Space Science

Status of the Hubble Space Telescope Program Gao ID: NSIAD-88-118BR May 2, 1988

Pursuant to a congressional request, GAO provided information regarding the National Aeronautics and Space Administration's (NASA) Hubble Space Telescope (HST) Program, focusing on: (1) the program's current cost, schedule, and performance status; (2) the Space Telescope Science Institute's role in the program; and (3) NASA orbital maintenance plans for the telescope.

GAO found that: (1) technical and management difficulties and a space shuttle accident delayed the telescope's launch, now scheduled for June 1989; (2) this delay increased estimated development costs from $435 million in 1978 to over $1.4 billion; (3) estimated operations, maintenance, and refurbishment costs total about $2.8 billion through fiscal year 1993; (4) HST program and NASA officials are extensively testing the telescope; (5) NASA contracted with the Space Telescope Science Institute to solicit and select astronomers' HST observational proposals and to collect, archive, and distribute HST data; (6) NASA has a memorandum of agreement with the European Space Agency to provide the Institute with 15 full-time staff to assist it in disseminating data in Europe; (7) NASA plans to provide the Institute with funds to allocate to American scientists' and certain American-employed foreign nationals' observational proposals; and (8) NASA is studying ways to reduce the number of maintenance and reboost missions currently necessary.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.