Coast Guard
Action Needed as Approved Deepwater Program Remains Unachievable
Gao ID: GAO-12-101T October 4, 2011
This testimony discusses our recent work on the Coast Guard's Deepwater acquisition, which represents the majority of the Coast Guard's efforts to recapitalize its fleet of vessels and aircraft. This statement is based on our July 28, 2011, report, Coast Guard: Action Needed as Approved Deepwater Program Remains Unachievable. This report discusses areas in which the Coast Guard has strengthened its acquisition management capabilities but also emphasizes actions the Coast Guard needs to take to address the cost growth, schedule delays, and capability shortfalls that have made the approved Deepwater Program unachievable. Today's climate of rapidly building fiscal pressures underscores the importance of assessing priorities--from a Coast Guard-wide perspective--so that more realistic budgets can be submitted to Congress. Such a step would help alleviate what has become a pattern of churn in revising program baselines when unrealistic planned funding does not materialize, which contributes to schedule delays and can lead to other issues such as unhealthy competition for funding. We also recognize several steps that the Coast Guard has taken to improve the management of the Deepwater Program. For example, the Coast Guard has updated its Major Systems Acquisition Manual to better reflect best practices and has significantly reduced its relationship with the prior lead systems integrator, Integrated Coast Guard Systems, by awarding fixed-price contracts outside of the prior construct. To continue this improvement, our July 2011 report made several recommendations with which the Department of Homeland Security (DHS) concurred. We have reviewed the Coast Guard's recapitalization efforts since 2001 and have built an extensive body of work over the last 10 years that has focused on the need for the Coast Guard to improve its acquisition workforce, contractor management, and oversight capability. For the July 2011 report, we assessed (1) the extent to which the Deepwater Program's planned cost and schedule baselines have been exceeded and the credibility of cost estimates and schedules for selected assets; (2) the progression of the execution, design, and testing of the assets within the Deepwater Program; and (3) whether the Coast Guard has undertaken a fleet mix study that addresses trade-offs in a cost-constrained environment.
The Deepwater Program continues to exceed the cost and schedule baselines approved by DHS in 2007, but we found that several factors preclude a solid understanding of the true cost and schedule of the program. Based upon approved baselines, as of May 2011, the total Deepwater Program could cost as much as $29.3 billion, an increase of more than 20 percent in 4 years. This $29.3 billion includes the latest revised baseline for assets that have updated cost and schedule estimates since the 2007 baseline. As we reported last year, these revised baselines reflect the Coast Guard's and DHS's efforts to understand acquisition costs of Deepwater vessels and aircraft and to gain insight into the drivers of the cost growth. However, additional cost growth is looming because the Coast Guard has yet to develop revised baselines for all assets, including the Offshore Patrol Cutter--the largest cost driver in the program, comprising approximately $8 billion of the $24.2 billion 2007 baseline. In addition, Coast Guard officials stated that some of the more recently approved acquisition program baselines fall short of true funding needs. This not only exacerbates the uncertainty surrounding the total cost of the Deepwater acquisition, but also contributes to the approved Deepwater Program no longer being achievable. In addition to cost growth, forthcoming delays identified in the Coast Guard's fiscal years 2012-2016 capital investment plan indicate that the final asset delivery dates approved in the 2007 Deepwater baseline and some of the revised baselines are no longer achievable for most assets. Coast Guard-wide support is required to fully plan, present, and fund an achievable program. In October 2010, the Assistant Coast Guard Commandant for Acquisition identified the need to develop and implement effective decision making to maximize results and manage risks within resource constraints. Action items to accomplish this are laid out in the Acquisition Directorate's Blueprint for Continuous Improvement (Blueprint), which was signed by the Commandant. Acquisition officials responsible for implementing the Blueprint action items acknowledged that successful implementation requires buy-in from leadership. However, senior Coast Guard budget officials responsible for capital investment planning told us that they are not held responsible for accomplishing the objectives outlined in the Blueprint. In July 2010, we recommended that the Coast Guard complete, and present to Congress, a comprehensive review of the Deepwater Program. Specifically, we recommended that the review clarify the overall cost, schedule, quantities, and mix of assets required to meet mission needs, including trade-offs in light of fiscal constraints, given that the currently approved Deepwater baseline was no longer feasible. The Coast Guard's efforts, as of July 2011, have not addressed this recommendation. To support its role as systems integrator, the Coast Guard planned to complete a fleet mix analysis in July 2009 to eliminate uncertainty surrounding future mission performance and to produce a baseline for the Deepwater acquisition. However, the first phase of the Coast Guard's analysis, completed in December 2009 and termed fleet mix analysis phase 1, was not cost-constrained and is, according to Coast Guard officials, not feasible.
GAO-12-101T, Coast Guard: Action Needed as Approved Deepwater Program Remains Unachievable
This is the accessible text file for GAO report number GAO-12-101T
entitled 'Coast Guard: Action Needed as Approved Deepwater Program
Remains Unachievable' which was released on October 4, 2011.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
United States Government Accountability Office:
GAO:
Testimony:
Before the Subcommittee on Coast Guard and Maritime Transportation,
Committee on Transportation and Infrastructure, House of
Representatives:
For Release on Delivery:
Expected at 10:30 a.m. EDT:
Tuesday, October 4, 2011:
Coast Guard:
Action Needed as Approved Deepwater Program Remains Unachievable:
Statement of John P. Hutton:
Director, Acquisition and Sourcing Management:
GAO-12-101T:
Chairman LoBiondo, Ranking Member Larsen, and Members of the
Subcommittee:
I am pleased to be here today to discuss our recent work on the Coast
Guard's Deepwater acquisition, which represents the majority of the
Coast Guard's efforts to recapitalize its fleet of vessels and
aircraft.[Footnote 1] My statement today is based on our July 28,
2011, report, Coast Guard: Action Needed as Approved Deepwater Program
Remains Unachievable.[Footnote 2] This report discusses areas in which
the Coast Guard has strengthened its acquisition management
capabilities but also emphasizes actions the Coast Guard needs to take
to address the cost growth, schedule delays, and capability shortfalls
that have made the approved Deepwater Program unachievable. Today's
climate of rapidly building fiscal pressures underscores the
importance of assessing priorities--from a Coast Guard-wide
perspective--so that more realistic budgets can be submitted to
Congress. Such a step would help alleviate what has become a pattern
of churn in revising program baselines when unrealistic planned
funding does not materialize, which contributes to schedule delays and
can lead to other issues such as unhealthy competition for funding. We
also recognize several steps that the Coast Guard has taken to improve
the management of the Deepwater Program. For example, the Coast Guard
has updated its Major Systems Acquisition Manual to better reflect
best practices and has significantly reduced its relationship with the
prior lead systems integrator, Integrated Coast Guard Systems, by
awarding fixed-price contracts outside of the prior construct. To
continue this improvement, our July 2011 report made several
recommendations with which the Department of Homeland Security (DHS)
concurred.
We have reviewed the Coast Guard's recapitalization efforts since 2001
and have built an extensive body of work over the last 10 years that
has focused on the need for the Coast Guard to improve its acquisition
workforce, contractor management, and oversight capability. For the
July 2011 report, we assessed (1) the extent to which the Deepwater
Program's planned cost and schedule baselines have been exceeded and
the credibility of cost estimates and schedules for selected assets;
(2) the progression of the execution, design, and testing of the
assets within the Deepwater Program; and (3) whether the Coast Guard
has undertaken a fleet mix study that addresses trade-offs in a cost-
constrained environment. To conduct our work, we reviewed the Coast
Guard's Major Systems Acquisition Manual, budget documents, and key
asset documents including operational requirements documents,
acquisition strategies and plans, acquisition program baselines, life-
cycle cost estimates, test reports, and contracts. We interviewed
Coast Guard and DHS officials responsible for the Coast Guard's
acquisitions, budgeting and resources for Deepwater, testing assets,
and developing operational requirements. Our work for the July 28,
2011, report was conducted from September 2010 through July 2011 in
accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient and appropriate evidence to provide a reasonable basis for
our findings and conclusions based on our audit objectives. We believe
that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives.
True Cost and Schedule for the Deepwater Program Are Not Known, Cost
Increases and Delays Are Looming, and Budget Planning Exacerbates
Program Uncertainties:
The Deepwater Program continues to exceed the cost and schedule
baselines approved by DHS in 2007, but we found that several factors
preclude a solid understanding of the true cost and schedule of the
program. Based upon approved baselines, as of May 2011, the total
Deepwater Program could cost as much as $29.3 billion, an increase of
more than 20 percent in 4 years. This $29.3 billion includes the
latest revised baseline for assets that have updated cost and schedule
estimates since the 2007 baseline. As we reported last year, these
revised baselines reflect the Coast Guard's and DHS's efforts to
understand acquisition costs of Deepwater vessels and aircraft and to
gain insight into the drivers of the cost growth[Footnote 3]. However,
additional cost growth is looming because the Coast Guard has yet to
develop revised baselines for all assets, including the Offshore
Patrol Cutter--the largest cost driver in the program, comprising
approximately $8 billion of the $24.2 billion 2007 baseline. In
addition, Coast Guard officials stated that some of the more recently
approved acquisition program baselines fall short of true funding
needs. This not only exacerbates the uncertainty surrounding the total
cost of the Deepwater acquisition, but also contributes to the
approved Deepwater Program no longer being achievable. For example,
the National Security Cutter baseline, as revised in December 2008,
reflects a total acquisition cost of $4.7 billion.[Footnote 4]
However, our review of more recent Coast Guard documentation
demonstrates that an estimated $5.6 billion is required to complete
the planned acquisition of eight National Security Cutters--an
approximately 19 percent growth over the approved 2008 revised
estimate.
In addition to cost growth, forthcoming delays identified in the Coast
Guard's fiscal years 2012-2016 capital investment plan indicate that
the final asset delivery dates approved in the 2007 Deepwater baseline
and some of the revised baselines are no longer achievable for most
assets.[Footnote 5] Figure 1 shows delays in final asset delivery
dates according to (1) the 2007 baseline, (2) the asset's revised
baseline, and (3) the fiscal years 2012-2016 capital investment plan
submitted to Congress.
Figure 1: Final Asset Delivery Dates for Selected Deepwater Assets
Identified in the 2007 Deepwater Baseline, Revised Baselines, and
Fiscal Years 2012-2016 Capital Investment Plan:
[Refer to PDF for image: illustrated table]
Asset: National Security Cutter:
Fiscal year 2014: 2007 Deepwater baseline;
Fiscal year 2016: Revised baseline;
Fiscal year 2018: FY 2012 – 2016 Capital Investment Plan;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: 4 years.
Asset: Fast Response Cutter[B]:
Fiscal year 2016: 2007 Deepwater baseline;
Fiscal year 2021: Revised baseline;
Fiscal year 2022: FY 2012 – 2016 Capital Investment Plan;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: 6 years.
Asset: Medium Endurance Cutter Sustainment:
Fiscal year 2014: FY 2012 – 2016 Capital Investment Plan;
Fiscal year 2016: 2007 Deepwater baseline;
Fiscal year 2017: Revised baseline;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: (2 years).
Asset: Patrol Boat Sustainment:
Fiscal year 2013: 2007 Deepwater baseline;
Fiscal year 2014: Revised baseline;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: N/A.
Asset: Maritime Patrol Aircraft:
Fiscal year 2016: 2007 Deepwater baseline;
Fiscal year 2020: Revised baseline;
Fiscal year 2025: FY 2012 – 2016 Capital Investment Plan;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: 9 years.
Asset: HC-130J:
Fiscal year 2009: 2007 Deepwater baseline;
Fiscal year 2011: Revised baseline; FY 2012 – 2016 Capital Investment
Plan;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: 2 years.
Asset: HC-130H:
Fiscal year 2017: 2007 Deepwater baseline; Revised baseline;
Fiscal year 2022: FY 2012 – 2016 Capital Investment Plan;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: 5 years.
Asset: HH-65:
Fiscal year 2013: 2007 Deepwater baseline;
Fiscal year 2020: Revised baseline; FY 2012 – 2016 Capital Investment
Plan;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: 7 years.
Asset: HH-60:
Fiscal year 2019: 2007 Deepwater baseline;
Fiscal year 2020: Revised baseline; FY 2012 – 2016 Capital Investment
Plan;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: 1 year.
Asset: C4ISR:
Fiscal year 2014: 2007 Deepwater baseline;
Fiscal year 2025: FY 2012 – 2016 Capital Investment Plan;
Fiscal year 2027: Revised baseline;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: 11 years.
Asset: Offshore Patrol Cutter:
Fiscal year 2021: 2007 Deepwater baseline;
Fiscal year 2031: FY 2012 – 2016 Capital Investment Plan;
Change from 2007 baseline to FY 2012 – 2016 Capital Investment
Plan[A]: 10 years.
Source: GAO analysis of Coast Guard data.
[A] To calculate the change from the final asset delivery date
reported in the 2007 Deepwater baseline to the final asset delivery
date reported in fiscal years 2012-2016 capital investment plan, we
used the first month of each fiscal year. If the approved baselines
provide both threshold and objective dates, threshold dates (which are
the latest allowable dates) are used.
[B] In the 2007 baseline, costs for two variants of the Fast Response
Cutter were presented. For the 2007 baseline we used the last date
reported for final asset delivery.
[End of figure]
Delays in fielding new Deepwater assets increase the stress on the
Coast Guard's aging fleet. For example, to keep the legacy cutters in
service longer than expected requires costly maintenance and the
understanding that these aging cutters will not be able to fully
perform all types of missions. As a result, according to Coast Guard
headquarters officials, careful planning must occur to avoid placing a
cutter in an operational emergency where it is incapable of adequately
responding.[Footnote 6] We recently began a review of the status of
the Coast Guard's legacy vessel fleet.
Without cost and schedule estimates that are based on current and
reliable information, the Coast Guard has difficulty formulating
realistic budgets. The Coast Guard is currently managing an
acquisition portfolio that is expected to cost more than what its
annual budget will likely support. For example, Coast Guard
acquisition officials stated that up to $1.9 billion per year is
needed to support the approved Deepwater baselines, but these
officials expect Deepwater funding levels to be closer to $1.2 billion
annually over the next several years. Furthermore, the 2012-2016
capital investment plan demonstrates that the Coast Guard needs over
$2 billion in funding for Deepwater in fiscal year 2015--a greater
than 65 percent increase over the expected funding amount of $1.2
billion per year--to support the program as currently designed. When a
program's funding levels are lower than what the program was
previously projected to receive, the program can no longer remain on
the planned schedule. As a result, program baselines need to be
revised. For example, in September-October 2010, three of the projects
within the Deepwater Program, the C4ISR, HC-130H, and HH-60 projects,
reported potential baseline breaches due, in part, to reduced funding
in the fiscal years 2011-2015 capital investment plan.
Coast Guard-wide support is required to fully plan, present, and fund
an achievable program. In October 2010, the Assistant Coast Guard
Commandant for Acquisition identified the need to develop and
implement effective decision making to maximize results and manage
risks within resource constraints. Action items to accomplish this are
laid out in the Acquisition Directorate's Blueprint for Continuous
Improvement (Blueprint), which was signed by the Commandant.
Acquisition officials responsible for implementing the Blueprint
action items acknowledged that successful implementation requires buy-
in from leadership. However, senior Coast Guard budget officials
responsible for capital investment planning told us that they are not
held responsible for accomplishing the objectives outlined in the
Blueprint. And while DHS and the Coast Guard concurred with our
recommendation that the Coast Guard should adopt the Blueprint action
items, DHS stated that the Coast Guard's resource governance process
balances the agency's resource priorities across acquisition and front-
line operations and makes trade-offs. We recognize that part of the
standard budget development process includes trade-off decisions.
However, under this standard process, DHS and the Coast Guard have
continued to face the problem of approved acquisition programs not
being feasible.
Coast Guard Has Not Completed a Comprehensive Trade-off Analysis for
Deepwater Assets:
In July 2010, we recommended that the Coast Guard complete, and
present to Congress, a comprehensive review of the Deepwater Program.
Specifically, we recommended that the review clarify the overall cost,
schedule, quantities, and mix of assets required to meet mission
needs, including trade-offs in light of fiscal constraints, given that
the currently approved Deepwater baseline was no longer feasible.
[Footnote 7] The Coast Guard's efforts, as of July 2011, have not
addressed this recommendation. To support its role as systems
integrator, the Coast Guard planned to complete a fleet mix analysis
in July 2009 to eliminate uncertainty surrounding future mission
performance and to produce a baseline for the Deepwater acquisition.
However, the first phase of the Coast Guard's analysis, completed in
December 2009 and termed fleet mix analysis phase 1, was not cost-
constrained and is, according to Coast Guard officials, not feasible.
For example, the Coast Guard estimated the total acquisition costs
associated with the objective fleet mix could be as much as $65
billion--about $40 billion more than the $24.2 billion baseline
approved in 2007.
While the Coast Guard has since undertaken a second, cost-constrained,
phase of the fleet mix analysis, officials responsible for the
analysis stated that the study primarily assesses the rate at which
the Coast Guard could acquire the current Deepwater program of record.
As of September 2011, according to Coast Guard officials, phase 2 of
the fleet mix analysis has been finalized and is under review within
the Coast Guard. In addition to the Coast Guard's analysis, DHS's
Program Analysis & Evaluation office began a study to gain insight
into the Deepwater surface program of record. A DHS official involved
in the study stated that the analysis will examine performance trade-
offs between the National Security Cutter, Offshore Patrol Cutter, a
modernized 270' cutter, and the Navy's Littoral Combat Ship.[Footnote
8] According to DHS officials, the cutter study was provided to the
Office of Management and Budget in July 2011. From a broader
perspective, it is unclear how, or whether, DHS and the Coast Guard
will reconcile and use these studies to make trade-off decisions
regarding the Deepwater Program that balance effectiveness with
affordability.
Key Decisions Remain to Ensure That Promised Capabilities Are Achieved:
At the individual project level, knowledge-based decisions are needed
as Deepwater enters its fourth year with the Coast Guard as systems
integrator. Uncertainties about the information technology systems,
which were intended to make Deepwater a system of systems, continue
and are compounded as assets are designed and delivered without a
clear vision for the overall program. For example, it is unclear
whether or not full data sharing between assets remains a goal for the
Coast Guard. According to the Coast Guard's recent cost estimating
baseline document, only 127 air and surface assets--fewer than half of
the approximately 300 assets within the approved Deepwater Program--
will have information technology systems that enable full
communication as envisioned. Key decisions also remain in acquiring
the Offshore Patrol Cutter, even though DHS approved the requirements
document for this asset in October 2010. For example, as of July 2011,
the Coast Guard had yet to determine which information technology
system will be used for the cutter, whether it will have a facility
for processing classified information, and whether it will have air
search capabilities.
Summary of Actions We Recommended to DHS and Coast Guard:
In July 2011, we made a number of recommendations to DHS and the Coast
Guard, with which DHS concurred on behalf of the department and the
Coast Guard. For example, we recommended that directorates across the
Coast Guard should adopt action items consistent with those in the
Blueprint related to managing projects within resource constraints. We
also recommended that DHS develop a working group with Coast Guard
participation to review the results of the three studies to identify
cost, capability, and quantity trade-offs that would produce a program
that fits within expected budget parameters. Lastly, we made
recommendations to help ensure that assets meet mission needs. For
example, we made recommendations aimed at improving the affordability
and feasibility of the Offshore Patrol Cutter's requirements document
and increasing the confidence that the information technology system,
Maritime Patrol Aircraft, and cutter small boats will meet mission
needs. We will be following up on these recommendations with the Coast
Guard and DHS.
Chairman LoBiondo, Ranking Member Larsen, this concludes my prepared
statement. I would be pleased to respond to any questions you or other
Members of the Subcommittee may have.
GAO Contacts and Staff Acknowledgments:
For further information about this report, please contact John P.
Hutton, Director, Acquisition and Sourcing Management, at (202) 512-
4841 or huttonj@gao.gov. Other individuals making key contributions to
this report include Michele Mackin, Assistant Director; Molly Traci;
Jose Cardenas; Mya Dinh; Laurier Fish; Carlos Gomez; Kristine
Hassinger; and Rebecca Wilson.
[End of section]
Related Products:
Coast Guard: Action Needed as Approved Deepwater Program Remains
Unachievable. [hyperlink, http://www.gao.gov/products/GAO-11-743].
Washington, D.C.: July 28, 2011.
Coast Guard: Opportunities Exist to Further Improve Acquisition
Management Capabilities. [hyperlink,
http://www.gao.gov/products/GAO-11-480]. Washington, D.C.: April 13,
2011.
Coast Guard: Observations on Acquisition Management and Efforts to
Reassess the Deepwater Program. [hyperlink,
http://www.gao.gov/products/GAO-11-535T]. Washington, D.C.: April 13,
2011.
Coast Guard: Deepwater Requirements, Quantities, and Cost Require
Revalidation to Reflect Knowledge Gained. [hyperlink,
http://www.gao.gov/products/GAO-10-790]. Washington, D.C.: July 27,
2010.
Department of Homeland Security: Assessments of Selected Complex
Acquisitions. [hyperlink, http://www.gao.gov/products/GAO-10-588SP].
Washington, D.C.: June 30, 2010.
Coast Guard: Observations on the Requested Fiscal Year 2011 Budget,
Past Performance, and Current Challenges. [hyperlink,
http://www.gao.gov/products/GAO-10-411T]. Washington, D.C.: February
25, 2010.
Coast Guard: Better Logistics Planning Needed to Aid Operational
Decisions Related to the Deployment of the National Security Cutter
and Its Support Assets. [hyperlink,
http://www.gao.gov/products/GAO-09-497]. Washington, D.C.: July 17,
2009.
Coast Guard: As Deepwater Systems Integrator, Coast Guard Is
Reassessing Costs and Capabilities but Lags in Applying Its
Disciplined Acquisition Approach. [hyperlink,
http://www.gao.gov/products/GAO-09-682]. Washington, D.C.: July 14,
2009.
Coast Guard: Observations on Changes to Management and Oversight of
the Deepwater Program. [hyperlink,
http://www.gao.gov/products/GAO-09-462T]. Washington, D.C.: March 24,
2009.
Coast Guard: Change in Course Improves Deepwater Management and
Oversight, but Outcome Still Uncertain. [hyperlink,
http://www.gao.gov/products/GAO-08-745]. Washington, D.C.: June 24,
2008.
Status of Selected Assets of the Coast Guard's Deepwater Program.
[hyperlink, http://www.gao.gov/products/GAO-08-270R]. Washington,
D.C.: March 11, 2008.
Coast Guard: Status of Efforts to Improve Deepwater Program Management
and Address Operational Challenges. [hyperlink,
http://www.gao.gov/products/GAO-07-575T]. Washington, D.C.: March 8,
2007.
Coast Guard: Status of Deepwater Fast Response Cutter Design Efforts.
[hyperlink, http://www.gao.gov/products/GAO-06-764]. Washington, D.C.:
June 23, 2006.
Coast Guard: Changes to Deepwater Plan Appear Sound, and Program
Management Has Improved, but Continued Monitoring Is Warranted.
[hyperlink, http://www.gao.gov/products/GAO-06-546]. Washington, D.C.:
April 28, 2006.
Coast Guard: Progress Being Made on Addressing Deepwater Legacy Asset
Condition Issues and Program Management, but Acquisition Challenges
Remain. [hyperlink, http://www.gao.gov/products/GAO-05-757].
Washington, D.C.: July 22, 2005.
Coast Guard: Preliminary Observations on the Condition of Deepwater
Legacy Assets and Acquisition Management Challenges. [hyperlink,
http://www.gao.gov/products/GAO-05-651T]. Washington, D.C.: June 21,
2005.
Coast Guard: Deepwater Program Acquisition Schedule Update Needed.
[hyperlink, http://www.gao.gov/products/GAO-04-695]. Washington, D.C.:
June 14, 2004.
Contract Management: Coast Guard's Deepwater Program Needs Increased
Attention to Management and Contractor Oversight. [hyperlink,
http://www.gao.gov/products/GAO-04-380]. Washington, D.C.: March 9,
2004.
Coast Guard: Actions Needed to Mitigate Deepwater Project Risks.
[hyperlink, http://www.gao.gov/products/GAO-01-659T]. Washington,
D.C.: May 3, 2001.
[End of section]
Footnotes:
[1] The Department of Homeland Security fiscal year 2012 budget
request to Congress included a proposal to eliminate the term
"Integrated Deepwater System" from its annual appropriation. At the
time of this statement, Congress had not passed the department's
fiscal year 2012 appropriations act; therefore, this statement
continues to use the term Deepwater. The Coast Guard acquisition
portfolio includes 17 major programs and projects, 13 of which
constitute the Deepwater Program. In addition to vessels and aircraft,
the Deepwater Program includes Command, Control, Communications,
Computers, Intelligence, Surveillance, and Reconnaissance (C4ISR)
referred to in this statement as information technology.
[2] GAO, Coast Guard: Action Needed as Approved Deepwater Program
Remains Unachievable, [hyperlink,
http://www.gao.gov/products/GAO-11-743] (Washington, D.C.: July 28,
2011).
[3] GAO, Coast Guard: Deepwater Requirements, Quantities, and Cost
Require Revalidation to Reflect Knowledge Gained, [hyperlink,
http://www.gao.gov/products/GAO-10-790] (Washington, D.C.: July 27,
2010).
[4] The total acquisition cost of $4.7 billion is in then-year dollars.
[5] The Coast Guard's capital investment plan is a 5-year plan
presented to Congress that includes Acquisition, Construction, and
Improvement. The Coast Guard updates the capital investment plan
annually, and it represents the Coast Guard's submission for the
President's Budget in any given year.
[6] For additional detail see: GAO, Coast Guard: Progress Being Made
on Addressing Deepwater Legacy Asset Condition Issues and Program
Management, but Acquisition Challenges Remain, [hyperlink,
http://www.gao.gov/products/GAO-05-757] (Washington, D.C.: July 22,
2005).
[7] [hyperlink, http://www.gao.gov/products/GAO-10-790].
[8] According to a DHS official involved in this analysis, the
characteristics of the Offshore Patrol Cutter are based on the
operational requirements document, and the characteristics of the
modernized 270' are theoretical because this cutter does not exist.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: