Information Technology

Actions Needed to Fully Establish Program Management Capability for VA's Financial and Logistics Initiative Gao ID: GAO-10-40 October 26, 2009

Since 2005, the Department of Veterans Affairs (VA) has been undertaking an initiative to develop an integrated financial and asset management system known as the Financial and Logistics Integrated Technology Enterprise (FLITE). FLITE is the successor to an earlier initiative known as the Core Financial and Logistics System (CoreFLS) that the department undertook in 1998 and discontinued in 2004 because it failed to support VA's operations. In light of the past performance of CoreFLS and the Office of Management and Budget's designation of FLITE as high risk, GAO was asked to (1) determine the status of pilot system development and (2) evaluate key program management processes, including VA's efforts to institute effective human capital management, develop a reliable program cost estimate, use earned value management (a recognized means for measuring program progress), establish a realistic program schedule, employ effective requirements development and management, and perform independent verification and validation. To do so, GAO reviewed program documentation and interviewed relevant officials.

Contract award and performance of work tasks had been started for one of two planned pilot systems--the Strategic Asset Management system. However, as of mid-September, the project had fallen behind (by 2 months) and the contractor had missed the deadline for initiating and completing planned tasks and delivering work products such as a system security plan. In particular, the contractor had not started 11 of 34 tasks, including conducting a security assessment, and was behind schedule on 16 of the remaining 23 tasks, including analyzing business processes. Program officials generally attributed the delays to VA having insufficient program and acquisition staff to perform necessary activities associated with awarding and executing the pilot contract and to poor project management by the pilot system contractor. A second project--for the Integrated Financial Accounting System pilot--is expected to start in October 2009. VA has taken steps to institute effective management of FLITE; however, the department has not yet fully established capabilities needed to ensure that the program will be successfully implemented. Specifically, VA has (1) recently filled long-standing staff vacancies, and only one program office staff opening remains; (2) not developed a cost estimate that includes total program costs or reconciled its estimate with an independent estimate; (3) not performed key actions necessary for reliable earned value management; (4) not yet established a schedule that is reliable; (5) not identified all mandatory federal financial management system requirements and ensured that system requirements are based on business requirements; and (6) not addressed all of the findings of its independent verification and validation organization in a timely manner. Until VA reconciles its cost estimate, ensures compliance with earned value management system standards, establishes a reliable schedule, ensures all relevant federal and system requirements are identified and traceable, and addresses all independent verification and validation findings, it could continue to experience schedule delays and further increase its risk of not providing the financial and asset management capabilities that users need.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone:


GAO-10-40, Information Technology: Actions Needed to Fully Establish Program Management Capability for VA's Financial and Logistics Initiative This is the accessible text file for GAO report number GAO-10-40 entitled 'Information Technology: Actions Needed to Fully Establish Program Management Capability for VA's Financial and Logistics Initiative' which was released on December 1, 2009. This text file was formatted by the U.S. Government Accountability Office (GAO) to be accessible to users with visual impairments, as part of a longer term project to improve GAO products' accessibility. Every attempt has been made to maintain the structural and data integrity of the original printed product. Accessibility features, such as text descriptions of tables, consecutively numbered footnotes placed at the end of the file, and the text of agency comment letters, are provided but may not exactly duplicate the presentation or format of the printed version. The portable document format (PDF) file is an exact electronic replica of the printed version. We welcome your feedback. Please E-mail your comments regarding the contents or accessibility features of this document to Webmaster@gao.gov. This is a work of the U.S. government and is not subject to copyright protection in the United States. It may be reproduced and distributed in its entirety without further permission from GAO. Because this work may contain copyrighted images or other material, permission from the copyright holder may be necessary if you wish to reproduce this material separately. Report to the Committee on Veterans' Affairs, House of Representatives: United States Government Accountability Office: GAO: October 2009: Information Technology: Actions Needed to Fully Establish Program Management Capability for VA's Financial and Logistics Initiative: GAO Highlights: Highlights of GAO-10-40, a report to the Committee on Veterans' Affairs, House of Representatives. Why GAO Did This Study: Since 2005, the Department of Veterans Affairs (VA) has been undertaking an initiative to develop an integrated financial and asset management system known as the Financial and Logistics Integrated Technology Enterprise (FLITE). FLITE is the successor to an earlier initiative known as the Core Financial and Logistics System (CoreFLS) that the department undertook in 1998 and discontinued in 2004 because it failed to support VA‘s operations. In light of the past performance of CoreFLS and the Office of Management and Budget‘s designation of FLITE as high risk, GAO was asked to (1) determine the status of pilot system development and (2) evaluate key program management processes, including VA‘s efforts to institute effective human capital management, develop a reliable program cost estimate, use earned value management (a recognized means for measuring program progress), establish a realistic program schedule, employ effective requirements development and management, and perform independent verification and validation. To do so, GAO reviewed program documentation and interviewed relevant officials. What GAO Found: Contract award and performance of work tasks had been started for one of two planned pilot systems”the Strategic Asset Management system. However, as of mid-September, the project had fallen behind (by 2 months) and the contractor had missed the deadline for initiating and completing planned tasks and delivering work products such as a system security plan. In particular, the contractor had not started 11 of 34 tasks, including conducting a security assessment, and was behind schedule on 16 of the remaining 23 tasks, including analyzing business processes. Program officials generally attributed the delays to VA having insufficient program and acquisition staff to perform necessary activities associated with awarding and executing the pilot contract and to poor project management by the pilot system contractor. A second project”for the Integrated Financial Accounting System pilot”is expected to start in October 2009. VA has taken steps to institute effective management of FLITE; however, the department has not yet fully established capabilities needed to ensure that the program will be successfully implemented. Specifically, VA has: * recently filled long-standing staff vacancies, and only one program office staff opening remains; * not developed a cost estimate that includes total program costs or reconciled its estimate with an independent estimate; * not performed key actions necessary for reliable earned value management; * not yet established a schedule that is reliable; * not identified all mandatory federal financial management system requirements and ensured that system requirements are based on business requirements; and; * not addressed all of the findings of its independent verification and validation organization in a timely manner. Until VA reconciles its cost estimate, ensures compliance with earned value management system standards, establishes a reliable schedule, ensures all relevant federal and system requirements are identified and traceable, and addresses all independent verification and validation findings, it could continue to experience schedule delays and further increase its risk of not providing the financial and asset management capabilities that users need. What GAO Recommends: GAO is making recommendations aimed at improving program management. In written comments on a draft of this report, VA concurred with the recommendations and identified actions to address them. View [hyperlink, http://www.gao.gov/products/GAO-10-40] or key components. For more information, contact Valerie C. Melvin at (202) 512-6304 or melvinv@gao.gov. [End of section] Contents: Letter: Background: Pilot Project Is Behind Schedule: VA Has Recently Filled FLITE Program Staff Positions but Has Not Yet Fully Established Other Program Management Capabilities: Conclusions: Recommendations for Executive Action: Agency Comments and Our Evaluation: Appendix I: Objectives, Scope, and Methodology: Appendix II: Comments from the Department of Veterans Affairs: Appendix III: GAO Contacts and Staff Acknowledgments: Table: Table 1: Description of FLITE Program Office Entities and Supporting VA Organizations: Figures: Figure 1: Simplified View of FLITE Components: Figure 2: Relationship of VA's Oversight and Management Structure to FLITE Program: Figure 3: Simplified FLITE Program Structure and Supporting VA Organizations: Figure 4: FLITE Timeline: Abbreviations: ANSI: American National Standards Institute: CoreFLS: Core Financial and Logistics System: EIA: Electronic Industries Alliance: EVM earned value management: FLITE: Financial and Logistics Integrated Technology Enterprise: FMS: Financial Management System: FSIO: Financial Systems Integration Office: IFCAP: Integrated Funds Distribution, Control Point Activity, Accounting, and Procurement: IFAS: Integrated Financial Accounting System: IT: information technology: MQAS: Management Quality Assurance Service: OIG: Office of Inspector General: OMB: Office of Management and Budget: PDO: program director's office: PMO: program management office: SAM: Strategic Asset Management: SEI: Software Engineering Institute: SPAWAR: Space and Naval Warfare Systems Command: VA: Department of Veterans Affairs: [End of section] United States Government Accountability Office: Washington, DC 20548: October 26, 2009: The Honorable Bob Filner: Chairman: The Honorable Steve Buyer: Ranking Member: Committee on Veterans' Affairs: House of Representatives: Since 2005, the Department of Veterans Affairs (VA) has been undertaking an initiative to develop an integrated financial management and information system known as the Financial and Logistics Integrated Technology Enterprise (FLITE). FLITE is the successor to an earlier initiative that the department undertook known as the Core Financial and Logistics System (CoreFLS). After having reportedly spent more than $249 million on its development, the department discontinued CoreFLS because the pilot system failed to support VA's operations. According to the department, FLITE is intended to fulfill the critical need for a modernized and integrated financial and asset management capability. Such a capability would support VA's strategic goal to deliver world-class service to veterans and their families through effective communication and management of people, technology, business processes, and financial resources. In early 2007, the Office of Management and Budget (OMB) designated FLITE as a high-risk information technology investment.[Footnote 1] In light of VA's past performance with CoreFLS and the designation of FLITE as high risk, you requested that we (1) determine the status of pilot system development and (2) evaluate key program management processes for the initiative, including VA's efforts to institute effective human capital management, develop a reliable program cost estimate, use earned value management (EVM), establish a realistic program schedule, employ effective requirements development and management, and perform independent verification and validation. To accomplish our objectives, we reviewed relevant program documentation and interviewed appropriate VA and contractor officials. Specifically, to determine the status of FLITE pilot system development, we reviewed documentation such as program management plans and project status reports. To evaluate key FLITE program management processes, we compared VA's activities to plans and best practices. We performed our work at the Department of Veterans Affairs headquarters in Washington, D.C., from November 2008 to October 2009 in accordance with generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objectives. See appendix I for a more complete description of our objectives, scope, and methodology. Background: In recognition of their service to our country, the Department of Veterans Affairs (VA) provides medical care, benefits, social support, and lasting memorials to veterans and their families. It is the second- largest federal department with approximately 250,000 employees. In fiscal year 2008, VA reported incurring $97 billion in obligations for its overall operations. VA provides services to veterans and their families primarily through its three line administrations: * The Veterans Health Administration operates a nationwide network of 154 hospitals, 995 outpatient clinics, 135 community living centers, 49 residential rehabilitation treatment programs, and 232 community-based counseling centers. * The Veterans Benefits Administration provides assistance and benefits such as veterans' compensation, survivors' benefits, and employment assistance through 57 veterans' benefits regional offices. * The National Cemetery Administration manages 130 national cemeteries. To support its services to veterans and their families, VA relies on an assortment of business systems, including 13 different systems that currently support its asset and financial management. However, the department has long recognized that its business systems and processes are inefficient and do not effectively support the department's mission. For example, according to the department, * systems are not integrated, * manual entry that involves labor-intensive accounting processes is required, * business processes are not standardized,[Footnote 2] and: * processes and systems require multiple entry of business information and result in untimely financial reporting. Since fiscal year 1991, the department has reported on the need for an integrated financial management system and has reported financial management system functionality as a material weakness.[Footnote 3] This weakness continues to exist because many of VA's systems are outdated, leading to inefficiencies in the reliable, timely, and consistent preparation, processing, and analysis of financial information for the department's consolidated financial statements. To address this weakness and to improve stewardship and accountability over its resources, VA has for over a decade been pursuing improvements in its business processes and replacement of its existing financial and asset management systems with an integrated financial management system. Assessments of CoreFLS: The department's first attempt to replace its financial and asset management systems, CoreFLS, began in 1998. The goal of this modernization effort was to develop a single system to integrate the many financial and asset management systems used across the department. VA had planned to complete CoreFLS in March 2006; however, it terminated development of the system in July 2004 after CoreFLS pilot tests determined it did not fully support the department's operations and that the initiative suffered from significant project management weaknesses. According to VA's Office of Inspector General (OIG), the department had obligated about $249 million of the $472 million that had been budgeted for the initiative by the time of its termination. [Footnote 4] Following the failed CoreFLS pilot tests, VA hired Carnegie Mellon University's Software Engineering Institute (SEI) to perform an independent assessment of the project. In June 2004, SEI identified a number of management and technical deficiencies that had undermined the success of the initiative.[Footnote 5] SEI identified multiple findings related to problematic technical and functional execution, as well as poor management execution. Technical and functional problems included CoreFLS's inability to perform essential financial management functions, security weaknesses, and usability. Management problems were identified in the areas of acquisition and program management, business process re-engineering, and transition planning. In addition, in August 2004, VA's OIG reported multiple findings related to CoreFLS deployment, such as inadequate training, inability to monitor fiscal and acquisition operations, inaccurate data, and project management and security weaknesses.[Footnote 6] Further, in August 2007, VA's Management Quality Assurance Service (MQAS) summarized findings from four CoreFLS reviews completed between August 2005 and August 2006.[Footnote 7] Among the findings, MQAS identified numerous fiscal and contract administration issues resulting from poor administrative internal controls such as improper reimbursements of task orders and travel expenses. Collectively, VA identified 141 findings related to problems with the CoreFLS initiative, which the department categorized into functional areas of responsibility such as acquisition management, organizational change management, program management, and systems engineering. [Footnote 8] In a subsequent effort to capture lessons learned[Footnote 9] and ensure that mistakes from CoreFLS would not be repeated in later initiatives, VA developed a repository, in which it aggregated the findings from the three independent reviews of the initiative. Establishment and Management of the FLITE Program: In September 2005, in a subsequent effort to replace its financial and asset management systems, VA began work on FLITE. In this regard, the department undertook activities related to planning and requirements development. For example, the department: * documented business requirements and business processes, * initiated coordination for reporting and financial data warehouse development, * conducted a market analysis of providers with the software and hosting capability to support VA's existing financial management system, * established key personnel requirements to provide program support and awarded a program support contract, and: * started developing numerous planning documents (e.g., program management plan, acquisition plan, and concept of operations). According to VA's planning documents, FLITE is a multiyear development effort that is projected to deliver a fully operational system by 2014 at a total estimated cost of $608.7 million.[Footnote 10] The overall objectives of the FLITE program are to: * implement accessible and enterprise-level standardized business processes that result in increased efficiencies and enhanced internal controls; * provide VA executives and managers with timely, transparent financial and asset management information to make and implement effective policy, management, stewardship, and program decisions; and: * provide business data and information in a secure, shareable, open, and efficient manner to facilitate a service-oriented atmosphere. The FLITE program includes two main projects to acquire the integrated asset and financial management system: an asset management component, referred to as the Strategic Asset Management (SAM) initiative, and the financial management component, referred to as the Integrated Financial Accounting System (IFAS). The program also includes a third project, to acquire a data warehouse that is intended to provide financial and logistics data reporting and analysis. * SAM is intended to consolidate the asset and inventory management functions and the associated work management processes currently performed by multiple legacy applications into an advanced integrated system. It is to be the system of record for VA's physical assets and perform asset and inventory management, real property management, information technology (IT) asset management, and work order and project management functions currently performed by multiple legacy applications. VA has chosen IBM's Maximo Enterprise Asset Management software suite[Footnote 11] to implement these capabilities. * IFAS is to be the financial, procurement, and accounting management component, and, together with SAM, is intended to replace VA's legacy Financial Management System (FMS) and the Integrated Funds Distribution, Control Point Activity, Accounting, and Procurement (IFCAP)[Footnote 12] system. * The data warehouse is projected to consolidate data from multiple transactional systems, primarily SAM and IFAS, for improved reporting, querying, and analysis capability. It is also intended to allow users to run larger and more complex queries and reports faster, without affecting the performance of the source systems. Figure 1 shows a simplified view of the program's components. Figure 1: Simplified View of FLITE Components: [Refer to PDF for image: illustration] Strategic Asset Management and Integrated Financial Accounting System interact, and both provide material to the Data Warehouse. Strategic Asset Management: Facility management; Inventory management; Asset management; Requisitioning and procurement; Item management; Real property management; Work order management. Integrated Financial Accounting System: Project accounting; Accounting; Debt management; Reporting; Travel; Payment management; Vendor management; Requisitioning and procurement; Fixed assets; Budget execution. Source: GAO analysis of VA data. [End of figure] The program is a collaborative effort between the Assistant Secretary for Information and Technology, who serves as VA's Chief Information Officer, and the Assistant Secretary for Management, who serves as VA's Chief Financial Officer. Various groups within VA have different roles and responsibilities for overseeing and managing programs. Figure 2 depicts the relationships between these oversight groups and the FLITE program. Figure 2: Relationship of VA's Oversight and Management Structure to FLITE Program: [Refer to PDF for image: illustration] FLITE Program Office; interaction with: FLITE Oversight Board; Budget execution and other issues interaction with: * Budgeting and Near Term Issues Board; and; * Programming and Long Term Issues Board; Interaction with: Strategic Management Council; interaction with: VA Executive Board; Budget execution and other issues interaction with: Information Technology Leadership Board. Budgeting and Near Term Issues Board; and; Programming and Long Term Issues Board; interaction with: Information Technology Leadership Board. Source: GAO analysis of VA data. [End of figure] The roles and responsibilities of each oversight group are as follows: * The VA Executive Board provides the Secretary of Veterans Affairs with a forum for discussing programs with senior leadership before decisions are made. * The Strategic Management Council makes recommendations about programs to the VA Executive Board. * The Programming and Long Term Issues Board focuses on long term multiyear program planning. * The Budgeting and Near Term Issues Board is responsible for overseeing budget formulation and execution activities. * The IT Leadership Board is responsible for adjudicating inter-and intraboard issues about programs that cannot be resolved between the Programming and Long Term Issues and Budgeting and Near Term Issues Boards. * The FLITE Oversight Board is responsible for making decisions regarding FLITE business requirements, policies, and standards. The FLITE Program Office is responsible for overseeing and coordinating all aspects of the program. The office is responsible for performing these functions through the Program Director's Office (PDO), which is responsible for business requirements and processes, and the IT Program Management Office (PMO), which is responsible for technical solutions. Project teams are responsible for managing SAM, IFAS, and the data warehouse. In addition, other VA organizations provide the office with quality assurance, acquisition, and technology support. These program- specific and VA supporting organizations are depicted in figure 3. Figure 3: Simplified FLITE Program Structure and Supporting VA Organizations: [Refer to PDF for image: illustration] Systems Quality Assurance Service: Center for Acquisition Innovation: Austin Information Technology Center: (supporting organizations for): FLITE Program Office: * Program Director‘s Office; * IT Program Management Office; IFAS project team: SAM project team: Data warehouse: Also provide support to FLITE Program Office. Source: GAO analysis of VA data. [End of figure] Table 1 describes the components that comprise the program office and supporting VA organizations. Table 1: Description of FLITE Program Office Entities and Supporting VA Organizations: Title: FLITE Program Office; Description: This office includes the PDO and the IT PMO. Together, these offices are responsible for overseeing and coordinating all aspects of the FLITE program, including systems engineering, organizational change management, training, program management, communications, and risk and investment management, and for directing multidisciplinary efforts of VA and contractor personnel to accomplish various tasks. Title: IFAS project team; Description: This team is responsible for replacing VA's current FMS and portions of the IFCAP system. Title: SAM project team; Description: This team is responsible for consolidating the asset and inventory management, real property management, work order, and project management functionality currently performed by multiple legacy applications. Title: Data warehouse; Description: This project office has not been formally defined by the program office. Title: Center for Acquisition Innovation; Description: This entity is responsible for providing acquisition services to procure supplies and services to support FLITE. Title: Austin Information Technology Center; Description: This entity is responsible for providing IT enterprise solutions to support information technology needs, including providing design and conceptual support for IFAS and systems hosting services, application administration, and operational support for SAM and the financial reporting data warehouse. Title: Systems Quality Assurance Service; Description: This entity is responsible for managing and providing oversight of independent verification and validation activities and processes employed throughout the FLITE, SAM, and IFAS system development life cycles. Source: GAO analysis of VA data. [End of table] Planned Implementation of FLITE: VA is employing a multiphase approach for both the SAM and IFAS projects, which are to be implemented by contractors using commercial off-the-shelf systems. Specifically, these components are to be implemented through sequenced acquisitions and phased deployment and integration. The systems are planned to be implemented initially at pilot sites and subsequently refined and validated at beta sites before national deployment. The purpose of the pilot phase is to perform a final validation of the selected commercial off-the-shelf system and associated business processes in a production environment, gain experience in deploying the system, and obtain acceptance from the user community. The beta phase is to further hone the rollout capabilities by deploying the system to a limited number of sites that span the range of VA's organizational environments. Following the beta phase, the department plans to incorporate lessons learned from both phases and produce a set of repeatable processes that can be employed during national deployment of the system. For SAM, the department's plans include implementation at one pilot site and 15 beta sites. The SAM pilot contractor is to evaluate and analyze VA's business processes and requirements for a fit with the Maximo software's capabilities and produce updated business process documents based on the department's needs. Also, the contractor is to train the users at the pilot site, as well as provide operations and maintenance and help desk services. The pilot phase is expected to last for an estimated 12 months. Subsequent to the pilot, the department plans to deploy SAM at 15 VA beta sites over a period of approximately 12 months. The component is expected to be deployed nationwide over 21 months, with its completion expected by May 2013. Plans for IFAS include implementing the FMS replacement at five pilot/ beta sites and implementing the IFCAP replacement at two pilot/beta sites. The IFAS pilot phase is currently scheduled to begin in the first quarter of fiscal year 2010. The department plans to deploy this component in two separate subphases over approximately 4 years. The first subphase, which will replace FMS with a commercial off-the-shelf financial management system, is expected to take about 2 years to complete. The second subphase, which is planned to be done concurrently with the first phase, will replace IFCAP with the IFAS commercial off- the-shelf financial management system and is expected to take just over 4 years to complete. VA's approach to implementing the data warehouse calls for developing the warehouse after the underlying data structures of SAM and IFAS are defined and stabilized. The department expects to complete the data warehouse in the first quarter of fiscal year 2014. Figure 4 depicts the program timeline, from program proposal through deployment of the SAM, IFAS, and data warehouse components. Figure 4: FLITE Timeline: [Refer to PDF for image: timeline] Program initiation activities: FLITE proposed: FY 2005, Q4; PDO established: FY 2007, Q2; IT PMO established: FY 2007, Q3. SAM: Pilot implementation: FY 2009, Q3 to FY 2010, Q4; Acquisition planning and source selection: FY 2009, Q3 to FY 2010, Q4; Beta: FY 2010, Q3 to FY 2012, Q1; National deployment: FY 2012, Q1 to FY 2013, Q3. IFAS: FMS replacement: Acquisition planning and source selection: FY 2009, Q2 to FY 2009, Q4; Pilot: FY 2010, Q1 to FY 2010, Q4; National deployment: FY 2011, Q1 to FY 2012, Q4. IFAS: IFCAP replacement: Development: FY 2010, Q1 to FY 2011, Q1; Pilot: FY 2011, Q1 to FY 2011, Q2; Beta: FY 2011, Q2 to FY 2011, Q4; National deployment: FY 2011, Q4 to FY 2014, Q1. Data warehouse: Acquisition planning and source selection: FY 2009, Q4 to FY 2011, Q1; Development: FY 2011, Q1 to FY 2012, Q1; Pilot/Beta: FY 2012, Q1 to FY 2012, Q3; Deployment: FY 2012, Q3 to FY 2014, Q1. Source: GAO analysis of VA data. [End of figure] In 2009, the program office undertook various activities, including issuing the IFAS request for proposals (February), awarding a program management support contract (March), awarding the SAM pilot project contract and beginning work (April), issuing a request for proposals for independent verification and validation support (July), and initiating planning for the data warehouse (September). According to program officials, as of September 2, 2009, the department had spent approximately $90.8 million on FLITE. This amount included $73.0 million for about 40 contract actions on behalf of the program office: $28.5 million for program management and technical support, $27.8 million for software licenses, $10.9 million for the SAM project, $5.5 million for analyses (e.g., requirements analyses), and $0.3 million for other program activities (e.g., training). Prior GAO and OIG Reviews of FLITE: Both we and VA's OIG have previously reported on the FLITE initiative. In a September 2008 report, we noted that key planning documents related to the initiative lacked specificity and detail, and that VA had not addressed all the findings in the CoreFLS findings repository. [Footnote 14] We recommended that VA add more specificity and details to key planning documents, such as the concept of operations and work breakdown structure, and address all findings in the CoreFLS findings repository to minimize risk to the successful implementation of FLITE. In response to our report, as of September 2009, VA had updated key planning documents and reported that it had taken actions that addressed all of the findings identified in the repository. In September 2009, VA's OIG reported on VA's effectiveness in managing the FLITE program.[Footnote 15] The office noted, among other things, that although program managers had taken steps toward addressing the CoreFLS findings, deficiencies similar to those found in CoreFLS were also evident in FLITE. For example, OIG reported that FLITE program functions were not fully staffed. Pilot Project Is Behind Schedule: VA and its contractor have begun one of the two planned pilot systems-- the SAM component. Specifically, in April 2009, the department contracted with General Dynamics Information Technology Inc. to implement Maximo at the VA Medical Center in Milwaukee, Wisconsin. Among the activities the contractor is expected to perform are analyzing business processes, documenting requirements, configuring Maximo, and performing system tests. As of mid-September 2009, VA reported that, with the contractor only 5 months into the 1-year time period planned to complete the pilot, the project had fallen 2 months behind schedule. This 2-month schedule slip was a consequence of the contractor falling behind in its efforts to perform tasks and deliver products that are necessary to implement the pilot system. Specifically, of the 34 tasks planned to be undertaken by mid-September, the contractor reported that 11 had not yet been started--including conducting a security assessment and predeployment testing--and that of 23 tasks that had been initiated, 16 were behind schedule. For example, among the tasks that the contractor noted as behind schedule were analysis of security requirements, business process analysis, and system configuration. Regarding the seven remaining tasks, two had reportedly been completed and five were identified as being on schedule. The contractor reported that it had completed a requirements traceability matrix and was on schedule with respect to starting up a project management office, performing organizational change management activities, and developing quality assurance and control programs. Further, with respect to the delivery of products, the contractor reported that it had delivered only 7 of 37 products due by mid- September. The SAM project management plan and the requirements management plan were among the products that were delivered. Products that had not yet been delivered included the Maximo system configuration document, intended to provide detailed instructions to enable a trained Maximo administrator to incorporate all VA configuration requirements, and the SAM system security plan. VA attributed the project being 2 months behind schedule to a shortage of FLITE program office human capital resources and poor project management by the contractor. Specifically, according to the program director, the program did not have the personnel it needed during the initial months of the SAM pilot project to provide the contractor with the information it needed to make planned progress. Regarding the contractor's project management, VA stated that the contractor: * provided a project manager who did not possess the skills necessary to deliver quality and timely products, * delayed hiring a project scheduler and used an initial project scheduling approach that was incorrect, * used an ineffective and inefficient approach to analyzing VA's business processes and underestimated the time needed to obtain a thorough understanding of the processes, and: * underestimated the effort necessary to configure a database server used in the pilot's development environment. In mid-September, the FLITE program director stated that the department had filled almost all of the program office vacancies and that the contractor had begun to improve its project management weaknesses. Nevertheless, according to the program director, while the department does not expect any further delays in completing the SAM pilot, it does not expect to recover the 2-month schedule slippage that has already occurred. As a result, the department projected completion of the pilot in 14 months, instead of 12 months as originally planned. Additionally, activities are under way to initiate the IFAS pilot. Specifically, the department issued a request for proposals for a pilot contractor in February 2009. A contract for the IFAS pilot is planned for award in late October 2009. VA Has Recently Filled FLITE Program Staff Positions but Has Not Yet Fully Established Other Program Management Capabilities: VA has taken steps to institute effective management of the FLITE program; however, the department has not yet fully established key capabilities needed to ensure that system components will be implemented as planned. The department recently made progress toward filling program office staff vacancies. Nonetheless, more work is needed to fully establish program management capabilities in areas that are important to the development of its integrated financial and logistics system. Until VA completes efforts to develop and reconcile its cost estimate; comply with EVM system standards; implement performance measures for its schedule; include all relevant federal and system requirements; and perform effective, independent verification and validation, it will have increased risk that FLITE will experience cost overruns and schedule delays and will not provide the capabilities that users need. VA Recently Filled Vacant Program Office Positions: Our past work has found that the success of federal programs depends on having effective strategic human capital management and, in particular, having the right number of people with the right mix of knowledge and skills.[Footnote 16] VA has recently taken steps to fill long-standing vacancies in the FLITE program that have adversely impacted the program's ability to maintain schedules. Specifically, in mid- September, the program acquired 36 staff, filling 111 of 112 required positions. According to the Acting Assistant Secretary for the Office of Management, vacant FLITE program positions were filled by individuals who were reassigned, detailed, or newly hired when the VA Deputy Secretary became aware of the program's need for staff resources. As a result of the department's recent actions to fill vacant positions, the office should be better positioned to effectively manage the program. VA's FLITE Cost Estimate Is Incomplete: Federal guidelines[Footnote 17] recommend that operations and maintenance costs over the entire estimated life cycle of an investment be included in a cost estimate. Inclusion of these costs over the time period corresponding to the life of the investment is encouraged by the federal government's guidance for managing capital assets because such costs are a key element for establishing the total cost of ownership. Further, our Cost Estimating and Assessment Guide[Footnote 18] describes effective cost-estimating practices, including performance of a risk and uncertainty analysis and development of an independent cost estimate that provides an unbiased test of whether the program's estimate is reasonable. Typically, the two estimates are reconciled. In August 2008, the FLITE program office developed a program cost estimate of $608.7 million for fiscal years 2007 through 2014--when FLITE systems are expected to achieve full operational capability. However, the office did not project operations and maintenance costs over the entire estimated life of the FLITE investment, and it did not perform a risk and uncertainty analysis as encouraged by best practices. Program officials stated that they did not consider life- cycle operations and maintenance costs in their estimate because they wanted to capture only the cost for developing the FLITE system up to its full operational capability. Also, rather than perform a risk and uncertainty analysis of their own, the program office planned to rely on risk analyses by an outside entity, the Department of the Navy Space and Naval Warfare Systems Command (SPAWAR), that the department engaged to generate a risk adjusted independent cost estimate. Completed in April 2009, the SPAWAR estimate identified costs totaling $1.899 billion for the life of the program and included $1.061 billion of estimated operations and maintenance costs for fiscal year 2015 through fiscal year 2024, which represented the entire estimated life of the initiative. According to SPAWAR officials, they used our Cost Estimating and Assessment Guide as the method for developing the independent estimate.[Footnote 19] Also, to align with VA's estimate, SPAWAR used standardized cost elements and definitions to develop a probability-based estimate of $837.8 million for fiscal years 2007 through 2014. This estimate was $229.1 million higher than the department's estimate for this period. The department's estimate was not derived based on standardized cost elements and probability-driven risk and uncertainty costs assessments. VA has not yet reconciled its cost estimate with SPAWAR's estimate. According to department officials, a significant number of end-of- fiscal-year procurement requests and the department's prioritization of IT acquisitions had affected the timing of plans to reconcile the estimates. Program officials stated that they intend to incorporate federal polices and requirements, as well as address funding, budgetary, or contractual issues necessitated by the reconciliation. According to the officials, the department plans to initiate this work in December 2009 and to complete it in March 2010. Until the reconciliation is completed, effective administration of FLITE program planning, budgeting, acquisition, and performance management activities could be jeopardized if accurate cost data are not available to guide the execution of these functions. Completion of the reconciliation, which should include estimated operations and maintenance costs for the life of the program, is essential to increase the reliability of the FLITE cost estimate and reduce the risk that acquisition plans, budgets, and performance management activities will be unsuccessful or inefficient. VA Has Not Performed Key Actions Necessary for Reliable EVM for FLITE: OMB and department policies require major programs to use EVM to measure and report program progress.[Footnote 20] EVM is a tool for measuring program progress by comparing the value of work accomplished with the amount of work expected to be accomplished. Such a comparison permits actual performance to be evaluated, based on variances from the cost and schedule baselines--collectively referred to as a performance measurement baseline. Identification of significant variances and analysis of their causes helps program managers determine the need for corrective actions. Before EVM analysis can be reliably performed, developing a credible cost estimate is necessary to provide program managers with a clear definition of the cost, schedule, and risks associated with the scope of work planned. These inputs are then used to create a performance measurement baseline for EVM analysis. In addition, federal policy requires that systems used to collect and process EVM data be compliant with the industry standard developed by the American National Standards Institute (ANSI) and Electronic Industries Alliance (EIA), ANSI/EIA Standard 748.[Footnote 21] Program officials have recognized the importance of reliable EVM and finalized the FLITE Program Measurement Earned Value Management Plan in August 2009. The plan identified roles and responsibilities, applicable policy and guidance, and the program's EVM implementation approach. According to program officials, programwide earned value reporting that will include government, program management support, and SAM project work activities is expected to begin in October 2009. However, while VA plans to begin reporting earned value performance in October 2009, a reliable cost estimate, which is necessary for EVM reporting, is not expected to be completed by that time. Specifically, as noted earlier, the department has not reconciled its cost estimate for the program with SPAWAR's independent cost estimate. Program officials do not expect reconciliation of the cost estimate to begin until 2 months after earned value reporting is scheduled to begin. Additionally, VA officials have not yet ensured that all EVM systems for FLITE are certified for compliance with ANSI/EIA Standard 748. [Footnote 22] These compliance assessments are necessary to demonstrate the capability of providing reliable cost and schedule information for earned value reporting. Specifically, the compliance assessment for the SAM pilot contractor's system has not yet been completed. While program officials did not provide information that explained why a compliance assessment of the contractor's EVM system had not yet been completed, they stated that the contractor has a plan to obtain system certification. This activity is not expected to be complete until January 2010, 3 months after earned value reporting for the program is scheduled to begin. Until the agency has completed reconciling its cost estimate and ensured that contractors comply with EVM system industry standards, VA will have an increased risk of reporting and managing the program based on unreliable performance data. VA Has Not Established a Reliable Program Schedule for FLITE: GAO's Cost Estimating and Assessment Guide[Footnote 23] states that the success of a program depends in part on having a reliable schedule that realistically depicts the program's work activities to a specific degree of detail, reasonably indicates when those work activities will occur, estimates how long they will take to complete, and shows how the work activities are related to each other. For example, a reliable schedule would indicate when one work activity depends upon the completion of another before it can start and that required resources (e.g., labor and materials) are assigned to all activities. Overall, the schedule provides the road map for the orderly execution of a program, helps identify and address potential problems, provides a baseline to gauge progress, and promotes accountability. VA has not yet established a schedule for the program that is reliable. Program officials stated that they baselined (i.e., formally established) an integrated master schedule in January 2009. However, in the program's August and September 2009 Risk & Issues reports, program officials noted that the integrated master schedule was not complete and did not represent all program requirements. The reports also identified that the SAM pilot schedule (a key component of the overall program schedule) did not include sufficient detail to trace project tasks to contract requirements. Our analysis also concluded that the schedule was unreliable and noted that, in addition to issues VA identified with the program schedule, the integrated master schedule did not include key program management activities for reconciling the program cost estimate and implementing EVM, nor did it identify resources assigned to activities already under way or expected to start in the near future. Further, the schedule did not identify all dependencies and activities and did not break down all dependencies and activities to a sufficient level of detail to measure performance. Program officials acknowledged these deficiencies and stated that program management staffing shortages and delays in receiving a reliable project schedule from the SAM contractor have affected their ability to produce a reliable schedule for the program. They stated that in July 2009, they began working with stakeholders to address schedule issues and plan to improve the reliability of their schedule by finalizing a revised integrated master schedule by October 2009. Until VA completes a revised integrated master schedule that includes all key program activities broken down to a sufficient level of detail and identifies all resources and dependencies, the program's efforts to measure progress and identify potential problems will be impaired, and the program will have increased risk of missing critical milestones for system delivery. VA Has Not Identified and Effectively Managed All FLITE Requirements: According to SEI guidance, the requirements for a system should describe the functionality needed to meet user needs and perform as intended in the operational environment.[Footnote 24] Federal agencies also must ensure that their financial management systems comply with federal standards mandated by the Federal Financial Management Improvement Act of 1996.[Footnote 25] Also according to SEI guidance, an organization can ensure system requirements are based on business requirements by tracking the requirements from inception of the project and agreement on a specific set of business requirements to development of the system requirements, detailed design, code implementation, and test cases necessary for validating the requirements. Requirements must be traceable forward and backward (i.e., bidirectional traceability) through the development life cycle. Traceability helps reduce the risks of fielding a system that does not meet the needs of its users, incurring schedule delays, and increasing costs. VA has developed an initial set of 1,700 requirements that need to be addressed in the development of the SAM and IFAS components. FLITE requirements consist of core financial and procurement requirements related to the IFAS project, as well as inventory, supply, and real property requirements related to the SAM project. To develop the initial set of requirements for FLITE, program officials stated that they analyzed VA's current and planned financial and asset management business processes and researched the Financial Systems Integration Office's (FSIO)[Footnote 26] Core Financial System Requirements and Inventory, Supplies, and Materials System Requirements publications. [Footnote 27] The initial set of requirements was further defined and refined by obtaining input from consultants and VA financial and asset management experts. The department included all mandatory core financial system requirements in its IFAS requirements but did not include all mandatory inventory, supplies, and materials requirements in its SAM requirements. For example, our analysis showed that VA did not include requirements for recording whether goods and services are accepted or rejected and for performing a systematic review and follow- up of overdue in-transit items.[Footnote 28] Program officials explained that they did not include these requirements because they had not determined whether the requirements were applicable to the SAM project. The officials agreed to incorporate the missing requirements. VA is also in the process of finalizing its real property requirements for the SAM beta phase and still plans to develop additional requirements related to procurement for IFAS. Further, the department is identifying data analysis and reporting requirements for the data warehouse.[Footnote 29] Regarding requirements traceability, SAM project officials acknowledge that mapping system requirements to the related business requirements is fundamental to effective requirements management. However, according to FLITE officials, they made a business decision not to establish bidirectional traceability between the business and system requirements included in the SAM pilot request for proposals. Instead, they decided to require the pilot contractor to establish traceability between the business and system requirements after the contractor analyzes and refines the requirements. According to the officials, the contractor plans to complete these tasks by December 2009. In addition, program officials stated that they plan to establish bidirectional traceability between IFAS business and system requirements under the IFAS implementation contract scheduled to be awarded in October 2009. In this regard, the IFAS request for proposals states that the implementation contractor will be required to finalize IFAS requirements, as well as maintain and document the traceability of all requirements to design, develop, integrate, and test specifications. As the department develops its requirements, it is important that all relevant and applicable federal financial management system requirements be identified and incorporated into the program's requirements to ensure its planned financial management systems meet users' needs and comply with applicable federal laws. Further, until they have established traceability between the business and system requirements, VA will not be positioned to know whether the system requirements are complete and effectively address each business requirement. VA Has Begun Independent Verification and Validation of the FLITE Program, but All Findings Have Not Been Addressed in a Timely Manner: According to recognized industry standards[Footnote 30] and our prior reports,[Footnote 31] the purpose of independent verification and validation is to provide an independent review of system processes and products to ensure that quality standards are being met. As we have previously noted, the use of independent verification and validation is a recognized best practice for large and complex system development and acquisition programs such as FLITE and involves an independent organization conducting unbiased reviews of processes, products, and results to verify and validate that they meet stated requirements and standards. VA policy recognizes the importance of addressing independent verification and validation results in a timely manner. Recognizing the importance of independent verification and validation, the department's Systems Quality Assurance Service was tasked with performing independent verification and validation activities for the FLITE program.[Footnote 32] In April 2009, this organization developed a Software Quality Assurance Plan[Footnote 33] to guide independent verification and validation activities for the program. The plan was developed consistent with industry standards and generally contained the required elements. The plan also outlined reviews that would be performed by the Systems Quality Assurance Service, including product (e.g., program and project deliverables), process, internal controls, test readiness, and production readiness reviews. In addition, the Systems Quality Assurance Service is responsible for advising and assisting with the program's implementation of a suite of tools to support requirements management, change management, risk, and test management. Independent verification and validation of the FLITE program has been focused primarily on the review of program and project deliverables. According to program officials, as of September 2009, the Systems Quality Assurance Service had reviewed 30 FLITE work products and provided findings and recommendations to document owners.[Footnote 34] Out of 1,064 total findings, 947 (approximately 89 percent) had been fully addressed by the program or had been identified as obsolete by the Systems Quality Assurance Service. Of the 117 remaining findings, 59 had been addressed but had not yet been reflected in revised documents, and 58 required additional attention. Of the 58 findings and recommendations that remained open, the SAM pilot site readiness plan accounted for 18 that were identified in December 2008. According to the Systems Quality Assurance Service, these findings focused on the need for consistency with other project documentation, clarity in the timing of site activities, and incorporation of planned site-level activities into the program work breakdown structure. In addition, according to department officials, the FLITE acquisition strategy has two findings and recommendations that were identified in December 2008 and that remain to be addressed. These findings are related to VA's approach for acquiring SAM and IFAS integration support and the program's focus on front-end acquisition activities, rather than full life cycle acquisition processes. Unknown or incomplete system integration requirements may result in significant rework and adversely impact the program's cost, schedule, and quality. According to FLITE program officials, they have not had the human capital resources they need to address all the independent verification and validation findings and recommendations in a timely manner. As a result, independent verification and validation findings that highlight important program issues (e.g., determining an approach for integrating SAM and IFAS) have not received the attention that they need. As discussed earlier, the staff resources recently added could help address the program's inability to focus sufficient attention on resolving findings from initial independent verification and validation activities. It remains unclear whether the program office will be positioned to efficiently resolve findings raised when the scope of independent verification and validation activities expands to include system testing and production readiness reviews, which affect the extent to which FLITE components will meet stated requirements and quality standards. Conclusions: The pilot for VA's new asset management system has experienced a 2- month schedule delay just 5 months after award of the contract. While VA has recently taken steps to address the staffing shortages that have substantially contributed to this delay, it has not yet fully established the management capability necessary for FLITE to be successful. For example, the department's program cost estimate did not represent total program costs, nor has the estimate been reconciled with an independent estimate--a process that could increase its reliability. Further, it has not conducted EVM that is needed to ensure the reliability of the department's programwide reporting on the initiative. Also, VA has not yet made revisions that are needed to increase the reliability of the program's integrated master schedule. In addition, the requirements for the two major program systems, SAM and IFAS, do not yet address all the functions expected of federal asset management and financial management systems. Finally, key findings from independent reviews of the program have not been fully addressed on a timely basis. As a consequence, the department is faced with significant challenges in implementing FLITE's pilot systems as planned, while simultaneously working to fully establish program management capabilities. Program officials recognize the importance of reconciling their cost estimate, ensuring compliance with EVM system standards, establishing a reliable schedule, ensuring all relevant federal and system requirements are identified and traceable, and addressing all independent verification and validation findings. Further, they have stated that they plan to take such actions. However, just as program officials needed the department's support in filling long-standing program office vacancies, the full support of the department's top management is critical to ensuring that planned actions are executed. If the program is not effective in addressing its management weaknesses, the department increases the risk of repeating its unsuccessful earlier attempt to modernize the department's financial and logistics systems. Recommendations for Executive Action: To help guide and ensure successful completion of FLITE, the Secretary of Veterans Affairs should direct and ensure that the Assistant Secretary for Management and the Assistant Secretary for Information and Technology take the following five actions: * Improve the reliability of the program cost estimate by ensuring that the estimate includes system operations and maintenance costs and that the estimate is reconciled with the independent cost estimate. * Improve the reliability of program earned value management reporting by ensuring that contractor earned value management systems comply with industry standards. * Complete a revised integrated master schedule that includes all key program activities, including reconciliation of the program cost estimate and implementation of earned value management, and identifies all resources and dependencies. * Ensure that all relevant and applicable federal financial management system requirements are included in FLITE's requirements and establish and maintain requirements traceability. * Ensure that all comments from independent verification and validation reviews are addressed. Agency Comments and Our Evaluation: The VA Chief of Staff provided written comments on a draft of this report. In its comments, the department concurred with our recommendations and described actions to address them. For example, the department stated that it plans to reconcile the FLITE program cost estimate with the independent cost estimate by the second quarter of fiscal year 2010; ensure that future contractors' EVM systems comply with industry standards and begin an independent review of the program's EVM compliance by the first quarter of 2010; and include the reconciled program cost estimate in the integrated master schedule by the third quarter of fiscal year 2010. Further, the department stated that it plans to validate the completeness of FLITE requirements by mid- November 2009 and ensure that outstanding comments from independent verification and validation reviews are addressed by mid-December 2009. If the recommendations are properly implemented, they should better position VA to effectively manage the FLITE program. The department also provided a technical comment, which we have addressed in the report as appropriate. The department's written comments are reproduced in appendix II. As agreed with your offices, unless you publicly announce its contents earlier, we plan no further distribution of this report until 30 days from the date of this letter. At that time, we will send copies of the report to interested congressional committees, the Secretary of Veterans Affairs, and other interested parties. In addition, the report will be available at no charge on our Web site at [hyperlink, http://www.gao.gov]. If you or your staffs have questions about this report, please contact Valerie C. Melvin at (202) 512-6304 or melvinv@gao.gov, or Kay L. Daly at (202) 512-9095 or dalykl@gao.gov. Contact points for our Offices of Congressional Relations and Public Affairs may be found on the last page of this report. Key contributors to this report are listed in appendix III. Signed by: Valerie C. Melvin: Director, Information Management and Human Capital Issues: Signed by: Kay L. Daly: Director, Financial Management and Assurance: [End of section] Appendix I: Objectives, Scope, and Methodology: As requested, the objectives of our study were to (1) determine the status of the Financial and Logistics Integrated Technology Enterprise‘s (FLITE) pilot system development and (2) evaluate key program management processes, including the Department of Veterans Affairs‘ (VA) efforts to institute effective human capital management, develop a reliable program cost estimate, use earned value management, establish a realistic program schedule, employ effective requirements development and management, and perform independent verification and validation. To determine the status of the pilot system development, we: * obtained and analyzed program documentation, including program management plans, contracts, schedules, briefing slides, meeting minutes, and project status reports to identify from these reports the planned FLITE pilot activities and deliverables and determined to what extent these tasks had been completed; and; * supplemented department program documentation and our analyses by interviewing department and contractor officials, such as the program director, and observing project status meetings. We also evaluated VA‘s progress toward implementing our prior recommendations related to adding specificity and details to key planning documents by comparing updated documents, including the Program Management Plan and Strategic Asset Management (SAM) Concept of Operations to prior versions. To evaluate key program management processes, we: * compared program staffing plans with the program‘s staffing resource reports to determine the extent to which program human capital needs have been met; * compared the program cost estimate and estimating activities to Office of Management and Budget guidance and GAO‘s Cost Estimating and Assessment Guide[Footnote 35] to determine the estimate‘s completeness and the effectiveness of the estimating activities; * reviewed department documentation, such as the program‘s plan for earned value management implementation, and compared them to federal policy and GAO‘s Cost Estimating and Assessment Guide to determine the department‘s preparedness for conducting reliable earned value management; * reviewed the program schedule and compared it to planned activities, deliverables, and practices described in GAO‘s Cost Estimating and Assessment Guide to assess the schedule‘s reliability; * analyzed program documentation, including the department‘s business requirements, concept of operations for FLITE, traceability matrix, and requirements management plan, to determine the extent to which they reflect practices such as those recognized by SEI[Footnote 36] and include federal financial management system requirements; and; * reviewed program documentation, such as the software quality assurance plan, quality management plan, and technical review reports, to determine the extent to which the program has addressed independent verification and validation findings. We conducted this performance audit at VA headquarters in Washington, D.C., from November 2008 through October 2009 in accordance with generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objectives. [End of section] Appendix II: Comments from the Department of Veterans Affairs: The Secretary Of Veterans Affairs: Washington: October 19, 2009: Ms. Valerie Melvin: Director: Information Management and Human Capital Issues: U.S. Government Accountability Office: 441 G Street, NW: Washington, DC 20548: Dear Ms. Melvin: The Department of Veterans Affairs (VA) has reviewed the Government Accountability Offices (GAO) draft report, Information Technology; Actions Needed to Fully Establish Program Management Capability for VA's Financial and Logistics Initiative (GAO-10-40) and generally agrees with GAO's conclusions and concurs with GAO's recommendations to the Department. The enclosure specifically addresses GAO's recommendations and provides additional comments to the draft report. VA appreciates the opportunity to comment on your draft report. A similar response has been sent to Ms. Kay Daly. Sincerely, Signed by: John R. Gingrich: Chief of Staff: Enclosure: [End of letter] The Secretary Of Veterans Affairs: Washington: October 19, 2009: Ms. Kay Daly: Director: Financial Management and Assurance: U.S. Government Accountability Office: 441 G Street, NW: Washington, DC 20548: Dear Ms. Daly: The Department of Veterans Affairs (VA) has reviewed the Government Accountability Office's (GAO) draft report, Information Technology: Actions Needed to Fully Establish Program Management Capability for VA's Financial and Logistics Initiative (GAO-10-40) and generally agrees with GAO's conclusions and concurs with GAO's recommendations to the Department. The enclosure specifically addresses GAO's recommendations and provides additional comments to the draft report. VA appreciates the opportunity to comment on your draft report. A similar response has been sent to Ms. Valerie Melvin. Sincerely, Signed by: John R. Gingrich: Chief of Staff: Enclosure: [End of letter] Enclosure: Departments of Veterans Affairs (VA) Comments to Government Accountability Office (GAO) Draft Report, Information Technology: Actions Needed to Fully Establish Program Management Capability for VA's Financial and Logistics Initiative (GAO-10-40): GAO recommendation: To help guide and ensure successful completion of FLITE, the Secretary of Veterans Affairs should direct and ensure that the Assistant Secretary for Management and the Assistant Secretary for Information and Technology take the following five actions: Recommendation 1: Improve the reliability of the program cost estimate by ensuring that the estimate includes system operations and maintenance costs and that the estimate is reconciled with the independent cost estimate. VA response: Concur. Financial and Logistics Integrated Technology Enterprise (FLITE) completed a program manager's cost estimate that formed the basis of the e300 submission in December 2008 and subsequently issued a short-term contract for an independent cost estimate. The Department of Veterans Affairs (VA) fully intends to complete the cost estimation work for the ELITE program by reconciling it with the independent cost estimate provided by SPAWAR in July 2009. VA is contracting for a follow-on independent cost analysis which will include reconciliation of the Program Managers and independent cost estimates to validate assumptions. The Government expects to complete the cost estimate reconciliation by Q2 FY 2010. Recommendation 2: Improve the reliability of program earned value management reporting by ensuring that contractor earned value management systems comply with industry standards. VA response: Concur. VA is committed to continually improving its program and project management activities, to include the reliability of earned value management (EVM) reporting. To increase this reliability, VA will: * Conduct thorough validation activities to ensure all future FLITE contractors' EVM systems comply with the applicable American National Standards Institute (ANSI) standards, specifically ANSI/EIA Standard 748 and VA Earned Value Application guide and Directive 6061. * On a consistent basis, conduct integrated baseline reviews on all ELITE contracts with an EVM requirement. * Obtain an independent compliance review of the FLITE program's implementation of EVM. This activity will begin in Q1 FY 2010. * Ensure all Requests for Proposals issued by the FLITE program include mandatory EVM compliance requirements. * Ensure that when awarding contracts, there is formal proof of a contractors compliance with ANSI standards for use of an EVM system. * Ensure agreement with any applicable contractor, before and after award as appropriate, in order to verify the Performance Measurement Baseline (PMB). The PMB is the basis against which all performance will be measured and EVM data generated. * Maintain a change management process to ensure integrity of the cost and schedule baseline, This includes submission of formal change requests, based upon pre-determined thresholds and parameters, which will be reviewed by the overall FLITE Change Control Board. Recommendation 3: Complete a revised integrated master schedule that includes all key program activities, including reconciliation of the program cost estimate and implementation of earned value management and identifies all resources and dependencies. VA response: Concur. VA has included tasks for creating and maintaining integrated master schedules (IMS) in all its applicable contracts. The FLITE program has an existing overall IMS, which is supported by the project levels schedules. This IMS includes all key program activities and is fully developed. The FLITE program IMS will include the reconciled program cost estimate by Q3 FY 2010. Recommendation 4: Ensure that all relevant and applicable federal financial management system requirements are included in FLITE's requirements and establish and maintain requirements traceability. VA response: Concur. The Strategic Asset Management (SAM) system Project Office believes that the applicable federal financial management system requirements were included when the original SAM business requirements were developed. However, to ensure and validate this assumption, the SAM Project Office will cross reference these requirements with SAM requirements. Any requirement that may have been omitted will be added to the SAM Business Requirements document following established change control procedures. Any federal financial management system requirement determined not to be applicable to VA will be documented as to the reason why. The validation process will be accomplished by November 13, 2009. Recommendation 5: Ensure that all comments from independent verification and validation reviews are addressed. VA response: Concur. The 59 findings that were addressed are being included into the appropriate documents during their planned updates. The 58 findings requiring additional attention are being reviewed for document revision update. The planned updates and the review process will be completed by December 15, 2009. In addition, VA's Systems Quality Assurance Service will provide a biweekly status report for use by the FLITE program and project managers. The report will outline program and project quality assurance, testing activities and status. In addition all program and project level product reviews will be included in a current period activity table and a cumulative status tracking format which will allow for easy progress assessment for follow-up action. [End of section] Appendix III: GAO Contacts and Staff Acknowledgments: GAO Contacts: Valerie C. Melvin, (202) 512-6304 or melvinv@gao.gov: Kay L. Daly, (202) 512-9095 or dalykl@gao.gov: Staff Acknowledgments: In addition to the contacts named above, key contributions to this report were made by Mark T. Bird, Assistant Director; Michael S. LaForge, Assistant Director; Heather A. Collins; Neil J. Doherty; Rebecca Eyler; David A. Hong; Jacqueline K. Mai; Yvonne D. Moss; Robert L. Williams, Jr.; and Leonard E. Zapata. [End of section] Footnotes: [1] Investments that are designated as high risk require special attention from the highest level of agency management and oversight authorities due to size, complexity, or nature of the risk of the project. [2] VA currently does not have standardized systems or processes for managing physical assets, supply inventories, and related work order management across the department. While VA uses some common inventory, procurement, and asset management applications, each VA facility operates a customized version of each system. [3] The material weakness in financial management system functionality is linked to VA‘s outdated legacy financial systems, impacting VA‘s ability to prepare, process, and analyze financial information that is reliable, timely, and consistent. Legacy system deficiencies necessitated significant manual workarounds and a large number of general ledger adjustments, increasing the risk of processing errors and misstatements in the financial statements. [4] VA OIG, Issues at VA Medical Center Bay Pines, Florida and Procurement and Deployment of the Core Financial and Logistics System (CoreFLS), 04-01371-177 (Washington, D.C., Aug. 11, 2004). [5] Carnegie Mellon SEI, Report of the Independent Technical Assessment of the Department of Veterans Affairs CoreFLS Program (June 2004). [6] VA OIG, Issues at VA Medical Center Bay Pines, Florida and Procurement and Deployment of the Core Financial and Logistics System (CoreFLS), 04-01371-177. [7] VA MQAS, VA Lessons Learned: Findings and Recommendations Summary from CoreFLS Reviews, 07-04-SAD002 (Austin, Tex., Aug. 1, 2007). [8] The aggregated list of 141 lessons learned included 80 lessons learned from SEI, 22 from OIG, and 39 from MQAS. VA officials subsequently reduced the total number of lessons learned to 103 by eliminating duplicate findings. [9] The use of lessons learned is a principal component of an organizational culture committed to continuous improvement. Sharing such information serves to communicate acquired knowledge more effectively and to ensure that beneficial information is factored into planning, work processes, and activities. Lessons learned can be based on positive experiences or on negative experiences that result in undesirable outcomes. [10] VA developed their initial cost estimate for FLITE in August 2008. In April 2009, an independent cost estimate adjusted for program risks and uncertainties estimated FLITE costs to be $837.8 million. [11] Maximo is a Web-based asset management suite used to manage the complete life cycle of strategic assets, including planning, procurement, deployment, tracking, maintenance, and retirement. [12] IFCAP is a decentralized procurement, funds control, and front-end accounting system that complements the FMS functionality. It is used at the VA Medical Centers and certain Regional and Administrative Offices. IFCAP integrates functions of Fiscal Service, Acquisition and Logistics, and other VA Medical Center services that request supplies and services for VA. There are more than 150 stand-alone instances of IFCAP across VA. [13] SAM and IFAS are intended to be transactional systems but will not be optimized for query and reporting activities, which is the role that the data warehouse is intended to fill. [14] GAO, Veterans Affairs: Additional Details Are Needed in Key Planning Documents to Guide the New Financial and Logistics Initiative, [hyperlink, http://www.gao.gov/products/GAO-08-1097] (Washington, D.C.: Sept. 22, 2008). [15] VA OIG, Department of Veterans Affairs: Audit of FLITE Program Management‘s Implementation of Lessons Learned, 09-01467-216 (Sept. 16, 2009). [16] For example, our prior work has shown negative cost and schedule implications for complex services acquisitions at the Department of Homeland Security that did not have adequate staff. See GAO, Department of Homeland Security: Better Planning and Assessment Needed to Improve Outcomes for Complex Service Acquisitions, [hyperlink, http://www.gao.gov/products/GAO-08-263] (Washington, D.C.: Apr. 22, 2008). [17] Executive Office of the President, Office of Management and Budget, Circular No. A-11, Part 7, Planning, Budgeting, Acquisition, and Management of Capital Assets (Washington, D.C., June 2008). The OMB guidelines state that risk adjusted life cycle costs include the overall estimated cost over the time period corresponding to the life of the investment, including periodic and continuing costs of operations and maintenance. [18] GAO, GAO Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Capital Program Costs, [hyperlink, http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: March 2009). [19] To develop probability-based estimated costs leading to a risk- adjusted independent cost estimate for the FLITE program, SPAWAR used a risk-based cost-estimating technique called Latin Hypercube sampling. Latin Hypercube sampling is a sampling technology designed to ensure high forecast efficiency and accurately recreate the input distribution through sampling. Sampling is forced to represent values in each interval and, thus, is forced to recreate the input probability distribution. For the independent cost evaluation, SPAWAR used 50,000 iterations of the model to generate estimates from the model to enhance statistical efficiency. SPAWAR also obtained additional inputs from the FLITE PMO and obtained specific responses to independent cost evaluation team questions from the VA PMO, and subsequently reconsidered and modified some cost-related assumptions that VA used in creating their estimate. [20] OMB issued policy guidance (M-05-23) to agency chief information officers on improving technology projects that includes requirements for reporting performance to OMB using EVM (August 2005). VA, VA Earned Value Management System, VA Directive 6061, (February 2006). [21] See OMB, Capital Programming Guide, II.2.4, Establishing an Earned Value Management System. Reflected in the Federal Acquisition Regulation (FAR), 48 C.F.R. subpart 34.2. [22] Typically, an independent organization conducts the compliance review of an EVM system. Upon successful completion of the review, system acceptance should be documented, showing how each of the 32 ANSI/EIA Standard 748 guidelines have been satisfied. [23] [hyperlink, http://www.gao.gov/products/GAO-09-3SP]. [24] SEI is a federally funded research and development center whose objective is to provide leadership in software engineering and the transition of new software engineering technology into practice. [25] Specifically, the Federal Financial Management Improvement Act of 1996 states that financial management systems must comply substantially with financial management systems requirements located in a series of publications entitled Federal Financial Management Systems Requirements, which specifies the mandatory functional and technical requirements that agencies‘ systems must meet. [26] FSIO is responsible for coordinating the work related to federal financial management systems requirements. [27] FSIO, Core Financial System Requirements, OFFM-NO-0106 (Washington, D.C., January 2006) and Inventory, Supplies, and Materials System Requirements, JFMIP-SR-03-02 (Washington, D.C., August 2003). [28] Recording the acceptance or rejection of goods and services, as well as resolving overdue in-transit items, are useful when evaluating the performance of suppliers and in reconciling asset management data with financial data such as payment and general ledger posting activities. Additionally, recording the date goods and services are accepted is a critical data element for ensuring an agency complies with the Prompt Payment Act. (Prompt Payment Act codified at 31 U.S.C. §§ 3901-3904 and implemented at 5 C.F.R. 1315.) [29] According to the VA FLITE Real Property Strategy Working Paper, VA needs to perform additional analysis of VA business needs to determine if more real property business requirements are needed. Additionally, the FLITE program office plans to develop the additional requirements related to procurement, data analyses, and reporting during the IFCAP Replacement Development phase of the IFAS project and the data warehouse scheduled to begin in October 2009 and September 2010, respectively. [30] Institute of Electrical and Electronics Engineers, Inc., IEEE Standard for Software Verification and Validation, IEEE Std 1012-2004 (New York, N.Y., June 8, 2005). [31] GAO, Office of Personnel Management: Improvements Needed to Ensure Successful Retirement Systems Modernization, [hyperlink, http://www.gao.gov/products/GAO-08-345] (Washington, D.C.: Jan. 31, 2008) and Homeland Security: First Phase of Visitor and Immigration Status Program Operating, but Improvements Needed, [hyperlink, http://www.gao.gov/products/GAO-04-586] (Washington, D.C.: May 11, 2004). [32] VA‘s Systems Quality Assurance Service is organizationally independent of the FLITE Program and reports directly to the Office of Business Oversight and Office of Management for the escalation of significant issues. [33] Standards have been developed by the Institute of Electrical and Electronics Engineers (IEEE) to guide the development of software quality assurance plans, which typically include information on roles and responsibilities, tasks, metrics, software reviews, system tests, and independent verification and validation tools that will be utilized to support the software quality assurance process. [34] The document owner is responsible for managing the document review process; this includes identifying appropriate reviewers, consolidating adjudicated comments, and determining the acceptability of work products. [35] GAO, GAO Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Capital Program Costs, [hyperlink, http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: March 2009). [36] SEI is a federally funded research and development center whose objective is to provide leadership in software engineering and in the transition of new software engineering technology into practice. [End of section] GAO's Mission: The Government Accountability Office, the audit, evaluation and investigative arm of Congress, exists to support Congress in meeting its constitutional responsibilities and to help improve the performance and accountability of the federal government for the American people. GAO examines the use of public funds; evaluates federal programs and policies; and provides analyses, recommendations, and other assistance to help Congress make informed oversight, policy, and funding decisions. GAO's commitment to good government is reflected in its core values of accountability, integrity, and reliability. Obtaining Copies of GAO Reports and Testimony: The fastest and easiest way to obtain copies of GAO documents at no cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each weekday, GAO posts newly released reports, testimony, and correspondence on its Web site. To have GAO e-mail you a list of newly posted products every afternoon, go to [hyperlink, http://www.gao.gov] and select "E-mail Updates." Order by Phone: The price of each GAO publication reflects GAO‘s actual cost of production and distribution and depends on the number of pages in the publication and whether the publication is printed in color or black and white. Pricing and ordering information is posted on GAO‘s Web site, [hyperlink, http://www.gao.gov/ordering.htm]. Place orders by calling (202) 512-6000, toll free (866) 801-7077, or TDD (202) 512-2537. Orders may be paid for using American Express, Discover Card, MasterCard, Visa, check, or money order. Call for additional information. To Report Fraud, Waste, and Abuse in Federal Programs: Contact: Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: E-mail: fraudnet@gao.gov: Automated answering system: (800) 424-5454 or (202) 512-7470: Congressional Relations: Ralph Dawn, Managing Director, dawnr@gao.gov: (202) 512-4400: U.S. Government Accountability Office: 441 G Street NW, Room 7125: Washington, D.C. 20548: Public Affairs: Chuck Young, Managing Director, youngc1@gao.gov: (202) 512-4800: U.S. Government Accountability Office: 441 G Street NW, Room 7149: Washington, D.C. 20548:

The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.