Pursuant to a congressional request, GAO reviewed the National Aeronautics and Space Administration's (NASA) Orbital Maneuvering Vehicle (OMV) program, focusing on: (1) the need to continue the OMV program in light of reductions in OMV capabilities; and (2) the reasons for changes in OMV program costs and schedules.

GAO found that: (1) the OMV conceptual design has evolved over a number of years; (2) NASA estimated that OMV development would cost $736.5 million; (3) through fiscal year (FY) 1990, Congress appropriated $245.6 million, and NASA requested $85.4 million for OMV in its FY 1991 budget; (4) NASA does not need OMV to accomplish the primary missions for which it was designed; (5) in 1989, NASA restructured the OMV program to contain costs, and reduced or eliminated many planned OMV capabilities; (6) NASA has not yet decided to undertake any of the missions it has identified as potential applications for OMV; (7) OMV costs will likely continue to rise, especially if NASA is to make maximum use of the vehicle; (8) NASA is considering purchasing an additional vehicle, restoring capabilities, and modifying OMV to make it compatible with expendable launch vehicles; and (9) because of uncertainty about when and for what purposes OMV would be used, NASA has not prepared a comprehensive estimate of OMV operations costs.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone:


The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.