NASA
Assessments of Selected Large-Scale Projects
Gao ID: GAO-11-239SP March 3, 2011
GAO's work has shown that the National Aeronautics and Space Administration's (NASA) large-scale projects, while producing groundbreaking research and advancing our understanding of the universe, tend to cost more and take longer to develop than planned, and are often approved without evidence of a sound business case. Although space development is complex and diffi cult by nature, GAO has found that inherent risks are compounded by the need for better management and oversight practices. GAO has designated NASA's acquisition management a high risk area. This report provides a snapshot of how well NASA is planning and executing its acquisition of selected large-scale projects. It also provides observations about the performance of NASA's major projects and project management, outlines steps NASA is taking to improve its acquisitions, identifi es challenges that contribute to cost and schedule growth, and assesses 21 NASA projects, each with an estimated life-cycle cost of over $250 million.
GAO assessed 21 NASA projects with a combined life-cycle cost that exceeds $68 billion. Of those 21 projects, 16 had entered the implementation phase where cost and schedule baselines were established. Development costs for the 16 projects had an average growth of $94 million--or 14.6 percent--and schedules grew by an average of 8 months. The total increase in development costs for these projects was $1.5 billion. GAO found that 5 of the 16 projects were responsible for the overwhelming majority of this increase. The issue of cost growth is more signifi cant than the 14.6 percent average would indicate because it does not capture the cost growth that occurred before several projects reported baselines in response to a statutory requirement in 2005. Specifi cally, the 13 projects that GAO has reviewed over the past 3 years that established baselines prior to 2009 experienced an average development cost growth of almost 55 percent, with a total increase in development costs of almost $2.5 billion from their original confi rmation baselines. This does not refl ect considerable cost and schedule growth that will likely be experienced by NASA's largest science program--the James Webb Space Telescope (JWST). Based on the fi ndings of the independent panel that recently reviewed the JWST project and information that we obtained from project offi cials, it is likely that JWST will report signifi cant cost and schedule growth, estimated to be $1.4 billion or more and up to 15 months, respectively. Many of the projects GAO reviewed for this report experienced challenges in the areas of technology, design, funding, launch vehicles, development partner performance, parts, and contractor management. Reducing the kinds of challenges this assessment identifi es in acquisition programs hinges on developing a sound business case for a project. The development and execution of a knowledge-based business case for these projects can provide early recognition of challenges, allow managers to take corrective action, and place needed and justifi able projects in a better position to succeed. The inherent complexity of space development programs should not preclude NASA from achieving what it promises when requesting and receiving funds. In response to GAO's designation of NASA's acquisition management as a high risk area, NASA has developed a corrective action plan to improve the effectiveness of acquisition project management. The plan identifi es fi ve areas for improvement, each of which contains targets and goals to measure improvement. As part of this initiative, the agency is continuing its implementation of a new cost estimation tool, the Joint Cost and Schedule Confi dence Level, to help project offi cials with management, cost and schedule estimating, and maintenance of adequate levels of reserves. GAO is not making any new recommendations in this report. Instead GAO is issuing another report concurrently (GAO-11- 364R) that describes in more detail some of the issues identified in this report, such as transparency in project costs and lack of a consistent design metric, and will make recommendations to address the issues.
GAO-11-239SP, NASA: Assessments of Selected Large-Scale Projects
This is the accessible text file for GAO report number GAO-11-239SP
entitled 'NASA: Assessments of Selected Large-Scale Projects' which was
released on March 3, 2011.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
United States Government Accountability Office:
GAO:
February 2011:
Report to Congressional Committees:
NASA:
Assessment of Selected Large-Scale Projects:
GAO-11-239SP:
GAO Highlights:
Highlights of GAO-11-239SP, a report to congressional committees.
Why GAO Did This Study:
GAO‘s work has shown that the National Aeronautics and Space
Administration‘s (NASA) large-scale projects, while producing ground-
breaking research and advancing our understanding of the universe,
tend to cost more and take longer to develop than planned, and are
often approved without evidence of a sound business case. Although
space development programs are complex and difficult by nature, GAO
has found that inherent risks are exacerbated by poor management and
oversight practices. GAO has designated NASA‘s acquisition management
as a high risk area since 1990.
This report provides a snapshot of how well NASA is planning and
executing its acquisition of selected large-scale projects. It also
provides observations about the performance of NASA‘s major projects
and project management, outlines steps NASA is taking to improve its
acquisitions, identifies challenges that contribute to cost and
schedule growth, and assesses 21 NASA projects, each with an estimated
life-cycle cost of over $250 million.
No recommendations are provided in this report; however, GAO has
reported extensively and made recommendations on NASA acquisition
management in the past. We will also be making recommendations on
enhancing transparency and accountability in a separate letter to NASA.
What GAO Found:
GAO assessed 21 NASA projects with a combined life-cycle cost that
exceeds $68 billion. Of those 21 projects, 16 had entered the
implementation phase where cost and schedule baselines were
established. Development costs for the 16 projects had an average
growth of $94 million-”or 14.6 percent-”and schedules grew by an
average of 8 months. The total increase in development costs for these
projects was $1.5 billion. GAO found that 5 of the 16 projects were
responsible for the overwhelming majority of this increase. The issue
of cost growth is more significant than the 14.6 percent average would
indicate because it does not capture the cost growth that occurred
before several projects reported baselines in response to a statutory
requirement in 2005. Additionally, the 13 projects that GAO has
reviewed over the past 3 years that established baselines prior to
2009 experienced an average development cost growth of almost 55
percent, with a total increase in development costs of almost $2.5
billion from their original confirmation baselines. This does not
reflect considerable cost and schedule growth that will likely be
experienced by NASA‘s largest science program”-the James Webb Space
Telescope (JWST). Based on the findings of the independent panel that
recently reviewed the JWST project and information we obtained from
projects officials, it is likely that JWST will report significant
cost and schedule growth, estimated to be $1.4 billion or more and up
to 15 months, respectively.
Many of the projects GAO reviewed for this report experienced
challenges in the areas of technology, design, funding, launch
vehicles, development partner performance, parts, and contractor
management. Reducing the kinds of challenges this assessment
identifies in acquisition programs hinges on developing a sound
business case for a project. The development and execution of a
knowledge-based business case for these projects can provide early
recognition of challenges, allow managers to take corrective action,
and place needed and justifiable projects in a better position to
succeed. The inherent complexity of space development programs should
not preclude NASA from achieving what it promises when requesting and
receiving funds.
In response to GAO‘s designation of NASA‘s acquisition management as a
high risk area, NASA has developed a corrective action plan to improve
the effectiveness of acquisition project management. The plan
identifies five areas for improvement, each of which contains targets
and goals to measure improvement. As part of this initiative, the
agency is continuing its implementation of a new cost estimation tool,
the Joint Cost and Schedule Confidence Level, to help project
officials with management, cost and schedule estimating, and
maintenance of adequate levels of reserves.
View [hyperlink, http://www.gao.gov/products/GAO-11-239SP] or key
components. For more information, contact Cristina Chaplain at (202)
512-4841 or chaplainc@gao.gov.
[End of section]
Contents:
Foreword:
Letter:
Background:
Observations on NASA‘s Portfolio of Major Projects:
Observations from Our Assessment of Knowledge Attained by Key
Junctures in the Acquisition Process:
Observations on Other Challenges That Can Affect Project Outcomes:
Observations about NASA‘s Continued Efforts to Improve Its
Acquisition Management:
Project Assessments:
Aquarius:
Ares I Crew Launch Vehicle:
Global Precipitation Measurement (GPM) Mission:
Glory:
Gravity Recovery and Interior Laboratory (GRAIL:
Ice, Cloud, and Land Elevation Satellite-2 (ICESat-2):
James Webb Space Telescope (JWST):
Juno:
Landsat Data Continuity Mission (LDCM):
Lunar Atmosphere and Dust Environment Explorer (LADEE):
Magnetospheric Multiscale (MMS):
Mars Atmosphere and Volatile EvolutioN (MAVEN):
Mars Science Laboratory (MSL):
NPOESS Preparatory Project (NPP):
Orbiting Carbon Observatory 2 (OCO-2):
Orion Crew Exploration Vehicle:
Radiation Belt Storm Probes (RBSP):
Soil Moisture Active and Passive (SMAP):
Solar Probe Plus (SPP):
Stratospheric Observatory for Infrared Astronomy (SOFIA):
Tracking and Data Relay Satellite (TDRS) Replenishment:
Agency Comments and Our Evaluation:
Appendixes:
Appendix I: Comments from the National Aeronautics and Space
Administration:
Appendix II: Objectives, Scope, and Methodology:
Appendix III: Technology Readiness Levels:
Appendix IV: GAO Contact and Staff Acknowledgments:
Tables:
Table 1: Selected Major NASA Projects Reviewed in GAO Annual
Assessments:
Table 2: Cost and Schedule Growth of Selected NASA Projects
Currently in the Implementation Phase:
Table 3: Cost Growth from Confirmation for Selected Major NASA
Projects That Established Baselines Prior to Fiscal Year 2009:
Table 4: ARRA Funding for Reviewed NASA Projects:
Table 5: Schedule Growth for Selected NASA Projects with and without
Development Partners Baselined before 2009:
Figures:
Figure 1: NASA‘s Life Cycle for Flight Systems:
Figure 2: Summary of Projects Assessed by Phase of the NASA Project
Life Cycle:
Figure 3: Percentage of Major NASA Projects That Moved into
Implementation with Immature Technologies at the Preliminary
Design Review:
Figure 4: Percentage of Engineering Drawings Releasable at CDR for
Selected NASA Projects:
Figure 5: Comparison of Design Drawing Increase for Projects with
CDR prior to and since Fiscal Year 2009:
Figure 6: Notional Allocation of Reserves under the 70 Percent
Confidence Level Funding Requirements:
Figure 7: Illustration of Projects 2-Page Summary:
Abbreviations:
AFB: Air Force Base:
AFS: Air Force Station:
APS: Aerosol Polarimetry Sensor:
ARRA: American Recovery and Reinvestment Act of 2009:
ASI: Argenzia Spaciale Italiana (Italian Space Agency):
C&DH: Command and Data Handling:
CDDS: Cavity Door Drive System:
CDR: critical design review:
CMIC: Command and Data Handling Unit Module Interface Card:
CONAE: Comision Nacional de Actividades Espaciales (Space Agency of
Argentina):
CrIS: Cross-track Infrared Sounder:
CSA: Canadian Space Agency:
DCI: data collection instrument:
DM-2: Development Motor 2:
DPR: dual-frequency precipitation radar:
DT&E: Development Test & Evaluation:
ESA: European Space Agency:
ETU: engineering test unit:
GIDEP: Government Industry Data Exchange Program:
GLAST: Gamma-ray Large Area Space Telescope:
GMI: GPM microwave imager:
GPM: Global Precipitation Measurement (mission):
GRACE: Gravity Recovery and Climate Experiment:
GRAIL: Gravity Recovery and Interior Laboratory:
HEPS: High Efficiency Power Supply:
HOPE: Helium-Oxygen-Proton-Electron:
ICESat-2: Ice, Cloud, and Land Elevation Satellite-2:
IPO: Integrated Program Office:
ISS: International Space Station:
JAXA: Japan Aerospace Exploration Agency:
JCL: Joint Cost and Schedule Confidence Levels:
JPL: Jet Propulsion Laboratory:
JWST: James Webb Space Telescope:
KDP: key decision point:
LCROSS: Lunar Crater Observation and Sensing Satellite:
LDCM: Landsat Data Continuity Mission:
LDEX: Lunar Dust Experiment:
LIO: Low Inclination Observatory:
LLCD: Lunar Laser Com Demo:
LRO: Lunar Reconnaisance Orbiter:
MagEIS: Magnetic Electron Ion Spectrometer:
MAVEN: Mars Atmosphere and Volatile EvolutioN:
MEP: Mars Exploration Program:
MMRTG: Multi Mission Radioisotope Thermoelectric Generator:
MMS: Magnetospheric Multiscale:
MRO: Mars Reconnaissance Orbiter:
MSL: Mars Science Laboratory:
MSR: Monthly Status Review:
NAR: nonadvocate review:
NASA: National Aeronautics and Space Administration:
NID: NASA Interim Directive:
NLS: NASA Launch Services:
NMS: Neutral Mass Spectrometer:
NPR: NASA Procedural Requirements:
NPOESS: National Polar-Orbiting Operational Environmental Satellite
System:
NPP: NPOESS Preparatory Project:
OCFO: Office of the Chief Financial Officer (NASA):
OCO: Orbiting Carbon Observatory:
OLI: Operational Land Imager:
OT&E: Operational Test & Evaluation:
PA-1: Pad Abort-1:
PDR: preliminary design review:
RBSP: Radiation Belt Storm Probes:
RWA: reaction wheel assembly:
SAM: Sample Analysis at Mars:
SBC: single board computer:
SDO: Solar Dynamics Observatory:
SDP: Spin Plane Double Probe:
SID: Strategic Investments Division (NASA):
SMAP: Soil Moisture Active and Passive (mission):
SOFIA: Stratospheric Observatory for Infrared Astronomy:
TAT: Test Assessment Team:
TIM: total irradiance monitor:
TIRS: Thermal Infrared Sensor:
TLGA: Toroidal Low Gain Antenna:
TRL: technology readiness level:
UVS: Ultraviolet Spectrometer:
USGS: U.S. Geological Survey:
VIIRS: Visible Infrared Imaging Radiometer Suite:
WISE: Wide-field Infrared Survey Explorer:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
March 3, 2011:
We are pleased to present GAO‘s third annual assessment of selected
largescale National Aeronautics and Space Administration (NASA)
projects. This report provides a snapshot of NASA‘s planning and
execution of major acquisitions”-a topic that is on GAO‘s high risk
list.
This past year has been one of turmoil for NASA. The proposed
cancellation of the Constellation program”-the agency‘s largest
program-”has left NASA‘s human space flight program in a state of
flux. Its future work in this area depends on how budget issues and
direction are resolved between the Congress and the Administration.
While NASA continued to work toward the program of record for
Constellation, its focus has now turned to prioritizing work that can
be transitioned to the new path for human space flight set out in the
NASA Authorization Act of 2010 while continuing to comply with the
requirements of its fiscal year 2010 appropriations. Additionally,
funding constraints due to the delayed retirement of the shuttle
fleet, the plan to utilize the International Space Station at least 4
years longer than anticipated, and expected overruns in major projects,
such as the James Webb Space Telescope and the Mars Science Lab, will
affect NASA‘s plans for funding new projects for years to come. This
environment, coupled with a constrained budgetary outlook, heightens
the importance of efficient and effective project management to
maximize results. Furthermore, NASA needs to be equipped with the
knowledge to make hard choices among competing priorities within the
agency.
We recently issued an update to our high risk report where we
highlighted efforts NASA continues to make to improve its management
of major projects. For example, the agency has continued to implement
initiatives aimed at strengthening its cost and schedule estimating
processes. These initiatives, as well as other efforts, are intended
to provide key decisionmakers with increased knowledge to make
informed decisions before a project starts and to maintain disciplined
management and oversight once it begins. Increased discipline and
oversight, however, will require that senior NASA leaders have the
will to terminate or reshape projects that do not measure up, hold
appropriate parties accountable for poor outcomes, and recognize and
reward good management and good decisions. NASA continues to take
positive steps, but it will still be some time before the impact of
its efforts can be measured.
The NASA portfolio of major projects ranges from robotic probes designed
to explore the Martian surface, to satellites equipped with advanced
sensors to study the earth, to telescopes intended to explore the
universe. Some of these missions have literally changed the way we
view our planet and the universe. For example, the Kepler mission
recently identified the first Earth-size planet candidates in a
habitable zone where liquid water could exist on the planet‘s surface.
In many cases, NASA‘s projects are expected to incorporate new and
sophisticated technologies that must operate in harsh, distant
environments.
Although space development programs are complex and difficult by
nature, our work consistently finds that inherent risks of NASA‘s
complex development projects are heightened by the induced risks of
less than adequate management and oversight practices. In this year‘s
report, our work continues to show that NASA‘s major projects are
frequently approved without evidence of a sound business case that
ensures a match between requirements and reasonably expected
resources. As a result, the projects cost more and take longer to
develop than planned. We found that NASA frequently exceeded its
acquisition cost and schedule estimates, even when those estimates
were relatively new. In the last 3 years, 12 out of the 13 projects
that have been in development for several years significantly
exceeded their cost and/or schedule baseline estimates. In today‘s
fiscal environment, it is clear that this condition cannot be
sustained.
We believe that this report can provide insights that will help NASA
place programs in a better position to succeed, and help the agency
maximize its investments. Our work has shown that curbing the induced
challenges that can lead to cost and schedule growth hinges on
developing a sound business case that includes firm requirements,
mature technologies, a knowledge-based acquisition strategy, realistic
cost estimates, and sufficient funding. Consistent adoption of such
practices can improve results and may help ease the budgetary
pressures NASA is likely to continue to face over time.
Signed by:
Gene L. Dodaro:
Comptroller General of the United States:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
March 3, 2011:
Congressional Committees:
This is GAO's third annual assessment of National Aeronautics and
Space Administration's (NASA) large-scale projects. This report
provides a snapshot of how well NASA is planning and executing its
major acquisitions--an area that has been on GAO's high risk list
since 1990. Over the past year, NASA has again showed that its
projects produce ground-breaking research and advance our
understanding of the universe. For example, the Kepler spacecraft has
discovered the first confirmed planetary system with more than one
planet transiting the same star. Unfortunately, over the past year,
NASA has also experienced much turmoil and cost increases in several
of its major projects. For example, the proposed cancellation of the
Constellation Program, after spending over $11 billion since 2006,
caused uncertainty in NASA's human spaceflight program. More recently,
an independent panel concluded that the James Webb Space Telescope
project will require additional funding of $1.4 billion or more and a
launch delay of 15 months. In the past 2 years, we reported that 11
out of 17 NASA projects experienced significant cost and/or schedule
growth from baselines established only 2 or 3 years earlier.[Footnote
1] Such issues continue to impact NASA's ability to continue its
ground-breaking work in an efficient and effective manner.
NASA has taken steps over recent years to help improve its acquisition
management through several initiatives aimed at improving cost
estimating and management oversight. While the overall outcomes of
these efforts will take time to become apparent, NASA officials
indicate that they continue to be committed to the initiatives with
the goal of improving performance.
The Congress has expressed concern about NASA's performance and has
identified the need to standardize the reporting of cost, schedule,
and content for NASA research and development projects. In 2005, the
Congress required NASA to report cost and schedule baselines--
benchmarks against which changes can be measured--for all NASA
programs and projects with estimated life-cycle costs of at least $250
million that have been approved to proceed to the development stage,
known as implementation, in which components begin to take physical
form.[Footnote 2] It also required that NASA report to Congress when
development cost is likely to exceed the baseline estimate by 15
percent or more, or when a milestone is likely to be delayed beyond
the baseline estimate by 6 months or more.[Footnote 3] In response,
NASA began to establish cost and schedule baselines in 2006 and has
been using them as the basis for annual project performance reports to
the Congress provided in its budget submission each year.
The explanatory statement of the House Committee on Appropriations
accompanying the Omnibus Appropriations Act, 2009 directed GAO to
prepare project status reports on selected large-scale NASA programs,
projects, or activities.[Footnote 4] This report responds to that
mandate. Specifically, we assess (1) performance of NASA's major
projects and the agency's management of those projects during
development, (2) knowledge attained by key junctures in the
acquisition process, (3) other challenges that can affect project
execution, (4) NASA's continued efforts to improve its acquisitions,
and (5) 21 NASA projects, each with an estimated life-cycle cost over
$250 million.[Footnote 5] In doing so, the report expands on the
importance of providing decision-makers with an independent, knowledge-
based assessment of individual systems that identifies potential risks
and allows them to take actions to put projects that are early in the
development cycle in a better position to succeed.
Our approach included an examination of the current phase of a
project's development and how each project was advancing.[Footnote 6]
NASA provided updated cost and schedule data as of November 2010 for
16 of the 21 projects. We reviewed and compared that data to
previously established cost and schedule statutory baselines. We
assessed each project's cost and schedule and characterized growth in
either as significant if it exceeded the baselines that trigger
reporting to the Congress under the law.[Footnote 7] In addition, NASA
provided cost and schedule information from previously reported
projects that we used for historical analysis. We assessed technology
maturity and design stability using GAO's established criteria for
knowledge-based acquisitions and on other GAO work on system
acquisitions.[Footnote 8] Additionally, we identified other challenges
that can affect project outcomes--funding, launch vehicles,
development partner performance, parts, and contractor management--as
a result of our analysis based on interviews with project officials
and information provided by the projects. This list of challenges is
not exhaustive and we believe these challenges will evolve, as they
have from previous years, as we continue this work into the future. We
took appropriate steps to address data reliability. The individual
project offices were given an opportunity to provide comments and
technical clarifications on our assessments prior to their inclusion
in the final product, which were incorporated as appropriate. Appendix
III contains detailed information on our scope and methodology.
We conducted this performance audit from March 2010 to February 2011
in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe
that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives. We are not
making recommendations in this report:
Background:
A Sound Business Case Underpins Successful Acquisition Outcomes:
The development and execution of a knowledge-based business case for
NASA‘s projects can provide early recognition of challenges, allow
managers to take corrective action, and place needed and justifiable
projects in a better position to succeed. Our studies of best practice
organizations show the risks inherent in NASA‘s work can be mitigated by
developing a solid, executable business case before committing
resources to a new product development.[Footnote 9] In its simplest
form, this is evidence that (1) the customer‘s needs are valid and can
best be met with the chosen concept and that (2) the chosen concept
can be developed and produced within existing resources-”that is,
proven technologies, design knowledge, adequate funding, adequate
time, and adequate workforce to deliver the product when needed. A
program should not be approved to go forward into product development
unless a sound business case can be made. If the business case
measures up, the organization commits to the development of the
product, including making the financial investment. Our best practice
work has shown that developing business cases based on matching
requirements to resources before program start leads to more
predictable program outcomes-”that is, programs are more likely to be
successfully completed within cost and schedule estimates and deliver
anticipated system performance.[Footnote 10]
At the heart of a business case is a knowledge-based approach to product
development that is a best practice among leading commercial firms.
Those firms have created an environment and adopted practices that put
their program managers in a good position to succeed in meeting
expectations. A knowledge-based approach requires that managers
demonstrate high levels of knowledge as the program proceeds from
technology development to system development and, finally, production.
In essence, knowledge supplants risk over time. This building of
knowledge can be described over the course of a program as follows:
* When a project begins development, the customer‘s needs should match
the developer‘s available resources”mature technologies, time, and
funding. An indication of this match is the demonstrated maturity of the
technologies required to meet customer needs”referred to as critical
technologies. If the project is relying on heritage”or pre-existing”
technology, that technology must be in appropriate form, fit, and
function to address the customer‘s needs within available resources.
The project will normally enter development after completing the
preliminary design review, at which time a business case should be in
hand.
* Then, about midway through the product‘s development, its design
should be stable and demonstrate it is capable of meeting performance
requirements. The critical design review takes place at that point in
time because it generally signifies when the program is ready to start
building production-representative prototypes. If design stability is
not achieved, but a product development continues, costly re-designs
to address changes to project requirements and unforeseen challenges
can occur. By the critical design review, the design should be stable
and capable of meeting performance requirements.
* Finally, by the time of the production decision, the product must be
shown to be producible within cost, schedule, and quality targets and
have demonstrated its reliability, and the design must demonstrate
that it performs as needed through realistic system-level testing. Lack
of testing increases the possibility that project managers will not have
information that could help avoid costly system failures in late
stages of development or during system operations.
Our best practices work has identified numerous other actions that can
be taken to increase the likelihood that a program can be successfully
executed once that business case is established. These include ensuring
cost estimates are complete, accurate and updated regularly, and holding
suppliers accountable through such activities as regular supplier audits
and performance evaluations of quality and delivery. Moreover, we have
recommended using metrics and controls throughout the life cycle to
gauge when the requisite level of knowledge has been attained and when
to direct decision makers to consider criteria before advancing a
program to the next level and making additional investments.
NASA Life Cycle for Flight Systems:
NASA life cycle for flight system is defined by two phases-”
formulation[Footnote 11] and implementation[Footnote 12]-”and several
key decision points. See figure 1. These phases are then further
divided into incremental pieces: Phase A through Phase F.
Figure 1: NASA‘s Life Cycle for Flight Systems:
[Refer to PDF for image: life cycle illustration]
Formulation:
Pre-phase A: Concept Studies:
KDP A:
Phase A: Concept and Technology Development:
SCR:
Pre-NAR:
KDP B:
Phase B: Preliminary Design and Technology Completion:
PDR:
NAR:
KDP C:
Program start:
Phase C: Final Design and Fabrication:
CDR:
KDP D:
Phase D: System Assembly, Integration and Test, Launch:
KDP E:
Phase E: Operations and Sustainment:
KDP F:
Phase F: Closeout:
Implementation:
Management decision reviews:
Pre-NAR = preliminary non advocate review;
NAR = non advocate review;
KDP = key decision point.
Technical reviews:
SDR = system definition review;
PDR = preliminary design review;
CDR = critical design review.
Source: NASA data and GAO analysis.
[End of figure]
Project formulation consists of Phases A and B, during which time
the projects develop and define the project requirements and cost/
schedule basis and design for implementation, including developing an
acquisition strategy. During the end of the formulation phase, leading
up to the preliminary design review (PDR)[Footnote 13] and non-
advocate review (NAR),[Footnote 14] the project team completes its
preliminary design and technology development. NASA Interim Directive
NM 7120-81 for NASA Procedural Requirements 7120.5D, NASA Space Flight
Program and Project Management Requirements, specifies that during
formulation the project should complete development of mission-
critical or enabling technology. As needed, projects are required to
demonstrate evidence of technology maturity (i.e., component and/or
breadboard validation in the relevant environment) and document the
information in a technology readiness assessment report. The project
must also develop, document, and maintain a project management
baseline[Footnote 15] that includes the integrated master schedule and
baseline life-cycle cost estimate. The formulation phase is intended
to culminate in a confirmation review at which time cost and schedule
baselines are confirmed and project progress hence forth is
measured against these baselines.
After a project is confirmed, it begins implementation, consisting of
phases C, D, E, and F. During phase C, the project performs final
design and fabrication as well as testing of components. In phase D,
the project performs system assembly, integration, test, and launch
activities. Phases E and F consist of operations and sustainment and
project closeout. A second design review, the critical design review
(CDR),[Footnote 16] is held in the implementation phase during the
latter half of phase C. The purpose of the CDR is to demonstrate that
the maturity of the design is appropriate to support proceeding with
full-scale fabrication, assembly, integration, and test. After CDR and
the system integration review,[Footnote 17] the project must be
approved before continuing into the next phase.
NASA Projects Reviewed in GAO Annual Assessments:
The portfolio of projects we reviewed has evolved and grown in each of
the last 3 years. Once a project launches, we will no longer include a
2-page summary in our annual report. However, we do maintain and
continually assess historical cost, schedule, and performance
information collected
Table 1: Selected Major NASA Projects Reviewed in GAO Annual
Assessments:
Projects in Formulation:
2009:
Ares I;
GPM;
JWST;
LDCM;
Orion;
2010:
Ares I;
GPM;
LDCM;
Orion;
2011:
Ares I;
ICESat-2;
Orion;
SMAP;
SPP.
Projects in Implementation:
2009:
Aquarius;
Dawn[A];
GLAST[A];
Glory;
Herschel;
Kepler;
LRO;
MSL;
NPP;
OCO[B];
SDO;
SOFIA;
WISE;
2010:
Aquarius;
Glory;
GRAIL;
Herschel[A];
Juno;
JWST;
Kepler[A];
LRO[A];
MMS;
MSL;
NPP;
RBSP;
SDO[A];
SOFIA;
WISE[A];
2011:
Aquarius;
Glory;
GPM;
GRAIL;
Juno;
JWST;
LADEE;
LDCM;
MAVEN;
MSL;
MMS;
NPP;
OCO-2;
RBSP;
SOFIA;
TDRS Replenishment.
Source: GAO analysis of NASA data:
[A] NASA projects that have launched.
[B] NASA project that launched but failed to reach orbit.
[End of table]
Observations on NASA's Portfolio of Major Projects:
We assessed 21 large-scale NASA projects in this review. We based the
majority of our cost and schedule analysis on the 16 projects that are
currently in the implementation phase of the project life-cycle. We
also analyzed historical data from projects that were a part of our
previous reviews. We found that 5 of the 16 projects currently in
implementation experienced significant cost and/or schedule growth
from their statutory baselines.[Footnote 18] The remaining 11 projects
set statutory baselines in fiscal year 2009 or later and have reported
little or no deviations from their and cost and schedule baselines.
Three of these 11 projects that had been in formulation for most of
our review were confirmed late in 2010 and their baselines, according
to NASA officials, were to be reported for the first time in the
NASA's fiscal year 2012 budget submission. The remaining five projects
were in the formulation phase where cost and schedule baselines have
yet to be established.[Footnote 19] See figure 2 for a summary of
these projects.
Figure 2: Summary of Projects Assessed by Phase of the NASA Project
Life Cycle:
[Refer to PDF for image: illustration]
Total projects reviewed: 21;
Projects in formulation: 5;
Projects in implementation: 16;
Projects with significant cost and/or schedule growth: 5;
Projects that entered implementation in FY 2009/10: 8;
Projects entering implementation in FY 2011: 3.
Source: GAO analysis of NASA project data.
[End of figure]
Development costs for the 16 projects currently in implementation had
an average development cost growth of $89.1 million--or 13.8 percent--
and schedule growth of 8 months from their statutory baselines. The
total increase in development costs for the 16 projects in
implementation was over $1.4 billion. The five projects with baselines
set before fiscal year 2009 were responsible for the overwhelming
majority of this increase. All 5 projects have exceeded cost and
schedule thresholds set by the Congress since their statutory
baselines. Two projects--Glory and MSL--were re-baselined, but to gain
a more accurate picture of cost and schedule growth, we used their
original statutory baselines for our analysis. See table 2.
Table 2: Cost and Schedule Growth from Statutory Baseline of Selected
NASA Projects in the Implementation Phase (dollars in millions):
Project: NPP;
Baseline (FY): 2007;
Development cost growth: $154.2;
Percentage cost growth: 26.0% [shaded];
Launch delay (months): 42 [shaded].
Project: SOFIA;
Baseline (FY): 2007;
Development cost growth: $177.9;
Percentage cost growth: 19.3% [shaded];
Launch delay (months): 12 [shaded].
Project: Aquarius;
Baseline (FY): 2008;
Development cost growth: $34.6;
Percentage cost growth: 18.0% [shaded];
Launch delay (months): 23 [shaded].
Project: Glory[A];
Baseline (FY): 2008;
Development cost growth: $170.4;
Percentage cost growth: 100.9% [shaded];
Launch delay (months): 26 [shaded].
Project: MSL[B];
Baseline (FY): 2008;
Development cost growth: $751.3;
Percentage cost growth: 77.6% [shaded];
Launch delay (months): 26 [shaded].
Project: GRAIL;
Baseline (FY): 2009;
Development cost growth: $0.0;
Percentage cost growth: 0.0%;
Launch delay (months): 0.
Project: Juno;
Baseline (FY): 2009;
Development cost growth: $0.1;
Percentage cost growth: 0.0%;
Launch delay (months): 0.
Project: JWST;
Baseline (FY): 2009;
Development cost growth: $129.8;
Percentage cost growth: 5.0%;
Launch delay (months): 0.
Project: RBSP;
Baseline (FY): 2009;
Development cost growth: $0.1;
Percentage cost growth: 0.0%;
Launch delay (months): 0.
Project: GPM;
Baseline (FY): 2010;
Development cost growth: $3.0;
Percentage cost growth: 0.5%;
Launch delay (months): 0.
Project: LDCM;
Baseline (FY): 2010;
Development cost growth: $4.2;
Percentage cost growth: 0.7%;
Launch delay (months): 0.
Project: MMS;
Baseline (FY): 2010;
Development cost growth: $0.0;
Percentage cost growth: 0.0%;
Launch delay (months): 0.
Project: TDRS Replenishment;
Baseline (FY): 2010;
Development cost growth: $0.0;
Percentage cost growth: 0.0%;
Launch delay (months): 0.
Project: LADEE;
Baseline (FY): 2011;
Development cost growth: $0.0;
Percentage cost growth: 0.0%;
Launch delay (months): 0.
Project: MAVEN;
Baseline (FY): 2011;
Development cost growth: $0.0;
Percentage cost growth: 0.0%;
Launch delay (months): 0.
Project: OCO-2;
Baseline (FY): 2011;
Development cost growth: $0.0;
Percentage cost growth: 0.0%;
Launch delay (months): 0.
Project: Average;
Development cost growth: $89.1;
Percentage cost growth: 13.8%;
Launch delay (months): 8.
Project: Total Development Cost;
Development cost growth: $1,425.6.
Source: GAO analysis of NASA data.
[A] Glory established a new statutory baseline in FY 2009 after being
reauthorized by Congress:
[B] MSL established a new statutory baseline in FY 2010 after being
reauthorized by Congress:
Note: Shading indicates projects that exceeded cost and schedule
thresholds.
[End of table]
This table does not reflect considerable cost and schedule growth that
will likely be experienced by NASA's largest science program--the
James Webb Space Telescope. Based on the findings of the independent
panel that recently reviewed the JWST project and information we
obtained from projects officials, it is likely that JWST will report
significant cost and schedule growth, estimated to be $1.4 billion or
more and up to 15 months, respectively.
Table 2 also includes information from 11 projects that were all
confirmed in the last two years and have not reported significant cost
or schedule growth. Many of these projects are entering, or have
recently entered, the test and integration phase where cost and
schedule growth is typically realized. Specifically, seven projects
plan to have their system integration review in fiscal year 2011 or
2012. Importantly, many of these projects have experienced similar
challenges as the older projects that have reported cost and/or
schedule growth, such as issues with maturing technology and not
meeting design criteria.
As previously stated, the Glory and MSL projects both sought
reauthorization from Congress because of development cost growth in
excess of 30 percent despite having statutory baselines reestablished
in 2008.[Footnote 20] Congress reauthorized the Glory project and new
statutory cost and schedule baselines were established in fiscal year
2009,[Footnote 21] after the project experienced a 53 percent cost
growth and 6-month launch delay from its original statutory baseline
estimates in fiscal year 2008. Although Glory's development costs have
increased by almost 31 percent from the new baseline established in
2009, Glory is scheduled to launch in February 2011 before a second
reauthorization would need to be sought. Similarly, MSL was
reauthorized by the Congress and NASA established new statutory cost
and schedule baselines early in fiscal year 2010 after reporting a 68
percent growth in cost and a 26 month schedule delay from its original
statutory baselines established in fiscal year 2008.
The issue of cost growth is more significant than the 13.8 percent
average identified in table 2 would indicate because it does not
capture the cost growth that occurred before the five projects
exhibiting the most considerable growth established baselines in
response to the statutory requirement in 2005. Additionally, when
considering all 13 projects included in our reviews for the past three
years that were confirmed prior to fiscal year 2009,[Footnote 22] we
found that NASA's major projects have experienced an average
development cost growth of over 51 percent, with the total increase in
development costs of over $2.3 billion from their original
confirmation baselines. In addition, 9 of these projects experienced
significant cost growth in excess of 15 percent, the point at which
NASA is required to notify the Congress if a project has exceeded the
threshold for reporting. See table 3.
Table 3: Cost Growth from Confirmation for Selected Major NASA
Projects that Established Baselines Prior to Fiscal Year 2009 (dollars
in millions).
Project: Aquarius;
Development Cost: Baseline: $193.0;
Development Cost: Current: $227.3;
Development Cost: Difference: $34.3;
Development Cost: Change: 17.8%.
Project: Dawn;
Development Cost: Baseline: $198.0;
Development Cost: Current: $266.4;
Development Cost: Difference: $68.4;
Development Cost: Change: 34.5%.
Project: GLAST;
Development Cost: Baseline: $384.0;
Development Cost: Current: $418.8;
Development Cost: Difference: $34.8;
Development Cost: Change: 9.1%.
Project: Glory;
Development Cost: Baseline: $159.0;
Development Cost: Current: $337.6;
Development Cost: Difference: $178.6;
Development Cost: Change: 112.3%.
Project: Herschel;
Development Cost: Baseline: $95.0;
Development Cost: Current: $126.7;
Development Cost: Difference: $31.7;
Development Cost: Change: 33.4%.
Project: Kepler;
Development Cost: Baseline: $313.0;
Development Cost: Current: $388.7;
Development Cost: Difference: $75.7;
Development Cost: Change: 24.2%.
Project: LRO;
Development Cost: Baseline: $421.0;
Development Cost: Current: $451.3;
Development Cost: Difference: $30.3;
Development Cost: Change: 7.2%.
Project: MSL;
Development Cost: Baseline: $969.0;
Development Cost: Current: $1,802.2;
Development Cost: Difference: $833.0;
Development Cost: Change: 86.0%.
Project: NPP;
Development Cost: Baseline: $513.0;
Development Cost: Current: $780.1;
Development Cost: Difference: $267.1;
Development Cost: Change: 52.1%.
Project: OCO;
Development Cost: Baseline: $187.0;
Development Cost: Current: $230.2;
Development Cost: Difference: $43.2;
Development Cost: Change: 23.1%.
Project: SDO;
Development Cost: Baseline: $597.0;
Development Cost: Current: $667.0;
Development Cost: Difference: $70.0;
Development Cost: Change: 11.7%.
Project: SOFIA;
Development Cost: Baseline: $306.0;
Development Cost: Current: $1,128.4;
Development Cost: Difference: $822.4;
Development Cost: Change: 268.8%.
Project: WISE;
Development Cost: Baseline: $192.0;
Development Cost: Current: $191.8;
Development Cost: Difference: -$0.2;
Development Cost: Change: -0.1%.
Project: Average;
Development Cost: Difference: $191.5;
Development Cost: Change: 54.99%.
Total Development Cost:
Development Cost: Baseline:$4,527.0;
Development Cost: Current: $7,016.3;
Development Cost: Difference: $2,4,89.3.
Source: GAO analysis of NASA data.
[End of table]
If changes NASA continues to implement to improve its acquisition
management have their intended impact, we would expect to see
improvements over time to the overall performance of the portfolio of
projects in maintaining cost and schedule baselines established at
their confirmation reviews.
Observations from Our Assessment of Knowledge Attained by Key
Junctures in the Acquisition Process:
Many of NASA's projects are one-time articles, meaning that there is
little opportunity to apply knowledge gained to the production of a
second, third, or future increments of spacecraft. While space
development programs are complex and difficult by nature and most are
one-time efforts, NASA is still responsible for achieving what it
promises when requesting and receiving funds. We have previously
reported that NASA would benefit from a more disciplined, knowledge-
based approach to its acquisitions. For the projects reviewed this
year, we continue to identify projects that have not met best practice
standards for technology maturity and design stability and have
experienced challenges in development. These challenges were assessed
based on knowledge that, according to acquisition best practices,
should be attained at key junctures in the project life-cycle to
lessen the risks to the project.
Technology Challenges:
[Side bar: Projects experiencing technology challenges:
* Ares I
* Glory;
* GPM;
* GRAIL;
* Juno;
* JWST;
* LADEE;
* LDCM;
* MMS;
* MSL;
* NPP;
* Orion;
* SOFIA.
End side bar]
During the course of our review, we found that 13 projects had
experienced technology issues, such as a lack of technology maturity
for both critical and heritage technologies. Specifically, of the 18
projects that had completed the preliminary design review--the point
in time where best practices say requisite technology maturity should
be reached to lessen risk--11 projects reported moving forward with
immature technologies.[Footnote 23] Two other projects--MMS and NPP--
reported issues with immature technologies for instruments that were
being developed by partners.
Our best practices work has shown that a technology readiness level
(TRL) of 6--demonstrating a technology as a fully integrated prototype
in a relevant environment--is the level of maturity needed to minimize
risks for space systems entering product development. For NASA,
projects enter development following the project's preliminary design
review and confirmation review.[Footnote 24] NASA's acquisition policy
states that by the preliminary design review a TRL of 6 is desirable
prior to integrating a new technology on a project.[Footnote 25]
Technology maturity is a fundamental element of a sound business case,
and its absence is a marker for subsequent problems, especially as the
project begins more detailed design efforts.[Footnote 26]
Similarly, our work has shown that the use of heritage technology--
proven components that are being modified to meet new requirements--
can also cause problems when the items are not sufficiently matured to
meet form, fit, and function standards of the project that will be
using it by the preliminary design review.[Footnote 27] NASA
frequently employs heritage technologies that have to be modified from
their original form, fit, and function. NASA's Systems Engineering
Handbook states that particular attention must be given to heritage
systems because they are often used in architectures and environments
different from those in which they were designed to operate. Further,
the Handbook states that modification of heritage systems is a
frequently overlooked area in technology development and that there is
a tendency by project management to overestimate the maturity and
applicability of heritage technology to a new project. Our work has
shown, and NASA's own guidance concurs, that this is an area that is
frequently underestimated when developing project cost estimates.
Although NASA distinguishes critical technologies from heritage
technologies, our best practices work has found critical technologies
to be those that are required for the project to successfully meet
customer requirements, regardless of whether or not they are based on
existing or heritage technology. Therefore, whether technologies are
labeled as "critical" or "heritage," if they are important to the
development of the spacecraft or instrument--enabling it to move
forward in the development process--they should be matured by the
preliminary design review.
NASA is making progress with regard to adhering to best practices
standards for technology maturity at the preliminary design review as
the number of projects not meeting this criteria has decreased in
recent years. Nearly two thirds of the projects in our current review,
however, do not meet this standard. See figure 3 for an analysis of
projects that we reviewed in the past three years that held their
preliminary design review and the percent of those projects that moved
into implementation with immature technologies.
Figure 3: Percentage of Major NASA Projects with Immature Technologies
at the Preliminary Design Review:
[Reefer to PDF for image: stacked vertical bar graph]
Year: 2009;
Projects meeting technology maturity criteria: 17%;
Projects not meeting technology maturity criteria: 83%.
Year: 2010;
Projects meeting technology maturity criteria: 29%;
Projects not meeting technology maturity criteria: 71%.
Year: 2011;
Projects meeting technology maturity criteria: 38%;
Projects not meeting technology maturity criteria: 63%.
Source: GAO analysis of data provided by NASA.
Note: Totals may not add to 100% due to rounding.
[End of figure]
Proceeding into implementation with immature technologies increases a
project's risk of cost and schedule overruns. For instance, the MSL
project was given approval to move into the implementation phase
despite reporting that seven of its critical technologies were not
mature at the time of its preliminary design review. At the critical
design review a year later, three of the seven critical technologies
had been replaced by backup technologies with two of the seven still
assessed as immature, including one of the replacement technologies,
Challenges in development contributed to the MSL project's 26-month
schedule delay and $750 million increase in total lifecycle costs. In
another example, one of Glory's main instruments--the Aerosol
Polarimetry Sensor--was assessed as an immature critical technology at
the project's preliminary design review, yet the project was approved
to proceed in to implementation. Since then, the project has
experienced numerous issues with development of that instrument,
resulting in over a year delay in its delivery and a cost increase to
the project of over $100 million.
Other projects in formulation are allocating extra time and funding in
order to mature critical technologies by their preliminary design
review. By investing in technology development early on in the
project, the project may safeguard against some cost and schedule
growth once it is in the implementation phase. For example, two
projects in the formulation phase--ICESat-2 and Solar Probe Plus--have
both allocated increased time and funding for development of their
multi-beam laser and sunshield technologies, respectively, which
should help to lessen risk to the projects moving forward.
Finally, when analyzing the number of reported critical technology
development efforts by the projects in our review, we found four of
the 21 projects in our review reported no development of new critical
technologies, while another eight projects reported development of
only one critical technology. Upon presenting this data to senior NASA
officials, we were told that it appears the projects did not
accurately identify the number of critical technologies they plan to
develop and suggested that the projects were only including
technologies at the system level. We plan to continue to work with
NASA to ensure projects are accurately identifying their critical
technologies, both for our purposes, as well as to assist NASA
decision makers in assessing the readiness of projects to move forward
in their development lifecycles.
Design Challenges:
[Side bar: Projects experiencing design challenges:
* Aquarius;
* Glory;
* GPM;
* Juno;
* JWST;
* MAVEN;
* MMS;
* MSL;
* NPP;
* SOFIA.
End of side bar]
Ten of the 12 of the projects we reviewed that held their critical
design review[Footnote 28]--the point in time where best practices say
requisite design maturity should be reached to lessen risk--did not
meet the best practices criteria of having 90 percent engineering
drawings releasable. See figure 4.
Figure 4: Percent of Engineering Drawings Releasable at CDR for
Selected NASA Projects:
[Refer to PDF for image: vertical bar graph]
Projects that completed CDR: Aquarius;
Engineering drawings releasable at CDR: 16%;
Best practices criteria: 90%.
Projects that completed CDR: Glory;
Engineering drawings releasable at CDR: 64%;
Best practices criteria: 90%.
Projects that completed CDR: GPM;
Engineering drawings releasable at CDR: 50%;
Best practices criteria: 90%.
Projects that completed CDR: GRAIL;
Engineering drawings releasable at CDR: 82%;
Best practices criteria: 90%.
Projects that completed CDR: Juno;
Engineering drawings releasable at CDR: 39%;
Best practices criteria: 90%.
Projects that completed CDR: JWST;
Engineering drawings releasable at CDR: 84%;
Best practices criteria: 90%.
Projects that completed CDR: LDCM;
Engineering drawings releasable at CDR: 85%;
Best practices criteria: 90%.
Projects that completed CDR: MSL;
Engineering drawings releasable at CDR: 0%;
Best practices criteria: 90%.
Projects that completed CDR: NPP;
Engineering drawings releasable at CDR: 65%;
Best practices criteria: 90%.
Projects that completed CDR: OCO-2;
Engineering drawings releasable at CDR: 95%;
Best practices criteria: 90%.
Projects that completed CDR: RBSP;
Engineering drawings releasable at CDR: 68%;
Best practices criteria: 90%.
Projects that completed CDR: TDRS;
Engineering drawings releasable at CDR: 95%;
Best practices criteria: 90%.
Source: GAO analysis of data provided by NASA.
[End of figure]
We have previously reported that NASA's acquisition policy does not
specify a metric by which a project's design stability is measured at
the critical design review.[Footnote 29] Guidance in NASA's Systems
Engineering Handbook, however, mirrors the best practices metric that
at least 90 percent of engineering drawings should be releasable by
the critical design review. Discussions with project officials showed
the metric was used inconsistently to gauge design stability. For
example, Goddard Space Flight Center requires greater than 80 percent
drawings released at the critical design review, yet several project
officials reported that the "rule of thumb" for NASA projects is
between 70 and 90 percent. As shown in figure 6 above, 7 of the 12
projects reported releasable engineering drawings of less than 70
percent, lower than even the "rule of thumb" used by several project
managers. The 12 projects averaged having only 62 percent of their
engineering drawings releasable at their critical design reviews, an
increase from the less than 40 percent we reported last year. While
the average has improved, it is still well below the best practices
metric. Further, nearly all of the projects we reviewed over the last
three years held their critical design review without 90 percent of
engineering drawings being releasable--failing to meet NASA Systems
Engineering Handbook guidance and our best practices criteria for
design stability.
Achieving design stability allows projects to "freeze" the design and
minimize changes in the future. An unstable design, on the other hand,
can result in costly re-engineering and re-work efforts, design
changes, and schedule slippage. The majority of the 12 projects that
held their critical design review had increases, in two cases well
over 100 percent, to the number of engineering drawings released after
its critical design review when, according to NASA's Systems
Engineering Policy, a project's design is to be stable enough to
support full-scale fabrication, assembly, integration and test.
[Footnote 30] This is particularly evident in projects in our review
that held their critical design reviews prior to fiscal year 2009, or
projects that have more of a history to track variances. As shown in
figure 5 below, these four projects, on average, had a 107 percent
increase in expected engineering drawings after the critical design
review after having only 36 percent of drawings releasable at that
review. The remaining eight projects have only recently held their
critical design review in fiscal year 2009 or later and have not
reported a large increase in expected drawings.
Figure 5: Comparison of design drawing increase for projects with CDR
prior to and since fiscal year 2009:
[Refer to PDF for image: vertical bar graph]
Projects with CDR prior to FY 2009:
Average drawings released at CDR: 36.25%;
Average increase in expected drawings after CDR: 107%.
Projects with CDR in FY 2009 or later:
Average drawings released at CDR: 74.75%.
Average increase in expected drawings after CDR: 8.25%.
Source: GAO analysis of data provided by NASA.
[End of figure]
Some of the projects we reviewed in the past three years pointed to
other activities that occurred prior to the critical design review as
evidence of design stability. In addition to releasable engineering
drawings, NASA often relies on subject matter experts in the design
review process and other methods to assess design stability. For
example, the Standing Review Board[Footnote 31] provides an expert
assessment of the technical and programmatic approach, risk posture,
and progress against the project baseline at key decision points to be
assured that the project has a stable design. Furthermore, some
projects reported using engineering models and engineering test units
to assess design stability. For example, a MMS project official
reported that the number of complete engineering test units is as
important, if not more so, than design drawings. By using engineering
models that are as flight ready as possible, MMS project officials
reported that they can see where problems are and better identify
risks. In addition, a GPM project official said that the lack of
releasable drawings at the critical design review did not have a
serious impact in terms of design stability as testing was almost
complete on the engineering test units and flight units were already
designed and ready to begin manufacturing. The Juno project released
only 39 percent of engineering drawing at its critical design review
and project officials reported that they used engineering models for
all instruments to demonstrate design maturity at CDR rather then
released engineering drawings. The Juno project, however, experienced
a 46 percent increase in expected number of engineering drawings after
its CDR, indicating that the design was not stable.
As mentioned above, NASA does not use a common measure to assess
design stability before allowing programs to move from the design
phase to the test and integration phases of the development process.
Our studies and others have found that significant cost growth occurs
in these phases and, in some instances, has tied these problems to
issues related to design. Moreover, a recent study by the National
Research Council[Footnote 31] found that the critical design review
milestone for many NASA missions may be held prematurely--driven by
schedule rather than driven by design maturity. Regardless of how
stability is measured, common quantitative measures employed at
critical design review, such as percentage of engineering drawings
that are in a releasable state, can provide evidence that the design
is stable and provide assurance that it is mature and will meet
performance requirements. These measures can also be an indication to
decision makers that the requisite knowledge has been attained to
allow the project to proceed in its development lifecycle and better
enable them to assess the performance of individual projects against
the overall portfolio of projects.
Observations on Other Challenges That Can Affect Project Outcomes:
In addition to collecting and analyzing data on the attainment of
knowledge at key junctures, we collected and assessed data on five
additional areas that can present challenges to obtaining positive
project outcomes, including: funding, launch vehicle, development
partner performance, parts, and contractor management. Challenges with
contractors did not present as big a challenge to projects covered by
this review compared to previous reports, but continue to warrant
monitoring by the projects and other decision makers as a common area
that challenges project execution. The degree to which each area
challenged project execution varied and, in most instances, we did not
designate any specific challenge as a primary factor for cost and/or
schedule growth.
Funding Challenges:
[Side bar:
Projects experiencing funding challenges:
* Aquarius;
* Ares I;
* Glory;
* GPM;
* JWST;
* Orion;
* SOFIA.
Projects that received ARRA funding:
* Aquarius;
* Ares I;
* Glory;
* GPM;
* ICESat-2;
* JWST;
* LDCM;
* OCO-2;
* Orion;
* SMAP.
End of side bar]
Matching funding to requirements is critical to the success of complex
acquisitions yet it is often insufficient in government acquisitions
as agencies tend to start more projects than can be afforded and often
have to make cuts in budgets after programs begin in order to address
cost increases in highly problematic efforts. Several studies have
highlighted this issue in NASA and NASA's administrator recently
stressed the need to ensure projects are affordable before they are
started. This year, we identified 3 projects that faced significant
cost and schedule problems because their original funding did not
align with program plans. These include Ares 1, Orion, and JWST and
they represent NASA's largest investments. In addition, we identified
10 projects received unanticipated funding from the American Recovery
and Reinvestment Act of 2009.[Footnote 33] This event was an anomaly
and it carried with it restrictions and requirements that narrowed the
scope of projects it could be applied to and required additional
administrative work, which initially dissuaded some projects and
contractors from accepting the funds. Nevertheless, the stimulus
funding enabled NASA to mitigate the impact of cost increases being
experienced in its largest projects and to also address problems being
experienced in other projects. In several cases, NASA took advantage
of the funding build additional knowledge about technology or design
before key milestones.
According to NASA officials and independent reviews, the projected
budgets for JWST, Ares I, and Orion were inadequate to perform work in
certain fiscal years. In November 2010, an independent review panel
concluded the JWST budget baseline accepted at the confirmation review
did not reflect the most probable cost with adequate reserves in each
year of project execution. This resulted in a project that was not
executable within the budgeted resources. According to the review, the
project was able to stay within its yearly budget allocation by
deferring planned work in the budget year to future years. This
approach was an ineffective control measure as costs were postponed
and funded from a subsequent year's allocation at a cost that was
typically two-to three-times higher due to the impact of the deferrals
on other work. Further, the panel estimated that the project will need
an additional $1.4 billion or more for an earliest launch date of
September 2015--$500 million of which will be needed in fiscal years
2011 and 2012. Also, as we have reported previously, NASA initiated
the Constellation program relying on the accumulation of a large
rolling budget reserve in fiscal years 2006 and 2007 to fund program
activities in fiscal years 2008 through 2010.[Footnote 34] This poorly
phased funding plan diminished both the Ares I and Orion projects'
ability to deal with technical problems and funding shortfalls in
2010, and, in part, led the President to propose cancellation of the
program in the fiscal year 2011 budget submission. An independent
review commissioned by the Administration also found that the Ares I
and Orion programs did not have budget profiles that matched the work
that needed to be done.
With regard to the American Recovery and Reinvestment Act of 2009
(ARRA), 10 projects used these additional funds to offset existing
funding issues, such as covering the cost of delays or averting "stop
work" orders to contractors, or to lessen risk by initiating or
further enhancing technology development efforts and long lead
procurements that otherwise would not have funded at that time. The
Science Mission Directorate conducted extensive analysis on how best
to utilize the funding, because officials told us that these
additional funds would not necessarily alleviate all technology
development or other schedule delays, and in some cases the funds
would have no impact. See table 4 below for the NASA projects in our
review receiving this funding and how these funds were used.
Table 4: ARRA Funding for Reviewed NASA Projects:
Project: Ares;
ARRA funds: $102.4 million;
Use of funds: To manufacture and assemble engine components for
development testing, completion of a test stand, and preparation for
test operations.
Project: Aquarius;
ARRA funds: $8.6 million;
Use of funds: To maintain the current workforce through the planned
launch.
Project: Glory;
ARRA funds: $16.0 million;
Use of funds: To maintain the current workforce through the planned
launch.
Project: GPM;
ARRA funds: $32.0 million;
Use of funds: To accelerate construction of the GPM Microwave Imager
(GMI) instrument to ensure the core spacecraft is successfully
launched at the earliest possible opportunity.
Project: ICESat-2;
ARRA funds: $20.4 million;
Use of funds: To mature the micro-pulse laser designs.
Project: JWST;
ARRA funds: $75.0 million;
Use of funds: To maintain workforce levels and achieve the earliest
possible launch date.
Project: LDCM;
ARRA funds: $63.4 million;
Use of funds: To initiate development of the thermal infra-red sensor
(TIRS);
Other LDCM development.
Project: OCO-2;
ARRA funds: $18.0 million;
Use of funds: To acquire long lead components for the spacecraft and
facilitate instrument development in order to accelerate and enable
the earliest possible OCO-2 launch.
Project: Orion;
ARRA funds: $165.9 million;
Use of funds: To avoid workforce reductions and mitigate technical
challenges with its launch abort system, landing parachutes, solar
arrays, heatshield, and propulsion systems.
Project: SMAP;
ARRA funds: $64.0 million;
Use of funds: To procure long lead components and conduct component
level preliminary design reviews in order to accelerate the launch
date.
Source: GAO presentation of data provided by NASA.
[End of table]
Launch Vehicle Challenges:
[Side bar:
Projects experiencing launch vehicle:
challenges;
* Glory;
* GRAIL;
* ICESat-2;
* LADEE;
* MAVEN;
* NPP;
* SMAP;
* SPP.
End of side bar]
Eight of 21 projects in our review have experienced challenges with
launch vehicles. The primary concern is the retirement of the Delta II
medium launch vehicle. Over the past decade, NASA has launched about
60 percent of its science missions on the Delta II. NASA plans to
continue to use the Delta II as a launch vehicle for three remaining
science missions--Aquarius, Gravity Recovery and Interior Laboratory,
and National Polar-orbiting Operational Satellite System Preparatory
Project--the last of which is currently scheduled to launch in October
2011. These projects have identified risks associated with the last
flights, such as the availability of workforce and spare parts that
they, along with NASA's Launch Services Program, have taken steps to
mitigate.
Our recent work on NASA's transition plans for future medium launch
vehicles indicates that emerging NASA science missions will face
increased risks until new vehicles are certified.[Footnote 35] NASA
science missions requiring a medium class launch vehicle that are
approaching their preliminary design review face uncertainties
committing to as-yet uncertified and unproven launch vehicles that
will eventually replace the Delta II. Several missions, including the
SMAP and ICESat-2 missions are approaching the point in the
development lifecycle where it is optimal to finalize a decision on
launch vehicle. NASA plans to fill the gap left by the retirement of
the Delta II by eventually certifying the Falcon 9 and Taurus II
vehicles[Footnote 36] for use by NASA science missions in the relative
cost and performance range of the Delta II. This approach, however, is
not without risk as these vehicles are largely unproven. In a recent
report, we recommended that NASA perform detailed cost estimates to
determine the likely costs of certification of these new vehicles and
provide adequate budgeting for the risks associated with this
approach.[Footnote 37] NASA concurred with this recommendation and
agreed to provide cost estimates for certification and the resolution
of technical issues during certification of the Falcon 9.
Other launch challenges beyond the Delta II transition affected
projects in our review this year. For example, the Taurus XL, which
failed during the launch of OCO, was scheduled to return to flight in
late 2010 for the Glory mission. NASA and the Taurus XL launch vehicle
contractor were operating under constrained timelines to complete
Taurus XL return to flight activities; however, the Glory project
experienced technical challenges that led the project to delay the
launch from November 2010 to February 2011, providing enough time to
address return to flight activities. A malfunction in the ground
support equipment associated with the Taurus XL launch vehicle has
subsequently delayed launch of the Glory project until March 2011.
Development Partner Challenges:
[Side bar:
Projects experiencing development partner challenges:
* Aquarius;
* GPM;
* Juno;
* LDCM;
* MMS;
* NPP.
End of side bar]
Six projects reported challenges with international or domestic
development partners not meeting project commitments within planned
resources. Project officials reported several reasons why development
partners were unable to fulfill their obligations, including a lack of
experience in producing spacecraft and the lack of adequate funding. For
example, delays in the development of the spacecraft bus by Argentina‘s
National Committee of Space Activities was identified as the reason
for the Aquarius project‘s 15 percent development cost increase and 18-
month schedule slip that NASA reported to the Congress in February
2010. Since that time, the project has determined that the launch will
be delayed by at least another 5 months for a total delay of 23
months. Project officials said that while Argentina‘s National
Committee of Space Activities is technically competent, it lacks
experience in managing spacecraft production projects. Aquarius
project officials estimate the cost impact of these delays to be
approximately $35 million. In addition, projects also experienced
challenges related to development partners‘ providing adequate funding
for their contributions. For example, the GPM project identified a
project risk that their international development partner, the
Japanese Space Agency, may be unable to fund needed launch support
services as originally planned.
In the past 3 years, we reviewed 13 projects that established their
baseline prior to fiscal year 2009. As shown in table 5, the average
schedule delay from their baselines is 17.6 months for the projects
with foreign or domestic development partners, but 10.6 months for
projects that had no development partner.
Table 5: Schedule Growth for Selected NASA Projects with and without
Development Partners Baselined before 2009:
Projects with Partners: Dawn;
Baseline (FY): 2007;
Launch Delay (months): 0.
Projects with Partners: GLAST;
Baseline (FY): 2007;
Launch Delay (months): 9.
Projects with Partners: Herschel;
Baseline (FY): 2007;
Launch Delay (months): 21.
Projects with Partners: LRO;
Baseline (FY): 2008;
Launch Delay (months): 8.
Projects with Partners: NPP;
Baseline (FY): 2007;
Launch Delay (months): 42.
Projects with Partners: SOFIA;
Baseline (FY): 2007;
Launch Delay (months): 12.
Projects with Partners: Aquarius;
Baseline (FY): 2008;
Launch Delay (months): 23.
Projects with Partners: MSL;
Baseline (FY): 2008;
Launch Delay (months): 26.
Projects with Partners: Average;
Launch Delay (months): 17.6.
Projects without Partners: Kepler;
Baseline (FY): 2007;
Launch Delay (months): 9.
Projects without Partners: SDO;
Baseline (FY): 2007;
Launch Delay (months): 18.
Projects without Partners: Glory;
Baseline (FY): 2008;
Launch Delay (months): 20.
Projects without Partners: OCO;
Baseline (FY): 2008;
Launch Delay (months): 5.
Projects without Partners: WISE;
Baseline (FY): 2008;
Launch Delay (months): 1.
Projects without Partners: Average:
Launch Delay (months): 10.6.
Source: GAO Analysis of NASA data.
[End of table]
Although the cost and schedule growth for some of the projects that
have development partners can be attributed to other challenges, for
example technology or design issues, there are instances where the
performance of the development partners was the primary factor of cost
and schedule growth. For example, the Aquarius, NPP and Hershel
projects all experienced significant delays as a direct result of
issues related to their development partners.
Parts Challenges:
[Side bar:
Projects experiencing parts challenges:
* Glory;
* Juno;
* LADEE;
* LDCM;
* MSL;
* OCO-2;
* RBSP;
* TDRS Replenishment.
End of side bar]
While most of the projects in our assessment reported challenges
related to parts quality or availability, 8 projects this year
experienced an impact to their cost or had to make alterations to
their schedules as a result of the challenges. According to NASA
officials, parts problems are not uncommon for projects, and NASA's
testing process is designed to identify part failures at the
component, subsystem, and system level before they lead to mission
failure. For example, a parts quality problem discovered during the
testing and integration of the Glory project resulted in an additional
$61million in cost and delayed the project by 17 months. The project
had to replace the printed wiring board of the spacecraft's single
board computer due to reliability problems with the original board. In
addition, the project recently discovered excessive wear of the Slip
Ring Assembly in the solar arrays, resulting in an additional three
month launch delay. In addition, the MSL project experienced a part
failure associated with the transition joints in the propulsion system
which caused the joints to overheat and fail. Project officials
reported this issue was realized after the project finished building
its propulsion system, causing the project to rebuild the system and
adopt a new joint design. The transition to the new design delayed
rover testing from 2009 to early 2010.
NASA centers work together and communicate potential systemic issues.
For example, parts personnel at Goddard Space Flight Center maintain a
center-level parts database, which links to the agency-wide Government
Industry Data Exchange Program alert system.[Footnote 38] GAO has an
on-going assessment of parts quality across the government space
sector and will be reporting on actions being taken by NASA and other
agencies to prevent and mitigate such problems.
Contractor Management Challenges:
[Side bar:
Projects experiencing contractor management challenges:
* Glory;
* Juno;
* JWST;
* Orion;
* RBSP;
* SOFIA.
End of side bar]
Five projects in implementation and one project in formulation
reported experiencing contractor challenges including not completing
work on time, not identifying risks for the project, and inadequate
oversight. Contractor management challenges have been reported for a
greater number of projects and with a greater impact for projects in
past reports. Although the impact of this challenge on projects we
reviewed this year has diminished, as contractors spend about 85
percent of NASA's annual budget, their performance is critical in
terms of achieving the success of many NASA missions. As a result, we
continue to identify this area as a common project challenge that can
contribute to cost and schedule growth.
In one case, RBSP project officials are expecting the delivery of the
Magnetic Electron Ion Spectrometer instrument to be delayed due to
the time a vendor is taking in providing needed flight hardware for the
instrument. Consequently, the project has re-planned the schedule to
accommodate the late delivery and integration of the instrument. This
re-plan maintains the launch readiness date by reordering the
observatory integration and test flow and changing selected subsystem
and instrument delivery dates.
In another example, an independent review panel found that the JWST
project did not have staff resident at the prime contractor facility
to help avoid surprises, especially since the contract represented
approximately half of the JWST project‘s budget. The panel said that
this is a normal practice and is done for other projects at Goddard
Space Flight Center. Further, while project officials told us that the
project‘s prime contractor and one of the subcontractors came forward
after confirmation with large cost increases that the contractor had
not previously identified as risks, the panel found that these risks
had been identified and that the project had asked the prime
contractor to submit them in a formal proposal before they could be
recognized as risks. GAO has ongoing work to review NASA‘s
contractor surveillance and oversight practices and will issue a
report later in 2011.
Observations about NASA's Continued Efforts to Improve Its Acquisition
Management:
In response to GAO‘s designation of NASA‘s acquisition management as a
high risk area,[Footnote 39] NASA developed a corrective action plan
to improve the effectiveness of its program/project management.
[Footnote 40] The plan identifies five areas for improvement”-
program/project management, cost reporting process, cost estimating
and analysis, standard business processes, and management of financial
management systems-”each of which contains targets and goals to
measure improvement. As part of this initiative, the agency is
continuing its implementation of a new cost estimating tool, the Joint
Cost and Schedule Confidence Level, to help project officials with
management, cost and schedule estimating, and maintenance of adequate
levels of reserves. In addition to the corrective action plan, NASA is
in the process of implementing Earned Value Management within certain
programs and specific in-house efforts to help the projects monitor the
scheduled work done by its contractors and employees; however, this
management tool has not yet been institutionalized within the NASA
Centers. These two efforts, in addition to other improvements NASA is
making to address acquisition management, are positive steps toward
addressing NASA‘s issues with meeting cost and schedule baselines. It
is, however, too early to assess their impact on NASA‘s performance.
Additionally, NASA‘s progress could be hindered by the continued lack
of a consistent measure for ensuring design stability as well as little
transparency with regard to costs for projects in the early, critical
phases of development, both of which are key to ensuring that internal
and external decision makers are well informed. We recently raised
both issues as potential impediments to success in congressional
testimony and plan to recommend improvements in a separate report.
[Footnote 41]
Joint Cost and Schedule Confidence Levels Being Implemented:
NASA's Joint Cost and Schedule Confidence Levels (JCL) initiative,
adopted in January 2009, is a point-in-time estimate that includes,
among other things, all cost and schedule elements, incorporates and
quantifies known risks, assesses the impacts of cost and schedule to
date, and addresses available annual resources. The primary goals of
the JCL are to help project officials with management, cost and
schedule estimating, and maintenance of adequate levels of reserves;
provide assurance to stakeholders that NASA will meet cost and
schedule targets; and to provide transparency on the effects of
funding changes on the probability of meeting cost and schedule
commitments. NASA requires that a JCL be conducted the prior to the
confirmation review. NASA policy also requires that projects be
baselined and budgeted at the 70 percent confidence level and funded
at a level equivalent to at least the 50 percent confidence level for
the project.[Footnote 42] According to NASA officials, this would
include reserves held at the directorate and project level. The total
amount of reserves held at the project level varies based on where the
project is in its lifecycle. The reserves represent the amount of
estimated costs that are not allocated to the specific project sub-
elements. See figure 6 for a visual depiction of this funding
allocation.
Figure 6: Notional Allocation of Reserves under the 70 Percent
Confidence Level Funding Requirements:
[Refer to PDF for image: line graph]
The graph depicts the amount NASA budgets for project reserves and
mission directorate or program reserves.
Source: GAO analysis of NASA policy.
Note: The amount of project reserves varies as the project moves
through its lifecycle.
[End of figure]
NASA's Associate Administrator for the Science Mission Directorate
indicated that adoption of the new JCL process will reduce NASA's
portfolio because the cost estimating will be more accurate at the 70
percent confidence level, reflecting higher costs from the outset to
avoid higher cost overruns in the future, and as a result NASA will
have fewer dollars available to start new projects.
Five out of the 21 projects[Footnote 43] in our review have recently
completed the JCL process, and several others are in the process of
conducting a JCL analysis. NASA is still in the process of refining
the tools used to create the JCL based on feedback from the projects.
As NASA evolves its cost estimation processes and as we continue to
conduct our reviews of the projects that have gone through the JCL
process, we can better assess the impact this initiative has on the
projects' ability to meet cost and schedule commitments and to address
potential cost and schedule drivers.
Implementation of Earned Value Management at NASA Centers in Progress:
Earned value management (EVM) is a program management tool that
integrates the technical, cost, and schedule parameters of a contract
and uses those parameters to measure cost and schedule variances.
During our review, we found that implementation of earned value
management is occurring within 11 projects and earned value data is
reported by projects on a monthly basis to upper level project
management. While earned value management is being used by these
projects, it has not yet been used consistently by the projects as a
tool for managing cost and schedule. According to a briefing from the
NASA Advisory Council's Audit, Finance, and Analysis Committee, NASA's
goal is to develop and deploy an agency-wide EVM capability that is
compliant with generally accepted standards.[Footnote 44] At this
time, only the Jet Propulsion Laboratory, a Federally Funded Research
and Development Center and not a NASA Center, has a compliant system.
If implemented appropriately, EVM provides objective reports of
project status, produces early warning signs of impending schedule
delays and cost overruns, and can identify specific development
efforts contributing to those overruns. For example, MSL's June 2010
earned value management report identified the avionics and actuators
as the primary drivers of the project's cost overruns. In particular,
the data showed that ongoing unplanned technical issues with three of
the heritage avionics technologies would likely result in a cost
overrun of $11.5 million. More consistent use of this management tool
could help address the project challenges identified earlier in this
report that threaten the project's cost and schedule during project
development. The data we received from NASA was not received in a
timely manner and was incomplete. As a result, we were unable to
perform a detailed analysis by project to provide our own
determination of whether the information provided by the contractors
is accurate and could be relied on by the projects and management as a
tool to assess progress. We plan to conduct a more thorough analysis
of EVM data in ongoing work and in future iterations of this work.
Transparency and Accountability Not Sufficient to Provide Proper
Oversight:
These initiatives aimed at improving cost estimating and management
oversight are positive steps. However, we recently testified that NASA
does not yet provide enough transparency during project development to
help Congress identify risks and inefficiencies and ensure earlier
accountability.[Footnote 45] Currently, NASA does not share cost and
schedule information for projects in the early, critical phases of
development and only makes this information public after the projects
have been formally approved to enter implementation. Projects
establish preliminary cost baselines in formulation phase; these
estimates, however, are for planning purposes only as they enable NASA
decision makers to better manage the overall portfolio of projects.
NASA does not report deviations from these preliminary baselines to
the Congress. In addition, NASA does not report information on what
has been spent to date on the projects in formulation, as it does in
its annual budget submission for projects in implementation. To add
some perspective to this timing, neither the Ares nor Orion projects
has reached this point, despite having spent over $9 billion dollars
combined; and JWST just reached this point in 2008, despite having
spent nearly $2 billion before then.
Despite the absence of established external cost and schedule
baselines to measure the progress of the project, cost growth and
schedule delays can and do occur during the formulation phase. NASA's
internal analysis of past projects indicates that there is an average
of 14 percent growth in the development cost estimates during the
formulation phase. While there is a need to allow projects a period of
time for discovery and to pursue different concepts--particularly
highly complex efforts such as JWST--inadequate transparency into
their progress for what sometimes amounts to five or more years can
preclude effective oversight and accountability and make it even more
difficult to stop projects that are not on track to meet the agency's
goals with available resources. Additional insight to cost could
better enable Congress to make more informed decisions when approving
the projects through the annual appropriations process.
In addition, a recently released report from the Independent
Comprehensive Review Panel[Footnote 46] concerning problems affecting
the JWST program concluded that significant changes are still needed
in NASA's oversight and accountability functions to ensure that
programs base their decisions on sound knowledge. The panel noted that
NASA's governance policy is inconsistent with accountability for
project execution. In particular, the panel found that a lack of clear
lines of authority and accountability contributed to a lack of
executive leadership in resolving the broken JWST life-cycle cost
baseline. Additionally, the study found that JWST's flawed budget
should have been discovered as part of the Goddard Spaceflight
Center's execution responsibility, but the interpretation of the
agency's governance policy on the role of the center in this regard is
ambiguous and not interpreted uniformly within NASA. As a result, the
report noted that ongoing, regular independent assessment and
oversight processes at the agency are missing.
Project Assessments:
The two-page assessments of the projects we reviewed provide a profile
of each project and describe the challenges we identified this year,
as well as challenges that we have identified in the past. On the
first page, the project profile presents a general description of the
mission objectives for each of the projects; a picture of the
spacecraft or aircraft; a schedule timeline identifying key dates for
the project; a table identifying programmatic and launch information;
a table showing the current statutory baseline year cost and schedule
estimates and the November 2010 cost and schedule data; a table
showing the challenges relevant to the project; and a project summary
narrative. To maintain information on challenges the projects
experience over their lifetime, we continued to identify project
challenges that were reported in prior reports. On the second page of
the assessment, we provide an analysis of the project challenges and
the extent to which each project faces cost, schedule, or performance
risk because of these challenges. In addition, NASA project offices
were provided an opportunity to review drafts of the assessments prior
to their inclusion in the final product, and the projects provided
both technical corrections and more general comments. We integrated
the technical corrections as appropriate and characterized the general
comments below the project update. See figure 7 below for an
illustration of the layout of each two-page assessment.
Figure 7: Illustration of Project Two-Page Summary:
[Refer to PDF for image: illustration]
A. General description of mission‘s science objectives.
B. Illustration of spacecraft or aircraft.
C. Schedule timeline identifying key dates for the project including
when the project began formulation, major design reviews, confirmation
to begin the implementation phase, and scheduled launch readiness.
D. Project Essentials Programmatic information including the responsible
NASA center, international or domestic partners, major contractors, and
launch information.
E. Project Performance Cost and schedule baseline estimates and the
latest estimate updates as of February 2011.
F. Project Challenges Summary listing the challenges facing the project
based on a successful acquisition business case.
G. Project Summary Brief narrative describing current status of the
project with regard to the challenges identified.
H. Project Update Analysis of project challenges and the extent to which
each project faces cost, schedule, or performance risk because of these
challenges.
I. Project Office comments General comments provided by the cognizant
project office.
Source: GAO analysis.
[End of figure]
[End of section]
Project data:
Common Name: Aquarius:
Aquarius is a satellite mission developed by NASA and the Space Agency
of Argentina (Comisión Nacional de Actividades Espaciales, CONAE) to
investigate the links between the global water cycle, ocean
circulation, and the climate. It will measure global sea surface
salinity. The Aquarius science goals are to observe and model the
processes that relate salinity variations to climatic changes in the
global cycling of water and to understand how these variations
influence the general ocean circulation. By measuring salinity
globally for 3 years, Aquarius will provide a new view of the ocean‘s
role in climate.
[Refer to PDF for image: artist depiction]
Source: Aquarius Project.
Formulation:
Formulation start: 12/03;
Preliminary design review: 6/05.
Implementation:
Project Confirmation: 9/05;
Critical design review: 9/06;
GAO review: 12/10;
Launch readiness date: 6/11.
Project essentials:
NASA Center Lead: Jet Propulsion Laboratory (JPL)[A];
International Partner: Argentina's National Committee of Space
Activities (CONAE);
Major Contractors: In-house development;
Projected Launch Date: June 2011;
Launch Location: Vandenberg AFB, California;
Launch Vehicle: Delta II;
Mission Duration: 3 years for Aquarius mission; 5 years for SAC-D
(CONAE) mission.
[A] JPL is a federally funded research and development center.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2008): $241.8;
Latest (Feb. 2011): $279.0;
Change: 15.4%.
Formulation Cost:
Baseline Est. (FY 2008): $35.5;
Latest (Feb. 2011): $35.6;
Change: 0.3%.
Development Cost:
Baseline Est. (FY 2008): $192.7;
Latest (Feb. 2011): $227.3;
Change: 18.0%.
Operations Cost:
Baseline Est. (FY 2008): $13.6;
Latest (Feb. 2011): $16.1;
Change: 18.4%.
Launch Schedule:
Baseline Est. (FY 2008): 7/2009;
Latest (Feb. 2011): 6/2011;
Change: 23 months.
[End of table]
Recent/Continuing Project Challenges:
* Development Partner Issues;
* Funding Issues.
Previously Reported Challenges:
* Design Stability.
Project Summary:
The launch of Aquarius has been delayed from the July 2009 baseline to
June 2011 because of delays in CONAE‘s spacecraft development and
problems with the propulsion system thrusters. The launch delay, which
added costs to the project, prompted NASA to report to the Congress in
February 2010 that the Aquarius project exceeded its development cost
and schedule baselines by 15 percent and more than 6 months,
respectively. NASA completed its development of the Aquarius
instrument, which is currently being integrated with the Argentine-
developed spacecraft. Project officials estimated the cost of the past
schedule slips to be about $35.5 million.
Project Update:
NASA reported to Congress in the agency‘s fiscal year 2011 budget
estimates that the Aquarius mission‘s development costs had grown by
15 percent from its 2008 baseline. Additionally, the project‘s current
June 2011 launch date represents a 23-month schedule slip. These cost
and schedule overruns are due to delays by the international partner.
Development Partner Issues: According to project officials and budget
documents, delays in the development of the spacecraft bus by CONAE
were responsible for the 15 percent development cost increase and 18-
month schedule slip that NASA reported to Congress in February 2010.
Since that time, the project has determined that the launch will be
delayed by another 5 months to June 2011, for a total delay of 23
months. To facilitate the work of its partners, the Jet Propulsion
Laboratory (JPL) project team said that it appointed a chief mission
engineer to help facilitate upcoming tests and reviews; however, JPL
officials stated that they have not had full access to INVAP, CONAE‘s
prime contractor, due to contractual agreements between INVAP and
CONAE. Additionally, CONAE was responsible for flying the instrument to
Vandenberg Air Force Base for launch but could not find a viable
commercial aircraft. Project officials said that they are working with
the U.S. Air Force to secure a no-cost flight for the integrated
satellite, but may have to pay for the flight at a cost of
approximately $1 million.
Funding Issues: Since no funds are being exchanged between the U.S.
and Argentina for this project, NASA bears the costs it incurs
associated with any schedule delays. Project officials told us that
all of the project‘s contingency reserves have been eroded due to past
schedule delays with the spacecraft bus as well as current schedule
delays associated with the SAC-D instruments being provided by CONAE.
These schedule slips increased NASA‘s costs by an estimated $35.5
million in the past. Project officials stated that the primary cost
driver associated with the launch delay is staffing costs, estimated
to be approximately $4.9 million. Further, the project received $8.6
million under the American Recovery and Reinvestment Act of 2009 that
was used to maintain the current Aquarius workforce through launch.
Other Issues to be Monitored: During thermal vacuum testing on the
spacecraft bus, INVAP discovered a problem with the spacecraft‘s
propulsion systems thrusters that has contributed to delaying the launch
until June 2011. After an analysis of the Dual Thruster Module, the
Aquarius/SAC-D team determined that the problem was likely due to one
or more procedural issues in the test process at the manufacturer or its
vendor. Refurbishment of all of the Dual Thruster Module flight units
is complete and the flight units were re-integrated with the
observatory. INVAP planned to complete integration and testing by
November 2010.
Project Office Comments:
The Aquarius project provided technical comments to a draft of this
assessment, which were incorporated as appropriate. The project
officials also commented that NASA and CONAE will continue to work
together to meet the earliest possible launch date.
[End of Aquarius data]
Ares I Crew Launch Vehicle:
Common Name: Ares I:
NASA‘s Ares I Crew Launch Vehicle was designed to carry the Orion Crew
Exploration Vehicle into low Earth orbit for missions to the
International Space Station and the Moon as part of the Constellation
Program. The mission of the Ares I project was to deliver a safe,
reliable, and affordable launch system with a 24.5-metric ton lift
capability.
[Refer to PDF for image: illustration]
Source: Ares Projects Office.
Formulation:
Formulation start: 9/05;
Preliminary design review: 9/08;
GAO review: 12/10.
Project Confirmation:
Implementation:
Critical design review: 9/11;
Launch readiness date: 3/15.
Project Essentials:
NASA Center Lead: Marshall Space Flight Center;
Partners: None;
Major Contractors: Alliant Techsystems, Pratt and Whitney Rocketdyne,
Boeing;
Projected Launch Date: March 2015;
Launch Location: Kennedy Space Center, Florida;
Launch Vehicle: Ares I;
Mission Duration: N/A.
Table: Project Performance (then year dollars in millions):
Latest (Feb. 2011):
Preliminary Estimate of Project Life Cycle Cost[A]: $17,000 to $20,000.
[A] This estimate is preliminary, as the project is in formulation and
there is still uncertainty in the value as design options are
explored. NASA uses these estimates for planning purposes. This
estimate is for the Ares I vehicle only.
Launch Schedule: 3/2015.
[End of table]
Recent/Continuing Project Challenges:
* Funding Issues;
* Technology Issues.
Project Summary:
The President‘s fiscal year 2011 budget proposed cancellation of the
Ares I project leading to uncertainty, both financial and
programmatic, within the project. Given constrained resources, the
project prioritized work and did not accomplish some of the work
originally planned for 2010; however, it successfully tested
Development Motor 2 to gain data on project elements. In early fall
2010, Congress passed the NASA Authorization Act of 2010 directing NASA
to develop a space launch system and crew vehicle for missions
utilizing existing Ares I contracts and capabilities to the extent
practicable.
Project Update:
The President proposed cancellation of the Constellation Program,
including the Ares I project, in the fiscal year 2011 budget request.
This proposal led to much debate within Congress and uncertainty, both
financial and programmatic, within the project. As a result, the
project prioritized work for the year and did not complete some of the
work originally planned for 2010. In early fall 2010, Congress passed
the NASA Authorization Act of 2010, which directed NASA to develop a
space launch system and crew vehicle for missions to near earth orbit
and regions of space beyond low-Earth orbit no later than December
2016. In developing this vehicle, Congress directed the agency to
extend or modify existing vehicle development and associated contracts
to the extent practicable.
Funding Issues: The Ares I project received over $102 million under
the American Recovery and Reinvestment Act of 2009 (ARRA) that was
used to manufacture and assemble engine components for development
testing, completion of a test stand, and preparation for test
operations. However, project officials explained that due to a series
of budgetary constraints for the first 4 months of fiscal year 2010 that
roughly offset the amount gained from the ARRA funding, the project
could not perform all of its originally planned work. While initially
parts of the project were able to maintain momentum, termination
liability issues identified in June 2010 caused the three project
prime contractors to stop certain portions of the work on their
respective contracts. At this time, the project redirected its funding
to activities that would potentially benefit NASA‘s goals and
objectives beyond the current fiscal year. For example, in August 2010,
the project successfully tested Development Motor 2 (DM-2). The DM-2
test was conducted to gain data on project elements tested including
the redesigned rocket nozzle, new insulation, and the motor casing‘s
liner. According to project officials, the project was flexible in its
planning while it maintained the program of record during fiscal year
2010.
Technology Issues: The Ares I project has been working to mitigate
several challenges related to the development of heritage technology.
However, given the funding uncertainty that has surrounded Ares I, the
project has been unable to implement the mitigation strategies. For
example, last year, NASA identified thrust oscillation as a technical
issue. Thrust oscillation, which causes shaking during launch and
ascent, occurs in some form in every solid rocket engine. Computer
modeling indicated that there was a possibility that the magnitude and
frequency of thrust oscillation within the first stage would be outside
the limits of the Ares I design and could cause excessive vibration in
the Orion capsule and threaten crew safety. According to project
officials, the project plans to mitigate the risk by adding damper and
isolation techniques at the interface between the launch vehicle and
the Service Module. However, this risk cannot be closed until funding
is obtained to implement the mitigation strategy. Furthermore,
vibroacoustics”-the pressure of the acoustic waves produced by the
firing of the Ares I first stage and the rocket‘s acceleration through
the atmosphere”-continues to be a concern to the project.
Vibroacoustics may cause unacceptable structural vibrations throughout
Ares I and Orion and force NASA to qualify components to higher
vibration tolerance thresholds than originally expected. According to
the project, the global mitigation strategy for the excessive
vibration has been on hold due to budget constraints. The project is
unable to finalize the design without knowing the final configuration
of the crew exploration vehicle. Finally, last year we reported that
analysis of the Ares I flight path also indicated that, under some
conditions, the Ares I vehicle could hit the launch tower during
liftoff and the vehicle would need to be steered away from the launch
tower or not launched during high winds. NASA officials told us they
have developed a plan to mitigate this risk.
Project Office Comments:
The Ares I project office provided technical comments on a draft of
this assessment, which were incorporated as appropriate. The project
office also commented that it has utilized resources to make progress
on the Constellation Program while focusing on goals that yield
benefits to future human spaceflight endeavors.
[End of Ares I data]
Global Precipitation Measurement (GPM) Mission:
Common Name: GPM:
[Refer to PDF for image: artist depiction]
Source: GPM Project Office.
The Global Precipitation Measurement (GPM) mission, a joint NASA and
Japan Aerospace Exploration Agency (JAXA) project, seeks to improve
the scientific understanding of the global water cycle and the
accuracy of precipitation forecasts. The GPM is composed of a core
spacecraft carrying two main instruments: a Dual-frequency
Precipitation Radar (DPR) and a GPM Microwave Imager (GMI). GPM
builds on the work of the Tropical Rainfall Measuring Mission and will
provide an opportunity to calibrate measurements of global
precipitation.
Formulation:
Formulation start: 7/02;
Preliminary design review: 11/08.
Implementation:
Project Confirmation: 12/09;
Critical design review: 12/09;
GAO review: 12/10;
Launch core spacecraft: 7/13.
Project Essentials:
NASA Center: Goddard Space Flight Center;
International Partner: Japanese Aerospace Exploration Agency (JAXA);
Major Contractors: Ball Aerospace;
Projected Launch Date: July 21, 2013;
Launch Location: Tanegashima Island, Japan;
Launch Vehicle: JAXA supplied;
Mission Duration: 3 years.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2009): $975.9;
Latest (Feb. 2011): $928.9;
Change: -4.8%.
Formulation Cost:
Baseline Est. (FY 2009): $349.2;
Latest (Feb. 2011): $349.2;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 20098): $555.2;
Latest (Feb. 2011): $514.8;
Change: -7.3%.
Operations Cost:
Baseline Est. (FY 2009): $71.6;
Latest (Feb. 2011): $64.9;
Change: -9.4%.
Launch Schedule:
Baseline Est. (FY 2009): 7/2013;
Latest (Feb. 2011): 7/2013;
Change: 0 months.
[End of table]
Project Summary:
Prior to establishing the project‘s baseline cost and schedule
estimate, NASA descoped the planned second spacecraft of the GPM
mission. The project‘s international partner, JAXA, is providing the
launch vehicle for the core spacecraft. However, GPM project officials
were tracking potential funding issues with JAXA. GPM received $32
million under the American Recovery and Reinvestment Act of 2009,
which was used to maintain the current schedule, expedite some work on
the GMI-1, and begin work on a second GMI.
Project Update:
Funding Issues: Prior to establishing the project‘s baseline cost
estimate, NASA removed funding for the second spacecraft of the GPM
mission, the Low Inclination Observatory (LIO), due to lack of funding.
The Low Inclination Observatory (LIO) was primarily intended to fly a
second GPM Microwave Imager (GMI-2), which would gather additional
science data to further support the GPM mission. Project officials
reported that NASA is currently pursuing an international development
partner willing to fund the launch vehicle and spacecraft needed for
the second GMI instrument. However, despite de-scoping the LIO launch
vehicle and spacecraft, the project continues to invest in the
development of the GMI-2 instrument. A GPM project official reported
that GMI-2 will be put into storage in 2013 if the LIO mission is not
going to launch soon after that. Although the science requirements for
GPM could still be met without flying the GMI-2 instrument, project
officials reported that without the instrument the available science
data from the mission would not be as robust.
GPM received $32 million under the American Recovery and Reinvestment
Act of 2009. According to project officials, this enabled GPM to
maintain schedule in fiscal year 2009, move some of the GMI work
planned for fiscal year 2011 into fiscal year 2010, and start the GMI-
2 development on schedule in October 2009.
Development Partner Issues: GPM project officials were tracking
potential funding issues with the Japanese Aerospace and Exploration
Agency (JAXA), which is providing the launch vehicle for the first GPM
spacecraft as a risk to the cost and schedule of the project. In
addition, the GPM project is tracking the availability of the JAXA-
supplied Dual-frequency Precipitation Radar (DPR) instrument. The
project reports that delays in the DPR instrument's development have
compressed the schedule available for integration and testing.
Design Issues: The project has currently released 96 percent of its
engineering drawings, but only 53 percent were released by the mission
critical design review (CDR) held in December 2009. A project official
said that the lack of released drawings at critical design review
didn‘t have a serious impact in terms of design stability as testing
was almost complete on engineering testing units and flight units were
already designed and ready to begin manufacturing.
Project officials delayed the CDR of the fully demiseable aluminum
propulsion tank from August 2010 to October 2010 due to difficulties
with parts assembly. The GPM spacecraft was designed to be demiseable”-
that is, it will burn up during re-entry into the Earth‘s atmosphere
to limit orbital debris. However, in December 2008, an updated re-
entry structural analysis at Johnson Space Center of GPM indicated
that the spacecraft would not be demiseable as originally predicted by
the GPM project office and Johnson Space Center. The project had
initially delayed the start of the implementation phase and
establishment of GPM cost and schedule baselines by 8 months in order
to reconcile the project budget with available funding and to resolve
the demisability issue.
Project Office Comments:
The GPM project office provided technical comments to a draft of this
assessment, which were incorporated as appropriate. Project officials
also commented that overall the GPM Project is making progress.
[End of GMP data]
Glory:
Common Name: Glory:
[Refer to PDF for image: artist depiction]
Source: Glory Project Office.
Glory project is a low-Earth orbit satellite that will contribute to
the U.S. Climate Change Science Program. The satellite has two
principal science objectives: (1) collect data on the properties of
aerosols and black carbon in the Earth‘s atmosphere and climate
systems and (2) collect data on solar irradiance. The satellite has
two main instruments-”the Aerosol Polarimetry Sensor (APS) and the
Total Irradiance Monitor (TIM)-”as well as two cloud cameras. The TIM
will allow NASA to have uninterrupted solar irradiance data by bridging
the gap between NASA‘s Solar Radiation and Climate Experiment and the
National Polar-orbiting Operational Environmental Satellite System
(NPOESS).
Formulation:
Formulation start: 9/05;
Preliminary design review: 9/05.
Implementation:
Project Confirmation: 12/05;
Critical design review: 7/06;
GAO review: 12/10;
Launch readiness date: 2/11.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2009): $347.9;
Latest (Feb. 2011): $424.1;
Change: 21.9%.
Formulation Cost:
Baseline Est. (FY 2009): $70.5;
Latest (Feb. 2011): $70.8;
Change: 0.4%.
Development Cost:
Baseline Est. (FY 2009): $259.1;
Latest (Feb. 2011): $337.6;
Change: 30.3%.
Operations Cost:
Baseline Est. (FY 2009): $18.3;
Latest (Feb. 2011): $15.8;
Change: -13.7%.
Launch Schedule:
Baseline Est. (FY 2009): 67/2009;
Latest (Feb. 2011): 3/2011;
Change: 21 months.
Recent/Continuing Project Challenges:
* Launch Issues;
* Funding Issues;
* Parts Issues.
Previously Reported Challenges:
* Technology Maturity;
* Complexity of Heritage Technology;
* Design Stability;
* Contractor Performance.
Project Summary:
Significant cost increases and schedule delays have persisted on Glory
despite being reauthorized by Congress and re-baselined in 2009.
Development costs have increased by about 30 percent since 2009.
Recent cost increases and schedule delays are residual effects of
switching to an alternate single board computer provider, the late
delivery of the APS instrument, and, more recently, due to part
quality issues found in the solar array drive assembly. Glory will
launch on the Taurus XL launch vehicle, which is returning to flight
after the vehicle failed during a 2009 launch.
Project Update:
Parts Issues: The Glory project has experienced significant schedule
delays due to reliability problems with key parts found during
testing. For example, in June 2010, the project discovered excessive
wear and debris of the Slip Ring Assembly, a part contained in the
solar array drive assembly that rendered one of the array wings
unacceptable for flight. The corrected solar array drive assembly was
integrated with the spacecraft in November 2010. The other solar array
drive assembly was inspected, found to have no signs of wear or
debris, and sent back to the contractor for integration with the
spacecraft. This issue has resulted in an additional 3 month launch
delay.
Prior to the solar array issue, the project switched from using a
single board computer (SBC) to an alternate SBC produced by another
company. According to the project manager, continued reliability
issues with the initial SBC, including cracks in the printed wiring
boards, required the project to seek another vendor for the SBC as the
part failed during testing. While the new SBC has now been integrated
with the spacecraft and is performing well, project officials estimate
the total cost impact of this switch in technology to be approximately
$60.9 million.
Launch Issues: The Glory project has been tracking the return to
flight activities of the Taurus XL launch vehicle as a risk to
achieving its launch readiness date in February 2011. The vehicle
failed during the launch of the Orbiting Carbon Observatory (OCO) in
February 2009. The launch failure Mishap Investigation Board (MIB)
subsequently released findings and suggested corrective actions.
Specifically, the MIB found that a payload fairing-”a clamshell-shaped
cover that encloses and protects a payload during early flight-”failed
to separate during ascent. NASA‘s Launch Services Program has
developed a corrective action plan and, according to a Launch Services
Program official, the Taurus XL corrective actions were on track to
meet the launch vehicle readiness review for Glory in September 2010.
The return to flight activities for the Taurus XL is on-going while
the project performs test and integration of instruments after the
over one year late delivery of the APS and a parts failure in the
Single Board Computer. A malfunction in the ground support equipment
associated with the Taurus XL launch vehicle has subsequently delayed
the launch of the Glory project until March 2011.
Funding Issues: The Glory project‘s development costs have increased
by almost 31 percent and its launch has been delayed by 21 months
since being reauthorized by Congress and re-baselined in 2009 after a 53
percent development cost increase. Cost increases and schedule delays
are a residual result of switching to an alternate single board
computer provider due to reliability issues, the late delivery of the
APS instrument, and, more recently, due to parts failure in the solar
array drive assembly. Since Glory‘s original fiscal year 2008
baseline, the project‘s development costs have grown by 113 percent
and its launch has been delayed over 2 years. The Glory project also
received $16 million under the American Recovery and Reinvestment
Act of 2009 (ARRA) which was used to maintain the current workforce
through the planned launch.
Project Office Comments:
The Glory project office provided technical comments to a draft of
this assessment, which were incorporated as appropriate. Project
officials also commented that the project continues to monitor the
Taurus XL return to flight activities.
[End of Glory data]
Gravity Recovery and Interior Laboratory (GRAIL):
Common Name: GRAIL:
[Refer to PDF for image: artist depiction]
Source: Courtesy of NASA/JPL-Caltech.
The GRAIL mission will seek to determine the structure of the lunar
interior from crust to core, advance our understanding of the thermal
evolution of the Moon, and extend our knowledge gained from the Moon
to other terrestrial-type planets. GRAIL will achieve its science
objectives by placing twin spacecraft in a low altitude and nearly
circular polar orbit. The two spacecraft will perform high-precision
measurements between them. Analysis of changes in the spacecraft-to-
spacecraft data caused by gravitational differences will provide
direct and precise measurements of lunar gravity. GRAIL will
ultimately provide a global, high-accuracy, high-resolution gravity
map of the Moon.
Formulation:
Formulation start: 12/07;
Preliminary design review: 11/08.
Implementation:
Project Confirmation: 1/09;
Critical design review: 11/09;
GAO review: 12/10;
Launch readiness date: 9/11.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2009): $496.2;
Latest (Feb. 2011): $496.2;
Change: 0.0%.
Formulation Cost:
Baseline Est. (FY 2009): $50.5;
Latest (Feb. 2011): $50.5;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2009): $427.0;
Latest (Feb. 2011): $427.0;
Change: 0.0%.
Operations Cost:
Baseline Est. (FY 2009): $18.7;
Latest (Feb. 2011): $18.7;
Change: 0.0%.
Launch Schedule:
Baseline Est. (FY 2009): 9/2011;
Latest (Feb. 2011): 9/2011;
Change: 0 months.
[End of table]
Recent/Continuing Project Challenges:
* Technology Issues;
* Launch Issues.
Project Summary:
During formulation it was determined that the reaction wheel assembly
did not meet mission requirements. The project office undertook a new
development effort of the reaction wheel, but because of a mechanical
design flaw found in testing, it will not be delivered on schedule. In
addition, the schedule for testing and integration for avionics has
been impacted by late delivery of parts and hardware problems. Project
officials continue to be concerned about the availability of Delta II
Heavy launch personnel and resources for the mission.
Project Update:
Technology Issues: GRAIL project officials said they included no new
technology in designing the GRAIL orbiters to keep the mission simple,
cost effective, and as close to the Gravity Recovery and Climate
Experiment (GRACE) mission as possible. Therefore, the GRAIL project
instruments are similar to those used in the GRACE mission. All
heritage technologies for the project, except for the reaction wheel
assembly, were deemed mature at the preliminary design review. Project
officials told us that during formulation they reviewed the reaction
wheel assembly and determined that it did not meet the standards for
this mission and caused the project to undertake a new development
effort. The electronics of the newly developed reaction wheel are
combined into the mechanical assembly, and the project decreased the
diameter of the mechanical assembly. However, the reaction wheel
assembly flight units are not on track for on-time delivery because of
a mechanical design flaw found in testing. The project determined that
there was a problem with the bearing material and modifications had to
be made to allow for proper load bearings and stability. The project
has determined the root cause of the problem and developed a design
update to correct the problem. Project officials said that schedule
contains enough margin to accommodate the late delivery of the
reaction wheel assembly without affecting the launch schedule.
Launch Issues: Last year, we reported that GRAIL project officials
were concerned about the availability of trained personnel to process
the launch since GRAIL would have been the last NASA project to launch
on the Delta II launch vehicle. Since that time, the NPOESS
Preparatory Project (NPP) has delayed its launch date, and therefore,
GRAIL is no longer the last NASA project scheduled to launch on the
Delta II launch vehicle. Project officials told us they continue to be
concerned about the availability of Delta II launch personnel and
continue to monitor that availability as a risk to the project. NASA
launch services is monitoring changes in Delta II launch services
personnel and processes and the post-production support proposals for
all major subcontractors.
Other Issues to be Monitored: Project officials told us the delivery
of the avionics flight boxes have been delayed due to late delivery of
parts, which will impact the system level environmental tests for these
units and, therefore, are on the critical path. However, the project
mitigated this risk by using engineering test units of the avionics
boxes since the flight unit deliveries were delayed past the beginning
of test and integration in July 2010. Project officials told us that
the project can conduct system-level testing using engineering test
units if the avionics boxes are further delayed since the electronics
boards are the same in both units and can be swapped out prior to the
system-level environmental testing. The project expects that the two
flight units will be delivered by early 2011. The project has modified
its schedule to accommodate for the delay in the delivery of the
flight avionics and reported it has sufficient schedule margin to meet
the launch date.
Project Office Comments:
The GRAIL project office commented that the project has completed all
the major milestones on schedule and is currently on track to meet its
launch readiness date.
[End of GRAIL data]
Ice, Cloud, and Land Elevation Satellite-2 (ICESat-2):
Common Name: ICESat-2:
[Refer to PDF for image: artist depiction]
Source: ICESat-2 Project Office.
Formulation:
Formulation start: 12/09;
GAO review: 12/10;
Preliminary design review: 11/11.
Implementation:
Critical design review: 11/12;
Launch readiness date: 10/15.
Table: Project Performance (then year dollars in millions):
Latest (Feb. 2011):
Preliminary Estimate of Project Life Cycle Cost[A]: not available.
Launch Schedule: 10/2015.
[A] The project has not yet reached the point in the acquisition
life cycle where a preliminary life cycle cost estimate would
normally be developed.
[End of table]
Recent Project Challenges:
* Launch Issues;
* Funding Issues.
Project Summary:
ICESat-2 was approved to begin formulation in December 2009. The project
‘s internal cost estimates exceeded the cost cap, which led the
project to evaluate potential cost reduction activities and re-scope
options. These activities delayed the Mission Definition Review
originally planned for August 2010 until January 2011. The project
used $20.4 million in American Recovery and Reinvestment Act of 2009
funds to work with four major laser vendors to mature the micro-pulse
laser designs. However, the acquisition and testing for the laser
subsystem is behind schedule.
Project Update:
Launch Issues: ICESat-2 is tracking a risk due to the lack of medium
class launch vehicle availability. The project is concerned that a
delay in identifying a launch vehicle for the mission will lead to
cost and schedule impact. The only certified vehicle currently
available to NASA missions in the ICESat-2 launch time frame is the
Atlas V, an intermediate launch vehicle. The only medium class launch
vehicle currently available under NASA‘s contract for launch services
is the Falcon 9; however, it has not yet been certified. If ICESat-2
selects the Falcon 9, the mission launch date would be tied to a
successful certification of the launch vehicle. The Atlas V comes at a
higher cost than what NASA has traditionally paid for a medium
capability launch vehicle. Officials told us that the project is
currently allocating $100 million for the launch vehicle. The project
planned to develop a procurement package to initiate procurement of a
launch vehicle in early fiscal year 2011.
Funding Issues: NASA provided cost parameters for the ICESat-2
mission; however, the project‘s internal life cycle cost estimates
exceeded the cost cap by $100 million. Project officials are currently
evaluating how they can reduce the project‘s life-cycle cost estimates
through various re-scoping options, such as partnering with another
ongoing mission or reducing the mission life. Due to these activities,
the project‘s Mission Definition Review, originally scheduled for
August 2010, was not scheduled to occur until January 2011 at the
earliest. In addition, the project used $20.4 million in American
Recovery and Reinvestment Act of 2009 (ARRA) funding for the micro-
pulse laser development contracts to retire project risk earlier.
However, the acquisition and testing of these laser subsystems is
behind schedule due to delays associated with the ARRA reporting by
the agency. Also, according to project officials, the project received
$28 million in fiscal year 2010 funding from the President‘s global
climate initiative, but it was unable to use all of the additional funds
within the fiscal year and is unsure whether it will receive funding
from this initiative in fiscal year 2011.
Other Issues to be Monitored: The project entered the formulation
phase in December 2009. During the mission concept review process, the
project responded to changing science requirements, particularly the
need to accurately measure slope through micro-pulse laser technology.
The Advanced Topographic Laser Altimeter System is the single
instrument on the ICESat-2 mission. The project identified two critical
technologies, the micro-pulse lasers and the Laser Reference System
(LRS). The project expects that both technologies will be mature at
the preliminary design review scheduled for November 2011. The
micropulse lasers being developed for ICESat-2 use a low energy pulse
at a high frequency, a change from the high power lasers used on the
original ICESat mission. The project is working with four major laser
vendors to mature the micro-pulse laser technology and designs.
Despite delays in awarding the contracts, the vendors are working
toward the original milestone delivery dates to reduce schedule risk.
The LRS is designed to provide absolute laser pointing knowledge in
order to pinpoint the ice footprint location 6 meters on the ground.
Project Office Comments:
The ICESat-2 project provided technical comments to a draft of this
assessment, which were incorporated as appropriate. Project officials
also commented that ICESat-2 is currently in formulation and
activities are on-going to confirm a mission that fits within the cost
cap. NASA does not formally commit to a project‘s schedule and cost
until Key Decision Point (KDP)-C, which ICESat-2 has not yet reached.
[End of ICESat-2 data]
James Webb Space Telescope (JWST):
Common Name: JWST:
[Refer to PDF for image: artist depiction]
Source: Northrop Grumman Aerospace Systems.
Formulation:
Formulation start: 3/99;
Preliminary design review: 3/08.
Implementation:
Project Confirmation: 7/08;
Critical design review: 3/10;
GAO review: 12/10;
Launch readiness date: 6/14.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2009): $4963.6;
Latest (Feb. 2011): $5095.4;
Change: 2.7%.
Formulation Cost:
Baseline Est. (FY 2009): $1800.1;
Latest (Feb. 2011): $1800.2;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2009): $2581.1;
Latest (Feb. 2011): $2710.9;
Change: 5.0%.
Operations Cost:
Baseline Est. (FY 2009): $582.4;
Latest (Feb. 2011): $584.5;
Change: 0.4%.
Launch Schedule:
Baseline Est. (FY 2009): 6/2014;
Latest (Feb. 2011): 6/2014;
Change: 0 months.
[End of table]
Recent/Continuing Project Challenges:
* Funding Issues;
* Contractor Issues;
* Design Issues.
Previously Reported Challenges:
* Complexity of Heritage Technology.
Project Summary:
NASA is taking steps to address deficiencies identified by two
independent reviews this year. One independent review panel found that
the earliest possible launch date for JWST is September 2015, a 15-
month delay from the baseline estimate. To meet this date, the panel
estimated the project would need an additional $500 million over the
next 2 fiscal years and a total life-cycle cost of approximately $6.5
billion. A separate review team reported that JWST‘s test plans
exceeded the money and time available. As a result of these reviews,
the program office at NASA headquarters will now report directly to
the NASA Associate Administrator.
Project Update:
Funding Issues: According to an October 2010 Independent Comprehensive
Review Panel (ICRP) report, JWST‘s baseline did not reflect the most
probable cost and resulted in a project that was not executable with
the given budget. The ICRP found that the budget was understated
because it did not include known threats and provided insufficient
reserves, particularly in the year of confirmation and the year
following. The panel also reported problems with overall project
management and a lack of effective oversight by Division managers who
concurred with the project‘s practice of deferring work to later years
without assessing the future impact. To address existing funding
concerns, JWST received $75 million under the American Recovery and
Reinvestment Act of 2009. Despite these additional funds, the ICRP
found that the earliest launch date possible is September 2015”-15
months after the baseline schedule. Further, the ICRP reported
that JWST‘s life-cycle cost would likely increase by $1.4 billion or
more, $500 million of which would be required in the next 2 fiscal
years. In response to the panel‘s recommendations, NASA made several
organizational changes, including establishing a new program office at
headquarters that reports directly to the NASA Associate Administrator
and managing the project‘s budget separately from Astrophysics.
Contractor Issues: At confirmation, the project believed it had
sufficient insight into contractor performance to predict future
trends and used Earned Value Management data to predict cost overruns
at the contractor. Project officials told us that shortly after
confirmation the prime contractor and a subcontractor came forward
with previously unidentified risks to project cost, leaving the
project with insufficient reserves. The ICRP found that the project
had identified these cost risks, but failed to account for them in
project reserves because they had not yet been formally documented by
the contractor. The project intends to take over testing and
integration responsibilities for the OTE/ISIM instruments from the
contractor. Despite these challenges, the project is approaching the
end of the 5-year polishing phase for the OTE primary mirror segments
and started the fourth round of cryo testing on the primary mirrors in
May 2010.
Design Issues: The project has identified challenges in analytically
demonstrating that the design of the ISIM composite structure had the
necessary strength and performance capability. The ISIM structure and
the bonds used to attach instruments must be designed to withstand
very low temperatures for an indefinite period. The project needed to
develop and verify new analytical techniques for testing which required
additional time and money. At mission critical design review, the
project planned for two thermal and optical performance tests of the
ISIM. The project continues to track ISIM‘s thermal testing as a major
risk. Other Issues to be Monitored: The scale, complexity, and
cryogenic nature of JWST prohibit a traditional ’Test as you Fly“ end-
to-end testing program; therefore, the project is more dependent on
analysis and subcomponent testing. After the mission critical design
review, NASA chartered a Test Assessment Team (TAT) to evaluate the
project‘s test plans. The TAT report found that some of the test plans
exceeded the money and time available and made recommendations to
prioritize verification tasks, help the project gain efficiencies,
particularly in the thermal testing, and reduce costs and shorten the
schedule. The project has formally concurred with most of the TAT
recommendations. The project also addressed residual concerns from the
mission preliminary design review over the sunshield testing at the
instrument CDR in January 2010 and is pending closure as the project
works on details of the test plan.
Project Office Comments:
The JWST project office provided technical comments to a draft of this
assessment, which were incorporated as appropriate. The project
officials also commented that the project and its international
partners have made good technical progress and retired some of the
highest technical risks. In addition, NASA is executing a
reorganization of the project and developing a new independent cost
estimate to address management and budget challenges highlighted in
the recent ICRP report.
[End of JWST data]
Juno:
Common Name: Juno:
[Refer to PDF for image: artist depiction]
Source: NASA/JPL.
Formulation:
Formulation start: 7/05;
Preliminary design review: 5/08.
Implementation:
Project Confirmation: 8/08;
Critical design review: 4/09;
GAO review: 12/10;
Launch readiness date: 8/11.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2009): $1107.0;
Latest (Feb. 2011): $1107.0;
Change: 0.0%.
Formulation Cost:
Baseline Est. (FY 2009): $186.3;
Latest (Feb. 2011): $186.3;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2009): $742.3;
Latest (Feb. 2011): $742.3;
Change: 0.0%.
Operations Cost:
Baseline Est. (FY 2009): $178.4;
Latest (Feb. 2011): $178.4;
Change: 0.0%.
Launch Schedule:
Baseline Est. (FY 2009): 8/2011;
Latest (Feb. 2011): 8/2011;
Change: 0 months.
[End of table]
Recent/Continuing Project Challenges:
* Technology Issues;
* Design Issues;
* Parts Issues;
* Contractor Issues.
Previously Reported Challenges:
* Development Partner Issues.
Project Summary:
Juno continues to address issues with heritage technology. The Command
and Data Handling Unit, a required component of the spacecraft,
remains on the critical path due to late workforce ramp-up by the
contractor and start of the flight design effort and could cause a
delay in the scheduled launch. Furthermore, modifications have been
made to the Command and Data Handling Unit‘s Module Interface Card
board to address Mars Reconnaissance Orbiter in flight issues.
Finally, poor materials quality caused the failure of certain
components of the spacecraft‘s solar arrays during testing and led to
a change in supplier.
Project Update:
Technology Issues: After the preliminary design review, the project
reassessed the Toroidal Low Gain Antenna (TLGA) as being immature when
it was determined that the materials being used in the highly charged
particle environment could store an electrical charge, which would in
turn interfere with some lower-level science requirements from two of
the instruments on the spacecraft. The project has since coated the
surface of the TLGA with germanium to provide a discharge path to the
grounded metal structure that resolved the interference issue.
Design Issues: The Juno project had released only 39 percent of the
engineering drawings at the critical design review (CDR). Project
officials, however, said they used engineering models for all
instruments to demonstrate design maturity at CDR. For some spacecraft
components, the Juno project did not build or test engineering models
because they were of heritage designs. For example, some spacecraft
components being utilized are very similar to the ones used on the
Mars Reconnaissance Orbiter (MRO); therefore, the project accepted
some of the spacecraft card designs based on qualification testing. In
addition, subsystem and component-level reviews were held prior to the
mission CDR, and project officials told us the results of these lower-
level reviews provided evidence that the design was stable. However,
modifications have been made to the Command and Data Handling Unit‘s
Module Interface Card (CMIC) board to respond to two series of
reset/sideswap events found during the MRO design review as well as
MRO in-flight software issues. The root cause of the problems in the
MRO CMIC board has not been determined, but Juno has made a total of
12 design changes to mitigate the problems in Juno‘s CMIC design.
Parts Issues/Contractor Issues: The molybdenum tabs, parts attached to
the solar cells used to conduct power from the cells to the solar
array power harness, failed during testing. The project established a
failure review board that found the failures were caused by poor
materials quality. The project subsequently switched the material
supplier for this part. The failure review board also investigated
solar array disbonding issues and found that they were caused by
contractor workmanship errors in the surface preparation of the solar
array panels. The contractor adjusted its procedures and re-fabricated
the panels.
Other Issues to be Monitored: Juno project officials said that they
began integration and testing in April 2010. The project is
experiencing delays in the delivery of the Command and Data Handling
(C&DH) module as a result of late workforce ramp-up and a late start
of the flight design effort. The C&DH module remains on the critical
path and could cause a delay to Juno‘s launch. Assembly and testing
has begun with a test unit version of the C&DH module while design
issues are addressed on the flight unit. Furthermore, to address
schedule concerns on the Italian Space Agency‘s (ASI) development of
the Ka-band translator after the 2009 earthquake in Italy, the project
requested and ASI agreed to upgrade the engineering model to be a
flyable engineering model. This flyable engineering model has already
been fully tested, delivered to the Juno project, and installed on the
flight system. Although the project expected to fly the engineering
model, work continued on the original flight model. The original
flight model was delivered and integrated on the spacecraft in
September 2010.
Project Office Comments:
The Juno project office provided technical comments to a draft of this
assessment, which were incorporated as appropriate. Project officials
also commented that the project has successfully resolved several
technical issues and has accommodated any delays via technical and
schedule resiliency and that the project team continues to make good
progress toward its projected launch date of August 5, 2011.
[End of Juno data]
Landsat Data Continuity Mission (LDCM):
Common Name: LDCM:
[Refer to PDF for image: artist depiction]
Source: Orbital.
The Landsat Data Continuity Mission (LDCM), a partnership between NASA
and the U.S. Geological Survey, seeks to extend the ability to detect
and quantitatively characterize changes on the global land surface at
a scale where natural and man-made causes of change can be detected
and differentiated. It is the successor mission to Landsat 7. The
Landsat data series, begun in 1972, is the longest continuous record
of changes in the Earth‘s surface as seen from space. Landsat data is
a resource for people who work in agriculture, geology, forestry,
regional planning, education, mapping, and global change research.
Formulation:
Formulation start: 10/03;
Preliminary design review: 7/09.
Implementation:
Project Confirmation: 12/09;
Critical design review: 5/10;
GAO review: 12/10;
Launch readiness date: 6/13.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2010): $941.7;
Latest (Feb. 2011): $941.6;
Change: 0.0%.
Formulation Cost:
Baseline Est. (FY 2010): $341.5;
Latest (Feb. 2011): $341.4;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2010): $583.4;
Latest (Feb. 2011): $587.6;
Change: 0.7%.
Operations Cost:
Baseline Est. (FY 2010): $16.8;
Latest (Feb. 2011): $12.5;
Change: -25.6%.
Launch Schedule:
Baseline Est. (FY 2010): 6/2013;
Latest (Feb. 2011): 6/2013;
Change: 0 months.
[End of table]
Recent Project Challenges:
* Funding Issues;
* Parts Issues.
Previously Reported Challenges:
* Technology Maturity;
* Development Partner Performance.
Project Summary:
In December 2009, NASA established a baseline launch readiness date
for the LDCM project of June 2013. However, internally the project
continues to plan for a December 2012 launch in order to avoid or
minimize a gap in LANDSAT data. When the project established the
baseline, the Thermal Infrared Sensor (TIRS) instrument was officially
added to the scope of the mission, increasing the mission cost by
approximately $160 million. The project is tracking parts issues for
all of its major components-”the TIRS and the Operational Land Imager
instruments and the spacecraft. The cost and schedule impacts of some
of these issues are uncertain.
Project Update:
Funding Issues: Last year the project reported an estimated lifecycle
cost range of $730-800 million but established a baseline life-cycle
cost estimate of $941.7 million due to the addition of the Thermal
Infrared Sensor (TIRS) instrument in December 2009, at an estimated
additional cost of $160 million. The TIRS instrument was officially
added to the scope of LDCM due to demand from the science community.
With that addition, LDCM‘s instrument payload consists of two
instruments, the Operational Land Imager (OLI)-”a multi-spectral
imaging sensor to detect and characterize land changes”-and the TIRS-”
a sensor that has a wide range of uses, including water resource
management and wildfire risk assessment. LDCM received $63.4 million
in American Recovery and Reinvestment Act (ARRA) funding, and used the
money to procure items for the components of the TIRS instrument, the
spacecraft, and the OLI instrument.
At confirmation in December 2009, the project and the Standing Review
Board presented Joint Cost and Schedule Confidence Level (JCL) results
based on mutually agreeable risks and uncertainty factors. The JCL
estimates developed for the project resulted in a 50-percent
confidence level launch date of December 2012, and a 70-percent
confidence date of June 2013. The project continues to plan internally
for a December 2012 launch date in order to avoid a potential data gap
and has $91 million budgeted for risk mitigation in order to meet the
earlier date. LDCM is working with its ground system partner, the
United States Geological Survey (USGS), to determine the likelihood of
a data availability gap and steps to mitigate the risk of a gap.
Additionally, to address funding shortfalls at USGS and reduce the
risk to mission success, NASA and USGS amended the final
implementation agreement for LDCM to increase NASA‘s role in the
ground system development and shift some of the funding
responsibilities to USGS in later years, which decreased the
LDCM estimate for operations to decrease by 25 percent.
Parts Issues: The project is tracking risks associated with the TIRS
and OLI instruments and the spacecraft. The project discovered that
the main electronics boards on the main electronics box of the TIRS
instrument were not meeting thermal stability requirements. While TIRS
is a new, in-house development effort and is on the project‘s critical
path, many of the subsystems and components were used in earlier
flight projects. The issues with the main electronics box cost $3.8
million, but the problem had no net impact to the project‘s schedule.
The OLI instrument experienced problems with the black chrome plating
and dark mirror coating. According to project officials, the black
chrome plating did not withstand testing and lost adhesion, due to
poor plating processes at the vendor. As a result, the vendor rebuilt
the Solar Calibration Assembly. These issues currently have no overall
impact on the project‘s schedule, and the cost impacts have been
negotiated. On the spacecraft, the project identified contamination of
the Reaction Wheel Assembly (RWA) lubricant and scheduled to have new
bearings installed by the vendor. Project officials said that they
have identified windows during integration and test where a new unit
can be inserted. Although the problem caused a six month schedule slip
for the RWA, the project expects no impact on the overall schedule
because the delay was largely absorbed by the integration and testing
workarounds and subsystem schedule slack.
Last year, we reported that the project had released 83 percent of its
design drawings as of September 2009. In April 2010, the project had
released 93 percent of its drawings and held a successful mission
critical design review (CDR) in May 2010, but the project is tracking
risks on each of the major components. Currently, the project reports
that 97 percent of the total design drawings have been released.
Project Office Comments:
The LDCM project provided technical comments to a draft of this
assessment, which were incorporated as appropriate. Project officials
also commented that the mission has set a commitment for a launch
readiness date of June 2013, but the project is aggressively working
to launch in December 2012 in order to minimize the chance of a data
gap should Landsat 5 or Landsat 7 cease operations.
[End of LDCM data]
Lunar Atmosphere and Dust Environment Explorer (LADEE):
Common Name: LADEE:
[Refer to PDF for image: artist depiction]
Source: LADEE Project Office.
The Lunar Atmosphere and Dust Environment Explorer (LADEE) mission
objective is to determine the global density, composition, and time
variability of the lunar atmosphere. LADEE‘s measurements will
determine the size, charge, and spatial distribution of
electrostatically transported dust grains. Additionally, LADEE will
carry an optical laser communications demonstrator that will test high-
bandwidth communication from lunar orbit.
Formulation:
Formulation start: 2/09;
Preliminary design review: 7/10.
Implementation:
Project Confirmation: 8/10;
GAO review: 12/10;
Critical design review: 8/11;
Launch readiness date: 11/13.
Table: Project Performance (then year dollars in millions):
Total Project Cost[A]:
Baseline Est. (FY 2010): $262.9;
Latest (Feb. 2011): $262.9;
Change: 0.0%.
Formulation Cost:
Baseline Est. (FY 2010): $79.5;
Latest (Feb. 2011): $79.5;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2010): $168.2;
Latest (Feb. 2011): $168.2;
Change: 0.0%.
Operations Cost:
Baseline Est. (FY 2010): $15.2;
Latest (Feb. 2011): $15.2;
Change: 0.0%.
Launch Schedule:
Baseline Est. (FY 2010): 11/2013;
Latest (Feb. 2011): 11/2013;
Change: 0 months.
[A] This estimate does not include the LLCD instrument which
is being funded by the Space Operations Mission Directorate
at a cost of approximately $65 million.
[End of table]
Recent Project Challenges:
* Technology Issues;
* Parts Issues;
* Launch Issues.
Project Summary:
The LADEE project was confirmed on August 23, 2010, to proceed into
implementation. LADEE will be flying three heritage instruments, as
well as the Lunar Laser Com Demo, which is being developed by the
Space Operations Mission Directorate at a cost of approximately $65
million. NASA will launch the project on the Minotaur V. A bid protest
delayed the issuance of a delivery order for the launch vehicle and
postponed development of a Soft-Ride system that will protect
instrumentation during launch.
Project Update:
Technology Issues: LADEE utilizes three instruments that have been
designed for other missions but require modifications to their form,
fit, and function. None of the three instruments were considered
mature at the preliminary design review in July 2010. NASA flew the
Lunar Dust Experiment (LDEX) on various configurations on the HEOS 2,
Galileo, Ulysses, and Cassini projects. The Neutral Mass Spectrometer
(NMS) is a subset of the Sample Analysis at Mars instrument being
developed for the Mars Science Laboratory. The Ultraviolet
Spectrometer (UVS) is based on the design of the UVS instrument flown
on the Lunar Crater Observation and Sensing Satellite (LCROSS). The
project will also fly the Lunar Laser Com Demo (LLCD) as a ride along
technology demonstration on LADEE. The LLCD is being developed by the
Space Operations Mission Directorate at a cost of approximately $65
million, which is not included in the LADEE cost estimates.
Parts Issues: The UVS has run into problems with the source vendor and
parts quality and, therefore, is not identical to the LCROSS version
of the instrument. Project officials determined that the printed
wiring board for the UVS was being developed in a facility with no
quality systems or workmanship standards in place. The project decided
to keep the printed wiring board design, but had another vendor
produce the boards at a NASA-approved facility. Implementation of this
change cost the project approximately $1.1 million.
Launch Issues: LADEE will be launched on a Minotaur V, which was
procured under the Air Force‘s indefinite delivery indefinite quantity
contract with a commercial launch vehicle provider. A bid protest
regarding the selection of the Minotaur V, however, delayed the
issuance of the delivery order for the vehicle and the project‘s
preliminary design review by 3 months and the critical design review
by 5 months. Furthermore, the project will need to equip the launch
vehicle with a Soft-Ride system in order to protect the project‘s
instrumentation from excessive vibration during launch. While there is
no new development effort behind the Soft-Ride, the system must be
tuned to the particular load environment and spacecraft design, which
will be delayed until the launch vehicle delivery order is issued.
Other Issues to be Monitored: The LADEE project has not reached a
design review where we could assess design stability. As of September
2010, the project expected to release 58 percent of its design
drawings by the preliminary design review and 83 percent by the
critical design review. Because of its focus on being a low cost
mission, LADEE‘s only critical technology is the RF antenna on the
spacecraft, which, according to the project office, is proceeding on
schedule.
Project Office Comments:
The LADEE project office provided technical comments to a draft of
this assessment, which were incorporated as appropriate. LADEE project
officials also commented that the bid protest on the launch vehicle
has been resolved and that the Minotaur will be procured under an Air
Force contract with a commercial launch service provider.
[End of LADEE data]
Magnetospheric Multiscale (MMS):
Common Name: MMS:
[Refer to PDF for image: Computer Model]
Source: MMS Project Office.
The Magnetospheric Multiscale (MMS) is made up of four identically
instrumented spacecraft. The mission will use the Earth's
magnetosphere as a laboratory to study the microphysics of magnetic
reconnection, energetic particle acceleration, and turbulence.
Magnetic reconnection is the primary process by which energy is
transferred from solar wind to Earth‘s magnetosphere and is the
physical process determining the size of a space weather storm. The
spacecrafts will fly in a pyramid formation, adjustable over a range
of 10 to 400 kilometers, enabling them to capture the three-
dimensional structure of the reconnection sites they encounter. The
data from MMS will be used as a basis for predictive models of space
weather in support of exploration.
Formulation:
Formulation start: 5/20;
Preliminary design review: 5/09.
Implementation:
Project Confirmation: 6/09;
Critical design review: 8/10;
GAO review: 12/10;
Launch readiness date: 3/15.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2010): $1082.7;
Latest (Feb. 2011): $1082.7;
Change: 0.0%.
Formulation Cost:
Baseline Est. (FY 2010): $173.0;
Latest (Feb. 2011): $173.0;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2010): $857.4;
Latest (Feb. 2011): $857.4;
Change: 0.0%.
Operations Cost:
Baseline Est. (FY 2010): $52.3;
Latest (Feb. 2011): $52.3;
Change: 0.0%.
Launch Schedule:
Baseline Est. (FY 2010): 3/2015;
Latest (Feb. 2011): 3/2015;
Change: 0 months.
[End of table]
Recent Project Challenges:
* Development Partner Issues;
* Design Issues;
* Technology Issues.
Project Summary:
The MMS project used $6 million in cost reserves to move development
work for the Spin Plane Double Probe instrument from Sweden to the
University of New Hampshire because Sweden was not providing adequate
levels of funding for project development. The movement of development
work has resulted in a delay of approximately 6 months for the
completion of the design for the instrument. However, project
officials do not believe the delay will impact the mission‘s March
2015 launch readiness date.
Project Update:
Development Partner Issues: The MMS project used approximately $6
million in reserve funds to move work from Sweden to the University of
New Hampshire because Sweden was not making satisfactory progress on
the production of the Spin Plane Double Probe (SDP) instrument due to
inadequate levels of funding. After considering three potential
candidates, the MMS project selected the University of New Hampshire
in 2010 to assume production of the SDP deployment mechanism, the most
complex element of the SDP instrument. Sweden will continue to provide
SDP flight hardware as well as mission science support. As a result of
these changes, the completion of the design for the SDP is behind
schedule by approximately 6 months, but MMS officials believe this
change poses no threat to the mission‘s launch readiness date in March
2015.
Design Issues: In August 2010, the project completed its mission
critical design review (CDR). At that time the project had released 77
percent of its engineering design drawings. Last year, project officials
told us that having 70 to 80 percent of design drawings completed by
CDR is normal, but they had not established any goals for the project.
MMS officials stated that the number of complete engineering test
units is as important, if not more so, than design drawings. According
to project officials, MMS uses high fidelity instrument models as a
risk reduction effort. By using engineering models that are as flight-
ready as possible, project officials reported that they can see where
problems are and better identify risks. Additionally, they stated that
proceeding with the manufacture of flight hardware without having
built flightlike engineering units to test the design, will almost
always lead to schedule overruns to solve design issues.
Technology Issues: Following mission CDR in August 2010, the MMS
project has yet to fully address the form, fit, and function of the
payload separation system, a key heritage technology. All four MMS
satellites will launch stacked on a single Atlas V launch vehicle.
When the top spacecraft deploys, springs will push off the first
satellite and trigger a command for each subsequent satellite to
deploy. The technology required for the separation system is not new;
however, the project is working closely with the contractor to ensure
that all four satellites separate in a consistent manner which
supports the need for them to fly in a pyramid formation.
Other Issues to be Monitored: MMS was authorized to enter formulation,
the phase that precedes implementation, in 2002 with an initial cost
estimate of $369 million. The project was authorized to enter
implementation in June 2009 with a baseline life-cycle cost estimate
of over $1 billion. The project manager said the initial cost estimate
was for a smaller instrument suite than what is currently planned for
the mission and added that one cost driver for the project since the
initial cost estimate was the requirement for magnetic and
electrostatic cleanliness. The initial cost estimate also did not
account for the higher cost of the Atlas V, which is a larger launch
vehicle than the Delta II initially considered by the project.
Project Office Comments:
The MMS project office provided technical comments to a draft of this
assessment, which were incorporated as appropriate. Project officials
also commented that MMS continues to make technical progress. In 2010,
the MMS project completed the detailed design of the instruments and
spacecraft.
[End of MMS data]
Mars Atmosphere and Volatile EvolutioN (MAVEN):
Common Name: MAVEN:
[Refer to PDF for image: artist depiction]
Source: NASA GSFC MAVEN Project Office.
The Mars Atmosphere and Volatile EvolutioN (MAVEN) mission, a robotic
orbiter mission, will provide a comprehensive picture of the Mars upper
atmosphere, ionosphere, solar energetic drivers, and atmospheric
losses. MAVEN will deliver comprehensive answers to long-standing
questions regarding the loss of Mars‘ atmosphere, climate history,
liquid water, and habitability. MAVEN will provide the first direct
measurements ever taken to address key scientific questions about Mars‘
evolution.
Formulation:
Formulation start: 9/08;
Preliminary design review: 7/10.
Implementation:
Project Confirmation: 10/10;
GAO review: 12/10;
Critical design review: 7/11;
Launch readiness date: 11/13.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2011): $671.2;
Latest (Feb. 2011): $671.2;
Change: 0.0%.
Formulation Cost:
Baseline Est. (FY 2011): $63.8;
Latest (Feb. 2011): $63.8;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2011): $567.2;
Latest (Feb. 2011): $567.2;
Change: 0.0%.
Operations Cost:
Baseline Est. (FY 2011): $40.1;
Latest (Feb. 2011): $40.1;
Change: 0.0%.
Launch Schedule:
Baseline Est. (FY 2011): 11/2013;
Latest (Feb. 2011): 11/2013;
Change: 0 months.
[End of table]
Recent Project Challenges:
* Design Issues;
* Launch Issues.
Project Summary:
MAVEN was selected under the Mars Scout Program-”a NASA initiative to
send a series of small, low-cost robotic missions to Mars. The project
was competitively selected from innovative proposals by the scientific
community. The project is relying on heritage technologies, but
project officials acknowledged that these technologies required
modifications to their form, fit, and function to operate as necessary
for MAVEN‘s requirements. The project is being designed to the Atlas V
launch vehicle, which is significantly more expensive than it was under
the previous launch services contract.
Project Update:
Design Issues: At the preliminary design review, the project manager
decided not to authorize the Respin of the High Efficiency Power
Supply (HEPS), MAVEN‘s power supply system, because of a high
probability of failure and therefore violates the mission assurance
requirements. The project met with the contractor to discuss HEPS
design, fabrication, assembly, test history and qualification in order
to resolve this issue. The MAVEN project has not reached a design
review where we could assess design stability. At the mission
preliminary design review in July 2010, the project estimated that it
would have 85 percent of its engineering drawings released at the
critical design review.
Launch Issues: According to project officials, the project was given
approval to initiate selection of a launch vehicle in September 2010
after the new NASA Launch Services (NLS) contract was awarded. Project
officials told us the project had been designing to two vehicles prior
to the new contract being awarded. However, the only available vehicle
that currently meets the needs of the MAVEN project is the
intermediate-class Atlas V, which will be significantly more expensive
than it was under the previous NLS contract. In October 2010, NASA
announced that the Atlas V had been selected as the launch vehicle for
MAVEN at a total cost of $187 million. Science Mission Directorate
officials told us that they incorporated this increased cost into the
project‘s baseline during the confirmation review.
Other Issues to be Monitored: In order to control project costs, the
project plans to minimize development activities of new technology by
designing MAVEN spacecraft and instruments based on available heritage
hardware. The MAVEN project identified seven heritage technologies,
all of which are required to meet the mission‘s science requirements.
Prior to the preliminary design review, the project deemed all heritage
technologies to be mature, but project officials acknowledged that
these heritage technologies do not take into account modifications of
form, fit, and function needed to operate in the Martian environment and
require modifications. For example, while MAVEN‘s magnetometer design
is similar to those flown on prior NASA projects, a minor change to
the electronics of the magnetometer is necessary to extend its dynamic
range. The project is also concerned that measurements from the
magnetometer may become corrupted due to the amount of electronic
interference, or noise, on the spacecraft. To alleviate this concern,
project officials decided to reconfigure the solar cells on the panel
to minimize the magnetic field at the location of the instrument. As a
result of this reconfiguration and additional analysis, project
officials reported the risk has been mitigated. Furthermore, project
officials told us they are evaluating ways to ensure that the
spacecraft and instruments will continue to operate and collect data
during major solar flares.
Project Office Comments:
The MAVEN project office provided technical comments to a draft of
this assessment, which were incorporated as appropriate. Project
officials also commented that the project entered into implementation
in October 2010 and is on track for critical design review scheduled
for July 2011.
[End of MAVEN data]
Mars Science Laboratory (MSL):
Common Name: MSL:
[Refer to PDF for image: photograph]
Source: NASA/JPL-Caltech.
The Mars Science Laboratory (MSL) is part of the Mars Exploration
Program (MEP). The MEP seeks to understand whether Mars was, is, or
can be a habitable world. To answer this question, the MSL project
will investigate how geologic, climatic, and other processes have
worked to shape Mars and its environment over time, as well as how they
interact today. The MSL will continue this systematic exploration by
placing a mobile science laboratory on the Mars surface to assess a
local site as a potential habitat for life, past or present. The MSL is
considered one of NASA‘s flagship projects and will be the most
advanced rover yet sent to explore the surface of Mars.
Formulation:
Formulation start: 11/03;
Preliminary design review: 6/06.
Implementation:
Project Confirmation: 8/06;
Critical design review: 6/07;
GAO review: 12/10;
Launch readiness date: 11/11.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2010): $2394.2;
Latest (Feb. 2011): $2476.3;
Change: 3.4%.
Formulation Cost:
Baseline Est. (FY 2010): $515.5;
Latest (Feb. 2011): $515.5;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2010): $1719.9;
Latest (Feb. 2011): $1802.0;
Change: 4.8%.
Operations Cost:
Baseline Est. (FY 2010): $158.8;
Latest (Feb. 2011): $158.8;
Change: 0.0%.
Launch Schedule:
Baseline Est. (FY 2010): 11/2011;
Latest (Feb. 2011): 11/2011;
Change: 0 months.
[End of table]
Recent/Continuing Project Challenges:
* Design Issues;
* Parts Issues.
Challenges Previously Reported:
* Technology Maturity;
* Complexity of Heritage Technology.
Project Summary:
Congress reauthorized the MSL and it was subsequently re-baselined in
January 2010 because the project had exceeded its 2008 cost baseline
by more than 30 percent. In 2009, MSL‘s cost had grown more than $834
million and its scheduled launch had been delayed 26 months from its
original 2008 baseline due to work needed to overcome technical
challenges with the actuators and avionics. This increase includes
more than an 86 percent increase in development costs.
Project Update:
Congress reauthorized the MSL in the Consolidated Appropriations Act
of 2010 and NASA subsequently rebaselined the project in January 2010
after it had exceeded its 2008 development cost baseline by more than
30 percent. Since the original project baseline in 2008, the life-
cycle cost for the project has increased by more than $834 million”
including more than an 86 percent increase in development costs”-and
the launch has been delayed until November 2011 since launch windows
for Mars mission are optimally aligned every 26 months. These cost and
schedule overruns were driven by problems with the actuators and
avionics. Specifically, the project experienced problems with the
actuators that allow the vehicle to move and execute the sample
operations performed by the lab. The project has since redesigned the
actuators and retired this risk. The project indicated that project
reserves may be inadequate to meet the scheduled work for 2011.
Design Issues: The MSL project design was not stable at the Critical
Design Review (CDR). Several design changes were required after CDR to
address various issues. For example, project officials told us the
avionics hardware was a new design and had been delivered in an
immature state. They had hoped to have all issues with the avionics
hardware completed by November 2009; however, project officials said the
design of the hardware is still not complete and the project has
delayed the software development which includes about 12 deliverables.
The avionics computer element is currently the leading risk to the MSL
schedule and its functionality is critical to the mission‘s success.
Furthermore, the Sample Analysis at Mars Wide Range Pump has had a
series of development problems and although the project has worked
through about 10 engineering models, it continues to struggle to pass
the life test. The project built and tested two different pump designs
in parallel that met the science requirements and conducted an
accelerated life test on them. The project plans to make a decision
between the two designs at the conclusion of the life test and pump
qualification testing, currently scheduled for fall 2010. The project
is also monitoring performance degradation of the Multi Mission
Radioisotope Thermoelectric Generator (MMRTG) due to the thermocouples
that convert the heat generated by the plutonium into electricity
degrading at a faster rate than predetermined, or about 10 percent.
According to the project manager, the MMRTG can still meet its
objectives with a 10 percent decay rate, but if this rate increases
the project cannot meet its requirements and will be forced to cut the
nominal number of samples collected or the distance the rover is to
travel during the primary mission.
Parts Issues: The project experienced a parts failure associated with
the transition joints in the propulsion system which caused the joints
to fail under load. Project officials reported this issue was realized
after the project finished building its propulsion system, causing the
project to rebuild the system and adopt a new joint design. The
transition to the new design required a rework and retest of the
descent cruise stages. According to project officials, the project
also encountered parts issues on the avionics package, including
a shorting out of the pins on the avionics processor and a packaging
issue that caused a disconnect between the analog components and the
configuration of the board.
Project Office Comments:
The MSL project office provided technical comments to a draft of this
assessment, which were incorporated as appropriate. The project
believes that the GAO assessment largely reflects the history of the
project and most of the issues identified have been resolved.
[End of MSL data]
NPOESS Preparatory Project (NPP):
Common Name: NPP:
[Refer to PDF for image: photograph]
Source: Ball Aerospace.
The National Polar-orbiting Operational Environmental Satellite System
(NPOESS) Preparatory Project (NPP) is a joint mission with the
National Oceanic and Atmospheric Administration (NOAA) and the U.S.
Air Force. The satellite will measure ozone, atmospheric and sea surface
temperatures, land and ocean biological productivity, Earth radiation,
and cloud and aerosol properties. The NPP mission has two objectives.
First, NPP will provide a continuation of global weather observations
following the Earth Observing System missions Terra and Aqua. Second,
NPP will function as an operational satellite and will provide data
until the first NPOESS satellite launches.
Formulation:
Formulation start: 11/98;
Preliminary design review: 1/03;
Critical design review: 8/03.
Implementation:
Project Confirmation: 11/03;
GAO review: 12/10;
Launch readiness date: 10/11.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2007): $672.8;
Latest (Feb. 2011): $864.3;
Change: 28.5%.
Formulation Cost:
Baseline Est. (FY 2007): $47.3;
Latest (Feb. 2011): $47.1;
Change: 0.5%.
Development Cost[A]:
Baseline Est. (FY 2007): $593.0;
Latest (Feb. 2011): $780.1;
Change: 31.6%.
Operations Cost:
Baseline Est. (FY 2007): $32.5;
Latest (Feb. 2011): $37.1;
Change: 14.0%.
Launch Schedule:
Baseline Est. (FY 2007): 4/2008;
Latest (Feb. 2011): 10/2011;
Change: 42 months.
[End of table]
Recent/Continuing Project Challenges:
* Development Partner Issues;
* Launch Issues.
Previously Reported Challenges:
* Technology Maturity;
* Complexity of Heritage Technology;
* Design Stability.
Project Summary:
NPP has experienced over $183 million in development cost growth and a
42-month launch delay, and officials told us that there is more work
remaining than the schedule allows. The last of the partner-provided
instruments was delivered for integration on the satellite in June
2010, although a number of risks remain. Project officials said that
many problems were uncovered late in the development process, leading
NASA to revise NPP mission success criteria. In February 2010, the
White House announced a restructuring of the NPOESS program, which
could affect the launch schedule.
Project Update:
NPP project officials have attributed cost and schedule overruns to
development partner challenges and a lack of central authority between
the three NPOESS agencies. Further, DOD, with agreement from its
partner agencies, restructured the NPOESS program in 2006, but the
program continued to experience cost and schedule growth. Since NPP
was baselined in fiscal year 2007, the project‘s development cost has
increased by 26 percent in the fiscal year 2011 budget request, and
its schedule has increased by 42 months.
Development Partner Issues: Management and developmental partner
challenges have continued to result in cost overruns and schedule
delays in the Visible Infrared Imaging Radiometer Suite (VIIRS) and
Crosstrack Infrared Sounder (CrIS) instruments. The project office
attributes almost all of the cost and schedule changes to the late
delivery of these partner-provided instruments. The CrIS was the last
instrument to arrive for NPP and was delivered to the spacecraft
contractor in June 2010. Issues with the CrIS instrument moved
the launch date from January 2011 to October 2011. Furthermore,
because NPOESS is now not scheduled to launch until 2014, NPP will
still be a demonstration satellite as originally intended but will
have to function as an operational satellite, providing interim data
until NPOESS launches.
In February 2010, the White House announced plans to restructure the
NPOESS program, into the Joint Polar Satellite System (JPSS), to
address cost overruns and schedule delays. As a result of the
restructure, NOAA and DOD will undertake separate satellite system
acquisitions. The NPOESS program continues to develop the instruments
and ground systems supporting NPP, but, according to project
officials, the management of the instruments‘ contracts is being
transferred from the NPOESS Integrated Program Office (IPO), which is
a joint U.S. Air Force and NOAA program office, to DOD‘s Space and
Missile Systems Center. The NPP project is taking steps to facilitate
cooperation and gain more authority with the technical elements than
it had at the beginning of NPP but believes the restructuring will
cause further launch delays due to fiscal constraints stemming from a
lack of necessary funds to cover termination liability for NPOESS
contracts.
Although all critical technologies are mature, NPP continues to report
an inability to reduce risks to an acceptable level on three
instruments provided by its development partners-the VIIRS, the CrIS,
and the Ozone Mapper Profiler Suite. Project officials told us they
lack confidence in the processes used by the IPO, are unsure how these
instruments will function on orbit. Further, they believe there is
more work remaining than the schedule allows for an October 2011
launch. For example, the NPP project is currently tracking the VIIRS
system‘s door deployment testing as a schedule risk. Because of the
uncertainty of the instrument‘s functionality, NASA is updating the
NPP Mission Success Criteria based on these risk assessments in order
to lower expectations and define minimum mission success criteria.
Launch Issues: Since this will be one of the last missions to be
launched on a Delta II, NASA is tracking the availability of trained
personnel to launch NPP as a risk. While NASA rates the impact of a
launch slip on NPP and the other three remaining missions scheduled
for the Delta II as high risk, the agency currently considers this as
a low probability as there are sufficient existing processes and
mitigation efforts in place.
Project Office Comments:
The NPP project provided technical comments to a draft of this
assessment, which were incorporated as appropriate. Project officials
also commented the project is working with the newly formed JPSS Program
to finalize an integrated NPP schedule to launch. They added that NPP
will continue to be a demonstration satellite for NPOESS/JPSS.
However, with the NPOESS/JPSS-1 satellite‘s launch delay to 2014,
agencies will use the NPP data operationally.
[End of NPP data]
Orbiting Carbon Observatory 2 (OCO-2):
Common Name: OCO-2:
[Refer to PDF for image: artist depiction]
Source: Jet Propulsion Laboratory.
NASA‘s Orbiting Carbon Observatory 2 (OCO-2) is based on the original
OCO mission that failed to reach orbit in 2009 and is designed to
enable more reliable predictions of climate change. It will make
precise, time-dependent global measurements of atmospheric carbon
dioxide. These measurements will be combined with data from a ground-
based network to provide scientists with the information needed to
better understand the processes that regulate atmospheric carbon
dioxide and its role in the carbon cycle. NASA hopes enhanced
understanding of the carbon cycle will improve predictions of future
atmospheric carbon dioxide increases and the potential impact on the
climate.
Formulation:
Formulation start: 3/10;
Critical design review: 8/10.
Implementation:
Project Confirmation: 9/10;
GAO review: 12/10;
Launch readiness date: 2/13.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2009): $349.9;
Latest (Feb. 2011): $349.9;
Change: 0.0%
Formulation Cost:
Baseline Est. (FY 2009): $60.9;
Latest (Feb. 2011): $60.9;
Change: 0.0%
Development Cost:
Baseline Est. (FY 2009): $249.0;
Latest (Feb. 2011): $249.0;
Change: 0.0%.
Operations Cost:
Baseline Est. (FY 2009): $40.0;
Latest (Feb. 2011): $40.0;
Change: 0.0%.
Launch Schedule:
Baseline Est. (FY 2009): 2/2013;
Latest (Feb. 2011): 2/2013;
Change: 0 months.
[End of table]
Recent Project Challenges:
* Parts Issues;
* Funding Issues.
Project Summary:
OCO-2 entered a tailored formulation phase in March 2010. The project
management‘s goal is to minimize changes from the OCO mission. The
project office worked with NASA to develop preliminary cost estimates,
which are higher than the 2008 estimate of $273.1 million for OCO, due
in part to the project obtaining a full set of spares for OCO-2. NASA
has selected the Taurus XL launch vehicle for OCO-2, the same vehicle
used for the OCO mission. The project received $18 million under the
American Recovery and Reinvestment Act of 2009 that was used to enable
the earliest possible launch.
Project Update:
Parts Issues: The project is making every effort to duplicate the
original OCO design using identical hardware, drawings, documents,
procedures, and software wherever possible and practical in order to
produce OCO-2 with minimum cost, schedule, and performance risk.
However, project officials stated that there were no engineering
models for many of the OCO components and the original components were
lost on OCO, making the rebuild difficult, particularly due to
obsolescence of parts. The OCO-2 project will procure a full set of
spares to help avoid problems with parts obsolescence during the
development and testing of flight hardware. OCO-2 encountered
difficulties with two particular components due to lack of spares and
parts obsolescence. The cryocooler used on OCO was a spare that the
project received at no cost; however, the same cryocoolers were not
available for OCO-2. Additionally, the flight computer from OCO is now
obsolete. OCO-2 is redesigning and updating the flight computer in
order to avoid converting all technology to a new flight computer.
Project officials said they held a successful critical design review
(CDR) for the redesigned flight computer based on an engineering
development unit and they expected the new design to be fully
validated by the end of 2010.
Funding Issues: The OCO-2 project office helped NASA develop a life-
cycle cost estimate based on the original life-cycle costs of OCO. In
December 2008, OCO‘s life-cycle cost estimate was $273.1 million,
compared to OCO-2‘s baseline estimate of $349.9 million. Project
officials attributed the higher life-cycle cost estimate for OCO-2 to
development of a new crycooler, inflation, procurement of a full set
of spares, and an increase in the cost of the launch vehicle. For
example, NASA did not have acquisition costs for the cryocooler for
the original OCO mission. OCO-2 is acquiring two new cryocoolers
through an interagency transfer with the National Oceanic and
Atmospheric Administration (NOAA), but will have to contract for two
new units to provide to NOAA for its future use. The project also used
$18 million under the American Recovery and Reinvestment Act of 2009
to acquire long lead items for the spacecraft, instrument development,
and project management to enable the earliest possible launch of an
OCO recovery mission.
Other Issues to be Monitored: OCO-2 entered a tailored formulation
phase in March 2010 to expedite entering implementation because the
project has been designed and built once. According to project
officials the tailored formulation reduces the number of reviews;
therefore, OCO-2‘s first major review was the mission CDR, which was
held in August 2010, and preceded project confirmation. At CDR, the
project had released 95 percent of its engineering drawings for the
instrument and spacecraft. In June 2010, NASA selected Orbital
Sciences Corporation to launch OCO-2 aboard a Taurus XL, the same
vehicle used for OCO in 2009. Orbital and NASA ran concurrent mishap
investigations following the OCO launch failure, and Orbital has
addressed the findings of each report. The Glory mission, the first to
launch on the Taurus XL since the 2009 launch failure, is scheduled to
launch in March 2011. OCO-2 is the next mission in line for the Taurus
XL.
OCO-2 includes a single instrument, the three-channel grating
spectrometer, based on heritage technology from the OCO mission.
Although the project reports that the spectrometer‘s technology
maturity is high, the project will make minor changes in components
and some obsolete parts that will need to be replaced.
Project Office Comments:
The OCO-2 project provided technical comments to a draft of this
assessment, which were incorporated as appropriate. The project
officials also commented that OCO-2 is intended to duplicate, as much
as possible, the OCO mission that was lost due to the Taurus XL
failure. As such, OCO-2 was granted a waiver from the normal NASA
project formulation process. OCO-2 is baselining a launch in February
2013.
[End of OCO-2 data]
Orion Crew Exploration Vehicle:
Common Name: Orion:
[Refer to PDF for image: artist depiction]
Source: Lockheed Martin Space Systems.
NASA‘s Orion Crew Exploration Vehicle, was designed to carry crew and
cargo to the International Space Station (ISS) and to the Moon as part
of the Constellation Program. The 5-meter diameter Orion capsule was
designed to be launched by the Ares I Crew Launch Vehicle and to carry
four astronauts to the ISS and the Moon after linking up with an earth
departure stage. The capsule will return to Earth and descend on
parachutes to the surface. Orion has three main elements”-the crew
module (capsule), service module/spacecraft adapter, and launch abort
system.
Formulation:
Formulation start: 7/06;
Preliminary design review: 8/09;
GAO review: 12/10.
Implementation:
Critical design review: 2/11;
Launch readiness date: 3/15.
Table: Project Performance (then year dollars in millions):
Latest (Feb. 2011):
Preliminary Estimate of Project Life Cycle Cost[A]: $20,000 to $29,000.
Launch Schedule: 3/2015.
[A] This estimate is preliminary, as the project is in formulation and
there is still uncertainty in the value as design options are
explored. NASA uses these estimates for planning purposes. This
estimate is for the Orion vehicle only.
[End of table]
Recent/Continuing Project Challenges:
* Funding Stability;
* Technology Issues.
Previously Reported Challenges:
* Contractor Performance.
Project Summary:
The President‘s fiscal year 2011 budget proposed cancellation of the
Orion project leading to uncertainty, both financial and programmatic,
within the project. Given constrained resources, the project
prioritized work and did not accomplish some of the work originally
planned for 2010. The project did, however, successfully complete a
test of the launch abort system and continue progress on mitigating
other technical challenges. In early fall 2010 Congress passed the
NASA Authorization Act of 2010 directing NASA to utilize existing
Orion contracts and capabilities to the extent practicable.
Project Update:
The President proposed cancellation of the Constellation Program,
including the Orion project, in his fiscal year 2011 budget request.
This proposal led to much debate within Congress and uncertainty, both
financial and programmatic, within the project. As a result, the
project prioritized work for the year and did not complete some of the
work originally planned for 2010. In early fall 2010, Congress passed
the NASA Authorization Act of 2010, which directed NASA to continue
development of a multipurpose crew vehicle capable of reaching near-
Earth and beyond near-Earth orbit no later than December 2016. In
developing this vehicle, Congress directed the agency to continue to
advance development of the human safety features, designs, and systems
in the Orion project and to utilize existing contracts and
capabilities to the extent practicable.
Funding Issues: Funding shortfalls and uncertainty have impacted
workforce availability, shifted the Orion schedule and testing
strategy, and deferred procurement of new items. For example, during
fiscal year 2010, NASA and Lockheed Martin had arranged an agreement
under which Lockheed Martin would have performed $200 million worth of
work during the current fiscal year that NASA would pay for during
later phases of the Orion project. However, according to project
officials, NASA decided not to execute the agreement because NASA
lacked sufficient budget authority to obligate funds to pay for the
work. This left the project, and the entire Constellation Program,
without the $200 million worth of work that they had expected and with
limited resources for completing the remaining work for fiscal year
2010, so therefore, the project prioritized development activities and
tests. The Orion project received nearly $166 million of funding under
the American Recovery and Reinvestment Act of 2009 that according to
project officials halted layoffs at Lockheed Martin and helped the
project overcome technical challenges. The value of the development
contracts for Orion has increased by $2.5 billion since 2006.
Technology Issues: The Orion project identified one critical heritage
technology for the spacecraft: the thermal protection system, or
heatshield, that is required for the spacecraft to survive reentry
from earth orbit. According to project officials, the new material for
the heatshield has been tested against the material used in the Apollo
program and performs as well as or better than the heritage material.
However, given the current funding constraints and uncertainty
surrounding the Orion project, the Orion project office prioritized
development activities, and while the heatshield development and
testing are continuing on plan, the determination of the manufacturing
processes has been deferred.
In addition, development of the launch abort system, which would pull
the Orion capsule away from the Ares I launch vehicle in the case of a
catastrophic problem during launch, remains a high risk area even
though it was not identified as a critical technology. In May 2010,
the project tested the Launch Abort System in the Orion‘s Pad Abort
(PA-1) test. According to project officials, PA-1 was an important
developmental milestone for the launch abort system, but certain items
that were found during the test will require design modifications to
the system that will not be tested until funding is available. The
project has also developed a new controller for the launch abort
system, and planned to test it in the ascent abort test in 2012.
However, due to funding instability, it is unknown when and if this
test will take place.
Project Office Comments:
The Orion project office provided technical comments on a draft of
this assessment, which were incorporated as appropriate. Project
officials also commented that the project has continued its work on
the Constellation program. Reductions in planned work content were
made to ensure availability of funds required to complete work already
under contract. These reductions have made it difficult for NASA to
achieve some of its goals and outcomes planned for fiscal year 2010.
NASA remains poised to leverage Constellation assets to contribute to
future exploration beyond low-Earth orbit.
[End of Orion data]
Radiation Belt Storm Probes (RBSP):
Common Name: RBSP:
[Refer to PDF for image: photograph]
Source: © 2010 The Johns Hopkins University/Applied Physics
Laboratory. All Rights Reserved.
The Radiation Belt Storm Probes (RBSP) mission will explore the Sun‘s
influence on the Earth and near-Earth space by studying the planet‘s
radiation belts at various scales of space and time. This insight into
the physical dynamics of the Earth‘s radiation belts will provide
scientists data to make predictions of changes in this little
understood region of space. Understanding the radiation belt
environment has practical applications in the areas of spacecraft
system design, mission planning, spacecraft operations, and astronaut
safety. The two spacecrafts will measure the particles, magnetic and
electric fields, and waves that fill geospace and provide new
knowledge on the dynamics and extremes of the radiation belts.
Formulation:
Formulation start: 9/06;
Preliminary design review: 10/08.
Implementation:
Project Confirmation: 12/08;
Critical design review: 12/09;
GAO review: 12/10;
Launch readiness date: 5/12.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2009): $685.8;
Latest (Feb. 2011): $685.9;
Change: 0.0%.
Formulation Cost:
Baseline Est. (FY 2009): $88.2;
Latest (Feb. 2011): $88.2;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2009): $533.9;
Latest (Feb. 2011): $534.0;
Change: 0.0%.
Operations Cost:
Baseline Est. (FY 2009): $63.7;
Latest (Feb. 2011): $63.7;
Change: 0.0%.
Launch Schedule:
Baseline Est. (FY 2009): 5/2012;
Latest (Feb. 2011): 5/2012;
Change: 0 months.
[End of table]
Recent Project Challenges:
* Parts Issues;
* Contractor Issues.
Project Summary:
RBSP project officials reported parts failure and contractor issues
that may result in the delayed delivery and integration of two key
science instruments. Project officials expect delays in the delivery
of the Helium-Oxygen-Proton-Electron instrument due to a parts
functionality failure and in the delivery of necessary flight hardware
for the MagEIS instrument that may impact its integration with the
spacecraft. RBSP‘s systems integration review was held in October 2010.
Project Update:
Parts Issues: RBSP project officials expect delays in the delivery and
integration the Helium-Oxygen-Proton-Electron (HOPE) instrument.
Delivery of HOPE may be delayed due to a parts functionality failure
within the high voltage Optocoupler. Currently, the project considers
this parts issue a risk to mission cost and schedule. However, the
project manager reported that there are sufficient schedule reserves and
that they have confidence that issues can be resolved without schedule
growth. Project officials said that other NASA missions had issues
with the same part. The manufacturer is working to develop a revised
Optocoupler to meet multiple mission needs.
NASA provided instructions that prohibited the use of certain
connectors as part of their ongoing monitoring of quality parts and
qualification standards, which caused the project to review the type
of connectors used in the observatory and replace the connectors as
applicable. The project has successfully qualified a connector to
replace the NASA-prohibited connectors. The new connector has been
successfully installed on flight model boards across the project. RBSP
project officials classify the likelihood of an in-flight failure
if the prohibited connectors were used as very small; however,
possible consequences including loss of the spacecraft or an
instrument are significant.
Contractor Issues: Delivery of the Magnetic Electron Ion Spectrometer
(MagEIS) instrument is expected to be delayed due to the time a vendor
is taking in providing needed flight hardware for the instrument. A
project official reported that the vendor was contacted and encouraged
to prioritize its commitment to the RBSP contract. However, officials
reported that the project underwent a schedule replan to accommodate
the late delivery and integration of MagEIS. This replan maintains the
launch readiness date by re-ordering the observatory integration and
test flow and changing selected subsystem and instrument delivery
dates.
Other Issues to be Monitored: Project officials indicated that one of
the primary challenges for RBSP is developing a spacecraft capable of
withstanding the high levels of radiation that it will encounter
during the mission. RBSP includes many design elements, such as
aluminum shielding around all major subsystems, and is undergoing
extensive testing and qualification to ensure sufficient ’radiation
hardening.“ The project manager reported that spacecraft electronic-
related parts radiation testing is nearly complete with no problems
reported.
Only 69 percent of the engineering design drawings, instead of the
planned 87 percent, were released by the December 2009 critical design
review (CDR) for RBSP. In April 2010, the project had released 93
percent of its drawings. Project officials said that RBSP was the
first project at the Johns Hopkins University/Applied Physics
Laboratory to use a new tracking package for reviewing and approving
design drawings and therefore experienced some delays in releasing
drawings at CDR. Project officials reported that there have been only
minimal design changes since the CDR and there are no significant
design changes expected in the future.
Project Office Comments:
The RBSP project office provided technical comments to a draft of this
assessment, which were incorporated as appropriate. Project officials
also commented that the System Integration Review was conducted on 12-
14 October 2010, with the Standing Review Board recommending that the
Project be allowed to proceed into observatory integration and test.
[End of RBSP data]
Soil Moisture Active and Passive (SMAP):
Common Name: SMAP:
[Refer to PDF for image: artist depiction]
Source: Jet Propulsion Laboratory.
NASA‘s Soil Moisture Active and Passive (SMAP) is one of four first-
tier missions recommended by the National Research Council‘s 2007
Earth Science Decadal Survey. SMAP leverages previous Earth Science
missions and is based on the soil moisture and freeze/thaw mission
concept developed by an earlier mission known as Hydros. The SMAP
mission will provide new information on global soil moisture and its
freeze/thaw state enabling new advances in hydrospheric science and
applications. The measures will improve understanding of regional and
global water cycles, improve weather forecasts, flood and drought
forecasts, and predictions of agricultural productivity and climate
changes.
Formulation:
Formulation start: 9/08;
GAO review: 12/10;
Preliminary design review: 3/11.
Implementation:
Project Confirmation: 6/11;
Critical design review: 3/12;
Launch readiness date: 11/14.
Table: Project Performance (then year dollars in millions):
Latest (Feb. 2011):
Preliminary Estimate of Project Life Cycle Cost[A]: $780 to $900.
[A] This estimate is preliminary, as the project is in formulation and
there is still uncertainty in the value as design options are
explored. NASA uses these estimates for planning purposes.
Launch Schedule: 11/2014.
[End of table]
Recent Project Challenges:
* Funding Issues;
* Launch Issues.
Project Summary:
SMAP received $64 million in American Recovery and Reinvestment Act of
2009 funds, as well as funding from the President‘s global climate
initiative, that the project used to address key mission and
implementation risks during formulation and to accelerate the launch
readiness date from May 2015 to November 2014. The project is
currently being designed to multiple launch vehicle specifications and
is tracking the timing of the launch vehicle selection as a top risk.
Project Update:
Funding Issues: SMAP entered formulation in September 2008 and the Jet
Propulsion Lab (JPL) was selected as the lead implementation center in
January 2009. NASA officials stated that SMAP was budgeted $30 million
in funding from the President‘s global climate initiative and $64
million in funding from the American Recovery and Reinvestment Act of
2009, which the project used to accelerate the launch date from May
2015 to November 2014.
Launch Issues: Late launch vehicle selection is one of the top risks
the project is monitoring. SMAP is currently being designed to fit the
specifications for three launch vehicles, including exploring a
partnership for a DOD-provided launch service on the Minotaur IV.
While designing to accommodate multiple launch vehicles is possible, a
project official said that it limits design capabilities and can raise
costs to the program as a result. Project officials stated that no
certified medium capability vehicle is currently available. The Falcon
9, which is available under the current Launch Services contract, has
yet to be certified, and if selected, the mission launch date will be
tied to a successful certification of the launch vehicle. NASA is
preparing a solicitation to acquire launch services and, if commercial
vehicles are not reasonably available, it may request approval by the
Secretary of Defense and submit a certification to Congress for
authorization to partner with DOD to use the Minotaur IV. The current
timeline for launch vehicle selection may result in a decision after
the project‘s preliminary design review (PDR).
Other Issues to be Monitored: Project officials stated that an early
focus on risk management enabled SMAP to mitigate several top mission
and implementation risks related to the aggressive schedule and the
scientific outputs of the mission. For example, the project developed
an end-to-end science measurement simulation to increase the data
volume requirements. The project expects to mitigate several other
development risks by the mission PDR in March 2011. For example, the
project reported it has three heritage technologies-”the radar,
radiometer, and the reflector boom assembly-”all of which it will adapt
for application. None of these technologies, however, is currently
mature. The project is tracking the radiometer as a project risk since
it requires additional Spectral Filtering for Radio Frequency
Interference (RFI) mitigation. The project has identified the spectral
filtering as a critical technology. Due to its extensive heritage, the
project is accepting the potential risk in cost growth and the
technical risks with a verification and validation (V&V) program that
includes a comprehensive set of assembly and system level analyses.
There is a cost risk, however, associated with the V&V program if the
project determines that additional tests and analyses are required.
SMAP leverages other Earth Science projects, namely the Aquarius
project, which is in the implementation phase, and the Hydros project
that was discontinued in 2005 due to lack of available funding. Although
SMAP has no funding partners, the National Oceanic and Atmospheric
Administration, the U.S. Department of Agriculture, and DOD are all
actively engaged with SMAP to develop an applications plan for the
data.
Project Office Comments:
The SMAP project provided technical comments to a draft of this
assessment, which were incorporated as appropriate. The project
officials also commented that the target launch readiness date of
November 2014 is a planning date at this point and can change as
funding, scope and schedule are brought into mutual alignment. NASA
will not formally commit to a launch readiness date until Project
Confirmation, Key Decision Point C, currently scheduled for summer
2011.
[End of SMAP data]
Solar Probe Plus (SPP):
Common Name: SPP:
[Refer to PDF for image: artist depiction]
Source: © 2010 Johns Hopkins University/Applied Physics Laboratory.
Solar Probe Plus (SPP) will explore the Sun's outer atmosphere, or
corona, as it extends into space. The spacecraft will orbit the Sun 24
times and its instruments will observe the generation and flow of
solar wind from very close range. By observing the corona, where solar
energetic particles are energized, there is potential to further
science in terms of shedding light on two central issues of
heliophysics: the origin and evolution of solar wind, and why the
sun‘s outer atmosphere is so much hotter than the visible surface. In
order to achieve its mission, parts of the spacecraft must be able to
withstand temperatures exceeding 2,500 degrees Fahrenheit, as well as
endure blasts of extreme radiation.
Formulation:
Formulation start: 11/09;
GAO review: 12/10;
Preliminary design review: 1/14;
Implementation:
Critical design review: 11/15;
Launch readiness date: 8/18.
Table: Project Performance (then year dollars in millions):
Latest (Feb. 2011):
Preliminary Estimate of Project Life Cycle Cost[A]: not available.
Launch Schedule: 8/2018.
[A] The project has not yet reached the point in the acquisition life
cycle where a preliminary life cycle cost estimate would normally be
developed.
Recent Project Challenges:
* Launch Issues.
Project Summary:
SPP is early in formulation, and therefore is unable to provide
official cost and schedule data at this time. Currently, the probe
will fly within closer proximity to the Sun than any other spacecraft.
Chief risks to the project in terms of cost and schedule include
development of a sunshield capable of protecting the instruments from
the harsh near-Sun environment, development of a cooling system for
the retractable solar array panels, and achieving the total launch
energy to get the spacecraft to its long-range destination.
Project Update:
Launch Issues: SPP project officials reported that one of the mission‘
s key challenges is achieving the total launch energy necessary to
launch the spacecraft toward its long range destination. The mission
will most likely require the use of an upper stage solid rocket
propellant to provide sufficient launch energy to set the spacecraft
on a trajectory to achieve solar exploration. Project officials
reported that they are working to understand the performance of the
standard stage and possible enhancements to upper stage performance
should this be needed. These enhancements could include the possible
use of a higher energy propellant and a composite case for mass
efficiency. The project commissioned a trade study which seeks to
identify the optimal combination of launch vehicle and propellant
upper stage to use for the launch. Project officials anticipate the
study to be completed by the Mission Design Review, currently
scheduled for May 2011.
Other Issues to be Monitored: A key challenge of the SPP mission will
be the development of critical technologies allowing science
instruments to function within the harsh near-Sun environment.
Although still in the concept and technology development phase,
project officials reported that the Thermal Protection System (TPS)-”a
carbon-foam filled sun shield that will measure over 8 feet in
diameter”-would sit atop the spacecraft shielding instruments from the
direct heat and radiation of the Sun. Project officials reported
that they have already completed production of a 30-inch square
prototype TPS shield, but at this time the technology is not fully
mature. A full prototype of this technology is expected to be matured
and built during Phase B.
A second area of mission technology development concerns the
production of two sets of solar arrays”-essentially solar power
generators-”that will retract and extend as the spacecraft moves
toward or away from the Sun. A solar array cooling system will be used
to ensure the solar panels stay at required temperatures. Project
officials reported that the cooling system will need the capacity to
dissipate up to 5,000 watts of thermal energy during the spacecraft‘s
closest approach to the Sun. In order to mitigate mission risk, a back-
up pump for the cooling system is planned to be integrated should the
first pump fail. However, as is the case with the TPS, it will be
impossible to replicate the extreme conditions the probe will be
exposed to during its closest proximity to the Sun.
Although the key technologies will be tested in representative
environments it will be impossible to replicate the extreme conditions
the fully assembled probe will be exposed to during its closest
proximity to the Sun requiring simulators for the TPS and Solar Arrays
in systems test. Thus, the functionality of the entire spacecraft in
the near-Sun environment cannot be verified fully through testing
prior to launch.
An Announcement of Opportunity was issued in December 2009 and project
officials reported that thirteen science proposals were considered by
a panel of NASA and other scientists. In 2010, the project selected
five science investigations, which when awarded will have a combined
value of approximately $165 million for preliminary analysis, design,
development, and testing.
Project Office Comments:
The SPP project office provided technical comments to a draft of this
assessment, which were incorporated as appropriate. Project officials
also commented that SPP is making progress going through formulation.
[End of SPP data]
Stratospheric Observatory for Infrared Astronomy (SOFIA):
Common Name: SOFIA:
[refer to PDF for image: illustration]
Source: SOFIA First Light Image Composite.
SOFIA is a joint project between NASA and the German Space Agency to
install a 2.5 meter telescope in a specially modified Boeing 747SP
aircraft. This airborne observatory is designed to provide routine
access to the visual, infrared, far-infrared, and sub-millimeter parts
of the spectrum. Its mission objectives include studying many
different kinds of astronomical objects and phenomena, including star
birth and death; the formation of new solar systems; planets, comets,
and asteroids in our solar system; and black holes at the center of
galaxies. Interchangeable instruments for the observatory are being
developed to allow a range of scientific measurement to be taken by
SOFIA.
Formulation:
Formulation start: 10/91.
Implementation:
Project Confirmation: 11/95;
Critical design review: 8/00;
GAO review: 12/10;
Initial operational capability: 12/10;
Full operational capability: 12/14.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2007): $2954.5;
Latest (Feb. 2011): $3002.9;
Change: 1.6%.
Formulation Cost:
Baseline Est. (FY 2007): $35.0;
Latest (Feb. 2011): $35.0;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2007): $919.5;
Latest (Feb. 2011): $1128.4;
Change: 22.7%.
Operations Cost:
Baseline Est. (FY 2007): $2000.0;
Latest (Feb. 2011): $1839.5;
Change: -8.0%.
Launch Schedule:
Baseline Est. (FY 2007): 12/2013;
Latest (Feb. 2011): 12/2014;
Change: 12 months.
[End of table]
Recent/Continuing Project Challenges:
* Technology Issues;
* Design Issues;
* Contractor Issues.
Previously Reported Challenges:
* Funding Issues.
Project Summary:
Since our last review, SOFIA has experienced a delay in the delivery
of hardware from vendors and development issues surrounding the Cavity
Door Drive System. While this resulted in a 7-month slip to initiation
of science flights in December 2010, the program completed a
significant progress milestone with the completion of the first light
flight on May 25, 2010. In 2009 and 2010, NASA reported to the
Congress that SOFIA exceeded both its cost and schedule baselines.
Project Update:
As required by law, NASA reported to the Congress in 2009 and 2010
that SOFIA exceeded its 2007 development cost baseline by more than 15
percent and its schedule baseline by more than 6 months. SOFIA‘s
development costs have increased more than 268 percent, over $1.1
billion, since its 1995 estimate. These cost increases are partly due
to challenges with modification of the aircraft to be used for SOFIA and
more recently development of the Cavity Door Drive System (CDDS). This
year, project officials told us SOFIA‘s development costs increased
due to increased flight hanger costs. Some data for the project was not
provided by NASA because, according to project officials, the project
documentation did not transfer in its entirety from Ames Research
Center to Dryden Flight Research Center.
Technology Issues: We could not assess the technology maturity of the
overall project as NASA did not provide information for heritage
technologies related to the aircraft modification. Data provided for
development of the instruments that will fly on SOFIA generally
indicates a high level of technology maturity. Many of these
technologies have already been used on ground-based telescopes.
Project officials told us that of the eight first generation science
instruments, one instrument was flown on the first light flight in May
2010, one instrument has been installed and tested on the ground, one
instrument is awaiting installation, and four instruments will be
installed by 2013.
Design Issues: We were unable to determine design stability of the
instruments since the drawings were still preliminary at the critical
design review. Last year, project officials reported that design work
on SOFIA was 97 percent complete and that all designs would be
complete by 2011. However, due to problems with the CDDS vendor and
longer-than-anticipated door testing, initial science flights have
been delayed one year. Because modifications to several subsystems
will be ongoing during the early science missions, project officials
told us designs will not be finalized until 2014 when the project is
scheduled to begin operations. A date for the preliminary design
review was not provided by NASA.
Contractor Issues: Since our last review, the SOFIA project has
experienced at least a 6-month slip in the scheduled commencement of
initial science flights due to late delivery of hardware and software in
the CDDS and rework of vendor supplied hardware. The project found
problems with software quality assurance, which indicated later on
that there were problems with hardware quality assurance and required
a rebuild of the CDDS components. NASA consequently reduced the
contractor‘s management role for both development and operations of
SOFIA and utilized government personnel to perform these functions in
house and to complete the CDDS. The project successfully completed the
first open door flight test on December 18, 2009, and experienced no
anomalies. To date, the project has conducted three open door
landings, two of which were unplanned and caused by nuisance faults.
The project manager stated that in the open door testing process there
was a high probability of a halt in the door system and the project was
prepared for this occurrence. He stated that there is no backup door
opening system, but that the project did have a default reset for door
issues in flight. The project continues to troubleshoot development of
the CDDS and is utilizing an independent consultant to investigate the
system and recommend future upgrades. In August 2010, the project
completed its second segment of flight tests with its telescope door
open to prepare the observatory for early science missions.
Project Office Comments:
The SOFIA project office provided technical comments to a draft of
this assessment, which were incorporated as appropriate. Project
officials also commented that the SOFIA project has made progress
toward the initiation of science observations.
[End of SOFIA data]
Tracking and Data Relay Satellite (TDRS) Replenishment:
Common Name: TDRS:
[Refer to PDF for image: artist depiction]
Source: © Boeing.
The Tracking and Data Relay Satellite (TDRS) System consists of in-
orbit communication satellites stationed at geosynchronous altitude
coupled with two ground stations located in New Mexico and Guam. The
satellite network and ground stations provide mission services for
near-Earth user satellites and orbiting vehicles. TDRS K and L are the
11th and 12th satellites, respectively, to be built for the TDRS
system and will contribute to the existing network by providing high
bandwidth digital voice, video, and mission payload data, as well as
health and safety data relay services to Earth-orbiting spacecraft, such
as the International Space Station.
Formulation:
Formulation start: 2/07;
Preliminary design review: 3/09.
Implementation:
Project Confirmation: 7/09;
Critical design review: 2/10;
GAO review: 12/10;
Launch readiness date TDRS K: 12/12;
Launch readiness date TDRS L: 12/13.
Table: Project Performance (then year dollars in millions):
Total Project Cost:
Baseline Est. (FY 2010): $451.3;
Latest (Feb. 2011): $434.1
Change: -3.8%.
Formulation Cost:
Baseline Est. (FY 2010): $241.9;
Latest (Feb. 2011): $241.9;
Change: 0.0%.
Development Cost:
Baseline Est. (FY 2010): $209.4;
Latest (Feb. 2011): $192.2;
Change: -8.2%.
Operations Cost:
Baseline Est. (FY 2010): $0.0;
Latest (Feb. 2011): $0.0;
Change: 0.0%.
Launch Schedule K:
Baseline Est. (FY 2010): 12/2012;
Latest (Feb. 2011): 12/2012;
Change: 0 months.
Launch Schedule L:
Baseline Est. (FY 2010): 12/2013;
Latest (Feb. 2011): 12/2013;
Change: 0 months.
[End of table]
Recent Project Challenges:
* Parts Issues.
Project Summary:
The TDRS project identified an issue with contamination of the
lubricants in the reaction wheel assemblies. The cost impact of this
issue is borne by the prime contractor. In June 2010, the project
awarded a contract to enhance existing ground-system architecture to
ensure the TDRS system continues providing space-to-ground
telecommunications. However, even with the successful launch of TDRS K
and L, NASA is only able to guarantee continuity of service of the
TDRS system through fiscal year 2016.
Project Update:
Parts Issues: In 2010, TDRS project officials discovered that the
lubricant in the reaction wheel assemblies was contaminated by
silicone. The project initially reported that it may take up to 18
months for the original supplier to provide replacements and that no
other appropriate reaction wheels are in production by alternative
vendors. However, project officials expected that replacement reaction
wheels would be made available in November and December 2010, which
equates to an approximate 2-month delay to scheduled wheel delivery
dates.
Other Issues to be Monitored: In June 2010, a cost-plus-award fee
contract was awarded to modernize the ground based communication
systems needed for TDRS K and L. In order to maximize the capabilities
of TDRS K, necessary enhancements to the ground system must be
prioritized within the 2 years prior to launch in 2012. TDRS K and L
are being designed with high-bandwidth communication abilities including
the transmission of images, video, voice, and other digital data from
Earth-orbiting spacecraft to the ground. The ground-based beamforming
architecture at the White Sands Complex in New Mexico is currently being
modified to provide TDRS K and L compatible beamformers for the ground
station. Project officials reported that the switch to ground-based
beamforming was required to provide compatibility with network demand
services developed in the late 1990‘s. Project officials recognize
challenges with updating ground segment equipment describing some
current instruments as vintage early 1990‘s and facing obsolescence
issues.
The TDRS System is considered by NASA to be a basic agency capability
and a national resource. The Space Shuttle and many near-Earth
spacecraft are totally dependent upon the satellite system for
communication, and therefore, NASA considers the TDRS Replenishment
project critical in terms of achieving launch schedule. However, even
with the successful launch of TDRS K and L, continuity of service for
TDRS System can only be ensured for NASA and other government agency
users through approximately fiscal year 2016 at current support
levels. The primary reason for this is due to an aging fleet of
satellites. The first TDRS satellite, now decommissioned, has been in
Earth orbit since 1983. According to a project official, the current
fixed price development contract for TDRS K and L includes an option
to produce two additional TDRS satellites”-designated M and N”-and the
addition of these two satellites could extend TDRS system service
continuity. However, in order to exercise the options for TDRS M and
N, NASA would need a financial commitment of $1.2 billion from
partnership organizations. Project officials reported that a decision
on exercising the option for TDRS M needs to be made no later than
November 30, 2011, and no later than November 30, 2012, for TDRS N.
Project Office Comments:
The TDRS project office provided technical comments to a draft of this
assessment, which were incorporated as appropriate. Project officials
commented that they agreed with the assessment as written.
[End of TDRS data]
Agency Comments and Our Evaluation:
We provided a draft of this report to NASA for review and comment. In
its written response, NASA agreed with our findings and stated that it
will continue to identify and address the challenges that may lead to
cost and schedule growth in its projects. NASA agreed that GAO‘s cost
and schedule growth figures reflect what the agency has experienced
since baselines were established in response to the 2005 statutory
reporting requirement. NASA also stated that the average cost growth
remains below the 15 percent threshold that requires Congressional
notification. While this is correct, it should be noted that the
notification requirements are for individual projects, not the
portfolio as a whole. In addition, NASA acknowledges that the current
estimates for the James Webb Space Telescope do not represent the cost
and schedule required to complete the project, and that the agency is
undertaking a comprehensive replanning activity to establish the best
budget phasing and schedule to minimize risk and life-cycle cost
within the overall constraints of its budget. We encourage NASA to
provide a revised budget and schedule for JWST that is based on a
sound, knowledge-based business case to allow the project to succeed.
NASA noted that its projects are high-risk, one-of-a-kind development
efforts that do not lend themselves to all the practices of a
’business case“ approach that we outlined since essential attributes
of NASA‘s project development differ from those of a production
entity. We agree and do not assess NASA‘s projects for production
maturity. We do, however, assess NASA projects at critical points in
the product development process to ensure that these projects are
proceeding with system development with a sound business case. At
these key junctures we have found that NASA could benefit from a more
disciplined approach to its acquisitions whereby decisions are based
upon high levels of knowledge. As we reported, inherent risks are
being heightened due to projects moving forward with immature
technologies, unstable designs, and other challenges, leading to cost
and schedule increases that make it hard for the agency to manage its
portfolio and make informed investment decisions. GAO looks forward to
working with NASA as it develops metrics to better measure design
stability and continues to refine the information it uses to
understand a project‘s status and make informed decisions.
NASA stated that the drawing release metric we use to assess design
stability was developed prior to the use of computerized drawings and
does not take into account improvements due to the use of this
technology. We acknowledge this point, but our analysis of NASA
projects shows that those projects that have met or come close to
meeting the best practices drawing release metric have fared better
with regard to cost and schedule than those projects that did not come
close to meeting the metric. Furthermore, in no way does GAO portend
that the drawing release metric is the only way to assess design
stability. Until NASA has taken steps to identify a consistent and
proven metric by which to measure projects with a portfolio
perspective, however, we will continue to use this metric to assess
stability. NASA has indicated that it will develop such metrics and
provide them to GAO in March 2011. We are encouraged by this progress
and look forward to receiving the information.
NASA expressed concern that technical corrections it provided to our
2-page summaries were not fully accepted. We incorporated the technical
comments where supporting documentation that meets our standards of
evidence was provided. We did not incorporate the comments where this
information was not provided or where the change was less a technical
correction and more a difference of opinion between GAO and NASA based
on facts or where space limitations required a briefer description of an
issue than requested by NASA. As this work will be continuing in future
years, we will continue to capture the progress made by all the
projects in our review. Finally, we take great strides to provide the
latest information possible in our report. We will continue to work
with NASA to ensure that updated information is provided to GAO in a
timely manner so that it can be included in our analysis.
NASA‘s written comments are reprinted in appendix I. NASA also
provided technical comments, which we addressed throughout the report
as appropriate and where sufficient evidence was provided to support
significant changes.
We will send copies of the report to NASA‘s Administrator and interested
congressional committees. We will also make copies available to others
upon request. In addition, the report will be available at no charge
on GAO‘s Web site at [hyperlink, http://www.gao.gov]. Should you or
your staff have any questions on matters discussed in this report,
please contact me at (202) 512-4841 or chaplainc@gao.gov. Contact
points for our Offices of Congressional Relations and Public Affairs
may be found on the last page of this report. GAO staff who made major
contributions to this report are listed in appendix IV.
Signed by:
Cristina Chaplain:
Director:
Acquisition and Sourcing Management:
[End of section]
List of Congressional Committees:
The Honorable Barbara A. Mikulski:
Chairwoman:
The Honorable Kay Bailey Hutchison:
Ranking Member:
Subcommittee on Commerce, Justice, Science, and Related Agencies:
Committee on Appropriations:
United States Senate:
The Honorable Bill Nelson:
Chairman:
The Honorable John Boozman:
Ranking Member:
Subcommittee on Science and Space:
Committee on Commerce, Science, and Transportation:
United States Senate:
The Honorable Frank R. Wolf:
Chairman:
The Honorable Chaka Fattah:
Ranking Member:
Subcommittee on Commerce, Justice, Science, and Related Agencies:
Committee on Appropriations:
House of Representatives:
The Honorable Stephen Palazzo:
Chairman:
The Honorable Gabrielle Giffords:
Ranking Member:
Subcommittee on Space and Aeronautics:
Committee on Science, Space, and Technology:
House of Representatives:
[End of section]
Appendix I: Comments from the National Aeronautics and Space
Administration:
National Aeronautics and Space Administration:
Office of the Administrator:
Washington, DC 20546-0001:
February 23, 2011:
Ms. Christina Chaplain:
Director:
Acquisition and Sourcing Management:
United States Government Accountability Office:
Washington, DC 20548:
Dear Ms. Chaplain:
The National Aeronautics and Space Administration (NASA) appreciates
the opportunity to comment on the Government Accountability Office
(GAO) draft report entitled "Assessments of Selected Large-Scale
Projects" (GAO-11-239SP). NASA values the continued open and
constructive communications between NASA and the GAO team on this
effort. NASA remains dedicated to continuous improvement of its
acquisition management processes and performance and will continue to
work with the GAO to identify and address the challenges that may lead
to cost and schedule growth of our projects.
We are pleased that GAO has again recognized NASA's ongoing efforts to
mitigate acquisition management risk and lay a stronger foundation for
reducing project cost and schedule growth. As was highlighted, NASA
instituted a Joint Cost and Schedule Confidence Level (JCL) policy in
2009 to increase the likelihood of project success at the specified
funding level. As expected in 2010, execution of the JCL process prior
to confirmation of several projects, including the Lunar Atmosphere
and Dust Environment Explorer, the Mars Atmosphere and Volatile
Evolution Mission, and the Orbiting Carbon Observatory 2, increased
insight by project managers, the Standing Review Board, and NASA
management surfacing uncertainties and contingencies with the
integrated cost and schedule plan. NASA will continue to assess the
impact of utilizing JCLs on project cost and schedule growth as these
projects complete their Systems Integration Reviews in the next two
years. Furthermore, with the completion and launch in 2011 of three
missions baselined under the earlier cost confidence level policy,
NASA will have a better measure of the impact of our acquisition
management improvement efforts over the last five years.
In its draft report, GAO states that NASA's project development costs
for the 16 projects in implementation in this review have increased by
an average of 14.6 percent from their baseline cost estimates and
experienced an average delay of eight months, an improvement of three
months since the previous report. NASA agrees with the cost and
schedule growth figures that are quoted and notes that the average
cost growth remains below the 15 percent threshold which requires
special notification to Congress. Furthermore, fewer projects have
exceeded this threshold since NASA's new cost estimating policies were
put into place. These figures are reflective of what has been
experienced since baselines were established in response to the 2005
statutory reporting requirement.
GAO notes that the calculation of NASA's average development cost and
schedule growth does not include anticipated growth on the James Webb
Space Telescope (JWST) project. The cost and schedule quoted in the
draft GAO report are the results of a rough estimate by the
Independent Comprehensive Review Panel (ICRP) which recently assessed
JWST and do not represent NASA's estimate of the cost and schedule
required to complete the project. In response to ICRP's findings and
recommendations, NASA is currently undertaking a comprehensive
replanning activity to establish the best budget phasing and schedule
to minimize the risk and life-cycle cost of JWST within the overall
constraints of NASA's budget. The revised budget and schedule will be
completed after the release of the President's 2012 Budget. Decisions
resulting from this replanning activity, with any required Agency
offsets, will be reflected in the President's 2013 Budget.
While NASA practices many elements of GAO's stated "business case"
approach, some essential aspects of NASA's project development differ
from those of a production entity, which is the basis for the GAO
approach. NASA's projects are generally high-risk, one-of-a-kind
developments and, therefore, do not have a production phase. The draft
GAO report acknowledges the unique nature of NASA projects but applies
a best practices approach that requires an incremental development
process. NASA's work pushes the boundary of our achievements and often
requires leaps, not steps, to accomplish the mission. NASA aims to
continue to innovate in an affordable and sustainable way and will
continue to work with GAO to determine which elements of the approach
are valuable for informing improvements and which may need to be
modified to account best for the complexity that surrounds our
challenging missions.
An area where NASA and GAO can work together to adapt the assessment
approach is in the determination of design stability. Although the
best practice recommends 90 percent drawing release by Critical Design
Review (CDR), the drawing release metric is a standard developed prior
to the use of computerized drawings and, hence, does not take into
account improvements due to the use of this technology. NASA continues
to develop metrics to measure design stability as well as other
knowledge required to understand a project's progress and maturity.
The draft GAO report notes challenges with launch vehicles,
specifically, NASA's transition plans for future medium-class launch
vehicles and cites a previous recommendation that NASA perform
detailed cost estimates for certification of new vehicles and
adequately budget for the associated risks. NASA is in the process of
estimating costs to certify the Falcon 9 and will budget accordingly.
Taurus II is not currently included in the NASA Launch Services
contract; however, NASA will follow the same process in the event that
it is added. In addition, NASA is working to resolve the inherent
conflict between the desire to minimize technical risk by identifying
the launch vehicle as early as possible (before Preliminary Design
Review) and the desire to minimize programmatic risk by not committing
to purchase a launch vehicle prior to mission confirmation (at Key
Decision Point-C, Post-Preliminary Design Review).
NASA is concerned that technical corrections to the Project Two-Page
Summaries that were provided in late 2010 were not fully accepted by
the GAO in the draft report. Many of these comments have been
resubmitted for GAO's consideration. NASA will work with the GAO team
to better understand why specific corrections were not accepted and to
better explain our issues if necessary. In addition, NASA understands
that the GAO's work was completed in the fall of 2010 and is concerned
that the assessment, therefore, does not recognize the significant
progress the Agency has made since then.
NASA will continue to follow through with our new policies and
management attention on cost and schedule growth in the coming year.
We are committed to continuous improvement in order to explore and
utilize space in an affordable way for the benefit of the Nation. To
this end, we look forward to continuing to work with the GAO to
measure and improve our performance.
Thank you for the opportunity to comment on this draft report. If you
have any questions or require additional information, please contact
Katie Gallagher at (202) 358-2185.
Sincerely,
Signed by:
Lori B. Garver:
Deputy Administrator:
[End of section]
Appendix II: Objectives, Scope, and Methodology:
Our objectives were to report on the status and challenges faced by
NASA systems with life-cycle costs of $250 million or more and to
discuss broader trends faced by the agency in its management of system
acquisitions. In conducting our work, we evaluated performance and
identified challenges for each of 21 major projects. We summarized our
assessments of each individual project in two components--a project
profile and a detailed discussion of project challenges. We did not
validate the cost and schedule data provided by NASA. However, we took
appropriate steps to address data reliability. Specifically, we
confirmed the accuracy of NASA-generated data with multiple sources
within NASA and, in some cases, with external sources. Additionally,
we corroborated data provided to us with published documentation. We
determined that the data provided by NASA project offices were
sufficiently reliable for our engagement purposes.
We developed a standardized data collection instrument (DCI) that was
completed by each project office. Through the DCI, we gathered basic
information about projects as well as current and projected
development activities for those projects. The cost and schedule data
estimates that NASA provided were the most recent updates as of
November 2010; performance data that NASA provided were also the most
recent updates as of September 2010. At the time we collected the
data, 8 of the 21 projects were in the formulation phase. Three of
these 8 projects--MAVEN, LADEE, and OCO-2--were confirmed and entered
the implementation phase late in 2010. To further understand
performance issues, we talked with officials from most project offices
and NASA's Office of the Chief Financial Officer (OCFO) Strategic
Investments Division (SID). We also collected cost and schedule data
for projects in operations that we had reviewed in prior reports for
historical purposes. These projects were DAWN, GLAST, Herschel,
Kepler, LRO, OCO, SDO, and WISE.
The information collected from each project office, Mission
Directorate, and OCFO/SID were summarized in a 2-page report format
providing a project overview; key cost, contract, and schedule data;
and a discussion of the challenges associated with the deviation from
relevant indicators from best practice standards. The aggregate
measures and averages calculated were analyzed for meaningful
relationships, e.g. relationship between cost growth and schedule
slippage and knowledge maturity attained both at critical milestones
and through the various stages of the project life cycle. Cost growth
averages used in this report are weighted averages and should not be
used as a point of comparison to previous reports where weighted
averages were not used. We identified cost and/or schedule growth as
significant where, in either case, a project's cost and/or its
schedule statutory baseline exceeded the thresholds that trigger
reporting to the Congress.
To supplement our analysis, we relied on GAO's work over the past
years examining acquisition issues across multiple agencies. These
reports cover such issues as contracting, program management,
acquisition policy, and estimating cost. GAO also has an extensive
body of work related to challenges NASA has faced with specific system
acquisitions, financial management, and cost estimating. This work
provided the context and basis for large parts of the general
observations we made about the projects we reviewed. Additionally, the
discussions with the individual NASA projects helped us identify
further challenges faced by the projects. Together, the past work and
additional discussions contributed to our development of a short list
of challenges discussed for each project. The challenges we identified
and discussed do not represent an exhaustive or exclusive list. They
are subject to change and evolution as GAO continues this annual
assessment in future years. The challenges, indicated as "issues," are
based on our definitions, not that of NASA.
Our work was performed primarily at NASA headquarters in Washington,
D.C. In addition, we visited NASA's Marshall Space Flight Center in
Huntsville, Alabama, and Goddard Space Flight Center in Greenbelt,
Maryland, to discuss individual projects. We also met with
representatives from NASA's Jet Propulsion Lab in Pasadena, California
and a contractor involved with several projects, Orbital Science
Corporation. In addition, we interviewed officials at Johnson Space
Center in Houston, Texas, Ames Research Center at Moffitt Field in
California, and Dryden Flight Research Center at Edwards Air Force
Base in California.
Data Limitations:
NASA only provided specific cost and schedule estimates for 16 of the
21 projects in our review. NASA provided internal preliminary
estimated total (life-cycle) cost ranges and associated schedules for
three of the projects that had not yet entered implementation, from
key decision point B (KDP-B), solely for informational purposes.
[Footnote 47] We did not receive cost estimates or ranges for two
projects--Ice, Cloud, and Land Elevation Satellite-2 and Solar Probe
Plus--since these projects had not yet reached their KDP-B, the point
in the acquisition life cycle where a preliminary life cycle cost
estimate would normally be developed. We did receive preliminary
scheduled launch dates for these two projects. NASA formally
establishes cost and schedule baselines, committing itself to cost and
schedule targets for a project with a specific and aligned set of
planned mission objectives, at key decision point C (KDP-C), which
follows a non-advocate review (NAR) and preliminary design review
(PDR). KDP-C reflects the life-cycle point where NASA approves a
project to leave the formulation phase and enter into the
implementation phase. NASA explained that preliminary estimates are
generated for internal planning and fiscal year budgeting purposes at
KDP-B, which occurs mid-stream in the formulation phase, and hence,
are not considered a formal commitment by the agency on cost and
schedule for the mission deliverables. NASA officials contend that
because of changes that occur to a project's scope and technologies
between KDP-B and KDP-C, estimates of project cost and schedule can
change significantly heading toward KDP-C.
We requested earned value management data for the 21 projects, and
received data on 11 of them. However, this information was received
late in our review and as a result we were unable to conduct a
detailed analysis on the earned value data.
We also requested independent cost estimates and Joint Cost and
Schedule Confidence Levels (JCL) for the projects that completed them.
We received independent cost estimates for 12 of the projects in our
review and for 6 projects that have launched since our last review. In
most cases we received independent cost estimates conducted at the
center level by the projects, along with estimates by the Aerospace
Corporation and/or by NASA's Independent Program Assessment Office. We
received JCL analyses from three of the five projects that have
completed their JCLs. However, this information was incomplete and
received late in our review and as a result we were unable to conduct
a thorough analysis of the data.
Project Profile Information on Each Individual 2-Page Assessment:
This section of the 2-page assessment outlines the essentials of the
project, its cost and schedule performance, and its summary. Project
essentials reflect pertinent information about each project,
including, where applicable, the major contractors and partners
involved in the project. These organizations have primary
responsibility over a major segment of the project or, in some cases,
the entire project.
Project performance is depicted according to cost and schedule changes
in the various stages of the project life cycle. To assess the cost
and schedule changes of each project we obtained data directly from
NASA OCFO/SID and from NASA's Integrated Budget and Performance
documents. For systems in implementation, we compared the latest
available information with the statutory cost and schedule baseline
estimates for each project.
All cost information is presented in nominal "then year" dollars for
consistency with budget data.[Footnote 48] Baseline costs are adjusted
to reflect the cost accounting structure in NASA's fiscal year 2009
budget estimates. For the fiscal year 2009 budget request, NASA
changed its accounting practices from full-cost accounting to
reporting only direct costs at the project level. The schedule
assessment is based on acquisition cycle time, which is defined as the
number of months between the project start, or formulation start, and
projected or actual launch date.[Footnote 49] Formulation start
generally refers to the initiation of a project; NASA refers to
project start as key decision point A, or the beginning of the
formulation phase. The preliminary design review typically occurs
during the end of the formulation phase, followed by a confirmation
review process, referred to as key decision point C, which allows the
project to move into the implementation phase. The critical design
review is held during the final design period of implementation and
demonstrates that the maturity of the design is appropriate to support
proceeding with full scale fabrication, assembly, integration, and
test. Launch readiness is determined through a launch readiness review
that verifies that the launch system and spacecraft/payloads are ready
for launch. The implementation phase includes the operations of the
mission and concludes with project disposal.
We assessed the extent to which NASA projects exceeded their statutory
cost and schedule baselines. To do this, we compared the project
statutory baseline cost and schedule estimates with the current cost
and schedule data reported by the project office in November 2010.
Project Challenges Discussion on Each Individual 2-Page Assessment:
To assess the project challenges for each project, we submitted a data
collection instrument to each project office. In the data collection
instrument, we requested information on the maturity of critical and
heritage technologies, number of releasable design drawings at project
milestones, and project contractors and partnerships. We also held
interviews with representatives from each of the projects to discuss
the information on the data collection instrument. These discussions
led to identification of further challenges faced by NASA projects.
The eight challenges we identified were largely apparent in the
projects that had entered the implementation phase, however, there
were instances where these challenges were identified in projects in
the formulation phase. We then reviewed pertinent project
documentation, such as the project plan, schedule, risk assessments,
and major project reviews to corroborate any testimonial evidence we
received in the interviews.
To assess issues with technology, we asked project officials to
provide the technology readiness levels (TRL) of each of the project's
critical technologies at various stages of project development.
Originally developed by NASA, TRLs are measured on a scale of one to
nine, beginning with paper studies of a technology's feasibility and
culminating with a technology fully integrated into a completed
product. (See appendix IV for the definitions of technology readiness
levels.) In most cases, we did not validate the project offices'
selection of critical technologies or the determination of the
demonstrated level of maturity. However, we sought to clarify the
technology readiness levels in those cases where the information
provided raised concerns, such as where a critical technology was
reported as immature late in the project development cycle.
Additionally, we asked project officials to explain the environments
in which technologies were tested.
Our best practices work has shown that a technology readiness level of
6--demonstrating a technology as a fully integrated prototype in a
relevant environment--is the level of maturity needed to minimize
risks for space systems entering product development. In our
assessment, the technologies that have reached technology readiness
level 6 are referred to as fully mature because of the difficulty of
achieving technology readiness level 7, which is demonstrating
maturity in an operational environment--space. Projects with critical
technologies that did not achieve maturity by the preliminary design
review were assessed as having a technology issues project challenge.
We did not assess technology maturity for those projects which had not
yet reached the preliminary design review at the time of this
assessment.[Footnote 50]
We also asked project officials to assess the TRL of each of the
project's heritage technologies at various stages of project
development. We also interviewed project officials about the use of
heritage technologies in their projects. We asked them what heritage
technologies were being used, what effort was needed to modify the
form, fit, and function of the technology for use in the new system,
whether the project encountered any problems in modifying the
technology, and whether the project considered the heritage technology
as a risk to the project. Heritage technologies were not considered
critical technologies by several of the projects we reviewed. Based on
our interviews, review of data from the data collection instruments,
and previous GAO work on space systems, we determined whether these
technology issues were a challenge for a particular project.
To assess issues with design, we asked project officials to provide
the percentage of engineering drawings completed or projected for
completion by the preliminary and critical design reviews and as of
our current assessment.[Footnote 51] In most cases, we did not verify
or validate the percentage of engineering drawings provided by the
project office. However, we collected the project offices' rationale
for cases where it appeared that only a small number of drawings were
completed by the time of the design reviews or where the project
office reported significant growth in the number of drawings released
after CDR. In accordance with GAO's best practices, projects were
assessed as having achieved design stability if they had at least 90
percent of projected drawings releasable by the critical design
review. Projects that had not met this metric were determined to have
a design stability project challenge. Though some projects used other
methods to assess design stability, such as computer and engineering
models and analyses, we did not assess the effectiveness of these
other methods. We did not assess design stability for those projects
that had not yet reached the critical design review at the time of
this assessment.
To assess issues with funding, we interviewed officials from NASA's
OCFO/SID and NASA project officials, and also relied upon past
interviews with project contractors about the stability of funding
throughout the project lifecycle. In addition, NASA received an
appropriation from the American Recovery and Reinvestment Act of 2009
(ARRA). NASA provided a record of projects involved in our review that
received ARRA funds and reported the amount of ARRA funds a project
received in the cost tab of the data collection instrument. We also
asked project and Mission Directorate officials to discuss how these
funds were used. Funding issues were considered a challenge if
officials indicated that project funding had been interrupted or
delayed resulting in an impact to the cost, schedule, or performance
of the project, if the project received ARRA funding, or if project
officials indicated that the project budgets do not have sufficient
funding in certain years based on the work expected to be
accomplished. We corroborated the funding changes and reasons with
budget documents when available.
To assess issues with launch, we interviewed NASA Launch Services and
project officials. We also interviewed contractor representatives from
Orbital Sciences Corporation to discuss the launch failure of the OCO-
1 mission in 2009 and the return to flight process for the Taurus XL
for the Glory and OCO-2 missions. Launch issues were considered a
challenge if, after establishing a firm launch date, a project had
difficulty rescheduling its launch date because it was not ready; if
the project could be affected by another project slipping its launch;
or if there were launch vehicle fleet issues. In addition, we assessed
the status of launch vehicle selection for projects in formulation and
considered it a challenge if the proposed timing for the launch
vehicle selection date falls after Preliminary Design Review due the
availability of certified medium class launch vehicles.
To assess issues with contractor management, we interviewed project
officials about their interaction and experience with contractors. We
also interviewed contractor representatives from Orbital Sciences
Corporation. We were informed about contractor performance problems
pertaining to their workforce, the supplier base, and technical and
corporate experience. We assessed a project as having this challenge
if these contractor issues caused the project to experience a cost
overrun, schedule delay, or decrease in mission capability. For
projects that did not have a major contractor, we considered this
challenge inapplicable to the project.
To assess issues with development partners, we interviewed NASA
project officials about their interaction with international or
domestic partners during project development. Development partner
issues was considered a challenge for the project if project officials
indicated that domestic or foreign partners were experiencing problems
with project development that impacted the cost, schedule, or
performance of the project for NASA. These challenges were specific to
the partner organization or caused by a contractor to that partner
organization. For projects that did not have an international or
domestic development partner, we considered this challenge not
applicable to the project.
To assess issues with parts quality, we submitted a data collection
instrument in conjunction with other on-going GAO work to all of the
projects in the implementation phase that were schedule to be
operating in a space environment. In addition, we asked project
officials to identify project components that encountered parts
quality or availability problems during development. Additionally, we
asked project officials to explain the environments in which the parts
quality issues were discovered and any implication on the project's
cost and schedule. We considered parts issues a challenge if there
were actual or potential cost and/or schedule impacts to the project
as a result of parts quality or availability, or if the project had to
take special steps in order to address parts issues.
The individual project offices were given an opportunity to comment on
and provide technical clarifications to the 2-page assessments prior
to their inclusion in the final product. We incorporated these
comments as appropriate and where sufficient supporting documentation
was provided.
We conducted this performance audit from March 2010 to February 2011
in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe
that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives.
[End of section]
Appendix IV: Technology Readiness Levels:
Technology readiness level: 1. Basic principles observed and reported;
Description: Lowest level of technology readiness. Scientific research
begins to be translated into applied research and development.
Examples might include paper studies of a technology's basic
properties;
Hardware: None (paper studies and analysis);
Demonstration environment: None.
Technology readiness level: 2. Technology concept and/or application
formulated;
Description: Invention begins. Once basic principles are observed,
practical applications can be invented. The application is speculative
and there is no proof or detailed analysis to support the assumption.
Examples are still limited to paper studies;
Hardware: None (paper studies and analysis);
Demonstration environment: None.
Technology readiness level: 3. Analytical and experimental critical
function and/or characteristic proof of concept;
Description: Active research and development is initiated. This
includes analytical studies and laboratory studies to physically
validate analytical predictions of separate elements of the
technology. Examples include components that are not yet integrated or
representative;
Hardware: Analytical studies and demonstration of nonscale individual
components (pieces of subsystem);
Demonstration environment: Lab.
Technology readiness level: 4. Component and/or breadboard;
Validation in laboratory environment;
Description: Basic technological components are integrated to
establish that the pieces will work together. This is relatively "low
fidelity" compared to the eventual system. Examples include
integration of "ad hoc" hardware in a laboratory;
Hardware: Low fidelity breadboard. Integration of nonscale components
to show pieces will work together. Not fully functional or form or fit
but representative of technically feasible approach suitable for
flight articles;
Demonstration environment: Lab.
Technology readiness level: 5. Component and/or breadboard validation
in relevant environment;
Description: Fidelity of breadboard technology increases
significantly. The basic technological components are integrated with
reasonably realistic supporting elements so that the technology can be
tested in a simulated environment. Examples include "high fidelity"
laboratory integration of components;
Hardware: High fidelity breadboard. Functionally equivalent but not
necessarily form and/or fit (size weight, materials, etc). Should be
approaching appropriate scale. May include integration of several
components with reasonably realistic support elements/subsystems to
demonstrate functionality;
Demonstration environment: Lab demonstrating functionality but not
form and fit. May include flight demonstrating breadboard in surrogate
aircraft. Technology ready for detailed design studies.
Technology readiness level: 6. System/subsystem model or prototype
demonstration in a relevant environment;
Description: Representative model or prototype system, which is well
beyond the breadboard tested for TRL 5, is tested in a relevant
environment. Represents a major step up in a technology's demonstrated
readiness. Examples include testing a prototype in a high fidelity
laboratory environment or in simulated realistic environment;
Hardware: Prototype. Should be very close to form, fit and function.
Probably includes the integration of many new components and realistic
supporting elements/subsystems if needed to demonstrate full
functionality of the subsystem;
Demonstration environment: High-fidelity lab demonstration or
limited/restricted flight demonstration for a relevant environment.
Integration of technology is well defined.
Technology readiness level: 7. System prototype demonstration in an
realistic environment;
Description: Prototype near or at planned operational system.
Represents a major step up from TRL 6, requiring the demonstration of
an actual system prototype in a realistic environment, such as in an
aircraft, vehicle or space. Examples include testing the prototype in
a test bed aircraft;
Hardware: Prototype. Should be form, fit and function integrated with
other key supporting elements/subsystems to demonstrate full
functionality of subsystem;
Demonstration environment: Flight demonstration in representative
realistic environment such as flying test bed or demonstrator aircraft;
Technology is well substantiated with test data.
Technology readiness level: 8. Actual system completed and "flight
qualified" through test and demonstration;
Description: Technology has been proven to work in its final form and
under expected conditions. In almost all cases, this TRL represents
the end of true system development. Examples include developmental
test and evaluation of the system in its intended weapon system to
determine if it meets design specifications;
Hardware: Flight qualified hardware;
Demonstration environment: Developmental Test and Evaluation (DT&E) in
the actual system application.
Technology readiness level: 9. Actual system "flight proven" through
successful mission operations;
Description: Actual application of the technology in its final form
and under mission conditions, such as those encountered in operational
test and evaluation. In almost all cases, this is the end of the last
"bug fixing" aspects of true system development. Examples include
using the system under operational mission conditions;
Hardware: Actual system in final form;
Demonstration environment: Operational Test and Evaluation (OT&E) in
operational mission conditions.
Source: GAO and its analysis of NASA data.
[End of table]
Appendix IV: GAO Contact and Staff Acknowledgments:
GAO Contact:
Cristina Chaplain (202) 512-4841 or chaplainc@gao.gov:
Acknowledgments:
In addition to the contact named above, Shelby S. Oakley, Assistant
Director; Jessica M. Berkholtz; Richard A. Cederholm; Justin D.
Dunleavy: Laura Greifner; Kristine R. Hassinger; Caryn E. Kuebler;
Jesse Lamarre-Vincent; Kenneth E. Patton; and Roxanna T. Sun made key
contributions to this report.
[End of section]
Footnotes:
[1] GAO, NASA: Assessments of Selected Large-Scale Projects,
[hyperlink, http://www.gao.gov/products/GAO-09-306SP] (Washington,
D.C.: Mar. 2, 2009) and GAO, NASA: Assessments of Selected Large-Scale
Projects, [hyperlink, http://www.gao.gov/products/GAO-10-227SP]
(Washington, D.C.: Feb. 1, 2010).
[2] National Aeronautics and Space Administration Authorization Act of
2005, Pub. L. No. 109-155, §103; 42 U.S.C. § 16613(b).
[3] 42 U.S.C. § 16613(d).
[4] See Explanatory Statement accompanying the Omnibus Appropriations
Act, 2009, Pub. L. No. 111-8, div. B, tit. III.
[5] Each assessment is presented in a two-page summary that analyzes
the project's cost and schedule status and project challenges we
identified with the objective to identify risks that, if mitigated,
could put NASA in a better position to succeed.
[6] Each project we reviewed was in either the formulation phase or
the implementation phase of the project life cycle. In the formulation
phase, the project defines requirements--what the project is being
designed to do--matures technology, establishes a schedule, estimates
costs, and produces a plan for implementation. In the implementation
phase, the project carries out these plans, performing final design
and fabrication as well as testing components and system assembly,
integrating these components and testing how they work together, and
launching the project. This phase also includes the period from
project launch through mission completion.
[7] NASA is required to report to Congress if development cost of a
program is likely to exceed the baseline estimate by 15 percent or
more, or if a milestone is likely to be delayed by 6 months or more.
42 U.S.C. § 16613(d).
[8] GAO, Best Practices: Using a Knowledge-Based Approach to Improve
Weapon Acquisition, [hyperlink,
http://www.gao.gov/products/GAO-04-386SP] (Washington, D.C.: Jan.
2004).
[9] GAO, Defense Acquisitions: Key Decisions to Be Made on Future
Combat System, [hyperlink, http://www.gao.gov/products/GAO-07-376]
(Washington, D.C.: Mar. 15, 2007); Defense Acquisitions: Improved
Business Case Key for Future Combat System's Success, [hyperlink,
http://www.gao.gov/products/GAO-06-564T] (Washington, D.C.: Apr. 4,
2006); NASA: Implementing a Knowledge-Based Acquisition Framework
Could Lead to Better Investment Decisions and Project Outcomes,
[hyperlink, http://www.gao.gov/products/GAO-06-218] (Washington, D.C.:
Dec. 21, 2005); NASA's Space Vision: Business Case for Prometheus 1
Needed to Ensure Requirements Match Available Resources, [hyperlink,
http://www.gao.gov/products/GAO-05-242] (Washington, D.C.: Feb. 28,
2005).
[10] [hyperlink, http://www.gao.gov/products/GAO-05-242].
[11] NASA defines formulation as the identification of how the program
or project supports the agency's strategic needs, goals, and
objectives; the assessment of feasibility, technology and concepts;
risk assessment, team building, development of operations concepts and
acquisition strategies; establishment of high-level requirements and
success criteria; the preparation of plans, budgets, and schedules
essential to the success of a program or project; and the
establishment of control systems to ensure performance to those plans
and alignment with current agency strategies. NASA Interim Directive
(NID) NM 7120-81 for NASA Procedural Requirements (NPR) 7120.5D,
paragraph 1.2.1(a) (Sept. 22, 2009) (Hereinafter cited as NID for NPR
7120.5D (Sept. 22, 2009).
[12] The implementation phase is defined as the execution of approved
plans for the development and operation of the program/project, and
the use of control systems to ensure performance to approved plans and
continued alignment with the Agency's strategic needs, goals, and
objectives. NID for NPR 7120.5D, paragraph 1.2.1(c) (Sept. 22, 2009).
[13] According to NID for NPR 7120.5D, Table 2-7 (Sept. 22, 2009), the
PDR demonstrates that the preliminary design meets all system
requirements with acceptable risk and within the cost and schedule
constraints and establishes the basis for proceeding with detailed
design. It shows that the correct design option has been selected,
interfaces have been identified, and verification methods have been
described. Full baseline cost and schedules, as well as risk
assessments, management systems, and metrics are presented.
[14] According to NID for NPR 7120.5D, Appendix A (Sept. 22, 2009), a
NAR is comprised of the analysis of a proposed program or project by a
(non-advocate) team composed of management, technical, and resources
experts (personnel) from outside the advocacy chain of the proposed
program or project. It provides agency management with an independent
assessment of the readiness of the program/project to proceed into
implementation.
[15] The management baseline is the integrated set of requirements,
cost, schedule, technical content, and associated joint confidence
level that forms the foundation for program or project execution and
reporting done as part of NASA's performance assessment and governance
process. NID for NPR 7120.5D, paragraph 2.1.8.2 and Appendix A (Sept.
22, 2009).
[16] According to NID for NPR 7120.5D, Table 2-7 (Sept. 22, 2009), the
CDR demonstrates that the maturity of the design is appropriate to
support proceeding with full scale fabrication, assembly, integration,
and test, and that the technical effort is on track to complete the
flight and ground system development and mission operations in order
to meet mission performance requirements within the identified cost
and schedule constraints. Progress against management plans, budget,
and schedule, as well as risk assessments are presented.
[17] The system integration review evaluates the readiness of the
project to start flight system assembly, test, and launch operations.
This review takes place after the CDR and just prior to the beginning
of phase D, where test and integration activities occur. NID for NPR
7120.5D, Table 2-7 and paragraph 4.6.1 (Sept. 22, 2009).
[18] For purposes of our analysis, cost or schedule growth is
significant if it exceeds the thresholds that trigger reporting to
Congress under the law. The thresholds are development cost growth of
15 percent or more from the baseline cost estimate or a milestone
delay of 6 months or more beyond the baseline schedule estimate. 42
U.S.C. § 16613(d).
[19] NASA did not provide a formal cost and schedule baselines for the
projects in formulation, citing that the estimates are preliminary.
Baselines are established when the project transitions to
implementation.
[18] The System Integration Review evaluates the readiness of the
project to start flight system assembly, test, and launch operations.
This review takes place after the CDR and just prior to the beginning
of phase D, where test and integration activities occur. NID for NPR
7120.5D, Table 2-7 and paragraph 4.6.1 (Sept. 22, 2009).
[20] If development cost of a program will exceed the baseline
estimate by more than 30 percent, then NASA is required to seek
reauthorization from Congress in order to continue the program. If the
program is reauthorized, NASA is required to establish new cost and
schedule baselines. 42 U.S.C. § 16613(e).
[21] 42 U.S.C. § 16613(e).
[22] These 13 projects include 5 projects reviewed this year and 8
projects from our previous reports in this series. For many of these
projects, the confirmation baseline was set prior to the requirement
for the statutory baseline. They are of analytical interest because
(1) they are or were in the implementation phase, and (2) measuring
cost growth from a project's confirmation baseline, not its statutory
baseline, allows for more of a more consistent comparison of project
cost growth among NASA's portfolio of projects.
[23] The Ares and Orion projects have completed their preliminary
design reviews, but have not yet held confirmation reviews.
[24] The "product development" stage in GAO's knowledge-based approach
is equivalent to "implementation" in NASA's lifecycle.
[25] NASA Procedural Requirements (NPR) 7123.1A , NASA Systems
Engineering Processes and Requirements Appendix G, paragraph G.19(b)
(Mar. 26, 2007)
[26] Appendix IV provides a description of the metrics used to assess
technology maturity.
[27] Projects will modify the form, fit, and function of a heritage
technology to adapt to the new environment. For example, the size or
the weight of the component may change or the technology may function
differently than its use in a previous mission.
[28] We were unable to determine design stability for the SOFIA
project as some data was not provided to us for review by NASA
because, according to project officials, the project documentation did
not transfer in its entirety from Ames Research Center to Dryden
Flight Research Center. In addition, we were unable to determine
design stability for the MMS project as it did not provide us with
detailed drawing count data.
[29] [hyperlink, http://www.gao.gov/products/GAO-06-218] and GAO,
NASA: Issues Implementing the NASA Authorization Act of 2010,
[hyperlink, http://www.gao.gov/products/GAO-11-216T] (Washington,
D.C.: Dec. 1, 2010)
[30] NPR 7123.1A, Appendix G, paragraph G.8 (Mar. 26, 2007)
[31] For KDP/milestone reviews, external independent reviewers known
as Standing Review Board (SRB) members evaluate the program/project
and, in the end, report their findings to the decision authority. For
a program or project to prepare for the SRB, the technical team must
conduct their own internal peer review process. This process typically
includes both informal and formal peer reviews at the subsystem and
system level. NASA Systems Engineering Handbook, paragraph 6.7.2.1
(Dec. 2007)
[32] The National Academies, National Research Council, Controlling
Cost Growth of NASA Earth and Space Science Missions (Washington, D.C.
2010).
[33] Pub. L. No. 111-5.
[34] GAO, NASA: Constellation Program Cost and Schedule Will Remain
Uncertain Until a Sound Business Case is Established, [hyperlink,
http://www.gao.gov/products/GAO-09-844] (Washington, D.C.: Aug. 26,
2009).
[35] GAO, NASA: Medium Launch Transition Strategy Leverages Ongoing
Investments but Is Not Without Risk, [hyperlink,
http://www.gao.gov/products/GAO-11-107] (Washington, D.C.: Nov. 22,
2010)
[36] NASA provides funding to SpaceX and Orbital to help offset
International Space Station-related development costs of the Falcon 9
and the Taurus II, respectively. The Falcon 9 and Taurus II are
intended to be medium class launch vehicles.
[37] [hyperlink, http://www.gao.gov/products/GAO-11-107].
[38] Government Industry Data Exchange Program, or GIDEP, is a
partnership between Government Agencies and Industry to share
scientific and technical information through an on-line web-enabled
database. GIDEP alerts report a problem with parts, components,
materials, specifications, software, manufacturing processes, or test
equipment that can cause a functional failure.
[39] GAO, High-Risk Series: An Update, [hyperlink,
http://www.gao.gov/products/GAO-07-310] (Washington, D.C.: Jan. 2007).
[40] National Aeronautics and Space Administration, Plan for
Improvement in the GAO High-Risk Area of Contract Management, Oct. 31,
2007.
[41] GAO, Additional Cost Transparency and Design Criteria Needed for
National Aeronautics and Space Administration (NASA) Projects,
[hyperlink, http://www.gao.gov/products/GAO-11-346R] (Washington,
D.C.: Mar. 3, 2011).
[42] NASA Policy Directive 1000.5A, Policy for NASA Acquisitions,
paragraphs 1(h)(1)(a) and 1(h)(2) (Jan. 15, 2009).
[43] Seven of the 21 projects were not required to complete the JCL
process at the time of our review.
[44] American National Standards Institute/Electronic Industries
Alliance Standard, Earned Value Management Systems, ANSI/EIA-748-B-
2007 approved July 9, 2007.
[45] [hyperlink, http://www.gao.gov/products/GAO-11-216T].
[46] Jet Propulsion Laboratory: James Webb Space Telescope (JWST)
Independent Comprehensive Review Panel (ICRP): Final Report, JPL D-
67250 (Pasadena, Calif.: Oct.29, 2010).
[47] These missions include Ares I, Soil Moisture Active and Passive,
and Orion.
[48] Because of changes in NASA's accounting structure, its historical
cost data are relatively inconsistent. As such, we used "then-year"
dollars to report data consistent with the data NASA reported to us.
[49] Some projects reported that their spacecraft would be ready for
launch sooner than the date that the launch authority could provide
actual launch services. In these cases, we used the actual launch date
for our analysis rather than the date that the project reported
readiness.
[50] According to NASA officials, projects that were in formulation at
the time of the agency's 2007 revision of its project management
policy are required to comply with that policy. Projects that had
already entered implementation at the time of the revision were
directed to implement those requirements that would not adversely
affect the project's cost and schedule baselines.
[51] In our calculation for percentage of total number of drawings
project for release, we used the number of drawings released at
critical design review as a fraction of the total number of drawings
projected, including where a growth in drawings occurred. So, the
denominator in the calculation may have been larger than what was
projected at the critical design review. We believe that this more
accurately reflected the design stability of the project.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: