Rejection of Low Bid for Failure To Provide Timely Bid Bond]

Gao ID: B-198873 June 16, 1980

A firm protested it's rejection as a low bidder for failure to provide a timely bid bond. GAO found that the objection to the bond requirement should have been raised before bid opening, thus the bidder's objection was untimely. The protest was not considered for this reason.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.