Air Traffic Control

Status of FAA's Implementation of the Display System Replacement Project Gao ID: T-RCED-00-19 October 11, 1999

This testimony provides information on the status of the Federal Aviation Administration's (FAA) implementation of the Display System Replacement project. This system replaces the controllers' workstations and other equipment in the nation's en route centers and is one of FAA's major projects under the air traffic control modernization program. GAO's testimony is based on prior reports and testimonies.

GAO noted that: (1) FAA's revised approach to modernization--acquiring new systems by using a more incremental approach as opposed to its prior practice of tackling large, complex projects all at once--appears to be paying dividends; (2) the DSR project, which evolved from FAA's restructuring of the Advanced Automation System, reflects this incremental approach; (3) with DSR, FAA has concentrated on replacing the controllers' workstations and other supporting equipment and plans to add new functions and capabilities later; (4) with the former project, FAA had attempted to do both--replace old equipment and add new functions concurrently; (5) another aspect of the new modernization approach involves working actively with the aviation community to make decisions more collaboratively, as opposed to unilaterally making decisions about air traffic control modernization; (6) FAA has achieved a more successful implementation of DSR than other aspects of its modernization program; (7) FAA developed DSR within its estimated cost and schedule milestones; (8) nationwide, DSR has been delivered to all of the facilities that were scheduled to receive it, and FAA is in various stages of testing and using it; (9) one of these facilities (Boston) is expected to begin using DSR in a limited capacity in late October and should begin full operations in January 2000; (10) one lesson learned from the earlier implementation of DSR at en route facilities is that the transition of new equipment, coupled with other factors, had an impact on FAA's delivery of air traffic services; (11) FAA has an opportunity to replicate its success with DSR on other modernization projects that are underway and with future efforts; (12) however, it will be very important for FAA to continue to incorporate the factors contributing to DSR's success, namely: (a) using an incremental approach to modernization; (b) collaborating with internal users and with external users; and (c) implementing recommendations to improve the modernization program; (13) FAA has begun to take actions to develop a complete systems architecture to guide modernization, improve its investment management approach, develop mature software acquisition capabilities, and change its organizational culture; and (14) as FAA embarks on full implementation of DSR and other planned equipment upgrades to improve safety and efficiency, it will be important for the agency to continue to monitor efficiency measures to determine if the changes that have been implemented are having the intended effect of minimizing impacts on service.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.