Elderly Housing

Successes/Problems in Implementing HUD's Cost Containment Requirements Gao ID: RCED-86-55BR December 4, 1985

In response to a congressional request, GAO reviewed the Department of Housing and Urban Development's (HUD) Section 202 Elderly Housing Program to determine: (1) the extent to which HUD cost control efforts were working; (2) additional opportunities for reducing program costs; and (3) who is benefiting from the program.

GAO found that: (1) projects built under the cost containment program had smaller units, fewer amenities, and cost an average of 16 percent less to construct than the projects built before cost containment; (2) without cost containment, it would have cost about $100 million more to finance the 12,400 units HUD approved for funding in fiscal year 1985; (3) problems have been encountered in implementing cost containment, largely because of the use of fair market rents to control costs; (4) program costs could be reduced an additional $19 million annually if more efficiency units were built to house the single elderly; (5) additional savings would be possible if more consideration were given to project costs when selecting projects for funding; (6) most of the beneficiaries in the projects sampled had very low incomes and received substantial rent subsidies under the HUD Section 8 Rental Assistance Program; and (7) most of the projects sampled served few, if any, minorities.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.