Air Traffic System

Pilot Program To Contract Out Maintenance at Selected Facilities Gao ID: RCED-87-104BR April 17, 1987

In response to a congressional request, GAO reviewed the Federal Aviation Administration's (FAA) proposed test program to contract for maintenance at selected air traffic control facilities to: (1) provide information on test design and status; (2) evaluate the test's potential for air traffic safety and efficiency; (3) determine if the program would adequately test contractor performance; and (4) assess FAA ability to estimate and control test costs.

GAO found that: (1) the test would last 5 years, would cost $130 million, and would involve three of the nine FAA regions; (2) FAA would provide guidance and orientation during a projected 9-month transition from FAA to contractor personnel; (3) FAA suspended its planning, since Congress denied its 1987 budget request for initial funding for the test, but would complete planning if 1988 funding were granted; (4) although FAA designed the test program to maintain current safety and efficiency levels, the program might accelerate attrition in its maintenance work force; (5) FAA would use the first 2 to 3 years to test contractors' abilities to perform maintenance functions independently; (6) FAA designed the test to allow contractors use of FAA training materials and support throughout the test; (7) since FAA has not completed an up-to-date cost estimate, it would develop a better projection if planning were resumed; (8) FAA intends to be a silent bidder to preclude the possibility of potential contractors' underbidding or low buy-in; and (9) FAA intends to require full contractor liability for equipment and aircraft-related accidents.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.