Superfund
EPA's Costs to Remediate Existing and Future Sites Will Likely Exceed Current Funding Levels
Gao ID: GAO-10-857T June 22, 2010
This testimony summarizes the findings of our report on funding issues related to the Environmental Protection Agency's (EPA) Superfund program. To protect human health and the environment from the effects of hazardous substances, Congress enacted the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) in 1980, which established the Superfund program. Since 1980, EPA has identified more than 47,000 hazardous waste sites potentially requiring cleanup. As of the end of fiscal year 2009, 1,269 of the most seriously contaminated sites were included on EPA's National Priorities List (NPL): 1,111 nonfederal sites and 158 federal facilities. At the time of listing, EPA had determined that these sites posed relatively high risks to human health or the environment from releases or threatened releases of hazardous substances, such as lead and polychlorinated biphenyl. These substances can cause a variety of health effects--such as birth defects, cancer, and developmental disorders--in people exposed to them. Of the nonfederal sites listed on the NPL at the end of fiscal year 2009, EPA identified 75 that have "unacceptable human exposure"--actual or reasonably expected exposure of an individual to hazardous substances, pollutants, or contaminants at levels that present an unacceptable risk--to contaminants for people living, recreating, and/or working in the surrounding areas. In addition, another 164 of the sites listed on the NPL at the end of fiscal year 2009 may potentially pose serious risks since EPA is in the process of determining if there is unacceptable human exposure at these sites.
Over 60 percent of the 75 nonfederal NPL sites with unacceptable human exposure have all or more than half of the work remaining to complete remedial construction. According to EPA regional officials' responses to our survey, EPA has plans to control human exposure at all of the 75 sites with unacceptable human exposure; however, our survey results also show that EPA regional officials expect 41 of the sites to continue to have unacceptable exposure until fiscal year 2015 or later. Similarly, over 60 percent of the 164 nonfederal NPL sites with unknown human exposure have all or more than half of the work remaining to complete remedial construction, according to EPA regional officials' responses to our survey. The majority of the sites with unknown human exposure that have all of the work remaining to complete construction are in the remedial investigation phase, which is when EPA usually determines a site's human exposure status, according to EPA guidance. EPA may also designate a site as having unknown human exposure during the construction phase of work, or after a site has met the construction complete milestone, if new information suggests that there may be risk at the site, or if an investigation is under way to assess a potential exposure pathway not previously analyzed. EPA's annual costs to conduct remedial construction in the most efficient manner at nonfederal NPL sites for fiscal years 2010 through 2014 may range from $335 million to $681 million, according to EPA regional officials' estimates. These estimates include EPA's costs to conduct remedial actions at 142 of the 416 nonfederal sites that are not construction complete. For the remaining 274 sites, EPA regional officials were unable to provide cost estimates for 57 sites, expect responsible parties to fully fund remedial actions at 206 sites, and do not expect to incur additional costs to complete construction at 11 sites because these sites are already fully funded. These annual cost estimates for remedial construction at these sites exceed past annual funding allocations for such actions. For example, EPA regional officials' cost estimates for remedial construction for the next 2 years--fiscal years 2011 and 2012--are $253 million to $414 million greater than the $267 million in annual funding that EPA allocated for remedial actions in fiscal year 2009. From fiscal years 2000 through 2009, EPA allocated $220 million to $267 million in annual funding for remedial actions. According to EPA headquarters officials, however, funds from additional sources--such as prior year funds, settlements with responsible parties, and state cost share agreements--may also be available to fund remedial construction from year to year. While the amount of funding available through these sources may vary substantially from year to year, according to EPA headquarters officials, approximately $123 to $199 million was available from additional sources for remedial actions in fiscal years 2007 through 2009.
GAO-10-857T, Superfund: EPA's Costs to Remediate Existing and Future Sites Will Likely Exceed Current Funding Levels
This is the accessible text file for GAO report number GAO-10-857T
entitled 'Superfund: EPA's Costs to Remediate Existing and Future
Sites Will Likely Exceed Current Funding Levels' which was released on
June 22, 2010.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the Subcommittee on Superfund, Toxics and Environmental Health,
Committee on Environment and Public Works, United States Senate:
United States Government Accountability Office:
GAO:
For Release on Delivery:
Expected at 2:30 p.m. EDT:
Tuesday, June 22, 2010:
Superfund:
EPA's Costs to Remediate Existing and Future Sites Will Likely Exceed
Current Funding Levels:
Statement of John B. Stephenson, Director:
Natural Resources and Environment:
GAO-10-857T:
Mr. Chairman and Members of the Subcommittee:
I am pleased to be here to summarize the findings of our report on
funding issues related to the Environmental Protection Agency's (EPA)
Superfund program, which is being released today.[Footnote 1] To
protect human health and the environment from the effects of hazardous
substances, Congress enacted the Comprehensive Environmental Response,
Compensation, and Liability Act (CERCLA) in 1980, which established
the Superfund program.[Footnote 2] Since 1980, EPA has identified more
than 47,000 hazardous waste sites potentially requiring cleanup. As of
the end of fiscal year 2009, 1,269 of the most seriously contaminated
sites were included on EPA's National Priorities List (NPL): 1,111
nonfederal sites and 158 federal facilities.[Footnote 3] At the time
of listing, EPA had determined that these sites posed relatively high
risks to human health or the environment from releases or threatened
releases of hazardous substances, such as lead and polychlorinated
biphenyl. These substances can cause a variety of health effects--such
as birth defects, cancer, and developmental disorders--in people
exposed to them. Of the nonfederal sites listed on the NPL at the end
of fiscal year 2009, EPA identified 75 that have "unacceptable human
exposure"--actual or reasonably expected exposure of an individual to
hazardous substances, pollutants, or contaminants at levels that
present an unacceptable risk--to contaminants for people living,
recreating, and/or working in the surrounding areas. In addition,
another 164 of the sites listed on the NPL at the end of fiscal year
2009 may potentially pose serious risks since EPA is in the process of
determining if there is unacceptable human exposure at these sites.
[Footnote 4]
The Superfund cleanup process begins with the discovery of a
potentially hazardous site or the notification to EPA of possible
releases of hazardous substances that may threaten human health or the
environment. EPA regional offices use a screening system called the
Hazard Ranking System (HRS) to numerically assess sites' relative
potential threat to human health and the environment. The HRS scores
sites on four possible pathways of exposure: groundwater, surface
water, soil, and air. Those sites with sufficiently high scores are
eligible for proposal to the NPL.[Footnote 5] EPA regions submit these
sites to EPA headquarters for possible listing on the NPL on the basis
of a variety of additional factors, including the availability of
alternative state or federal programs and concurrence from the
governor of the state or environmental agency head in which the site
is located. Sites that EPA decides should be listed are proposed in
the Federal Register. After a period of public comment, EPA reviews
the comments and decides whether to formally list the sites as "final"
on the NPL.
Once EPA lists a site, it is typically cleaned up through EPA's
Superfund remedial program. EPA or a responsible party will begin the
remedial process by conducting a remedial investigation and
feasibility study to identify the nature and extent of contamination,
quantify potential risks, and evaluate potential remedies.[Footnote 6]
The culmination of these studies is a Record of Decision (ROD), which
identifies EPA's selected remedy for addressing the site's
contamination.[Footnote 7] The selected remedy is then designed during
remedial design and implemented with construction activities in the
remedial action phase, when actual cleanup of the site generally
begins. When all physical construction at a site is complete, all
immediate threats have been addressed, and all long-term threats are
under control, EPA generally considers the site to be "construction
complete." Of the 1,111 nonfederal sites listed on the NPL as of the
end of fiscal year 2009, 695 had reached EPA's construction complete
milestone, while the remaining 416 had not. Most sites then enter into
the operation and maintenance phase, when the responsible party or the
state maintains the remedy and EPA ensures that the remedy continues
to protect human health and the environment. Eventually, when EPA and
the state determine that no further site response is needed, EPA may
delete the site from the NPL.[Footnote 8]
NPL cleanup efforts are typically expensive and can take many years.
While responsible parties are liable for conducting or paying for site
cleanup of hazardous substances, in some cases, parties cannot be
identified or may be unwilling or financially unable to perform the
cleanup. To fund EPA-led cleanups at nonfederal NPL sites, EPA uses
the Hazardous Substance Superfund (trust fund) from which EPA receives
annual appropriations. Historically, the trust fund was financed
primarily by taxes on crude oil and certain chemicals, as well as an
environmental tax on corporations based on their taxable income;
however, the authority for these taxes expired in 1995,[Footnote 9]
and shortly thereafter the balance in the trust fund started
diminishing. Since 2001, appropriations from general revenues have
been the largest source of funding for the trust fund. At the start of
fiscal year 2009, the trust fund had a balance of $137 million.
Superfund program appropriations have averaged about $1.2 billion
annually since 1981, although the annual level of these appropriated
funds has generally declined in recent years when adjusted for
inflation.
In fiscal year 2009, EPA received about $1.29 billion for the
Superfund program, of which approximately $605 million was for the
remedial program.[Footnote 10] Of this amount, EPA allocated $125
million for preconstruction activities--remedial investigation,
feasibility study, and remedial design activities--as well as other
nonconstruction activities, including conducting prelisting activities
through cooperative agreements with states, oversight of all
responsible party-lead activities, and providing general support and
management. In addition, EPA allocated $267 million for remedial
actions. EPA allocated the remaining $213 million for headquarters and
regional personnel to implement and oversee the overall program; for
site management; and for providing technical and analytical support
for all non-NPL sites as well as proposed, final, and deleted NPL
sites. In addition, as part of the American Recovery and Reinvestment
Act of 2009 (Recovery Act), EPA's Superfund remedial program received
an additional $600 million.[Footnote 11]
My testimony today summarizes highlights from our report.
Specifically, I will discuss (1) the cleanup and funding status at
currently listed nonfederal NPL sites with unacceptable or unknown
human exposure, (2) what is known about the future costs to EPA to
conduct remedial actions at nonfederal NPL sites that are not
construction complete, (3) the process EPA uses to allocate remedial
program funding, and (4) the number of sites EPA and selected state
officials expect will be added to the NPL over the next 5 years, and
what they expect the costs of cleaning up those sites will be.
The findings of our report are based on an electronic survey of branch
chiefs from the 10 EPA regions; data from EPA's Comprehensive
Environmental Response, Compensation, and Liability Information System
and Integrated Financial Management System; EPA guidance and planning
documents; and interviews with officials from EPA headquarters and
regional offices, 10 selected states, and the Association of State and
Territorial Solid Waste Management Officials. The report contains a
detailed overview of our scope and methodology. This work was
conducted in accordance with generally accepted government auditing
standards. Those standards require that we plan and perform the audit
to obtain sufficient, appropriate evidence to provide a reasonable
basis for our findings and conclusions based on our audit objectives.
We believe that the evidence obtained provides a reasonable basis for
our findings and conclusions based on our audit objectives.
Considerable Work Remains at Most Nonfederal NPL Sites with
Unacceptable or Unknown Human Exposure, and Some Site Cleanups Have
Not Been Funded at the Most Efficient Level:
As detailed in our report, over 60 percent of the 75 nonfederal NPL
sites with unacceptable human exposure have all or more than half of
the work remaining to complete remedial construction. According to EPA
regional officials' responses to our survey, EPA has plans to control
human exposure at all of the 75 sites with unacceptable human
exposure; however, our survey results also show that EPA regional
officials expect 41 of the sites to continue to have unacceptable
exposure until fiscal year 2015 or later.[Footnote 12] Similarly, over
60 percent of the 164 nonfederal NPL sites with unknown human exposure
have all or more than half of the work remaining to complete remedial
construction, according to EPA regional officials' responses to our
survey. The majority of the sites with unknown human exposure that
have all of the work remaining to complete construction are in the
remedial investigation phase, which is when EPA usually determines a
site's human exposure status, according to EPA guidance. EPA may also
designate a site as having unknown human exposure during the
construction phase of work, or after a site has met the construction
complete milestone, if new information suggests that there may be risk
at the site, or if an investigation is under way to assess a potential
exposure pathway not previously analyzed.
Since CERCLA was passed in 1980 through the end of fiscal year 2009,
EPA reported expending a total of $3 billion in constant 2009 dollars
on the 75 sites with unacceptable exposure and $1.2 billion in
constant 2009 dollars on the 164 sites where exposure is unknown.
[Footnote 13] However, despite the relatively high level of
expenditures at sites with unacceptable human exposure, EPA regional
and headquarters officials told us that construction has not been
conducted in the most timely and cost-efficient manner at some of
these sites because EPA had to balance limited annual resources among
various program activities. At the Eureka Mills site in Utah, people
who are in contact with soil and dust contaminated with lead from
mining activities face human health risks. From 2003 to 2008, the site
received $6.6 million to $10 million a year for construction, even
though regional officials said that an additional $3 to $5 million per
year would have allowed them to complete construction at the site 3 to
4 years earlier at a reduced overall cost. However, with the addition
of $26.5 million for the Eureka Mills site in fiscal year 2009 from
Recovery Act funding, officials said that they will be able to
complete construction at least 1 year earlier than planned and control
human exposure at the site. In response to our survey, EPA regional
officials noted that they are using Recovery Act funding to partially
or completely control the unacceptable human exposure at 20 NPL sites.
However, despite EPA's use of Recovery Act funds to control human
exposure at these sites, EPA officials noted that EPA's constrained
funding has caused delays in the control of human exposure at some
sites.
EPA's Costs for Conducting Remedial Construction at Nonfederal NPL
Sites Will Likely Exceed Recent Funding Levels for These Activities:
As we noted in our report, EPA's annual costs to conduct remedial
construction in the most efficient manner at nonfederal NPL sites for
fiscal years 2010 through 2014 may range from $335 million to $681
million, according to EPA regional officials' estimates (see table 1).
[Footnote 14] These estimates include EPA's costs to conduct remedial
actions at 142 of the 416 nonfederal sites that are not construction
complete. For the remaining 274 sites, EPA regional officials were
unable to provide cost estimates for 57 sites, expect responsible
parties to fully fund remedial actions at 206 sites, and do not expect
to incur additional costs to complete construction at 11 sites because
these sites are already fully funded.
Table 1: EPA Regional Officials' Estimates of Costs to EPA to Conduct
Remedial Construction in the Most Efficient Manner at Existing
Nonfederal Sites on the NPL, as of September 30, 2009:
Fiscal year: 2010;
Cost: $412 million.
Fiscal year: 2011;
Cost: $681 million.
Fiscal year: 2012;
Cost: $520 million.
Fiscal year: 2013;
Cost: $420 million.
Fiscal year: 2014;
Cost: $335 million.
Fiscal year: 2015 and beyond;
Cost: $3.036 billion.
Source: GAO analysis of EPA regional officials' responses to our
survey.
Note: These data include EPA's cost estimates for 142 of the 416
nonfederal sites that are not construction complete. For the remaining
274 sites, EPA was unable to provide annual cost estimates for 57
sites, EPA indicated that responsible parties are fully funding
remedial actions at 206 sites, and EPA does not expect to incur
additional costs to complete construction at 11 sites. Unless
otherwise specified, these numbers are as reported by EPA, and are not
adjusted for inflation by GAO.
[End of table]
These annual cost estimates for remedial construction at these sites
exceed past annual funding allocations for such actions. For example,
EPA regional officials' cost estimates for remedial construction for
the next 2 years--fiscal years 2011 and 2012--are $253 million to $414
million greater than the $267 million in annual funding that EPA
allocated for remedial actions in fiscal year 2009. From fiscal years
2000 through 2009, EPA allocated $220 million to $267 million in
annual funding for remedial actions. According to EPA headquarters
officials, however, funds from additional sources--such as prior year
funds, settlements with responsible parties, and state cost share
agreements--may also be available to fund remedial construction from
year to year. While the amount of funding available through these
sources may vary substantially from year to year, according to EPA
headquarters officials, approximately $123 to $199 million was
available from additional sources for remedial actions in fiscal years
2007 through 2009. Our analysis indicates that, even if this level of
funding were available in future years, it would not supplement EPA's
annual funding allocation enough to cover the estimated costs for
conducting remedial construction in fiscal years 2011 and 2012.
Therefore, despite funding from additional sources, EPA's estimated
costs to conduct remedial construction will exceed available funds if
funding for remedial construction remains constant.
Furthermore, these annual cost estimates are likely understated. These
officials were not able to provide annual construction cost estimates
for 57 of the 416 nonfederal sites that are not yet construction
complete because they are in the early stages of the remedial process,
and EPA does not yet know the extent of the contamination and/or has
not chosen a cleanup remedy for them.[Footnote 15] For some additional
sites, EPA regional officials were unable to provide cost estimates
for construction at some of the operable units at the site. In
addition, EPA regional officials' estimates did not include costs for
conducting long-term response actions--such as operating groundwater
treatment facilities--which are considered part of the remedial
action, or for performing 5-year site reviews, both of which EPA funds
from its remedial action allocation and would, therefore, increase the
cost estimate for remedial actions.
EPA's estimates also did not include construction costs for sites that
currently have a potentially responsible party that may be unable to
fund the cleanup. EPA officials told us that EPA has identified one or
more potentially responsible parties at 206 of the 416 nonfederal NPL
sites that are not yet construction complete. However, officials also
said that they were slightly or not at all confident that a
responsible party would fund future remedial actions at 27 of these
sites.
EPA headquarters and regional officials also told us that EPA's actual
costs for construction are typically higher than its cost estimates
because of a number of uncertainties. Most importantly, according to
EPA officials, the extent of contamination at a site is often greater
than EPA expected when it developed the cost estimate, which can
expand the scope of work and remedies needed and increase overall
construction costs. For example, we recently reported that at the
Federal Creosote Superfund site in New Jersey, the greater-than-
expected quantities of contaminated material contributed to a $111
million increase in construction costs over EPA's estimates.[Footnote
16] Another factor that can increase construction costs is a change in
acceptable contaminant levels. In addition, according to EPA, the
actual costs of goods and services--such as energy, construction
materials, and labor--may increase above estimated prices, causing an
increase in the actual construction cost. EPA officials noted that
there may be some instances when construction costs are overestimated
because, for example, there is less contamination at a site than
previously thought or the prices of goods and services decrease;
however, the officials commented that this is rare. The frequent
occurrence of additional unexpected costs enhances the likelihood that
EPA's costs for remedial actions over the next several years will
exceed recent funding levels for these activities, and EPA may be
forced to choose between funding construction at some sites in the
most efficient manner or funding construction at more sites less
efficiently.
EPA Allocates Remedial Program Funding Separately for Preconstruction
Activities and Remedial Actions, and Limited Funding Has Caused Delays
at Some Sites:
As explained in our report, EPA allocates funds separately for pre-
construction activities--such as remedial investigation and remedial
design--and remedial actions. EPA headquarters allocates funds for pre-
construction activities to the regions for them to distribute among
sites. EPA headquarters determines the amount of resources that the
Superfund program will allocate to the regions by using a model that
distributes available funding based on a combination of historical
allocations and a work-based scoring system that scores each region
based on projects planned for the upcoming year.[Footnote 17]
According to EPA's Superfund Program Implementation Manual, at the
initiation of the planning process, headquarters provides general
projections of funding for preconstruction activities that will be
available to the regions. On the basis of these projections, each
region then develops a plan for allocating these funds to sites.
Before finalizing this plan, each region holds planning discussions
with headquarters to discuss actions that can be accomplished during
the year and alters its plans, as needed, based on refined projections
of available funding from headquarters.
To allocate funding for remedial actions, EPA headquarters works in
consultation with the regions to allocate funds on a site-by-site
basis. EPA's Superfund Program Implementation Manual states that sites
with ongoing construction receive priority for funding over new
construction work. Headquarters develops the initial plan for ongoing
construction based on regional funding requests, projections of
available funding, and discussions with regional officials. According
to EPA, the agency's goal in allocating funds is to ensure that all
sites with ongoing construction continue to progress toward
construction completion while also funding some new construction
projects.
According to EPA headquarters and regional officials, the funds for
both preconstruction activities and remedial actions have not been
sufficient to clean up some sites in the most timely and cost-
efficient manner. EPA officials from several regions told us that
their regions currently receive about half or less than half of the
funding they could use for preconstruction activities. As a result,
according to our survey, which collected data on fiscal years 2000
through 2009, most regions have sites that have experienced delays in
the preconstruction phase because of insufficient funding. Similarly,
sites with ongoing construction have experienced delays caused by
limited funding, according to EPA officials. Since fiscal year 2000,
most regions have experienced delays because of insufficient funding
at one or more sites with ongoing construction, according to responses
to our survey. According to several EPA regional officials, delays in
funding for sites with ongoing construction increase the length of
time it takes to clean up a site; the total cost of cleanup; and, in
some cases, the length of time populations are exposed to
contaminants. In addition, funding limitations have caused delays at
sites that were ready to begin new construction. According to EPA
Superfund Accomplishment Reports, between fiscal years 2004 and 2008,
54 sites, or over one-third of all sites ready for new construction
funding, were not funded in the year that they were ready to begin
construction, and some sites were not funded for several years after
they were construction-ready.
EPA officials told us that EPA prioritized sites to receive the $582
million in American Recovery and Reinvestment Act funds allocated to
remediation in a manner similar to the way EPA prioritizes sites for
remedial actions. According to EPA headquarters officials, 25 sites
needing new construction funding in fiscal year 2009 would most likely
not have received funding had Recovery Act funding not been available.
Most EPA Regional and Selected State Officials Expect an Increase in
the Number of Sites Added to the NPL over the Next 5 Years but Cannot
Estimate the Cleanup Costs:
Our report also notes that most of the EPA regional officials and
state officials we interviewed told us they expect the number of sites
listed on the NPL over the next 5 years will be greater than the
number listed in the past 5 years. EPA regional officials estimate
that from 101 to 125 sites--an average of 20 to 25 sites per year--
will be added to the NPL over the next 5 years. This is higher than
the 79 sites--an average of about 16 sites per year--added from fiscal
years 2005 through 2009. As table 2 shows, all EPA regions expect that
the number of sites added to the NPL over the next 5 years from their
region could increase. According to EPA headquarters officials, the
number of sites proposed for listing over time has decreased as a
result of the expanded use of other cleanup programs, including state
programs. Most of the officials who expect an increase in listings
noted that current economic conditions--which can limit states'
abilities to clean up sites under their own programs and responsible
parties' abilities to pay for cleanup--are a contributing factor to
the expected increase in listed sites.
Table 2: Comparison of the Number of Sites EPA Listed from Fiscal Year
2005 through 2009 and the Number of Sites Projected to Be Listed from
Fiscal Years 2010 through 2014, by Region:
EPA region: 1;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 3;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 3 to 5;
Projected change in the number of sites listed: 0 to + 2.
EPA region: 2;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 12;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 15 to 20;
Projected change in the number of sites listed: + 3 to 8.
EPA region: 3;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 8;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 10 to 15;
Projected change in the number of sites listed: + 2 to 7.
EPA region: 4;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 14;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 20 to 25;
Projected change in the number of sites listed: + 6 to 11.
EPA region: 5;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 14;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 20;
Projected change in the number of sites listed: + 6.
EPA region: 6;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 9;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 10 to 15;
Projected change in the number of sites listed: + 1 to 6.
EPA region: 7;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 8;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 10;
Projected change in the number of sites listed: + 2.
EPA region: 8;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 4;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 5;
Projected change in the number of sites listed: + 1.
EPA region: 9;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 4;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 3 to 5;
Projected change in the number of sites listed: -1 to + 1.
EPA region: 10;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 3;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 5;
Projected change in the number of sites listed: + 2.
EPA region: All regions;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 79;
Number of sites EPA regional officials project will be added to the
NPL over the next 5 years: 101 to 125;
Projected change in the number of sites listed: + 22 to 46.
Sources: GAO analysis based upon EPA data and regional officials'
projections.
[End of table]
Most of the officials we spoke with in the 10 selected states also
expect that the number of sites listed from their states over the next
5 years could increase above the number of sites listed over the past
5 years, as table 3 shows. For example, officials from the Michigan
Department of Natural Resources and Environment said that they expect
EPA to list five sites in Michigan to the NPL over the next 5 years,
even though no sites have been listed from their state since 1996.
These officials noted that the Superfund program has traditionally
been a program of last resort, but declining resources in their
state's cleanup program have renewed Michigan's interest in cleaning
sites up through the federal program.
Table 3: Comparison of the Number of Sites EPA Listed from Each of the
10 States from Fiscal Years 2005 through 2009 and the Number of Sites
State Officials Project May Be Listed from Fiscal Years 2010 through
2014, by State:
State: Maine;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 0;
Number of sites state officials project will be added from their
states to the NPL over the next 5 years: 1 to 2;
Projected change in the number of sites listed: + 1 to 2.
State: New Jersey;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 6;
Number of sites state officials project will be added from their
states to the NPL over the next 5 years: 15 to 25;
Projected change in the number of sites listed: + 9 to 19.
State: Virginia;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 1;
Number of sites state officials project will be added from their
states to the NPL over the next 5 years: 1;
Projected change in the number of sites listed: 0.
State: Kentucky;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 0;
Number of sites state officials project will be added from their
states to the NPL over the next 5 years: 0 to 1;
Projected change in the number of sites listed: 0 to + 1.
State: Michigan;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 0;
Number of sites state officials project will be added from their
states to the NPL over the next 5 years: 5;
Projected change in the number of sites listed: + 5.
State: Louisiana;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 0;
Number of sites state officials project will be added from their
states to the NPL over the next 5 years: 1;
Projected change in the number of sites listed: + 1.
State: Iowa;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 0;
Number of sites state officials project will be added from their
states to the NPL over the next 5 years: 0;
Projected change in the number of sites listed: 0.
State: Montana;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 1;
Number of sites state officials project will be added from their
states to the NPL over the next 5 years: 1 to 2;
Projected change in the number of sites listed: 0 to + 1.
State: California;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 3;
Number of sites state officials project will be added from their
states to the NPL over the next 5 years: 5;
Projected change in the number of sites listed: + 2.
State: Washington;
Number of sites EPA listed from fiscal year 2005 through fiscal year
2009: 2;
Number of sites state officials project will be added from their
states to the NPL over the next 5 years: 1 to 4;
Projected change in the number of sites listed: -1 to + 2.
Sources: GAO analysis based upon EPA data and state agency officials'
projections.
[End of table]
Neither EPA regional officials nor state officials we contacted were
able to provide cost estimates for many of the sites they expect to be
added to the NPL over the next 5 years. Furthermore, when these
officials were able to provide cost estimates, most of them were
imprecise figures based on limited knowledge and best professional
judgment. Officials also explained that they could not provide cost
estimates for some of the sites, because either the type and extent of
contamination are not yet known, or officials have not yet identified
the actual sites that may be listed. Therefore, it is impossible to
accurately estimate what the cost may be to clean up these sites.
However, we reported in July 2009 that the average amount EPA spent to
clean up individual sites has increased in recent years.[Footnote 18]
For example, EPA spent an average of approximately $7.5 million at
sites that reached EPA's construction complete milestone in fiscal
year 1999. EPA's expenditures increased to an average of about $10.2
million in total expenditures per site at sites reaching construction
complete in fiscal year 2007. In that report, we noted that individual
site costs may have increased because the sites on the NPL now are
more complex than in the past, construction costs have been rising,
and EPA has not been able to identify as many responsible parties to
fund site cleanups as in the past, leaving a higher share for EPA to
fund.
In addition to the number of sites that could be listed, the number of
sites eligible for the NPL could increase if EPA begins to assess, as
a part of its listing process, the risk of vapor intrusion caused by
subsurface hazardous substances that have migrated via the air into
homes and commercial properties. Although sites with vapor intrusion
can pose considerable human health risks, EPA's HRS--the mechanism
used to identify sites that qualify for NPL listing--does not
currently recognize these risks; therefore, unless a site with vapor
intrusion is listed on some other basis--such as groundwater
contamination--EPA cannot clean up the site using remedial program
funding. Many EPA regional officials and state officials noted that
vapor intrusion is a concern, and several of these officials told us
that they believe additional sites would be eligible for listing if
assessments of vapor intrusion were included as part of the listing
process. According to an EPA headquarters official, based on recent
discussions with regional officials, up to 37 sites could be eligible
for NPL listing if EPA includes vapor intrusion assessments as part of
the listing process. However, according to EPA headquarters officials,
EPA must first determine whether or not it can consider the vapor
intrusion pathway under its existing HRS regulations, and it has not
yet made such a determination. While these sites are not currently
eligible for NPL listing, the EPA headquarters official noted that EPA
is addressing vapor intrusion at 13 of these sites through its
Superfund removal program; however, this official also told us that,
when conducting removal actions, EPA is limited in its ability to
fully remediate the source of contamination. For example, according to
an official from the Montana Department of Environmental Quality,
preliminary data collected at the Billings PCE site[Footnote 19]--
which the official noted is not eligible for NPL listing--indicated
vapor intrusion in buildings, and EPA conducted a removal action at
this site. However, according to this official, it is unclear whether
the removal action was effective in mitigating the vapor intrusion
contamination, and people may continue to be exposed.
In conclusion, we found that limited funding for the Superfund program
has caused delays in cleaning up some sites in recent years. This
limited funding, coupled with increasing costs of cleanup, has forced
EPA to choose between cleaning up a greater number of sites more
slowly at higher cost and cleaning up fewer sites more quickly at
lower cost. Compounding these challenges, EPA does not currently
assess the relative risk posed by vapor intrusion when deciding which
sites to include on the NPL, and assessing this risk could lead to an
increase in the number of sites listed on the NPL. However, if these
sites are not assessed and, if needed, listed on the NPL, some
seriously contaminated hazardous waste sites with unacceptable human
exposure may not be cleaned up. In our report being released today, we
are recommending that the Administrator of EPA determine the extent to
which EPA will consider vapor intrusion as part of the NPL listing
process and how this will affect the number of sites listed in the
future. EPA agreed with our recommendation.
Mr. Chairman, this concludes my prepared statement. I would be pleased
to respond to any questions that you or Members of the Subcommittee
may have at this time.
GAO Contact and Staff Acknowledgments:
For questions about this statement, please contact John Stephenson at
(202) 512-3841 or stephensonj@gao.gov. Individuals making key
contributions to this testimony include Barbara Patterson and Vincent
P. Price, Assistant Directors; Deanna Laufer; and Kyerion Printup.
Elizabeth Beardsley, Pamela Davidson, and Mehrzad Nadji also made
important contributions.
[End of section]
Footnotes:
[1] GAO, Superfund: EPA's Estimated Costs to Remediate Existing Sites
Exceed Current Funding Levels, and More Sites Are Expected to Be Added
to the National Priorities List, [hyperlink,
http://www.gao.gov/products/GAO-10-380] (Washington, D.C.: May 6,
2010).
[2] Pub. L. No. 96-510 (1980), codified, as amended, at 42 U.S.C. §§
9601-9675 (2010).
[3] The 158 federal facilities are owned and operated by federal
agencies, such as the Departments of Defense, Energy, and the Interior.
[4] At the remaining 872 sites, EPA has determined that human exposure
has been controlled, but additional work to clean up the sites may
still be needed. EPA refers to sites with unacceptable human exposure
as "current human exposures not under control" and sites with unknown
human exposure as "insufficient data to determine human exposure
control status."
[5] While the HRS is the principal mechanism EPA uses to place sites
on the NPL, two additional mechanisms can also be used. More
specifically, a site can be listed regardless of score if a state or
territory designates the site as its single top-priority site. In
addition, a site may be listed if the Agency for Toxic Substances and
Disease Registry of the U.S. Public Health Service has issued a health
advisory that recommends removing people from the site, EPA determines
the site poses a significant threat to public health, and EPA
anticipates it will be more cost-effective to use its remedial
authority than to use its emergency removal authority to respond to
the site.
[6] For certain remedial actions, additional work at a site may be
required after construction is completed, such as continuing
groundwater restoration efforts or monitoring the site to ensure that
the remedy remains protective. For EPA-lead remedial actions that have
a groundwater or surface water restoration component, EPA funds the
necessary activities--known as long-term response actions--for up to
10 years before turning over these responsibilities to the state.
[7] Cleanup at a site is often divided into smaller units (operable
units) by geography, pathways of contamination, or type of remedy.
[8] Although most sites progress through the cleanup process in
roughly the same way, EPA may take different approaches based on site-
specific conditions.
[9] The budget proposed by the administration for fiscal year 2011
reflects legislative proposals to reestablish a tax to support the
Superfund program.
[10] The remaining $680 million was for other activities, such as
emergency response and removal, enforcement, and operations and
administration.
[11] Of the $600 million, EPA allocated $582 million to remedial
cleanup activities and $18 million to internal EPA activities related
to the management, oversight, and reporting of Superfund Recovery Act
funds.
[12] Thirty of the 41 sites that EPA regional officials expect will
continue to pose unacceptable risk until fiscal year 2015 or later are
"teenager sites"--sites that have been on the NPL for at least 13
years.
[13] These totals include construction costs and all other
appropriated site-specific Superfund expenditures through fiscal year
2009, except for reimbursable and homeland security supplemental
expenditures.
[14] Our survey asked EPA regional officials to provide the
approximate projected costs to EPA to complete construction at a site
in the most efficient manner, given what is currently known about
contamination at a site. EPA regional officials provided cost
estimates based on various information, including ROD estimates,
estimates developed during remedial design or construction, and
estimates developed during remedial investigations and feasibility
studies. According to EPA officials, cost estimates for individual
fiscal years for a site may change because of a number of factors,
such as a site's construction readiness and contracting delays.
[15] For 9 of the 57 sites, EPA officials did provide a broad range of
costs for construction, but we did not include those costs in our
analysis because EPA officials were unable to provide more precise,
annual cost figures for those sites.
[16] GAO, Superfund: Information on Cost and Other Issues Related to
the Cleanup of the Federal Creosote Site, [hyperlink,
http://www.gao.gov/products/GAO-10-277] (Washington, D.C.: February
25, 2010).
[17] As part of this allocation, EPA headquarters includes funding for
other nonconstruction activities, including conducting prelisting
activities through cooperative agreements with states, oversight of
all responsible party-lead activities, and providing general support
and management.
[18] GAO, Superfund: Litigation Has Decreased and EPA Needs Better
Information on Site Cleanup and Cost Issues to Estimate Future Program
Funding Requirements, [hyperlink,
http://www.gao.gov/products/GAO-09-656] (Washington, D.C.: July 15,
2009).
[19] PCE is perchloroethylene, which is a manufactured chemical used
for dry cleaning and metal degreasing. Potential health effects from
exposure to PCE include dizziness, headaches, sleepiness, confusion,
nausea, difficulty in speaking and walking, loss of consciousness, and
death.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: