Information Technology
Management Improvements Needed on the Department of Homeland Security's Next Generation Information Sharing System
Gao ID: GAO-09-40 October 8, 2008
The Department of Homeland Security (DHS) is responsible for coordinating the federal government's homeland security communications with all levels of government. In support of this mission, DHS implemented, and has been enhancing, the Homeland Security Information Network (HSIN). It also has proposed a follow-on system, called Next Generation HSIN (HSIN Next Gen). GAO was asked to determine whether (1) DHS has stopped further improvements on HSIN and if so, the department's rationale for doing so and plans for acquiring its proposed follow-on system HSIN Next Gen and (2) the department is effectively managing the HSIN Next Gen acquisition. To accomplish this, GAO analyzed documentation, interviewed officials, and compared acquisition management processes and practices defined in industry best practices with those planned and underway by DHS.
DHS halted further improvements on the existing HSIN system in September 2007. Since then, the department has continued to operate and maintain the system while a replacement--HSIN Next Gen--is being planned and acquired. DHS decided in large part to pursue this replacement due to the existing system has security and information-sharing limitations that do not meet department and other users' needs, thus impeding the department's ability to effectively perform its mission; and the new system is to be a key part of a departmentwide consolidation effort to, among other things, reduce the number of systems within DHS that share sensitive but unclassified information. DHS has developed an acquisition strategy for HSIN Next Gen, whereby the system is to be implemented in four phases, each providing for an increasing number of users to be transitioned to the system. For example, DHS plans to begin transitioning existing HSIN users beginning in May 2009. Further, in May 2008, DHS issued a task order engaging a contractor to acquire, deploy, operate, and maintain the new system. The total estimated value of the task order's initial year is $19 million; the order also includes 4 option years that if exercised, are estimated to be worth $62 million. DHS intends to continue to use the existing HSIN with the goal of terminating its use in September 2009 when HSIN Next Gen is to be fully completed. DHS estimates it will cost $3.1 million to operate and maintain HSIN between now and its planned September 2009 termination. DHS is in the process of implementing key acquisition management controls for HSIN Next Gen, but has yet to implement the full set of controls essential to effectively managing information technology system projects in a rigorous and disciplined manner. Specifically, it has not fully implemented key process controls in the areas of project and acquisition planning, requirements development and management, and risk management. DHS officials, including the Office of Operations Coordination and Planning's Chief Information Officer, who is responsible for managing the project, attribute the partial implementation of these key processes in large part to the aggressive schedule for acquiring and deploying HSIN Next Gen. The Chief Information Officer also stated the department plans to address these weaknesses by, for example, tasking its contractor to assist in the development and completion of the risk management process area, but had not yet established dates for when all of these activities will be completed. Until these weaknesses are effectively addressed and DHS implements and institutionalizes the full set of acquisition management controls, the project will be at increased risk of operating in an ad hoc and chaotic manner--potentially resulting in increased project costs, delayed schedules, and performance shortfalls.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-09-40, Information Technology: Management Improvements Needed on the Department of Homeland Security's Next Generation Information Sharing System
This is the accessible text file for GAO report number GAO-09-40
entitled 'Information Technology: Management Improvements Needed on the
Department of Homeland Security's Next Generation Information Sharing
System' which was released on October 8, 2008.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to Congressional Requesters:
United States Government Accountability Office:
GAO:
October 2008:
Information Technology:
Management Improvements Needed on the Department of Homeland Security's
Next Generation Information Sharing System:
GAO-09-40:
GAO Highlights:
Highlights of GAO-09-40, a report to congressional requesters.
Why GAO Did This Study:
The Department of Homeland Security (DHS) is responsible for
coordinating the federal government‘s homeland security communications
with all levels of government. In support of this mission, DHS
implemented, and has been enhancing, the Homeland Security Information
Network (HSIN). It also has proposed a follow-on system, called Next
Generation HSIN (HSIN Next Gen). GAO was asked to determine whether (1)
DHS has stopped further improvements on HSIN and if so, the
department‘s rationale for doing so and plans for acquiring its
proposed follow-on system HSIN Next Gen and (2) the department is
effectively managing the HSIN Next Gen acquisition. To accomplish this,
GAO analyzed documentation, interviewed officials, and compared
acquisition management processes and practices defined in industry best
practices with those planned and underway by DHS.
What GAO Found:
DHS halted further improvements on the existing HSIN system in
September 2007. Since then, the department has continued to operate and
maintain the system while a replacement”HSIN Next Gen”is being planned
and acquired. DHS decided in large part to pursue this replacement due
to:
* the existing system has security and information-sharing limitations
that do not meet department and other users‘ needs, thus impeding the
department‘s ability to effectively perform its mission; and:
* the new system is to be a key part of a departmentwide consolidation
effort to, among other things, reduce the number of systems within DHS
that share sensitive but unclassified information.
DHS has developed an acquisition strategy for HSIN Next Gen, whereby
the system is to be implemented in four phases, each providing for an
increasing number of users to be transitioned to the system. For
example, DHS plans to begin transitioning existing HSIN users beginning
in May 2009. Further, in May 2008, DHS issued a task order engaging a
contractor to acquire, deploy, operate, and maintain the new system.
The total estimated value of the task order‘s initial year is $19
million; the order also includes 4 option years that if exercised, are
estimated to be worth $62 million. DHS intends to continue to use the
existing HSIN with the goal of terminating its use in September 2009
when HSIN Next Gen is to be fully completed. DHS estimates it will cost
$3.1 million to operate and maintain HSIN between now and its planned
September 2009 termination.
DHS is in the process of implementing key acquisition management
controls for HSIN Next Gen, but has yet to implement the full set of
controls essential to effectively managing information technology
system projects in a rigorous and disciplined manner. Specifically, it
has not fully implemented key process controls in the areas of:
* project and acquisition planning,
* requirements development and management, and:
* risk management.
DHS officials, including the Office of Operations Coordination and
Planning‘s Chief Information Officer, who is responsible for managing
the project, attribute the partial implementation of these key
processes in large part to the aggressive schedule for acquiring and
deploying HSIN Next Gen. The Chief Information Officer also stated the
department plans to address these weaknesses by, for example, tasking
its contractor to assist in the development and completion of the risk
management process area, but had not yet established dates for when all
of these activities will be completed. Until these weaknesses are
effectively addressed and DHS implements and institutionalizes the full
set of acquisition management controls, the project will be at
increased risk of operating in an ad hoc and chaotic manner”potentially
resulting in increased project costs, delayed schedules, and
performance shortfalls.
What GAO Recommends:
GAO recommends strengthening acquisition management controls before the
department starts to migrate existing users to the new system by, among
other things, staffing the program office appropriately, ensuring all
user requirements are gathered, and identifying key risks surrounding
the project. In written comments on this report, DHS described actions
planned and underway to address GAO recommendations.
To view the full product, including the scope and methodology, click on
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-09-40]. For more
information, contact David A. Powner at (202) 512-9286 or
pownerd@gao.gov.
[End of section]
Contents:
Letter1:
DHS Has Stopped Current HSIN System Improvements and Is in the Process
of Acquiring a Replacement System:
DHS Has Yet to Implement the Management Controls Essential to
Effectively Manage the HSIN Next Gen Acquisition:
Conclusions:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Briefing Slides to Congressional Staff:
Appendix II: Comments from the Department of Homeland Security:
Appendix III: GAO Contact and Staff Acknowledgments:
Abbreviations:
DHS: Department of Homeland Security:
CIO: Chief Information Officer:
HSIN: Homeland Security Information Network:
HSIN: Next Gen: Next Generation HSIN:
IT: information technology:
OPS: Office of Operations Coordination and Planning:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
October 8, 2008:
The Honorable Joseph I. Lieberman:
Chairman:
The Honorable Susan M. Collins:
Ranking Member:
Committee on Homeland Security and Governmental Affairs:
United States Senate:
The Honorable Bennie G. Thompson:
Chairman:
Committee on Homeland Security:
House of Representatives:
The Department of Homeland Security (DHS) is responsible for
coordinating the federal government's homeland security communications
with all levels of government--including state and local. In support of
this mission, the department deployed, and has been making improvements
to, the Homeland Security Information Network (HSIN) as part of its
goal to establish an infrastructure for sharing homeland security
information. In 2005,[Footnote 1] and more recently in January
2007,[Footnote 2] we designated homeland security information sharing
as a high-risk area. Consequently, it is important that federal
networks and associated systems, applications, and data facilitate this
vital information sharing, and do so in a manner that produces
effective information sharing among and between the various levels of
government. This is particularly crucial for DHS's HSIN, which is the
department's primary information technology (IT) system for sharing
terrorism and related information. Recently, DHS proposed a follow-on
system to HSIN, which it refers to as Next Generation HSIN (HSIN Next
Gen).
This report responds to your request that we determine whether (1) DHS
has stopped further improvements on HSIN and if so, the department's
rationale for doing so and plans for acquiring its proposed follow-on
system HSIN Next Gen and (2) the department is effectively managing the
HSIN Next Gen acquisition.
On July 11, 2008, and July 17, 2008, we provided a briefing to staff of
the House Homeland Security Committee and Senate Homeland Security and
Governmental Affairs Committee, respectively. Prior to these staff
briefings (on July 9, 2008), we provided the briefing to responsible
DHS officials, who agreed in large part with our findings, conclusions,
and recommendations. This report transmits (1) the slides that we used
during the briefings and (2) the recommendations that we made to the
Secretary of Homeland Security and the Director, Office of Operations
Coordination and Planning, who is responsible for managing HSIN and
HSIN Next Gen. The full briefing, including our scope and methodology,
is reprinted as appendix I.
DHS Has Stopped Current HSIN System Improvements and Is in the Process
of Acquiring a Replacement System:
In September 2007, the department halted further improvements on the
existing HSIN system. Since then, DHS has continued to operate and
maintain the system while its replacement--HSIN Next Gen--is being
planned and acquired. The department decided to pursue the replacement
for two reasons. First, the existing system has security and
information-sharing limitations that do not meet department and other
users' needs. For example, with regard to security, the current HSIN
does not support role-based access controls[Footnote 3] and two-factor
authentication.[Footnote 4] These limitations hinder the department's
ability to effectively perform its mission.
Second, the replacement system is to be used as a key part of a
departmentwide consolidation effort aimed at reducing the number of
multiple portals or Web-based systems within DHS by consolidating the
systems across the department that are to share sensitive but
unclassified information. In particular, HSIN Next Gen is to provide
secure access to DHS sensitive but unclassified information and
services for all department user communities, including those in the
law enforcement, intelligence, immigration, and emergency and disaster
management communities.
With regard to DHS plans to acquire HSIN Next Gen, the department has
developed an acquisition strategy for the system and plans to have all
users on the new system by September 2009. The system will be
implemented in four phases, each addressing a functional portion of the
requirements and providing for an increasing number of users to be
transitioned to the system. Specifically, during the first phase of
implementation, the department plans to bring on board up to 20,000 new
users from critical infrastructure sectors such as agriculture and
food, and transportation systems. In addition, during the second phase
(called Initial Operational Capability) and third phase (called
Maturing Operational Capability), DHS plans to transition over 26,000
users that currently use the existing HSIN system; this transition of
existing HSIN users is to begin in May 2009. To help carry out the
strategy, DHS issued a task order in May 2008 engaging a contractor to
acquire, deploy, operate, and maintain the new system. The total
estimated value of the base year of this arrangement is $19 million,
and the total estimated value, if each of the four options is
exercised, is $62 million.
DHS intends to continue to use the existing HSIN with the goal of
terminating its use in September 2009 when HSIN Next Gen is to be fully
implemented. DHS estimates it will cost $3.13 million to operate and
maintain HSIN between now and its planned September 2009 termination.
DHS Has Yet to Implement the Management Controls Essential to
Effectively Manage the HSIN Next Gen Acquisition:
As we have previously reported,[Footnote 5] the success of critical
projects such as HSIN depends on developing and implementing a full set
of acquisition management controls to effectively manage the project.
While DHS is in the process of implementing key acquisition management
controls for HSIN Next Gen, it has yet to implement the full set of
controls essential to managing HSIN Next Gen in a disciplined and
rigorous manner. Specifically, it has not implemented key process
controls in the areas of:
* project and acquisition planning, which includes key processes, such
as developing a program office and identifying staff roles and
responsibilities;
* requirements development and management, which involves key
processes, such as gathering, analyzing, and validating user
requirements; and:
* risk management, which includes key processes, such as identifying
and analyzing risks and assigning responsibilities for managing risks.
With regard to project and acquisition planning, DHS has established a
program office for HSIN Next Gen, including filling the position of
project manager. However, it has not adequately staffed the HSIN Next
Gen program office and identified staff roles and responsibilities.
In addition, in the area of requirements development and management,
the department has gathered and analyzed requirements from critical
infrastructure sector users. However, it has not gathered requirements
from all other HSIN users and developed a change control process for
managing change to requirements.
Further, regarding risk management, DHS has begun to develop a risk
management plan that defines staff roles and responsibilities. However,
it has yet to identify all key risks surrounding the project and
develop risk mitigation plans and completion milestones.
DHS officials, including the Office of Operations Coordination and
Planning's (OPS) Chief Information Officer (CIO), who is responsible
for managing the project, attribute the partial implementation of these
key processes in large part to the aggressive schedule for acquiring
and deploying HSIN Next Gen. In our view, engaging a contractor and
commencing work before implementing mature controls is not a recipe for
success. Specifically, our research and experience at federal agencies
have shown that the probability of success is low using this approach.
The OPS CIO stated the department plans to address these weaknesses by,
for example, tasking its contractor to assist in the development and
completion of the risk management process area, but had not yet
established dates for when all of these activities will be completed.
Consequently, until these weaknesses are effectively addressed and DHS
implements and institutionalizes the full set of acquisition management
controls, the project will be at increased risk of operating in an ad
hoc and chaotic manner--potentially resulting in increased project
costs, delayed schedules, and performance shortfalls.
Conclusions:
DHS has been challenged in its ability to efficiently and effectively
manage the department's existing primary information-sharing system. In
particular, although DHS has invested upwards of $70 million on the
system, it still does not fully meet user needs and as a result, has
not been fully utilized. DHS intends to address this performance
shortfall by, among other things, acquiring a replacement system. A key
challenge for DHS in this effort will be ensuring it develops an
information-sharing system that effectively addresses its users' needs
and in the process, does not waste or unwisely invest critical
department resources.
To its credit, DHS has initiated some important steps in establishing
sound and capable acquisition controls, but much remains to be
accomplished before DHS management efforts can be considered effective
and thereby minimize the risks associated with HSIN Next Gen delivering
promised capabilities and benefits on time and within budget.
Investing money given the current state of management controls puts the
project at risk. Given what is at stake, it is extremely important that
DHS direct its attention to these management issues, and mitigate the
associated risks as soon as possible.
Recommendations for Executive Action:
To minimize risks to the HSIN Next Gen project, we are making six
recommendations to the Secretary of Homeland Security aimed at
strengthening management of the project. We recommend that the
Secretary direct the Director, Office of Operations Coordination and
Planning to strengthen program management controls by:
* staffing the program office appropriately;
* identifying staff roles and responsibilities;
* ensuring all requirements are gathered, analyzed, and validated;
* developing and implementing a requirements change control process;
and:
* ensuring effective risk management by identifying all key risks
surrounding the project and developing risk mitigation plans and
completion milestones.
We also recommend that these controls be implemented before the
department starts to migrate users to HSIN Next Gen's Initial
Operational Capability.
Agency Comments and Our Evaluation:
In written comments on a draft of this report, which were in a letter
signed by DHS's Director of Operations Coordination and Planning and
are reprinted in appendix II, the department described actions planned
and underway to address our recommendations. These actions are
consistent with those described by DHS in response to our July 9, 2008,
briefing to the department in which it largely agreed with our
findings, conclusions, and recommendations.
We are sending copies of this report to interested congressional
committees and the Secretary of Homeland Security. We will also make
copies available to others on request. In addition, the report will be
available at no charge on the GAO Web site at [hyperlink,
http://www.gao.gov].
Should you or your staffs have any questions concerning this report,
please contact me at 202-512-9286 or by e-mail at pownerd@gao.gov.
Contact points for our Offices of Congressional Relations and Public
Affairs may be found on the last page of this report. GAO staff who
made key contributions to this report are listed in appendix III.
Signed by:
David A. Powner:
Director, Information Technology Management Issues:
[End of section]
Appendix I: Briefing Slides to Congressional Staff:
Information Technology: Management Improvements Needed on the
Department of Homeland Security's Next Generation Information Sharing
System:
Briefing to the Staffs of the Senate Committee on Homeland Security and
Governmental Affairs:
July 17, 2008:
House Committee on Homeland Security:
July 11, 2008:
Table of Contents:
Introduction:
Objectives, Scope, and Methodology:
Results in Brief:
Background:
Results:
* HSIN Is Currently Operational but Further Improvements Have Been
Halted;
* Acquisition Management Controls Needed;
Conclusions:
Recommendations:
Agency Comments and Our Evaluation:
Attachment I: Scope and Methodology:
Introduction:
The Department of Homeland Security (DHS) is responsible for
coordinating the federal government's homeland security communications
with all levels of government-including state and local. In support of
this mission, the department implemented, and has been enhancing, the
Homeland Security Information Network (HSIN) as part of its goal to
establish an infrastructure for sharing homeland security
information.[Footnote 6] Recently, DHS proposed a follow-on system to
HSIN, which it refers to as Next Generation HSIN (HSIN Next Gen).
In 2005,[Footnote 7] and more recently in January 2007,[Footnote 8] we
designated homeland security information sharing as a high-risk area.
Consequently, it is important that federal networks and associated
systems, applications, and data facilitate this vital information
sharing, and do so in a manner that produces effective information
sharing among and between the various levels of government. This is
particularly crucial for DHS's HSIN, which is the department's primary
information technology (IT) system for sharing terrorism and related
information.
Objectives, Scope, and Methodology:
As agreed, our objectives were to determine whether:
* DHS has stopped further improvements on HSIN and if so, the
department's rationale for doing so and plans for acquiring its
proposed follow-on system called HSIN Next Gen system, and
* the department is effectively managing the HSIN Next Gen acquisition.
For our first objective, we analyzed documentation and interviewed DHS
officials from the office responsible for managing HSIN and HSIN Next
Gen, the Office of Operations Coordination and Planning (OPS), to
assess efforts planned and underway to implement HSIN system
improvements and acquire HSIN Next Gen.
For our second objective, we compared processes and practices defined
in the Software Engineering Institute's Capability Maturity Model®
Integration for Acquisition (CMMI- ACQ)[Footnote 9] and in our prior
work analyzing best practices in industry and government[Footnote 10]
with those planned and underway by the department to determine the
extent of implementation. In judging implementation, we used the
following criteria: the processes were (1) fully implemented if all of
the related guidance was addressed; (2) partially implemented if some,
but not all, of the related guidance was addressed; and (3) not
implemented if none of the related guidance was addressed.
Details of our scope and methodology are provided in attachment I. We
conducted this performance audit from January 2008 to June 2008, in
accordance with generally accepted government auditing standards. Those
standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe that
the evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives.
Results In Brief:
Accountability Integrity Reliability DHS halted further improvements on
the existing HSIN system in September 2007. Since then, the department
has continued to operate and maintain the system while a replacement-
called HSIN Next Gen-is being planned and acquired. DHS decided to
pursue this replacement for two reasons.
* First, the existing system has security and information sharing
limitations that do not meet department and other users' needs, thus
impeding the department's ability to effectively perform its mission.
* Second, the replacement system is to be used as a key part of a
departmentwide consolidation effort to reduce the number of duplicative
DHS Web-based systems.
DHS has developed an acquisition strategy for the system and plans to
have all users on the new system by September 2009. DHS intends to
continue to use the existing HSIN with the goal of retiring it once
HSIN Next Gen has been completed. DHS estimates it will cost $3.13
million to operate and maintain HSIN between now and retirement.
DHS is in the process of implementing key acquisition management
controls for HSIN Next Gen. For example, DHS has established a program
office for HSIN Next Gen, including filling the position of project
manager. In addition, DHS has begun to develop a risk management plan
that defines staff roles and responsibilities. However, DHS has yet to
implement the full set of controls essential to effectively managing IT
system projects in a rigorous and disciplined manner. Specifically, it
has not fully implemented key process controls in the areas of:
* project and acquisition planning,
* requirements development and management, and:
* risk management;
DHS officials, including the OPS Chief Information Officer (CIO), who
is responsible for managing the project, attribute the partial
implementation of these key processes in large part to the aggressive
schedule for acquiring and deploying HSIN Next Gen. DHS has activities
planned and underway to address missing controls, but has not
established dates for when all of these activities will be completed.
Until DHS has implemented these controls, there is increased risk of
the project operating in an ad hoc and chaotic manner-potentially
resulting in increased project costs, delayed schedules, and
performance shortfalls. Accordingly, we are making recommendations to
the Secretary of Homeland Security to (1) strengthen management
controls, including project and acquisition planning, requirements
development and management, and risk management; and (2) ensure that
these controls be implemented before users are transitioned to HSIN
Next Gen Initial Operational Capability.
In orally commenting on a draft of this briefing, DHS officials stated
that they agreed with our findings and recommendations and described
actions they have initiated to implement our recommendations. They also
generally agreed with our conclusions. However, DHS officials stated
that the risk raised in our conclusions was mitigated by their IT
experience. While experience is important, key process controls, such
as rigorous and disciplined requirements and risk management, are also
essential to IT project success.
DHS is the lead department involved in securing our nation's homeland.
Its mission includes, among other things, leading the unified national
effort to secure the United States, preventing and deterring terrorist
attacks, and protecting against and responding to threats and hazards
to the nation.
As part of its mission and as required by the Homeland Security Act of
2002,[Footnote 11] the department is also responsible for coordinating
efforts across all levels of government and throughout the nation,
including with federal, state, tribal, local, and private sector
homeland security resources. This includes coordinating the federal
government's networks and other communications systems with state and
local governments.
In 2004, DHS developed and implemented HSIN as the department's primary
IT system for sharing terrorism and related information with federal,
state, and local agencies, among others. Specifically, this Web-based
communication system is to provide a secure and trusted national IT
system for sensitive but unclassified information sharing and
collaboration among federal, state, local, tribal, territorial, private
sector, and international partners engaged in preventing, protecting
from, responding to, and recovering from all threats, hazards, and
incidents within DHS's authority.
HSIN offers both real-time chat and instant messaging capability, as
well as a document library that contains reports from multiple federal,
state, and local sources. Available through the system are suspicious
incident and pre-incident information and analysis of terrorist
threats, tactics, and weapons. Each community of interest has Web pages
that are tailored for the community and contain general and community-
specific news articles, links, and contact information.
HSIN is to support a number of homeland security-related mission areas
that cover thousands of users across the United States. These mission
areas include over 35 user groups, commonly referred to as communities
of interest, including:
* emergency management,
* law enforcement,
* counterterrorism,
* individual states, and:
* private sector communities.
Other DHS component organizations, such as the Office of Infrastructure
Protection, the Coast Guard, and Federal Emergency Management Agency,
use HSIN as a tool to further their respective missions and therefore
have assisted in the development, operations and maintenance, and
enhancement of HSIN. For example, according to the Office of
Infrastructure Protection, it works with the critical infrastructure
sectors-that is, groups of similar private and government entities that
operate and maintain systems and assets, whether physical or virtual,
so vital to the nation that their incapacity or destruction would have
a debilitating impact on national security, national economic security,
national public health or safety, or any combination of those
matters[Footnote 12]-to gather user requirements and develop business
processes in order to integrate HSIN into the critical sectors'
information-sharing environment.
The Office of Operations Coordination and Planning (OPS) CIO is
responsible for ensuring that HSIN supports the needs of the department
and its partners. This includes managing HSIN operations and
maintenance, making necessary enhancements to the current system, and
developing and acquiring HSIN Next Gen. The OPS CIO reports directly to
the OPS Director who in turn reports directly to the DHS Secretary and
Deputy Secretary.
Through fiscal year 2007, the department reports it has expended about
$70 million on HSIN, and for fiscal year 2008, the department had
budgeted about $21 million for operations, maintenance, and
enhancement.
In April 2007,[Footnote 13] we reported that when coordinating efforts
between HSIN and other state and local information-sharing initiatives,
DHS did not fully adhere to key practices aimed at enhancing
information sharing, collaboration, and avoiding duplication. For
example, in developing the system, the department did not work with two
key state and local initiatives, which are major parts of the Regional
Information Sharing System program, to fully develop joint strategies
to meet mutual needs.
In addition, it did not develop compatible policies, procedures, and
other means to operate across organizational boundaries. DHS's limited
use of these practices was attributable to a number of factors,
including the department's expediting its schedule to deploy
information-sharing capabilities after the events of September 11,
2001, and in doing so not developing a comprehensive inventory of key
state and local information- sharing initiatives.
Prior GAO Reviews Have Identified Opportunities for Improvement:
As a result, we found there was increased risk that, among other
things, effective information sharing is not occurring. Additionally,
the department risked duplication of state and local capabilities. We
recommended, among other things, that DHS:
* identify and develop a comprehensive inventory of state and local
initiatives;
* assess whether there are opportunities for HSIN to improve
information sharing and avoid duplication of effort; and:
* where there are opportunities, implement effective coordination and
collaboration practices.
In response, DHS largely agreed with our recommendations and initiated
actions to implement them. Examples include the following:
* In October 2007 and in February 2008, the HSIN Advisory Council-a
HSIN user group composed of representatives from state, tribal, and
local governments and the private sector-met to discuss HSIN
information-sharing activities and provided strategic-level
recommendations to the OPS Director.
* The HSIN Mission Coordinating Committee-a user group composed of
representatives from DHS's components (e.g., the Office of
Infrastructure Protection, the Coast Guard, and the Federal Emergency
Management Agency)-has met five times over the past year to address
their respective users' requirements for HSIN.
In July 2007,[Footnote 14] we reported on challenges the department
faced when using HSIN to share information with critical infrastructure
sectors. Examples included:
* DHS officials responsible for leading the national effort to reduce
critical infrastructure risk stated that although they encouraged
critical sector entities to use HSIN, the system did not provide the
capabilities that were promised, including providing the level of
security expected by certain sectors.
* An internal DHS review of HSIN determined that the department had not
clearly defined the purpose and scope of the system, and that the
system had been developed without sufficient planning and project
management.
Results: Objective 1:
HSIN Is Currently Operational but Further Improvements Have Been
Halted:
DHS Has Stopped Current HSIN System Improvements and Is in the Process
of Acquiring a Replacement System:
The department halted further HSIN improvements in September 2007 but
it continues to operate and maintain the system while its replacement-
HSIN Next Gen-is being planned and acquired.
DHS decided to pursue a replacement system based on two reasons. First,
the current system has security and information-sharing limitations
that do not meet its users' needs and thus impedes the department's
ability to effectively perform its mission. Second, the new system is
to be used as part of a departmentwide effort-referred to as the portal
consolidation program-to consolidate multiple portals or Web-based
systems and improve sensitive but unclassified information-sharing
capabilities within the department.
DHS has developed a HSIN Next Gen acquisition strategy and as part of
the strategy, issued a May 2008 task order engaging a contractor to
develop the system. DHS plans to have all users on the new system by
September 2009. In the interim, DHS plans to continue to operate and
maintain HSIN as the new system is acquired and deployed and users are
transitioned to it. Once user transition is complete, the department
intends to retire HSIN.
HSIN Improvements Halted Due to System Limitations:
In September 2007, DHS executives, including the Undersecretary for
Management, Chief Information Officer, Director of Operations
Coordination and Planning, and key system user representatives (e.g.,
Office of Infrastructure Protection), met to discuss HSIN operations.
Key representatives said HSIN was not meeting their needs due to system
security and information-sharing limitations.
System security limitations cited included the system's inability to
support
* role-based access controls, which limit system functions based on a
user's designated role, and:
* two-factor authentication, which is a way of verifying someone's
identity by using two of the following: something the user knows
(password), something the user has (badge), or something unique to the
user (fingerprint).
Information-sharing limitations included the system's inability to:
* enable users to access HSIN and systems outside of DHS (such as the
state and local law enforcement's Regional Information Sharing System)
using single sign capability (i.e., requiring only one user name and
password);
* enable users to send alerts and notifications and receive alerts
through e-mail or cell phones;
* support online meetings and presentations; and:
* upload new users into the system in bulk.
HSIN Improvements Halted:
According to user representatives, these limitations were hindering
their ability to perform the mission of the department. For example,
representatives from the Office of Infrastructure Protection (which is
part of the National Protection and Programs Directorate) stated that
without the security controls, private-sector officials from the
critical infrastructure sectors were reluctant to share with DHS
sensitive information about sector infrastructure that is essential to
protecting the homeland, thus inhibiting the department's ability to
adequately build trusted relationships with sector officials. In
response, the Office of Infrastructure Protection initiated an effort
to obtain requirements from HSIN critical infrastructure sectors users,
augmenting the requirements the department had for the existing system.
Consequently, the executives at the September 2007 meeting (referenced
above) decided the best way to implement the missing security and
information-sharing capabilities was via a new system, rather than by
enhancing the existing system. According to these officials, they based
their decision largely on the view that the existing system could not
be enhanced to provide these capabilities in a cost-effective manner.
These officials also decided at this time to halt any further HSIN
enhancements until the new system (HSIN Next Gen) was implemented, at
which point they planned to retire the current HSIN system.
HSIN Next Gen's Goal Is to Also Eliminate Duplication:
In addition, in October 2007 the Under Secretary for Management issued
a memorandum detailing how HSIN Next Gen is to be used as an integral
part of the department's portal consolidation program. According to the
memorandum, the current DHS Web environment consists of more than 100
Web-based systems, which are mostly duplicative in capabilities. HSIN
Next Gen is part of a departmentwide program aimed at reducing the
number of duplicative Web-based systems within DHS by consolidating the
systems across the department that are used to share sensitive but
unclassified information, and by replacing portal technologies that
limit its information-sharing capabilities.
In particular, according to the memorandum, HSIN Next Gen is to provide
secure access to DHS information and services for all DHS user
communities, including those in the law enforcement, intelligence,
immigration, and emergency and disaster management communities.
Homeland Security Information Network Next Generation:
As part of the system acquisition and implementation strategy, DHS
plans to continue operating and maintaining HSIN until September 2009.
The department estimates the cost to operate and maintain the current
system through September 2009 will be $3.13 million. DHS reports it
will have spent a total of $91 million on HSIN by the end of fiscal
year 2008.
In parallel, the department plans to begin developing and implementing
HSIN Next Gen in four phases; the phases-along with a brief description
of their functional purpose-are as follows.
* Phase one, referred to as Spiral 1, is to establish an operational
platform for the HSIN critical sector users' requirements.
* The second phase, Initial Operational Capability, is to (1) deliver
requirements currently supported by HSIN, as well as provide additional
security controls and (2) begin migrating users of the current system
to HSIN Next Gen.
* Phase three, Maturing Operational Capability, is to migrate all
remaining users of the current system to HSIN Next Gen.
* The fourth phase, called the Final Operational Capability, is to
provide for improved content management; better information discovery
and delivery; and improved alert, notification, and public announcement
functions.
Each phase is intended to, among other things, address a functional
portion of the requirements and provide for an increasing number of
users to be transitioned to the system. In addition, DHS plans to draw
upon the existing HSIN system and capabilities, rather than developing
a complete infrastructure replacement. Specifically, where possible, it
plans to re-use existing HSIN hardware and software. The department
plans to use the contractor (discussed in detail below) to help them do
this. However, it has yet to set a date for when this is to be
completed.
Further, in terms of users, during the first phase of implementation,
the department plans to bring on board up to 20,000 critical sector
users. In addition, over the second and third phases, DHS plans to
transition over 26,000 users that currently use the existing HSIN
system.
In May 2008, the department issued a task order to a
contractor[Footnote 15] to acquire, deploy, operate, and maintain the
new system. The total estimated value of the base year of this
arrangement is $19 million, and the total estimated value, if each of
the four options is exercised, is $62 million.
Accountability Integrity Reliability Results: Objective 1
Homeland Security Information Network Next Generation Each of the HSIN
Next Gen phases, the timing of their implementation, the percentage of
users to be transitioned, and the date the contractor was issued the
task order are depicted in figure 1.
Figure 1: HSIN Next Generation Phases and Associated Milestones:
This figure is a chart showing HSIN Next Generation phases and
associated milestones.
[See PDF for image]
Source: GAO analysis of DHS data.
[End of figure]
Key dates are:
* May 2008 - issued task order to contractor for HSIN Next Gen.
* August 2008 - implement Spiral 1 with the goal of supporting up to
20,000 critical sectors users.
* May 2009 - complete Initial Operational Capability with 13,000
current users scheduled to transition.
* September 2009 - implement Maturing Operational Capability with the
transition of the remaining 13,000 users.
* November 2009 - complete Final Operational Capability by delivering
new functionality to users.
Results: Objective 2:
Acquisition Management Controls Needed:
DHS Has Yet to Implement the Management Controls Essential to
Effectively Manage the HSIN Next Gen Acquisition:
DHS is in the process of implementing key acquisition management
controls, but it has yet to implement the full set of controls
essential to managing HSIN Next Gen in a disciplined and rigorous
manner. Specifically, it has not implemented key process controls in
the areas of:
* project and acquisition planning,
* requirements development and management, and:
* risk management.
Until DHS has fully implemented these controls, it increases the risk
of the project operating in an ad hoc and chaotic manner-potentially
resulting in increased project costs, delayed schedules, and
performance shortfalls.
As we have previously reported,"[Footnote 16] the success of critical
projects such as HSIN depends on developing and implementing a full set
of acquisition management controls to effectively manage the project.
Leading organizations, such as the Software Engineering Institute and
the Chief Information Officer's Council, and our research and
experience at federal agencies have shown that such process controls
are significant in successful system acquisition and development
projects. In particular, the CMMI-ACQ[Footnote 17] has defined a suite
of key acquisition process control areas that are necessary to manage
system acquisitions in a rigorous and disciplined fashion. These
process areas include:
* project and acquisition planning,
* requirements development and management, and:
* risk management.
The following table provides a list of key processes within each
process area.
Table 1: Key Processes for Effectively Managing IT Projects Process
area Key processes:
Process area: Project and acquisition planning;
Key processes: * developing a program office;
* obtaining appropriate staff, and ensuring that staff have the skills
and knowledge needed to manage the project;
* identifying staff roles and responsibilities;
* identifying key deliverables and milestones for the project and
acquisition.
Process area: Requirements development and management;
Key processes: * gathering user requirements;
* analyzing and validating user requirements;
* managing any changes to the requirements in collaboration with
stakeholders.
Process area: Risk management;
* identifying and analyzing risks;
* assigning responsibilities for managing risks;
* developing mitigation plans and completion milestones for identified
risks.
Source: GAO summary of leading practices, including practices
identified by the Software Engineering Institute, the Chief Information
Officer's Council, and the Office of Management and Budget.
[End of table]
DHS is currently implementing key acquisition controls for the HSIN
Next Gen but it has yet to implement the full set of controls essential
to effectively managing the project.
Table 2 provides a summary of the status of the project relative to
each of the key process areas.
Table 2: Summary of the Status of HSIN Next Gen Acquisition Management
Controls as of June 2008:
Process area: Project and acquisition planning;
Key processes: * Establish a program office;
Status: Key process area implemented.
Process area: Project and acquisition planning;
Key processes: * Obtain appropriate staff;
Status: Key process area not implemented.
Process area: Project and acquisition planning;
Key processes: * Identify staff roles and responsibilities;
Status: Key process area not implemented.
Process area: Project and acquisition planning;
Key processes: * Identify key deliverables and milestones for project
and acquisition;
Status: Key process area implemented.
Process area: Requirement development and management;
Key processes: * Gather user information;
Status: Key process area partially implemented.
Process area: Requirement development and management;
Key processes: * Analyze and validate user requirements;
Status: Key process area partially implemented.
Process area: Requirement development and management;
Key processes: * Manage change to requirements;
Status: Key process area not implemented.
Process area: Risk management;
Key processes: * Identify and analyze risks;
Status: Key process area partially implemented.
Process area: Risk management;
Key processes: Assign responsibilities for managing risks;
Status: Key process area implemented.
Process area: Risk management;
Key processes: * Develop mitigation plans and completion 0 milestones
for identified risks;
Status: Key process area not implemented.
Source: GAO analysis of agency data.
[End of table]
With regard to project and acquisition planning, DHS has implemented
two of the four key processes. Specifically, it has:
* established a program office for HSIN Next Gen, including filling the
position of the project manager, and developed an April 2008 mission
needs statement for HSIN Next Gen; and:
* developed a project schedule, identifying key deliverables and
milestones, for the HSIN Next Gen project and acquisition.
However, having already issued a task order to the contractor for HSIN
Next Gen, the department has not filled two positions that it
identified it needed to appropriately staff the program office.
According to DHS officials, including the OPS CIO, they are in the
process of hiring two full-time employees by the end of fiscal year
2008. In addition, the department is in the process of identifying
staff roles and responsibilities, but has yet to finalize the effort.
Until the program office is adequately staffed and roles and
responsibilities have been defined, DHS will be challenged in its
ability to manage the HSIN Next Gen acquisition and project, including
overseeing the contractor tasked to develop the system.
With regard to requirements development and management, DHS has
partially implemented two of the three key processes, and has yet to
implement the remaining process. Specifically, for Spiral 1, DHS has:
* gathered user requirements from the critical infrastructure sector
users, and:
* analyzed these requirements through the OPS CIO, HSIN stakeholders,
and the HSIN Mission Coordinating Committee.
The department used these user requirements, the existing HSIN
requirements, and pending change requests for the current system to
create the Functional Requirements Document dated March 2008. This
document defines and outlines the known user requirements for HSIN Next
Gen. The Functional Requirements Document was included as part of the
HSIN Next Gen solicitation documentation (i.e., request for proposals)
used to award the contractor in May 2008. However, while DHS has
gathered and analyzed user requirements from critical infrastructure
sector users, it has not gathered requirements from all other HSIN
users. Moreover, DHS has yet to validate the requirements.
In addition, DHS has not developed a change control process for
managing change to requirements in collaboration with stakeholders,
including developing criteria for evaluation and acceptance of
requirements.
DHS has efforts planned and underway to address these weaknesses. For
example, the department is in the process of establishing an initiative
(called the HSIN Mission Integration Effort) to improve its ability to
gather user requirements by having a formal outreach process to
communicate with HSIN users. According to the OPS CIO, this is part of
the department's effort to improve its capability to gather
requirements from HSIN users. In addition, DHS plans to validate
requirements for each HSIN Next Gen phase before they are completed,
which is to be by August 2008 for Spiral 1. Further, DHS plans to
establish a change control board to manage HSIN Next Generation
requirements by September 2008.
While these are steps in the right direction, until they are completed
and DHS has fully gathered, analyzed, and validated all user
requirements and implemented effective change management, it faces the
risk that HSIN Next Gen will not meet user and mission needs, which is
a problem it faced with the existing HSIN and why it is currently
working on a replacement system.
With regard to risk management, DHS has implemented one of the key
processes and part of another, and has yet to implement the remaining
process. Specifically, DHS's HSIN Next Gen Acquisition Plan (dated
February 2008):
* assigns responsibility for managing the risks; and:
* partially identifies a list of primary risks both internal and
external to the department, such as:
- insufficient funding to execute future development,
- insufficient government staff to execute the project, and:
- changes in HSIN user requirements that could negatively impact cost
and schedule.
In addition to these efforts, DHS has begun to develop a risk
management plan that defines staff roles and responsibilities,
including procedures for identifying and tracking risks and assessing
the probability and impact of individual risks.
However, the department has yet to develop risk mitigation plans and
completion milestones, which includes recommended courses of action for
each critical risk. The department intends to develop such plans, which
are to provide risk mitigation strategies with alternatives and
mitigation project plans, including activities, schedules, and resource
requirements. However, the department has yet to establish a date for
when this is to be completed.
In addition, the list of primary risks prepared did not include all key
risks. For example, HSIN Next Gen's schedule, which has been identified
by the OPS CIO as being aggressive, has not been identified as a risk.
Until DHS fully implements and institutionalizes risk management, there
is increased probability that unanticipated risks may occur that could
have a critical impact on HSIN Next Gen's cost, schedule, and
performance.
The OPS CIO stated that the reason for the partial implementation of
these key processes is attributable in large part to an aggressive
schedule for acquiring and deploying HSIN Next Gen.
In our view, engaging a contractor and commencing work before
implementing mature controls is not a recipe for success. Specifically,
our research and experience at federal agencies have shown that the
probability of success is low using this approach. A case in fact is
the existing HSIN system which was acquired and deployed via an overly
aggressive schedule with the result being it did not meet all users'
needs, necessitating in part the need for the HSIN Next Gen
replacement.
The OPS CIO stated the department plans to address these weaknesses by,
for example, tasking its contractor to assist in the development and
completion of the risk management process area. However, until the
processes have been implemented and institutionalized, and the full set
of acquisition management controls are implemented, the project will be
at increased risk of operating in an ad hoc and chaotic manner-
potentially resulting in increased project costs, delayed schedules,
and performance shortfalls.
Conclusions:
DHS has been challenged in its ability to efficiently and effectively
manage the department's existing primary information-sharing system. In
particular, although DHS has invested upwards of $70 million on the
system, it still does not fully meet user needs and as a result, has
not been fully utilized. DHS intends to address this performance
shortfall by, among other things, acquiring a replacement system. A key
challenge for DHS in this effort will be ensuring it develops an
information-sharing system that effectively addresses its users' needs
and in the process, does not waste or unwisely invest critical
department resources.
To its credit, DHS has initiated some important steps in establishing
sound and capable acquisition controls, but much remains to be
accomplished before DHS management efforts can be considered effective
and thereby minimize the risks associated with HSIN Next Gen delivering
promised capabilities and benefits on time and within budget.
Investing money given the current state of management controls puts the
project at risk. Given what is at stake, it is extremely important that
DHS direct its attention to these management issues, and mitigate the
associated risks as soon as possible.
Recommendations:
To minimize risks to the HSIN Next Gen project, we are making
recommendations to the Secretary of Homeland Security aimed at
strengthening management of the project. We recommend that the
Secretary direct the Director, Office of Operations Coordination and
Planning to strengthen program management controls by:
* staffing the program office appropriately;
* identifying staff roles and responsibilities;
* ensuring all requirements are gathered, analyzed, and validated;
* developing and implementing a requirements change control process;
and:
* ensuring effective risk management by identifying all key risks
surrounding the project and developing risk mitigation plans and
completion milestones. We also recommend that these controls be
implemented before the department starts to migrate users to HSIN Next
Gen's Initial Operational Capability.
Agency Comments and Our Evaluation:
In oral comments on a draft of this briefing, DHS officials agreed with
our findings and recommendations and described actions that they have
underway to address our recommendations. In particular, the OPS CIO
stated that they have engaged a contractor to help them organize the
HSIN program office, which includes identifying staff roles and
responsibilities.
DHS officials also generally agreed with our conclusions. However, they
took exception with the statement in our conclusions that investing
money given the current state of management controls puts the project
at risk. According to DHS officials, including the OPS CIO, they
believe the risks to the project are mitigated by the IT experience of
the HSIN staff, including the knowledge it has gained over the past 4
years in operating, maintaining, and enhancing HSIN. While we agree
that IT experience is important, our research and experience at federal
agencies have shown that, in addition to people, key processes, such as
rigorous and disciplined requirements and risk management, are
essential to IT project success.
DHS officials also provided technical comments, which we have
incorporated into the briefing as appropriate.
Attachment I:
Scope and Methodology:
To address our first objective, we:
* assessed department efforts to stop HSIN system improvements by
analyzing agency documentation and then discussing with agency
officials via interviews. For example, we:
- reviewed executive-level correspondence, memos, strategies, and
related documentation describing the department's plans for the current
system, including ceasing system improvements and the reasons for doing
this;
- reviewed cost estimates to determine the planned costs of the
operations and maintenance, and discussed the costs of enhancing the
current system with OPS officials; and:
- interviewed OPS officials to clarify our understanding of the
documentation and the department's rationale for choosing to develop
the follow-on system.
* analyzed DHS plans for the proposed follow-on system. Specifically,
we:
- evaluated the HSIN Next Gen acquisition plan, requirements document,
request for proposals, and related documentation to determine what
activities were planned and when they were to be accomplished; and:
- reviewed independent cost estimates to determine the planned costs
for the development, operations, and maintenance of the new system.
To address our second objective, we assessed the extent to which the
department was managing the acquisition of HSIN Next Gen based on the
processes defined in the Software Engineering Institute's Capability
Maturity Model® Integration for Acquisition (CMMI-ACQ).[Footnote 18] In
particular, we analyzed the department's efforts in acquisition
planning, requirements development and management, and risk management.
In doing so, we:
* assessed HSIN Next Gen acquisition and project planning documentation
and interviewed OPS officials to obtain key milestones;
* reviewed the HSIN Next Gen system requirements and interviewed
officials from OPS and the Office of Infrastructure Protection, and
representatives from HSIN governance bodies in order to understand how
requirements were gathered and managed; and:
* evaluated the HSIN Next Gen risks and risk management plan, and
interviewed OPS officials to understand how risks were identified and
are to be managed.
In making these judgments, we used the following criteria: processes
were:
* fully implemented if all of the related guidance was addressed;
* partially implemented if some, but not all, of the related guidance
was addressed; and:
* not implemented if none of the related guidance was addressed.
We conducted our work at DHS headquarters offices in Washington, D.C.,
and the Office of Infrastructure Protection in Arlington, Virginia. We
conducted this performance audit from January 2008 to June 2008, in
accordance with generally accepted government auditing standards. Those
standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe that
the evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives.
[End of section]
Appendix II: Comments from the Department of Homeland Security:
Operations Coordination and Planning:
U.S. Department of Homeland Security:
Washington, DC 20528:
Homeland Security:
September 19, 2008:
David A. Powner:
Director, Information Technology Management Issues:
U.S. Government Accountability Office:
Dear Mr. Powner:
The Office of Operations Coordination and Planning (OPS) appreciates
the opportunity to comment on the Government Accountability Office
(GAO) report, "Information Technology: Management Improvements Needed
on the Department of Homeland Security's Next Generation Information
Sharing System." OPS in coordination with the DHS Office of the Chief
Information Officer (OCIO) are working to establish a secure and
trusted information sharing and collaboration environment for Sensitive
but Unclassified (SBU) information for use by DHS and non-DHS partners
engaged in preventing, protecting from, responding to, and recovering
from all threats, hazards, and incidents within the authority of DHS.
The decision to upgrade the Homeland Security Information Network
(HSIN) technology platform meets the growing needs of HSIN users. The
current technology platform does not provide the necessary capabilities
required to provide the necessary trust and interoperability. Upgrading
HSIN technology addresses current user needs and provides a robust and
trusted foundation adjustable over time to meet arising end user
information sharing requirements. The project to upgrade the HSIN
technology platform is called HSIN NextGen. It is important to
understand that HSIN Next Generation (NextGen) is primarily a software
upgrade to the current HSIN technology platform rather than an
acquisition of a replacement system. The HSIN NextGen project, along
with operations and maintenance of the current HSIN platform, is being
done within the existing HSIN investment profile and does not require
additional money.
The HSIN NextGen project will follow a phased implementation approach
based on industry best practices. This approach allows the Department
to effectively and efficiently move all current HSIN users onto an
enhanced platform, constituting initial operating capability (IOC), by
October, 2009. The current HSIN technology platform will remain
operational throughout the phased implementation to ensure continued
service for all users. Phase 1 of the HSIN NextGen project, driven by
the HSIN Critical Sectors (HSIN-CS) priority requirements, was achieved
on August 25, 2008.
The following responses address the recommendations within the report:
Recommendation: Staffing the program office appropriately:
OPS has advertised for a HSIN Program Requirements Manager and is
working with the DHS Office of the Chief Human Capital Officer to fill
this position within 60 days. Two GS-I5 leadership and technical
positions have been advertised and we anticipate having personnel
onboard within 60 to 90 days. The HSIN Program Manager is assisted by
an experienced team of professional contracting firms. The roles filled
by the contractors include cost, earned value management, schedule,
performance, architecture, change process, and other support functions
that are typical of a program management office.
The OPS CIO plans to fill ten additional billets beginning in Fiscal
Year 2009 (FY09), pending Departmental approval. These billets will
support architecture, security, privacy, and other functions. These
specialists will ensure HSIN addresses statutory and interoperability
requirements with partner tools. These resources will provide more
robust requirements management and process control.
The HSIN program is not currently staffed to support simultaneous,
significant outreach initiatives to our partners. To meet this demand,
DHS plans to increase overall OPS CIO Division staffing in FY09 and
FYI0, subject to Congressional approval of existing budget requests.
The augmented HSIN Outreach Team will build on our diverse partner
community relationships to facilitate integrating HSIN into the partner
communities' day-to-day operations that map to the DHS mission
(Awareness, Prevent, Protect, Respond, and Recover). These new funds
will be dedicated entirely to mission integration and focused on our
Federal, State, local, and private sector partners.
Recommendation: Identifying staff roles and responsibilities:
In April 2008, the OPS CIO initiated an effort by an outside team to
analyze the current OPS CIO Division, which includes HSIN Program
Management. This effort provided recommendations for transforming the
OPS CIO Division and enable DHS to more effectively meet its complex,
integrated mission requirements, both within DHS and across the larger
homeland security community. The team conducted extensive research and
performed over thirty-five interviews with OPS CIO staff, OPS
stakeholders, and DHS-wide leaders. Then, the team applied proven
analytical methods to form strategic and tactical views of
organization, examining the CIO functions and capabilities it requires
for the future. In addition, the team conducted a detailed, bottom-up
assessment of existing capabilities and supporting activities. Four key
areas were analyzed:
* Process: Develop an understanding of the existing and future
processes including functions, tasks and activities needed to perform
the mission of the OPS CIO Division;
* People: Develop an understanding of the existing and future staff and
expertise needed to support the mission and processes of the OPS CIO
Division;
* Technology: Develop an understanding of the existing and future
technologies including applications, data and technology standards
needed to perform the mission of the OPS CIO Division;
* Physical Infrastructure: Develop an understanding of the existing,
future facilities and working environment needed to perform the mission
of the OPS CIO Division;
The recommendation for the future state of the OPS CIO Division
includes a detailed description of the organization model, including
the processes, people, technology and infrastructure required, to
implement the recommended organization.
Recommendation: Ensuring all requirements are gathered, analyzed, and
validated:
User requirements were the primary driver of the decision to upgrade
the HSIN environment. These are not the only driver of the process.
Initial phases will not meet every user requirement. The prioritization
of certain user requirements is necessary. The Department must set
timeline milestones in addition to identifying user requirements. This
ensures that the awarded task order is completed in a timely manner,
while initially ensuring that the Department meets the most urgent
system requirements. Phases I through 3 of the HSIN NextGen project
address the user needs to provide a secure and trusted information
sharing and collaboration platform.
The Department determined that the HSIN NextGen project must first
address the security and trust requirements identified through HSIN
Community of Interest (COl) owners' input. Based upon input from many
of the HSIN Community of Interest (COI) owners, the Department
determined that the HSIN NextGen project must first address the
security and trust requirements identified by all COIs. State, local
and tribal first responders have reached out to the Department by
requesting changes and sending requirements through the HSIN Helpdesk
and/ or through the HSIN Mission Advocates. These change requests and
requirements were recorded in the HSIN Change Request Tracking System
(CHARTS). Many change requests were made by HSIN-CS and State, local,
or tribal users. All change requests and requirements were examined and
where possible incorporated into the HSIN NextGen Functional
Requirements Document (FRD). The operational user requirements, which
include policy, business process, and governance, will be gathered
through identified DHS business leads and the HSIN Outreach Team.
Using a best practices approach, the HSIN Mission Integration Effort
will gather user requirements and establish on-the-ground relationships
through HSIN representatives (Mission Advocates). The HSIN Outreach
Team is in the initial phase of an important engagement with the
Commonwealth of Virginia, among others. Working closely with
operational personnel in Virginia, the Department will further the
understanding of the Commonwealth's information sharing needs and aid
to support the Department partners' homeland security mission. In the
future, the Department will engage with more partners to further
examine the needs of our State, local, tribal and Federal partners.
The Department further determined that the most time sensitive and
pressing needs of the existing HSIN COIs were those of the HSIN
Critical Sectors (HSIN-CS). HSIN-CS provides a common environment for
the critical infrastructure/key resource (CI/KR) stakeholder partners.
NPPD has gathered and validated necessary user requirements for this
phase from their stakeholders over a two year period. The critical
infrastructure/key resource community is a well governed and defined
community. The National Protection and Programs Directorate, Office of
Infrastructure Protection (NPPD/IP), has determined that implementing
the HSIN-CS priority requirements at the earliest moment was an
absolute necessity to avoid mission degradation and loss of the
voluntary participation of the I8 infrastructure sectors.
Recommendation: Developing and implementing a requirements change
control process:
There must be one overarching requirements process that brings
business, functional and technical architecture products into
alignment. This is a complex undertaking, given the necessity for
interoperability, as well as the depth, breadth, and volunteer nature
of potential HSIN user groups. The phased approach to migrating
communities onto the upgraded HSIN environment mitigates many risks.
The HSIN NextGen project will make the HSIN environment responsive and
flexible to user requirements through a single, well-designed
requirements process. The diversity of customer requirements and the
need for a more standards-based platform, responsive to changing user
requirements, is a driver for the HSIN NextGen project. The use of the
maturing governance structure will ensure customer needs are met. The
Information Sharing Governance Board (ISGB), along with the Information
Sharing Coordinating Council (ISCC) and other mission coordination
bodies, will work with the HSIN Program Manager to make certain that
the requirements are captured, reviewed, and, if appropriate,
implemented into the HSIN program change management process. DHS will
adapt its tactics and timeline as needed using the phased deployment
strategy and a segment architecture approach.
Future phases of HSIN NextGen will create improved versions based upon
continued input from HSIN users. Currently, and moving forward in
future phases, improvements to HSIN have been and will continue to be
driven by the input of Federal, State, local, private sector, and
tribal users with each phase improving upon the last. We anticipate
that once HSIN users have a chance to understand and use the upgraded
HSIN capabilities, they will suggest additional improvements or
enhancements. These requests will translate into requirements to be
submitted into the HSIN change management process and then incorporated
into subsequent phases of the HSIN NextGen project.
To ensure success, a governance structure was initiated that integrated
a larger segment architecture framework and the phased implementation
approach. This structure continues to evolve to ensure that all
stakeholders are involved and end user requirements are accurately
captured, vetted, managed, and implemented. Key program activities and
decisions are guided by DHS policies, processes, and procedures for
consistency, repeatability, and compliance. The HSIN governance
structure allows HSIN program resources to engage with mission leaders
from all segments to determine whether HSIN is an appropriate solution
for that target segment. If so, the governance structure allows us to
identify mission requirements of that segment community and determine
whether HSIN can meet those requirements in a timely, cost effective
manner. The Department will move forward with the implementation of
additional capabilities for new or existing mission areas based on
whether HSIN can meet those requirements in a timely, cost effective
manner. Once that determination is made, additional capabilities will
be designed, developed, and validated with participation from
stakeholders.
Recommendation: Ensuring effective risk management by identifying all
key risks surrounding the project and developing risk mitigation plans
and completion milestones:
The HSIN Program Team exercises a proactive approach to risk. OPS
identifies and mitigate risks before they manifest as schedule
slippage, cost overruns, and unsatisfied requirements. Our risk
management approach incorporates a continuing, closed-loop review and
analysis of technical, programmatic, cost, and schedule risks
throughout the entire program lifecycle. OPS uses proven management
toolsets for detailed documentation and tracking of all identified
risks/problems from point of discovery through risk resolution (e.g.
web portals to facilitate user entry, tracking, reporting and
maintenance of a centralized repository for all deliverables and
product information). Our risk management approach monitors overall
program health to ensure goals are being met. The Risk Management Plan
consists of the following key areas:
* Risk Identification: Project managers are responsible for proactively
identifying and documenting potential problems, issues, risks and
dependencies at every program level;
* Risk Reporting: Project managers conduct regular issue/risk review
meetings to ensure risks are reported appropriately and in a timely
manner. Prior to the internal program review (IPR), probability-of-
occurrence and consequence-of-failure analyses are conducted to
quantify and rank all identified risks;
* Risk Mitigation Strategy: In addition to routine risk reporting,
project manager are responsible for mitigation strategies for every
risk that is identified. Impacted areas and/or systems, resources and
skills required, as well as potential level of effort to provide
resolution, are captured in the strategy;
* Risk Escalation: Risks ranked high and medium may require special
attention and/or action plans for mitigation, thus the overall Risk
Management plans include an escalation path based on risk category and
impacted area;
I look forward to working with you to ensure that user communities that
depend upon HSIN are able to accomplish their missions. If I may be of
further assistance, please contact my office.
Sincerely,
Signed by:
Roger T. Rufe, Jr.:
[End of section]
Appendix III: GAO Contact and Staff Acknowledgments:
GAO Contact:
David A. Powner, (202) 512-9286 or pownerd@gao.gov:
Staff Acknowledgments:
In addition to the contact named above, the following staff also made
key contributions to this report: Gary Mountjoy, Assistant Director;
Barbara Collier; Kaelin Kuhn; Rebecca LaPaze; and Lori Martinez.
[End of section]
Footnotes:
[1] GAO, High-Risk Series: An Update, GAO-05-207 (Washington, D.C.:
January 2005).
[2] GAO, High-Risk Series: An Update, GAO-07-310 (Washington, D.C.:
January 2007).
[3] Role-based access controls limit system functions based on a user's
designated role.
[4] Two-factor authentication is a way of verifying someone's identity
by using two of the following: something the user knows (password),
something the user has (badge), or something unique to the user
(fingerprint).
[5] For example, GAO, Information Technology: Management Improvements
Needed on Immigration and Customs Enforcement's Infrastructure
Modernization Program, GAO-05-805 (Washington, D.C.: Sept. 7, 2005) and
Census Bureau: Important Activities for Improving Management of Key
2010 Decennial Acquisitions Remain to be Done, GAO-06-444T (Washington,
D.C.: Mar. 1, 2006).
[6] The Homeland Security Act of 2002 directed DHS to establish
communications to share homeland security information with federal
agencies, state and local governments, and other specified groups.
[7] GAO, High-Risk Series: An Update, GAO-05-207 (Washington, D.C.:
January 2005).
[8] GAO, High-Risk Series: An Update, GAO-07-310 (Washington, D.C.:
January 2007).
[9] Carnegie Mellon Software Engineering Institute, Capability Maturity
Model® Integration for Acquisition (CMMI-ACQ), Version 1.2 (November
2007).
[10] For example, GAO, Information Technology: Management Improvements
Needed on Immigration and Customs Enforcement's Infrastructure
Modernization Program, GAO-05-805 (Washington, D.C.: Sept. 7, 2005) and
Census Bureau: Important Activities for Improving Management of Key
2010 Decennial Acquisitions Remain to be Done, GAO-06-444T (Washington,
D.C.: Mar. 1, 2006).
[11] Homeland Security Act of 2002, Pub. L. No. 107-296 (Nov. 25,
2002).
[12] The critical infrastructure sectors include agriculture and food;
banking and finance; chemical; commercial facilities; commercial
nuclear reactors, materials, and waste; communications; critical
manufacturing; dams; defense industrial base; drinking water and water
treatment systems; emergency services; energy; government facilities;
information technology; national monuments and icons; postal and
shipping; public health and health care; and transportation systems.
[13] GAO, Information Technology: Numerous Federal Networks Used to
Support Homeland Security Need to Be Better Coordinated with Key State
and Local Information-Sharing Initiatives, GAO-07-455 (Washington,
D.C.: April 16, 2007).
[14] GAO, Critical Infrastructure Protection: Sector Plans and Sector
Councils Continue to Evolve, GAO-07-706R (Washington, D.C.: July 10,
2007).
[15] The department issued a cost-plus-fixed-fee task order under the
Enterprise Acquisition Gateway for Leading Edge Solutions (EAGLE).
EAGLE is a DHS multiple award indefinite-delivery/indefinite-quantity
contract, under which DHS conducted a competition for the HSIN Next Gen
task order.
[16] For example, GAO-05-805 and GAO-06-444T.
[17] Carnegie Mellon Software Engineering Institute, Capability
Maturity Model Integration for Acquisition (CMMI-ACQ), Version 1.2
(November 2007).
[18] Carnegie Mellon Software Engineering Institute, Capability
Maturity Model® Integration for Acquisition (CMMI-ACQ), Version 1.2
(November 2007).