Space Shuttle

NASA's Major Changes to Flight Hardware Gao ID: NSIAD-88-173FS June 27, 1988

In response to a congressional request, GAO identified the types of changes that the National Aeronautics and Space Administration (NASA) made to the space shuttle's flight hardware, focusing on enhancements: (1) it made to flight hardware; (2) that cost at least $5 million each; and (3) it implemented from 1981 through 1987.

GAO found that NASA: (1) made 56 changes to the space shuttle; (2) initiated 31 changes before the Challenger accident and 25 after the accident; (3) budgeted about $403 million in three increments through 1993; (4) awarded a $198.2 million development contract for the first increment; and (5) estimated that the cost of the changes would total about $2.4 billion. GAO also found that the primary justifications for making the changes included: (1) studies which evaluated existing system designs; (2) the high costs of repairing outdated equipment; (3) improving the reliability of existing components; (4) demonstrating and improving component capabilities; (5) correcting components that were not fully functioning as designed or as necessary; (6) replacing obsolete parts; and (7) increasing safety.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.