Financial Audit
Restatement to the General Services Administration's Fiscal Year 2003 Financial Statements
Gao ID: GAO-06-70R December 6, 2005
The Secretary of the Treasury, in coordination with the Director of the Office of Management and Budget (OMB), is required to annually prepare and submit audited financial statements of the U.S. government to the President and Congress. We are required to audit these consolidated financial statements (CFS) and report on the results of our work. An issue meriting concern and close scrutiny that emerged during our fiscal year 2004 CFS audit was the growing number of Chief Financial Officers (CFO) Act agencies that restated certain of their financial statements for fiscal year 2003 to correct errors. Errors in financial statements can result from mathematical mistakes, mistakes in the application of accounting principles, or oversight or misuse of facts that existed at the time the financial statements were prepared. Frequent restatements to correct errors can undermine public trust and confidence in both the entity and all responsible parties. Further, when restatements do occur, it is important that financial statements clearly communicate, and readers of the restated financial statements understand, that the financial statements originally issued by management in the previous year and the opinion thereon should no longer be relied on and instead the restated financial statements and related auditor's opinion should be used. Because of the varying nature and circumstances surrounding the restatements, we are issuing a number of separate reports on the matter. This report communicates our observations regarding GSA's fiscal year 2003 restatement. Going forward, we hope that the lessons learned from the fiscal year 2003 restatement, together with our recommendations, will help GSA and its auditor avoid the need for restatements to GSA's future financial statements. We reviewed four key areas with respect to the restatement of GSA's fiscal year 2003 financial statements: (1) the nature and cause of the errors that necessitated the restatement, including planned corrective actions by the agency and its auditors; (2) the timing of communicating the material misstatement to users of the financial statements; (3) the extent of transparency exhibited in disclosing the nature and impact of the material misstatement in the financial statements and the reissued auditor's report; and (4) audit issues that contributed to the failure to detect the errors that necessitated the restatement during the audit of the agency's fiscal year 2003 financial statements.
Improperly transferring costs related to one major construction project out of the Construction in Process (CIP) account and into the Buildings account led to the material misstatement that necessitated the restatement of two separate and distinct line items on GSA's originally issued fiscal year 2003 Balance Sheet. Specifically, at fiscal year 2003 year end, GSA recorded an adjusting journal entry to transfer about $952 million of construction costs from the CIP account to the Buildings account. This amount was derived based on a statistical sample of construction projects included in GSA's unadjusted year-end balance for the CIP account. The largest project included in GSA's statistical sample was a multiphase project totaling about $68.6 million, which was incorrectly classified as substantially complete at that time. This incorrect classification, when projected to the population of CIP projects, was the basis for about $921 million of the $952 million, or over 96 percent, of the estimated costs transferred at year end. GSA's auditor did not detect the error because its fiscal year 2003 audit tests were not adequately designed to test the validity of GSA's transfers of construction costs between the two accounts. Although the journal entry used to record the transfer between the accounts involved a material amount and GSA's contracted independent public accountant (IPA) had reported a reportable condition relating to CIP transfers in its previous two years audit reports, in our view, the IPA did not adequately understand the significant components underlying this journal entry. As a result, the IPA randomly selected 10 projects from GSA's statistical sample of 99 projects and did not review the above noted project that GSA had incorrectly classified. Further, in our view, the title of GSA's note disclosure of the restatement could be misinterpreted.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-06-70R, Financial Audit: Restatement to the General Services Administration's Fiscal Year 2003 Financial Statements
This is the accessible text file for GAO report number GAO-06-70R
entitled 'Financial Audit: Restatement to the General Services
Administration's Fiscal Year 2003 Financial Statements' which was
released on December 6, 2005.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
December 6, 2005:
Ms. Kathleen M. Turco:
Chief Financial Officer:
General Services Administration:
The Honorable Brian D. Miller:
Inspector General:
General Services Administration:
Subject: Financial Audit: Restatement to the General Services
Administration's Fiscal Year 2003 Financial Statements:
As you know, the Secretary of the Treasury, in coordination with the
Director of the Office of Management and Budget (OMB), is required to
annually prepare and submit audited financial statements of the U.S.
government to the President and Congress. We are required to audit
these consolidated financial statements (CFS) and report on the results
of our work.[Footnote 1] An issue meriting concern and close scrutiny
that emerged during our fiscal year 2004 CFS audit was the growing
number of Chief Financial Officers (CFO) Act agencies that
restated[Footnote 2] certain of their financial statements for fiscal
year 2003 to correct errors.[Footnote 3] Errors in financial statements
can result from mathematical mistakes, mistakes in the application of
accounting principles, or oversight or misuse of facts that existed at
the time the financial statements were prepared. Frequent restatements
to correct errors can undermine public trust and confidence in both the
entity and all responsible parties. Further, when restatements do
occur, it is important that financial statements clearly communicate,
and readers of the restated financial statements understand, that the
financial statements originally issued by management in the previous
year and the opinion thereon should no longer be relied on and instead
the restated financial statements and related auditor's opinion should
be used.
Eleven of the 23 CFO Act agencies[Footnote 4] restated certain of their
financial statements for fiscal year 2003. Five CFO Act agencies had
restatements in fiscal year 2003 covering their fiscal year 2002
financial statements. Three CFO Act agencies had restatements covering
both years. We noted that the extent of the restatements to CFO Act
agencies' fiscal year 2003 financial statements varied from agency to
agency, ranging from correcting two line items on one agency's balance
sheet to correcting numerous line items on several of another agency's
financial statements. In some cases, the net operating results of the
agency were affected by the restatement. The amounts of the agencies'
restatements ranged from several million dollars to more than $91
billion.
Nine of the 11 agencies that had restatements for fiscal year 2003
received unqualified opinions on their originally issued fiscal year
2003 financial statements. The auditors for 6 of these 9 agencies
issued unqualified opinions on the restated financial statements,
replacing the previous unqualified opinions on the respective agencies'
original fiscal year 2003 financial statements. The auditors for 2 of
these 9 withdrew their unqualified opinions on the fiscal year 2003
financial statements and issued other than unqualified opinions on the
respective agencies' restated fiscal year 2003 financial statements
because they could not determine whether there were any additional
misstatements and the effect of any such misstatements on the restated
fiscal year 2003 financial statements. For the remaining agency, the
principal auditor of the agency's fiscal year 2004 financial statements
was not the principal auditor of the agency's fiscal year 2003
financial statements, and an audit opinion on the agency's restated
fiscal year 2003 financial statements was not issued.
Our review focused on the 9 agencies with restatements for fiscal year
2003 that received unqualified opinions on their originally issued
fiscal year 2003 financial statements.[Footnote 5] These were the
Department of Agriculture, Department of State, Department of Justice,
Department of Transportation, Department of Health and Human Services,
General Services Administration (GSA), National Science Foundation,
Nuclear Regulatory Commission, and Office of Personnel Management.
Because of the varying nature and circumstances surrounding the
restatements, we are issuing a number of separate reports on the
matter. This report communicates our observations regarding GSA's
fiscal year 2003 restatement. Going forward, we hope that the lessons
learned from the fiscal year 2003 restatement, together with our
recommendations, will help GSA and its auditor avoid the need for
restatements to GSA's future financial statements.
We reviewed four key areas with respect to the restatement of GSA's
fiscal year 2003 financial statements: (1) the nature and cause of the
errors that necessitated the restatement, including planned corrective
actions by the agency and its auditors; (2) the timing of communicating
the material misstatement to users of the financial statements; (3) the
extent of transparency[Footnote 6] exhibited in disclosing the nature
and impact of the material misstatement in the financial statements and
the reissued auditor's report; and (4) audit issues that contributed to
the failure to detect the errors that necessitated the restatement
during the audit of the agency's fiscal year 2003 financial statements.
Results in Brief:
Improperly transferring costs related to one major construction project
out of the Construction in Process (CIP)[Footnote 7] account and into
the Buildings account led to the material misstatement that
necessitated the restatement of two separate and distinct line items on
GSA's originally issued fiscal year 2003 Balance Sheet. Specifically,
at fiscal year 2003 year end, GSA recorded an adjusting journal entry
to transfer about $952 million of construction costs from the CIP
account to the Buildings account. This amount was derived based on a
statistical sample of construction projects included in GSA's
unadjusted year-end balance for the CIP account. The largest project
included in GSA's statistical sample was a multiphase project totaling
about $68.6 million, which was incorrectly classified as substantially
complete[Footnote 8] at that time. This incorrect classification, when
projected to the population of CIP projects, was the basis for about
$921 million of the $952 million, or over 96 percent, of the estimated
costs transferred at year end.
GSA's auditor did not detect the error because its fiscal year 2003
audit tests were not adequately designed to test the validity of GSA's
transfers of construction costs between the two accounts. Although the
journal entry used to record the transfer between the accounts involved
a material amount and GSA's contracted independent public accountant
(IPA) had reported a reportable condition relating to CIP transfers in
its previous two years audit reports, in our view, the IPA did not
adequately understand the significant components underlying this
journal entry. As a result, the IPA randomly selected 10 projects from
GSA's statistical sample of 99 projects and did not review the above
noted project that GSA had incorrectly classified. Further, in our
view, the title of GSA's note disclosure of the restatement could be
misinterpreted.
We are recommending that GSA's CFO ensures that GSA fully and
effectively implements control procedures to properly transfer costs
from the CIP account to the Buildings account. We are also making a
recommendation to GSA's Inspector General to work with the IPA so that
audit procedures to sufficiently test for any similar errors in the
transfer of amounts from the CIP account to the Buildings account in
the future are implemented.
GSA, along with its Inspector General concurred with our
recommendations for ensuring reliable balances in the CIP and Buildings
accounts. In separate responses on a draft of this report, they
described the accounting and auditing procedures planned to avoid
similar restatements of this nature in the future.
Background:
In conducting the fiscal year 2004 audit of the CFS, we reviewed the 23
CFO Act agencies' performance and accountability reports for possible
restatements and identified 11 agencies that had restated certain of
their audited fiscal year 2003 financial statements.
The primary intended users of federal agencies' financial reports are
citizens, Congress, federal executives, and federal program
managers.[Footnote 9] Each of these groups may use federal agencies'
financial statements to satisfy their specific needs. Citizens are
interested in many aspects of the federal government, particularly
federal programs that affect their financial well-being. Congress is
interested in monitoring and assessing the efficiency and effectiveness
of federal programs. Federal executives, such as central agency
officials at OMB and the Department of the Treasury (Treasury), are
interested in federal financial statements to assist the President of
the United States. OMB assists the President in overseeing the
preparation of the federal budget by formulating the President's
spending plans, evaluating the effectiveness of agency programs,
assessing competing funding demands among agencies, and setting funding
priorities. Treasury assists the President in managing the finances of
the federal government and prepares the CFS, which is based on audited
financial statements prepared by federal agencies. GAO audits the CFS
and reports on the results of its audit. Finally, federal program
managers use agency financial statements as tools for managing their
operations within the limits of the spending authority granted by
Congress.
The primary accounting and auditing standards that apply to restatement
disclosures by federal entities are the Federal Accounting Standards
Advisory Board's Statement of Federal Financial Accounting Standards
(SFFAS) No. 21, Reporting Corrections of Errors and Changes in
Accounting Principles, and the American Institute of Certified Public
Accountants (AICPA) Codification of Auditing Standards, AU section 561,
Subsequent Discovery of Facts Existing at the Date of the Auditor's
Report.[Footnote 10]
Objective, Scope, and Methodology:
The objective of our review of the restatement of GSA's fiscal year
2003 financial statements was to determine the nature and cause of the
errors, the transparency and timing of communicating the material
misstatements, any audit issues relating to such misstatements, and any
actions being taken to help preclude similar errors from occurring in
the future.
We reviewed the nature and causes of the restatement, and we also
examined corrective action plans to be implemented by GSA to help
preclude similar errors from occurring in the future. We interviewed
the preparers and auditors of GSA's fiscal year 2003 financial
statements, including staff from the agency's Office of Inspector
General (OIG), and we obtained and reviewed relevant audit
documentation. Our work was not designed to and we did not test the
accuracy or appropriateness of the restatement.
In our review, we considered certain accounting and auditing standards,
including SFFAS No. 21; the Financial Accounting Standards Board's
Statement of Financial Accounting Standards No. 16, Prior Period
Adjustments; and the AICPA Codification of Auditing Standards, AU
section 420, Consistency of Application of Generally Accepted
Accounting Principles, AU section 508, Reports on Audited Financial
Statements, and AU section 561.
We performed our review of the restatement of GSA's fiscal year 2003
financial statements from December 2004 to October 2005 in accordance
with U.S. generally accepted government auditing standards.
We requested comments on the draft of this report from GSA's CFO and
Inspector General or their designees. Written comments from GSA's
Acting Administrator and Inspector General are reprinted in enclosures
I and II, respectively, and are also discussed in the Agency Comments
section.
Issues Related to Restatement of GSA's Fiscal Year 2003 Balance Sheet:
With respect to the restatement of GSA's fiscal year 2003 Balance
Sheet, we identified the following three areas that need improvement:
(1) identification of substantially complete CIP transfers, (2) design
of audit procedures relating to adjusting journal entries used to
transfer amounts from the CIP account, and (3) the title of the note
disclosure of the restatement. These issues are discussed in detail
below.
Adjustment to CIP and Buildings Accounts Were Erroneous:
GSA's Balance Sheet for fiscal year 2003 was restated because of an
error in the adjusting journal entry that was used to transfer
approximately $952 million of estimated costs from the CIP account to
the Buildings account. The error caused the Buildings line item on the
Balance Sheet to be materially overstated by approximately $921 million
and the CIP line item on the Balance Sheet to be materially understated
by this same amount.
The CIP general ledger account includes construction of, and major
improvements and renovation projects to, buildings that GSA owns and
leases to other federal entities. Upon substantial completion, certain
costs are to be transferred to the appropriate Property and Equipment
(P&E) asset account. The transfer from the CIP account to the
appropriate P&E account is necessary for proper classification of
assets in the Balance Sheet as well as accurate and complete reporting
of depreciation expenses. Depreciation is not calculated and recorded
until the asset is transferred from CIP to the appropriate asset
account.
When a new CIP project is established, regional personnel are expected
to enter all necessary information, including the expected date of
completion into the Inventory Reporting Information System (IRIS) that
GSA management uses to monitor the status of construction projects.
Construction costs are accumulated in the CIP account. Once a project
is substantially complete, the project manager is supposed to enter the
date of substantial completion into IRIS so that the CIP account
project costs will be automatically transferred into the Real Property
Accounting Depreciation System (RPADS). Also, building projects that
meet certain capitalization criteria and are determined to have been
substantially completed during the reporting period should be
transferred to the Buildings account from the CIP account.
Transfers of the costs of substantially completed projects from the CIP
to the appropriate P&E account are necessary for proper classification
of the related assets in the Balance Sheet. For fiscal year 2003, GSA's
net Buildings account and CIP account totaled about 52 percent of its
total assets. However, according to the IPA's fiscal year 2004 Report
on Internal Control, since fiscal year 2001, GSA has experienced
problems related to cost transfers from CIP to the appropriate P&E
account. Specifically, the IPA's report noted that GSA's Public
Buildings Service (PBS) controls over transferring substantially
complete CIP projects continue to need improvement.
GSA has been aware that weaknesses in these processes can lead to the
failure to recognize the completion of construction projects on a
timely basis. Among the causes of the underlying weaknesses previously
reported by GSA's auditor are regional personnel not entering
completion dates in IRIS, and manual procedures performed by central
staff not addressing all CIP issues. In order to mitigate these control
weaknesses, each quarter GSA's PBS uses a random statistical sample to
assess the accuracy of data in its RPADS and makes an adjusting journal
entry to correct for any errors for reporting purposes.
Based on PBS's review of a statistical sample of projects still
classified in IRIS as CIP at the end of fiscal year 2003, GSA recorded
an adjusting journal entry to transfer about $952 million of estimated
costs from the CIP account to the Buildings account. In September 2004,
during GSA's OIG review of GSA's quarterly financial statements, the
OIG discovered an error in the agency's classification of the largest
project included in GSA's end of fiscal year 2003 statistical sample.
Specifically, the OIG found that PBS incorrectly classified a $68.6
million multiphase project from the fiscal year 2003 CIP sample as
substantially complete when it should have remained in CIP. PBS
identified the multiphase project as substantially complete without
obtaining written documentation from the region responsible for the
project to support such a determination. This incorrect classification,
when projected to the population of CIP projects, was the basis for
about $921 million of the approximately $952 million of the estimated
costs that were transferred. As a result, GSA's adjusting journal entry
to transfer approximately $952 million in estimated costs from the CIP
account to the Buildings account was overstated by about $921 million.
GSA's OIG communicated the error to GSA management and to the IPA in
September 2004, which was appropriate. After researching the issue, GSA
management concurred that the error warranted an adjustment to restate
the CIP and Buildings line items on the fiscal year 2003 Balance Sheet.
To reduce the risk of similar errors in the future, GSA officials told
us that GSA has refined its methodology for determining the CIP
transfer amounts. Starting with fiscal year 2005, GSA will semi-
annually review all of the CIP projects over $7 million and
statistically sample the remaining lower cost CIP projects to develop
an adjusting journal entry, if necessary. In addition, according to
GSA's Corrective Action Plan, GSA intends to improve its controls over
transferring substantially complete CIP projects by enforcing its
control procedures at the project level to ensure that all
substantially complete and only substantially complete CIP projects are
transferred out of the CIP account. GSA's plan calls for GSA regions to
make entries into a weekly nationwide CIP Progress Report to certain
GSA officials regarding the number of projects: (1) with no substantial
completion date, (2) with substantial completion dates in the past, and
(3) marked to be completed in the current month. In addition, according
to GSA's Plan, PBS intends to work with regions to develop regional
action plans that enforce entering timely substantial completion dates
at the project level.
Auditor's Procedures Were Not Adequately Designed to Detect Error in
the Transfer of CIP Costs:
The above-noted error was not discovered during the audit of GSA's
fiscal year 2003 financial statements because the fiscal year 2003
audit procedures performed by GSA's IPA were not adequately designed to
detect the error. The journal entry used to record the transfer between
the accounts involved a material amount and GSA's IPA had reported a
reportable condition relating to CIP transfers in its previous two
years audit reports. In addition, as noted above, over 96 percent of
the estimated costs that were transferred resulted from the incorrectly
classified multiphase project. Nevertheless, the IPA randomly selected
10 projects from GSA's statistical sample of 99 projects and did not
review the largest cost project in the sample, which is the above noted
project that GSA had incorrectly classified.
The Financial Audit Manual (FAM)[Footnote 11] states that during the
audit planning process, the auditor should identify conditions that
significantly increase inherent, fraud, and control risk. Among other
things, the auditor should perform procedures to identify account
balances and transactions that might signal inherent risk. According to
FAM 260.40, the auditor should obtain an understanding of the financial
reporting process and the controls over journal entries and other
adjustments; identify and select journal entries and other adjustments
for testing; determine the nature, timing, and extent of the testing;
and inquire of individuals involved in the financial reporting process
about inappropriate or unusual activity related to the processing of
journal entries and adjustments. In our view, if the IPA had had a
better understanding of the significant components of the calculations
used to determine the material adjusting journal entry that transferred
construction costs from the CIP account to the Buildings account and
had then designed and performed sufficient audit procedures over such
components, the error that necessitated the restatement might have been
detected.
According to GSA's IPA, future audits will include testing more
projects from GSA's sample. Specifically, the IPA intends to increase
the sample size from 10 to about 45. Given the known risks in this
area, it will be important for the IPA to perform adequate audit
procedures over any significant adjusting journal entries made by GSA
to transfer CIP costs.
The Title of GSA's Note Disclosure of the Restatement Could Be
Misinterpreted:
The notes to GSA's comparative fiscal years 2004 and 2003 financial
statements included a note disclosure titled "Prior Period
Reclassification." In our view, this title could be misinterpreted,
since the note disclosure discussed the adjustment to correct the $921
million material misstatement and the adjustment represented a
restatement as defined by SFFAS No. 21 rather than a prior period
reclassification.
Conclusions:
The restatement was caused by an error that GSA's OIG identified. GSA
corrected the error and issued restated financial statements. Going
forward, the key will be for GSA to ensure that the planned corrective
actions established to help prevent future errors in the transfer of
CIP costs are fully and effectively implemented. In addition, it will
be important that GSA's OIG work with GSA's IPA so that audit
procedures to detect any similar errors in the future are fully and
effectively implemented.
Recommendations for Executive Action:
We recommend that GSA's Chief Financial Officer ensure that GSA fully
and effectively implements control procedures to properly transfer
costs from the CIP account to the Buildings account.
We recommend that GSA's Inspector General, work with GSA's IPA so that
audit procedures to sufficiently test adjusting journal entries related
to the transfer of amounts from the CIP account to the Buildings
account are fully and effectively implemented.
Agency Comments:
In commenting on a draft of this report, GSA's Acting Administrator
stated that GSA concurs with our recommendation to implement control
procedures to properly transfer costs from the CIP account to the
Buildings account and has made changes in the statistical sample
process as we acknowledged in our report. He also stated that GSA
developed a weekly report that is sent to the regional offices to
highlight the CIP projects where the estimated substantial completion
date is overdue, missing, or scheduled to occur within 30 days to
assist in ensuring the CIP projects are accurately capitalized and
depreciated in a timely fashion. GSA's Inspector General concurred with
our recommendation and stated that his office will continue to work
with the IPA regarding auditing the transfer of CIP to the Buildings
account and that since fiscal year 2003, the IPA's testing in this area
has expanded to reduce the likelihood that a similar error would occur
in the future. He also stated that his office will continue to monitor
the IPA's efforts to plan and perform its tests of the adjusting
journal entries related to the transfer of amounts from the CIP account
to the Buildings account.
Within 60 days of the date of this report, we would appreciate
receiving a written statement on actions taken to address these
recommendations.
We are sending copies of this report to the Chairmen and Ranking
Minority Members of the Senate Committee on Homeland Security and
Governmental Affairs; the Subcommittee on Federal Financial Management,
Government Information, and International Security, Senate Committee on
Homeland Security and Governmental Affairs; the House Committee on
Government Reform; and the Subcommittee on Government Management,
Finance and Accountability, House Committee on Government Reform. In
addition, we are sending copies to the Fiscal Assistant Secretary of
the Treasury and the Controller of OMB. This report is also available
at no charge on GAO's Web site at www.gao.gov.
We appreciate the courtesy and cooperation extended to us by your staff
throughout our work. We look forward to continuing to work with your
offices to help improve financial management in the federal government.
If you have any questions about the contents of this report, please
contact me at (202) 512-3406 or engelg@gao.gov.
Signed by:
Gary T. Engel:
Director:
Financial Management and Assurance:
Enclosure I: Comments from the Acting Administrator, General Services
Administration:
GSA Administrator:
November 28, 2005:
The Honorable David M. Walker:
Comptroller General of the United States:
Government Accountability Office:
Washington, DC 20548:
Dear Mr. Walker:
The General Services Administration (GSA) appreciates this opportunity
to review and provide comments to the Government Accountability
Office's (GAO's) draft report, FINANCIAL AUDIT: Restatement to the
General Services Administration's Fiscal Year 2003 Financial
Statements, GAO-06-70R.
The draft report recommends that GSA's Chief Financial Officer ensure
that GSA fully and effectively implements control procedures to
properly transfer costs from the Construction in Process (CIP) account
to the Buildings account.
GSA concurs with the recommendations to implement controls procedures
to properly transfer cost from the CIP account to Buildings account and
has made changes in the statistical sample process as you acknowledged
in the report. Specifically, beginning with the September 2004
statistical sample, the Public Buildings Service (PBS) Chief Financial
Officer's (CFO's) Office required the Regional Offices to provide
documentation that supports the status of the project as of the date
the sample was pulled. In addition, beginning in March 2005, the sample
process was restructured to segregate the CIP universe into strata.
Stratum one contains all projects over $7 million dollars in addition
to some other special projects that are reviewed 100 percent, thus
eliminating the need to project the error rates on large projects over
the population. These projects are reviewed every quarter and represent
approximately 75 percent of the total adjusted CIP account balance.
Stratum two contains all projects that make up 1 percent of the
adjusted CIP account balance. Stratum three contains all remaining CIP
projects. A statistical sample is drawn semi-annually from both Stratum
two and three and the error rate is projected over each Stratum's
universe. Also, the PBS CFO's Office developed a weekly report that is
sent to the regional offices to highlight the CIP projects where the
Estimated Substantial Completion date is overdue, missing, or scheduled
to occur within 30 days. The report highlights those projects to assist
in ensuring the CIP projects are accurately capitalized and depreciated
in a timely fashion.
Should you have any questions, please contact Kathleen M. Turco, Acting
Deputy Administrator. Staff inquiries may be directed to Mr. Donzell
Jackson, Director, Financial Consulting and Analysis Division at (202)
501-0110.
Sincerely,
Signed by:
David L. Bibb:
Acting Administrator:
[End of section]
Enclosure II: Comments from the Inspector General, General Services
Administration:
U.S. GENERAL SERVICES ADMINISTRATION:
Office of Inspector General:
NOV 21 '05:
Mr. Gary T. Engel:
Director:
Financial Management and Assurance:
Government Accountability Office:
441 G St., NW:
Washington, DC 20548:
Dear Mr. Engel:
Thank you for the opportunity to respond to your report entitled,
Financial Audit. Restatements to the General Services Administration's
Fiscal Year 2003 Financial Statements.
Your report recommends "GSA's Inspector General work with GSA's
independent public accountant (IPA) so that audit procedures to
sufficiently test adjusting journal entries related to the transfer of
amounts from the Construction in Progress (CIP) account to the
Buildings account are fully and effectively implemented." We concur
with your recommendation, and continue to work with GSA's IPA regarding
the transfer of CIP to the Building account. Since Fiscal Year 2003,
the IPA's testing in this area has expanded to reduce the likelihood
that a reclassification would occur in the future. The IPA has achieved
this through segregating the CIP population and increasing the sample
size. We will continue to monitor the IPA's efforts to plan and perform
its tests of the adjusting journal entries related to the transfer of
amounts from the CIP account to the Buildings account.
We understand and appreciate the impact of financial statement errors
on the public's trust and confidence in GSA and the Federal Government
as a whole, and remain deeply committed to working with GSA's IPA to
ensure that tests are sufficient. If you should have any questions or
would like to discuss this issue further, please contact Eugene
Waszily, Assistant Inspector General for Auditing, of my staff on (202)
501-0374.
Sincerely,
Signed by:
Brian D. Miller:
Inspector General:
[End of section]
(198396):
FOOTNOTES
[1] The Government Management Reform Act of 1994 has required such
reporting, covering the executive branch of government, beginning with
financial statements prepared for fiscal year 1997. 31 U.S.C. § 331
(e). The federal government has elected to include certain financial
information on the legislative and judicial branches in the CFS as
well.
[2] A financial statement restatement occurs when an entity either
voluntarily or prompted by its auditors or regulators revises public
financial information that has previously been reported.
[3] According to Federal Accounting Standards Advisory Board, Statement
of Federal Financial Accounting Standards (SFFAS) No. 21, Reporting
Corrections of Errors and Changes in Accounting Principles, prior
period financial statements presented should be restated only to
correct errors that caused such statements to be materially misstated.
[4] The Federal Emergency Management Agency (FEMA) was transferred to
the Department of Homeland Security (DHS) effective March 1, 2003. With
this transfer, FEMA was no longer required to prepare and have audited
stand-alone financial statements under the CFO Act, leaving 23 CFO Act
agencies for the remainder of fiscal year 2003 and for fiscal year
2004. The DHS Financial Accountability Act, Pub. L. No. 108-330, 118
Stat. 1275 (Oct. 16, 2004), added DHS to the list of CFO Act agencies,
increasing the number of CFO Act agencies again to 24 beginning in
fiscal year 2005.
[5] The 2 agencies that had restatements for fiscal year 2003 but did
not receive unqualified opinions on their originally issued fiscal year
2003 financial statements were the Department of Defense and the Small
Business Administration.
[6] Transparency is the full, accurate, and timely disclosure of
information.
[7] The United States General Ledger uses the term Construction in
Progress, but GSA presents this account as Construction in Process in
the fiscal year 2003 financial statements. We will use the term
Construction in Process (CIP) to refer to the account.
[8] According to the IPA's Property Cycle memorandum, GSA defines
substantial completion as the date when GSA can use the constructed
item for its intended use. Substantial completion is not equivalent to
the completion date for the contract. Substantial completion is also
the date for the transfer of the project from the work in process
account to the Buildings account.
[9] Federal Accounting Standards Advisory Board, Statement of Federal
Financial Accounting Concepts No. 1, Objectives of Federal Financial
Reporting.
[10] Generally accepted government auditing standards incorporate AICPA
reporting standards and Statements on Auditing Standards unless the
Comptroller General of the United States excludes them by formal
announcement.
[11] GAO/President's Council on Integrity and Efficiency, Financial
Audit Manual, GAO-01-765G (Washington, D.C.: July 2001), updated by GAO-
04-1015G and GAO-04-924G (July 2004).