Nuclear Regulatory Commission
Preliminary Observations on Efforts to Improve Security at Nuclear Power Plants
Gao ID: GAO-04-1064T September 14, 2004
The events of September 11, 2001, and the subsequent discovery of commercial nuclear power plants on a list of possible terrorist targets have focused considerable attention on the plants' capabilities to defend against a terrorist attack. The Nuclear Regulatory Commission (NRC), an independent agency established by the Energy Reorganization Act of 1974 to regulate the civilian use of nuclear materials, is responsible for regulating and overseeing security at commercial nuclear power plants. GAO was asked to review (1) NRC's efforts since September 11, 2001, to improve security at nuclear power plants, including actions NRC has taken to implement some of GAO's September 2003 recommendations to improve security oversight and (2) the extent to which NRC is in a position to assure itself and the public that the plants are protected against terrorist attacks. This testimony reflects the preliminary results of GAO's review. GAO will issue a more comprehensive report in early 2005.
NRC responded quickly and decisively to the September 11, 2001, terrorist attacks with multiple steps to enhance security at commercial nuclear power plants. NRC immediately advised the plants to go to the highest level of security according to the system in place at the time and issued advisories and orders to the plants to make certain enhancements, such as installing more physical barriers and augmenting security forces, that could be completed quickly to shore up security. According to NRC officials, their inspections found that the plants complied with these advisories and orders. Later, in April 2003, NRC issued a new design basis threat (DBT), which establishes the maximum terrorist threat that a facility must defend against, and required the plants to develop and implement new security plans to address the new threat by October 2004. It is also improving its force-on-force exercises, as GAO recommended in its September 2003 report. These exercises are an important agency tool to ensure that the plants' security plans are adequate to protect against the DBT. While its efforts to date have enhanced security, NRC is not yet in a position to provide an independent determination that each plant has taken reasonable and appropriate steps to protect against the new DBT. According to NRC officials, the facilities' new security plans are on schedule to be implemented by October 2004. However, NRC's review of the plans, which are not available to the general public for security reasons, has primarily been a paper review and is not detailed enough for NRC to determine if the plans would protect the facility against the threat presented in the DBT. For example, the plans GAO reviewed are largely based on a template and often do not include important site-specific information, such as where responding guards are stationed, how the responders would deploy to their defensive positions, and how long deployment would take. In addition, NRC officials are generally not visiting the facilities to obtain site-specific information and assess the plans in terms of each facility's layout. NRC is largely relying on force-on-force exercises it conducts to test the plans, but these exercises will not be conducted at all facilities for 3 years. NRC's oversight of plants' security could also be improved. However, NRC does not plan to make some improvements in its inspection program that GAO previously recommended and still believes are needed. For example, NRC is not following up to verify that all violations of security requirements have been corrected or taking steps to make "lessons learned" from inspections available to other NRC regional offices and nuclear power plants. Moreover, if NRC needs to revise its DBT further as the terrorist threat is better defined, it will need longer to make and test all the necessary enhancements. The Department of Energy, for example, is currently reviewing the DBT for its nuclear facilities.
GAO-04-1064T, Nuclear Regulatory Commission: Preliminary Observations on Efforts to Improve Security at Nuclear Power Plants
This is the accessible text file for GAO report number GAO-04-1064T
entitled 'Nuclear Regulatory Commission: Preliminary Observations on
Efforts to Improve Security at Nuclear Power Plants' which was released
on September 14, 2004.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the Subcommittee on National Security, Emerging Threats, and
International Relations, Committee on Government Reform, House of
Representatives:
United States Government Accountability Office:
GAO:
For Release on Delivery Expected at 10:00 a.m. EDT:
Tuesday, September 14, 2004:
Nuclear Regulatory Commission:
Preliminary Observations on Efforts to Improve Security at Nuclear
Power Plants:
Statement of Jim Wells, Director:
Natural Resources and Environment:
GAO-04-1064T:
GAO Highlights:
Highlights of GAO-04-1064T, testimony before the Subcommittee on
National Security, Emerging Threats, and International Relations,
Committee on Government Reform, House of Representatives:
Why GAO Did This Study:
The events of September 11, 2001, and the subsequent discovery of
commercial nuclear power plants on a list of possible terrorist
targets have focused considerable attention on the plants‘
capabilities to defend against a terrorist attack. The Nuclear
Regulatory Commission (NRC), an independent agency established by the
Energy Reorganization Act of 1974 to regulate the civilian use of
nuclear materials, is responsible for regulating and overseeing
security at commercial nuclear power plants.
GAO was asked to review (1) NRC‘s efforts since September 11, 2001, to
improve security at nuclear power plants, including actions NRC has
taken to implement some of GAO‘s September 2003 recommendations to
improve security oversight and (2) the extent to which NRC is in a
position to assure itself and the public that the plants are protected
against terrorist attacks. This testimony reflects the preliminary
results of GAO‘s review. GAO will issue a more comprehensive report in
early 2005.
What GAO Found:
NRC responded quickly and decisively to the September 11, 2001,
terrorist attacks with multiple steps to enhance security at commercial
nuclear power plants. NRC immediately advised the plants to go to the
highest level of security according to the system in place at the time
and issued advisories and orders to the plants to make certain
enhancements, such as installing more physical barriers and augmenting
security forces, that could be completed quickly to shore up security.
According to NRC officials, their inspections found that the plants
complied with these advisories and orders. Later, in April 2003, NRC
issued a new design basis threat (DBT), which establishes the maximum
terrorist threat that a facility must defend against, and required the
plants to develop and implement new security plans to address the new
threat by October 2004. It is also improving its force-on-force
exercises, as GAO recommended in its September 2003 report. These
exercises are an important agency tool to ensure that the plants‘
security plans are adequate to protect against the DBT.
While its efforts to date have enhanced security, NRC is not yet in a
position to provide an independent determination that each plant has
taken reasonable and appropriate steps to protect against the new DBT.
According to NRC officials, the facilities‘ new security plans are on
schedule to be implemented by October 2004. However, NRC‘s review of
the plans, which are not available to the general public for security
reasons, has primarily been a paper review and is not detailed enough
for NRC to determine if the plans would protect the facility against
the threat presented in the DBT. For example, the plans GAO reviewed
are largely based on a template and often do not include important
site-specific information, such as where responding guards are
stationed, how the responders would deploy to their defensive
positions, and how long deployment would take. In addition, NRC
officials are generally not visiting the facilities to obtain site-
specific information and assess the plans in terms of each facility‘s
layout. NRC is largely relying on force-on-force exercises it conducts
to test the plans, but these exercises will not be conducted at all
facilities for 3 years. NRC‘s oversight of plants‘ security could also
be improved. However, NRC does not plan to make some improvements in
its inspection program that GAO previously recommended and still
believes are needed. For example, NRC is not following up to verify
that all violations of security requirements have been corrected or
taking steps to make ’lessons learned“ from inspections available to
other NRC regional offices and nuclear power plants. Moreover, if NRC
needs to revise its DBT further as the terrorist threat is better
defined, it will need longer to make and test all the necessary
enhancements. The Department of Energy, for example, is currently
reviewing the DBT for its nuclear facilities.
www.gao.gov/cgi-bin/getrpt?GAO-04-1064T.
To view the full product, including the scope and methodology, click
on the link above. For more information, contact Jim Wells, (202)
512-3841, wellsj@gao.gov.
[End of section]
Mr. Chairman and Members of the Subcommittee:
We are pleased to be here today to discuss our ongoing review of the
Nuclear Regulatory Commission's (NRC) efforts to improve security at
the nation's 104 commercial nuclear power plants licensed to operate.
These plants, which are located at 65 facilities in 31 states, provide
about 20 percent of the nation's electricity.[Footnote 1] We are
conducting this review at your request and expect to issue our final
report early next year.
The events of September 11, 2001, and the subsequent discovery of
commercial nuclear power plants on a list of possible terrorist targets
have focused considerable attention on the plants' capabilities to
defend against a terrorist attack. However, as you know, NRC is not
alone in the challenges it faces to protect against terrorism.
Recently, the 9/11 Commission's report highlighted the accomplishments
and challenges that remain on many fronts in the nation's fight against
terrorism. In recent testimony before this Committee, the Comptroller
General applauded the efforts of the 9/11 Commission and discussed its
recommendations to improve information sharing and analysis by the
intelligence agencies.[Footnote 2] We have also testified several times
before this Subcommittee on weaknesses in border security, federal
action needed to address security challenges at the nation's chemical
facilities, and the issues faced by the Department of Energy (DOE) in
its efforts to secure its nuclear facilities.[Footnote 3]
To protect commercial nuclear power plants from a terrorist attack, NRC
formulates a design basis threat (DBT), which establishes the maximum
terrorist threat that a facility must prepare to defend against. The
DBT characterizes the elements of a postulated attack, including the
number of attackers, their training, and the weapons and tactics they
are capable of using. Each facility must prepare a security plan
describing its strategy for defending against the threat presented in
the DBT. NRC is responsible for reviewing and approving these plans,
inspecting the facilities to verify compliance with the plans and other
NRC requirements, and conducting force-on-force exercises (mock
terrorist attacks) at the facilities to ensure that the facilities'
execution of their security plans could repel an attack. NRC considers
the DBT and the security plans to be safeguards or sensitive
information and does not make them available to the general public.
Our current review is the second on NRC's security program since the
September 11 attacks. In our earlier report, issued in September 2003,
we made a number of recommendations to NRC to improve its oversight of
security at commercial nuclear power plants.[Footnote 4]
In my testimony today, I will (1) describe NRC's efforts since
September 11, 2001, to improve security at nuclear power plants,
including actions it has taken to implement some of our September 2003
recommendations to improve security oversight and (2) discuss our
preliminary views on the extent to which NRC is in a position to assure
itself and the public that its efforts will protect the plants against
terrorist attacks. To conduct this work, we reviewed the security
advisories and orders NRC has issued to the facilities since September
11, 2001. We also reviewed security documents, such as the DBT and
individual facilities' draft security plans,[Footnote 5] and
interviewed NRC security program officials. We did the work reflected
in this statement from March 2004 through August 2004 in accordance
with generally accepted government auditing standards.
In our final report, we will discuss the extent to which NRC is using a
risk management approach to improve security at nuclear power plants.
More specifically, we will report on NRC's efforts to (1) define the
threat faced by nuclear power plants, (2) identify and characterize the
vulnerabilities that would allow a threat to be realized, (3) assess
the risks and determine priorities for protecting the plants, and (4)
identify the countermeasures to reduce the risk of a successful
terrorist attack.
In summary:
NRC responded quickly to the September 11, 2001, terrorist attacks with
multiple steps to enhance security at commercial nuclear power plants.
For example, NRC:
* immediately advised the plants to go to the highest level of security
according to the system in place at the time;
* issued a series of advisories and orders to the plants to make
certain security enhancements--such as installing additional physical
barriers, augmenting security forces, increasing patrols, and further
restricting plant access--that could be completed quickly to shore up
security until a more comprehensive analysis of the terrorist threat
and how to best protect the plants against that threat could be
completed;
* issued a new DBT in April 2003 and required the plants to develop and
implement--by October 2004--new security plans setting out how the
plants will protect against the threat defined in the new DBT. NRC
expects the plants will meet this deadline; and:
* improved its force-on-force exercises, which are an important agency
tool to ensure that the plants are secure, by planning to conduct the
exercises every 3 years instead of every 8 years and to make them more
realistic, which we had recommended.
While we applaud these efforts, it will take several more years for NRC
to make an independent determination that each plant has taken
reasonable and appropriate steps to protect against the threat
presented in the new DBT. The plants' development and implementation of
security plans to comprehensively address the new DBT is a critical
step in ensuring that individual plants can defend against terrorism.
Although new security plans are to be approved and implemented by
October 29, 2004, NRC will not have detailed knowledge about security
at individual facilities to ensure that these plans provide this
protection. NRC will not have this detailed knowledge, primarily for
two reasons:
* First, NRC's review of the new security plans has been rushed and is
largely a paper review. NRC is conducting its review of the plans over
a 6-month period--as the plants are implementing the plans--and NRC
reviewers are generally not visiting the plants to obtain details about
the plans and view how the plans interface with the plants' physical
layout. For example, the plans do not detail defensive positions at the
site, how the defenders would deploy to respond to an attack, or how
long the deployment would take. In addition, NRC is not requesting, and
the facilities are generally not submitting for review, the documents
and studies supporting the draft security plans.
* Second, it will take up to 3 years for NRC to test implementation of
the new plans through force-on-force exercises at all facilities.
Moreover, NRC is considering action that could potentially compromise
the integrity of the exercises. The agency is planning to require the
use of an adversary force trained in terrorist tactics, as we
recommended in our September 2003 report. However, NRC is considering
the use of a force provided by a company that the nuclear power
industry selected; this company provides guards for about half the
facilities to be tested. This relationship with the industry raises
questions about the force's independence. Furthermore, NRC is not
taking advantage of other opportunities to improve the effectiveness of
the exercises and its oversight in general by implementing other
recommendations from our September 2003 report. For example, NRC is not
following up to verify that all violations it found in previous
inspections have been corrected and is not taking steps to make
"lessons-learned" from inspections available to other regional offices
and nuclear power plants, as we had recommended.
In addition to these concerns, we note that NRC's DBT is similar to the
DOE's DBT for its nuclear facilities. As you know, in April 2004, DOE
officials told this Subcommittee that it would have to revisit its
post-September 11 DBT. If NRC also decides to revisit and revise its
DBT, NRC will need even longer to put all the necessary security
enhancements in place and to test them. Funding the costs of the
additional protection could also be an issue. NRC has already stated
that the current DBT is the largest reasonable threat against which a
regulated private guard force should be expected to defend under
existing law. Also, certain potential vulnerabilities, such as airborne
assaults, are currently being addressed outside of the DBT. Any changes
in this approach to certain vulnerabilities could similarly place
additional requirements on the plants.
Background:
NRC is an independent agency established by the Energy Reorganization
Act of 1974 to regulate the civilian use of nuclear materials. NRC's
Office of Nuclear Security and Incident Response, which was established
in April 2002, is primarily responsible for regulating and overseeing
security at commercial nuclear power plants. This office also develops
overall agency policy and provides management direction for evaluating
and assessing technical issues involving security at nuclear
facilities. In addition, it coordinates with the Department of Homeland
Security, the intelligence and law enforcement communities, DOE, and
other agencies on security matters.
NRC begins regulating security at a commercial nuclear power plant when
the plant is constructed. Before granting an operating license, NRC
must approve a security plan for the plant. If more than one plant is
located at a facility, the licensee prepares a physical security plan
covering all the plants at the site. Since 1977, NRC has required
facilities to have a security plan that is designed to protect against
a DBT for radiological sabotage.[Footnote 6] The DBT characterizes the
elements of a possible attack, including the number of attackers, their
training, and the weapons and tactics they are capable of using. Since
it was first issued in 1977, the DBT has been revised twice, each time
to reflect increased terrorist threats. The first revision occurred in
1993 in response to the first terrorist attack on the World Trade
Center in New York City and to a vehicle intrusion at the Three Mile
Island nuclear power plant in Pennsylvania.[Footnote 7] The second
revision was issued on April 29, 2003, in response to the September 11,
2001, terrorist attacks.
NRC oversees plant security through several activities, particularly
security inspections and force-on-force exercises. In annual security
inspections at all the plants, inspectors are to check that the plant's
security programs meet NRC requirements for access authorization,
access control, and response to contingency events. The inspectors also
are to review changes to the plant's security plan and self-assessment
of security. NRC suspended these inspections in September 2001 to focus
its resources on the implementation of security enhancements from NRC's
advisories and orders. NRC reinstated the inspection program in early
2004.
NRC began conducting force-on-force exercises under its security
inspection program in 1991. The agency suspended these exercises, which
were referred to as Operational Safeguards Response Evaluation (OSRE)
exercises, after the September 11, 2001, attacks because they
considered it unsafe to perform mock attacks during a period of
heightened security and because NRC and licenses security resources
were focused on responding to the events of September 11, 2001. NRC has
conducted some exercises during 2003 and 2004 to gain the information
necessary to initiate a revised, permanent force-on-force exercise
program sometime in the near future. Although NRC officials have not
decided on an exact date, they anticipate that the exercises will
resume very soon after the facilities have implemented their security
plans, which is scheduled for the end of October 2004.
NRC Actions Since September 11, 2001, to Improve Security at Nuclear
Power Plants:
Shortly after September 11, 2001, NRC began to respond to the
heightened risk of terrorist attacks. Between September 11, 2001, and
the end of March 2003, the agency issued over 60 advisories to
licensees of nuclear power plants. These advisories recommended
enhancements that could be made quickly to shore up security until a
more comprehensive analysis of the terrorist threat and how best to
protect the plants against the threat could be completed. NRC
immediately advised the plants to go to the highest level of security
according to the system in place at the time. It followed with
advisories and orders designed to increase the size and improve the
proficiency of plants' security forces, restrict access to plants, and
increase and improve plants' defensive barriers. For example, on
October 6, 2001, NRC issued a major advisory, recommending that the
licensees take immediate action to increase the number of security
guards and to be cautious about using temporary employees.
From October 2001 to January 2002, NRC conducted a three-phase security
inspection, checking the facilities to see if they had implemented
these advisories. In phase one, NRC inspectors used an NRC-prepared
checklist to document the implementation status of NRC's October 6,
2001 advisory. In phase two, security inspectors conducted a more in-
depth evaluation of the facilities' implementation of the advisories.
During phase three, NRC's security inspectors reviewed each facility's
security program to determine if it had complied with the additional
measures recommended in the October 6, 2001, advisory. NRC concluded
that all facilities were in compliance but that the facilities had not
consistently interpreted the recommended measures.
NRC used the results from the three-phase inspection to develop a
February 25, 2002, order requiring facilities to implement additional
security measures by August 31, 2002.[Footnote 8] Many of these
measures had been recommended in previous advisories. NRC then
conducted security inspections to verify facilities' compliance with
all aspects of the order. The inspections were completed in December
2003, and NRC found that all nuclear power facilities were in
compliance with the order.
NRC also acted on an item that had been a security concern for a number
of years--the use of temporary clearances for temporary employees at
the plants. Commercial nuclear power plants use hundreds of temporary
employees for maintenance--most frequently during the period when the
plant is shut down for refueling. In the past, NRC found instances in
which personnel who failed to report criminal records had temporary
clearances that allowed them unescorted access to vital areas.[Footnote
9] In an October 6, 2001, advisory, NRC suggested that facilities limit
temporary clearances for temporary workers. On February 25, 2002, NRC
issued an order that limited the use and duration of temporary
clearances, and on January 7, 2003, NRC issued an order to eliminate
the use of temporary clearances altogether. NRC now requires a criminal
history review and a background check investigation to be completed
before allowing temporary workers to have unescorted access to the
power plant.
NRC issued its revised DBT in April 2003 to reflect the post-September
11 terrorist threat. In January 2003, NRC developed a draft DBT that it
sent to federal, state, and local law enforcement agencies, federal
intelligence and counterintelligence agencies, and the nuclear industry
for review and comment. Between January and April of 2003, revisions
were made, and the revised drafts were sent for additional comments. On
April 29, 2003, NRC issued an order requiring the facilities to protect
the power plants from a terrorist attack fitting within the parameters
of the new DBT. The new DBT reflected the increased size of a potential
terrorist force, the more sophisticated weaponry, and the different
methods of deployment demonstrated by the September 11 terrorist
attacks. NRC stated that this new DBT was the "largest reasonable
threat against which a regulated private guard force should be expected
to defend under existing law." Licensees were given 1 year to develop
new security plans based on the new DBT.
At the same time, NRC issued two other orders that (1) limited work
hours for security personnel (to 16 hours per 24-hour period, 26 hours
per 48-hour period, and 72 hours per week) so that excessive hours
would not impair security forces in performing their duties and (2)
required enhanced training and qualifications for the plants' security
forces. All told, according to the Nuclear Energy Institute,[Footnote
10] by the end of 2004, the nuclear power industry will have invested
about $1 billion in security enhancements since September 11, 2001.
During this period, NRC also developed and strengthened its relations
with other federal agencies. It collaborated with the Federal Aviation
Administration on protecting airspace over the plants and worked with
the Department of Homeland Security, Federal Bureau of Investigation,
and local law enforcement agencies to monitor and analyze security
threats and to determine additional security measures needed to meet
such threats.
NRC has also taken, or is taking, steps to implement our September 2003
recommendations to improve its security inspections and force-on-force
exercises. We had recommended that the NRC Commissioners ensure that
the agency's security inspection program and force-on-force exercise
program are restored promptly. NRC reinstated the security inspection
program in February 2004.
NRC has not yet made force-on-force exercises a required activity, as
we recommended, but it is taking steps in that direction. During 2003,
NRC completed a "pilot" force-on-force program, which included 15
exercises. This pilot program was designed to determine how future
force-on-force exercises would be conducted. After completing the 15
pilot exercises, NRC summarized the results in a "lessons learned"
document. NRC is now conducting "transition" force-on-force exercises
to help it formulate a new, permanent program. Participation in both
the pilot and most of the transition exercises was voluntary for the
facilities. Only some of the pilot exercises tested the full DBT, and
none of the transitional exercises have or will test the full terrorist
capabilities of the DBT. NRC officials said that they will not start
conducting exercises using the new DBT until November 2004, after the
facilities have implemented their new security plans.
NRC is also making the following additional improvements we recommended
for these exercises:
* conducting the exercises more frequently at each site--every 3 years
rather than the once every 8 years schedule of the past;
* using laser equipment in all force-on-force exercises to more
accurately account for shots fired and to establish a more realistic
setting;
* continuing the practice, begun in 2000, of prohibiting licensees from
temporarily increasing the number of guards defending the plant and
enhancing plant defenses for force-on-force exercises, or requiring
that any temporary security enhancements be officially incorporated
into the licensees' security plans; and:
* requiring the exercises to make use of the full terrorist
capabilities stated in the DBT, including the use of an adversary force
that has been trained in terrorist tactics.
NRC Cannot Yet Provide Assurances That Its Efforts Will Protect Nuclear
Power Plants Against Terrorist Attacks as Outlined in the New DBT:
As the principal regulator of commercial nuclear power plants, NRC has
an important responsibility to provide an independent determination
that each plant is protected against the threat presented in the new
DBT. While its efforts to date have no doubt enhanced security, NRC
cannot yet provide this determination for three principal reasons.
First, its review of the facilities' new security plans setting out how
the facilities will respond to the threat presented in the new DBT is
not detailed enough. Second, it will not test the effectiveness of all
the plans and security at all plants with force-on-force exercises for
3 years, and it does not plan to make some improvements in its security
oversight that we believe are needed and have previously recommended.
Third, NRC could potentially need to further revise its DBT as the
terrorist threat is better defined, which could require changes in the
security plans and additional security improvements.
NRC's Review of Security Plans Is Not Detailed Enough to Determine if
They Effectively Address the New DBT:
NRC's strategy for reviewing the facilities' security plans generally
allows for only a document review. While NRC staff originally estimated
that it would take 2 years to review the plans, NRC now expects to take
6 months--from April 29, 2004, through October 29, 2004--to review and
approve the facilities' security plans. The facilities are also
expected to have their plans implemented by that date.
To review the plans in 6 months, NRC assigned 20 NRC staff and
contracted for 20 staff from DOE's Idaho National Engineering
Laboratory to perform the reviews. The facilities' use of an industry-
developed template is also expected to help speed the review.[Footnote
11] The template was intended to provide standard language for about 80
percent of the plans' contents. However, the plans we reviewed relied
almost entirely on the template language and provided little facility-
specific information.
Agency officials are generally not visiting the facilities to obtain
site-specific information and assess the plans in terms of each
facility's particular layout. Since completion of our work, NRC has
decided to visit six or seven of the plants to verify information in
the plan; however, it will not visit the vast majority of plants. In
addition, the plans do not contain much detail. For example, the 12
plans NRC provided for our review do not include information about
where responding guards are stationed, where their defensive positions
are located, how the responders would deploy to their defensive
positions, and how long deployment would take.[Footnote 12] The plans
state that "[p]hysical security measures and specific response
protocols for the onsite security force are contained in facility
implementing procedures." Also, in all the plans we reviewed, the
defensive positions are described only as being established "where
necessary." None of the plans we reviewed specified the type of weapons
the security forces will carry; stating only that the forces will meet
NRC's minimum requirements. According to staff from our Office of
Special Investigations with experience in law enforcement and physical
security, the security plans are, at best, general guidelines.
The plans often refer to other documents that detail how the
requirements will be met and how the plans will be implemented.
However, because of the 6-month review time frame, NRC officials do not
plan to review these supporting documents as part of their approval
process. According to NRC officials, the principal purpose of the plans
is to commit the facilities to comply with all NRC security regulations
and the template-based plans accomplish that purpose for about 80 to 90
percent of the information.
NRC's Security Oversight Is Limited by Timing of Key Activities and
Inaction on Some of Our Recommendations:
NRC will not determine the adequacy of the sites' procedures and
programs for implementing their security plans and the sites' ability
to actually implement the plan until it conducts inspections and force-
on-force exercises at the sites. Because NRC plans to annually inspect
all sites and conduct force-on-force exercises on a 3-year cycle, it
could be 2007 before NRC can say with assurance that all the sites can
be protected from a terrorist attack as presented in the new DBT.
In addition to the limitations of the security inspections and the
timing of the force-on-force exercises, NRC has not implemented some of
the recommendations we made in our September 2003 report to improve its
oversight. We recommended that the NRC Commissioners:
* require that NRC regional inspectors conduct follow-up visits to
verify that corrective action has been taken when security violations,
including non-cited violations,[Footnote 13] have been identified;
* ensure that NRC routinely collects, analyzes, and disseminates:
information on security problems, solutions, and lessons learned and
shares this information with all NRC regions and licensees; and:
* enforce NRC's requirement that force-on-force exercise reports be
issued within 30 to 45 days after the end of the exercise to ensure
prompt correction of the problems noted.
Implementation of these recommendations is needed to correct some
important program limitations. For example, during annual inspections,
NRC inspectors often classified security problems as non-cited
violations if the problem had not been identified frequently in the
past or if the problem had no direct, immediate, adverse consequence at
the time that it was identified. Instances of a security guard sleeping
on duty and a security officer falsifying logs to show that he had
checked vital areas and barriers when he was actually in another part
of the plant, for example, were treated as non-cited violations. This
classification tends to minimize the seriousness of the problem. Non-
cited violations do not require a written response from the licensee
and do not require NRC inspectors to verify that the problem has been
corrected. NRC used non-cited violations extensively for serious
problems, thereby allowing the licensees to correct the problem on
their own without NRC verification of the correction. Consequently, we
believe NRC may not be fully aware of the quality of security at a
site, and the lack of follow-up and verification reduces assurances
that needed improvements have been made.
NRC also has not created a system to share the security problems,
solutions, and lessons learned that it finds during security
inspections with all the NRC regions and licensees. NRC did create a
management review panel that is tracking the regions' findings during
the security inspections and the dispositions of the findings. It is
also keeping a database of all the findings and dispositions or
solutions; however, the database is not accessible by the regions and
licensees.
With respect to NRC's enforcement of its requirement for force-on-force
exercise reports, NRC officials said they do plan to issue reports when
the permanent force-on-force program is reinstated, but the reports
will not be made public. During the pilot force-on-force exercises, NRC
did not issue any reports, although it prepared a "lessons learned"
document for the Commissioners. In addition, an NRC official stated
that NRC will not issue reports on the new transitional force-on-force
exercises, but will prepare another internal lessons learned document.
We continue to believe that NRC needs to promptly issue reports on each
exercise to ensure that any security problems are quickly corrected.
These reports would also provide the documentation needed to assess
trends and patterns among facilities as well as at particular
facilities over time.
Finally, although NRC is taking action--as we recommended in our
September 2003 report--to establish an adversary force trained in
terrorist tactics, NRC is not establishing the force in a manner that
provides confidence that the force will be independent and highly
trained, and will endeavor to find weaknesses in the facilities'
security. NRC delegated the task of establishing the adversary force to
an organization--the Nuclear Energy Institute--that represents the
licensees of nuclear power plants. The company the Institute selected
currently provides security guards to about half of the nuclear power
sites to be tested. The company's relationship with the industry raises
questions about the force's independence. Of further concern, this
company was recently involved in a controversy over similar tests.
During a June 2003 DOE force-on-force exercise at a nuclear site in Oak
Ridge, Tennessee, security guards working for this company received
uncharacteristically high scores. A subsequent investigation by DOE's
Office of the Inspector General indicated that the guards might have
cheated on the test and perhaps on many other tests at Oak Ridge,
dating back to the mid-1980s. It was alleged that the guards had
studied plans for the simulated attacks before they were carried out,
had disabled the laser sensors they wore during tests to determine when
they were "shot" by mock enemies, arranged trucks and other obstacles
to help foil simulated attacks, created special, nonstandard plans to
help them perform better on tests, and put more guards on duty at the
time of the tests than would normally have been present.
If NRC Needs to Revise Its DBT, Additional Security Enhancements Could
Be Required:
In April 2004, DOE told this Subcommittee that it would have to review
its post-September 11, 2001, DBT for its nuclear facilities to
determine if it should be more stringent.[Footnote 14] If NRC decides,
as it gains a better understanding of the terrorist threat, that it
also needs to reconsider its DBT, it could take longer to put all
necessary enhancements in place and test them with force-on-force
exercises. Depending on the additional enhancements needed, funding of
the costs of the additional protection and how quickly it could be put
in place could also become an issue. NRC previously stated that its
April 29, 2003, DBT is the largest reasonable threat against which a
regulated private guard force should be expected to defend under
current law.
Similarly, NRC is addressing certain potential vulnerabilities outside
of the DBT. For example, the terrorists' use of aircraft on September
11 raised questions about nuclear power plants' vulnerabilities to such
attacks. According to NRC, although the design of many facilities
considered the probability of accidental aircraft crashes that may pose
undue risks to public health and safety, only a few facilities were
specifically designed to withstand an accidental impact. Nonetheless,
NRC believes that nuclear power facilities are among the most hardened
industrial facilities in the United States. They are massive structures
with thick exterior walls and interior barriers of reinforced concrete
designed to withstand tornadoes (and projectiles propelled by
tornadoes), hurricanes, fires, floods, and earthquakes. NRC also
believes that the efforts to enhance security at airports and on
airplanes and to identify potential terrorists and prevent potential
attacks before they occur are an important part of reducing the threat
of airborne attacks.
After the September 11 attacks, the Federal Aviation Administration,
working with NRC, advised pilots to avoid the airspace above or in
proximity to all nuclear power facilities and not to circle in their
vicinity. NRC also undertook a major classified research and
engineering effort, in conjunction with national laboratories, to
evaluate the vulnerabilities and potential effects of a large
commercial aircraft's hitting a nuclear power site. This effort
includes consideration of additional preventive or mitigating measures
to enhance the protection of public health and safety in the event of a
deliberate aircraft crash into a nuclear power plant or spent (used)
nuclear fuel storage facility. The results are classified and cannot be
discussed in this open hearing. According to NRC officials, certain
types of aircraft hitting facilities at certain locations pose some
risks. The officials noted that, in these cases, the plants would have
enough time to take advantage of certain safety features to
substantially lessen the risks. NRC officials also believe that the
plants would have sufficient time to implement emergency preparedness
plans, if necessary.
Airborne assaults on plants remain a public concern. If further
consideration of NRC's aircraft study results lead to changes in NRC's
approach, the DBT may need to be revised further, again raising
questions about the timing and cost of improvements.
In closing, the nation's commercial nuclear power plants are no doubt
more secure against a terrorist attack now than they were on September
11, 2001. NRC responded quickly and decisively to the attacks by
requiring various enhancements to existing security at the plants. It
will be some time, however, before NRC can provide the public with
assurances that what has been done is enough. Some of these
enhancements are still being put in place, and NRC cannot independently
determine that the enhancements will adequately secure the facilities
until they have been effectively tested with force-on-force exercises.
While our assessment of NRC activities is still underway, we believe
that it is important for NRC to act quickly and take a strong
leadership role in establishing a worthy adversary team for these
exercises, establish priorities for the facilities to be tested,
carefully analyze the test results for shortcomings in facility
security, and be willing to require additional security improvements as
warranted.
Mr. Chairman, this testimony provides our preliminary views. We would
be happy to respond to any questions that you or Members of the
Subcommittee may have.
For further GAO Contact and Staff Acknowledgements:
For further information on this testimony, please contact Jim Wells at
(202) 512-3841 or at Wellsj@gao.gov. Raymond H. Smith, Jr.; Kenneth E.
Lightner, Jr.; Jill Ann Roth Edelson; Kevin L. Jackson; Carol
Herrnstadt Shulman; and Barbara R. Timmerman made key contributions to
this testimony.
FOOTNOTES
[1] More than one nuclear power plant are located at some facilities.
[2] GAO, 9/11 Commission Report: Reorganization, Transformation, and
Information Sharing, GAO-04-1033T (Washington, D.C.: Aug. 3, 2004).
[3] GAO, Border Security: Additional Actions Needed to Eliminate
Weaknesses in the Visa Revocation Process, GAO-04-899T, (Washington,
D.C.: July 13, 2004); GAO, Homeland Security: Federal Action Needed to
Address Security Challenges at Chemical Facilities, GAO-04-482T
(Washington, D.C.: February 23, 2004); GAO, Nuclear Security: DOE Must
Address Significant Issues to Meet the Requirements of the New Design
Basis Threat, GAO-04-701T (Washington, D.C.: April 27, 2004); and GAO,
Nuclear Security: Several Issues Could Impede the Ability of DOE's
Office of Energy, Science and Environment to Meet the May 2003 Design
Basis Threat, GAO-04-894T (Washington, D.C.: June 22, 2004).
[4] GAO, Nuclear Regulatory Commission: Oversight of Security at
Commercial Nuclear Power Plants Needs to Be Strengthened, GAO-03-752,
(Washington, D.C.: September 4, 2003).
[5] We reviewed 12 of the 65 facilities' draft security plans.
According to NRC officials, the plans we reviewed were generally
representative of all the plans.
[6] Radiological sabotage against a nuclear power plant is a deliberate
act that could directly or indirectly endanger public health and safety
by exposure to radiation.
[7] On February 7, 1993, an intruder drove onto the Three Mile Island
power plant site, through a gate, and crashed through a roll-up door
into the turbine area. The intruder challenged security barriers and
disrupted operations for 4 hours before he was apprehended.
[8] NRC Order EA-02-026.
[9] The vital area, within the protected area, contains the plant's
equipment, systems, devices, or material whose failure, destruction, or
release could endanger the public health and safety by exposure to
radiation. This area is protected by guard stations, reinforced gates,
surveillance cameras, and locked doors.
[10] The institute represents licensees of commercial nuclear power
plants.
[11] NRC provided input to the template's development.
[12] Staff from our Office of Special Investigations with experience in
law enforcement and physical security assisted in reviewing these
plans.
[13] A non-cited violation is a problem that had not been identified
more than twice in the past year or had no immediate, direct
consequences at the time it was identified.
[14] DOE's post-September 11, 2001, DBT, which is similar to NRC's in
terms of the threat it outlines, was issued in May 2003. DOE has not
yet completed its review of the DBT.