Coast Guard
Status of Efforts to Improve Deepwater Program Management and Address Operational Challenges
Gao ID: GAO-07-575T March 8, 2007
The Coast Guard's Deepwater program is a 25-year, $24 billion plan to replace or modernize its fleet of vessels and aircraft. While there is widespread acknowledgment that many of the Coast Guard's aging assets need replacement or renovation, concerns exist about the acquisition approach the Coast Guard adopted in launching the Deepwater program. From the outset, GAO has expressed concern about the risks involved with the Coast Guard's acquisition strategy, and continues to review Deepwater program management. This statement discusses (1) the Coast Guard's acquisition approach for the Deepwater program; (2) Coast Guard efforts to manage the program, hold contractors accountable, and control costs through competition; (3) the status of the Coast Guard's efforts to acquire new or upgraded Deepwater assets; and (4) operational challenges the Coast Guard is facing because of performance and design problems with Deepwater patrol boats.
In 2001, we described the Deepwater program as "risky" due to the unique, untried acquisition strategy for a project of this magnitude. The Coast Guard used a system-of-systems approach to replace deteriorating assets with a single, integrated package of assets. The Coast Guard also used a system integrator--which relies on a contractor for requirements development, design, and source selection of major system and subsystem subcontractors. The Deepwater program is also a performance-based acquisition, meaning that it is structured around the results to be achieved rather than the manner in which the work is performed. If performance-based acquisitions are not appropriately planned and structured, there is an increased risk that the government may receive products or services that are over cost estimates, delivered late, and of unacceptable quality. From the program's outset, GAO has raised concerns about the risks involved with the Coast Guard's Deepwater acquisition strategy. In 2004, GAO reported that program management, contractor accountability, and cost control were all challenges, and made recommendations in these areas. The Coast Guard has taken some actions to address these issues. Of the 10 classes of upgraded or new Deepwater aircraft and vessels, the delivery record for first-in-class assets (that is, the first asset to be delivered within each class) is mixed. Specifically, 7 of the 10 asset classes are on or ahead of schedule, while 3 asset classes are currently behind schedule due to various problems related to designs, technology, or funding. The Coast Guard is facing operational challenges because of performance and design problems with Deepwater patrol boats. Specifically, in November 2006, performance problems led the Coast Guard to suspend all normal operations of the 123-foot patrol boats that had been converted from 110-foot patrol boats. In addition, in February 2006, the Coast Guard suspended design work on the Fast Response Cutter, due to design risks that has led to a delivery delay for the vessel.
GAO-07-575T, Coast Guard: Status of Efforts to Improve Deepwater Program Management and Address Operational Challenges
This is the accessible text file for GAO report number GAO-07-575T
entitled 'Coast Guard: Status of Efforts to Improve Deepwater Program
Management and Address Operational Challenges' which was released on
March 8, 2007.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
United States Government Accountability Office:
Before the Subcommittee on Coast Guard and Maritime Transportation,
Committee on Transportation and Infrastructure,
GAO:
For Release on Delivery Expected at 10:00 a.m. EST:
Thursday, March 8, 2007:
Coast Guard:
Status of Efforts to Improve Deepwater Program Management and Address
Operational Challenges:
Statement of Stephen L. Caldwell, Acting Director:
Homeland Security and Justice Issues:
GAO-07-575T:
GAO Highlights:
Highlights of GAO-07-575T, a report to before the Subcommittee on Coast
Guard and Maritime Transportation, Committee on Transportation and
Infrastructure, U.S. House of Representatives
Why GAO Did This Study:
The Coast Guard‘s Deepwater program is a 25-year, $24 billion plan to
replace or modernize its fleet of vessels and aircraft. While there is
widespread acknowledgment that many of the Coast Guard‘s aging assets
need replacement or renovation, concerns exist about the acquisition
approach the Coast Guard adopted in launching the Deepwater program.
From the outset, GAO has expressed concern about the risks involved
with the Coast Guard‘s acquisition strategy, and continues to review
Deepwater program management.
This statement discusses (1) the Coast Guard‘s acquisition approach for
the Deepwater program; (2) Coast Guard efforts to manage the program,
hold contractors accountable, and control costs through competition;
(3) the status of the Coast Guard‘s efforts to acquire new or upgraded
Deepwater assets; and (4) operational challenges the Coast Guard is
facing because of performance and design problems with Deepwater patrol
boats.
What GAO Found:
In 2001, we described the Deepwater program as ’risky“ due to the
unique, untried acquisition strategy for a project of this magnitude.
The Coast Guard used a system-of-systems approach to replace
deteriorating assets with a single, integrated package of assets. The
Coast Guard also used a system integrator”which relies on a contractor
for requirements development, design, and source selection of major
system and subsystem subcontractors. The Deepwater program is also a
performance-based acquisition, meaning that it is structured around the
results to be achieved rather than the manner in which the work is
performed. If performance-based acquisitions are not appropriately
planned and structured, there is an increased risk that the government
may receive products or services that are over cost estimates,
delivered late, and of unacceptable quality.
From the program‘s outset, GAO has raised concerns about the risks
involved with the Coast Guard‘s Deepwater acquisition strategy. In
2004, GAO reported that program management, contractor accountability,
and cost control were all challenges, and made recommendations in these
areas. The Coast Guard has taken some actions to address these issues.
Of the 10 classes of upgraded or new Deepwater aircraft and vessels,
the delivery record for first-in-class assets (that is, the first asset
to be delivered within each class) is mixed. Specifically, 7 of the 10
asset classes are on or ahead of schedule, while 3 asset classes are
currently behind schedule due to various problems related to designs,
technology, or funding.
The Coast Guard is facing operational challenges because of performance
and design problems with Deepwater patrol boats. Specifically, in
November 2006, performance problems led the Coast Guard to suspend all
normal operations of the 123-foot patrol boats that had been converted
from 110-foot patrol boats. In addition, in February 2006, the Coast
Guard suspended design work on the Fast Response Cutter, due to design
risks that has led to a delivery delay for the vessel.
Figure: Deepwater Vessel and Aircraft Classes:
[See PDF for Image]
Source: U.S. Coast Guard.
[End of figure]
What GAO Recommends:
This testimony contains no recommendations. In 2004, GAO made 11
recommendations on management and oversight, contractor accountability,
and cost control through competition. In addition, in April 2006 we
reported that progress had been made, but continued monitoring was
warranted.
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-575T].
To view the full product, including the scope and methodology, click on
the link above. For more information, contact Stephen L. Caldwell at
(202) 512-9610 or CaldwellS@gao.gov.
[End of section]
Mr. Chairman and Members of the Committee:
Thank you for inviting me here today to discuss GAO's recent reviews of
Coast Guard's Deepwater program, a $24 billion effort to upgrade or
replace existing aircraft and vessels to ensure Coast Guard's ability
to meet its many missions. The Deepwater program is eventually to
include 10 major classes of new or upgraded assets--5 major classes
each of aircraft and vessels. To carry out this effort, the Coast Guard
has relied on an acquisition strategy that gives responsibility to a
contractor (systems integrator) for designing, integrating, and
delivering a number of aircraft, vessels, and supporting communications
equipment. Using a systems integrator in this fashion means that the
government is acquiring management capacity it has historically
maintained in house through a service contract.
GAO has been involved in reviewing the Deepwater program since 2001,
and has informed Congress, the Department of Homeland Security (DHS),
and the Coast Guard of risks and challenges associated with the
program. Specifically, GAO has raised concerns related to the Coast
Guard's acquisition strategy for Deepwater, changes in the asset mix
and delivery schedules, as well as Coast Guard's ability to manage the
program and oversee the systems integrator's performance.[Footnote 1]
In March 2004, we made recommendations to the Coast Guard to address
three areas of concern: improving program management, strengthening
contractor accountability, and promoting cost control through greater
competition among potential subcontractors.
Challenges associated with specific Deepwater assets have recently
received significant attention. For example, the Commandant made a
decision to remove the 123-foot patrol boats, a converted legacy asset,
from service on November 30, 2006 due to operational and safety
concerns. This decision has created operational gaps for those missions
the patrol boats perform and the Coast Guard is currently attempting to
address this through a number of different strategies.
This statement offers information on the Coast Guard's efforts to
manage the Deepwater program and address operational challenges that
have arisen. Specifically, it discusses:
* the Coast Guard's acquisition approach for the Deepwater program;
* Coast Guard efforts to manage the Deepwater program, hold contractors
accountable, and control costs through competition;
* the status of the Coast Guard's efforts to acquire new or upgraded
Deepwater assets; and:
* operational challenges the Coast Guard is facing because of
performance and design problems with Deepwater patrol boats.
The information noted in this testimony is based on our review of key
documents, including the 2005 Deepwater Acquisition Program Baseline;
schedule information provided by the Coast Guard; Coast Guard memoranda
regarding the 123-foot patrol boat conversion; and Coast Guard's human
capital plan, its award fee and award term documentation, and its
competition monitoring plan. We conducted interviews with Coast Guard
officials at agency headquarters in Washington, D.C; officials in Coast
Guard's System Integration Program Office in Arlington, VA; and Coast
Guard contractor staff. In addition, we interviewed Coast Guard
officials during visits to the Pacific and Atlantic Area Commands and
their associated Maintenance and Logistics Commands and at the Coast
Guard's Aircraft Repair and Supply Center. Our work was conducted from
August 2006 to February 2007 in accordance with generally accepted
government auditing standards. In addition, GAO has been reviewing the
Deepwater program since 2001, and some of the information in this
testimony comes from our earlier work. Appendix I contains a list of
related GAO products.
Summary:
In 2001, we described the Deepwater program as "risky" due to the
unique, untried acquisition strategy for a project of this magnitude
within the Coast Guard. The Coast Guard used a system-of-systems
approach to replace deteriorating assets with a single, integrated
package of aircraft, vessels, and unmanned aerial vehicles to be linked
through systems that provide command, control, communications,
computer, intelligence, surveillance, and reconnaissance (C4ISR), and
supporting logistics. In a system-of-systems, the delivery of Deepwater
assets are interdependent, thus schedule slippages and uncertainties
associated with potential changes in the design and capabilities of any
one asset increases the overall risk that the Coast Guard might not
meet its expanded homeland security missions within given budget
parameters and milestone dates. The Coast Guard also used a systems
integrator--which can give the contractor extensive involvement in
requirements development, design, and source selection of major system
and subsystem subcontractors. The Deepwater program is also a
performance-based acquisition, meaning that it is structured around the
results to be achieved rather than the manner in which the work is
performed. If performance-based acquisitions are not appropriately
planned and structured, there is an increased risk that the government
may receive products or services that are over cost estimates,
delivered late, and of unacceptable quality.
In 2004 and in subsequent assessments in 2005 and 2006, we reported
concerns about the Deepwater program related to three main areas--
program management, contractor accountability, and cost control. The
Coast Guard's ability to effectively manage the program has been
challenged by staffing shortfalls and poor communication and
collaboration among Deepwater program staff, contractors, and field
personnel who operate and maintain the assets. Despite documented
problems in schedule, performance, cost control, and contract
administration, measures for holding the contractor accountable
resulted in an award fee of $4 million (of the maximum $4.6 million)
for the first year. Through the first 4 years of the Deepwater
contract, the systems integrator received award fees that ranged from
87 percent to 92 percent of the total possible award fee (scores that
ranged from "very good" to "excellent" based on Coast Guard criteria),
for a total of over $16 million. Further, the program's ability to
control Deepwater costs is uncertain given the Coast Guard's lack of
detailed information on the contractor's competition decisions. While
the Coast Guard has taken some actions to improve program outcomes, our
assessment of the program and its efforts to address our
recommendations continues, and we plan to report on our findings later
this year.
Of the 10 classes of upgraded or new Deepwater aircraft and vessels,
the delivery record for first-in-class assets (that is, the first of
multiple aircraft or vessels to be delivered within each class) is
mixed. Specifically, 7 of the 10 asset classes are on or ahead of
schedule. Among these, five first-in-class assets have been delivered
on or ahead of schedule; and two others remain on schedule but their
planned delivery dates are in 2009 or beyond. Three Deepwater asset
classes are currently behind schedule due to various problems related
to designs, technology, or funding. For example, the Fast Response
Cutter (a new vessel), which had been scheduled for first-in-class
delivery in 2007, has been delayed by at least 2 years in part because
work on its design was suspended until technical problems related to
its hull and other issues can be addressed. The Vertical Unmanned
Aerial Vehicle (a new aircraft), which had also been scheduled for
delivery in 2007, has been delayed by 6 years due to evolving
technological developments, among other things. In addition, the
Offshore Patrol Cutter, which had a planned delivery date in 2010, has
now been delayed by 5 years.
The Coast Guard is facing operational challenges because of performance
and design problems with Deepwater patrol boats. Specifically, the
conversion of legacy 110-foot patrol boats to upgraded 123-foot patrol
boats was stopped at eight hulls (rather than the entire fleet of 49)
due to deck cracking, hull buckling, and shaft alignment problems.
These patrol boat conversion problems ultimately led the Coast Guard to
suspend all normal operations of the eight converted 123-foot patrol
boats on November 30, 2006. The Coast Guard is now exploring options to
address the resulting short-term operational gaps. There have also been
design problems with the new Fast Response Cutter (FRC), intended to
replace all 110-foot and 123-foot patrol boats. In February 2006, the
Coast Guard suspended design work on the FRC due to design risks, such
as excessive weight and horsepower requirements.[Footnote 2] According
to the Coast Guard, it has decided to acquire two classes of FRCs in an
effort to not delay delivery of the FRCs further. the Coast Guard two
classes of FRCs. One class is to be based on an adapted design from a
patrol boat already on the market and another class is to be redesigned
to address the problems in the original FRC design plans. As with the
123-foot patrol boats, the Coast Guard is looking at options to address
these long-term operational gaps.
Background:
The Coast Guard is the lead federal agency for maritime security within
DHS. The Coast Guard is responsible for a variety of missions,
including ensuring ports, waterways, and coastline security; conducting
search and rescue missions; interdicting illicit drug shipments and
illegal aliens; and enforcing fisheries laws. In 1996, in order to
continue carrying out its responsibilities and operations, the Coast
Guard initiated the Deepwater program to replace or upgrade its aging
vessels, aircraft, and other essential equipment.
As originally conceived, Deepwater was designed around producing
aircraft and vessels that would function in the Coast Guard's
traditional at-sea roles--such as interdicting illicit drug shipments
or rescuing mariners from difficulty at sea--and the original 2002
Deepwater program was focused on those traditional missions. After the
terrorist attacks on September 11, 2001, the Coast Guard was also
assigned homeland security missions related to protection of ports,
waterways, and coastal areas. Based on its revised mission
responsibilities, the Coast Guard updated its Deepwater Acquisition
Program Baseline in November 2005. The new baseline contained changes
in the balance between new assets to be acquired and legacy assets to
be upgraded and adjusted the delivery schedule and costs for many of
these assets. Overall, the Deepwater acquisition schedule was
lengthened by 5 years, with the final assets now scheduled for delivery
in 2027.
Upon its completion, the Deepwater program is to consist of 5 new
classes of vessels, 1 new class of fixed-wing aircraft, 1 new class of
unmanned aerial vehicles, 2 classes of upgraded helicopters, and 1
class of upgraded fixed-wing aircraft.[Footnote 3] The 215 new vessels
consist of five new asset classes--the National Security Cutter (NSC),
Offshore Patrol Cutter (OPC), Fast Response Cutter (FRC), Long-Range
Interceptor (LRI), and Short-Range Prosecutor (SRP). The 240 aircraft
are composed of two new aircraft classes, the Vertical Unmanned Aerial
Vehicle (VUAV) and the Maritime Patrol Aircraft (MPA); and three
upgraded asset classes--the Long-Range Surveillance Aircraft (LRS),
Medium-Range Recovery Helicopter (MRR), and the Multi-Mission Cutter
Helicopter (MCH).
Table 1 provides an overview, by asset class, of the Deepwater vessels
to be acquired and table 2 provides an overview of the Deepwater
aircraft to be acquired or upgraded. As noted in Table 1, the 140-foot
FRC was designated as a replacement vessel for the 110-foot and 123-
foot patrol boats.
Figure 1: Deepwater Vessel Classes to be Acquired:
[See PDF for image]
Source: GAO analysis of Coast Guard documentation.
[End of figure]
Figure 2: Deepwater Aircraft Classes to be Upgraded or Acquired:
[See PDF for image]
Source: GAO analysis of Coast Guard documentation.
[End of figure]
Since 2001, we have reviewed the Deepwater program and have informed
Congress, DHS, and Coast Guard of the problems, risks, and
uncertainties inherent with such a large acquisition that relies on a
systems integrator to identify the assets needed and then using tiers
of subcontractors to design and build the assets. In March 2004, we
made recommendations to the Coast Guard to address three broad areas of
concern: improving program management, strengthening contractor
accountability, and promoting cost control through greater competition
among potential subcontractors (see table 3). [Footnote 4]
Table 1: Status of GAO Recommendations to the U.S. Coast Guard
Regarding Management of the Deepwater Program, as of April 28, 2006:
Areas of concern: Key components of management and oversight;
Recommendations to the U.S. Coast Guard: Put in place a human capital
plan to ensure adequate staffing of the Deepwater program;
Recommendation status: Partially implemented[A] (human capital plan was
revised).
Recommendations to the U.S. Coast Guard: Improve integrated product
teams (IPTs) responsible for managing the program by providing better
training, approving charters for sub-IPTs, and improving systems for
sharing information between teams;
Recommendation status: Partially implemented.
Recommendations to the U.S. Coast Guard: Provide field operators and
maintenance personnel with timely information and training on how the
transition to Deepwater assets will occur and how maintenance
responsibilities are to be divided between the systems integrator and
Coast Guard personnel;
Recommendation status: Partially implemented.
Areas of concern: Procedures for ensuring contractor accountability;
Recommendations to the U.S. Coast Guard: Develop measurable award fee
criteria consistent with guidance from the Office of Federal
Procurement Policy;
Recommendation status: Implemented.
Recommendations to the U.S. Coast Guard: Provide for better input from
U.S. Coast Guard performance monitors;
Recommendation status: Implemented.
Recommendations to the U.S. Coast Guard: Hold the systems integrator
accountable in future award fee determinations for improving
effectiveness of the IPTs;
Recommendation status: Implemented.
Recommendations to the U.S. Coast Guard: Establish a baseline for
determining whether the acquisition approach is costing the government
more than the traditional asset replacement approach;
Recommendation status: Will not be implemented.
Recommendations to the U.S. Coast Guard: Establish a time frame for
when the models and metrics will be in place with the appropriate
degree of fidelity to be able to measure contractor's progress toward
improving operational effectiveness;
Recommendation status: Partially implemented.
Recommendations to the U.S. Coast Guard: Establish criteria to
determine when to adjust the project baseline and document the reasons
for change;
Recommendation status: Partially implemented.
Areas of concern: Control of future costs through competition;
Recommendations to the U.S. Coast Guard: For subcontracts over $5
million awarded by the systems integrator to the two major
subcontractors, require notification to the Coast Guard about decision
to perform the work in-house rather than contracting it out;
Recommendation status: Implemented.
Recommendations to the U.S. Coast Guard: Develop a comprehensive plan
for holding the systems integrator accountable for ensuring adequate
competition among suppliers;
Recommendation status: Partially implemented.
Source: GAO-04-380 and GAO-06-546.
Note: AWhile the Coast Guard has revised its human capital plan, it has
not yet addressed the rest of the recommendation, which is to ensure
adequate staffing for the Deepwater program.
[End of table]
Coast Guard's Acquisition Approach to the Deepwater Program:
In 2001, we described the Deepwater program as "risky" due to the
unique, untried acquisition strategy for a project of this magnitude
within the Coast Guard. The approach included the development of a
system-of-systems, a single systems integrator, and a performance-based
contract.
System of Systems:
Rather than using the traditional approach of replacing classes of
ships or aircraft through a series of individual acquisitions, the
Coast Guard chose to use a system-of-systems acquisition strategy that
would replace its deteriorating assets with a single, integrated
package of aircraft, vessels, and unmanned aerial vehicles, to be
linked through systems that provide C4ISR, and supporting
logistics.[Footnote 5] Through this approach, the Coast Guard hoped to
avoid "stovepiping" the acquisition of vessels and aircraft, which
might lead to a situation where they could not operate optimally
together.
Despite the Coast Guard's intention to avoid stovepiping in the
acquisition process, we found that the Deepwater program has not been
as integrated as hoped. Our past work on Deepwater noted that decisions
on aircraft were made by one subcontractor, while decisions regarding
vessels were made by another subcontractor. These separate lines of
decision-making can lessen the likelihood that a system-of-systems
outcome will be achieved if decisions affecting the entire program are
made without the full consultation of all parties involved. Our more
recent work on the Fast Response Cutter (FRC)--which is discussed in
more detail later--indicated that changes in the design and delivery
date for the FRC could affect the operations of the overall system-of-
systems approach. Because the delivery of Deepwater assets are
interdependent within the system-of-systems acquisition approach,
schedule slippages and uncertainties associated with potential changes
in the design and capabilities of the new assets have increased the
risks of the Coast Guard failing to meet its expanded homeland security
missions within given budget parameters and milestone dates.
Systems Integrator:
In June 2002, the Coast Guard awarded the Deepwater contract to
Integrated Coast Guard Systems (ICGS). ICGS--a business entity jointly
owned by Northrop Grumman and Lockheed Martin--is responsible for
designing, constructing, deploying, supporting, and integrating the
Deepwater assets to meet Coast Guard requirements.
Government agencies have turned to the systems integrator approach when
they believe they do not have the in-house capability to design,
develop, and manage complex acquisitions.[Footnote 6] This type of
business arrangement can give the contractor extensive involvement in
requirements development, design, and source selection of major system
and subsystem subcontractors. Giving contractors more control and
influence over the government's acquisitions in a systems integrator
role creates a potential risk that program decisions and products could
be influenced by the financial interest of the contractor--which is
accountable to its shareholders--which may not match the primary
interest of the government, maximizing its return on taxpayer dollars.
The systems integrator arrangement creates an inherent risk, as the
contractor is given more discretion to make certain program decisions.
Along with this greater discretion comes the need for more government
oversight and an even greater need to develop well-defined outcomes at
the outset.
Performance-based Acquisition:
The Deepwater program has been designated as a performance-based
acquisition. When buying services, federal agencies are currently
required to employ--to the maximum extent feasible--this concept,
wherein acquisitions are structured around the results to be achieved
as opposed to the manner in which the work is to be performed. That is,
the government specifies the outcome it requires while leaving the
contractor to propose decisions about how it will achieve that outcome.
Performance-based contracts for services are required to include a
performance work statement; measurable performance standards (i.e., in
terms of quality, timeliness, quantity, etc.) as well as the method of
assessing contractor performance against these standards; and
performance incentives, where appropriate. If performance-based
acquisitions are not appropriately planned and structured, there is an
increased risk that the government may receive products or services
that are over cost estimates, delivered late, and of unacceptable
quality.
Deepwater Indicative of Broader, Systematic Acquisition Challenges:
Some of the problems the Coast Guard is experiencing with the Deepwater
program are similar to problems we have reported on in other those we
have found and reported about in other complex, developmental
systems.[Footnote 7] These problems stem from:
* Program requirements that are set at unrealistic levels, then changed
frequently as recognition sets in that they cannot be achieved. As a
result, too much time passes; threats may change; and/or members of the
user and acquisition communities may simply change their minds. The
resulting program instability causes cost escalation, schedule delays,
fewer quantities, and reduced contractor accountability.
* Program decisions to move into design and production without adequate
standards or knowledge.
* Contracts, especially service contracts, that often do not have
measures in place at the outset in order to control costs and
facilitate accountability.
* Contracts that typically do not accurately reflect the complexity of
projects or appropriately allocate risk between the contractors and the
taxpayers.
* Agency acquisition workforces that are challenged because of size,
skills, insufficient knowledge, and succession planning.
* Incentive and award fees that are often paid based on contractor
efforts versus positive results, such as cost, quality, and schedule.
* Inadequate government oversight that results in little to no
accountability for recurring and systemic problems.
Preliminary Observations on Deepwater Program Management, Contractor
Accountability, and Cost Control:
Since the inception of the Deepwater program, we have expressed
concerns about the risks involved with the Coast Guard's system-of-
systems acquisition approach and the Coast Guard's ability to manage
and oversee the program. Our concerns have centered on three main
areas: program management, contractor accountability, and cost control
through competition. We have made a number of recommendations to
improve the program--most of which the Coast Guard has agreed with and
is working to address. However, while actions are under way, a project
of this magnitude will likely continue to experience other problems as
more becomes known.
Program Management:
In 2004, we reported that the Coast Guard had not effectively
implemented key components needed to manage and oversee the systems
integrator. Specifically, we reported at that time and subsequently on
issues related to integrated product teams (IPT), the Coast Guard's
human capital strategy, and communication with field personnel
(individuals responsible for operating and maintaining the assets). Our
preliminary observations on the Coast Guard's progress in improving
these program management areas, based on our ongoing work, follow.
Integrated Product Teams:
In 2004, we found that IPTs, the Coast Guard's primary tool for
managing the Deepwater program and overseeing the contractor, had not
been effective due to changing membership, understaffing, insufficient
training, lack of authority for decision making, and inadequate
communication. We recommended the Coast Guard take actions to address
IPT effectiveness. We subsequently reported that IPT decision-making
was to a large extent stovepiped, and some teams lacked adequate
authority to make decisions within their realm of
responsibility.[Footnote 8] Coast Guard officials stated that they
believed collaboration among the subcontractors was problematic and
that the systems integrator wielded little influence to compel
decisions among them. For example, proposed design changes to assets
under construction were submitted as two separate proposals from both
subcontractors rather than one coherent plan. More recently, Coast
Guard performance monitors reported this approach complicated the
government review of design changes because the two proposals often
carried overlapping work items, thereby forcing the Coast Guard to act
as the systems integrator in those situations. Although some efforts
have been made to improve the effectiveness of the IPTs--such as
providing them with more timely charters and entry-level training--our
preliminary observations are that more improvements are needed.
Despite changes to the metrics, the Coast Guard's ability to assess IPT
performance continues to be problematic. Former assessments of IPT
effectiveness simply focused on measures such as frequency of meetings,
attendance, and training. As a result, IPTs received positive
assessments while the assets under their realm of responsibility--such
as the National Security Cutter--were experiencing problems. While the
Coast Guard's new IPT measurements include outcome-based metrics, such
as cost and schedule performance of assets, Deepwater's overall program
management quarterly reports, which are prepared by Coast Guard in
collaboration with ICGS, , which prepared by Coast Guard in
collaboration with ICGS, show that the connection between IPT
performance and program results continues to be misaligned.[Footnote 9]
For example, the first quarterly report to incorporate the new
measurements, covering the period October to December 2006, indicates
that the IPTs' performance for all domains is "on-schedule or non-
problematic" even while some assets' cost or schedule performance is
rated "behind schedule or problematic." [Footnote 10] Further, even
though the Deepwater program is addressing fundamental problems
surrounding the 123-foot patrol boat and FRC, IPTs no longer exist for
these assets. In some cases, Coast Guard officials stated they have
established work groups outside of the existing IPT structure to
address identified issues and problems related to assets, such as the
NSC.
Human Capital:
We also reported in 2004 that the Coast Guard had not adequately
staffed its program management function for Deepwater. Although its
Deepwater human capital plan set a goal of a 95 percent or higher "fill
rate" annually for both military and civilian personnel, funded
positions were below this goal. We recommended that the Coast Guard
follow the procedures in its Deepwater human capital plan to ensure
that adequate staffing was in place and that turnover of Coast Guard
military personnel was proactively addressed. The Coast Guard
subsequently revised its Deepwater human capital plan in February 2005
to emphasize workforce planning, including determining needed
knowledge, skills, and abilities and developing ways to leverage
institutional knowledge as staff rotate out of the program. We reported
in 2005 that the Coast Guard also took some short-term steps to improve
Deepwater program staffing, such as hiring contractors to assist with
program support functions, shifting some positions from military to
civilian to mitigate turnover risk, and identifying hard-to-fill
positions and developing recruitment plans specifically for them.
However, more recently we have learned that while the Coast Guard has
revised a human capital plan, key human capital management objectives
outlined in the revised plan have not been fully implemented. Thus, key
human capital management objectives outlined in the revised plan have
not been accomplished and the staffing levels needed to accomplish the
known workload have not been achieved. In one example, a manager cited
the need for five additional staff per asset under his domain to
satisfy the current workload in a timely manner: contracting officer's
technical representative, scheduler, cost estimator, analyst, and
configuration manager. Further, a February 2007 independent analysis
found that the Coast Guard does not possess a sufficient number of
acquisition personnel or the right level of experience needed to manage
the Deepwater program.[Footnote 11] The Coast Guard has identified an
acquisition structure re-organization that includes human capital as
one component of the reform.
Communication with Operations and Maintenance Personnel:
In 2004, we found that the Coast Guard had not adequately communicated
to operations and maintenance personnel in field locations about
decisions on how the new and old assets were to be integrated during
the transition and whether Coast Guard or systems integrator personnel-
-or both--would be responsible for maintenance. We recommended that the
Coast Guard provide timely information and training on the transition
to Deepwater assets. In 2006, we reported that the Coast Guard had
taken some steps to improve communications between Deepwater program
and field personnel, including having field personnel as members on
some IPTs. However, we continued to express concerns that field
personnel were not receiving important information regarding training,
maintenance, and integration of new Deepwater assets.
During our ongoing work, the field personnel involved in operating and
maintaining the assets and Deepwater program staff we interviewed
expressed continued concern that maintenance and logistics plans had
not been finalized. Another official commented that there continues to
be a lack of clarity defining roles and responsibilities between the
Coast Guard and systems integrator for maintenance and logistics. Coast
Guard officials stated in fall 2006 that the systems integrator was
contractually responsible for developing key documents related to plans
for the maintenance and logistics for the NSC and Maritime Patrol
Aircraft. However, Deepwater program officials stated that because the
Coast Guard was not satisfied with the level of detail provided in
early drafts of these plans, it was simultaneously developing "interim"
plans that it could rely on while the systems integrator continued to
develop its own versions.
Concerns Remain with Holding Systems Integrator Accountable:
Our 2004 review revealed that the Coast Guard had not developed
quantifiable metrics to hold the systems integrator accountable for its
ongoing performance. For example, the process by which the Coast Guard
assessed performance to make the award fee determination after the
first year of the contract lacked rigor. At that time, we also found
that the Coast Guard had not yet begun to measure contractor
performance against Deepwater contract requirements--the information it
would need by June 2006 to decide whether to extend the systems
integrator's contract award term by up to another 5 years.
Additionally, we noted that the Coast Guard needed to establish a solid
baseline against which to measure progress in lowering total ownership
cost--one of the three overarching goals of the Deepwater program.
Furthermore, the Coast Guard had not developed criteria for potential
adjustments to the baseline.
Award Fee Criteria:
In 2004 we found the first annual award fee determination was based
largely on unsupported calculations. Despite documented problems in
schedule, performance, cost control, and contract administration
throughout the first year, the program executive officer awarded the
contractor an overall rating of 87 percent, which fell in the "very
good" range as reported by the Coast Guard award fee determining
official. This rating resulted in an award fee of $4 million of the
maximum $4.6 million. The Coast Guard continued to report design, cost,
schedule, and delivery problems, and evaluation of the systems
integrator's performance continued to result in award fees that ranged
from 87 percent to 92 percent of the total possible award fee (with 92
percent falling into the "excellent" range), or $3.5 to $4.8 million
annually, for a total of over $16 million the first 4 years on the
contract.
The Coast Guard continues to refine the award fee criteria under which
it assesses the systems integrator's performance. The current award fee
criteria demonstrate the Coast Guard's effort to use both objective and
subjective measures and to move toward clarity and specificity with the
criteria being used. For example, the criteria include 24 specific
milestone activities and dates to which the systems integrator will be
held accountable for schedule management. However, we recently observed
two changes to the criteria that could affect the Coast Guard's ability
to hold the contractor accountable. First, the current award fee
criteria no longer contain measures that specifically address IPTs,
despite a recommendation we made in 2004 that the Coast Guard hold the
systems integrator accountable for IPT effectiveness. The Coast Guard
had agreed with this recommendation and, as we reported in 2005, it had
incorporated award fee metrics tied to the systems integrator's
management of Deepwater, including administration, management
commitment, collaboration, training, and empowerment of the IPTs.
Second, a new criterion to assess both schedule and cost management
states that the Coast Guard will not take into account milestone or
cost impacts determined by the government to be factors beyond the
systems integrator's control. However, a Coast Guard official stated
that there are no formal written guidelines that define what factors
are to be considered as being beyond the systems integrator's control,
what process the Coast Guard is going to use to make this
determination, or who is ultimately responsible for making those
determinations.
Award Term Evaluation:
The Deepwater program management plan included three overarching goals
of the Deepwater program: increased operational effectiveness, lower
total ownership cost, and customer satisfaction to be used for
determining whether to extend the contract period of performance, known
as the award term decision. We reported in 2004 that the Coast Guard
had not begun to measure the systems integrator's performance in these
three areas, even though the information was essential to determining
whether to extend the contract after the first 5 years.[Footnote 12] We
also reported that the models the Coast Guard was using to measure
operational performance lacked the fidelity to capture whether
improvements may be due to Coast Guard or contractor actions, and
program officials noted the difficulty of holding the contractor
accountable for operational effectiveness before Deepwater assets are
delivered. We made a recommendation to Coast Guard to address these
issues.
According to a Coast Guard official, the Coast Guard evaluated the
contractor subjectively for the first award term period in May 2006,
using operational effectiveness, total ownership costs, and customer
satisfaction as the criteria. The result was a new award term period of
43 of a possible 60 months. To measure the system's operational
effectiveness, the Coast Guard has developed models to simulate the
effect of the Deepwater assets' capabilities on its ability to meet its
missions and to measure the "presence" of those assets. However, in its
assessment of the contractor, the Coast Guard assumed full operational
capability of assets and communications and did not account for actual
asset operating data. Furthermore, the models still lacked the fidelity
to capture whether operational improvements are attributable to Coast
Guard or contractor actions. As a result the contractor received credit
for factors that may have been beyond its control--although no formal
process existed for approving such factors. Total ownership cost was
difficult to measure, thus the contractor was given a neutral score,
according to Coast Guard officials.[Footnote 13] Finally, the
contractor was rated "marginal" in customer satisfaction.
The Coast Guard has modified the award term evaluation criteria to be
used to determine whether to grant a further contract extension after
the 43-month period ends in January 2011. The new criteria incorporate
more objective measures.
* While the three overall Deepwater program objectives (operational
effectiveness, total ownership costs, and customer satisfaction)
carried a weight of 100 percent under the first award term decision,
they will represent only about a third of the total weight for the
second award term decision. The criteria include items such as new
operational effectiveness measures that will include an evaluation of
asset-level key performance parameters, such as endurance, operating
range, and detection range.
* The new award term criteria have de-emphasized measurement of total
ownership cost, concentrating instead on cost control. Program
officials noted the difficulty of estimating ownership costs far into
the future, while cost control can be measured objectively using actual
costs and earned value data. In 2004, we recommended that the Coast
Guard establish a total ownership cost baseline that could be used to
periodically measure whether the Deepwater system-of-systems
acquisition approach is providing the government with increased
efficiencies compared to what it would have cost without this approach.
Our recommendation was consistent with the cost baseline criteria set
forth in the Deepwater program management plan. The Coast Guard agreed
with the recommendation at the time, but subsequently told us it does
not plan to implement it.
Establishing Criteria and Documenting Changes to the Baseline:
Establishing a solid baseline against which to measure progress in
lowering total ownership cost is critical to holding the contractor
accountable. The Coast Guard's original plan, set forth in the
Deepwater program management plan, was to establish as its baseline the
dollar value of replacing assets under a traditional, asset-by-asset
approach as the "upper limit for total ownership cost." In practice,
the Coast Guard decided to use the systems integrator's estimated cost
of $70.97 billion plus 10 percent (in fiscal year 2002 dollars) for the
system-of-systems approach as the baseline. In 2004, we recommended
that the Coast Guard establish criteria to determine when the total
ownership cost baseline should be adjusted and ensure that the reasons
for any changes are documented.
Since then, the Coast Guard established a process that would require
DHS approval for adjustments to the total ownership cost baseline. The
Deepwater Program Executive Officer maintains authority to approve
baseline revisions at the asset or domain level. However, depending on
the severity of the change, these changes are also subject to review
and approval by DHS. In November 2005, the Coast Guard increased the
total ownership cost baseline against which the contractor will be
evaluated to $304 billion[Footnote 14]. Deepwater officials stated that
the adjustment was the result of incorporating the new homeland
security mission requirements and revising dollar estimates to a
current year basis. Although the Coast Guard is required to provide
information to DHS on causal factors and propose corrective action for
a baseline breach of 8 percent or more, the 8 percent threshold has not
been breached because the threshold is measured against total program
costs and not on an asset basis.[Footnote 15] For example, the decision
to stop the conversion of the 49 110-foot patrol boats after 8 hulls
did not exceed the threshold; nor did the damages and schedule delay to
the NSC attributed to Hurricane Katrina. During our ongoing work, Coast
Guard officials acknowledged that only a catastrophic event would ever
trigger a threshold breach. According to a Coast Guard official, DHS
approval is pending on shifting the baseline against which the systems
integrator is measured to an asset basis.
Limited Knowledge of Cost Control Achieved Through Competition:
Our 2004 report also had recommendations related to cost control
through the use of competition. We reported that, although competition
among subcontractors was a key mechanism for controlling costs, the
Coast Guard had neither measured the extent of competition among the
suppliers of Deepwater assets nor held the systems integrator
accountable for taking steps to achieve competition.[Footnote 16] As
the two first-tier subcontractors to the systems integrator, Lockheed
Martin and Northrop Grumman have sole responsibility for determining
whether to provide the Deepwater assets themselves or hold
competitions--decisions commonly referred to as "make or buy." We noted
that the Coast Guard's hands-off approach to make-or-buy decisions and
its failure to assess the extent of competition raised questions about
whether the government would be able to control Deepwater program
costs.
The Coast Guard has taken steps to establish a reporting requirement
for the systems integrator to provide information on competition on a
semi-annual basis. The systems integrator is to provide detailed plans,
policies, and procedures necessary to ensure proper monitoring,
reporting, and control of its subcontractors. Further, reports are to
include total procurement activity, the value of competitive
procurements, and the subcontractors' name and addresses. The systems
integrator provided the first competition report in October 2006.
However, because the report did not include the level of detail
required by Coast Guard guidelines, a Coast Guard official deemed that
the extent of competition could not be validated by the information
provided and a request was made to the systems integrator for more
information. We will continue to assess the Coast Guard's efforts to
hold the systems integrator accountable for ensuring an adequate degree
of competition.
Deepwater Asset Delivery Schedule Shows Mixed Results:
Our review of available data show that as of January 2007, of the 10
classes of Deepwater assets to be acquired or upgraded, 4 are ahead of
schedule; 3 remain on schedule (but for 1 of these, design problems
have arisen); and 3 are behind scheduled delivery and face design,
funding, or technology challenges. Using the 2005 Deepwater Acquisition
Program Baseline as the baseline, figure 1 indicates, for each asset
class, whether delivery of the first-in-class (that is, the first of
several to be produced in its class) is ahead of schedule, on schedule,
or behind schedule, as of January 2007.
Figure 3: Comparison of the Estimated Delivery Dates for the First-in-
Class Deepwater Assets from the 2005 Deepwater Acquisition Baseline and
as of January 2007:
[See PDF for image]
Source: GAO analysis of documentation provided by U.S. Coast Guard.
[End of figure]
Among the Deepwater assets, 3 of the 5 aircraft classes are upgrades to
existing legacy systems, and these are all on or ahead of schedule; 1
new aircraft class is ahead of schedule; and the remaining new aircraft
class is 6 years behind schedule. With respect to Deepwater vessels,
all 5 asset classes are new, and of these, 2 are behind schedule, and a
third, while on schedule, faces structural modifications. The remaining
2 new maritime assets are small vessels that are on or ahead of
schedule at this time.
Assets That Are on or Ahead of Schedule as of January 2007:
The status of each asset class, and our preliminary observations on the
factors affecting their status, is discussed below.
Long-Range Interceptor:
The LRI is a 36-foot small boat that is to be carried and deployed on
each NSC and OPC. Coast Guard has one LRI on contract for delivery in
August 2007, to match delivery of the first NSC.
Short-Range Prosecutor:
According to the Coast Guard, the SRP is on schedule at this time and 8
have been delivered to date. Coast Guard is currently planning to
pursue construction and delivery of the remaining SRPs outside of the
systems integrator contract. By doing so, the Coast Guard expects to
achieve a cost savings.
Maritime Patrol Aircraft:
The MPA is a commercial aircraft produced in Spain that is being
acquired to replace the legacy HU-25 aircraft and will permit the Coast
Guard to carryout missions such as search and rescue, marine
environmental protection, and maritime security. The first MPA was
delivered to the Coast Guard in December 2006 and the second and third
are due for delivery by April 2007. Pilots and aircrew participated in
training classes in Spain, and Coast Guard is to take responsibility
for the development and implementation of MPA's maintenance and
logistics.
Long-Range Surveillance Aircraft:
The LRS is an upgraded legacy fixed-wing aircraft that includes 6 C-
130Js and 16 C-130Hs. The first aircraft entered the modification
process in January 2007, and five additional aircraft are to be
modified by July 2008. In fiscal year 2008, funding has been requested
to upgrade the C-130H radar and avionics, and for the C-130J fleet
introduction.
Medium-Range Recovery Helicopter:
The MRR is an upgraded legacy HH-60 helicopter. It began receiving a
series of upgrades beginning in fiscal year 2006, which will continue
into fiscal year 2012, including the service life extension program and
radar upgrades.
Multi-Mission Cutter Helicopter:
The MCH is an upgraded legacy HH-65 helicopter. According to Coast
Guard officials, the MCH assets will not have a single delivery date,
as the process involves three phases of upgrades. Phase I is the
purchase and delivery of new engines and engine control systems, Phase
II is a service-life extension program, and Phase III includes
communications upgrades. A Coast Guard official stated that 84 of the
95 HH-65s should be re-engined by June 2007, and all 95 should be
finished by October 2007. The fiscal year 2008 congressional budget
justification states that Phase II began in fiscal year 2007 and will
end in fiscal year 2014, and that Phase III is to begin in fiscal year
2008 and is to end in fiscal year 2014.
National Security Cutter:
According to Coast Guard documentation, the first NSC is on schedule
for delivery in August 2007 despite required modifications regarding
its structural integrity. In particular, the Coast Guard Commandant
recently stated that internal reviews by Coast Guard engineers, as well
as by independent analysts, have concluded that the NSC, as designed,
will need structural reinforcement to meet its expected 30-year service
life. In addition, the DHS Office of Inspector General recently
reported that the NSC design will not achieve a 30-year service life
based on an operating profile of 230 days underway per year in general
Atlantic and North Pacific sea conditions and added that Coast Guard
technical experts believe the NSC's design deficiencies will lead to
increased maintenance costs and reduced service life.[Footnote 17]
To address the structural modifications of the NSC, Coast Guard is
taking a two-pronged approach. First, Coast Guard is working with
contractors to enhance the structural integrity of the hulls of the
remaining six NSCs that have not yet been constructed. Second, after
determining that the NSC's deficiencies are not related to the safe
operation of the vessel in the near term, Coast Guard has decided to
address the structural modifications of the hulls of the first two
cutters as part of planned depot-level maintenance after they are
delivered. The Commandant stated that he decided to delay the repairs
to these hulls to prevent further delays in construction and delivery.
Deepwater Assets Behind Schedule as of January 2007:
Offshore Patrol Cutter:
Coast Guard officials have stated that further work on the development
of the OPC is on hold and the Coast Guard did not request funding for
the OPC in fiscal years 2007 or 2008. Delivery of the first OPC has
been delayed by 5 years--from 2010 to 2015.
Fast Response Cutter:
Concerns about the viability of the design of the FRC have delayed the
delivery of the first FRC by at least 2 years. Coast Guard suspended
design work on the FRC in late February 2006 because of design risks.
Because the Coast Guard has suspended design work, Coast Guard
officials now estimate that the first FRC delivery will slip to fiscal
year 2010, at the earliest.
Vertical Unmanned Aerial Vehicle:
According to the Coast Guard, evolving technological developments and
the corresponding amount of funding provided in fiscal year 2006 have
delayed the delivery of the VUAV by 6 years--from 2007 to 2013. As a
result, the Coast Guard has adjusted the VUAV development plan. The
fiscal year 2008 DHS congressional budget justification indicates that
the Coast Guard does not plan to request funding for the VUAV through
fiscal year 2012. Coast Guard originally intended on matching the NSC
and VUAV delivery dates so that the VUAV could be launched from the NSC
to provide surveillance capabilities beyond the cutter's visual range
or sensors. However, with the delay in the VUAV's development schedule,
it no longer aligns with the NSC's initial deployment schedule.
Specifically, Coast Guard officials stated that the VUAV will not be
integrated with the NSC before fiscal year 2013, 6 years later than
planned. Coast Guard officials stated that they are discussing how to
address the operational impacts of having the NSC operate without the
VUAV. In addition, Coast Guard officials explained that since the time
of the original contract award, the Department of Defense has
progressed in developing a different unmanned aerial vehicle--the Fire
Scout--that Coast Guard officials say is more closely aligned with
Coast Guard needs. Coast Guard has issued a contract to an independent
third party to compare the capabilities of its planned VUAV to the Fire
Scout.
Performance and Design Problems Creating Operational Challenges:
In addition to the overall management problems, there have been
problems with the performance and design of Deepwater patrol boats and
its replacement vessel, the FRC, that pose significant operational
challenges for the Coast Guard.
Performance Problems with the Converted 123-foot Patrol Boats:
Between January 2001 and November 2006, numerous events led up to the
failure of the Coast Guard's bridging strategy to convert the legacy
110-foot patrol boats into 123-foot patrol boats. In January 2001, an
independent study found that the 110-foot patrol boats based in south
Florida and Puerto Rico were experiencing severe hull corrosion and
that their structural integrity was deteriorating rapidly.[Footnote 18]
To address these issues, the Coast Guard's original (2002) Deepwater
plan included a strategy to convert all 49 of the 110-foot patrol boats
into 123-foot patrol boats and to strengthen the hulls. Also, the plan
was to provide additional capabilities, such as stern launch and
recovery capabilities and enhanced C4ISR. While Coast Guard originally
planned to convert all 49 of its 110-foot patrol boats to 123-foot
patrol boats, it halted the patrol boat conversion program after 8
boats because of continued deck cracking, hull buckling, and the
inability of these converted patrol boats to meet post-September 11,
2001 mission requirements. The Commandant then decided to remove these
8 converted boats from service on November 30, 2006 because of
operational and safety concerns.
The Coast Guard is taking actions to mitigate the operational impacts
resulting from the removal of the 123-foot patrol boats from service.
Specifically, in recent testimony, the Commandant of the Coast Guard
stated that Coast Guard has taken the following actions:
* multi-crewing certain 110-foot patrol boats with crews from the 123-
foot patrol boats that have been removed from service so that patrol
hours for these vessels can be increased;
* deploying other Coast Guard vessels to assist in missions formerly
performed by the 123-foot patrol boats; and:
* securing permission from the U.S. Navy to continue using 179-foot
cutters on loan from the Navy for an additional 5 years (these were
originally to be returned to the Navy in 2008) to supplement the Coast
Guard's patrol craft.
Design Problems with the Fast Response Cutter:
The FRC--which was intended as a long-term replacement for the legacy
110-foot patrol boats--has experienced design problems that have
operational implications. As we recently reported, the Coast Guard
suspended design work on the FRC due to design risks such as excessive
weight and horsepower requirements.[Footnote 19] Specifically,
beginning in January 2005, Coast Guard engineers raised concerns about
the viability of the FRC design (which involved building the FRC's
hull, decks, and bulkheads out of composite materials rather than
steel). Then, in February 2006, the Coast Guard suspended FRC design
work after an independent design review by third-party consultants
demonstrated, among other things, that the FRC would be far heavier and
less efficient than a typical patrol boat of similar length, in part,
because it would need four engines to meet Coast Guard speed
requirements.
To address the design problems and schedule delays that have occurred
with the FRC, the Coast Guard is proceeding with a "dual-path approach"
for acquiring new patrol boats. The first component of the dual-path
approach is to have the Deepwater systems integrator purchase a
commercial off-the-shelf patrol boat design that can be adapted for
Coast Guard use. The purpose of designing the first class of FRCs based
on an adaptation of a patrol boat already on the market is to expedite
delivery. According to Coast Guard officials, unlike the original
plans, this FRC class is not expected to meet all performance
requirements originally specified, but is intended as a way to field an
FRC more quickly than would otherwise occur and that can, therefore,
serve as an interim replacement for the deteriorating fleet of 110-foot
patrol boats.
The second component of the dual-path approach would be to completely
redesign an FRC to address the problems in the original FRC design
plans. However, due to continuing questions about the feasibility of
its planned composite hull, the Coast Guard has delayed a decision
about its development or acquisition until it receives results from two
studies. First, the Coast Guard is conducting a business case analysis
comparing the use of composite versus steel hulls., as well as a study
by Second, the Coast Guard told us that DHS's Science and Technology
Directorate will be conducting tests on composite hull technology., and
that it will wait to see the results of these tests before making a
decision on the redesigned FRC. Until recently, the Coast Guard
anticipated delivery of the redesigned FRC in 2010. However, the
decision to not request funding for this redesigned FRC in fiscal year
2008, and to await the results of both studies before moving forward,
will likely further delay delivery of the redesigned FRC. In regard to
the suspension of FRC design work, as of our June 2006 report, Coast
Guard officials had not yet determined how changes in the design and
delivery date for the FRC would affect the operations of the overall
system-of-systems approach.
Mr. Chairman, this concludes my testimony. I would be happy to respond
to any questions Members of the Committee may have.
GAO Contacts and Acknowledgments:
For further information about this testimony, please contact Stephen L.
Caldwell, Acting Director, Homeland Security and Justice, (202) 512-
9610, caldwells@gao.gov; or John Hutton, Acting Director, Acquisition
and Sourcing Management, (202) 512-4841, huttonj@gao.gov.
Other individuals making key contributions to this testimony include
Penny Berrier Augustine, Amy Bernstein, Christopher Conrad, Adam
Couvillion, Kathryn Edelman, Melissa Jaynes, Crystal M. Jones, Michele
Mackin, Jessica Nierenberg, Raffaele Roffo, Leslie Sarapu, Karen Sloan,
and Jonathan R. Tumin.
[End of section]
Appendix I: Related GAO Products:
Coast Guard: Preliminary Observations on Deepwater Program Assets and
Management Challenges, GAO-07-446T (Washington, D.C.: February 15,
2007).
Coast Guard: Coast Guard Efforts to Improve Management and Address
Operational Challenges in the Deepwater Program, GAO-07-460T
(Washington, D.C.: February 14, 2007).
Homeland Security: Observations on the Department of Homeland
Security's Acquisition Organization and on the Coast Guard's Deepwater
Program, GAO-07-453T (Washington, D.C.: February 8, 2007).
Coast Guard: Status of Deepwater Fast Response Cutter Design Efforts,
GAO-06-764 (Washington, D.C.: June 23, 2006).
Coast Guard: Changes to Deepwater Plan Appear Sound, and Program
Management Has Improved, but Continued Monitoring is Warranted, GAO-06-
546 (Washington, D.C.: Apr. 28, 2006).
Coast Guard: Progress Being Made on Addressing Deepwater Legacy Asset
Condition Issues and Program Management, but Acquisition Challenges
Remain, GAO-05-757 (Washington, D.C.: Jul. 22, 2005).
Coast Guard: Preliminary Observations on the Condition of Deepwater
Legacy Assets and Acquisition Management Challenges, GAO-05-651T
(Washington, D.C.: Jun. 21, 2005).
Coast Guard: Preliminary Observations on the Condition of Deepwater
Legacy Assets and Acquisition Management Challenges, GAO-05-307T
(Washington, D.C.: Apr. 20, 2005).
Coast Guard: Deepwater Program Acquisition Schedule Update Needed, GAO-
04-695 (Washington, D.C.: Jun. 14, 2004).
Contract Management: Coast Guard's Deepwater Program Needs Increased
Attention to Management and Contractor Oversight, GAO-04-380
(Washington, D.C.: Mar. 9, 2004).
Coast Guard: Actions Needed to Mitigate Deepwater Project Risks, GAO-
01-659T (Washington, D.C.: May 3, 2001).
Coast Guard: Progress Being Made on Deepwater Project, but Risks
Remain, GAO-01-564 (Washington, D.C.: May, 2, 2001):
FOOTNOTES
[1] GAO, Coast Guard: Progress Being Made on Deepwater Project, but
Risks Remain, GAO-01-564 (Washington, D.C.: May 2, 2001); GAO, Contract
Management: Coast Guard's Deepwater Program Needs Increased Attention
to Management and Contractor Oversight, GAO-04-380 (Washington, D.C.:
Mar. 9, 2004).
[2] GAO, Coast Guard: Status of Deepwater Fast Response Cutter Design
Efforts, GAO-06-764 (Washington, D.C.: June 23, 2006).
[3] In addition to these asset classes, Coast Guard plans to procure
surveillance data from another unmanned aerial vehicle, the RQ-4A.
Because this is not to be acquired as a capital investment, we do not
include it among the assets to be acquired or upgraded.
[4] GAO-04-380
[5] C4ISR refers to command, control, communications, computer,
intelligence, surveillance, and reconnaissance.
[6] This management approach of using a systems integrator has been
used on other government programs that require system-of-systems
integration, such as the Army's Future Combat System, a networked
family of weapons and other systems.
[7] GAO, High Risk Series: An Update, GAO-07-310 (Washington, D.C.:
January 2007).
[8] GAO, Coast Guard: Progress Being Made on Addressing Legacy Asset
Condition Issues and Program Management, but Acquisition Challenges
Remain, GAO-05-757 (Washington, D.C.: July 22, 2005).
[9] The program management reports were produced on a monthly basis in
the past; now they are produced on a quarterly basis.
[10] IPTs are focused on the development and fielding of a particular
product (e.g., the NSC) and are organized by domain. Examples of
domains are air, surface, C4ISR, and legacy assets.
[11] Defense Acquisition University, Quick Look Study: United States
Coast Guard Deepwater Program, (Fort Belvoir, VA.) Feb. 5, 2007
[12] An award term contract is a contract in which the contractor is
rewarded for excellent performance with an extension of the contract
period instead of an additional fee.
[13] The award term determination rated total ownership cost as "good."
[14] For a variety of reasons, including the Coast Guard's expanded
homeland security mission, the baseline was increased from $70.97
billion plus 10 percent (fiscal year 2002 dollars) to $304 billion
(fiscal year 2006 dollars).
[15] According to DHS officials, a baseline breach occurs when a cost
or schedule threshold is exceeded or when a performance threshold
cannot be met.
[16] See GAO-04-380.
[17] DHS OIG-07-23.
[18] CSC Advanced Marine, Evaluation of the 110' WPB Class Cutter Fleet
(January 2001).
[19] GAO-06-764.
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts
newly released reports, testimony, and correspondence on its Web site.
To have GAO e-mail you a list of newly posted products every afternoon,
go to www.gao.gov and select "Subscribe to Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office 441 G Street NW, Room LM
Washington, D.C. 20548:
To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202)
512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S.
Government Accountability Office, 441 G Street NW, Room 7125
Washington, D.C. 20548:
Public Affairs:
Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800
U.S. Government Accountability Office, 441 G Street NW, Room 7149
Washington, D.C. 20548: