Progress Being Made on Deepwater Project, but Risks Remain Gao ID: GAO-01-564 May 2, 2001

The Coast Guard is in the final stages of planning the largest procurement project in its history-the modernization or replacement of more than 90 cutters and 200 aircraft used for missions more than 50 miles from shore. This project, called the Deepwater Capability Replacement Project, is expected to cost more than $10 billion and take 20 years or longer to complete. Congress and the Coast Guard are at a major crossroads with the project. Planning is essentially complete, and Congress will soon be asked to commit to a multibillion-dollar project that will define the way the Coast Guard performs many of its missions for decades to come. The deepwater acquisition strategy is unique and untried for a project of this magnitude. It carries many risks that could potentially cause significant schedule delays and cost increases. The project faces risks in the following four areas: (1) planning the project around annual funding levels far above what the administration has told the Coast Guard it can expect to receive, (2) keeping costs under control in the contract's later years, (3) ensuring that procedures and personnel are in place for managing and overseeing the contractor once the contract is awarded, and (4) minimizing potential problems with developing unproven technology. All of these risks can be mitigated to varying degrees, but not without management attention.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone:


The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.