Impact of Shortages of Processed Materials on Programs of Vital National Interest
Gao ID: PSAD-76-14 February 27, 1976During periods of shortages in processed materials, some Federal programs of vital national interest are delayed because they do not qualify as "defense related" and, therefore, cannot obtain priority ratings for procurement.
In 1973 and 1974 contractors were faced with producer-imposed material allocations, rapidly increasing procurement leadtimes, and rising prices. The situation was complicated by producers' imposing allocation systems on their customers and refusing to accept orders from new customers. Many of the countermeasures taken were basically good management practices which should have been employed earlier. The decision to provide priority support for civil and civilian programs should depend upon an independent and balanced assessment of urgent needs.
RecommendationsOur recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director: No director on record Team: No team on record Phone: No phone on record