Transportation Infrastructure

Central Artery/Tunnel Project Faces Financial Uncertainties Gao ID: RCED-96-131 May 10, 1996

At a cost of more than $1 billion per mile, the Central Artery/Tunnel project--an Interstate Highway System project in Boston, Massachusetts--ranks as one of the largest, most complex, and expensive highway construction projects ever undertaken. About $4.7 billion in federal and state money has been obligated so far, but this amount is less than half of the more than $10 billion that will likely be needed to complete the project. To date, about 86 percent of the funding for the Central Artery/Tunnel project has come from federal sources. This report evaluates (1) the estimated total cost of the Central Artery/Tunnel project and (2) the plans of the Commonwealth of Massachusetts for financing it.

GAO found that: (1) in January 1996, Massachusetts estimated that the project's total cost was $7.8 billion, but that estimate did not include $1 billion in previously identified costs or account for the effects of inflation; (2) project costs could total more than $10.4 billion if Massachusetts does not successfully contain construction costs well below historic levels; (3) Massachusetts has directed two state agencies to contribute $200 million toward project costs, but federal and state funding may not be sufficient to complete the project by 2004; (4) federal funding may be limited by the lack of provisions giving the state access to unobligated balances from previous years; and (5) Massachusetts has identified several funding options, but shortfalls exist under all of the options because of its plans to accelerate construction and begin numerous projects within a short period of time.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.