Defense Acquisitions
Challenges Associated with the Navy's Long-Range Shipbuilding Plans
Gao ID: GAO-06-587T March 30, 2006
The Navy's long-range shipbuilding plan spells out its approach to meeting the Navy's future needs. This plan shows the Navy is embarking on an ambitious, expensive undertaking to develop, design, and construct a number of new ship classes. The Navy expects these vessels to successfully execute missions in a variety of environments through use of advanced technologies, while utilizing reduced crews and greater automation to lower costs. The Navy also expects these vessels to be constructed in quantities that sustain the industrial base and expand the overall size of the Navy. The plan calls for the number of ships to increase by about 10 percent to an average of about 309 ships through 2036. This effort will cost billions of dollars. At the request of Projection Forces Subcommittee of the House Armed Services Committee, GAO examined the Navy's shipbuilding plan and is providing this discussion of 1) the multiple objectives the plan proposes to meet; 2) the challenges that must be met to execute the plan; and 3) ways the Navy can reduce the tension between the demand for and supply of shipbuilding funds.
While the Navy's shipbuilding plan is beneficial in that it lays out a strategic approach for decision making, there is tension inherent among the plan's multiple objectives. For example, demanding mission requirements can result in more costly ships that cannot be built in the numbers desired for presence and shipyard workload. These tensions presage the potential trade-offs that will likely have to be made. The key is to anticipate and make trade-offs early in the context of the overall shipbuilding strategy. If the Navy starts more programs than it can finish within available resources, it may be forced to make trade-offs in the future that it may not find acceptable today. Assuming the long-range shipbuilding plan is consistent with national military priorities, the main challenge in execution is keeping the supply and demand for funds in a rational balance that does not overly sacrifice one objective to meet another. The Navy projects a supply of shipbuilding funds that will double by 2011 and stay high. At the same time, increasing demands on the federal budget--including for weapons for other services--suggest such growth in shipbuilding funds may not materialize. The Navy's own ability to control the demand for shipbuilding funds is also a challenge. If the Navy cannot control cost growth on new ships, some other objectives of the plan will have to be sacrificed, such as mission capability or presence. There are several ways the Navy can help reduce the tension between the demand for and supply of shipbuilding funds. To control unanticipated cost growth on individual programs, it is important that the Navy ensure programs have sufficiently high levels of knowledge before making programmatic, budgetary, or contractual commitments. To maximize the amount of funds the Navy can devote within its budget to shipbuilding, it must continue to find ways to lower total ownership costs by reducing manning requirements and to improve operational availability of ships through means such as rotational crewing.
GAO-06-587T, Defense Acquisitions: Challenges Associated with the Navy's Long-Range Shipbuilding Plans
This is the accessible text file for GAO report number GAO-06-587T
entitled 'Defense Acquisitions: Challenges Associated with the Navy's
Long-Range Shipbuilding Plan' which was released on March 31, 2006.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony Before the Subcommittee on Projection Forces, Committee on
Armed Services, House of Representatives:
United States Government Accountability Office:
GAO:
For Release on Delivery Expected at 4:00 p.m. EST:
Thursday, March 30, 2006:
Defense Acquisitions:
Challenges Associated with the Navy's Long-Range Shipbuilding Plan:
Statement of Paul L. Francis, Director:
Acquisition and Sourcing Management:
GAO-06-587T:
GAO Highlights:
Highlights of GAO-06-587T, a testimony to the Subcommittee on
Projection Forces, Committee on Armed Services, House of
Representatives:
Why GAO Did This Study:
The Navy‘s long-range shipbuilding plan spells out its approach to
meeting the Navy‘s future needs. This plan shows the Navy is embarking
on an ambitious, expensive undertaking to develop, design, and
construct a number of new ship classes. The Navy expects these vessels
to successfully execute missions in a variety of environments through
use of advanced technologies, while utilizing reduced crews and greater
automation to lower costs. The Navy also expects these vessels to be
constructed in quantities that sustain the industrial base and expand
the overall size of the Navy. The plan calls for the number of ships to
increase by about 10 percent to an average of about 309 ships through
2036. This effort will cost billions of dollars.
At the request of Projection Forces Subcommittee of the House Armed
Services Committee, GAO examined the Navy‘s shipbuilding plan and is
providing this discussion of 1) the multiple objectives the plan
proposes to meet; 2) the challenges that must be met to execute the
plan; and 3) ways the Navy can reduce the tension between the demand
for and supply of shipbuilding funds.
What GAO Found:
While the Navy‘s shipbuilding plan is beneficial in that it lays out a
strategic approach for decision making, there is tension inherent among
the plan‘s multiple objectives. For example, demanding mission
requirements can result in more costly ships that cannot be built in
the numbers desired for presence and shipyard workload. These tensions
presage the potential trade-offs that will likely have to be made. The
key is to anticipate and make trade-offs early in the context of the
overall shipbuilding strategy. If the Navy starts more programs than it
can finish within available resources, it may be forced to make trade-
offs in the future that it may not find acceptable today.
Multiple Objectives Embodied in the Navy Shipbuilding Plan:
[See PDF for image]
GAO (presentation).
[End of figure]
Assuming the long-range shipbuilding plan is consistent with national
military priorities, the main challenge in execution is keeping the
supply and demand for funds in a rational balance that does not overly
sacrifice one objective to meet another. The Navy projects a supply of
shipbuilding funds that will double by 2011 and stay high. At the same
time, increasing demands on the federal budget”including for weapons
for other services”suggest such growth in shipbuilding funds may not
materialize. The Navy‘s own ability to control the demand for
shipbuilding funds is also a challenge. If the Navy cannot control cost
growth on new ships, some other objectives of the plan will have to be
sacrificed, such as mission capability or presence.
There are several ways the Navy can help reduce the tension between the
demand for and supply of shipbuilding funds. To control unanticipated
cost growth on individual programs, it is important that the Navy
ensure programs have sufficiently high levels of knowledge before
making programmatic, budgetary, or contractual commitments. To maximize
the amount of funds the Navy can devote within its budget to
shipbuilding, it must continue to find ways to lower total ownership
costs by reducing manning requirements and to improve operational
availability of ships through means such as rotational crewing.
www.gao.gov/cgi-bin/getrpt?GAO-06-587T.
To view the full product, including the scope and methodology, click on
the link above. For more information, contact Paul Francis at (202) 512-
4841 or francisp@gao.gov.
[End of section]
Mr. Chairman and Members of the Subcommittee:
I am pleased to be here today to discuss the Navy's long-range
shipbuilding plan. The plan lays out the Navy's approach to meeting its
future needs. If followed literally, the plan will be an expensive
undertaking that will require billions in new ship construction
funding. The feasibility of the plan depends on a number of factors,
including increasing the supply of shipbuilding funds while controlling
the demand for funds by individual programs.
Today I would like to discuss (1) the multiple objectives that the
Navy's long-range shipbuilding plan proposes to meet, (2) the
challenges that must be met to execute the plan, and (3) ways that the
Navy can reduce the tension between the demand and supply for
shipbuilding funds. Before discussing these issues, I want to recognize
the value of the Navy's having prepared the plan as requested by
Congress. I look at it as a vehicle for discussing and debating
strategic shipbuilding issues before embarking on individual programs.
This course is much preferable to pursuing individual programs without
a strategic direction in mind. Thus, the shipbuilding plan is not
something that should be used to polarize hardened positions, but
rather to permit an intelligent discussion that will make for better
decisions in the future.
Summary:
The Navy is embarking on an ambitious undertaking to develop, design,
and construct a number of new ship classes to support operations on,
under, and beyond the world's oceans. The Navy expects these vessels to
successfully execute missions in a variety of environments through use
of advanced technologies, while utilizing reduced crews and greater
automation to lower costs. The Navy also expects these vessels to be
constructed in quantities that sustain the industrial base and increase
the number of Navy ships. There is tension inherent among the multiple
objectives of the plan. For example, demanding mission requirements can
result in more costly ships that cannot be built in the numbers desired
for presence and shipyard workload. Requirements to reduce manning can
actually demand more automation and sophistication, which can translate
into higher acquisition cost. These tensions presage the potential
trade-offs that will likely have to be made. The key is to anticipate
and make trade-offs early in the context of the overall shipbuilding
strategy. If the Navy starts more programs than it can finish within
available resources, it may be forced to make trade-offs in the future
that it would not find acceptable today.
Assuming the long-range shipbuilding plan is consistent with national
military priorities, the main challenge in execution is keeping the
supply and demand for funds in a rational balance that does not overly
sacrifice one objective to meet another. The Navy plan requires more
funds than may reasonably be expected. Specifically the plan projects a
supply of shipbuilding funds that will double by 2011 and will stay at
high levels for years to follow. At the same time, increasing demands
stemming from other federal programs, ongoing military operations, and
acquisitions by the other services suggest such growth in shipbuilding
funds may not materialize. The Navy's own ability to control the demand
for shipbuilding funds is also a challenge. Cost growth has been
particularly high for first-in-class ships--on the order of 27 percent.
The shipbuilding plan calls for more than double the number of new ship
classes to start construction in the next 10 years, as compared with
the last 10 years. If the Navy cannot control cost growth on these new
ships, some other objectives of the plan will have to be sacrificed,
such as mission capability or numbers of ships, which could impact
presence and overall warfighting capabilities.
There are several ways the Navy can help reduce the tension between the
demand and supply of shipbuilding funds. To control unanticipated cost
growth on individual programs, it is important that the Navy ensure
programs have sufficiently high levels of knowledge before making
programmatic, budgetary, or contractual commitments. Good practices
along these lines include attaining requirements stability, technology
maturity, and design stability early in programs; gaining actual
experience with design before budgeting and contracting for
construction; contracting for the construction of the lead ship
separately from the construction of follow-on ships; and making better
use of tools such as cost performance reports. To maximize the amount
of funds the Navy can devote within its budget to shipbuilding, it must
continue to find ways to lower total ownership costs by reducing
manning requirements and to improve operational availability of ships
through means such as rotational crewing.
Shipbuilding Plan Proposes to Meet Multiple Objectives:
The Chief of Naval Operations recently released a long-range plan for
shipbuilding[Footnote 1] that encapsulates the Navy's vision of the
future naval force structure. This is an ambitious plan that proposes
to meet multiple objectives, including:
* building ships that support new missions,
* building more sophisticated ships to support existing missions,
* building workhorse ships like tugboats,
* increasing numbers of ships to improve presence and ability to carry
out missions,
* designing ships and operating concepts to reduce manning
requirements, and:
* devising construction workloads to stabilize the industrial base.
The plan would boost the number of ships in the Navy's inventory from
today's level of 281 to an average of about 309 ships through 2036--a
10 percent increase.[Footnote 2] The plan includes developing and
constructing a number of new ship classes to support the way the
service would like to operate in the future. New ships are proposed for
nearly every class, from improved aircraft carriers and submarines to
new types of surface combatants. The DD(X) destroyer is to provide
strike and volume fires with increased range and lethality. Seabasing
is to be facilitated by large deck, expeditionary warfare ships and
connectors, by future maritime prepositioning forces, and by a new
generation of combat logistics forces. Littoral combat ships are to
provide defenses against submarine, mine, and surface threats. Theater
ballistic missile defense technologies are to be employed on guided
missile destroyers and cruisers.
Many of these ships are expected to perform their missions with reduced
crew sizes that are to be achieved through increased automation. The
Navy also plans to change the way it deploys and structures its fleet
around the world by shifting to a greater presence in the Pacific and
employing rotational crewing strategies. The fleet is expected to have
the capacity to overmatch the nation's most capable adversaries, in all
waters, blue, green and brown.
In addition, the Navy's shipbuilding plan seeks to stabilize the
industrial base by providing predictable workloads for the shipyards.
The Navy has previously reported that a stable shipbuilding industry is
essential to meet requirements for an affordable and capable force
structure. Cost growth in any given shipbuilding program could result
in a fluctuation in the number of ships procured, leading to less work
in a particular yard and even cost growth in other shipbuilding
programs. We have reported, for example, that overhead costs for the
DDG 91 and DDG 92, two ships in the current class of destroyers,
increased as a result of the delay in signing the contract for the
DD(X). Similarly, the pace of the DD(X) detail design and construction
schedule has been dictated in part by the desire to avoid work gaps in
shipyards.
Laying out such a plan now is constructive because it can be seen as
the first stages of an investment strategy or portfolio for new ship
acquisitions. Without a plan to guide program choices, there is a risk
that individual programs will dictate the plan. A long-term plan, to
the extent that it is consistent with national military priorities and
is rationalized by reasonable resource expectations, can enable trade-
offs to be seen and addressed in advance, leading to better informed
choices now. Such a plan makes debate possible before irreversible
commitments are made.
There is an inherent tension among the multiple objectives of the plan,
which presage the potential trade-offs that will likely have to be
made. These are depicted in simple form in figure 1.
Figure 1: Multiple Objectives Embodied in the Navy Shipbuilding Plan:
[See PDF for image]
[End of figure]
The tensions between objectives can play out in several ways. If, for
example, a class of ship is expected to perform multiple challenging
missions, it will have sophisticated subsystems and costs will be high.
The cost of the ship may prevent its being built in desired numbers,
reducing presence and reducing work for the industrial base.
Requirements to reduce manning can actually add sophistication if
mission requirements are not reduced. To some extent, this has happened
with the DD(X) destroyer. Several years ago, it was anticipated that
the ship would cost about $1 billion, and 32 would be produced. Over
time, sophistication and cost of the ship grew as mission requirements
increased while manning levels lower than current destroyers were
maintained. Today, each DD(X) ship will cost an average of $3.2
billion, and no more than seven are anticipated.[Footnote 3] Presence
(in terms of quantity) was reduced; shipyard work was reduced; and
currently the program is looking at reducing some mission capacity to
control cost. Similarly, the cost of the Virginia class submarine has
precluded producing the volume originally anticipated. The key is to
anticipate and make trade-offs early in the context of the overall
shipbuilding strategy. Otherwise, the strategy will be the yield of the
individual ship programs--a suboptimal outcome.
Challenges Facing the Execution of the Navy's Plan:
Assuming the long-range shipbuilding plan is consistent with national
military priorities, the main challenge in execution is keeping the
supply and demand for funds in a rational balance that does not unduly
sacrifice one objective to meet another. Except for the savings the
Navy is able to generate from reductions in operation, support, and
personnel costs, as well as reductions in non-ship acquisitions, the
supply of funds will largely be beyond the Navy's control. The demand
for funds, on the other hand, is dictated mainly by the numbers and
cost of individual acquisition programs and should be a managed outcome
on the part of the Navy.
Challenge 1: Securing a Sufficient Supply of Funds for Shipbuilding:
The main risk in the Navy's shipbuilding plan is that it requires more
funds than may reasonably be expected. To support its plan, the Navy
depends on significant increases in funding for new ship construction.
The plan calls for shipbuilding funds to grow from $8.7 billion in
fiscal 2007 to $17.2 billion in fiscal 2011 and beyond that sustains
levels well above current funding. Should this funding fail to
materialize, whether due to other demands on the federal budget that
limit Navy funds or to overruns in other Navy programs, the
shipbuilding plan will not be executable and trade-offs will have to be
made.
When contemplating an increase in funding that almost doubles the
shipbuilding budget in the near future, it is important to keep in mind
that demands on federal discretionary funds, which include the Navy's
budget, are growing as well. Budget simulations show that the nation
faces a large and growing structural deficit due primarily to known
demographic trends and growing health care costs. In addition, current
military operations, such as those in Iraq and Afghanistan, put further
pressure on DOD's weapon system investments by accelerating the need
for replacement or refurbishment of existing weapons.
Within this context, the development and production of new weapon
systems remains one of the largest discretionary investments the
federal government makes. From 2001 to 2006, DOD has doubled its
planned investments in ongoing major weapons from $700 billion to $1.4
trillion. As shown in figure 1, DOD is planning to increase its
procurement budget from about $75 billion to about $100 billion (33
percent) over the next 5 years to accommodate these growing
investments.
Figure 2: Total Obligation Authority for Procurement (Dollars in Fiscal
Year 2006 Millions):
[See PDF for image]
[End of figure]
According to the shipbuilding plan, the Navy will have to find
substantial new funds at a time when the Army is planning to get
increased funds for its Future Combat System and the Air Force plans to
purchase F-22A Raptors and Joint Strike Fighters. Given the increased
funding needed to cover the systems already underway and the
competition for funds beyond the acquisition of systems, it will be
very difficult for the Navy to secure the kinds of increases it needs
to afford the long-range shipbuilding program.
Challenge 2: Controlling the Demand for Funds in Individual
Shipbuilding Programs:
Cost growth has been a long-standing problem for all types of weapon
systems. For an individual program, cost growth represents additional
and unanticipated demand for more funds. If more funds are not
available, quantities to the warfighter are reduced and buying power is
sacrificed. Shipbuilding programs, like other systems, have experienced
cost growth. Cost growth has been particularly high on first-of-class
ships. In the last 10 years, only a few first-of-class ships have been
built. However, based on the long-range plan, the number of first-of-
class ships will more than double in the next 10 years. If the Navy
cannot control cost growth on these new ships, some other objectives of
the plan would have to be sacrificed, such as mission capability or
presence.
Recent shipbuilding outcomes suggest that cost growth continues to be a
problem for the Navy, particularly on the lead ship(s) of a new class.
(See table 1.)
Table 1: Cost Growth in Lead Ships (Dollars in Millions):
[See PDF for image]
[A] Estimated cost from the President's budget submission for year of
ship authorization.
[B] Includes all prior year requests through fiscal year 2007.
[C] SSN 775 is the second Virginia class submarine, but will be the
first hull delivered by Northrop Grumman Newport News shipyard.
[End of table]
For example, the first-in-class USS San Antonio (LPD 17), commissioned
in January 2006, experienced cost growth of $804 million above its
initial budget--an increase of 84 percent. The budgets for the new
attack submarines, USS Virginia (SSN 774) and Texas (SSN 775), have
grown by $492 million and $523 million, respectively, requiring
Congress to appropriate additional funds to cover these increases. It
is not only the first ship in the class that is at risk for cost
growth; the second ship, if it is assembled in a different shipyard, is
at risk as well. This was the case with the SSN 775. Devoting resources
to support completion of prior year shipbuilding programs reduces the
buying power of the Navy's budget for construction and can slow the
pace of modernization. The Navy is in its early stages of procuring a
number of advanced, new ship classes, including the DD(X) destroyer,
CVN 21 aircraft carrier, and the Littoral Combat Ship. Their actual
costs have yet to be realized.
The Navy's long-term shipbuilding plan envisions procuring several new
classes of ships to meet force structure needs. In fact, the Navy plans
to more than double its new class construction programs over the next
10 years. (See fig. 3.)
Figure 3: Schedule for Construction of New Lead Ships:
[See PDF for image]
* Dates beyond fiscal year 2011 are notional.
[End of figure]
The financial strain of starting so many new ship programs may be
unprecedented in post-World War II times. Successful development,
design, and construction of these new classes will be predicated on the
Navy's ability to break past patterns of cost growth. Otherwise, the
Navy could be forced to divert funding from planned ship classes to
cover cost overruns on its current programs. If the Navy starts more
programs than it can finish within available resources, it may be
forced to make trade-offs in the future that it would not find
acceptable today.
Better Management of Acquisitions Can Help Reduce Unanticipated Demands
for More Funds:
There are several steps the Navy can take to help control unanticipated
cost growth on individual programs. Primarily, these steps involve
having sufficiently high levels of knowledge before making
programmatic, budgetary, or contractual commitments. These measures
include:
* attaining requirements stability, technology maturity, and design
stability early in programs;
* gaining actual experience with design before budgeting and
contracting for construction;
* contracting the construction of the lead ship separately from the
construction of follow-on ships; and:
* employing good cost-estimating techniques and making better use of
cost reports.
Implementing a Knowledge-Based Acquisition Process Can Reduce the Risk
of Cost Growth in Shipbuilding Programs:
A first step in stemming unanticipated cost growth is for the Navy to
follow a knowledge-based acquisition approach for its new shipbuilding
programs. Over the last several years, we have undertaken a body of
work that examines weapon acquisitions by drawing upon lessons learned
from best product development practices in both the private sector and
DOD. Collectively, best practices comprise a process that ensures a
high level of knowledge at key program decision points. Central to
successful outcomes is the separation of technology development and
product development. The process of developing technology is one of
discovery and must allow room for unexpected failures that could result
in delays. The process of developing a product culminates in delivery
and depends on specific knowledge about a new product to stabilize
design and plan for production. Similarly, it is important to stabilize
design before production to avoid rework and resequencing of work,
which ultimately results in cost growth and schedule delays.
Matching Customer Needs and Developer Resources Early Is Key to a
Knowledge-Based Approach:
One of the most important practices in reaching a match between
resources and requirements is achieving a high level of technology
maturity at the start of system development. This improves the ability
to establish realistic cost, schedule, and performance objectives as
well as the ability to meet them. We believe that in shipbuilding,
technology maturity should be reached by the preliminary design review.
This assures that the form, fit, and function of the individual
components of a vessel are understood before they become integrated in
a system design. Including immature technologies in the system design
increases the risk of discovering problems late and can increase the
cost and time needed to complete design and fabrication.
The match between resources and requirements can be achieved in several
ways. The Littoral Combat Ship provides one way. Rather than attempting
to achieve full capability in a single leap, the program is structured
to deliver incremental capabilities to the warfighter through
evolutionary acquisition. Evolutionary acquisition has the potential to
reduce cycle times and costs by enabling developers to rely more on
available resources rather than making promises about unproven
technologies. The CVN-21 carrier program provides a different way to
get the match. One critical technology that the Navy wants to
incorporate on the new carrier is the electromagnetic aircraft
launching system. Since this system affects the design of the ship, the
Navy is spending a lot of time and money to demonstrate this key
technology before committing to the ship's design. The DD(X) program is
somewhere in between. It has a rational approach to maturing 12
critical technologies through demonstration models, but these were not
complete before the detail design phase began, and thus the DD(X)
program carry technical risk into that phase.
We have found that it is essential that at program start, a match must
be made between the customer's requirements and the product developer's
available resources in terms of knowledge, time, money, and capacity.
One fundamental is a balanced set of requirements that takes into
account not only a desire for sizeable gains in performance, but also
the resources--technology, time, and money--that are available to
execute the program.
Early Stabilization of Design Can Reduce Expensive Rework and
Resequencing of Work:
Another key knowledge-based practice is achieving a stable product
design at the system-level design readiness review. According to Navy
and contractor officials, design stability in shipbuilding is achieved
through completion of general arrangement drawings, ship
specifications, and major equipment lists. Attaining design stability
on time can help assure that a product will meet customer requirements
as well as cost and schedule targets. Programs that have entered
construction before achieving stable system designs did experience
significant cost growth. The lack of design maturity in these programs
led to rework and resequencing of work, increasing the number of labor
hours needed for ship construction. For example, in the LPD 17 program,
ship design continued to evolve even as construction proceeded. Without
a stable design, outfitting work for individual ship sections was often
delayed from early in the building cycle to later, when these sections
were integrated on the hull. Shipbuilders stated that doing the work at
this stage could cost up to five times the original cost. On LPD 17,
1.3 million labor hours were deferred from the build phase to the
integration phase. Consequently, LPD 17 took much longer to construct
and cost more than originally estimated.
Individual Ship Strategies Align Knowledge and Decision Points
Differently:
While shipbuilding programs may differ in the specific knowledge that
must be gained to reduce risk, the order and timing in which such
knowledge must be achieved should not vary. Technology maturity must be
proven before a design can be considered stable, and production
outcomes cannot be guaranteed until a stable design is demonstrated.
Similarly, this knowledge should correspond with and inform key
decisions in a program. For example, in programs other than
shipbuilding, the Milestone B decision represents the commitment to
design and develop a system for production, at which time requirements
should be firm and critical technologies mature.
However, each shipbuilding program seems to embody its own strategy for
making decisions that vary from program to program. Milestone B means
different things in different shipbuilding programs. In the DD(X)
program, negotiation of a construction contract was authorized at
Milestone B, which was held shortly after the critical design review.
The CVN-21 program plans to gain approval to negotiate construction of
the first ship at a major program review held over 2 years after
Milestone B decision. In yet another approach, the Littoral Combat Ship
began construction of its first vessels about 2 years before its
scheduled Milestone B decision. This inconsistency in both decision
points and knowledge gained makes it difficult to gauge whether an
individual program is attaining sufficient levels of knowledge at the
right points in time.
Practices for Estimating Costs, Budgeting, and Contracting Can Make
Funding Demands More Realistic:
The Navy can take steps to more realistically provide the funds needed
to execute individual programs. These include some methodological
practices for cost estimates and better alignment of budgeting and
contracting commitments with requisite levels of knowledge. The Navy
has begun implementing some of these practices, but more can be done.
Cost Estimating and Reporting:
In our analysis of shipbuilding programs last year, we found that the
Navy tended to underestimate the costs needed to construct ships--which
resulted in large cost increases after ship construction began. One way
to improve the quality of cost estimates and reduce the magnitude of
unbudgeted cost growth is to present a confidence level for a cost
estimate based on risk and uncertainty analyses. By conducting
uncertainty analyses that measure the probability of cost growth, the
Navy can identify a level of confidence for its cost estimates. The
Navy can then make better-informed budget decisions on whether to
proceed with a program.
The Navy has begun taking some action to improve its cost estimating
capabilities, including the use of quantitative risk analysis in
generating shipbuilding cost estimates. For example, the Navy did
conduct an uncertainty analysis for the DD(X) cost estimate. The
analysis showed the current estimate to have a confidence level of 45
percent, meaning that the program has a 45 percent chance of achieving
its estimated cost. This represents a positive step in creating more
transparent cost estimates. We believe that the Navy and DOD should go
on to establish an acceptably high confidence level on which to base
more realistic program commitments and budget requests. Recently, the
Defense Acquisition Performance Assessment panel recommended that an 80
percent confidence level is necessary to ensure realism in a budget
request.
The Navy can also use contractor cost performance reports more
effectively. With the significant risk of cost growth in shipbuilding
programs, it is important that the Navy receive timely and complete
cost performance reports to allow it to take corrective actions more
quickly. DOD recently issued changes to its earned value management
policy requiring contract performance reports to be submitted no less
than monthly. Monthly cost performance reports can help improve the
Navy's ability to mitigate risk on ships currently under construction.
Although the Navy will implement this policy on future contracts, it
stated that it will not apply monthly reporting requirements
retroactively. As a result, current programs such as the Virginia class
submarine, which continues to experience high cost growth, will only
receive cost performance reports on a quarterly basis--slowing the
Navy's ability to take corrective action against negative cost and
performance trends.
Budgeting and Contracting:
The Navy can better ensure realism in its budgets and contracts by
separating requests for funding detail design from construction.
Generally, the Navy has requested authorization for both detail design
and construction of the lead ship in a single budget year, before
research and development have been completed and an independent cost
estimate developed. Contract prices are often negotiated for
constructing the lead ship and early follow-on ships before detail
design has even begun. In our February 2005 report, we recommended that
the Navy allow time to gain knowledge from detail design before
negotiating contract prices for the construction of the lead ship and
time to gain knowledge from the lead ship before negotiating contracts
for follow-on ships. This would enable knowledge and experience to be
gained with the design before locking in budget requests and
contractual commitments.
Budget requests for DD(X) illustrate the problems with requesting
funding early, when uncertainty about costs is high. The Navy first
requested funding for detail design and construction of the lead ship
in February 2004 as part of its fiscal year 2005 budget request.
According to the Navy's budget presentation, detail design and
construction would cost $2.7 billion. The Congress did not fund
construction of the lead ship but instead provided funding for detail
design and some materials in the fiscal years 2005 and 2006 budgets. In
March 2005, the Navy completed a detailed life-cycle cost estimate for
DD(X) that placed the cost of DD(X) at $3.3 billion. The independent
cost estimate placed the cost even higher. The budget request for
fiscal year 2007 now includes $3.3 billion for each of the two lead
ships. Though the accuracy of this estimate is still being debated, it
is clearly more realistic than the budget estimates of 2 years ago.
The same logic applies to contracting for follow-on ships. Early
negotiation of follow-on ship contracts can also affect the realism of
program cost estimates and budget requests to fund these contracts.
Experience has shown the difficulty in delivering the lead ship of a
class within estimates. Negotiating contracts for follow-on ships at
the same time as the lead ship extends the estimating weaknesses to
those ships as well. The result is unbudgeted demands for increased
funds. While the Navy maintains that this practice can give the
government some leverage in negotiating prices, a possible advantage
only exists in the case of ships acquired under fixed-price contracts-
-a rare occurrence for new ship classes.
Savings in Long-Term Operations and Maintenance Costs are Needed to
Free Funds for Shipbuilding:
The Navy's efforts to control personnel costs and minimize total
ownership costs have been important in their own right. Today, these
efforts are becoming increasingly important because the savings they
produce are one source of the increased funding sought for the Navy's
long-range shipbuilding plan.
Optimizing Ship Crew Size Can Reduce Total Ownership Costs:
The ship's crew is the single largest cost incurred over the ship's
life cycle. One way to lower personnel costs is to use a systems-
engineering approach called human systems integration to optimize crew
size. This is particularly important in the early phases of a ship
program as total ownership costs are largely determined during a ship's
design. (See fig. 4.)
Figure 4: Total Ownership Costs Are Determined Early in a System's
Development:
[See PDF for image]
[End of figure]
Applying human systems integration principles to optimize crew size has
the potential to yield substantial cost and operational benefits,
including saving billions of dollars by reducing total ownership costs
and increasing operational performance and ship maintainability.
We have reported that the Navy has not consistently optimized ship crew
size.[Footnote 4] For example, we calculated that a nominal 25 percent
reduction in a large deck amphibious ship such as the LHA(R) with a
1,245-person crew could provide a personnel cost avoidance of nearly $1
billion over the service life of a ship.[Footnote 5] However, the
LHA(R) program did not establish a crew reduction requirement. As a
result it is unlikely to achieve a meaningful reduction in crew size.
The DD(X) destroyer program is an example of how requiring human
systems integration early, establishing a crew size reduction
requirement as part of the design, and holding program managers
accountable can create significant progress toward reducing crew size.
While actual reductions remain to be seen, currently, the crew size for
the DD(X) is estimated at 150, compared with 382 for the current DDG 51
class destroyer.
Increasing Operational Availability:
The Navy has developed and implemented several initiatives to increase
the operational availability of Navy and Marine Corps fleet forces,
including the Fleet Response Plan and rotational crewing. Navy
officials have cited these initiatives as ways to increase readiness
and reduce the numbers of ships needed in the Navy's force structure,
thereby freeing funding for other priorities. The Fleet Response Plan
modifies the Navy's pre-2001 rotational deployment policy, replacing 6-
month routine deployments with more flexible deployment options for as
many as eight carrier strike groups when and where needed. The Navy has
also demonstrated that rotating crews aboard surface ships on extended
deployments may be a feasible alternative to traditional 6-month ship
deployments. According to the 2006 Quadrennial Defense Review Report,
the Fleet Response Plan has increased the amount of time a ship or
other naval unit is fully ready to deploy, and rotational crewing has
further increased the operational availability of forces by up to 33
percent.
These are positive results for which the Navy deserves credit. As the
Navy extends these initiatives to more ships, we have recommended steps
it can take to get maximum return on investment and offset billions of
dollars in future total ownership costs. These include establishing an
analytical framework--consisting of formal measurable goals,
objectives, and metrics--that could be used to assess the feasibility
of operational availability initiatives and determine their impact on
operational requirements, ship condition, and crew morale.[Footnote 6]
In the past, the Navy had not systematically collected or developed
accurate cost data to perform complete cost-effectiveness analysis. We
believe that the Navy needs to more systematically collect data on
current and potential operational availability initiatives, including
complete and accurate cost data for cost-effectiveness analyses. This
will facilitate informed decisions about the potential for applying
these initiatives to current and future ships.
Mr. Chairman this concludes my statement and I would be pleased to
answer any questions.
Objectives, Scope, and Methodology:
To develop information on obstacles for the Navy's long-term
shipbuilding strategy and practices for improving the acquisition of
programs that make up that strategy, we relied largely on work
previously performed for a number of related GAO products as well as
the Navy's planning documents and testimony. In the course of our
previous work we analyzed the documentation of and interviewed
officials associated with a number of shipbuilding programs including
CVN-21, DD(X), and the Littoral Combat Ship. In our past work on
analyzing cost growth in shipbuilding, we reviewed cost performance and
earned value data on a number of ships then in construction, as well as
applicable Navy acquisition guidance. In addition, we interviewed
officials with the Navy and Office of Secretary of Defense with
oversight of cost estimating and contract execution. To supplement work
previously performed we analyzed the Navy's most recent long-term plan
for shipbuilding and updated some figures on cost estimates through use
of the Navy's budget justification documentation.
Contact and Staff Acknowledgments:
For future questions about this statement, please contact me at (202)
512-4841. Individuals making key contributions to this statement
include Robert L. Ackley, Christina Connelly, Ryan Consaul, Diana
Dinkelacker, Christopher R. Durbin, J. Kristopher Keener, Patricia W.
Lentini, Roderick W. Rodgers, Janet St. Laurent, Martin G. Campbell,
and Karen Zuckerstein.
Related GAO Products:
Military Readiness: Navy's Fleet Response Plan Would Benefit from a
Comprehensive Management Approach and Rigorous Testing. GAO-06-84,
Washington, D.C.: Nov. 22, 2005.
Defense Acquisitions: Progress and Challenges Facing the DD(X) Surface
Combatant Program. GAO-05-924T, Washington, D.C.: July 19, 2005.
Defense Acquisitions: Assessments of Selected Major Weapon Programs.
GAO-05-301, Washington, D.C.: March 31, 2005.
Defense Acquisitions: Plans Need to Allow Enough Time to Demonstrate
Capability of First Littoral Combat Ships. GAO-05-255, Washington,
D.C.: March 1, 2005.
Defense Acquisitions: Improved Management Practices Could Help Minimize
Cost Growth in Navy Shipbuilding Programs. GAO-05-183, Washington,
D.C.: Feb. 28, 2005.
Force Structure: Navy Needs to Fully Evaluate Options and Provide
Standard Guidance for Implementing Surface Ship Rotational Crewing. GAO-
05-10, Washington, D.C.: Nov. 10, 2004.
Military Personnel: Navy Actions Needed to Optimize Ship Crew Size and
Reduce Total Ownership Costs. GAO-03-520, Washington, D.C.: June 9,
2003.
FOOTNOTES
[1] Report to Congress on Annual Long-Range Plan for Construction of
Naval Vessels for FY 2007.
[2] According to the Navy's plan the naval ship inventory would
increase to 315 by 2012, peak at 330 in 2019, and decline slowly to 296
by 2036.
[3] According to the Navy's November 2005 Acquisition Program Baseline
for the DD(X) program, program acquisition unit cost (PAUC) is
$3,154.79 million. PAUC is calculated by dividing program acquisition
cost, including research and development funding, by the program
acquisition quantity.
[4] See GAO, Military Personnel: Navy Actions Needed to Optimize Ship
Crew Size and Reduce Total Ownership Costs, GAO-03-520 (Washington,
D.C.: June 9, 2003).
[5] Fiscal year 2002 dollars.
[6] See GAO, Force Structure: Navy Needs to Fully Evaluate Options and
Provide Standard Guidance for Implementing Surface Ship Rotational
Crewing, GAO-05-10 (Washington, D.C.: Nov. 10, 2004); GAO, Military
Readiness: Navy's Fleet Response Plan Would Benefit from a
Comprehensive Management Approach and Rigorous Testing, GAO-06-84
(Washington, D.C.: Nov. 22, 2005).