea conditions and added that Coast Guard
technical experts believe the NSC's design deficiencies will lead to
increased maintenance costs and reduced service life.[Footnote 6]
To address the structural modifications of the NSC, Coast Guard is
taking a two-pronged approach. First, Coast Guard is working with
contractors to enhance the structural integrity of the hulls of the
remaining six NSCs that have not yet been constructed. Second, after
determining that the NSC's deficiencies are not related to the safe
operation of the vessel in the near term, Coast Guard has decided to
address the structural modifications of the hulls of the first two
cutters as part of planned depot-level maintenance about 5 years after
they are delivered. The Commandant stated that he decided to delay the
repairs to these hulls to prevent further delays in construction and
delivery.
Deepwater Assets Behind Schedule as of January 2007:
Offshore Patrol Cutter:
Coast Guard officials have stated that further work on the development
of the OPC is on hold and the Coast Guard did not request funding for
the OPC in fiscal years 2007 or 2008. Delivery of the first OPC has
been delayed by 5 years--from 2010 to 2015.
Fast Response Cutter:
Concerns about the viability of the design of the FRC have delayed the
delivery of the first FRC by at least 2 years. As we have previously
reported,[Footnote 7] design and delivery of the original FRC was
accelerated as a bridging strategy to offset the failed conversion of
the 110-foot patrol boats into 123-foot patrol boats. According to the
2005 Deepwater Acquisition Program Baseline, the first FRC was
scheduled to be delivered in 2007--11 years earlier than the 2018 date
listed in the original (2002) Deepwater plan. Coast Guard suspended
design work on the FRC in late February 2006; however, because of
design risks, including excessive weight and horsepower requirements.
As a result, Coast Guard is moving forward with a "dual-path approach"
for acquiring new patrol boats to replace its existing 110-foot and 123-
foot patrol boats.
The first component of this dual path approach is to have the Deepwater
system integrator purchase a commercial (off-the-shelf) patrol boat
design that can be adapted for Coast Guard use.[Footnote 8] According
to Coast Guard officials, unlike the original plans, this FRC class is
not expected to meet all performance requirements originally specified,
but is intended as a way to field an FRC more quickly than would
otherwise occur and that can, therefore, serve as an interim
replacement for the deteriorating fleet of 110-foot patrol boats. The
Coast Guard Commandant recently stated that the Coast Guard expects
delivery of the commercial FRCs in the first half of fiscal year 2010,
about 2 years behind the estimated delivery date specified in the 2005
Deepwater Acquisition Program Baseline.
The second component of the dual-path approach is to eventually acquire
another cutter--a redesigned FRC.[Footnote 9] However, due to
continuing questions about the feasibility of its planned composite
hull, Coast Guard has now further delayed a decision about its
development or acquisition until it receives results from two studies.
First, the Coast Guard is conducting a business case analysis comparing
the use of composite versus steel hulls. Second, the Coast Guard told
us that DHS's Science and Technology Directorate will be conducting
tests on composite hull technology, and that it will wait to see the
results of these tests before making a decision on the redesigned FRC.
Until recently, the Coast Guard anticipated delivery of the redesigned
FRC in 2009 or 2010. However, the decision to not request funding for
this redesigned FRC in fiscal year 2008, and to await the results of
both studies before moving forward, will likely further delay delivery
of the redesigned FRC.
Vertical Unmanned Aerial Vehicle:
According to the Coast Guard, evolving technological developments and
the corresponding amount of funding provided in fiscal year 2006 have
delayed the delivery of the VUAV by 6 years--from 2007 to 2013. As a
result, the Coast Guard has adjusted the VUAV development plan. The
fiscal year 2008 DHS congressional budget justification indicates that
the Coast Guard does not plan to request funding for the VUAV through
fiscal year 2012. Coast Guard originally intended on matching the NSC
and VUAV delivery dates so that the VUAV could be launched from the NSC
to provide surveillance capabilities beyond the cutter's visual range
or sensors. However, with the delay in the VUAV's development schedule,
it no longer aligns with the NSC's initial deployment schedule.
Specifically, Coast Guard officials stated that the VUAV will not be
integrated with the NSC before fiscal year 2013, 6 years later than
planned. Coast Guard officials stated that they are discussing how to
address the operational impacts of having the NSC operate without the
VUAV. In addition, Coast Guard officials explained that since the time
of the original contract award, the Department of Defense has
progressed in developing a different unmanned aerial vehicle--the Fire
Scout--that Coast Guard officials say is more closely aligned with
Coast Guard needs. Coast Guard has issued a contract to an independent
third party to compare the capabilities of its planned VUAV to the Fire
Scout.
Preliminary Observations on the Status of Deepwater Program Management,
Contractor Accountability, and Cost Control:
Since the inception of the Deepwater program, we have expressed
concerns about the risks involved with the Coast Guard's system-of-
systems acquisition approach and the Coast Guard's ability to manage
and oversee the program. Our concerns have centered on three main
areas: program management, contractor accountability, and cost control
through competition. We have made a number of recommendations to
improve the program--most of which the Coast Guard has agreed with and
is working to address. However, while actions are under way, a project
of this magnitude will likely continue to experience other problems as
more becomes known. We will continue our work focusing on the Coast
Guard's efforts to address our recommendations and report on our
findings later this year.
Program Management:
In 2004, we reported that the Coast Guard had not effectively
implemented key components needed to manage and oversee the system
integrator. Specifically, we reported at that time and subsequently on
issues related to integrated product teams (IPT), the Coast Guard's
human capital strategy, and communication with field personnel
(individuals responsible for operating and maintaining the assets). Our
preliminary observations on the Coast Guard's progress in improving
these program management areas, based on our ongoing work, follow.
Integrated Product Teams:
In 2004, we found that IPTs, the Coast Guard's primary tool for
managing the Deepwater program and overseeing the contractor, had not
been effective due to changing membership, understaffing, insufficient
training, lack of authority for decision making, and inadequate
communication. We recommended the Coast Guard take actions to address
IPT effectiveness. We subsequently reported that IPT decision-making
was to a large extent stove-piped, and some teams lacked adequate
authority to make decisions within their realm of
responsibility.[Footnote 10] Coast Guard officials believed
collaboration among the subcontractors was problematic and that the
system integrator wielded little influence to compel decisions among
them. For example, proposed design changes to assets under construction
were submitted as two separate proposals from both subcontractors
rather than one coherent plan. According to Coast Guard performance
monitors, this approach complicated the government review of design
changes because the two proposals often carried overlapping work items,
thereby forcing the Coast Guard to act as the system integrator in
those situations. Although some efforts have been made to improve the
effectiveness of the IPTs--such as providing them with more timely
charters and entry-level training--our preliminary observations are
that more improvements are needed.
The Coast Guard's ability to assess IPT performance continues to be
problematic. Former assessments of IPT effectiveness simply focused on
measures such as frequency of meetings, attendance, and training. As a
result, IPTs received positive assessments while the assets under their
realm of responsibility--such as the National Security Cutter--were
experiencing problems. The new team measurements include outcome-based
metrics such as cost and schedule performance of assets (ships,
aircraft, and command, control, communications, computers,
intelligence, surveillance, and reconnaissance (C4ISR)). However,
Deepwater's overall program management quarterly report shows that the
connection between IPT performance and program results continues to be
misaligned.[Footnote 11] For example, the first quarterly report to
incorporate the new measurements, covering the period October to
December 2006, indicates that the IPTs' performance for all domains is
"on-schedule or non-problematic" even while some assets' cost or
schedule performance is rated "behind schedule or problematic."
[Footnote 12] Further, even though the Deepwater program is addressing
fundamental problems surrounding the 123-foot patrol boat and FRC, IPTs
no longer exist for these assets. In some cases, Coast Guard officials
stated they have established work groups outside of the existing IPT
structure to address identified issues and problems related to assets,
such as the NSC. We will continue to review the IPTs' roles and
relevance in the management of the Deepwater program.
Human Capital:
We also reported in 2004 that the Coast Guard had not adequately
staffed its program management function for Deepwater. Although its
Deepwater human capital plan set a goal of a 95 percent or higher "fill
rate" annually for both military and civilian personnel, funded
positions were below this goal. We recommended that the Coast Guard
follow the procedures in its Deepwater human capital plan to ensure
that adequate staffing was in place and that turnover of Coast Guard
military personnel was proactively addressed. The Coast Guard
subsequently revised its Deepwater human capital plan in February 2005
to emphasize workforce planning, including determining needed
knowledge, skills, and abilities and developing ways to leverage
institutional knowledge as staff rotate out of the program. We reported
in 2005 that the Coast Guard also took some short-term steps to improve
Deepwater program staffing, such as hiring contractors to assist with
program support functions, shifting some positions from military to
civilian to mitigate turnover risk, and identifying hard-to-fill
positions and developing recruitment plans specifically for them.
However, in February 2007, Coast Guard officials told us that key human
capital management objectives outlined in the revised plan have not
been accomplished and that the staffing levels needed to accomplish the
known workload have not been achieved. In one example, a manager cited
the need for five additional staff per asset under his domain to
satisfy the current workload in a timely manner: contracting officer's
technical representative, scheduler, cost estimator, analyst, and
configuration manager. Further, a February 2007 independent analysis
found that the Coast Guard does not possess a sufficient number of
acquisition personnel or the right level of experience needed to manage
the Deepwater program.[Footnote 13] The Coast Guard has identified an
acquisition structure re-organization that includes human capital as
one component of the reform. We will continue to monitor the
implementation of the reorganization as part of our ongoing work.
Communications with Field Personnel:
In 2004, we found that the Coast Guard had not adequately communicated
to field personnel decisions on how the new and old assets were to be
integrated during the transition and whether Coast Guard or system
integrator personnel--or both--would be responsible for maintenance. We
recommended that the Coast Guard provide timely information and
training on the transition to Deepwater assets. In 2006, we reported
that the Coast Guard had taken some steps to improve communications
between Deepwater program and field personnel, including having field
personnel as members on some IPTs. However, we continued to express
concerns that field personnel were not receiving important information
regarding training, maintenance, and integration of new Deepwater
assets.
During our ongoing work, the field personnel involved in operating and
maintaining the assets and Deepwater program staff we interviewed
expressed continued concern that maintenance and logistics plans had
not been finalized. Another official commented that there continues to
be a lack of clarity defining roles and responsibilities between the
Coast Guard and system integrator for maintenance and logistics. Coast
Guard officials stated in fall 2006 that the system integrator was
contractually responsible for developing key documents related to plans
for the maintenance and logistics for the NSC and Maritime Patrol
Aircraft. However, Deepwater program officials stated that because the
Coast Guard was not satisfied with the level of detail provided in
early drafts of these plans, it was simultaneously developing "interim"
plans that it could rely on while the system integrator continued to
develop its own versions. While the Coast Guard's more active role may
help its ability to ensure adequate support for Deepwater assets that
are coming on-line in the near term, our on-going work will continue to
focus on this issue.
Concerns Remain with Holding System Integrator Accountable:
Our 2004 review revealed that the Coast Guard had not developed
quantifiable metrics to hold the system integrator accountable for its
ongoing performance. For example, the process by which the Coast Guard
assessed performance to make the award fee determination after the
first year of the contract lacked rigor. At that time, we also found
that the Coast Guard had not yet begun to measure contractor
performance against Deepwater program goals--the information it would
need by June 2006 to decide whether to extend the system integrator's
contract award term by up to another 5 years. Additionally, we noted
that the Coast Guard needed to establish a solid baseline against which
to measure progress in lowering total ownership cost--one of the three
overarching goals of the Deepwater program. Furthermore, the Coast
Guard had not developed criteria for potential adjustments to the
baseline. Preliminary observations from our ongoing work on the Coast
Guard's efforts to improve system integrator accountability follow.
Award Fee Criteria:
In 2004 we found the first annual award fee determination was based
largely on unsupported calculations. Despite documented problems in
schedule, performance, cost control, and contract administration
throughout the first year, the program executive officer awarded the
contractor an overall rating of 87 percent, which fell in the "very
good" range as reported by the Coast Guard award fee determining
official. This rating resulted in an award fee of $4 million of the
maximum $4.6 million. The Coast Guard continued to report design, cost,
schedule, and delivery problems, and evaluation of the system
integrator's performance continued to result in award fees that ranged
from 87 percent to 92 percent of the total possible award fee (with 92
percent falling into the "excellent" range), or $3.5 to $4.8 million
annually, for a total of over $16 million the first 4 years on the
contract. The Coast Guard continues to revise the award fee criteria
under which it assesses the system integrator's performance.
The current award fee criteria demonstrate the Coast Guard's effort to
use both objective and subjective measures and to move toward clarity
and specificity with the criteria being used. For example, the criteria
include 24 specific milestone activities and dates to which the system
integrator will be held accountable for schedule management. However,
we recently observed two changes to the criteria that could affect the
Coast Guard's ability to hold the contractor accountable. First, the
current award fee criteria no longer contain measures that specifically
address IPTs, despite a recommendation we made in 2004 that the Coast
Guard hold the system integrator accountable for IPT effectiveness. The
Coast Guard had agreed with this recommendation and, as we reported in
2005, it had incorporated award fee metrics tied to the system
integrator's management of Deepwater, including administration,
management commitment, collaboration, training, and empowerment of the
IPTs. Second, a new criterion to assess both schedule and cost
management states that the Coast Guard will not take into account
milestone or cost impacts determined by the government to be factors
beyond the system integrator's control. However, a Coast Guard official
stated that there are no formal written guidelines that define what
factors are to be considered as being beyond the system integrator's
control, what process the Coast Guard is going to use to make this
determination, or who is ultimately responsible for making those
determinations.
Award Term Evaluation:
The Deepwater program management plan included three overarching goals
of the Deepwater program: increased operational effectiveness, lower
total ownership cost, and customer satisfaction to be used for
determining whether to extend the contract period of performance, known
as the award term decision. We reported in 2004 that the Coast Guard
had not begun to measure the system integrator's performance in these
three areas, even though the information was essential to determining
whether to extend the contract after the first 5 years.[Footnote 14] We
also reported that the models the Coast Guard was using to measure
operational performance lacked the fidelity to capture whether
improvements may be due to Coast Guard or contractor actions, and
program officials noted the difficulty of holding the contractor
accountable for operational effectiveness before Deepwater assets are
delivered. We made a recommendation to Coast Guard to address these
issues.
According to a Coast Guard official, the Coast Guard evaluated the
contractor subjectively for the first award term period in May 2006,
using operational effectiveness, total ownership costs, and customer
satisfaction as the criteria. The result was a new award term period of
43 of a possible 60 months. To measure the system's operational
effectiveness, the Coast Guard has developed models to simulate the
effect of the Deepwater assets' capabilities on its ability to meet its
missions and to measure the "presence" of those assets. However, in its
assessment of the contractor, the Coast Guard assumed full operational
capability of assets and communications and did not account for actual
asset operating data. Furthermore, the models still lacked the fidelity
to capture whether operational improvements are attributable to Coast
Guard or contractor actions. As a result the contractor received credit
for factors beyond its control--although no formal process existed for
approving such factors. Total ownership cost was difficult to measure,
thus the contractor was given a neutral score, according to Coast Guard
officials.[Footnote 15] Finally, the contractor was rated "marginal" in
customer satisfaction.
The Coast Guard has modified the award term evaluation criteria to be
used to determine whether to grant a further contract extension after
the 43-month period ends in January 2011. The new criteria incorporate
more objective measures.
* While the three overall Deepwater program objectives (operational
effectiveness, total ownership costs, and customer satisfaction)
carried a weight of 100 percent under the first award term decision,
they will represent only about a third of the total weight for the
second award term decision. The criteria include items such as new
operational effectiveness measures that will include an evaluation of
asset-level key performance parameters, such as endurance, operating
range, and detection range.
* The new award term criteria have de-emphasized measurement of total
ownership cost, concentrating instead on cost control. Program
officials noted the difficulty of estimating ownership costs far into
the future, while cost control can be measured objectively using actual
costs and earned value data. In 2004, we recommended that the Coast
Guard establish a total ownership cost baseline that could be used to
periodically measure whether the Deepwater system-of-systems
acquisition approach is providing the government with increased
efficiencies compared to what it would have cost without this approach.
Our recommendation was consistent with the cost baseline criteria set
forth in the Deepwater program management plan. The Coast Guard agreed
with the recommendation at the time, but subsequently told us it does
not plan to implement it.
In our current work, we will explore the implication of the revised
award term evaluation criteria and the Coast Guard's ability to measure
the overarching goals of the acquisition strategy.
Establishing Criteria and Documenting Changes to the Baseline:
Establishing a solid baseline against which to measure progress in
lowering total ownership cost is critical to holding the contractor
accountable. The Coast Guard's original plan, set forth in the
Deepwater program management plan, was to establish as its baseline the
dollar value of replacing assets under a traditional, asset-by-asset
approach as the "upper limit for total ownership cost." In practice,
the Coast Guard decided to use the system integrator's estimated cost
of $70.97 billion plus 10 percent (in fiscal year 2002 dollars) for the
system-of-systems approach as the baseline. In 2004, we recommended
that the Coast Guard establish criteria to determine when the total
ownership cost baseline should be adjusted and ensure that the reasons
for any changes are documented.
Since then, the Coast Guard established a process that would require
DHS approval for adjustments to the total ownership cost
baseline.[Footnote 16] The Deepwater Program Executive Officer
maintains authority to approve baseline revisions at the asset or
domain level. However, depending on the severity of the change, these
changes are also subject to review and approval by DHS. In November
2005, the Coast Guard increased the total ownership cost baseline
against which the contractor will be evaluated to $304 billion.
Deepwater officials stated that the adjustment was the result of
incorporating the new homeland security mission requirements and
revising dollar estimates to a current year basis. Although the Coast
Guard is required to provide information to DHS on causal factors and
propose corrective action for a baseline breach of 8 percent or more,
the 8 percent threshold has not been breached because the threshold is
measured against total program costs and not on an asset
basis.[Footnote 17] For example, the decision to stop the conversion of
the 49 110-foot patrol boats after 8 hulls did not exceed the
threshold; nor did the damages and schedule delay to the NSC attributed
to Hurricane Katrina. During our ongoing work, Coast Guard officials
acknowledged that only a catastrophic event would ever trigger a
threshold breach. According to a Coast Guard official, DHS approval is
pending on shifting the baseline against which the system integrator is
measured to an asset basis.
Limited Knowledge of Cost Control Achieved Through Competition:
Further, our 2004 report also had recommendations related to cost
control through the use of competition. We reported that, although
competition among subcontractors was a key mechanism for controlling
costs, the Coast Guard had neither measured the extent of competition
among the suppliers of Deepwater assets nor held the system integrator
accountable for taking steps to achieve competition.[Footnote 18] As
the two first-tier subcontractors to the system integrator, Lockheed
Martin and Northrop Grumman have sole responsibility for determining
whether to provide the Deepwater assets themselves or hold
competitions--decisions commonly referred to as "make or buy." We noted
that the Coast Guard's hands-off approach to make-or-buy decisions and
its failure to assess the extent of competition raised questions about
whether the government would be able to control Deepwater program
costs.
The Coast Guard has taken steps to establish a reporting requirement
for the system integrator to provide information on competition on a
semi-annual basis. The system integrator is to provide detailed plans,
policies, and procedures necessary to ensure proper monitoring,
reporting, and control of its subcontractors. Further, reports are to
include total procurement activity, the value of competitive
procurements, and the subcontractors' name and addresses. The system
integrator provided the first competition report in October 2006.
However, because the report did not include the level of detail
required by Coast Guard guidelines, a Coast Guard official deemed that
the extent of competition could not be validated by the information
provided and a request was made to the system integrator for more
information. We will continue to assess the Coast Guard's efforts to
hold the system integrator accountable for ensuring an adequate degree
of competition.
Mr. Chairman, this concludes my testimony. I would be happy to respond
to any questions Members of the Committee may have.
GAO Contact and Staff Acknowledgments:
For further information about this testimony, please contact:
John Hutton, Acting Director, Acquisition and Sourcing Management,
(202) 512-4841, huttonj@gao.gov:
Stephen L. Caldwell, Acting Director, Homeland Security & Justice,
(202) 512-9610, caldwells@gao.gov:
[End of section]
In addition to the contacts named above, Penny Berrier Augustine, Amy
Bernstein, Christopher Conrad, Adam Couvillion, Kathryn Edelman,
Melissa Jaynes, Crystal M. Jones, Michele Mackin, Jessica Nierenberg,
Raffaele Roffo, Karen Sloan, and Jonathan R. Tumin made key
contributions to this report.
Appendix I: RElated GAO Products:
Coast Guard: Status of Deepwater Fast Response Cutter Design Efforts,
GAO-06-764 (Washington, D.C.: June 23, 2006).
Coast Guard: Changes to Deepwater Plan Appear Sound, and Program
Management Has Improved, but Continued Monitoring is Warranted, GAO-06-
546 (Washington, D.C.: Apr. 28, 2006).
Coast Guard: Progress Being Made on Addressing Deepwater Legacy Asset
Condition Issues and Program Management, but Acquisition Challenges
Remain, GAO-05-757 (Washington, D.C.: Jul. 22, 2005).
Coast Guard: Preliminary Observations on the Condition of Deepwater
Legacy Assets and Acquisition Management Challenges, GAO-05-651T
(Washington, D.C.: Jun. 21, 2005).
Coast Guard: Preliminary Observations on the Condition of Deepwater
Legacy Assets and Acquisition Management Challenges, GAO-05-307T
(Washington, D.C.: Apr. 20, 2005).
Coast Guard: Deepwater Program Acquisition Schedule Update Needed, GAO-
04-695 (Washington, D.C.: Jun. 14, 2004).
Contract Management: Coast Guard's Deepwater Program Needs Increased
Attention to Management and Contractor Oversight, GAO-04-380
(Washington, D.C.: Mar. 9, 2004).
Coast Guard: Actions Needed to Mitigate Deepwater Project Risks, GAO-
01-659T (Washington, D.C.: May 3, 2001).
Coast Guard: Progress Being Made on Deepwater Project, but Risks
Remain, GAO-01-564 (Washington, D.C.: May, 2, 2001).
FOOTNOTES
[1] GAO, Contract Management: Coast Guard's Deepwater Program Needs
Increased Attention to Management and Contractor Oversight, GAO-04-380
(Washington, D.C.: Mar. 9, 2004).
[2] GAO, Coast Guard: Changes to Deepwater Appear Sound, and Program
Management Has Improved, but Continued Monitoring is Warranted, GAO-06-
546 (Washington, D.C.: Apr. 28, 2006).
[3] In addition to these asset classes, Coast Guard plans to procure
surveillance data from another unmanned aerial vehicle, the RQ-4A.
Because this is not to be acquired as a capital investment, we do not
include it among the assets to be acquired or upgraded.
[4] GAO-04-380
[5] CSC Advanced Marine, Evaluation of the 110' WPB Class Cutter Fleet
(January 2001).
[6] DHS OIG-07-23.
[7] GAO, Coast Guard: Status of Deepwater Fast Response Cutter Design
Efforts, GAO-06-764 (Washington, D.C.: June 23, 2006).
[8] Coast Guard refers to this vessel as the FRC-B.
[9] Coast Guard refers to this as the FRC-A.
[10] GAO, Coast Guard: Progress Being Made on Addressing Legacy Asset
Condition Issues and Program Management, but Acquisition Challenges
Remain, GAO-05-757 (Washington, D.C.: July 22, 2005).
[11] The program management reports were produced on a monthly basis in
the past; now they are produced on a quarterly basis.
[12] IPTs are focused on the development and fielding of a particular
product (e.g., the NSC) and are organized by domain. Examples of
domains are air, surface, C4ISR, and legacy assets.
[13] Defense Acquisition University, Quick Look Study: United States
Coast Guard Deepwater Program, (Fort Belvoir, VA.) Feb. 5, 2007
[14] Award-term incentives can best be described as a variant of an
award-fee incentive, where the contractor is rewarded for excellent
performance with an extension of the contract period instead of
additional fee.
[15] The award term determination rated total ownership cost as "good."
[16] According to DHS officials, a baseline breach occurs when a cost
or schedule threshold is exceeded or when a performance threshold
cannot be met.
[17] According to DHS officials, a baseline breach occurs when a cost
or schedule threshold is exceeded or when a performance threshold
cannot be met.
[18] See GAO-04-380.
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts
newly released reports, testimony, and correspondence on its Web site.
To have GAO e-mail you a list of newly posted products every afternoon,
go to www.gao.gov and select "Subscribe to Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office 441 G Street NW, Room LM
Washington, D.C. 20548:
To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202)
512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S.
Government Accountability Office, 441 G Street NW, Room 7125
Washington, D.C. 20548:
Public Affairs:
Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800
U.S. Government Accountability Office, 441 G Street NW, Room 7149
Washington, D.C. 20548: