Los Angeles Red Line

Financing Decisions Could Affect This and Other Los Angeles County Rail Capital Projects Gao ID: RCED-96-147 May 14, 1996

The federal government has agreed to pick up the tab for about half of the $5.5 billion in final design and construction costs for the Red Line subway project in Los Angeles. The 23.4-mile Red Line project consists of three segments, which are in varying states of completion. This report reviews (1) the project's estimated cost and (2) the Los Angeles County Metropolitan Transportation Authority's financing plans. GAO also provides information on the Federal Transit Administration's oversight of the project's quality control and quality assurance practices.

GAO found that: (1) as of February 1996, the project's estimated total cost was $5.9 billion; (2) project costs have increased due to construction problems, new construction requirements, and project enhancements; (3) additional design problems and pending lawsuits may further increase project costs; (4) the Authority plans to use $3.1 billion in federal funds and $2.8 billion in state and local funds to finance the project, but it may not realize about $380 million of the total; (5) the Authority may have to reduce the funding or scope of other rail projects, defer or cancel planned projects, or extend the project's construction schedule to cover current or future funding shortfalls, but extending the project's construction schedule could also increase costs; (6) in response to FTA actions, the Authority is reorganizing its quality control and assurance programs and increasing program staff; and (7) FTA has increased the number of on-site oversight personnel to improve project monitoring.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.