Procedures Used for Holding Architects and Engineers Responsible for the Quality of Their Design Work
Gao ID: LCD-76-333 July 14, 1977Government contracts with architects and engineers require the provision of all design and engineering information necessary for preparing plans and specifications. When contract modifications (change orders) are issued because of architect and engineer negligence, the resulting costs are recoverable.
Some Federal agencies are not adequately documenting causes for errors and omissions in plans and specifications prepared by architects and engineers (A/Es) even though required to do so. Consequently, the agencies paid millions of dollars without determining responsibility. This precludes the Government from recovering potential costs from A/Es in instances where the A/E performed negligently. The Government should not pay increased construction costs where the A/E is responsible. Enforcing already existing procedures and other steps could reduce change order costs and help the Government better enforce A/E liability. Added costs of litigation against contractors for negligence will be offset, at least partly, by savings from not paying change order costs. Better evaluations of A/E performance are needed.
RecommendationsOur recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director: No director on record Team: No team on record Phone: No phone on record