Space Projects

Status and Remaining Challenges of the Advanced X-ray Astrophysics Facility Gao ID: NSIAD-92-77 February 28, 1992

The Advanced X-ray Astrophysics Facility is being designed for NASA at an estimated cost of about $2 billion. Since fiscal year 1989, the program's estimated cost has risen by about 23 percent and its launch schedule has slipped by two years, mainly because of budget cuts imposed by NASA and Congress. To keep program costs down, NASA has used part of its cost reserves being held for future unanticipated changes and has reduced the number of spare parts it plans to buy, a move that has increased the program's schedule risk. Further cost increases could result if NASA launches the observatory on an expendable launch vehicle rather than the space shuttle. Test results to date show that the first pair of mirrors has met the requirements for mirror resolution mandated by Congress, and NASA expects overall mirror performance to meet contractual standards. NASA will have to overcome several challenges, however, if it is to successfully launch and operate the observatory.

GAO found that: (1) since fiscal year 1989, the program's estimated cost has increased from $1.6 billion to $1.9 billion, an increase of $380 million; (2) although there has been some cost growth in the program, most of the increase can be attributed to schedule stretchouts caused by budget cuts; (3) in order to keep program costs from increasing, NASA plans to reduce the number of spare parts it will purchase and use a portion of the cost reserves it is holding for future unanticipated changes; (4) reducing spare parts increases the program's schedule risk, since certain parts cannot be replaced quickly; (5) if NASA decides to launch the observatory on an expendable launch vehicle rather than the space shuttle, it could cost up to $286 million to redesign the observatory and an additional $250 million for a launch vehicle; (6) NASA was required to fabricate and test the largest pair of mirrors to an exact standard for mirror resolution before beginning other tasks and test results completed in September 1991 showed that the mirrors met the requirement; (7) NASA believes that those test results to date provide confidence that all pairs of mirrors, when assembled, will meet the contractual standard for collecting and focusing X-rays; and (8) before it can launch the observatory, NASA must resolve such challenges as developing additional test equipment, other observatory components, and science instruments.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.