VA Real Property
Realignment Progressing, but Greater Transparency about Future Priorities Is Needed
Gao ID: GAO-11-521T April 5, 2011
The Department of Veterans Affairs (VA) has undertaken various planning efforts to realign its real property portfolio, including the Capital Asset Realignment for Enhanced Services (CARES), creation of a 5-year capital plan, and its newest effort, the Strategic Capital Investment Planning process (SCIP). Through these efforts, VA has identified numerous real property priorities it believes should be completed if the agency's facilities are to meet veterans' needs for services now and in the future. In January 2011, GAO reported on the extent to which VA's capital planning efforts (1) have resulted in changes to its real property portfolio and (2) follow leading practices and provide information for informed decision making. This statement summarizes the results of this report. To perform the work for the report, GAO reviewed leading capital planning practices and data on VA's real property portfolio and future priorities. GAO also interviewed VA officials and veterans service organizations and visited sites in 5 of VA's 21 veterans integrated service networks.
GAO reported that, through its capital planning efforts, VA had taken steps to realign its real property portfolio from hospital based, inpatient care to outpatient care, but a substantial number of costly projects and other long-standing challenges also remain. Several of VA's most recent capital projects--such as community based outpatient clinics, rehabilitation centers for blind veterans, and a spinal cord injury center--were based on its CARES efforts and subsequent capital planning. VA officials and veterans service organizations GAO contacted agreed that these facilities have had a positive effect on veterans' access to services. However, VA had identified several high-cost priorities such as facility repairs and projects that have not yet been funded. For example, VA reported in its 5-year capital plan for fiscal years 2010-2015 that it had a backlog of $9.4 billion of facility repairs. The 5-year plan further identified an additional $4.4 billion in funding to complete 24 of the 69 ongoing major construction projects. Besides substantial funding priorities, GAO also found that VA, like other agencies, has faced underlying obstacles that have exacerbated its real property management challenges and can also impact its ability to fully realign its real property portfolio. GAO previously reported that such challenges include competing stakeholder interests, legal and budgetary limitations, and capital planning processes that did not always adequately address such issues as excess and underutilized property. VA's capital planning efforts generally reflected leading practices, but lacked transparency about the cost of future priorities that could better inform decision making. For example, VA's 2010-2015 capital plan linked its investments with its strategic goals, assessed the agency's capital priorities, and evaluated various alternatives. Also, SCIP strengthened VA's capital planning efforts by extending the horizon of its 5-year plan to 10 years and providing VA with a longer range picture of the agency's future real property priorities. VA officials told GAO that SCIP builds on its existing capital planning processes, addresses leading practices, and further strengthens VA's efforts in some areas. GAO has not fully assessed SCIP and it remains to be seen what impact SCIP will have on the results of VA's capital planning efforts. While these changes were positive steps, GAO found that VA's planning efforts lacked transparency regarding the magnitude of costs of the agency's future real property priorities, which may limit the ability of VA and Congress to make informed funding decisions among competing priorities. For instance, for potential future projects, VA's 2010-2015 capital plan only listed project name and contained no information on what these projects were estimated to cost or the priority VA had assigned to them beyond what was then the current budget year. Transparency about future requirements would benefit congressional decision makers by putting individual project decisions in a long-term, strategic context, and placing VA's fiscal situation within the context of the overall fiscal condition of the U.S. government. In the report, GAO recommended that VA annually provide to Congress the full results of its SCIP process and any subsequent capital planning efforts, including details on estimated costs of future projects. VA concurred with this recommendation.
GAO-11-521T, VA Real Property: Realignment Progressing, but Greater Transparency about Future Priorities Is Needed
This is the accessible text file for GAO report number GAO-11-521T
entitled 'VA Real Property: Realignment Progressing, but Greater
Transparency about Future Priorities Is Needed' which was released on
April 5, 2011.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
United States Government Accountability Office:
GAO:
Testimony:
Before the Committee on Veterans' Affairs, House of Representatives:
For Release on Delivery:
Expected at 10:30 a.m. EDT:
Tuesday, April 5, 2011:
VA Real Property:
Realignment Progressing, but Greater Transparency about Future
Priorities Is Needed:
Statement of Lorelei St. James:
Acting Director, Physical Infrastructure Issues:
GAO-11-512T:
GAO Highlights:
Highlights of GAO-11-521T, a testimony before the Committee on Veterans‘
Affairs, House of Representatives.
Why GAO Did This Study:
The Department of Veterans Affairs (VA) has undertaken various
planning efforts to realign its real property portfolio, including the
Capital Asset Realignment for Enhanced Services (CARES), creation of a
5-year capital plan, and its newest effort, the Strategic Capital
Investment Planning process (SCIP). Through these efforts, VA has
identified numerous real property priorities it believes should be
completed if the agency‘s facilities are to meet veterans‘ needs for
services now and in the future. In January 2011, GAO reported on the
extent to which VA‘s capital planning efforts (1) have resulted in
changes to its real property portfolio and (2) follow leading
practices and provide information for informed decision making. This
statement summarizes the results of this report. To perform the work
for the report, GAO reviewed leading capital planning practices and
data on VA‘s real property portfolio and future priorities. GAO also
interviewed VA officials and veterans service organizations and
visited sites in 5 of VA‘s 21 veterans integrated service networks.
What GAO Found:
GAO reported that, through its capital planning efforts, VA had taken
steps to realign its real property portfolio from hospital based,
inpatient care to outpatient care, but a substantial number of costly
projects and other long-standing challenges also remain. Several of VA‘
s most recent capital projects-”such as community based outpatient
clinics, rehabilitation centers for blind veterans, and a spinal cord
injury center”-were based on its CARES efforts and subsequent capital
planning. VA officials and veterans service organizations GAO
contacted agreed that these facilities have had a positive effect on
veterans‘ access to services. However, VA had identified several high-
cost priorities such as facility repairs and projects that have not
yet been funded. For example, VA reported in its 5-year capital plan
for fiscal years 2010-2015 that it had a backlog of $9.4 billion of
facility repairs. The 5-year plan further identified an additional
$4.4 billion in funding to complete 24 of the 69 ongoing major
construction projects. Besides substantial funding priorities, GAO
also found that VA, like other agencies, has faced underlying
obstacles that have exacerbated its real property management
challenges and can also impact its ability to fully realign its real
property portfolio. GAO previously reported that such challenges
include competing stakeholder interests, legal and budgetary
limitations, and capital planning processes that did not always
adequately address such issues as excess and underutilized property.
VA‘s capital planning efforts generally reflected leading practices,
but lacked transparency about the cost of future priorities that could
better inform decision making. For example, VA‘s 2010-2015 capital
plan linked its investments with its strategic goals, assessed the
agency‘s capital priorities, and evaluated various alternatives. Also,
SCIP strengthened VA‘s capital planning efforts by extending the
horizon of its 5-year plan to 10 years and providing VA with a longer
range picture of the agency‘s future real property priorities. VA
officials told GAO that SCIP builds on its existing capital planning
processes, addresses leading practices, and further strengthens VA‘s
efforts in some areas. GAO has not fully assessed SCIP and it remains
to be seen what impact SCIP will have on the results of VA‘s capital
planning efforts. While these changes were positive steps, GAO found
that VA‘s planning efforts lacked transparency regarding the magnitude
of costs of the agency‘s future real property priorities, which may
limit the ability of VA and Congress to make informed funding
decisions among competing priorities. For instance, for potential
future projects, VA‘s 2010-2015 capital plan only listed project name
and contained no information on what these projects were estimated to
cost or the priority VA had assigned to them beyond what was then the
current budget year. Transparency about future requirements would
benefit congressional decision makers by putting individual project
decisions in a long-term, strategic context, and placing VA‘s fiscal
situation within the context of the overall fiscal condition of the
U.S. government.
What GAO Recommends:
In the report, GAO recommended that VA annually provide to Congress
the full results of its SCIP process and any subsequent capital
planning efforts, including details on estimated costs of future
projects. VA concurred with this recommendation.
View [hyperlink, http://www.gao.gov/products/GAO-11-521T] or key
components. For more information, contact Lorelei St. James at (202)
512-2834 or stjamesl@gao.gov.
[End of section]
Chairman Miller, Ranking Member Filner, and Members of the Committee:
I am pleased to be here today as you examine construction planning
issues related to the Department of Veterans Affairs (VA). VA is one
of the largest federal property-holding agencies, with more than
33,000 acres of land and over 5,500 buildings. VA uses this diverse
inventory of real property to ensure that veterans receive medical
care, benefits, social support, and lasting memorials. Over time, VA
has recognized the need to modernize its facilities and realign its
real property portfolio to provide accessible, high-quality, and cost-
effective access to its services. Its Capital Asset Realignment for
Enhanced Services (CARES) planning effort, which began over a decade
ago, was designed to assess its building and land ownership in
response to changing veterans' inpatient and outpatient demand for
care. Since its 2004 CARES decision report, VA has undertaken
additional planning efforts to realign its real property portfolio.
For example, with its annual budget submission to Congress, VA began
including 5-year capital plans that included information about
projects it was seeking to start, as well as the estimated costs from
first year through completion. More recently, VA developed a Strategic
Capital Investment Planning (SCIP) process, which is intended to
continue VA's efforts to prioritize its most urgent real property
priorities. Through these capital planning efforts, VA has identified
numerous real property priorities that it believes should be completed
if the agency's facilities are to meet veterans' demand for services.
This statement is primarily based on our January 2011 report, which
addressed the impact of CARES and the effectiveness of VA's capital
planning process.[Footnote 1] This statement addresses the following
questions also covered in the report:
1. To what extent have VA's capital planning efforts resulted in
changes to its real property portfolio and what priorities remain?
2. To what extent do VA's capital planning efforts follow leading
federal practices and provide the information needed for informed
decision making?
To perform this work, we reviewed leading capital planning practices
and data on VA's real property portfolio and future priorities. We
also interviewed VA officials and veterans service organizations, and
visited sites in 5 of VA's 21 veterans integrated service networks.
More detailed information on our scope and methodology can be found in
appendix I of the report.
Our work was performed in accordance with generally accepted
government auditing standards. This report did not assess the results
of VA's capital planning proposals that are reflected in the
President's fiscal year 2012 budget, which was released after our
report was issued.
In summary, we found that through its capital planning efforts, VA had
taken steps to realign its real property portfolio from hospital
based, inpatient care to outpatient care, but a substantial number of
costly projects and other long-standing challenges also remain.
Several of VA's most recent capital projects--such as community based
outpatient clinics, rehabilitation centers for blind veterans, and a
spinal cord injury center--were based on its CARES efforts and
subsequent capital planning. VA officials and veterans service
organizations we contacted agreed that these facilities have had a
positive effect on veterans' access to services. However, VA had
identified several high-cost priorities such as facility repairs and
projects that have not yet been funded. For example, VA reported in
its 5-year capital plan for fiscal years 2010-2015 that it had a
backlog of $9.4 billion of facility repairs. The 5-year plan further
identified an additional $4.4 billion in funding to complete 24 of the
69 ongoing major construction projects. Besides substantial funding
priorities, we also found that VA, like other agencies, has faced
underlying obstacles that have exacerbated its real property
management challenges and can also impact its ability to fully realign
its real property portfolio. We have previously reported that such
challenges include competing stakeholder interests, legal and
budgetary limitations, and capital planning processes that did not
always adequately address such issues as excess and underutilized
property.
Furthermore, we found that VA's capital planning efforts generally
reflected leading practices, but lacked transparency about the cost of
future priorities that could better inform decision making. For
example, VA's 2010-2015 capital plan linked its investments with its
strategic goals, assessed the agency's capital priorities, and
evaluated various alternatives. Also, SCIP strengthened VA's capital
planning efforts by extending the horizon of its 5-year plan to 10
years, and providing VA with a longer range picture of the agency's
future real property priorities. VA officials told us that SCIP builds
on its existing capital planning processes, addresses leading
practices, and further strengthens VA's efforts in some areas. We have
not fully assessed SCIP and it remains to be seen what impact SCIP
will have on the results of VA's capital planning efforts. While these
changes were positive steps, we found that VA's planning efforts
lacked transparency regarding the magnitude of costs of the agency's
future real property priorities, which may limit the ability of VA and
Congress to make informed funding decisions among competing
priorities. For instance, for potential future projects, VA's 2010-
2015 capital plan only listed project name and contained no
information on what these projects were estimated to cost or the
priority VA had assigned to them beyond what was then the current
budget year. Transparency about future requirements would benefit
congressional decision makers by putting individual project decisions
in a long-term, strategic context, and placing VA's fiscal situation
within the context of the overall fiscal condition of the U.S.
government. It is important to note that providing future cost
estimates to Congress for urgent, major capital programs is not
without precedent in the federal government. Other federal agencies,
such as the Department of Defense, have provided more transparent
estimates to Congress regarding the magnitude of its future capital
priorities beyond immediate budget priorities.
We concluded in our report that billions of dollars have already been
appropriated to VA to realign and modernize its portfolio.
Furthermore, VA had identified ongoing and future projects that could
potentially require several additional billion dollars over the next
few years to complete. Given the fiscal environment, VA and Congress
would benefit from a more transparent view of potential projects and
their estimated costs. Such a view would enable VA and Congress to
better evaluate the full range of real property priorities over the
next few years and, should fiscal constraints so dictate, identify
which might take precedence over the others. In short, more
transparency would allow for more informed decision making among
competing priorities, and the potential for improved service to
veterans over the long term would likely be enhanced. To enhance
transparency and allow for more informed decision making related to
VA's real property priorities, we recommended that the Secretary of
Veterans Affairs provide the full results of VA's SCIP process and any
subsequent capital planning efforts, including details on the
estimated cost of all future projects, to Congress on a yearly basis.
VA concurred with the recommendation. We have not yet assessed the
extent to which VA has implemented our recommendation in relation to
the President's 2012 budget.
Finally, I would also like to refer to a report we issued in December
2009, on VA construction.[Footnote 2] This report may be relevant to
today's discussion because it assessed VA's cost estimating approach
for major projects. We found that while about half of 32 major ongoing
construction projects we reviewed were within VA's budget, 18 projects
experienced cost increases, and 11 had experienced schedule delays
since they were first submitted to Congress. Five projects experienced
a cost increase of over 100 percent. There were several reasons for
construction project cost increases and schedule delays, including VA
preparing initial cost estimates that were not thorough, significant
changes to project scope after the initial estimate was submitted, and
unforeseen events such as an increase in the cost of construction
materials. VA had taken steps to improve initial construction project
cost estimates, but we reported that it could better assess the risks
to costs and schedules. We recommended that for all major projects, VA
conduct a cost risk analysis, a schedule risk analysis when
appropriate, and require the use of an integrated master schedule. VA
concurred with our recommendations.
Chairman Miller, Ranking Member Filner, and Members of the Committee,
this concludes my prepared remarks. I would be happy to answer any
questions that you may have.
For further information regarding this statement, please contact
Lorelei St. James at (202) 512-2834 or at stjamesl@gao.gov. Contact
points for our Offices of Congressional Relations and Public Affairs
may be found on the last page of this statement. David Sausville,
Assistant Director; George Depaoli; and Erica Miles also made key
contributions to this statement.
[End of section]
Footnotes:
[1] GAO, VA Real Property: Realignment Progressing, but Greater
Transparency about Future Priorities Is Needed, [hyperlink,
http://www.gao.gov/products/GAO-11-197] (Washington, D.C.: Jan. 31,
2011).
[2] GAO, VA Construction: VA Is Working to Improve Project Cost
Estimates, but Should Analyze Cost and Schedule Risks, [hyperlink,
http://www.gao.gov/products/GAO-10-189] (Washington D.C.: Dec, 14,
2009).
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: