Global Positioning System
Significant Challenges in Sustaining and Upgrading Widely Used Capabilities
Gao ID: GAO-09-325 April 30, 2009
The Global Positioning System (GPS), which provides positioning, navigation, and timing data to users worldwide, has become essential to U.S. national security and a key tool in an expanding array of public service and commercial applications at home and abroad. The United States provides GPS data free of charge. The Air Force, which is responsible for GPS acquisition, is in the process of modernizing GPS. In light of the importance of GPS, the modernization effort, and international efforts to develop new systems, GAO was asked to undertake a broad review of GPS. Specifically, GAO assessed progress in (1) acquiring GPS satellites, (2) acquiring the ground control and user equipment necessary to leverage GPS satellite capabilities, and evaluated (3) coordination among federal agencies and other organizations to ensure GPS missions can be accomplished. To carry out this assessment, GAO's efforts included reviewing and analyzing program documentation, conducting its own analysis of Air Force satellite data, and interviewing key military and civilian officials.
It is uncertain whether the Air Force will be able to acquire new satellites in time to maintain current GPS service without interruption. If not, some military operations and some civilian users could be adversely affected. In recent years, the Air Force has struggled to successfully build GPS satellites within cost and schedule goals; it encountered significant technical problems that still threaten its delivery schedule; and it struggled with a different contractor. As a result, the current IIF satellite program has overrun its original cost estimate by about $870 million and the launch of its first satellite has been delayed to November 2009--almost 3 years late. Further, while the Air Force is structuring the new GPS IIIA program to prevent repeating mistakes made on the IIF program, the Air Force is aiming to deploy the next generation of GPS sa this schedule is optimistic, given the program's late start, past trends in space acquisitions, and challenges facing the new contracto tellites 3 years faster than the IIF satellites. GAO's analysis found that r. Of particular concern is leadership for GPS acquisition, as GAO and other studies have found the lack of a single point of authority for space programs and frequent turnover in program managers have hampered requirements setting, funding stability, and resource allocation. If the Air Force does not meet its schedule goals for development of GPS IIIA satellites, there will be an increased likelihood that in 2010, as old satellites begin to fail, the overall GPS constellation will fall below the number of satellites required to provide the level of GPS service that the U.S. government commits to. Such a gap in capability could have wide-ranging impacts on all GPS users, though there are measures the Air Force and others can take to plan for and minimize these impacts. In addition to risks facing the acquisition of new GPS satellites, the Air Force has not been fully successful in synchronizing the acquisition and development of the next generation of GPS satellites with the ground control and user equipment, thereby delaying the ability of military users to fully utilize new GPS satellite capabilities. Diffuse leadership has been a contributing factor, given that there is no single authority responsible for synchronizing all procurements and fielding related to GPS, and funding has been diverted from ground programs to pay for problems in the space segment. DOD and others involved in ensuring GPS can serve communities beyond the military have taken prudent steps to manage requirements and coordinate among the many organizations involved with GPS. However, GAO identified challenges to ensuring civilian requirements and ensuring GPS compatibility with other new, potentially competing global space-based positioning, navigation, and timing systems.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-09-325, Global Positioning System: Significant Challenges in Sustaining and Upgrading Widely Used Capabilities
This is the accessible text file for GAO report number GAO-09-325
entitled 'Global Positioning System: Significant Challenges in
Sustaining and Upgrading Widely Used Capabilities' which was released
on May 7, 2009.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to the Subcommittee on National Security and Foreign Affairs,
Committee on Oversight and Government Reform, House of Representatives:
United States Government Accountability Office:
GAO:
April 2009:
Global Positioning System:
Significant Challenges in Sustaining and Upgrading Widely Used
Capabilities:
GAO-09-325:
GAO Highlights:
Highlights of GAO-09-325, a report to the Subcommittee on National
Security and Foreign Affairs, Committee on Oversight and Government
Reform, House of Representatives.
Why GAO Did This Study:
The Global Positioning System (GPS), which provides positioning,
navigation, and timing data to users worldwide, has become essential to
U.S. national security and a key tool in an expanding array of public
service and commercial applications at home and abroad. The United
States provides GPS data free of charge. The Air Force, which is
responsible for GPS acquisition, is in the process of modernizing GPS.
In light of the importance of GPS, the modernization effort, and
international efforts to develop new systems, GAO was asked to
undertake a broad review of GPS. Specifically, GAO assessed progress in
(1) acquiring GPS satellites, (2) acquiring the ground control and user
equipment necessary to leverage GPS satellite capabilities, and
evaluated (3) coordination among federal agencies and other
organizations to ensure GPS missions can be accomplished. To carry out
this assessment, GAO‘s efforts included reviewing and analyzing program
documentation, conducting its own analysis of Air Force satellite data,
and interviewing key military and civilian officials.
What GAO Found:
It is uncertain whether the Air Force will be able to acquire new
satellites in time to maintain current GPS service without
interruption. If not, some military operations and some civilian users
could be adversely affected.
* In recent years, the Air Force has struggled to successfully build
GPS satellites within cost and schedule goals; it encountered
significant technical problems that still threaten its delivery
schedule; and it struggled with a different contractor. As a result,
the current IIF satellite program has overrun its original cost
estimate by about $870 million and the launch of its first satellite
has been delayed to November 2009”almost 3 years late.
* Further, while the Air Force is structuring the new GPS IIIA program
to prevent mistakes made on the IIF program, the Air Force is aiming to
deploy the next generation of GPS satellites 3 years faster than the
IIF satellites. GAO‘s analysis found that this schedule is optimistic,
given the program‘s late start, past trends in space acquisitions, and
challenges facing the new contractor. Of particular concern is
leadership for GPS acquisition, as GAO and other studies have found the
lack of a single point of authority for space programs and frequent
turnover in program managers have hampered requirements setting,
funding stability, and resource allocation.
* If the Air Force does not meet its schedule goals for development of
GPS IIIA satellites, there will be an increased likelihood that in
2010, as old satellites begin to fail, the overall GPS constellation
will fall below the number of satellites required to provide the level
of GPS service that the U.S. government commits to. Such a gap in
capability could have wide-ranging impacts on all GPS users, though
there are measures the Air Force and others can take to plan for and
minimize these impacts.
In addition to risks facing the acquisition of new GPS satellites, the
Air Force has not been fully successful in synchronizing the
acquisition and development of the next generation of GPS satellites
with the ground control and user equipment, thereby delaying the
ability of military users to fully utilize new GPS satellite
capabilities. Diffuse leadership has been a contributing factor, given
that there is no single authority responsible for synchronizing all
procurements and fielding related to GPS, and funding has been diverted
from ground programs to pay for problems in the space segment.
DOD and others involved in ensuring GPS can serve communities beyond
the military have taken prudent steps to manage requirements and
coordinate among the many organizations involved with GPS. However, GAO
identified challenges to ensuring civilian requirements and ensuring
GPS compatibility with other new, potentially competing global space-
based positioning, navigation, and timing systems.
What GAO Recommends:
GAO‘s recommendations include that the Secretary of Defense appoint a
single authority to oversee development of GPS space, ground control,
and user equipment assets, to ensure they are synchronized, well
executed, and potential disruptions are minimized. DOD concurred with
our recommendations.
View [hyperlink, http://www.gao.gov/products/GAO-09-325] or key
components. For more information, contact Cristina Chaplain at (202)
512-4841 or chaplainc@gao.gov.
[End of section]
Contents:
Letter:
Results In Brief:
Background:
Air Force Faces Significant Challenges in Acquiring GPS Satellites:
New Satellite Capabilities Will Not Be Leveraged Because of Delayed
Delivery of Ground and User Equipment Capabilities:
Prudent Steps Taken so GPS Can Meet Broader Needs but Challenges Exist
in Coordinating Requirements and Ensuring Compatibility:
Conclusions:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Scope and Methodology:
Appendix II: International Global Satellite Navigation Systems:
Appendix III: Cooperation Between U.S. and Foreign Entities:
Appendix IV: Comments from the Department of Defense:
Appendix V: GAO Contacts and Staff Acknowledgments:
Related GAO Products:
Tables:
Table 1: GPS Satellite and Ground Control Segment Modernization:
Table 2: Key Differences in Program Framework for GPS IIF and GPS III:
Table 3: Delays in Delivery of GPS Operational Functionality:
Table 4: U.S. Cooperation with Foreign Entities on Satellite
Navigation:
Table 5: Non-U.S. Global Navigation Satellite Systems Currently in
Development:
Figures:
Figure 1: GPS Operational System:
Figure 2: National Space-Based PNT Organization Structure:
Figure 3: Schedule Development from Start to Launch for Space Programs
(in Months):
Figure 4: Probability of Maintaining a Constellation of at Least 24 GPS
Satellites Based on Reliability Data and Launch Schedule as of March
2009:
Figure 5: Probability of Maintaining a Constellation of at Least 18,
21, and 24 GPS Satellites Based on Reliability Data as of March 2009
and a 2-Year GPS III Launch Delay:
Figure 6: Gap in the Ability of the Military to Use the Modernized
Signal:
Figure 7: Responsibilities Among the Military Services for Procurement
of GPS User Equipment:
Figure 8: Interagency Process for Submitting and Validating GPS
Requirements:
Abbreviations:
AEP: Architecture Evolution Plan:
DASS: Distress Alerting Satellite System:
DOD: Department of Defense:
GNSS: Global Navigation Satellite Systems:
GPS: Global Positioning System:
IFOR: Interagency Forum for Operational Requirements:
JCIDS: Joint Capabilities Integration and Development System:
L2C: second civil signal:
L5: third civil signal:
M-code: Military Code:
NASA: National Aeronautics and Space Administration:
OCS: Operational Control Segment:
OCX: Next Generation Control Segment:
OSD: Office of the Secretary of Defense:
PDOP: position dilution of precision:
PNT: Positioning, Navigation, and Timing:
SLR: Satellite Laser Ranging:
TSPR: Total System Performance Responsibility:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
April 30, 2009:
The Honorable John Tierney:
Chairman:
The Honorable Jeff Flake:
Ranking Member:
Subcommittee on National Security and Foreign Affairs:
Committee on Oversight and Government Reform:
House of Representatives:
The Global Positioning System (GPS)--a space-based satellite system
that provides positioning, navigation, and timing data to users
worldwide--has become essential to U.S. national security and a key
component in economic growth, transportation safety, homeland security,
and critical national infrastructure in the United States and abroad.
GPS is integrated into nearly every facet of U.S. military operations,
and the number of civil users is increasing. Other countries are now
developing their own independent global navigation satellite systems
that could offer capabilities that are comparable, if not superior to
GPS.
The U.S. government, which plans to invest more than $5.8 billion from
2009 through 2013 in the GPS space and ground control segments
currently under development, provides GPS service free of charge. The
Department of Defense (DOD) develops and operates GPS, and an
interdepartmental committee--co-chaired by DOD and the Department of
Transportation--manages the U.S. space-based positioning, navigation,
and timing infrastructure, which includes GPS. DOD also provides most
of the funding for GPS.
The Air Force, which is responsible for GPS acquisition, is in the
process of modernizing GPS to enhance its performance, accuracy, and
integrity. The modernization effort includes GPS IIF and IIIA, two
satellite acquisition programs currently underway that are to provide
new space-based capabilities and replenish the satellite constellation;
the ground control segment hardware and software; and user equipment
for processing modernized GPS capabilities.
In light of the global economic and national security importance of
GPS, the ongoing GPS modernization effort, and the international
efforts to develop new systems, you asked us to undertake a broad
review of the program and efforts to replenish and upgrade capability.
Specifically, we assessed progress in (1) acquiring GPS satellites, (2)
acquiring the ground control and user equipment necessary to leverage
GPS satellite capabilities, and (3) coordinating among federal agencies
and other organizations to ensure broader GPS missions can be
accomplished.
To assess the acquisition of satellite, ground control, and user
equipment, we interviewed Office of the Secretary of Defense (OSD) and
DOD officials from offices that manage and oversee the GPS program. We
also reviewed and analyzed program plans and documentation related to
cost, schedule, requirements, program direction, and satellite
constellation sustainment, and compared programmatic data to GAO's
criteria compiled over the last 12 years for best practices in system
development.[Footnote 1] We also conducted our own analysis, based on
data provided by the Air Force, to assess the implications of potential
schedule delays we identified in our assessment of the satellite
acquisition. To assess coordination among federal agencies and the
broader GPS community, we interviewed OSD and DOD officials from
offices that manage and oversee the GPS program, officials from the
military services, officials from the Department of Transportation and
other civil departments and agencies, and officials at the U.S.
Department of State and at various European space organizations. We
also analyzed how civil departments and agencies coordinate with DOD on
GPS civil requirements, and how the U.S. government coordinates with
foreign countries. Additional information on our scope and methodology
is in appendix I. We conducted this performance audit from October 2007
to April 2009 in accordance with generally accepted government auditing
standards. Those standards require that we plan and perform the audit
to obtain sufficient, appropriate evidence to provide a reasonable
basis for our findings and conclusions based on our audit objectives.
We believe that the evidence obtained provides a reasonable basis for
our findings and conclusions based on our audit objectives.
Results In Brief:
It is uncertain whether the Air Force will be able to acquire new
satellites in time to maintain current GPS service without
interruption. If not, some military operations and some civilian users
could be adversely affected.
* Under the IIF program, the Air Force had difficulty in successfully
building GPS satellites within cost and schedule goals; it encountered
significant technical problems which still threaten its delivery
schedule; and it faced challenges with a different contractor for the
IIF program. These problems were compounded by an acquisition strategy
that relaxed oversight and quality inspections as well as multiple
contractor mergers and moves, and the addition of new requirements late
in the development cycle. As a result, the IIF program has overrun its
original cost estimate of $729 million by about $870 million and the
launch of the first IIF satellite has been delayed to November 2009--
almost 3 years late.
* Further, while the Air Force is structuring the new GPS IIIA program
to prevent mistakes made on the IIF program, the Air Force is aiming to
deploy the GPS IIIA satellites 3 years faster than the IIF satellites.
We believe the IIIA schedule is optimistic given the program's late
start, past trends in space acquisitions, and challenges facing the new
contractor. Of particular concern is leadership for GPS acquisition, as
GAO and other studies have found the lack of a single point of
authority for space programs and frequent turnover in program managers
have hampered requirements setting, funding stability, and resource
allocation.
* If the Air Force does not meet its schedule goals for development of
GPS IIIA satellites, there will be an increased likelihood that in
2010, as old satellites begin to fail, the overall GPS constellation
will fall below the number of satellites required to provide the level
of GPS service that the U.S. government is committed to providing. Such
a gap in capability could have wide-ranging impacts on all GPS users,
though there are measures the Air Force and others can take to plan for
and minimize these impacts.
Moreover, the Air Force has not been fully successful in synchronizing
the acquisition and development of the next generation of GPS
satellites with the ground control and user equipment, thereby delaying
the ability of military users to utilize new GPS satellite
capabilities. For example, a modernized military signal will be
available for operations on GPS satellites over a decade before user
equipment will be fielded that can take strategic advantage of it. The
signal is designed to improve resistance to jamming of GPS. Also,
because leadership for acquisitions across the space community is
fragmented, there is no single authority responsible for synchronizing
all procurements and fielding related to GPS.
Lastly, DOD and others involved in ensuring GPS can serve communities
beyond the military have taken prudent steps to manage requirements and
coordinate among the many organizations involved with GPS. However, we
identified challenges in the areas of ensuring civilian requirements
can be met and ensuring GPS compatibility with other new, potentially
competing global space-based positioning, navigation, and timing
systems.
Because of (1) the criticality of the GPS system to the military,
various economic sectors, and the international community and (2)
schedule risks in the current program, we are recommending that the
Secretary of Defense appoint a single authority to oversee the
development of the GPS system, including DOD space, ground control, and
user equipment assets, to ensure that the program is well executed and
resourced and that potential disruptions are minimized. The appointee
should have authority to ensure DOD space, ground control, and user
equipment are synchronized to the maximum extent practicable; and
coordinate with the existing positioning, navigation, and timing
infrastructure to assess and minimize potential service disruptions in
the event that the satellite constellation was to decrease in size for
an extended period of time. After a review of a draft of this report,
DOD concurred with our recommendations and provided some additional
comments. The full text of DOD's comments may be found in appendix IV.
Background:
GPS is a global positioning, navigation, and timing network consisting
of space, ground control, and user equipment segments that support the
broadcasts of military and civil GPS signals. These signals each
include positioning and timing information, which enables users with
GPS receivers to determine their position, velocity, and time, 24 hours
a day, in all weather, worldwide. GPS is used by all branches of the
military to guide troops' movements, integrated logistics support and
battlespace situational awareness, and communications network
synchronization. In addition, bombs and missiles are guided to their
targets by GPS signals and GPS is used to locate military personnel in
distress. Early in the development of GPS, the scope was expanded to
include complementary civil capabilities.
Over time, GPS has become a ubiquitous infrastructure underpinning
major sections of the economy, including telecommunications, electrical
power distribution, banking and finance, transportation, environmental
and natural resources management, agriculture, and emergency services
in addition to the array of military operations it services. For
instance, civil agencies, commercial firms, and individuals use GPS to
accurately navigate from one point to another. Commercial firms use GPS
to route their vehicles, as do maritime industries and mass transit
systems. In addition to navigation, civil departments and agencies and
commercial firms use GPS and GPS augmentations[Footnote 2] to provide
high-accuracy, three-dimensional positioning information in real time
for use in surveying and mapping. The aviation community worldwide uses
GPS and GPS augmentations to increase the safety and efficiency of
flight. GPS is also used in the agricultural community for precision
farming, including farm planning, field mapping, soil sampling, tractor
guidance, and crop scouting. GPS helps companies and governments place
satellites in precise orbits, and at correct altitudes, and helps
monitor satellite constellation orbits. The precise time that GPS
broadcasts is crucial to economic activities worldwide, including
communication systems, electrical power grids, and financial networks.
GPS System Description:
GPS operations consist of three segments--the space segment, the ground
control segment, and the user equipment segment. All segments are
needed to take full advantage of GPS capabilities.
Figure 1: GPS Operational System:
[Refer to PDF for image: illustration]
Space segment:
satellites circling the globe;
Ground control segment:
Ground antenna;
Monitor station;
Master Control Station.
User segment:
Aviation;
Hand held devices;
Recreation;
Ground navigation;
Mapping and surveying;
Maritime.
Source: Copyright © Corel Corp. All rights reserved (map); Art
Explosion; GAO.
[End of figure]
The GPS space segment consists of a constellation of satellites that
move in six orbital planes approximately 20,200 kilometers above the
earth. GPS satellites broadcast encrypted military signals and civil
signals. In recent years, because numerous satellites have exceeded
their design life, the constellation has grown to 31 active satellites
of various generations. However, DOD predicts that over the next
several years many of the older satellites in the constellation will
reach the end of their operational life faster than they will be
replenished, thus decreasing the size of the constellation from its
current level and potentially reducing the accuracy of the GPS service.
The GPS ground control segment is comprised of a Master Control Station
at Schriever Air Force Base, Colorado; an Alternate Master Control
Station at Vandenberg Air Force Base, California; 6 Air Force and 11
National Geospatial-Intelligence Agency monitoring stations; and four
ground antennas with uplink capabilities. Information from the
monitoring stations is processed at the Master Control Station to
determine satellite clock and orbit status. The Master Control Station
operates the satellites and regularly updates the navigation messages
on the satellites. Information from the Master Control Station is
transmitted to the satellites via the ground antennas.
The GPS user equipment segment includes military and commercial GPS
receivers. These receivers determine a user's position by calculating
the distance from four or more satellites using the navigation message
on the satellites to triangulate its location. Military GPS receivers
are designed to utilize the encrypted military GPS signals that are
only available to authorized users, including military and allied
forces and some authorized civil agencies. Commercial receivers use the
civil GPS signal, which is publicly available worldwide.
GPS Modernization:
In 2000, DOD began an effort to modernize the space, ground control,
and user equipment segments of GPS to enhance the system's performance,
accuracy, and integrity. Table 1 shows the modernization efforts for
the space and ground control segment.
Table 1: GPS Satellite and Ground Control Segment Modernization:
Satellite evolution and capabilities:
Legacy: (1989 - 2002):
GPS IIA/IIR:
* Broadcasts signals for military and civil users.
Current: (2005 - 2012):
GPS IIR-M:
Includes IIA and IIR capabilities, plus:
* 2nd civil signal;
* 2nd military signal;
* Ability to increase signal power to improve resistance to jamming.
GPS IIF:
Includes IIR-M capabilities, plus:
* 3rd civil signal for transportation safety requirements.
Future: (2014 - 2023):
GPS III:
Includes IIF capabilities, plus:
* IIIA: stronger military signal to improve jamming resistance and 4th
civil signal that is interoperable with foreign signals;
* IIIB: near real-time command and control via cross links;
* IIIC: improved antijam performance for military users.
Ground control segment and capabilities:
Legacy: (Various versions from 1979-2007):
Legacy Operational Control System (OCS):
* Centralized computer mainframe;
* 1970s technology.
Current: (Came online in 2007):
Architecture Evolution Plan (AEP):
* Distributed architecture;
* Enables upgrades to the system;
* Next upgrade will control GPS IIF.
Future: (Planned to come online with initial capabilities in 2011):
Next Generation Operational Control Segment (OCX):
* Necessary for full operation of GPS IIR-M, IIF, and III satellites;
* Service-oriented architecture;
* Connects to the broader network.
Source: GAO analysis based on DOD program information and discussions
with DOD officials.
[End of table]
Full use of the military and civil GPS signals requires a ground
control system that can manage these signals. Newer software will
upgrade the ground control to a service oriented--or "plug and play"--
architecture that can connect to broader networks. In order to utilize
the modernized military signal from the ground, military users require
new user equipment with this capability, which will be provided by the
military GPS user equipment program.
Broader Management Structure:
The 2004 U.S. Space-Based Positioning, Navigation and Timing (PNT)
policy established a management structure to bring civil and military
departments and agencies together to form an interagency, multiuse
approach to program planning, resource allocation, system development,
and operations. The policy also encourages cooperation with foreign
governments to promote the use of civil aspects of GPS and its
augmentation services and standards with foreign governments and other
international organizations. As part of the management structure, an
executive committee advises and coordinates among U.S. government
departments and agencies on maintaining and improving U.S. space-based
PNT infrastructures, including GPS and related systems. The executive
committee is co-chaired by the Deputy Secretaries of the Department of
Defense and the Department of Transportation, and includes members at
the equivalent level from the Departments of State, Commerce, Homeland
Security, Interior, Agriculture, the Joint Chiefs of Staff, and the
National Aeronautics and Space Administration (NASA). Figure 2
describes the National Space-Based PNT organization structure.
Figure 2: National Space-Based PNT Organization Structure:
[Refer to PDF for image: organizational chart]
Top level:
White House.
Second level, reporting to the White House:
National Executive Committee for Space-Based PNT, Executive Steering
Group; Co-chairs: Defense and Transportation.
Steering Group Members:
Defense;
Transportation;
State;
Interior;
Agriculture;
Commerce;
Homeland Security;
Joint Chiefs of Staff;
NASA.
Advisory Board; Sponsor: NASA.
Third level, reporting to the National Executive Committee for Space-
Based PNT:
National Coordination Office; Host: Commerce.
Fourth level, reporting to National Coordination Office:
GPS International Working Group; Chair: State;
Engineering Forum; Co-chairs: Defense and Transportation;
Ad Hoc Working Groups.
Source: GAO presentation of National Executive Committee for Space-
Based Positioning, Navigation and Timing Data.
[End of figure]
The departments and agencies have various assigned roles and
responsibilities. For example, DOD is responsible for the overall
development, acquisition, operation, security, and continued
modernization of GPS. It has delegated acquisition responsibility to
the Air Force, though other DOD components and military services are
responsible for oversight, some aspects of user equipment development,
and for funding some parts of the program. The Department of
Transportation has the lead responsibility for the coordination of
civil requirements from all civil department and agencies. The
Department of State leads negotiations with foreign governments and
international organizations on GPS positioning, navigation, and timing
matters or regarding the planning, operations, management, and/or use
of GPS. (See appendix III).
Air Force Faces Significant Challenges in Acquiring GPS Satellites:
The Air Force's GPS IIF acquisition initially was not well executed,
and currently poses technical problems. The Air Force is implementing
lessons learned from the GPS IIF effort as it starts the GPS IIIA
program. However, based on our analysis, the GPS IIIA program faces a
compressed schedule along with new challenges to deliver the satellites
on time. A slip in the launch of the GPS IIIA satellites could increase
the likelihood that the GPS constellation will fall below the number of
satellites required to provide the level of GPS service the U.S.
government has committed to provide. This would not only have
implications for military users but also for the larger community of
GPS users, who may be less aware and equipped to deal with gaps in
coverage. However, the Air Force is evaluating different approaches
that could potentially reduce the risk of degrading the GPS service.
The IIF Program Was Not Well Executed, and Still Poses Technical
Problems:
The GPS IIF contract was awarded during an era of acquisition reform
that centered on an approach called Total System Performance
Responsibility (TSPR).[Footnote 3] TSPR gave a contractor total
responsibility for the integration of an entire weapon system and for
meeting DOD's requirements. This approach was intended to facilitate
acquisition reform and enable DOD to streamline a cumbersome
acquisition process and leverage innovation and management expertise
from the private sector. However, DOD later found that TSPR magnified
problems on a number of satellite acquisition programs because it was
implemented in a manner that enabled requirements creep and poor
contractor performance. For GPS IIF, the TSPR approach resulted in
relaxed specifications and inspections of the contractor, loss of
quality in the manufacturing process, and poor-quality parts that
caused test failures, unexpected redesigns, and the late delivery of
parts. The contractor did not provide data on design drawings and
statistical process control techniques were not used to monitor
production.
According to GPS program officials, the GPS IIF program was also
negatively impacted by multiple contractor mergers, acquisitions, and
moves. In 1996, shortly after Rockwell won the IIF contract, the
company's aerospace and defense units, including the Seal Beach,
California, facility where the IIF satellites were to be manufactured,
were acquired by Boeing. In December 1997, Boeing merged with McDonnell
Douglas and took over its Delta launch vehicle unit in Huntington
Beach, California, and subsequently GPS work was moved to that
facility. In October 2000, Boeing acquired Hughes Electronics
Corporation's space and communications business and related operations.
Boeing took over the Hughes facility in El Segundo, California, and
once again, GPS work was moved to another facility. As these events
occurred, the prime contractor consolidated development facilities to
remain competitive. In addition, the prime contractor lost valuable
workers and knowledge, causing inefficiencies in the program.
Shortly after the IIF contract was awarded in 1996, the Air Force also
added requirements. For example, the government decided to accelerate
the fielding of new civil and military GPS signals. Flexible power
capabilities were added to IIF several years later. These new
requirements drove design changes and resulted in technical issues and
cost overruns that impacted the schedule.
According to a GPS IIF program official, the combination of significant
requirements additions, loss of engineering expertise, parts
obsolescence, and fundamental design changes together caused the
contractor to "lose the recipe" for the IIF space vehicle. In essence,
by the completion of the design phase, the IIF space vehicle was to be
built in a third location, by different people, in a way that was not
initially anticipated. In addition, the program suffered from a lack of
management continuity. Since the program's inception, the IIF program
has had seven different program managers, the first five of whom only
served 1 year each.
According to a former deputy program director of the GPS program
office, past GPS programs seemed to operate well for a number of
reasons. The programs (1) never added major modifications to ongoing
programs and (2) had no qualms in terminating contractors if work did
not meet standards, business practices, or major milestones.
Furthermore, the GPS program performed more on-site contract management
to increase communications. This approach eliminated surprises like
cost and schedule overruns and held the contractor to a high level of
performance. Lastly, the former director noted that it was important to
balance the responsibility assigned to the program managers with the
authority they needed to properly implement the program. Prior GAO
reviews have identified all of these practices as essential to program
execution.[Footnote 4]
Air Force Improves Oversight of IIF, but Technical Issues Lead to More
Delays:
The Air Force has since taken action to improve the IIF program. In
2006, the program office[Footnote 5] increased its personnel at the
contractor's facility to observe operations and to verify that
corrective measures were being taken to address deficiencies in the
contractor's cost and schedule reporting system (also known as earned
value management[Footnote 6]). The Air Force increased the number of
personnel to work on the contractor site, which included military and
civilian personnel, as well as Defense Contract Management Agency
[Footnote 7] personnel and system engineering contractors. Greater
presence at the contractor's factory has enabled the government to find
out about problems as they happen and work with the contractor to come
up with solutions and resolve issues quicker, according to GPS program
officials.
Nonetheless, the program has experienced more technical problems. For
example, last year, during the first phase of thermal vacuum testing (a
critical test to determine space-worthiness that subjects the satellite
to space-like operating conditions), one transmitter used to send the
navigation message to the users failed. The program suspended testing
in August 2008 to allow time for the contractor to identify the causes
of the problem and take corrective actions. The program also had
difficulty maintaining the proper propellant fuel-line temperature;
this, in addition to power failures on the satellite, delayed final
integration testing. In addition, the satellite's reaction wheels, used
for pointing accuracy, were redesigned because on-orbit failures on
similar reaction wheels were occurring on other satellite programs--
this added about $10 million to the program's cost.
As a result of these problems, the IIF program experienced cost
increases and schedule delays. The launch of the first IIF satellite
has been delayed until November 2009--almost 3 years late. According to
the program office, the cost to complete GPS IIF will be about $1.6
billion--about $870 million over the original cost estimate of $729
million.
In addition, in 2006 we testified[Footnote 8] that diffuse leadership
over military space acquisitions was another factor contributing to
late delivery of capability and cost growth. We noted that the diverse
array of officials and organizations involved with a space program has
made it difficult to pare back and control requirements. GPS was one
example we cited. According to the Air Force, in 1998 the government
decided to accelerate the fielding of new civil and military GPS
signals and added requirements for these signals to the IIR and IIF GPS
satellites. These new requirements drove design changes and resulted in
technical issues, cost overruns, and program delays.
Problems Experienced in GPS IIF Seen in Other Space System
Acquisitions:
The problems experienced on the IIF program are not unlike those
experienced in other DOD space system acquisitions. We have previously
reported that the majority of major acquisition programs in DOD's space
portfolio have experienced problems during the past two decades that
have driven up costs, caused delays in schedules, and increased
technical risk.[Footnote 9] DOD has restructured several programs in
the face of delays and cost growth. At times, cost growth has come
close to or exceeded 100 percent, causing DOD to nearly double its
investment without realizing a better return on investment. Along with
the increases, many programs are experiencing significant schedule
delays--as much as 7 years--postponing delivery of promised
capabilities to the warfighter. Outcomes have been so disappointing in
some cases that DOD has gone back to the drawing board to consider new
ways to achieve the same, or less, capability.
Our work has identified a variety of reasons for the cost growth, many
of which surfaced in GPS IIF. Generally, we have found that DOD starts
its space programs too early, that is before it has assurance that the
capabilities it is pursuing can be achieved within resources and time
constraints. We have also tied acquisition problems in space to
inadequate contracting strategies; contract and program management
weaknesses; the loss of technical expertise; capability gaps in the
industrial base; tensions between labs that develop technologies for
the future and current acquisition programs; divergent needs in users
of space systems; and other issues that have been well documented.
We also noted that short tenures for top leadership and program
managers within the Air Force and the Office of the Secretary of
Defense have lessened the sense of accountability for acquisition
problems and further encouraged a view of short-term success.[Footnote
10] Several other studies have raised similar issues. In 2003, a study
[Footnote 11] conducted for the Defense Science Board, for example,
found that government capabilities to lead and manage the space
acquisition process have seriously eroded, particularly within program
management ranks. A 2005 Defense Science Board study[Footnote 12]
focused specifically on the future of GPS found that the program was
hampered by sometimes overlapping, sometimes disconnected roles of
Office of the Secretary of Defense staff components, the Joint Staff,
and the Air Force. More recently, a commission[Footnote 13] formed
pursuant to the John Warner National Defense Authorization Act for
Fiscal Year 2007[Footnote 14], concluded in 2008 that there is
currently no single authority responsible for national security space-
-which includes GPS--below the President and that within DOD
authorities are spread among a variety of organizations, including the
Office of the Secretary of Defense, the Air Force, the other military
services, the Missile Defense Agency, and the National Reconnaissance
Office with no effective mechanism to arrive at a unified budget and
set priorities. A study[Footnote 15] chartered by the House Select
Committee on Intelligence also recently found leadership for space
acquisitions to be too diffused at higher levels and that there are
critical shortages in skilled program managers. While recent studies
have made recommendations for strengthening leadership for space
acquisitions, no major changes to the leadership structure have been
made in recent years. In fact, an "executive agent" position within the
Air Force which was designated in 2001 to provide leadership has not
been filled since the last executive resigned in 2005.
GPS IIF acquisition problems have not been as extreme as those
experienced on other efforts such as the Space Based Infrared System
(SBIRS) and the National Polar-orbiting Operational Environmental
Satellite System (NPOESS). At the same time, however, the program was
not as technically complex or ambitious as these efforts.
DOD Is Implementing Lessons Learned from the GPS IIF Program as It
Starts the GPS IIIA Program, but Schedule Is Optimistic:
The Air Force is taking measures to prevent the problems experienced on
the GPS IIF program from recurring on the GPS IIIA program. However,
the Air Force will still be challenged to deliver IIIA on time because
the satellite development schedule is compressed. The Air Force is
taking the following measures:
* using incremental or block development, where the program would
follow an evolutionary path toward meeting needs rather than attempting
to satisfy all needs in a single step;
* using military standards for satellite quality;
* conducting multiple design reviews, with the contractor being held to
military standards and deliverables during each review;
* exercising more government oversight and interaction with the
contractor and spending more time at the contractor's site; and:
* using an improved risk management process, where the government is an
integral part of the process.
In addition, the Under Secretary of Defense for Acquisition,
Technology, and Logistics specified additional guidance for the GPS
IIIA program. This includes:
* reevaluating the contractor incentive/award fee approach;
* providing a commitment from the Air Force to fully fund GPS IIIA in
Program Objectives Memorandum[Footnote 16] 2010;
* funding and executing recommended mitigation measures to address the
next generation operational control segment and the GPS IIIA
satellites;
* combining the existing and new ground control segment levels of
effort into a single level of effort, giving the Air Force greater
flexibility to manage these efforts;
* not allowing the program manager to adjust the GPS IIIA program scope
to meet increased or accelerated technical specifications, system
requirements, or system performance; and:
* conducting an independent technology readiness assessment of the
contractor design once the preliminary design review is complete.
Table 2 below highlights the major differences in the framework between
the GPS IIF and GPS III programs.
Table 2: Key Differences in Program Framework for GPS IIF and GPS III:
Requirements:
GPS IIF: Addition of requirements after contract award;
GPS III: Not allowing an adjustment to the program to meet increased or
accelerated requirements.
Development:
GPS IIF: Immature technologies;
GPS III: Incremental development, while ensuring technologies are
mature.
Oversight:
GPS IIF: Limited oversight of contractor, relaxed specifications and
inspections, and limited design reviews;
GPS III: More contractor oversight with government presence at
contractor facility; use of military standards; and multiple levels of
preliminary design reviews, with the contractor being held to military
standards and deliverables during each review.
Source: GAO analysis based on discussion with the GPS program office
and program documentation.
[End of table]
The Air Force's Schedule for GPS IIIA May Be Optimistic:
While these measures should put the GPS IIIA program on sounder
footing, the program is facing serious obstacles--primarily in terms of
its ability to deliver satellites on schedule. At present, the GPS IIIA
program is on schedule and program officials contend that there is no
reason to assume that a delay is likely to occur. They point out that
the Air Force is implementing an incremental development approach and
GPS IIIA, the first increment of GPS III, is not expected to be as
technically challenging as other space programs. In addition, program
officials point out that the Air Force began risk reduction activities
in 1998, and has made a concerted effort to exert more oversight over
its contractors and ensure key decisions are backed by sufficient
knowledge about technologies, design, and production.
We recognize that these steps offer the best course for GPS to be
completed on time. However, we believe there is still considerable risk
that the schedule may not be met for the following reasons.
* First, the GPS IIIA program got off to a late start. The program was
originally scheduled to begin development in August 2007. However,
according to GPS program officials, the Air Force shifted funds from
GPS III to other commitments in its space portfolio and to address
problems in other programs. The Defense Space Acquisition Board
approved formal initiation of the GPS IIIA acquisition in May 2008.
* Second, when compared to other DOD satellite programs, the GPS IIIA
program schedule appears highly compressed. The Air Force is planning
to launch the first GPS IIIA satellite in 2014 to sustain the GPS
constellation. To launch in 2014, the Air Force has scheduled 72 months
from contract award to first satellite launch. This schedule is 3 years
shorter than the schedule the Air Force has so far achieved under its
IIF program. In fact, the time period between contract award and first
launch for GPS IIIA is shorter than most other major space programs we
have reviewed (see figure 3). Moreover, GPS IIIA is not simply a matter
of replicating the IIF program. Though the contractor has had previous
experience with GPS, it is likely that the knowledge base will need to
be revitalized. The contractor is also being asked to develop a larger
satellite bus to accommodate future GPS increments IIIB and IIIC. In
addition, the contractor is being asked to increase the power of a new
military signal by a factor of 10. In our opinion, there is little room
in the schedule to accommodate difficulties the contractor may have in
meeting either challenge. In addition, the GPS III program office still
has not been able to fill critical contracting and engineering
positions needed to assist in satellites design and contractor
oversight--both of which functions are to receive more emphasis on this
program than in the past. Consequently, the concerns that GPS IIIA
could experience a delay are not unreasonable. However, according to
DOD officials, the incremental approach to GPS acquisition should
significantly lower the risk of schedule delays. Nonetheless, no major
satellite program undertaken in the past decade has met its scheduled
goals.
Figure 3: Schedule Development from Start to Launch for Space Programs
(in Months):
[Refer to PDF for image: vertical bar graph]
Program: DSCS III;
Start to launch: 52 months.
Program: UHF Follow-On;
Start to launch: 58 months.
Program: MUOS (e);
Start to launch: 62 months.
Program: DMSP Block 5D-3;
Start to launch: 65 months.
Program: GPS III (e);
Start to launch: 72 months.
Program: STSS (e);
Start to launch: 78 months.
Program: Milstar II;
Start to launch: 78 months.
Program: WGS (e);
Start to launch: 83 months.
Program: AEHF(e)
Start to launch: 86 months.
Program: TSAT (e);
Start to launch: 89 months.
Program: Navstar GPS IIF (e);
Start to launch: 106 months.
Program: NPOESS (e);
Start to launch: 125 months.
Program: Milstar I;
Start to launch: 128 months.
Program: SBIRS High (e)
Start to launch: 158 months.
Source: GAO analysis based on program documentation.
Note:
DSCS - Defense Satellite Communications System.
UHF - Ultra High Frequency.
MUOS - Mobile User Objective System.
DMSP - Defense Meteorological Satellites Program.
GPS - Global Positioning System.
STSS - Space Tracking and Surveillance System.
WGS - Wideband Global Satellite Communications.
AEHF - Advanced Extremely High Frequency.
TSAT - Transformational Satellite Communications System.
NPOESS - National Polar-orbiting Operational Environmental Satellite
System.
SBIRS - Space Based Infrared System.
All programs with (e) denotation used current estimated dates for
launch.
[End of figure]
* Third, we compared the Air Force's GPS IIIA schedule to best
practices associated with effective schedule estimating. Past GAO work
has identified nine practices associated with effective schedule
estimating. We analyzed the Air Force's GPS IIIA schedule according to
these practices and found that one was met, one was not met, and the
other seven practices were only partially met. The practices deal with
how well the schedule identifies key development activities, the times
to complete these activities, as well as the amount of float time
associated with each of these activities--float time is the amount of
time a task can slip before affecting the critical path. Further, the
practices assess how well activities have been integrated with other
tasks and whether reserve times have been allocated to high-risk
activities. The primary purpose of all scheduling activities is to
establish a credible critical path. The best practices have been
designed to support that goal. Because the GPS IIIA schedule does not
follow all of the best practices, the reliability of the critical path
identified in the schedule is diminished.
A Delay in GPS III Could Severely Impact GPS Users:
Delays in the launch of the GPS IIIA satellites will increase the risk
that the GPS constellation will decrease in size to a level where it
will not meet some users' needs. If the GPS constellation falls below
the number of satellites required to provide the level of GPS service
that the U.S. government has committed to providing, some military and
civilian operations could be affected. DOD is evaluating different
approaches that could potentially mitigate the gap. However,
procurement of additional GPS IIF satellites does not appear to be
feasible.
A Delay in GPS III Could Affect GPS Constellation Performance:
The performance standards for both (1) the standard positioning service
provided to civil and commercial GPS users and (2) the precise
positioning service provided to military GPS users commit the U.S.
government to at least a 95 percent probability of maintaining a
constellation of 24 operational GPS satellites. Because there are
currently 31 operational GPS satellites of various blocks, the near-
term probability of maintaining a constellation of at least 24
operational satellites remains well above 95 percent. However, DOD
predicts that over the next several years many of the older satellites
in the constellation will reach the end of their operational life
faster than they will be replenished, and that the constellation will,
in all likelihood, decrease in size. Based on the most recent satellite
reliability and launch schedule data approved in March 2009, the
estimated long-term probability of maintaining a constellation of at
least 24 operational satellites falls below 95 percent during fiscal
year 2010 and remains below 95 percent until the end of fiscal year
2014, at times falling to about 80 percent. See figure 4 for details.
Figure 4: Probability of Maintaining a Constellation of at Least 24 GPS
Satellites Based on Reliability Data and Launch Schedule as of March
2009:
[Refer to PDF for image: line graph]
Fiscal year, beginning October 2008:
Actual probability of maintaining 24-satellite constellation: 100%.
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2009;
Actual probability of maintaining 24-satellite constellation: 99%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2010;
Actual probability of maintaining 24-satellite constellation: 98%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2011;
Actual probability of maintaining 24-satellite constellation: 92%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2012;
Actual probability of maintaining 24-satellite constellation: 87%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2013;
Actual probability of maintaining 24-satellite constellation: 87%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2014;
Actual probability of maintaining 24-satellite constellation: 86%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2015;
Actual probability of maintaining 24-satellite constellation: 77%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2016;
Actual probability of maintaining 24-satellite constellation: 87%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2017;
Actual probability of maintaining 24-satellite constellation: 86%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2018;
Actual probability of maintaining 24-satellite constellation: 91%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2019;
Actual probability of maintaining 24-satellite constellation: 89%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2020;
Actual probability of maintaining 24-satellite constellation: 97%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2021;
Actual probability of maintaining 24-satellite constellation: 99%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2022;
Actual probability of maintaining 24-satellite constellation: 99%;
Committed probability of maintaining 24-satellite constellation: 95%.
Fiscal year, beginning October 2023;
Actual probability of maintaining 24-satellite constellation: 99%;
Committed probability of maintaining 24-satellite constellation: 95%.
Source: GAO analysis of DOD data.
[End of figure]
The probability curve in figure 4 was generated using unique
reliability curves for each operational satellite in the current on-
orbit GPS constellation, and block-specific reliability curves for each
production (unlaunched) GPS satellite, including IIR-M, IIF, IIIA,
IIIB, and IIIC satellites. (See appendix I for a more complete
description of the approach used to generate this probability curve.)
Because the reliability curves associated with new blocks of GPS
satellites are based solely on engineering and design analysis instead
of actual on-orbit performance, this estimated long-term probability of
maintaining a 24-satellite constellation could change once actual on-
orbit performance data become available. For example, while the block
IIA satellites were designed to last only 7.5 years on average, they
have actually lasted about twice as long. If GPS IIF satellites were to
last twice as long as their currently estimated mean life expectancy of
11.5 years, the probability of maintaining a larger constellation would
increase, but the long-term probability of maintaining the 24-satellite
constellation would not improve significantly. Moreover, program
officials provided no evidence to suggest that the current mean life
expectancy for IIF satellites is overly conservative.
A delay in the production and launch of GPS III satellites could
severely impact the U.S. government's ability to meet its commitment to
maintain a 24-satellite GPS constellation. The severity of the impact
would depend upon the length of the delay. For example, a 2-year delay
in the production and launch of the first and all subsequent GPS III
satellites would reduce the probability of maintaining a 24-satellite
constellation to about 10 percent by around fiscal year 2018. This
significant gap in service would persist for about 2 years before the
constellation began to recover. Moreover, this recovery--that is, the
return to a high probability of maintaining a 24-satellite
constellation--would take an additional 2 to 3 years. Consequently, a 2-
year delay in the production and launch of GPS III satellites would
most likely result in a period of roughly 5 years when the U.S.
government would be operating a GPS constellation of fewer than 24
satellites, and a 12-year period during which the government would not
meet its commitment to maintaining a constellation of 24 operational
GPS satellites with a probability of 95 percent or better. For example,
the delay in GPS III would reduce the probability of maintaining a 21-
satellite constellation to between 50 and 80 percent for the period
from fiscal year 2018 through fiscal year 2020. Moreover, while the
probability of maintaining an 18-satellite constellation would remain
relatively high, it would still fall below 95 percent for about a year
over this period. See figure 5 for details.
Figure 5: Probability of Maintaining a Constellation of at Least 18,
21, and 24 GPS Satellites Based on Reliability Data as of March 2009
and a 2-Year GPS III Launch Delay:
[Refer to PDF for image: multiple line graph]
Fiscal year: October 2008;
Probability of maintaining 18-satellite constellation: 100%;
Probability of maintaining 21-satellite constellation: 100%;
Probability of maintaining 24-satellite constellation: 100%.
Fiscal year: October 2009;
Probability of maintaining 18-satellite constellation: 100%;
Probability of maintaining 21-satellite constellation: 100%;
Probability of maintaining 24-satellite constellation: 99%.
Fiscal year: October 2010;
Probability of maintaining 18-satellite constellation: 100%;
Probability of maintaining 21-satellite constellation: 100%;
Probability of maintaining 24-satellite constellation: 98%.
Fiscal year: October 2011;
Probability of maintaining 18-satellite constellation: 100%;
Probability of maintaining 21-satellite constellation: 99%;
Probability of maintaining 24-satellite constellation: 93%.
Fiscal year: October 2012;
Probability of maintaining 18-satellite constellation: 100%;
Probability of maintaining 21-satellite constellation: 99%;
Probability of maintaining 24-satellite constellation: 86%.
Fiscal year: October 2013;
Probability of maintaining 18-satellite constellation: 100%;
Probability of maintaining 21-satellite constellation: 99%;
Probability of maintaining 24-satellite constellation: 87%.
Fiscal year: October 2014;
Probability of maintaining 18-satellite constellation: 99%;
Probability of maintaining 21-satellite constellation: 97%;
Probability of maintaining 24-satellite constellation: 74%.
Fiscal year: October 2015;
Probability of maintaining 18-satellite constellation: 92%;
Probability of maintaining 21-satellite constellation: 83%;
Probability of maintaining 24-satellite constellation: 31%.
Fiscal year: October 2016;
Probability of maintaining 18-satellite constellation: 83%;
Probability of maintaining 21-satellite constellation: 40%;
Probability of maintaining 24-satellite constellation: 1%.
Fiscal year: October 2017;
Probability of maintaining 18-satellite constellation: 89%;
Probability of maintaining 21-satellite constellation: 41%;
Probability of maintaining 24-satellite constellation: 3%.
Fiscal year: October 2018;
Probability of maintaining 18-satellite constellation: 86%;
Probability of maintaining 21-satellite constellation: 56%;
Probability of maintaining 24-satellite constellation: 7%.
Fiscal year: October 2019;
Probability of maintaining 18-satellite constellation: 99%;
Probability of maintaining 21-satellite constellation: 37%;
Probability of maintaining 24-satellite constellation: 5%.
Fiscal year: October 2020;
Probability of maintaining 18-satellite constellation: 99%;
Probability of maintaining 21-satellite constellation: 81%;
Probability of maintaining 24-satellite constellation: 24%.
Fiscal year: October 2021;
Probability of maintaining 18-satellite constellation: 100%;
Probability of maintaining 21-satellite constellation: 92%;
Probability of maintaining 24-satellite constellation: 50%.
Fiscal year: October 2022;
Probability of maintaining 18-satellite constellation: 100%;
Probability of maintaining 21-satellite constellation: 97%;
Probability of maintaining 24-satellite constellation: 76%.
Fiscal year: October 2023;
Probability of maintaining 18-satellite constellation: 100%;
Probability of maintaining 21-satellite constellation: 99%;
Probability of maintaining 24-satellite constellation: 89%.
Source: GAO analysis of DOD data.
[End of figure]
Both Military and Civilian GPS Users Would Be Affected by a Delay in
GPS III:
The impacts to both military and civil users of a smaller constellation
are difficult to precisely predict. For example, a nominal 24-satellite
constellation with 21 of its satellites broadcasting a healthy standard
positioning service signal would continue to satisfy the availability
standard for good user-to-constellation geometry articulated in the
standard positioning service performance standard.[Footnote 17]
However, because the GPS constellation has been operating above the
committed performance standard for so long, military and civil users
have come to expect a higher level of service, even though this service
is not committed to them. Consequently, some users may sense an
operational impact even if the constellation were to perform at or near
its committed standards. In general, users with more demanding
requirements for precise location solutions will likely be more
impacted than other users.[Footnote 18] During our interviews with
military, civil, and commercial representatives, several examples of
possible impacts of a smaller GPS constellation were discussed.
* The accuracy of precision-guided munitions that rely upon GPS to
strike their targets could decrease. To accomplish their mission,
military forces would either need to use larger munitions or use more
munitions on the same target to achieve the same level of mission
success. The risks of collateral damage could also increase.
* Intercontinental commercial flights use predicted satellite geometry
over their planned navigation route, and may have to delay, cancel or
reroute flights.
* Enhanced-911 services, which rely upon GPS to precisely locate
callers, could lose accuracy, particularly when operating in "urban
canyons" or mountainous terrain.
Another important consideration is that both the standard positioning
service and precise positioning service performance standards assume
that users have unobstructed visibility to nearly the entire sky,
[Footnote 19] an assumption that does not hold for the large number of
users operating in moderately mountainous terrain, in the "urban
canyons" of large cities, or under forest foliage.
Different Approaches Are Being Evaluated that Could Potentially
Mitigate the Gap:
The Air Force is aware that there is some risk that the number of
satellites in the GPS constellation could fall below its required 24
satellites, and that this risk would grow significantly if the
development and launch of GPS IIIA satellites were delayed.
Consequently, an Air Force Space Command representative informed us
that the command has established an independent review team to examine
the risks and consequences of a smaller constellation on military and
civil users. However, at this time, Air Force representatives believe
that the best approach to mitigating the risk is to take all reasonable
steps to ensure that the current schedule for GPS IIF and III is
maintained. Those steps include a commitment from the Air Force to
fully fund GPS IIIA in the fiscal year 2010 Program Objectives
Memorandum, and use of an incremental development approach toward
meeting needs. This incremental approach would place a premium on
controlling schedule risk by, among other things, deferring
consideration of civil requirements for subsystems like the Distress
Alerting Satellite System (DASS) and the Satellite Laser Ranging (SLR)
payloads to GPS IIIB or GPS IIIC satellite blocks.
Options for developing lower-cost alternatives to current GPS
satellites appear to be very limited. For example, in 2007 the Air
Force Scientific Advisory Board examined whether small satellites--
which can be developed more quickly and at relatively low cost--might
help meet some PNT mission requirements. The board concluded that small
satellites may eventually have operational utility in augmenting GPS
III capabilities, with emphasis on enhancing the utility of the GPS M-
code signal's capabilities against jamming. However, the need for an
extensive control segment infrastructure to monitor and control these
small satellite augmentations, combined with the need to develop,
produce, and install user equipment, would make it very challenging to
field a near-term small satellite augmentation for PNT. With respect to
providing basic PNT services, the board noted that studies of PNT
satellite constellations, performed at different times and by different
organizations in the United States and elsewhere, demonstrate that a
robust constellation of relatively powerful satellites operating at
medium earth orbit is the best way to provide continuous worldwide PNT
services; this is a performance set that small satellites currently
cannot provide.
According to Air Force representatives, the procurement of additional
IIF satellites is not feasible, and initiating development of an
alternative full-scale, satellite-based PNT system appears to be
impractical. Such a system would likely be very expensive and would
compete with GPS III development for funding, making it harder for the
Air Force to meet its commitment to fully fund GPS IIIA development.
Moreover, the GPS III system development contract was awarded in
accordance with an approved GPS III acquisition strategy, which
selected one alternative from two competing contractors' designs; an
alternative system development would be, in effect, a significant
deviation from that approved strategy. Finally, it seems unlikely that
the award of a separate system development contract with another
contractor would have any real impact on reducing the risk of
delivering GPS IIIA requirements on the current schedule.
In the event that this strategy proves unsuccessful and the schedule
for GPS III slips, additional measures could be considered. For
example, excluding random failures, the operational life of a GPS
satellite tends to be limited by the amount of power that its solar
arrays can produce. This power level declines over time as the solar
arrays degrade in the space environment until eventually they cannot
produce enough power to maintain all of the satellite's subsystems.
However, according to Air Force representatives, the effects of this
power loss can be mitigated somewhat by actively managing satellite
subsystems--shutting them down when not needed--thereby reducing the
satellite's overall consumption of power. It would also be possible to
significantly reduce the satellite's consumption of power by shutting
off a secondary GPS payload. This would buy additional time for the
navigation mission of the satellite at the expense of the mission
supported by the secondary payload. The 2004 U.S. Space-Based
Positioning, Navigation and Timing (PNT) policy affirmed PNT as the
primary mission for the GPS constellation, and stated that no secondary
payload may adversely affect the performance, schedule, or cost of GPS,
its signals, or services. Nevertheless, at this time the Air Force has
no intention of shutting off the secondary GPS payload. Moreover, until
there is a more immediate risk that the constellation will fall below
its required size, there is no reason to take this step.
Military and civil users might also take steps in response to a smaller
GPS constellation. While a smaller GPS constellation could result in a
significant reduction in positioning and navigation accuracy at certain
times and locations, these times and locations are usually predictable
in near-real time. Consequently for military users, who must rely upon
GPS's precise positioning service, a smaller constellation could
require changes in its approach to mission planning to ensure that
operations are conducted at times when GPS accuracy is relatively high,
or changes in tactics employed during a mission. For example, military
users could utilize a larger number of (or more powerful) munitions to
achieve an equivalent level of mission effectiveness.
For civil and commercial users, one possible impact of a smaller GPS
constellation could be an increased use of other positioning,
navigation, and timing services, including those expected to be offered
through Europe's Galileo system by the middle of the next decade. U.S.
government officials at the various civil agencies and departments
clearly understand what the government has committed to through GPS and
they all have designed programs to function with this limit, with
augmentations.
New Satellite Capabilities Will Not Be Leveraged Because of Delayed
Delivery of Ground and User Equipment Capabilities:
To maximize the benefit of GPS, the deployment of its space, ground
control, and user equipment capabilities must be synchronized so that
the full spectrum of military assets--weapons, aircraft, and ships, for
example--and individual users can take advantage of new capabilities
such as added protection from jamming. However, because of funding
shifts and diffuse leadership, the Air Force has not been successful in
synchronizing space, ground control, and user equipment segments. As a
result of the poor synchronization, new GPS capabilities may be
delivered in space for years before military users can take advantage
of these capabilities.
Air Force Has Deferred the Delivery of Ground Control Capabilities:
The Air Force used funding set aside for the ground control segment to
resolve GPS IIF development problems, causing a delay in the delivery
of new ground control capabilities. The GPS ground control segment has
evolved over time from the Operational Control Segment (OCS) to the
current Architecture Evolution Plan (AEP). GPS IIIA satellites are to
be controlled by a future ground control system called Next Generation
Control Segment, or OCX. OCS was supposed to control and exploit GPS
IIF space capabilities. However, because of the addition of new
requirements and technical issues on the IIF program, funding was
diverted from OCS to GPS IIF satellite development efforts. As a
result, the delivery of new ground control capabilities will occur
later than originally planned.
Table 3 below illustrates satellite functions and capabilities that
have yet to be made operational through the ground control segment. For
example, in 2005 the Air Force began launching its GPS IIR-M satellites
that broadcast a second civil signal (the L2C). Unfortunately, the
ground control segment will not be able to make the second civil signal
operational until late 2012 or 2013.
Table 3: Delays in Delivery of GPS Operational Functionality:
GPS IIR-M satellites (first launch in 2005 & currently being launched):
Function or capability enabled: Command & telemetry for IIA & IIR and
satellites, and use of additional signals;
Original ground control program/version: OCS Version 5.0; September
2005;
Current or future ground control program/version: OCS Version 5.2.1;
September 2007;
Amount of delay (in months): 24.
Function or capability enabled: Command & telemetry for IIRM & IIF
satellites;
Original ground control program/version: OCS Version 5.0; September
2005;
Current or future ground control program/version: AEP Version 5.2.2;
March 2008;
Amount of delay (in months): 30.
Function or capability enabled: Selective Availability Anti-Spoofing
Module;
Original ground control program/version: OCS Version 5.0; September
2005;
Current or future ground control program/version: AEP Version 5.5;
September 2009;
Amount of delay (in months): 48.
Function or capability enabled: Second civil signal (L2C);
Original ground control program/version: OCS Version 6; September 2007;
Current or future ground control program/version: OCX Block I or II;
September 2012/September 2013;
Amount of delay (in months): 60-72.
Function or capability enabled: Military code (M-code);
Original ground control program/version: OCS Version 6; September 2007;
Current or future ground control program/version: OCX Block I or II;
September 2012/September 2013;
Amount of delay (in months): 60-72.
GPS IIF satellites (first launch planned for November 2009):
Function or capability enabled: Third civil signal (L5);
Original ground control program/version: OCS Version 6; September 2007;
Current or future ground control program/version: OCX Block I or II;
September 2012/September 2013;
Amount of delay (in months): 60-72.
Source: GPS program office.
[End of table]
By delaying the delivery of ground control capabilities, the Air Force
has created an imbalance between the capabilities offered by GPS
satellites and the ability to exploit and make operational these
capabilities through the ground control segment.
Synchronization Problems Will also Delay Fielding of Improved GPS
Capabilities to Military Users:
GPS satellites that will broadcast the modernized military signal
require military user equipment capable of receiving and processing the
signal so that military users can take advantage of the improved
military capabilities. Before the modernized military signal can be
considered initially operational, it must be broadcast from at least 18
satellites, which is expected to occur in 2013. For full operational
capability, it must be broadcast from 24 satellites, which is expected
to occur in 2015. Consequently, the new military signal will be made
operational by the GPS satellites and ground control system in about
2013, but the warfighter will not be able to take full advantage of
this new signal until about 2025--when the modernized user equipment is
completely fielded. See figure 6 for our analysis of the gap between
when the modernized military signal will be available on the GPS
satellites and when the military services will be able to take
advantage of it.
Figure 6: Gap in the Ability of the Military to Use the Modernized
Signal:
[Refer to PDF for image: illustration]
Timeline from 2010 to 2030.
2013: Military signal capability from ground segment/18th military
signal satellite launched;
2015: 24th military signal satellite launched;
2025: Army, Navy, and Marine Corps fully equipped with modernized GPS
user equipment.
12 years between military signal initial operational capability and
fully equipped military services.
10 years between military signal full operational capability and fully
equipped military services.
Source: GAO analysis of DOD documents and discussions with DOD
officials.
[End of figure]
Funding and Technical Issues Have Delayed User Equipment Development,
but the Air Force Is Seeking to Accelerate Development:
The Air Force will spend the next several years developing prototype
cards and production-ready receiver hardware for selected platforms
within the space, air, ground, and maritime environments. Even after
this is done, the services will still need to add the new user
equipment to other platforms, which could take 10 or more years. This
is due to the fact that the integration and installation of the new
user equipment on the remaining platforms has to be coordinated with
existing upgrade schedules for those platforms. As a result, the
services' ability to achieve a joint military navigation warfare
capability, an essential element in conducting future military
operations, may not be realized until 2025 based on user equipment
delivery schedules.
Funding issues are a contributing factor in the delay in fielding new
user equipment. According to Air Force officials, the GPS program
office focused on developing the satellites, particularly when
technical problems arose. Funding was diverted from the user equipment
program to the GPS satellite program to fix problems, which resulted in
delays in the development and acquisition of the user equipment.
Diffused leadership has been particularly problematic in terms of DOD's
ability to synchronize delivery of space, ground control, and user
equipment assets. The responsibility for developing and acquiring GPS
satellite and associated ground control segments and for acquiring and
producing user equipment for selected platforms for space, air, ground,
and maritime environments falls under the Air Force's Space and Missile
Systems Center. On the other hand, responsibility for acquiring and
producing user equipment for all other platforms falls on the military
services. Figure 7 illustrates how the responsibilities for developing,
acquiring, and producing GPS user equipment are divided among the
services.
Figure 7: Responsibilities Among the Military Services for Procurement
of GPS User Equipment:
[Refer to PDF for image: text box]
Satellites and ground control: Single program executive officer;
Air Force Space and Missile Systems Center (reports to Air Force Space
Command).
User equipment: No single program executive officer;
Air Force Space and Missile Systems Center develops common user
equipment form factors, which can be used by all Services, to
production ready status. This provides an industrial base,
specifications, and standards required for the each of the Services to
buy what they need.
Separate Air Force components, which do not report to Space and Missile
Systems Center, develop systems with embedded GPS capabilities on Air
Force-owned aircraft, intercontinental ballistic missiles, vehicles,
hand-held devices, small diameter bomb, etc. For example, the Air Force
Electronic Systems Center (which reports to the Air Force Materiel
Command) develops GPS user equipment for command, control, and
communications systems.
Navy's GPS user equipment procurement is divided between three main
activities. Procurement of surface ship, submarine and select aircraft
is performed by the Command, Control, Communications, Computers, and
Intelligence Program Executive Office through its navigation program
office. Procurement of GPS user equipment for the majority of naval
aircraft is done by the Naval Air Systems Command's Common Avionics
program office. Due to their unique and limiting GPS user equipment
form factors, Navy GPS-aided munitions are procured by each respective
weapon's program office within the Naval Air Systems and Naval Sea
Systems Commands.
The Marine Corps Systems Command procures hand held and embedded GPS
user equipment for Marine Air Ground Task Force employment in ground
armored and unarmored vehicles, indirect fire weapons systems, radios,
and other systems. Marine Corps aircraft GPS user equipment is procured
by the Naval Air Systems Command.
Army components, for example the Office for Intelligence, Electronic
Warfare and Sensors, procure common GPS capabilities such as handheld
devices and embedded cards for tanks, aircraft, and the High Mobility
Multipurpose Wheeled Vehicles. Platforms are responsible for developing
unique GPS capabilities.
Source: GAO presentation of DOD data.
[End of figure]
Because different military services are involved in developing user
equipment for the weapon systems they own and operate, there are
separate budget, management, oversight, and leadership structures over
the space and ground control and the user equipment segments. As such,
there is no single authority responsible for synchronizing all the
procurements and fielding related to GPS. A 2008 U.S. Strategic Command
Functional Solutions Analysis, conducted to provide recommendations for
solutions to positioning, navigation, and timing gaps, noted that the
Air Force is responsible for developing and integrating military GPS
user equipment for select platforms, and that integration and testing
of these platforms is required to be complete so that the user
equipment is available for procurement when the military signal becomes
operational. However, this analysis showed no military service program
office commitment of resources for procuring military GPS user
equipment in service programming documents. Furthermore, DOD's
management attention has been focused on delivering space capabilities.
Only recently has DOD begun to shift its focus by recognizing that the
user equipment segment needs to play an equal role in the overall GPS
synchronization effort.
Efforts to Speed up Delivery of User Equipment Face Obstacles:
There have been various recommendations to accelerate the fielding of
modernized military user equipment, though there are obstacles in the
way of implementation. In October 2005, the Defense Science Board
[Footnote 20] recommended that DOD initiate an aggressive program to
introduce antijam enhancements as soon as possible. In August 2006, OSD
issued a GPS User Equipment Development and Procurement Policy, which
mandated that certain equipment categories have the modernized GPS user
equipment by the time the 24th military code satellite is declared
operational. In June 2007, representatives from the Combatant Commands,
U.S. Strategic Command, and U.S. Joint Forces Command requested that an
aggressive schedule be established for all GPS segments to achieve
military code initial operational capability by fiscal year 2013. In
March 2008, the Joint Requirements Oversight Council recommended that
the Air Force adjust the development and acquisition of the modernized
GPS user equipment to ensure that warfighters can use space-based
capabilities. Recommendations included amending programmatic schedules
and funding profiles to incorporate military code capabilities at or
before the initial operational capability date.
To accelerate the delivery of the new user equipment, the Air Force
increased the user equipment budget by $272 million for fiscal years
2009 through 2011. In the conference reports accompanying the
Department of Defense Appropriation Act for Fiscal Year 2008 and the
National Defense Authorization Act for Fiscal Year 2008, conferees
recommended an additional $63.2 million in funding for GPS user
equipment. However, the additional funds will not speed up development
of the new user equipment to a large extent, because the program office
is experiencing technical issues in developing the prototype cards. The
major technical issue is with the difficulty in moving to a new
security architecture, Protection of Navigation, which will provide
information assurance.
According to a GPS program office official, OSD, the Air Staff, U.S.
Strategic Command, Air Force Space Command, and the GPS program office
are looking at ways to get some of the modernized military user
equipment to the field sooner. However, there are challenges with this
approach, particularly because certain security requirements--
antispoof,[Footnote 21] antijam, and antitamper--should be met before
user equipment can be fielded in conflict situations. According to an
official at the GPS program office, meeting these security requirements
is proving to be technically challenging, and attempting this at an
accelerated rate is risky.
Prudent Steps Taken so GPS Can Meet Broader Needs but Challenges Exist
in Coordinating Requirements and Ensuring Compatibility:
GPS has produced dramatic economic and security improvements both for
the United States and globally. Ensuring that it can continue to do so
is extremely challenging given competing interests, the span of
government and commercial organizations involved with GPS, and the
criticality of GPS to national and homeland security and the economy.
On the one hand, DOD must ensure military requirements receive top
priority and the program stays executable. In doing so, it must ensure
that the program is not encumbered by requirements that could disrupt
development, design, and production of satellites. On the other hand,
there are clearly other enhancements that could be made to GPS
satellites that could serve a variety of vital missions--particularly
because of the coverage GPS satellites provide--and there is an
expressed desire for GPS to serve as the world's preeminent
positioning, navigation, and timing system. In addition, while the
United States is challenged to deliver GPS on a tight schedule, other
countries are designing and developing systems that provide the same or
enhanced capabilities. Ensuring that these capabilities can be
leveraged without compromising national security or the preeminence of
GPS is also a delicate balancing act that requires close cooperation
between DOD, the Department of State, and other institutions.
Because of the scale and number of organizations involved in maximizing
GPS, we did not undertake a full-scale review of requirements and
coordination processes. However, we reviewed documents supporting these
processes and interviewed a variety of officials to obtain views on its
effectiveness. While there is a consensus that DOD and other federal
organizations involved with GPS have taken prudent steps to manage
requirements and optimize GPS use, we also identified challenges in the
areas of ensuring civilian requirements can be met and ensuring that
GPS is compatible with other new, potentially competing global space-
based positioning, navigation, and timing systems.
The Process for Approving GPS Civil Requirements Is Rigorous but
Untested:
The 2004 U.S. Space-Based Positioning, Navigation and Timing (PNT)
policy provides guidance for civil involvement in the development of
requirements for the modernization of GPS capabilities and the
requirements process includes an entry point for civil requirements.
This entry point is the Interagency Forum for Operational Requirements
(IFOR), working groups consisting of a civil and a military panel. The
IFOR receives proposed GPS requirements from civil agencies and assists
in developing and validating them. From this point, the proposed
requirement follows a DOD and civil path to validation with involvement
from various interagency boards and councils. Figure 8 illustrates this
formal process for submitting, considering, and validating civil GPS
requirements.
Figure 8: Interagency Process for Submitting and Validating GPS
Requirements:
[Refer to PDF for image: illustration]
Top level:
* Civil Department/Agency Requirements Processes (civil panel):
* Interagency Forum for Operational Requirements:
* Service‘s and Defense Agency Requirements Processes (military panel):
Next levels, civil panel:
From Civil Department/Agency Requirements Processes, there is a formal
coordination path to:
DOT Extended Positioning/Navigation Working Group: Coordinate and
adjudicate civil requirements. Formal coordination path to:
DOT Extended Positioning/Navigation Executive Committee: Approve civil
requirements. Formal coordination path to:
Validated civil requirements.
An adjudication path for issues that cannot be resolved at a lower
level has been established from the DOT Extended Positioning/Navigation
Working Group to Interagency Requirements Board;
An adjudication path for issues that cannot be resolved at a lower
level has been established from the Interagency Requirements Board to
the DOT Extended Positioning/Navigation Executive Committee, and from
that committee to the Interagency Requirements Oversight Council.
Interagency Requirements Oversight Council: Formal coordination path
to: Validated interagency requirements.
Next levels, military panel:
From Service‘s and Defense Agency Requirements Processes: Formal
coordination path to: Net-centric Functional Capabilities Board:
Coordinate and adjudicate military requirements.
Net-centric Functional Capabilities Board: Formal coordination path to:
Joint Capabilities Board: Coordinate and adjudicate military
requirements.
Joint Capabilities Board: Formal coordination path to: Joint
Requirements Oversight council: Approve military requirements.
Joint Requirements Oversight council: Formal coordination path to:
Validated military requirements.
An adjudication path for issues that cannot be resolved at a lower
level has been established from the Joint Capabilities Board to
Interagency Requirements Board;
An adjudication path for issues that cannot be resolved at a lower
level has been established from the Interagency Requirements Board to
the Joint Requirements Oversight council, and from that committee to
the Interagency Requirements Oversight Council.
Interagency Requirements Oversight Council: Formal coordination path
to: Validated interagency requirements.
Source: GAO presentation of Department of Transportation and U.S. Air
Force data.
[End of figure]
While the process for approving civil requirements on GPS has existed
since 2001, DOD and civil agencies consider it rigorous but relatively
untested because no civil unique requirements have completed the
initial step in the process. Civil agencies have submitted two proposed
requirements to the process; however, these requirements are not
directly related to the GPS mission. Instead, they would add hardware
to the GPS satellites and thus are considered secondary mission
requirements. However, according to civil agencies, the analyses and
documentation called for under the process are confusing and time-
consuming.
While GPS remains critical to national security and military
operations, government policy calls for GPS planning to consider
integration of civil requirements for the civilian infrastructure. The
process for considering civil GPS requirements is intended to maintain
fiscal discipline by ensuring only critical needs are funded and
developed. Specifically, the process requires that civil agencies
internally identify and validate their proposed requirements, and
conduct cost, risk, and performance analyses. Our past work has shown
that requirements add-ons are a major source of acquisition
instability. In this case, the formal process also requires that the
agency proposing the requirement pay the costs associated with adding
it to the GPS III satellites, thereby forcing agencies to separate
their wants from needs.
Civil Agencies Find the GPS Requirements Process Confusing:
According to the civil agencies that have proposed GPS requirements,
the formal requirements approval process is confusing and time-
consuming. Specifically, they stated that DOD's documentary and
analysis standards are new to civil agencies and therefore difficult
and time-consuming for them to manage. Some agencies have reported that
it is costly for them to pay for the more detailed supporting analyses
requested by DOD. For example, one civil agency had to withdraw and
resubmit a proposal for new GPS requirements because it lacked
necessary information, including a cost-benefit analysis. Furthermore,
civil agencies' submitted requirements have necessitated that DOD
perform further studies on compatibility and integration issues to
ensure that the proposed requirements will not adversely affect the
primary GPS mission.
The two civil requirements that have entered the requirements process
are the Distress Alerting Satellite System (DASS) and the geodetic
[Footnote 22] requirement implemented by Satellite Laser Ranging (SLR).
Both are joint civil and military mission requirements and would be
potential secondary payloads on GPS. DASS is an electronic unit that
will receive beacon signals identifying a distressed individual's
location and transmit this location data to emergency responders. The
SLR laser retroreflector, which weighs less than 7 pounds, is being
considered for inclusion starting with increment IIIB satellites.
Scientists would aim a laser to the reflector to more precisely
determine the satellite's position, ultimately allowing for more
precise measurements on the ground. This SLR capability would support
users who need to make very accurate measurements for scientific
applications.
* Distress Alerting Satellite System: The Coast Guard submitted the
DASS requirement to the IFOR in 2003. Early in the review process, a
debate on whether DASS was a civil or military requirement ensued. The
IFOR decided to have military and civil panels review the requirement
and resubmit it through the Joint Capabilities Integration and
Development System (JCIDS) process. It took a total of 5 years to
resolve the debate and prepare and resubmit the package. In July 2008,
the civil agencies submitted DASS requirements and an analysis of
alternatives to the IFOR for review. To date, a decision has not yet
been made as to if and when the capability will be inserted on GPS
satellites.
* Satellite Laser Ranging: In April 2007, NASA submitted the SLR
requirements package along with an analysis of alternatives to the
IFOR. The IFOR officially accepted the SLR package into the IFOR
process in August of that year. However, in June 2008, DOD opposed
implementation of the SLR capability due to integration and
compatibility concerns with the GPS satellites. A joint Air Force and
NASA working group was established to resolve the integration and
compatibility issues and report back to the IFOR by June 2009 prior to
moving the requirement from the IFOR into the JCIDS process.
DASS supporters have stated that the GPS constellation is the ideal
platform for search and rescue capabilities. The current search and
rescue capability is expected to degrade by 2017 and completely fail by
2020. More urgently, supporters say that the Canadian government's
offer to provide DASS hardware at a $90 million cost savings to the
United States must be acted upon by August 2009 or Canada may provide
this component to a developing foreign satellite navigation system. The
SLR capability, until recently, existed on two GPS satellites. One
satellite was decommissioned, and hence according to NASA does not meet
its or other civil agencies' needs to perform scientific and geodetic
applications. According to NASA, the SLR would need to be implemented
on most of the GPS constellation to meet geodetic requirements for
science and other user requirements. If the DOD does not include DASS
and SLR on GPS satellites, U.S. users of these capabilities may be
dependent on foreign systems which already include, or have plans to
include, both DASS-like and SLR capabilities in their satellite
navigation systems.
Coordinating GPS Activities with the International Community also
Presents Challenges:
The U.S. government--specifically the State Department--is faced with
challenges in ensuring GPS is compatible and interoperable with other
new, potentially competing global space-based positioning, navigation,
and timing systems. While the U.S. government has engaged a number of
other countries and international organizations in cooperative
discussions, only one legally binding agreement has been established.
Furthermore, some U.S. manufacturers of GPS receivers stated that
European Union manufacturers may have a competitive advantage over U.S.
companies with respect to the manufacture and sale of Galileo-capable
receivers, though officials with the European Commission disagree. In
addition, Department of State officials have expressed concerns over
the limited number of technical experts available to support activities
under these cooperative arrangements. Without these resources,
officials are concerned that it may be difficult to continue to ensure
the compatibility and interoperability of foreign systems.
Joint Statements of Cooperation Made and One Agreement Established:
The United States has made joint statements of cooperation with
Australia, India, Japan, and Russia to promote compatibility and
interoperability and mutual interests regarding the civil use of GPS
and its augmentations[Footnote 23] and established an executive
agreement with the European Community (see table 4 for a list of types
of cooperative arrangements with other countries).[Footnote 24] The
joint statements and executive agreement were sought to avoid
interference with each others' systems, and to facilitate the pursuit
of common civil signals. Under the national space-based PNT policy, it
is the Department of State's role to promote the civil aspects of GPS
and its augmentation services and standards with foreign governments
and other international organizations. The Department of State leads
negotiations with foreign governments and international organizations
regarding civil and, as appropriate, military space-based PNT matters
including, but not limited to, coordinating interagency review of
international agreements with foreign governments and international
organizations regarding the planning, operation, management, and or use
of the GPS and its augmentations. While most of the cooperative
arrangements are joint statements that express the parties' intent to
cooperate on GPS-related activities, the United States and the European
Commission have established an executive agreement that is considered
binding under international law.
Table 4: U.S. Cooperation with Foreign Entities on Satellite
Navigation:
Country: Japan;
Cooperative arrangement/effective dates: Executive agreement: [Empty];
Cooperative arrangement/effective dates: Joint statement: [Check];
Cooperative arrangement/effective dates: No agreement: [Empty];
Cooperative arrangement/effective dates: Date signed: 1998.
Country: EU;
Cooperative arrangement/effective dates: Executive agreement: [Check];
Cooperative arrangement/effective dates: Joint statement: [Empty];
Cooperative arrangement/effective dates: No agreement: [Empty];
Cooperative arrangement/effective dates: Date signed: 2004.
Country: Russia;
Cooperative arrangement/effective dates: Executive agreement: [Empty];
Cooperative arrangement/effective dates: Joint statement: [Check];
Cooperative arrangement/effective dates: No agreement: [Empty];
Cooperative arrangement/effective dates: Date signed: 2004.
Country: Australia;
Cooperative arrangement/effective dates: Executive agreement: [Empty];
Cooperative arrangement/effective dates: Joint statement: [Check];
Cooperative arrangement/effective dates: No agreement: [Empty];
Cooperative arrangement/effective dates: Date signed: 2007.
Country: India;
Cooperative arrangement/effective dates: Executive agreement: [Empty];
Cooperative arrangement/effective dates: Joint statement: [Check];
Cooperative arrangement/effective dates: No agreement: [Empty];
Cooperative arrangement/effective dates: Date signed: 2007.
Country: China;
Cooperative arrangement/effective dates: Executive agreement: [Empty];
Cooperative arrangement/effective dates: Joint statement: [Empty];
Cooperative arrangement/effective dates: No agreement: [Check];
Cooperative arrangement/effective dates: Date signed: N/A.
Source: GAO analysis of U.S. Department of State data.
[End of table]
U.S. and European Commission Working to Address Concerns Regarding
Access to Galileo Information:
According to the executive agreement with the European Community,
subject to applicable export controls, the United States and the
European Commission are to make sufficient information concerning their
respective civil satellite-based signals and augmentations publicly
available on a nondiscriminatory basis, to ensure equal opportunity for
persons who seek to use these signals, manufacture equipment to use
these signals, or provide value-added services which use these signals.
In 2006, the European Commission publicly released draft technical
specifications for its open service. The draft document requests
manufacturers to obtain a commercial license from the European
Commission to sell and import products designed to work with the
European satellite navigation system, Galileo. While this licensing
requirement applies to all manufacturers, some U.S. companies stated
that some foreign user equipment manufacturers who are members of the
Galileo consortia may have an unfair advantage over U.S. companies.
This is because the Galileo consortia currently have access to testing
hardware and may be able to introduce their products more quickly into
the marketplace once they are granted a commercial license.
Officials with the European Commission told us that they do not believe
the license restrictions or the knowledge gained from testing the
Galileo systems are discriminatory. They further stated that the
restrictions in obtaining a commercial license to sell user equipment
apply to all companies, not just U.S. companies and they have not yet
issued licenses to any company. In the meantime, a U.S. and European
Commission working group on trade and civil applications is discussing
the licensing issue.
However, U.S. firms have raised concerns to the Department of Commerce
(Commerce) on the lack of information from the European Commission
relating to the process for obtaining a license to sell Galileo
equipment. According to Commerce, U.S. firms have asserted that they
are not aware of how, where, or when to apply for such a license,
despite repeated inquiries to the U.S.-European Commission trade
working group and direct contacts with European Commission officials--
and the timeline for the licensing process is unknown. Commerce further
noted that U.S. manufacturers wanting to enter the Galileo market are
hesitant to invest in technology that is not officially licensed and
that could possibly be banned from sale. It takes industry 18 to 24
months to develop a market-ready receiver, and the first operational
Galileo satellite is scheduled for launch in 2010. U.S. firms are
concerned they will not have their products ready by that time and will
lose their market share to European companies with inside access to
technology and/or licensing information.
State Officials Believe International Efforts Lack Dedicated Resources:
According to Department of State officials, the department lacks
dedicated technical expertise to monitor international activities. The
Department of State relies on a small pool of experts from DOD and the
seven civil agencies represented on the National Executive Committee
for Space-Based PNT. These experts are often in high demand because
they work on other GPS-related activities and in some cases have other
assigned duties that are unrelated to GPS. According to the Department
of State, in many cases these experts and those in other agencies must
continually justify to their managers that their attendance at
international meetings is important. Given the progress made in working
with foreign governments to establish arrangements, share information,
and ensure compatibility and interoperability with GPS, Department of
State officials would like DOD and civil agencies to dedicate funding
and staff positions to international activities accompanied by a
sustained level of senior management support and understanding of the
importance of these activities. Without an expanded pool of technical
expertise and related resources, Department of State officials stated
they are concerned that ongoing international efforts to ensure
compatibility of foreign systems with GPS could be jeopardized.
Conclusions:
GPS has enabled transformations in military, civil, other government,
and commercial operations and has become part of the critical
infrastructure serving national and international communities. Clearly,
the United States cannot afford to see its GPS capabilities decrease
below its requirement, and optimally, it would stay preeminent. Over
the past decade, however, the program has experienced cost increases
and schedule delays. While the Air Force is making a concerted effort
to address acquisition problems, there is still considerable risk that
satellites will not be delivered on time, leading to gaps in
capability. Focused attention and oversight are needed to ensure the
program stays on track and is adequately resourced, that unanticipated
problems are quickly discovered and resolved, and that all communities
involved with GPS are aware of and positioned to address potential gaps
in service. But this is difficult to achieve given diffuse
responsibility over various aspects of the GPS acquisition program.
Moreover, disconnects between the space, ground control, and user
equipment components have significantly lessened the military's ability
to take advantage of enhancements, particularly as they relate to
assuring the continuity of service during military engagements. Without
more concentrated leadership attention, such disconnects could worsen,
particularly since (1) both the ground control and user equipment
programs have been subject to funding shifts to pay for problems
affecting the satellite segment, and (2) user equipment programs are
executed by separate entities over which no one single person has
authority. Lastly, ensuring that GPS can continue to produce dramatic
improvements to civil agencies' applications, calls for any weaknesses
that are identified in the civil agency GPS requirements process to be
addressed.
Recommendations for Executive Action:
Because of the criticality of the GPS system and potential delays, and
given the importance of GPS to the civil community, we are making the
following recommendations.
* We recommend that the Secretary of Defense appoint a single authority
to oversee the development of the GPS system, including DOD space,
ground control, and user equipment assets, to ensure that the program
is well executed and resourced and that potential disruptions are
minimized. The appointee should have authority to ensure DOD space,
ground control, and user equipment are synchronized to the maximum
extent practicable; and coordinate with the existing positioning,
navigation, and timing infrastructure to assess and minimize potential
service disruptions should the satellite constellation decrease in size
for an extended period of time.
* We recommend that the Secretaries of Defense and Transportation, as
the co-chairs of the National Executive Committee for Space-Based
Positioning, Navigation and Timing, address, if weaknesses are found,
civil agency concerns for developing requirements, and determine
mechanisms for improving collaboration and decision making and
strengthening civil agency participation.
Agency Comments and Our Evaluation:
DOD concurred with our first recommendation to appoint a single
authority to oversee the development of the GPS system, including
space, ground control, and user equipment assets, to ensure that the
program is well executed, resourced, and that potential disruptions are
minimized. DOD stated that it has recognized the importance of
centralizing authority to oversee the continuing synchronized evolution
of the GPS. According to DOD, the Deputy Secretary of Defense has
reaffirmed that the Assistant Secretary of Defense for Networks and
Information Integration (ASD NII)) is designated with authority and
responsibility for all aspects of the GPS. DOD further stated that the
U.S. Air Force is the single acquisition agent with responsibility for
synchronized modernization of GPS space, ground control, and military
user equipment.
In concurring with our recommendation on appointing a single authority
to oversee the development of the GPS system, DOD asserts that ASD NII
is designated with authority and responsibility for all aspects of GPS,
and that the Air Force is the single acquisition agent responsible for
synchronizing GPS segments. In addition, responsibility for acquiring
GPS military user equipment acquisitions falls under various officials
within the military services. We agree that given the diversity of
platforms and equipment variations involved, it would not be realistic
for the Air Force to unilaterally produce a "one-size-fits-all"
solution. However, this does not obviate the need for a single
authority to oversee the development of all GPS military user equipment
to better ensure greater coordination with deployed satellite
capabilities. Without an approach that enables a single individual to
make resource decisions and maintain visibility over progress, DOD is
at risk of facing the same issues in synchronizing the delivery of GPS
assets and wasting capability that will be available in space but not
on the ground. In addition, DOD may still want to consider establishing
a means by which progress in developing the satellites and ground
equipment receives attention from the highest levels of leadership that
is the Secretary and perhaps the National Security Council, given the
criticality of GPS to the warfighter and the nation, and the risks
associated with not meeting schedule goals.
DOD concurred with our second recommendation to address, if weaknesses
are found, civil agency concerns for developing requirements and
determine mechanisms for improving collaboration and decision making,
and strengthening civil agency participation. DOD acknowledged that it
employs a rigorous requirements process and is aware of the frustration
civil agencies face when using this process. DOD further indicated that
it worked to put in place an interagency requirements plan, and is
currently in the process of jointly coordinating the Charter for an
Interagency Forum for Operational Requirements to provide venues to
identify, discuss, and validate civil or dual-use GPS requirements.
Finally, DOD noted that it will continue to seek ways to improve civil
agency understanding of the DOD requirements process and work to
strengthen civil agency participation. We support DOD's efforts to
inform and educate other civil agencies on the requirements process. As
it undertakes these efforts, DOD should ensure that it is taking a more
active role in directly communicating with civil agencies to more
precisely identify concerns or weaknesses in the requirements process.
The full text of DOD's comments may be found in appendix IV. We also
received technical comments from the other departments and NASA, which
we incorporated where appropriate.
As agreed with your offices, unless you publicly announce the contents
of this report earlier, we plan no further distribution of it until 8
days from the report date. At that time, we will send copies of this
report to the Secretaries of Defense, Agriculture, Commerce, Homeland
Security, Interior, State, and Transportation; the National Aeronautics
and Space Administration; and interested congressional committees. The
report will also be available at no charge on the GAO Web site at
[hyperlink, http://www.gao.gov].
If you have any questions about this report or need additional
information, please contact me at (202) 512-4841 or chaplainc@gao.gov.
Contact points for our Offices of Congressional Relations and Public
Affairs may be found on the last page of this report. The major
contributors are listed in appendix V.
Signed by:
Cristina T. Chaplain:
Director:
Acquisition and Sourcing Management:
[End of section]
Appendix I: Scope and Methodology:
To assess the Global Positioning System (GPS) satellite, ground
control, and user equipment acquisition programs and determine whether
GPS capabilities are being synchronized, we reviewed and analyzed
program plans and documentation related to cost, schedule,
requirements, program direction, and satellite constellation
sustainment, and compared programmatic data to GAO's criteria compiled
over the last 12 years for best practices in system development. We
also interviewed officials from Air Force Space and Missile Systems
Center GPS program office; Air Force Space Command; Office of the Joint
Chiefs of Staff; Office of the Undersecretary of Defense for
Acquisition, Technology, and Logistics; Assistant Secretary of Defense
Office of Networks and Information Integration; United States Strategic
Command; 2nd Space Operations Squadron; and the services.
To determine the extent to which the Air Force had effectively
developed and maintained the GPS IIIA integrated master schedule, we
reviewed the program's schedule estimates and compared them with
relevant best practices to determine the extent to which they reflects
key estimating practices that are fundamental to having a reliable
schedule. In doing so, we interviewed GPS program officials to discuss
their use of best practices in creating the program's current schedule.
To assess the status of the GPS constellation, we interviewed officials
from the Air Force Space and Missile Systems Center GPS program office,
Air Force Space Command, and the 2nd Space Operations Squadron. To
assess the risks that a delay in the acquisition and fielding of GPS
III satellites could result in the GPS constellation falling below the
24 satellites required by the standard positioning service and precise
positioning service performance standards, we obtained information from
the Air Force predicting the reliability for 77 GPS satellites--each of
the 31 current (on-orbit) and 46 future GPS satellites--as a function
of time. Each satellite's total reliability curve defines the
probability that the satellite will still be operational at a given
time in the future. It is generated from the product of two reliability
curves--a wear-out reliability curve defined by the cumulative normal
distribution, and a random reliability curve defined by the cumulative
Weibull distribution. For each of the 77 satellites, we obtained the
two parameters defining the cumulative normal distribution, and the two
parameters defining the cumulative Weibull distribution. For each of
the 46 unlaunched satellites, we also obtained a parameter defining its
probability of successful launch, and its current scheduled launch
date. The 46 unlaunched satellites include 2 IIR-M satellites,[Footnote
25] 12 IIF satellites, 8 IIIA satellites, 8 IIIB satellites, and 16
IIIC satellites; launch of the final IIIC satellite is scheduled for
March 2023. Using this information, we generated overall reliability
curves for each of the 77 GPS satellites. We discussed with Air Force
and Aerospace Corporation representatives, in general terms, how each
satellite's normal and Weibull parameters were calculated. However, we
did not analyze any of the data used to calculate these parameters.
Using the reliability curves for each of the 77 GPS satellites, we
developed a Monte Carlo simulation[Footnote 26] to predict the
probability that at least a given number of satellites would be
operational as a function of time, based on the GPS launch schedule
approved in March 2009. We conducted several runs of our simulation--
each run consisting of 10,000 trials--and generated "sawtoothed" curves
depicting the probability that at least 21, 24, 27, and 30 satellites
would still be operational as a function of time. We compared the
results for a 24-satellite constellation with a similar Monte Carlo
simulation that the Aerospace Corporation performed for the Air Force.
We confirmed that our simulation produces results that are within about
2 percent of the Aerospace Corporation's results for all times between
October 2008 and April 2024. Using 10,000 trials per run, the results
of different runs of the same Monte Carlo simulation can vary by about
1 to 2 percent; consequently we concluded that we had successfully
replicated the Aerospace Corporation's results. We then used our Monte
Carlo simulation model to examine the impact of a 2-year delay in the
launch of all GPS III satellites. We moved each GPS III launch date
back by 2 years. We then reran the model and calculated new
probabilities that at least 18, 21, and 24 satellites would still be
operational as a function of time.
To assess impacts of a potential GPS service disruption on particular
types of military and civil GPS users, we interviewed numerous military
and civil GPS representatives and reviewed studies provided by civil
agencies.
To assess the coordination and collaboration among federal agencies and
the broader GPS community, and to determine the organization of the PNT
community, we analyzed documents from and conducted interviews with
officials in Washington, D.C. at the Office of the Assistant Secretary
of Defense for Networks and Information Integration; SAF/USA (Air Force
Directorate of Space Acquisitions); National Aeronautics and Space
Administration; the Departments of Transportation, State, Commerce, and
Homeland Security; the Space-Based National PNT Coordination Office;
and the U.S. GPS Industry Council. We also interviewed a private sector
GPS expert at Stanford University, and GPS industry representatives. To
analyze how the U.S. government coordinates with foreign countries on
GNSS (Global Navigation Satellite Systems), we met with representatives
of and reviewed documents from the U.S. Department of State and
European Space Agency (ESA) in Washington, D.C. To obtain information
on efforts by Australia, China, Japan, and Russia to develop GNSS, we
met with Department of State officials, reviewed materials provided by
these countries' representatives at GNSS conferences, and consulted the
official government space agency Web sites. We also traveled to Europe
to meet with experts in satellite navigation at the European Space
Agency, French Space Agency (CNES), European Commission Directorate-
General for Energy and Transport Satellite Navigation Unit, and
European GNSS industry experts. In addition, we attended a conference
in Berlin, Germany to learn about international coordination on PNT
systems and applications.
We conducted this performance audit from October 2007 to April 2009 in
accordance with generally accepted government auditing standards. Those
standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe that
the evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives.
[End of section]
Appendix II: International Global Satellite Navigation Systems:
In addition to the Global Positioning System (GPS), there are other
space-based global navigation satellite systems (GNSS) in operation and
in development. Russia has a system, GLONASS (Global Navigation
Satellite System). There are currently 20 GLONASS satellites in orbit,
and the Russians expect to have a full constellation of 24 satellites
in orbit by 2010 and ultimately to expand to a 30-satellite
constellation. The European Union (EU) is developing its own GNSS
program, Galileo. Originally started as a public-private partnership,
the program now is completely funded by the public sector. The EU has 2
test satellites in orbit now, and plans to have a 27-satellite
constellation with 3 spares by 2013. China also is in the process of
developing its own GNSS, Compass (also called Beidou). China currently
has 3 satellites in orbit, and plans to increase the constellation for
coverage of the Asia-Pacific region by 2010 and for worldwide coverage
by 2015. Table 5 lists the non-U.S. global navigation satellite systems
currently in development.
Table 5: Non-U.S. Global Navigation Satellite Systems Currently in
Development:
System name: Galileo;
Country: European Union;
Number of active satellites: 2 test satellites;
Number of planned satellites: 27; [Empty];
Planned date of full operation: 2013;
Interoperable signals: Interoperable L1C signal.
System name: GLONASS;
Country: Russia;
Number of active satellites: 20;
Number of planned satellites: 30; [Empty];
Planned date of full operation: 2011;
Interoperable signals: Interoperable L1C signal.
System name: Compass/Beidou;
Country: China;
Number of active satellites: 3;
Number of planned satellites: 35;
Planned date of full operation: Regional coverage in 2010;
Interoperable signals: Compatible and interoperable with GPS, no
broadcast on L1C at this time.
Source: GAO analysis based on information from foreign program
presentations.
[End of table]
[End of section]
Appendix III: Cooperation Between U.S. and Foreign Entities:
During 2007, the Department of State signed joint statements of
cooperation in the use of the Global Positioning System (GPS) with
Australia and India. The Australia joint statement expresses the
parties' intention to promote interoperability between GPS and
Australia's Ground-based Regional Augmentation System and Ground Based
Augmentation System. The India joint statement expressed the parties'
intention to promote GPS and India's GPS and GEO-Augmented Navigation
system. An executive agreement with the European Community and its
member states has been in effect since 2004 that expresses the
intention that GPS and Galileo will be interoperable at the user level
for the benefit of civil users around the world. This cooperation has
resulted in working groups that are reviewing technical, trade, and
security issues. The technical issues described in the executive
agreement involve GPS-Galileo radio frequency compatibility and
interoperability and the design and development of the next generation
of systems. For trade, a working group is determining how to maintain
nondiscriminatory trade practices in the global market for goods and
services related to space-based PNT, and a group was appointed to
review the security issues concerning GPS and Galileo.
The United States and Russia initiated cooperation in 2004, with the
parties expressing their intent to work together to maintain and
promote civil interoperability at the user level between GPS and
Russia's GLONASS system. Two working groups have been established to
address: (1) radio frequency compatibility and interoperability for
enhanced PNT and (2) technical interoperability between the search-and-
rescue capabilities planned for GPS and GLONASS.
The United States and Japan have had a relationship since signing a
joint statement in 1998. In the joint statement, the parties expressed
their intent to promote and facilitate civilian uses of GPS. Japan is
developing MTSAT-based Satellite Augmentation System (MSAS), a
geostationary satellite system similar to the U.S. Wide Area
Augmentation System. The United States and Japan most recently met in
November 2008 to discuss the civil use of GPS and Japan's MSAS and
Quasi-Zenith Satellite System.
[End of section]
Appendix IV: Comments from the Department of Defense:
Office Of The Assistant Secretary Of Defense:
Networks And Information Integration:
6000 Defense Pentagon:
Washington, DC 20301-6000:
April 24, 2009:
Ms. Christina Chaplain:
Director, Acquisition and Sourcing Management:
U. S. Government Accountability Office:
441 G Street, NW:
Washington, DC 20548:
Dear Ms. Chaplain:
This is the Department of Defense (DoD) response to the GAO draft
report, GAO-09-325, The Global Positioning System: Significant
Challenges in Sustaining and Upgrading Widely Used Capabilities, dated
March 12, 2009 (GAO Code 120696).
The Department fundamentally concurs with the findings and
recommendations expressed in the GAO report. However, factors relating
to the longevity of the Global Positioning System (GPS) program and the
complexity of its implementation across the range of military and
civilian users require that our concurrence be augmented by clarifying
comments, which have been provided separately.
GPS developmental satellites were initially launched over thirty years
ago. The system has evolved successfully through at least three
generations of spacecraft, ground control systems, and military user
equipment. During that time, GPS has become one of the most widely used
systems in the world for military and civilian positioning, navigation
and timing (PNT) purposes and sets the example for other nations
seeking to provide similar services.
In the United States, GPS is a fundamental enabler of national security
and economic infrastructures, enhancing efficiency and improving safety
and effectiveness of virtually all operations. As the cornerstone of
our National PNT Architecture, it is the centerpiece around which
future PNT services will evolve. The Department is fully aware of our
responsibility with respect to GPS and is committed to maintaining and
improving the services it provides. In that regard, DoD seeks the
support of the Congress in maintaining stability of GPS funding to
enable synchronized modernization of the next generation of GPS space,
ground control, and user equipment that is now underway.
We have determined that the report is unclassified and has been cleared
for open publication. Our point of contact for this review is Mr.
Raymond Swider, (703) 607-1122, raymond.swider@osd.mil.
Signed by: illegible, for:
Ronald C. Jost:
Deputy Assistant Secretary of Defense:
(C3, Space & Spectrum):
Enclosure:
GAO Draft Report Dated March 12, 2009:
GAO-09-325 (GAO CODE 120696):
’The Global Positioning System: Significant Challenges In Sustaining
And Upgrading Widely Used Capabilities“
Department Of Defense Comments To The GAO Recommendations:
Recommendation 1: The GAO recommends that the Secretary of Defense
appoint a single authority to oversee the development of the Global
Positioning System (GPS) system, including space, ground, and user
assets, to ensure that the program is well executed and resourced and
that potential disruptions are minimized. (p. 43/GAO Draft Report)
DOD Response: Concur with comment. The Department has recognized the
importance of centralizing authority to oversee the continuing
synchronized evolution of the GPS. To that end, the Deputy Secretary of
Defense has reaffirmed that the Assistant Secretary of Defense for
Networks and Information Integration (ASD(NII)) is the Department‘s
Principal Staff Assistant to oversee Positioning, Navigation, and
Timing, and, specifically, is designated with authority and
responsibility for all aspects of the Global Position System (GPS).
This designation is contained in Department of Defense Directive (DoDD)
4650.05, issued on February 19, 2008. A formal Department of Defense
Instruction is now in final coordination to further define the
oversight processes to be employed in executing DoDD 4650.05, and
completion is expected by May 2009. Further, under oversight of the
ASD(NII), the U.S. Air Force is the single acquisition agent with
responsibility for synchronized modernization of GPS space, ground
control, and military user equipment. The Air Force acquires and
operates the GPS space and control segments and provides the
fundamental system design and security requirements necessary for
acquisition of GPS user equipment and applications in support of
diverse missions across the Department. Given the diversity of
platforms, and equipment form factors involved, it is impossible for
the Air Force to unilaterally produce a ’one-size-fits-all“ solution
applicable to all DoD missions.
Recommendation 2: The GAO recommends that Secretary of Defense, as one
of the Position Navigation and Timing executive committee co-chairs,
address, if weaknesses are found, civil agency concerns for developing
requirements and determine mechanisms for improving collaboration and
decision making and strengthening civil agency participation. (p.
43/GAO Draft Report)
DOD Response: Concur with comment. The Department is aware that we
employ a rigorous requirements process in support of our extensive
operational and acquisition responsibilities and that the process is a
source of frustration for civil agencies without similar processes in
place. In an effort to address the issue, we have worked with the civil
agencies to put in place a GPS Interagency Requirements Plan, jointly
approved by the Vice Chairman of the Joint Chiefs of Staff, who is in
charge of our process, and the Department of Transportation (DOT),
acting on behalf of all civil agencies. Further, we are now in the
process of jointly coordinating the Charter for an Interagency Forum
for Operational Requirements (IFOR) to provide meeting venues to
identify, discuss, and validate civil or dual use GPS requirements for
inclusion in the DoD GPS acquisition process. Finally, we sponsor
educational outreach opportunities for civil agencies to become more
fully acquainted with the DoD requirements process, including a day-
long ’Requirements Process Summit“ jointly conducted by the Joint Staff
and DOT on April 29, 2008. We will continue to seek ways to improve
civil agency understanding of the DoD requirements process and work to
strengthen civil agency participation.
[End of section]
Appendix V: GAO Contacts and Staff Acknowledgments:
GAO Contact:
Cristina T. Chaplain (202) 512-4841 or chaplainc@gao.gov:
Staff Acknowledgments:
In addition to the contact named above, key contributors to this report
were Art Gallegos (Assistant Director), Greg Campbell, Jennifer Echard,
Maria Durant, Anne Hobson, Laura Hook, Sigrid McGinty, Angela
Pleasants, Jay Tallon, Hai Tran, and Alyssa Weir.
[End of section]
Related GAO Products:
Best Practices: Increased Focus on Requirements and Oversight Needed to
Improve DOD's Acquisition Environment and Weapon System Quality.
[hyperlink, http://www.gao.gov/products/GAO-08-294]. Washington, D.C.:
February 1, 2008.
Best Practices: An Integrated Portfolio Management Approach to Weapon
System Investments Could Improve DOD's Acquisition Outcomes.
[hyperlink, http://www.gao.gov/products/GAO-07-388]. Washington, D.C.:
March 30, 2007.
Best Practices: Stronger Practices Needed to Improve DOD Technology
Transition Processes. [hyperlink,
http://www.gao.gov/products/GAO-06-883]. Washington, D.C.: September
14, 2006.
Best Practices: Better Support of Weapon System Program Managers Needed
to Improve Outcomes. [hyperlink,
http://www.gao.gov/products/GAO-06-110]. Washington, D.C.: November 1,
2005.
Best Practices: Setting Requirements Differently Could Reduce Weapon
Systems' Total Ownership Costs. [hyperlink,
http://www.gao.gov/products/GAO-03-57]. Washington, D.C.: February 11,
2003.
Best Practices: Capturing Design and Manufacturing Knowledge Early
Improves Acquisition Outcomes. [hyperlink,
http://www.gao.gov/products/GAO-02-701]. Washington, D.C.: July 15,
2002.
Best Practices: Better Matching of Needs and Resources Will Lead to
Better Weapon System Outcomes. [hyperlink,
http://www.gao.gov/products/GAO-01-288]. Washington, D.C.: March 8,
2001.
Best Practices: A More Constructive Test Approach Is Key to Better
Weapon System Outcomes. [hyperlink,
http://www.gao.gov/products/GAO/NSIAD-00-199]. Washington, D.C.: July
31, 2000.
Best Practices: DOD Training Can Do More to Help Weapon System Programs
Implement Best Practices. [hyperlink,
http://www.gao.gov/products/GAO/NSIAD-99-206]. Washington, D.C.: August
16, 1999.
Best Practices: Better Management of Technology Development Can Improve
Weapon System Outcomes. [hyperlink,
http://www.gao.gov/products/GAO/NSIAD-99-162]. Washington, D.C.: July
30, 1999.
Best Practices: Successful Application to Weapon Acquisition Requires
Changes in DOD's Environment. [hyperlink,
http://www.gao.gov/products/GAO/NSIAD-98-56]. Washington, D.C.:
February 24, 1998.
Best Practices: Commercial Quality Assurance Practices Offer
Improvements for DOD. [hyperlink,
http://www.gao.gov/products/GAO/NSIAD-96-162]. Washington, D.C.: August
26, 1996.
[End of section]
Footnotes:
[1] For a list of reports on best practices, see Related GAO Products
at the end of this report.
[2] GPS is augmented by ground-based or space-based navigation aids
that are maintained by individual departments and agencies to provide
users with improvements to the GPS navigation signal in terms of
accuracy, availability, and/or integrity needs.
[3] GAO, Space Acquisitions: Actions Needed to Expand and Sustain Use
of Best Practices, [hyperlink, http://www.gao.gov/products/GAO-07-730T]
(Washington, D.C.: Apr. 19, 2007).
[4] GAO, Best Practices: DOD Can Help Suppliers Contribute More to
Weapon System Programs, [hyperlink,
http://www.gao.gov/products/GAO/NSIAD-98-87] (Washington, D.C.: Mar.
17, 1998); Space Acquisitions: Major Space Programs Still at Risk for
Cost and Schedule Increases, [hyperlink,
http://www.gao.gov/products/GAO-08-552T] (Washington, D.C.: Mar. 4,
2008); and, Defense Acquisitions: Results of Annual Assessment of DOD
Weapon Programs, [hyperlink, http://www.gao.gov/products/GAO-08-674T]
(Washington, D.C.: Apr. 29, 2008).
[5] On July 31, 2004, the GPS program office became the GPS Wing, when
the Air Force's Space and Missile Systems Center reorganized and
renamed its organizations to mirror the traditional Air Force
structure.
[6] Earned value management (EVM) is a program management tool that
integrates the technical, cost, and schedule parameters of a contract.
During the planning phase, an integrated baseline is developed by time-
phasing budget resources for defined work. As work is performed and
measured against the baseline, the corresponding budget value is
"earned." Using this earned value metric, cost and schedule variances
can be determined and analyzed. EVM provides significant benefits to
both the government and the contractor. An EVM system is required on
all DOD space-program-related contracts meeting certain thresholds
unless waived by the DOD Space Milestone Decision Authority.
[7] The Defense Contract Management Agency (DCMA) is the DOD component
that works directly with defense suppliers to help ensure that DOD,
federal, and allied government supplies and services are delivered on
time, at projected cost, and meet all performance requirements.
[8] GAO, Space Acquisitions: Improvements Needed in Space Systems
Acquisitions and Keys to Achieving Them, [hyperlink,
http://www.gao.gov/products/GAO-06-626T] (Washington, D.C.: Apr. 6,
2006).
[9] GAO, Space Acquisitions: Major Space Programs Still at Risk for
Cost and Schedule Increases, [hyperlink,
http://www.gao.gov/products/GAO-08-552T] (Washington, D.C.: Mar. 4,
2008).
[10] [hyperlink, http://www.gao.gov/products/GAO-06-626T].
[11] Defense Science Board/Air Force Scientific Advisory Board Task
Force, Acquisition of National Security Space Programs, Office of the
Under Secretary of Defense for Acquisition, Technology, and Logistics
(Washington, D.C.: May 2003).
[12] Defense Science Board Task Force, The Future of the Global
Positioning System, Office of the Under Secretary of Defense for
Acquisition, Technology, and Logistics (Washington, D.C.: Oct. 28,
2005).
[13] Independent Assessment Panel on the Organization and Management of
National Security Space, Leadership, Management, and Organization for
National Security Space, Institute for Defense Analysis (Alexandria,
Va.: Jul. 15, 2008).
[14] Pub. L. No. 109-364 § 914.
[15] House Permanent Select Committee on Intelligence, Report on
Challenges and Recommendations for United States Overhead Architecture,
United States House of Representatives (Washington, D.C.: Oct. 3,
2008).
[16] The Program Objectives Memorandum (POM) is an annual memorandum
submitted to the Secretary of Defense by the DOD component heads, which
recommends the total resource requirements and programs within the
parameters of the Secretary of Defense's fiscal guidance. The POM is a
major document in the Planning, Programming, Budgeting and Execution
process, and the basis for the component budget estimates. The POM is
the principle programming document that details how a component
proposes to respond to assignments in the Strategic Planning Guidance
and Joint Programming Guidance and satisfy its assigned functions over
the Future Years Defense Program. The POM shows programmed needs 6
years hence (i.e., in fiscal year 2004, POM 2006-2011 was submitted).
[17] This availability standard establishes thresholds for both global
average and worst-case position dilution of precision (PDOP), a figure
of merit commonly used to quantify the "goodness" of user-to-GPS-
constellation geometry.
[18] Some users with more demanding requirements employ GPS
augmentation systems that mitigate this impact. For example, many
applications using augmentations such as Satellite-Based Augmentation
Systems (SBAS), which in the United States is the Wide Area
Augmentation System (WAAS), have increased tolerance to degraded
accuracy and availability when the constellation may be operating at
minimum committed levels of availability.
[19] Both performance standards assume an unobstructed view of the
entire sky except for 5 degrees above the local horizon.
[20] Defense Science Board Task Force, The Future of the Global
Positioning System, Office of the Under Secretary of Defense for
Acquisition, Technology, and Logistics (Washington, D.C.: Oct. 28,
2005).
[21] Antispoofing is a process of encrypting one of the codes broadcast
by the satellites. This prevents an enemy from predicting the code
sequence and using that prediction to generate a code that could be
used to deceive a GPS set. The set would believe the deception code to
be real and could falsely calculate its position.
[22] Geodetic refers to the use of geodesy for measurements. Geodesy is
the science of measuring and monitoring the size and shape of the
Earth.
[23] Augmentation systems are U.S. government global and regional
systems that are maintained by individual departments and agencies to
provide users with improvements to the GPS navigation signal in terms
of accuracy, availability, and/or integrity needs.
[24] Although China is developing a space-based positioning,
navigation, and timing system, the United States has not established a
formal bilateral relationship with China. For the purposes of this
report, "cooperative arrangements" is used to mean joint statements of
cooperation and executive agreements.
[25] We completed our analysis prior to the successful launch of the
first of these two IIR-M satellites on March 24, 2009.
[26] Monte Carlo simulation refers to a computer-based analysis that
uses probability distributions for key variables, selects random values
from each of the distributions simultaneously, and repeats the random
selection over and over. Rather than presenting a single outcome--such
as the mostly likely or average scenario--Monte Carlo simulations
produce a distribution of outcomes that reflect the probability
distributions of modeled uncertain variables.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: