Air Traffic Control

Status of FAA's Modernization Effort Gao ID: RCED-91-132FS April 15, 1991

Pursuant to a congressional request, GAO provided information on the status of the Federal Aviation Administration's (FAA) overall air traffic control modernization program and selected individual major systems.

GAO found that FAA: (1) experienced increases in the overall cost of the modernization effort, and estimated that it would require about $31 billion in facilities and equipment appropriations through 2000, a $4 billion increase over its April 1990 estimate; (2) completed 30 modernization projects through 1990, accounting for 2 percent of the $31 billion, and had 203 active and planned projects in its Capital Investment Plan; (3) continued to experience cost increases ranging from $0.2 million to $504 million and schedule delays ranging from 8 to 23 months, for 12 major systems; (4) completed only one of six projects it anticipated completing in 1990; (5) redefined its major acquisitions to include those procurements exceeding $50 million, resulting in an increase in the number of major acquisitions from 11 in 1990 to 44 in 1991; and (6) made several efforts to increase its compliance with federal requirements to reevaluate major projects at critical points in the procurement process.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.