Elderly Housing

Project Funding and Other Factors Delay Assistance to Needy Households Gao ID: GAO-03-512 May 30, 2003

According to the Department of Housing and Urban Development (HUD), the most widespread and urgent housing problem facing elderly households is affordability. About 3.3 million elderly renter households in the United States have very low incomes (50 percent or less of median area income). The Section 202 Supportive Housing for the Elderly Program provides capital advances (grants) to nonprofit organizations to develop affordable rental housing exclusively for these households. GAO was asked to determine the role of the Section 202 program in addressing the need for affordable elderly housing and the factors affecting the timeliness of approving and constructing new projects.

HUD's Section 202 program provides a valuable housing resource for very low income elderly households. Although they represent a small share of all elderly households, very low income elderly renters have acute housing affordability problems because of their limited income and the need for supportive services. The Section 202 program, which offers about 260,000 rental units nationwide and ensures that residents receive rental assistance and access to services that promote independent living, is the only federal program devoted exclusively to providing this type of housing. However, even with the program's exclusive focus, Section 202 has reached only about an estimated 8 percent of very low income elderly households. About three-quarters of Section 202 projects in GAO's analysis did not meet HUD's time guideline for gaining approval to start construction. These delays held up the delivery of housing assistance to needy elderly households by nearly a year compared with projects that met HUD's guideline. Several factors contributed to these delays, in particular capital advances that were not sufficient to cover development costs. Project sponsors reported that insufficient capital advances often forced them to spend time seeking additional funds from HUD and other sources. Although HUD's policy is to provide sufficient funding to cover the cost of constructing a modestly designed project, HUD has acknowledged that its capital advances for the Section 202 program sometimes fall short. Other factors affecting the timeliness of the approval process include inadequate training and guidance for field staff responsible for the approval process, inexperienced project sponsors, and local zoning and permit requirements.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone:


GAO-03-512, Elderly Housing: Project Funding and Other Factors Delay Assistance to Needy Households This is the accessible text file for GAO report number GAO-03-512 entitled 'Elderly Housing: Project Funding and Other Factors Delay Assistance to Needy Households' which was released on June 17, 2003. This text file was formatted by the U.S. General Accounting Office (GAO) to be accessible to users with visual impairments, as part of a longer term project to improve GAO products' accessibility. Every attempt has been made to maintain the structural and data integrity of the original printed product. Accessibility features, such as text descriptions of tables, consecutively numbered footnotes placed at the end of the file, and the text of agency comment letters, are provided but may not exactly duplicate the presentation or format of the printed version. The portable document format (PDF) file is an exact electronic replica of the printed version. We welcome your feedback. Please E-mail your comments regarding the contents or accessibility features of this document to Webmaster@gao.gov. This is a work of the U.S. government and is not subject to copyright protection in the United States. It may be reproduced and distributed in its entirety without further permission from GAO. Because this work may contain copyrighted images or other material, permission from the copyright holder may be necessary if you wish to reproduce this material separately. Report to the Special Committee on Aging, U.S. Senate: May 2003: Elderly Housing: Project Funding and Other Factors Delay Assistance to Needy Households: GAO-03-512: GAO Highlights: Highlights of GAO-03-512, a report to Special Committee on Aging, U.S. Senate Why GAO Did This Study: According to the Department of Housing and Urban Development (HUD), the most widespread and urgent housing problem facing elderly households is affordability. About 3.3 million elderly renter households in the United States have very low incomes (50 percent or less of median area income). The Section 202 Supportive Housing for the Elderly Program provides capital advances (grants) to nonprofit organizations to develop affordable rental housing exclusively for these households. GAO was asked to determine the role of the Section 202 program in addressing the need for affordable elderly housing and the factors affecting the timeliness of approving and constructing new projects. What GAO Found: HUD‘s Section 202 program provides a valuable housing resource for very low income elderly households. Although they represent a small share of all elderly households, very low income elderly renters have acute housing affordability problems because of their limited income and the need for supportive services. The Section 202 program, which offers about 260,000 rental units nationwide and ensures that residents receive rental assistance and access to services that promote independent living, is the only federal program devoted exclusively to providing this type of housing. However, even with the program‘s exclusive focus, Section 202 has reached only about an estimated 8 percent of very low income elderly households. About three-quarters of Section 202 projects in GAO‘s analysis did not meet HUD‘s time guideline for gaining approval to start construction. These delays held up the delivery of housing assistance to needy elderly households by nearly a year compared with projects that met HUD‘s guideline. Several factors contributed to these delays, in particular capital advances that were not sufficient to cover development costs. Project sponsors reported that insufficient capital advances often forced them to spend time seeking additional funds from HUD and other sources. Although HUD‘s policy is to provide sufficient funding to cover the cost of constructing a modestly designed project, HUD has acknowledged that its capital advances for the Section 202 program sometimes fall short. Other factors affecting the timeliness of the approval process include inadequate training and guidance for field staff responsible for the approval process, inexperienced project sponsors, and local zoning and permit requirements. What GAO Recommends: GAO is making recommendations to reduce the time required for projects to receive approval from HUD to start construction. Specifically, GAO is recommending that HUD assess the effectiveness of the methods it uses to calculate the size of the Section 202 capital advances and make any appropriate changes to them. GAO is also making other recommendations to improve HUD‘s administration and oversight of the 202 program‘s performance. GAO provided a draft of this report to HUD for comment. HUD agreed with the report‘s conclusions and recommendations. www.gao.gov/cgi-bin/getrpt?GAO-03-512. To view the full product, including the scope and methodology, click on the link above. For more information, contact David G. Wood at (202) 512-8678 or WoodD@gao.gov. [End of section] Letter: Results in Brief: Background: Section 202 Is an Important Source of Housing for Elderly Households with Very Low Incomes: Section 202 Projects Reviewed Generally Did Not Meet Guidelines for Timeliness: Various Factors Can Impede the Timely Processing of Projects: Conclusions: Recommendations: Agency Comments and Our Evaluation: Appendixes: Appendix I: Scope and Methodology: Appendix II: Budget Information for the Section 202 Program: Section 202 Appropriations: Section 202 Unexpended Balances: Appendix III: Data Issues Concerning the American Housing Survey: Appendix IV: Federal Housing Programs and the Elderly: Housing Production Programs That Develop Elderly Housing: Target Households: Annual Housing Production Levels: Appendix V: Section 202 Program Data: Appendix VI: Survey of HUD Field Office Representatives: Appendix VII: Survey of Section 202 Sponsors and Consultants: Appendix VIII: Comments from the Department of Housing and Urban Development: Tables: Table 1: HUD Income Categories: Table 2: Field Office Performance in Approving Projects for Construction within 18 and 24 Months: Table 3: Field Office Performance and Problems with Funding Issues: Table 4: Annual Appropriations for the Housing for Special Populations Account in Fiscal Years 1998-2002: Table 5: Annual Balances of Unexpended Appropriations for Section 202 in Fiscal Years 1998-2002: Table 6: Housing Units Occupied by Homeowner and Renter Elderly Households in 2001: Table 7: Income Categories for Elderly Homeowner and Renter Households in 2001: Table 8: Elderly Renter Households with Very Low Incomes by Subsidy Status and Rent Burden in 2001: Table 9: Moderate or Severe Rent Burden of Unassisted Very Low Income Elderly Renter Households by Region in 2001: Table 10: Number of Elderly Renter Households with Very Low Incomes by Subsidy Status and Rent Burden in Metropolitan Areas in 2001: Table 11: Proportion of Elderly Renter Households with Very Low Incomes by Subsidy Status and Rent Burden in Metropolitan Areas in 2001: Table 12: Number of Elderly Renter Households with Very Low Incomes by Subsidy Status and Rent Burden in Nonmetropolitan Areas in 2001: Table 13: Proportion of Elderly Renter Households with Very Low Incomes by Subsidy Status and Rent Burden in Nonmetropolitan Areas in 2001: Table 14: Active Federal Rental Housing Production and Insurance Programs by Household Type Served and Program Rent Levels: Table 15: Approximate Volume of New Production of Housing Units by Active Federal Rental Housing Programs: Table 16: Distribution of Section 202 Projects, Capital Advance Funds, and PRAC Funds, by Fiscal Year and Construction Approval Status: Table 17: Status of Metropolitan and Nonmetropolitan Projects in Gaining Construction Start Approval, Projects Funded in Fiscal Years 1998 to 2000: Table 18: Field Office Performance in Approving Projects to Start Construction, All Projects Funded in Fiscal Years 1998 to 2000: Table 19: Field Office Performance in Approving Metropolitan Projects to Start Construction, All Metropolitan Projects Funded in Fiscal Years 1998 to 2000: Table 20: Field Office Performance in Approving Nonmetropolitan Projects to Start Construction, All Nonmetropolitan Projects Funded in Fiscal Years 1998 to 2000: Table 21: Average Duration of Stages of Section 202 Project Development, Projects Funded Fiscal Years 1998 to 2000 That Were Approved to Start Construction: Table 22: Factors Cited by HUD in Approved Time Extensions for Section 202 Projects Funded in Fiscal Years 1998 to 2000: Figures: Figure 1: U.S. Homeowners and Renters in 2001: Figure 2: Housing Cost Burdens of Very Low Income Elderly Renter Households in 2001: Figure 3: Units Developed under Section 202 Compared with All Units Occupied by Very Low Income Elderly Renter Households, 1985 to 2001: Figure 4: Section 202 Project Processing: Figure 5: Average Elapsed Time for Completed Section 202 Projects Funded in Fiscal Years 1998 and 1999: Figure 6: Section 202 Unexpended Fund Balances as of End of Fiscal Year End 2002: Figure 7: Survey Responses”Insufficient Capital Advances and Other Project Funding Issues: Figure 8: Survey Responses”Field Office Staff Issues: Figure 9: Survey Responses”HUD Program Administration Issues: Abbreviations: AHS: American Housing Survey: AMI: area median income: BMIR: below-market interest rate: DAP: Development Application Processing System: FHA: Federal Housing Administration: HFA: housing finance agencies: HUD: Department of Housing and Urban Development: PRAC: project rental assistance contract: REMS: Real Estate Management System: Letter May 30, 2003: The Honorable Larry Craig Chairman The Honorable John Breaux Ranking Minority Member Special Committee on Aging United States Senate: According to the Department of Housing and Urban Development (HUD), the most widespread and urgent housing problem facing elderly households is affordability--that is, finding housing that is not too expensive relative to household income.[Footnote 1] In 2001, there were about 26 million households nationwide in which the householder or householder's spouse was 62 years or older.[Footnote 2] Of these elderly households, about 3.3 million were renters with very low incomes, which HUD defines as 50 percent or less of area median income. The Section 202 Supportive Housing for the Elderly Program (the Section 202 program) provides funds to nonprofit organizations to develop affordable rental housing exclusively for very low income elderly households that are not receiving other forms of housing assistance. In fiscal year 2002, the Section 202 program received about $783 million in appropriations to fund, among other things, the construction of over 6,000 rental units. The Section 202 program provides two types of financial support to nonprofit sponsors that develop and operate projects. First, project sponsors receive a capital advance, or a grant, to cover land and construction costs for projects of modest design that comply with HUD's minimum property standards. HUD determines the amounts of capital advances using its published development cost limits, adjusted for areas with high construction costs. HUD's policy is to have the capital advance cover total development costs without the need for sponsors to obtain additional funding from other sources. Second, after the project is completed and elderly tenants move in, the sponsor receives monthly rental assistance payments to defray some of the operating expenses. The combination of a debt-free project and rental assistance payments enables project sponsors to offer units at rents that are generally equal to 30 percent of the renter's income. Section 202 also has requirements to ensure that sponsors make the appropriate supportive services, such as housekeeping and transportation, available to elderly tenants. Each year HUD announces the availability of Section 202 funds. Potential project sponsors submit their applications for these funds to HUD's field offices. An application includes the description of the sponsor's nonprofit status, past experiences in providing housing and supportive services, and the housing needs of the elderly in the market area to be served. Once the applications are ranked according to criteria published in the Federal Register, field offices make their selection recommendations to HUD headquarters. If HUD headquarters approves these recommendations, HUD reserves funds for these proposed projects and sends notification letters to project sponsors. Between the time HUD sends notification letters and approves the start of construction, the sponsors' must complete, and HUD must approve, design plans and other documentation. These actions are referred to as project processing. Generally, 45 of HUD's 81 field offices are responsible for processing Section 202 projects. HUD's guidelines stipulate that HUD field offices and project sponsors should complete project processing within 18 months of the date the funding is awarded.[Footnote 3] However, the field offices may grant extensions of up to 6 months. Delays in processing hold up the distribution of funds and contribute to the program's annual unexpended balances.[Footnote 4] Between fiscal years 1998 and 2002, for example, the program's unexpended balances increased from about $4.8 billion to $5.2 billion. Delays in processing also hinder efforts to provide much- needed housing to very low income elderly renter households. This report addresses the role of the Section 202 program in responding to the housing affordability needs of elderly renter households with very low incomes and the program's timeliness in processing projects for construction and expending appropriated funds. As agreed with your offices, our report discusses: (1) the role of the Section 202 program in meeting the housing needs of elderly renter households with very low incomes, (2) the extent to which Section 202 projects meet HUD's time guideline for project processing, and (3) the factors that keep Section 202 projects from meeting HUD's time guideline for project processing. To address these objectives, we analyzed data from the American Housing Survey and other sources on the affordability of rental housing for very low income elderly households and the levels of assistance the Section 202 program provides.[Footnote 5] In addition, we reviewed HUD program and budget data, surveyed all HUD field offices that process Section 202 projects, conducted site visits at selected offices, surveyed and interviewed project sponsors and consultants experienced in working with the Section 202 program, and observed a HUD training program on processing Section 202 projects. Unless stated otherwise, our analysis focused on Section 202 projects funded between fiscal years 1998 and 2000. Lack of reliable program data prevented us from reviewing all Section 202 projects funded before fiscal year 1998. Appendix I provides detailed information on our scope and methodology. We conducted our work primarily in Washington, D.C., between May 2002 and March 2003, in accordance with generally accepted government auditing standards. Results in Brief: As the only federal housing program that targets all of its rental units to very low income elderly households, Section 202 is an important source of affordable housing for these households. Because very low income elderly households often have difficulty affording market rents, program funding is directed to localities based in part on their proportions of elderly renter households that have a housing affordability problem--that is, that pay over 30 percent of their income for rent. Nationwide, about half of the 3.3 million elderly renter households with very low incomes have a housing affordability problem and do not receive government housing assistance. Section 202 insulates tenants in housing units subsidized by the program from increases in housing costs by limiting rents to 30 percent of household income. Section 202 provided housing for an estimated one-fifth of the 1.3 million renter households that received government housing assistance. Even with the program's exclusive focus on these households, Section 202 has reached less than 8 percent of eligible households. And though some other federal programs provide more rental housing for the elderly, they do not focus exclusively on the very low income group. More than 70 percent of Section 202 projects funded between 1998 and 2000 were delayed--that is, these projects took longer than the 18 months set out in HUD's guidelines to proceed from the date of the funding award to the date of HUD's approval to start construction. However, a majority of projects were approved for construction within 24 months, or 18 months plus the 6-month discretionary extension. Projects located in metropolitan areas were more than twice as likely as projects in nonmetropolitan areas to exceed the 18-month guideline. Further, projects that exceeded the 18-month guideline ultimately took an average of 11 months longer to finish than projects that met the time guideline, and these delayed projects contributed to the program's unexpended fund balances. At the end of fiscal year 2002, 14 percent of the Section 202 program's $5.2 billion in unexpended funds was associated with projects that had not yet been approved for start of construction after 18 months. Several factors impeded the timely processing of projects, according to project sponsors, consultants, and HUD field office staff. First, despite HUD's development cost policy, the capital advances that HUD awards do not always cover the cost of developing projects. Field offices, sponsors, and consultants reported that this factor often prolonged processing time, in part because sponsors needed to seek additional funding. We found that field offices that cited capital advance shortfalls and the need for sponsors to seek outside funding were less likely to have met the 18-month processing time guideline, compared with field offices that did not report these problems. Second, field offices, sponsors, and consultants reported that inconsistent implementation of procedures HUD adopted to streamline processing by field office staff, as well as limited training and out-of-date guidance on processing policies and procedures, impeded timely processing. Third, prolonged response times from HUD headquarters on requests for additional funds or time have affected processing times, according to project sponsors and consultants and HUD field offices. Fourth, HUD's project monitoring system has limitations that may impede HUD's ability to oversee project timeliness. Finally, field offices, sponsors, and consultants reported that other factors--including inexperienced sponsors and local requirements in areas such as permitting and zoning--negatively affected processing time for some projects. This report contains recommendations to the Secretary of HUD designed to improve both the timeliness of project processing and program oversight. Background: Elderly households occupied about 25 percent (26 million) of the approximately 106 million housing units in the U.S. in 2001, according to the Housing Survey. A large majority of these elderly households were homeowners. The homeownership rate was considerably higher for elderly households than for nonelderly households (fig.1). A smaller share of elderly households (19 percent) rented their homes. These elderly renter households comprised about 15 percent of all renter households nationwide. Figure 1: U.S. Homeowners and Renters in 2001: [See PDF for image] [End of figure] The Housing Act of 1959 (P.L. 86-372) established the Section 202 program, which began as a direct loan program that provided below- market interest rate loans to private nonprofit developers, among others, to build rental housing for the elderly and people with disabilities. In 1990, the Cranston-Gonzalez National Affordable Housing Act (P.L. 101-625) modified Section 202 by converting it from a direct loan program into a capital advance program. In addition, the 1990 act created Section 811, another capital advance program, to produce housing specifically for people with disabilities and limited Section 202 to housing for the elderly. In its current form, Section 202 provides capital advances--effectively grants--to private nonprofit organizations (usually referred to as sponsors or owners) to pay for the costs of developing elderly rental housing. As long as rents on the units remain within the program's guidelines for at least 40 years, the sponsor does not have to pay back the capital advance. HUD calculates capital advances in accordance with development cost limits that it determines annually. These limits must account for several factors, including the costs of construction, reconstruction, or rehabilitation of supportive housing for the elderly that meets applicable state and local housing and building codes. HUD must, by statute, use current data that reflect these costs for each market area.[Footnote 6] HUD's policy is that these limits should cover the reasonable and necessary costs of developing a project of modest design that complies with HUD's minimum property standards, accessibility requirements, and project design and cost standards. Once HUD calculates a capital advance, the amount is placed on reserve, and the funds are made available to the sponsor.[Footnote 7] To be eligible to receive Section 202 housing assistance, tenants must have (1) one household member who is at least 62 years old and (2) household income that does not exceed the program's income limits. HUD has established general income categories that it and other federal agencies use to determine eligibility for many federal rental housing assistance programs (table 1).[Footnote 8] These amounts are subject to adjustments in areas with unusually high or low incomes or housing costs and are published. Only very low income households--those with incomes below 50 percent of the area's median income--are eligible for the Section 202 program. Table 1: HUD Income Categories: Income category: Low income; Percent of area median income: 80%. Income category: Very low income; Percent of area median income: 50%. Income category: Extremely low income; Percent of area median income: 30%. Source: HUD. Note: HUD does not officially refer to this category as "extremely low income," but the term is commonly used by housing experts to describe households that have incomes that do not exceed 30 percent of area median income. [End of table] Very low income households in Section 202 projects generally pay 30 percent of their income for rent. Because tenants' rent payments are not sufficient to cover the property's operating costs, the project sponsor receives an operating subsidy from HUD, called a project rental assistance contract. Under the project rental assistance contract, HUD pays the difference between the property's operating expenses (as approved by HUD) and total tenant rental receipts.[Footnote 9] Section 202 rental assistance is a project-based subsidy and, as such, is tied to rental units. The households receiving assistance can benefit from a project-based subsidy only while living in Section 202 units. For fiscal year 2002, Congress appropriated about $783 million for the Section 202 program to fund the construction of over 6,000 new units as well as new multiyear rental assistance contracts, service coordinators, renewals of expiring rental assistance contracts, and other activities as authorized by Section 202. From year to year, the Section 202 program has carried balances of unexpended appropriated dollars. According to HUD, in fiscal year 2002, the unexpended balance for Section 202 was approximately $5.2 billion. About 41 percent of this balance was for capital advance funds and 59 percent for rental assistance funds. Generally, some of the program's unexpended funds have not yet been awarded to projects, and others are attributable to projects that have not begun construction. Once construction begins, funds are expended over several years during the construction phase and during the term of the project rental assistance contract. See appendix II for additional budgetary data for the Section 202 program. Section 202 Is an Important Source of Housing for Elderly Households with Very Low Incomes: Section 202 is the only federal housing program that targets all of its rental units to very low income elderly households. Because these households often have difficulty affording market rents, program funding is directed to localities based in part on their proportions of elderly renter households that have a housing affordability problem-- that is, that pay over 30 percent of their income for rent and do not receive housing assistance. Nationwide, about 1.7 of the 3.3 million elderly renter households with very low incomes have a housing affordability problem. Section 202 insulates tenants in housing units subsidized by the program from increases in housing costs by limiting rents to 30 percent of household income. The program is a significant source of new and affordable housing for very low income elderly households: in 2001, 1.3 million such households received government housing assistance (about 40 percent of the total), and Section 202 provided housing for roughly one-fifth of them. Even with the program's exclusive focus on the very low income elderly, Section 202 has reached only a small share of eligible households. Though some other federal programs provide more housing for the elderly, they do not focus exclusively on these renter households. Section 202 Targets Very Low Income Elderly Households and Makes Supportive Services Available: Congress specifically intended the Section 202 program to serve very low income elderly households and to expand the supply of affordable housing that can accommodate the special needs of this group.[Footnote 10] HUD takes into account the level of need for the kind of housing Section 202 provides when allocating program funds to the field offices. Thus, the criteria for allocating funds to the offices include, among other things, the total number of very low income elderly renters in the area and the number in this group that pay more than 30 percent of their incomes for rent. HUD's allocation formula takes into account the amount of rent households pay in relation to their income. According to the American Housing Survey, in 2001 about 1.7 million households paid over 30 percent of their income for rent.[Footnote 11] HUD classified the "rent burden" these households face as either "moderate"--between 31 and 50 percent of household income--or "severe"--more than 50 percent of household income. As figure 2 illustrates, about 35 percent (over 1 million) of all elderly renter households with very low incomes had severe rent burdens, and about 15 percent (about 500,000) had moderate rent burdens.[Footnote 12] For detailed data on housing needs of these households, including data for metropolitan and nonmetropolitan areas, see appendix III. Figure 2: Housing Cost Burdens of Very Low Income Elderly Renter Households in 2001: [See PDF for image] Note: Other includes households that reported zero or negative income or no rent burden. [End of figure] Since Section 202 provides projects with rental assistance payments that cover a portion of the rent for each unit, the tenants themselves pay rents that equal a percentage of their household incomes--generally 30 percent. This percentage remains constant, so the amount of rent tenants pay increases only when household income rises, protecting them from rent increases that might be imposed in the private housing market when, for example, market conditions change. In contrast, low income elderly renter households that do not receive this type of assistance- -especially those with very low incomes--are vulnerable to high rent burdens and increases in housing costs. Most of these households have few or no financial resources, such as cash savings and other investments, and rely primarily on fixed incomes that may not increase at the same rate as housing costs. Section 202 serves another important function, potentially allowing households to live independently longer by offering tenants a range of services that support independent living--for example, meal services, housekeeping, personal assistance, and transportation. HUD ensures that sponsors have the managerial capacity to assess residents' needs, coordinate the provision of supportive services, and seek new sources of assistance to ensure long-term support. HUD pays a small portion of the costs of providing these services through its rental assistance payments.[Footnote 13] Section 202 Provides an Estimated One-fifth of All Government- subsidized Housing for Very Low Income Elderly Renters: Section 202 is an important source of housing for elderly households with very low incomes.[Footnote 14] Between 1998 and 2001, Section 202 approved the construction of from 3,890 to 7,350 assisted units annually, for an average of about 5,690 units. According to the American Housing Survey, in 2001 about 1.3 million, or 40 percent, of elderly renter households with very low incomes received some form of rental assistance in 2001 from a government housing program, including Section 202, public housing, or housing vouchers (fig. 2).[Footnote 15] According to our analysis of HUD program data, about 260,000 Section 202 units with rental assistance contracts (assisted units) generally served very low income elderly households through 2001. Taken together, these two sources of data suggest that around one-fifth of the 1.3 million assisted households identified in the American Housing Survey received assistance from Section 202.[Footnote 16] Although Section 202 is an important source of affordable elderly housing, the program reached a relatively small fraction of very low income elderly renter households. Between 1985 and 2001 the number of units assisted under the Section 202 program grew by about 4 percent annually, while the number of very low income elderly renter households declined by almost 1 percent annually. Yet at any given point in this period, Section 202 had reached no more than about 8 percent of these households that were eligible for assistance under the program (fig. 3). Also, during this period, many of these elderly renter households with very low incomes--ranging from about 45 to 50 percent--had housing affordability problems. Figure 3: Units Developed under Section 202 Compared with All Units Occupied by Very Low Income Elderly Renter Households, 1985 to 2001: [See PDF for image] [End of figure] Other federal programs that develop rental housing generally target different income levels, serve other populations in addition to the elderly (including families with children and people with disabilities) and do not require housing providers to offer supportive services for the elderly. For example, the Low-Income Housing Tax Credit Program, the largest of all current production programs, subsidizes the construction of about 86,000 units annually. However, according to one source, only around 13,200 of these units are intended for the elderly- -and, unlike Section 202, not all of these units serve very low income elderly renter households.[Footnote 17] In addition, these programs also do not have specific requirements ensuring that supportive services be available to elderly tenants. Appendix IV provides additional information on other federal housing programs. Section 202 Projects Reviewed Generally Did Not Meet Guidelines for Timeliness: According to HUD policy, Section 202 projects should complete project processing and be approved to start construction within 18 months after they are funded. Overall, 73 percent of Section 202 projects funded between fiscal years 1998 and 2000 did not meet this processing time guideline. However, about 55 percent of the projects were approved within 24 months. Projects located in metropolitan areas were about twice as likely as projects in nonmetropolitan areas to take more than 18 months to be approved. The percentage of projects approved within the specified time frame differed widely across HUD's field offices, with field offices located in the northeast and west approving the lowest percentages. As well as taking longer to complete than other projects--thus delaying benefits to very low income elderly tenants-- projects that were not approved for construction after the 18-month time frame accounted for 14 percent of the Section 202 program's balance of unexpended appropriations. HUD Expects Projects to Be Approved to Start Construction within 18 Months: Once HUD has made a funding award for a Section 202 project, HUD field office staff and project sponsors must complete various tasks, meetings, and paperwork before construction can commence (fig. 4). In this report, we refer to the tasks that take place between (1) the date when HUD sends a funding award letter to the sponsor and (2) the date that HUD authorizes the sponsor both to begin construction and to start drawing down the capital advance amount (initial closing) as project processing. The duration of the project processing period depends, in part, on project sponsors' timeliness in submitting the required documentation to HUD's field office reviewers. For example, sponsors must create owner corporations, hire consultants, obtain local permits and zoning approval, and design architectural and cost plans, among other things. HUD field offices must review all documentation before projects can be approved for construction. Figure 4: Section 202 Project Processing: [See PDF for image] [End of figure] As figure 4 illustrates, HUD's current time guideline for project processing is 18 months. Individual field offices have the discretion to extend processing for up to 6 more months without approval from HUD headquarters, but all extensions beyond those additional 6 months (that is, 24 months after the funding award) require approval from headquarters. After construction is authorized to begin, HUD gradually expends capital advance funds to cover development costs incurred by the sponsor. When construction is completed, HUD approves the final costs, and sponsors can begin leasing to eligible tenants. Over time, sponsors draw down funds from the reserved rental assistance amounts to support operating costs. To help assure that field office staff and project sponsors could complete project processing requirements within the 18-month time guideline, HUD adopted changes in 1996 that were intended to streamline procedures.[Footnote 18] One of the key changes included requiring field office staff to accept sponsor-provided certifications of architectural plans, cost estimates, and land appraisals. Previously, field office staff performed detailed technical reviews of these items. According to HUD policy, these streamlined procedures should have been used to process all projects in our analysis, which were funded between fiscal years 1998 and 2000. HUD Took Longer Than 18 Months to Approve Most Projects for Construction: Most Section 202 projects that received funding awards did not receive approval to begin construction within the 18-month guideline set out by HUD. Altogether, 73 percent of projects funded from fiscal years 1998 through 2000 did not meet the 18-month guideline. These projects accounted for 79 percent of the nearly $1.9 billion in funding awarded to projects during this period. The percentage of projects exceeding the guideline remained relatively stable over the years at around 72 percent (fiscal year 1998) to 75 percent (fiscal year 2000). During this period, the projects located in metropolitan areas (72 percent of all projects) were about twice as likely as projects in nonmetropolitan areas to exceed the 18-month guideline (see app. V for more detail).[Footnote 19] HUD field offices may grant up to 6-month extensions after the 18-month guideline for projects needing more time to gain approval to start construction, and many projects were approved within that 6-month time frame. HUD approved 55 percent of the projects funded from fiscal years 1998 through 2000 for construction within 24 months of the funding award--27 percent within 18 months and 28 percent within 19 to 24 months. The remaining 45 percent of projects took more than 24 months to be approved. In addition, metropolitan projects were about twice as likely as nonmetropolitan projects to take more than 24 months to gain approval to start construction. Field Offices' Performance in Meeting the Time Guideline Varied: We looked at the performance of the 45 individual HUD field offices that process Section 202 projects and found that they had varying degrees of success in meeting the 18-month guideline. We evaluated their performance by estimating the percentage of projects approved for construction (project approval rate) within 18 months for each field office. Among these offices, the median project approval rate for construction within 18 months was 22 percent (table 2), but field offices' performance varied widely. Eight field offices had no projects that met the 18-month guideline, while more than 90 percent of projects at one office did (see app. V for a breakdown of approval rates by field office). Field offices' performance varied by region, with those located in the northeast and west being least likely to approve projects within 18 months of the funding award. Table 2 also shows the rate of projects approved within 24 months. Table 2: Field Office Performance in Approving Projects for Construction within 18 and 24 Months: Median project approval rate for field offices: All field offices; Median project approval rate for field offices: Within 18 months: 22%; Within 24 months: 60%. Offices in northeast; Median project approval rate for field offices: Within 18 months: 9%; Within 24 months: 36%. Offices in west; Median project approval rate for field offices: Within 18 months: 15%; Within 24 months: 41%. Offices in south; Median project approval rate for field offices: Within 18 months: 34%; Within 24 months: 71%. Offices in midwest; Median project approval rate for field offices: Within 18 months: 29%; Within 24 months: 71%. Source: GAO analysis of HUD's Development Application Processing (DAP) System, December 2002. Note: The Puerto Rico field office is included in the median calculation for all field offices, but it is not part of any region, according to the Bureau of the Census definition. [End of table] Delayed Projects Affect the Program's Production Times and Expenditures: Meeting processing time guidelines is important because most of the delays in total production time--that is, the time between funding award and construction completion--stem from the project processing phase. When we compared the average total production times for completed projects that did not meet HUD's 18-month processing guideline and those that did, the delayed projects took 11 months longer than other projects to proceed from funding award to construction completion (fig. 5). Since the average time taken for the construction phase was very similar for all projects, most of the 11- month difference in total production time was attributable to the extra 10 months that delayed projects took to complete the processing phase. Figure 5: Average Elapsed Time for Completed Section 202 Projects Funded in Fiscal Years 1998 and 1999: [See PDF for image] Note: Projects funded in fiscal year 2000 are excluded from this analysis because no delayed projects had completed construction. [End of figure] Delayed processing of Section 202 projects also affected the Section 202 program's overall balances of unexpended appropriations. At the end of fiscal year 2002, for example, HUD had a total of $5.2 billion in unexpended Section 202 funds (fig. 6). A relatively small part of these unexpended funds--about 14 percent--was attributable to projects that had not yet been approved to start construction, even though they had exceeded HUD's 18-month processing time guideline. Consequently, none of the funds reserved for these projects had been expended. By contrast, the remaining 86 percent of unexpended funds were associated with projects for which HUD was in the process of expending funds for construction or rental assistance. For example, almost half of the unexpended balances--about 48 percent--resulted from projects that had already been completed but were still drawing down their rental assistance funds as intended under the multiyear project rental assistance contract between HUD and the project sponsor. (For additional details on unexpended fund balances, see app. II.): Figure 6: Section 202 Unexpended Fund Balances as of End of Fiscal Year 2002: [See PDF for image] Note: Other includes projects under construction and funding for other program purposes. [End of figure] Various Factors Can Impede the Timely Processing of Projects: Our review of projects funded from fiscal years 1998 through 2000 shows that several factors can prevent Section 202 projects from meeting the 18-month processing time guideline, including: issues related to capital advances, field office practices and the training and guidance that HUD has provided to field office staff, and HUD's program administration and oversight. First, despite HUD's intent, capital advances were not always sufficient to meet development costs. According to some sponsors and consultants, this factor often led sponsors to seek funding from other sources, including other HUD programs, which takes time. Second, some field offices, sponsors, and consultants reported that some field office staff had not fully implemented HUD's streamlined processing procedures and that HUD had offered only limited training and guidance to field office staff on processing policies and procedures. Third, additional time was needed for cases in which HUD headquarters responded to project sponsors' requests for additional funds or processing time. Fourth, limitations in HUD's project monitoring system impeded its ability to oversee project processing. Finally, factors external to HUD, such as sponsors' level of development experience and requirements established by local governments, also hindered processing. Insufficient Capital Advances Caused Some Sponsors to Seek Other Funding: Although HUD policy intends for capital advances to fund the cost of constructing a modestly designed project, capital advances have not always been sufficient to cover these expenses.[Footnote 20] HUD field staff, project sponsors, and consultants reported that program limits on capital advances often kept projects from meeting HUD's time guideline for approving projects for construction. Most field offices, and every sponsor and consultant that we surveyed, reported that insufficient capital advances negatively affected project processing time, and a substantial majority of respondents indicated that this problem occurred frequently (fig. 7). Many respondents also reported that securing secondary financing to supplement the capital advance amount often added to processing time. According to some sponsors and consultants, the capital advance amounts set by HUD were often inadequate to cover land, labor, and construction costs as well as fees imposed by local government. As a result, sponsors had to seek secondary financing from other federal, state, and local resources-- including other HUD programs--or redesign projects to cut costs, or both. Some sponsors and consultants said that the search for secondary financing could add months to the construction approval process because funding application and award cycles for other programs varied and because sponsors had to meet HUD's documentation requirements for every additional funding source before the agency could authorize construction. Figure 7: Survey Responses--Insufficient Capital Advances and Other Project Funding Issues: [See PDF for image] [End of figure] HUD has recognized that the development cost limits it uses to calculate capital advances have sometimes been inadequate and that, as a result, a number of sponsors have had to seek additional funding to construct their projects. According to a HUD official, the agency is currently considering initiating a study to determine how to calculate capital advances that can cover project development costs. Our survey and program data showed that field offices that reported problems with insufficient capital advances and sponsors securing secondary financing had a lower percentage of projects that met the 18- month time guideline than other offices (table 3).[Footnote 21] The median percentage of projects meeting the 18-month guideline was much lower for field offices that reported these problems than those that did not. In addition, field offices in the northeast and west--the regions with the lowest percentage of projects meeting the processing time guideline (see table 2 above)--were more likely than those in the south and midwest to report having problems with these factors. Table 3: Field Office Performance and Problems with Funding Issues: All field offices; Median rate of projects approved within 18 months: 22%. Field offices that reported insufficient capital advances and problems with sponsors obtaining secondary financing. Both factors are problems; Median rate of projects approved within 18 months: 18%. Neither factor is a problem; Median rate of projects approved within 18 months: 40%. Source: GAO survey of HUD field offices and Section 202 sponsors and consultants. Note: Of the 44 field offices that responded to the survey, 25 reported having problems with both factors and 15 reported having problems with neither factor. Three field offices reported problems with only one of the factors, and one field office did not respond to the questions. [End of table] Varying Field Office Practices and Inadequate Staff Training and Guidance Affected Timely Processing: Differences in the procedures field offices use to approve projects for construction and the extent of staff training and experience affected project processing time. For example, most consultants and sponsors in our survey responded that the unwillingness of field office staff to implement policy changes that HUD had adopted to streamline processing caused delays, as did insufficient training for and inexperience of field office staff (fig. 8). About 40 percent of them also reported that these problems occurred frequently. In addition, some consultants and sponsors whom we interviewed told us that some field offices continued to conduct much more detailed and time-consuming technical reviews of project plans than HUD's current policies require. These sponsors and consultants said that field staff departing from program guidelines caused confusion for sponsors about the type of information HUD required and delayed the process of obtaining HUD's approval to begin construction. A majority of HUD field office representatives also reported that a lack of staff training and experience can have a negative effect on processing time. However, HUD field office staff regarded these problems, as well as staff unwillingness to implement policy changes, as infrequent problems. HUD officials at headquarters acknowledged that some field staff were performing technical reviews contrary to program guidelines, but the officials did not know how many staff were doing so. Figure 8: Survey Responses--Field Office Staff Issues: [See PDF for image] [End of figure] HUD has provided limited guidance for field office staff on processing policies and procedures, which would ensure that all staff are up to date on the most current guidelines and requirements. In 1999, HUD headquarters issued a memorandum that reminded field office staff to process projects in accordance with streamlined procedures that had been adopted in 1996, such as replacing detailed technical review of project plans by field office staff with sponsor-provided certifications. Yet at the time of our review, most field office staff had not received any formal training on Section 202 project processing. According to HUD, in 2002, the agency required representatives from each field office to attend the first formal training on project processing for field office staff since at least 1992. Although HUD headquarters expected those who attended to relay what they had learned to other staff members in their own offices, our survey showed that by November 2002 no on-site training had occurred at about a quarter of the field offices. Also, only two field offices (5 percent) reported that training was relayed in a formal setting. We also found that HUD's field office staff was relying on out-of-date program handbooks that did not reflect the streamlined processing procedures.[Footnote 22] Although HUD stated that the agency intended to issue revised handbooks in order to ensure that all field offices follow current procedures, it had not yet done so at the time of our review. Based on written comments in our survey, some field office staff felt that an updated handbook would aid in the timely processing of Section 202 projects. Administrative and Oversight Weaknesses at HUD Headquarters Contributed to Delays: The time that HUD headquarters took to make certain administrative decisions also added to the time taken to process Section 202 projects. HUD headquarters must approve all requests for additional time to complete processing beyond 24 months after funding award and for additional capital advance funds. A HUD official noted that projects must already have exceeded the 18-month time guideline, and the discretionary 6-month extension, before HUD headquarters would be called on to approve a request for a time extension beyond 24 months. However, most of the field office representatives and project sponsors and consultants in our survey agreed that the time HUD headquarters took to make these decisions further prolonged processing time, with many respondents reporting that this issue was a frequent problem (fig. 9). Figure 9: Survey Responses--HUD Program Administration Issues: [See PDF for image] [End of figure] Further, HUD's project monitoring system was not as effective as it could have been and may have impeded HUD's oversight of project processing. HUD officials stated that, to monitor project processing, headquarters has periodically used its Development Application Processing (DAP) system to identify projects that exceeded the 18-month processing time guideline. In addition, the officials stated that headquarters contacted field offices on a quarterly basis to discuss the status of these delayed projects.[Footnote 23] Nevertheless, HUD headquarters officials have acknowledged that there are data inaccuracies in the DAP system, and the agency has instituted efforts to improve the system's reliability in identifying delayed projects. Furthermore, according to HUD, the DAP system does not collect data that would allow both headquarters and field office staff to follow a project through every stage of development and, as a result, many field offices maintain their own tracking systems to monitor projects through these stages. The lack of reliable, centralized data on the processing of Section 202 projects has limited HUD headquarters' ability to oversee projects' status, determine problematic processing stages, and identify field offices that might need additional assistance. HUD officials stated that enhancing the DAP system is a priority, but that a lack of funding has hindered such efforts. Issues External to HUD Caused Some Delays: Finally, other factors outside of HUD's direct control kept some projects from meeting time guidelines. Ninety-five percent of field office representatives and 90 percent of sponsors and consultants surveyed reported that project processing time was negatively affected when project sponsors were inexperienced. Nearly 60 percent of field offices, and almost 40 percent of sponsors and consultants, indicated that this problem occurred frequently. Local government requirements also negatively affected project processing, according to about 60 percent of field offices and about 85 percent of sponsors and consultants. About 35 percent of field offices and about 60 percent of sponsors and consultants reported that these requirements were frequently a problem. Also about 70 percent of field offices, sponsors, and consultants reported that, specifically, the local zoning process had a negative effect on project processing time, with about 40 percent of field offices and about 50 percent of sponsors and consultants indicating that this problem was frequent. Most field offices, sponsors, and consultants reported that other factors, such as community opposition and environmental issues, affected processing times but were not frequent problems for Section 202 projects. Although about 50 percent of field offices, and about 60 percent of sponsors and consultants, reported that community opposition had a negative effect on project processing time when it occurred, less than 10 percent of field offices, and about 30 percent of sponsors and consultants, reported such opposition to be a frequent problem. Also, about 50 percent of field offices, sponsors, and consultants indicated that environmental problems negatively affect processing when they occur, but only about 20 percent of them considered environmental problems to occur frequently. Appendixes VI and VII provides additional details on the results of our survey of HUD field office staff, sponsors, and consultants. Conclusions: The housing affordability problems of very low income elderly renter households--although they represent a small share of all elderly households--are particularly acute. These households represent one of the more vulnerable populations in the nation given their small incomes and need for supportive services. Considering the urgent housing needs of the Section 202 program's target population, ensuring that its projects are completed as soon as possible is critical. Delays in timely Section 202 processing can prolong project completion, on average, by nearly a year and result in higher balances of unexpended funds. Awarding capital advances that are sufficient to cover project development costs can alleviate delays by averting the need for sponsors to seek secondary financing or request approval from HUD headquarters for additional funding. While sufficient capital advance funding for projects, absent additional appropriations, can result in fewer units funded annually, it can also result in the prompt delivery of housing assistance to needy households and in the reduction of unexpended balances attributable to delayed projects. In addition, issuing an updated program handbook and providing adequate formal training can help in timely project processing by ensuring that staff are accountable for applying and interpreting HUD policies and procedures in a consistent manner. Finally, HUD's project monitoring system, in its current form, is not as effective as it can be and may hinder HUD's oversight. Maintaining reliable, centralized data on the processing of Section 202 projects is essential to overseeing projects' status as well as determining problematic processing stages. Recommendations: To reduce the time required for projects to receive approval to start construction, we recommend that the Secretary of Housing and Urban Development direct the Assistant Secretary for Housing to (1) evaluate the effectiveness of the current methods for calculating capital advances and (2) make any necessary changes to these methods, based on this evaluation, so that capital advances adequately cover the development costs of Section 202 projects consistent with HUD's project design and cost standards. In addition, to improve the performance of HUD field office and headquarters staff in processing projects in a timely manner, we recommend that HUD: * provide regular training to ensure that all field office staff are knowledgeable of and held accountable for following current processing procedures, * update its handbook to reflect current processing procedures, and: * improve the accuracy and completeness of information entered in the DAP system by field office staff and expand the system's capabilities to track key project processing stages. Agency Comments and Our Evaluation: We provided a draft of this report to HUD for its review and comment. In a letter from the Assistant Secretary for Housing (see app. VIII), HUD agreed with the report's conclusions, stating that the report demonstrated an excellent understanding of the importance of the Section 202 program in delivering affordable housing to very low income elderly households. HUD also concurred with the recommendations and provided information on how it intends to implement them. Regarding our recommendations concerning HUD's capital advance formula, the agency agreed that, in some locations, capital advances may be insufficient to cover project development costs and that delays can result when sponsors must seek additional funds from other sources. However, HUD also noted that increasing the per-unit development cost limits would result in fewer units constructed. Our draft report reached the same conclusion, but also stated that sufficient capital advances yield important benefits, such as the prompt delivery of housing assistance to needy households. As agreed with your offices, unless you publicly announce the contents of this report earlier, we plan no further distribution until 30 days from the report date. At that time, we will send copies of this report to interested members of Congress and congressional committees. We also will send copies to the HUD Secretary and make copies available to others upon request. In addition, the report will be available at no charge on the GAO Web site at http://www.gao.gov. Please contact me at (202) 512-8678 or Paul Schmidt at (312) 220-7681, if you or your staff have any questions concerning this report. Key contributors to this report were Susan Campbell, Emily Chalmers, Mark Egger, Daniel Garcia-Diaz, Curtis Groves, Ron La Due Lake, Marc Molino, Melissa Roye, William Sparling, and Julianne Stephens. David G. Wood Director, Financial Markets and Community Investment: Signed by David G. Wood: FOOTNOTES [1] U.S. Department of Housing and Urban Development. Housing Our Elders. (Washington, D.C.: 1999). Also see Commission on Affordable Housing and Health Facility Needs for Seniors in the 21st Century. A Quiet Crisis in America: A Report to Congress. (Washington, D.C.: 2003). [2] A householder is the person whose name is on the lease, deed, or mortgage. We chose 62 years to be consistent with HUD's definition of elderly. [3] These guidelines are based on HUD regulation (24 C.F.R. 891.165). [4] Unexpended balances include cumulative budget authority that has not been spent (outlayed) and that may be carried over from one year to the next. These balances may include either obligated or unobligated funds. [5] The survey, which the Bureau of the Census conducts for HUD, collects data on the nation's housing in odd-numbered years. The national sample covers approximately 55,700 housing units. All numerical estimates derived from the American Housing Survey have sampling errors of ±10 percent or less of the value of those numerical estimates, unless otherwise noted. All percentage estimates have sampling errors of ±6 percentage points or less, unless otherwise noted. [6] 12 U.S.C. 1701q(h)(1). [7] In addition, HUD requires a minimum capital investment (generally not to exceed $10,000) to assure the sponsor's commitment to the housing. [8] These other agencies include the Internal Revenue Service within the Department of the Treasury and Rural Housing Service within the Department of Agriculture. Both of these agencies administer affordable rental housing programs. [9] The term on rental assistance contracts is 5 years, although HUD has authorized these contracts for as long as 20 years. After these contracts expire, HUD renews them for 5 years, subject to the availability of funds. [10] 12 U.S.C. 1701q(a). [11] As in other surveys, estimates from the American Housing Survey are subject to both sampling and nonsampling errors. Appendix III provides the sampling error for all estimates presented in this report and discusses the types of nonsampling errors that may affect the estimates. [12] The sampling error for these half a million households with moderate rent burden was about ±78,410. [13] Tenants can also make co-payments to defray some of the services expenses. [14] The exact share of elderly units provided through the Section 202 program in relation to all federal housing programs cannot be calculated because many of these programs are used in combination with each other. [15] These programs are described in appendix IV. [16] Since this estimate is derived from two different sources, we cannot give a precise percentage, and thus, this estimate is intended to be illustrative. Appendixes I and III contain discussions of the data limitations in both of these sources. [17] Seniors Commission 2002, 53. [18] HUD Notice H 96-102. [19] HUD allocates Section 202 funding among field offices using a formula that targets funds based on the unmet needs of elderly renter households with housing problems. Also, the program allocates 85 percent of funding to metropolitan areas and 15 percent to nonmetropolitan areas. [20] See 66 Fed. Reg. 6647 (22 Jan. 2001). [21] We considered a field office to have a problem with insufficient capital advances and securing secondary financing if it reported that both of these factors occurred often to always. We considered a field office not to have a problem with these two factors if it reported that both of them occurred seldom or sometimes. [22] Handbook No. 4571.5 was issued on July 21, 1992. Handbook No. 4571.3 REV-1 was issued on April 9, 1993. [23] The agency has made some progress in approving some of these projects for construction or canceling them if they are no longer feasible. For example, 16 of the 169 projects that were pending construction approval at the end of fiscal year 2002 were approved for construction by December 2002, and 6 others had their funding awards canceled. [End of section] Appendixes: Appendix I: Scope and Methodology: We conducted this review to address: (1) the role of the Section 202 program in meeting the housing needs of elderly renter households with very low incomes, (2) the extent to which Section 202 projects meet the Department of Housing and Urban Development's (HUD) time guidelines for project processing, and (3) the factors that keep Section 202 projects from meeting HUD's time guidelines for project processing. To determine the role of the Section 202 program in meeting housing needs of elderly households, we analyzed household income and rental housing cost data from the American Housing Survey. The Bureau of the Census performs the survey for HUD every odd-numbered year. Appendix III provides a detailed discussion of the American Housing Survey. We also reviewed studies that involved the housing needs of elderly households. To determine the extent to which HUD's Section 202 and other housing programs serve elderly households, we used data from HUD's Real Estate Management System (REMS) as of the beginning of calendar year 2003. Specifically, we analyzed information on the overall number of properties and their associated units under Section 202 and other housing programs that serve the needs of elderly households. Although we did not independently verify the accuracy of the program data, we did perform internal checks to determine (1) the extent to which the data fields were populated, (2) the reasonableness of the values contained in the data fields, and (3) if any aberrations existed in the data we used. We concluded that the REMS data was reliable for purposes of this report. We also reviewed relevant regulations, policies, and procedures for Section 202 and other active federal programs. To explore the issue of timeliness in processing and some of the factors that may impede timely processing, we reviewed HUD program and budget data from HUD's Development Application Processing (DAP) System as of the end of calendar year 2002. Because HUD headquarters officials told us that program data from this system was not reliable for Section 202 projects funded before fiscal year 1998, we limited our review of Section 202 projects to those funded from fiscal years 1998 to 2000. While we did not independently verify the accuracy of the program data from this system, we periodically discussed the accuracy and interpretation of the data we used with HUD officials. In addition, we compared file records for projects funded since fiscal year 1998 with the data entered in the system for those projects by three HUD field offices that process Section 202 projects and generally found the data to be accurate. Also, we performed internal checks to determine the extent to which the data fields in DAP were populated and the reasonableness of the values contained in these fields. In cases where the data were not reasonable or questions arose, we contacted a HUD official to identify and correct errors. To determine the reasons why HUD awarded time extensions for certain projects listed in the system, we compiled and analyzed HUD's published notices of these extensions in the Federal Register. We also used a questionnaire to survey of all HUD field offices that process Section 202 projects. About 98 percent (44 out of 45) of the field offices that process Section 202 projects completed the questionnaire. We also conducted site visits at the Greensboro and Richmond field offices to obtain field office staff perceptions on factors that may impede timely processing. In addition, to gain a fuller perspective on these issues, we surveyed sponsors and consultants, identified by HUD and others, that were experienced in working with Section 202 projects. Collectively, these sponsors and consultants worked on approximately 260 projects since fiscal year 1998 representing approximately 40 percent of Section 202 units funded. In addition, we observed a HUD training session on processing Section 202 projects in August 2002. We conducted our work primarily in Washington, D.C., between May 2002 and March 2003, in accordance with generally accepted government auditing standards. [End of section] Appendix II: Budget Information for the Section 202 Program: This appendix provides information on the Housing for Special Populations appropriations account, which provides funding for the Section 202 and Section 811 programs.[Footnote 1] In fiscal year 2002, Congress appropriated over $1 billion for the Housing for Special Populations account--of which $783 million was earmarked for the Section 202 program. From year to year, the Section 202 program carries significant balances of unexpended appropriated funds. In fiscal year 2002, the unexpended balance for the Section 202 program was $5.2 billion. Section 202 Appropriations: In fiscal year 2002, Congress appropriated over $1 billion for the Housing for Special Populations appropriations account, which provides funding for both the Section 202 Supportive Housing for the Elderly and the Section 811 Supportive Housing for Persons with Disabilities Programs.[Footnote 2] Since fiscal year 1998, a total of $4.6 billion in appropriations were made available for both programs (table 4). In fiscal year 2002, the lion's share of the appropriations for the Housing for Special Populations account, about $783 million or 76 percent, went to the Section 202 program to fund, among other things, capital advances and project rental assistance contracts (PRACs) for new projects and PRAC renewals for existing projects.[Footnote 3] Since fiscal year 1998, about $3.6 billion have been appropriated for the Section 202 program. Appropriations for the Section 202 program in nominal dollars (that is, unadjusted for inflation) have increased since fiscal year 1998 at an average annual rate of about 5 percent. However, appropriations for Section 202 in constant 1998 dollars have increased by an average rate of about 2 percent annually. Table 4: Annual Appropriations for the Housing for Special Populations Account in Fiscal Years 1998-2002: Nominal dollars in millions. 1998; Housing for Special Populations: $839; Section 202 Supportive Housing for the Elderly: $645; Section 811 Supportive Housing for Persons with Disabilities: $194. 1999; Housing for Special Populations: 854; Section 202 Supportive Housing for the Elderly: 660; Section 811 Supportive Housing for Persons with Disabilities: 194. 2000; Housing for Special Populations: 911; Section 202 Supportive Housing for the Elderly: 710; Section 811 Supportive Housing for Persons with Disabilities: 201. 2001; Housing for Special Populations: 994; Section 202 Supportive Housing for the Elderly: 777; Section 811 Supportive Housing for Persons with Disabilities: 217. 2002; Housing for Special Populations: 1,024; Section 202 Supportive Housing for the Elderly: 783; Section 811 Supportive Housing for Persons with Disabilities: 241. Total; Housing for Special Populations: 4,622; Section 202 Supportive Housing for the Elderly: 3,575; Section 811 Supportive Housing for Persons with Disabilities: 1,047. Source: GAO analysis of HUD data. [End of table] Section 202 Unexpended Balances: The Section 202 program carries significant balances of unexpended appropriations from year to year. Unexpended balances include the cumulative amount of budget authority that has not been spent (outlayed) and may consist of either obligated or unobligated funds. Some of the unexpended balances are expected to be carried over annually for various programmatic reasons, including the time required for project sponsors to prepare their application for program funds and finalize plans as well as the time required for HUD's field offices to review and process them. However, some unexpended funds can also result from problems in the timeliness of project processing. Between fiscal years 1998 and 2002, the program's unexpended balance increased from about $4.8 billion to $5.2 billion. In nominal dollars, this balance has increased by an average annual rate of about 2 percent between fiscal years 1998 and 2002. In constant 1998 dollars, unexpended balances for Section 202 actually decreased by an average rate of less than 1 percent annually. Table 5 shows the annual balances of unexpended appropriations for the Section 202 program since fiscal year 1998. Table 5: Annual Balances of Unexpended Appropriations for Section 202 in Fiscal Years 1998-2002: Nominal dollars in millions; [Empty]. Section 202 Supportive Housing for the Elderly; $4,839; Fiscal year: 1999: $4,998; Fiscal year: 2000: $5,048; Fiscal year: 2001: $5,138; Fiscal year: 2002: $5,219. Capital advance; 1,774; Fiscal year: 1999: 1,789; Fiscal year: 2000: 1,949; Fiscal year: 2001: 2,041; Fiscal year: 2002: 2,164. PRAC (rental assistance); 3,065; Fiscal year: 1999: 3,209; Fiscal year: 2000: 3,099; Fiscal year: 2001: 3,097; Fiscal year: 2002: 3,055. Housing for Special Populations; 6,343; Fiscal year: 1999: 6,547; Fiscal year: 2000: 6,701; Fiscal year: 2001: 6,899; Fiscal year: 2002: 7,074. Source: GAO analysis of HUD data. [End of table] As table 5 shows, unexpended PRAC funds account for a large share of the total unexpended balances for the Section 202 program as well as for the overall Housing for Special Populations account. Before fiscal year 1997, HUD provided individual projects with PRAC amounts that covered rental assistance payments generally for 20 years. Since fiscal year 1997, HUD provided PRAC amounts that covered rental assistance payments for 5 years. In both cases, PRAC funds are obligated, but remain unexpended, for multiple years after project occupancy--unlike capital advance funds, which are fully expended by project completion. With the reduction of the PRAC term from 20 to 5 years, HUD expects PRAC funds to comprise a declining share of the overall unexpended balance for the Section 202 program. [End of section] Appendix III: Data Issues Concerning the American Housing Survey: In reporting on the housing affordability problems of elderly renter households with very low incomes, this report relies on data from the 2001 American Housing Survey (AHS). We assessed the reliability of the data by reviewing AHS documentation, performing electronic testing of the data files to check for completeness of data files, and replicating published tables.[Footnote 4] We determined that the data are reliable enough for the purposes of this report. AHS is a probability sample of about 55,700 housing units interviewed between August and November 2001.[Footnote 5] Because this sample is based on random selections, the specific sample selected is only one of a large number of samples that might have been drawn. Since each sample could have provided different estimates, we express our confidence in the precision of this sample's results as 95 percent confidence intervals (for example, +7 percentage points). This is the interval that would contain the actual population value for 95 percent of the samples that could have been drawn. As a result, we are 95 percent confident that each of the confidence intervals in this report will include the true values in the study population. In the following section, we provide 95 percent confidence intervals for the estimates used in this report. We calculated these confidence intervals by adding and subtracting the sampling error for each estimate to or from the estimate itself.[Footnote 6] Estimates from the survey are also subject to certain nonsampling errors, such as incomplete data and wrong answers. According to the survey documentation, errors due to incomplete data and wrong answers can be greater than sampling errors for some survey questions.[Footnote 7] Of the survey questions we rely upon for our analysis (age, tenure, income, housing costs, rent subsidies, and location), the survey question on income was subject to a high level of inconsistency in survey responses. Also relevant to this report, AHS is known to underreport income when compared to the Current Population Survey and other independent sources. However, our analysis concentrates on elderly renters with very low income, for which this should be less of an issue. According to a Census study based on relatively older data (from the early 1980s), much of the underreporting of income in the survey seems to derive from interest and dividend income as well as wages and salary.[Footnote 8] Consequently, the underreporting of income may be less of a problem among very low income elderly households who do not tend to rely on these sources of income. Generally, HUD's own internal analysis suggests that very low income renters in AHS tend to report their income more accurately than other groups. For example, in an unpublished analysis, HUD found that the income reported by very low income renters in the 1989 AHS was about 2 percent greater than the income reported in the 1990 Decennial Census. Nonetheless, current information on the extent of underreporting, especially among elderly renter households with very low incomes, is not available. The survey also collects data on the type of government housing assistance the household receives. For example, it asks if the household lives in a unit owned by a public housing authority or receives vouchers. However, households surveyed may misreport their specific programs. As a result, the survey does not provide sufficient and reliable detail on the specific housing assistance program that is serving the household. According to the survey documentation, units requiring income verification are usually subsidized. Table 6 shows the distribution of units that are occupied by homeowners and renters in 2001. A great majority of elderly households were homeowners. About 21 million (± 460,000) of 26 million (± 498,000) elderly households owned their homes. Elderly renter households consisted of about 5 million (± 242,000) households. : Table 6: Housing Units Occupied by Homeowner and Renter Elderly Households in 2001: [See PDF for image] Source: GAO analysis of the American Housing Survey, 2001. [End of table] Table 7 provides details on the estimated number of households who owned or rented their homes by income category (very low income and low income) in 2001. About 3.7 million (± 208,000) elderly renter households have very low incomes. About 4.3 million (± 223,000) elderly renter households have low incomes. These figures include households that do not pay cash rent. Based on the data from tables 6 and 7, over four-fifths (85 ± 2 percent) of elderly renter households have low incomes and approximately three-quarters (73 ± 3 percent) have very low incomes. Table 7: Income Categories for Elderly Homeowner and Renter Households in 2001: [See PDF for image] Source: GAO analysis of the American Housing Survey, 2001. [End of table] Table 8 shows the number of units occupied by elderly renter households with very low incomes by subsidy status and rent burden. About 1.7 million (± 141,000) elderly renter households with very low incomes have moderate or severe rent burdens. The majority of these actually have severe rent burdens. About 1.3 million (± 125,000) renter households with very low incomes receive some form of government assistance. Households that do not pay cash rent appear in the tables above in this appendix for informational purposes. However, since they do not pay cash rents, we exclude these households from our estimates of rent burdens in this report. : : Table 8: Elderly Renter Households with Very Low Incomes by Subsidy Status and Rent Burden in 2001: [See PDF for image] Source: GAO analysis of the American Housing Survey, 2001. [End of table] Table 9 looks at unassisted elderly renter households with rent burdens. Of the 1.7 million (± 141,000) households with rent burdens, about 60 percent are located either in the northeast or the south regions. The northeast and south contained about 542,000 (± 81,000) and 477,000 (± 76,000), respectively, of the nation's rent burdened elderly renter households with very low incomes. Table 9: Moderate or Severe Rent Burden of Unassisted Very Low Income Elderly Renter Households by Region in 2001: [See PDF for image] Source: GAO analysis of the American Housing Survey, 2001. [End of table] The following four tables show the number and proportion of units occupied by elderly renter households with very low incomes by subsidy status and rent burden in metropolitan areas (tables 10 and 11) and nonmetropolitan areas (tables 12 and 13). About 1.4 million (± 131,000) elderly renter households with very low incomes in metropolitan areas and 234,000 (± 53,000) in nonmetropolitan areas have moderate or severe rent burden (tables 10 and 12). The proportion of households with rent burdens was generally higher in metropolitan areas than in nonmetropolitan areas (tables 11 and 13). In addition, households in nonmetropolitan areas were less likely than those in metropolitan areas to have severe rent burdens. Table 10: Number of Elderly Renter Households with Very Low Incomes by Subsidy Status and Rent Burden in Metropolitan Areas in 2001: [See PDF for image] Source: GAO analysis of the American Housing Survey, 2001. [End of table] Table 11: Proportion of Elderly Renter Households with Very Low Incomes by Subsidy Status and Rent Burden in Metropolitan Areas in 2001: Renter households: Subsidized; Estimate: 38%; Sampling error: 3%; 95 percent confidence interval: From: 35%; 95 percent confidence interval: To: 41%. Renter households: Unassisted; Estimate: 62%; Sampling error: 3%; 95 percent confidence interval: From: 59%; 95 percent confidence interval: To: 65%. Renter households: Zero income; Estimate: 4%; Sampling error: 1%; 95 percent confidence interval: From: 3%; 95 percent confidence interval: To: 5%. Renter households: No rent burden; Estimate: 6%; Sampling error: 2%; 95 percent confidence interval: From: 4%; 95 percent confidence interval: To: 8%. Renter households: Rent burden; Estimate: 52%; Sampling error: 3%; 95 percent confidence interval: From: 48%; 95 percent confidence interval: To: 55%. Renter households: Moderate rent burden; Estimate: 14%; Sampling error: 2%; 95 percent confidence interval: From: 12%; 95 percent confidence interval: To: 17%. Renter households: Severe rent burden; Estimate: 37%; Sampling error: 3%; 95 percent confidence interval: From: 34%; 95 percent confidence interval: To: 41%. Source: GAO analysis of the American Housing Survey, 2001: [End of table] Table 12: Number of Elderly Renter Households with Very Low Incomes by Subsidy Status and Rent Burden in Nonmetropolitan Areas in 2001: [See PDF for image] [End of table] Table 13: Proportion of Elderly Renter Households with Very Low Incomes by Subsidy Status and Rent Burden in Nonmetropolitan Areas in 2001: Renter households: Subsidized; Estimate: 48%; Sampling error: 7%; 95 percent confidence interval: From: 40%; 95 percent confidence interval: To: 55%. Renter households: Unassisted; Estimate: 52%; Sampling error: 7%; 95 percent confidence interval: From: 45%; 95 percent confidence interval: To: 60%. Renter households: Zero income; Estimate: 3%; Sampling error: 3%; 95 percent confidence interval: From: 0%; 95 percent confidence interval: To: 5%. Renter households: No rent burden; Estimate: 6%; Sampling error: 4%; 95 percent confidence interval: From: 3%; 95 percent confidence interval: To: 10%. Renter households: Rent burden; Estimate: 43%; Sampling error: 7%; 95 percent confidence interval: From: 36%; 95 percent confidence interval: To: 50%. Renter households: Moderate rent burden; Estimate: 21%; Sampling error: 6%; 95 percent confidence interval: From: 15%; 95 percent confidence interval: To: 27%. Renter households: Severe rent burden; Estimate: 22%; Sampling error: 6%; 95 percent confidence interval: From: 16%; 95 percent confidence interval: To: 28%. Source: GAO analysis of the American Housing Survey, 2001: [End of table] Excluded from these estimates are the housing affordability needs of very low income homeowners. Although homeowners can experience housing affordability problems, homeowners and renters face different challenges in affording their homes. Unlike renters, homeowners have equity in their homes--about 68 percent (± 1 percent) of elderly homeowners own their homes free and clear. In addition, elderly homeowners face certain challenges in maintaining their housing, such as paying for property maintenance and accessibility modification.[Footnote 9] As a result, rental programs, such as Section 202, do not directly address the problems homeowners experience. [End of section] Appendix IV: Federal Housing Programs and the Elderly: The federal government has multiple housing programs that subsidize the development of rental properties. Many of these programs also subsidize the development of properties that are intended to serve primarily elderly households. Unlike Section 202, most federal housing programs do not target a single type of household. Rather, they serve many different types of households, such as families with children, people with disabilities, and the elderly, and they produce units with rents that are affordable to households at different income levels. Housing Production Programs That Develop Elderly Housing: In addition to Section 202, the federal government has multiple active housing production programs that continue to expand the number of assisted households by subsidizing the development of new rental housing. These federal programs, described below, can also subsidize individual rental properties that are intended primarily to serve elderly households. Active Housing Production Programs: * Low-Income Housing Tax Credits and Tax-Exempt Multifamily Housing Bonds provide federal tax incentives for private investment and are often used in conjunction with other federal and state subsidies in the production of new and rehabilitated rental housing. * HOME Investment Partnerships provides formula-based grants to states and localities to build, acquire, or rehabilitate affordable rental housing or provide tenant-based rental assistance.[Footnote 10] * Section 515/521 Rural Rental Assistance provides below-market loans and rental assistance to support the development of rental housing in rural areas. * Multifamily mortgage insurance programs provide mortgage insurance for the development of rental housing without federally-funded interest rate subsidies or project-based rental assistance.[Footnote 11] The Housing Choice Voucher program (housing vouchers) is another important source of assistance for elderly households. The program supplements tenants' rental payments in privately owned, moderately priced apartments chosen by the tenants. Currently, about 260,000 of the approximately 1.5 million voucher households are elderly. However, unlike the Section 202 or other programs discussed, housing vouchers is not a production program and does not directly subsidize the development of new or rehabilitated housing. In addition to the active housing production programs, the federal government also has programs that no longer subsidize the development of rental properties but, in some cases, continue to provide operating subsidies, rental assistance payments, or other subsidies for rental properties that were developed under these programs in the past. Over the years, these inactive housing production programs, described in the next section, subsidized many rental properties that were intended primarily to serve elderly households. Inactive Housing Production Programs: * Public Housing financed the development and operation of properties managed and owned by local housing authorities.[Footnote 12] * Section 236 and Section 221(d)(3) Below Market Interest Rate provided mortgage insurance for the development of rental housing with federally funded interest rate subsidies. * Section 8 project-based rental assistance programs provided project- based rental assistance to properties that were financed with Department of Housing and Urban Development (HUD) mortgage insurance, tax exempt bonds, and below-market interest rate loans.[Footnote 13] Target Households: Unlike Section 202, most active federal housing programs do not target a single type of household. Rather, they serve many different types of households, such as families with children, persons with disabilities, and the elderly. Furthermore, most federal housing programs target households at different income levels, not just households with very low incomes (50 percent or less of area media income) as does Section 202. Table 14 provides information on targeted household types and rent levels of the active housing production and insurance programs. Table 14: Active Federal Rental Housing Production and Insurance Programs by Household Type Served and Program Rent Levels: Rental housing production program: Section 202 Supportive Housing; Household type served: Elderly; Program rent levels affordable to households with: 50% or less of area median income (AMI) for all units. Rental housing production program: Low-Income Housing Tax Credits; Household type served: Multiple household types; Program rent levels affordable to households with: 50% of AMI for 20% of units or; 60% of AMI for 40% of units. Rental housing production program: Tax-Exempt Multifamily Housing Bonds; Household type served: Multiple household types; Program rent levels affordable to households with: 50% of AMI for 20% of units or; 60% of AMI for 40% of units. Rental housing production program: HOME Investment Partnerships; Household type served: Multiple household types; Program rent levels affordable to households with: 65% of AMI for all units and; 50% of AMI for 20% of units. Rental housing production program: Section 811 Supportive Housing; Household type served: Persons with disabilities; Program rent levels affordable to households with: 50% or less of AMI for all units. Rental housing production program: Section 515 Rural Rental Housing with Section 521 rental assistance; Household type served: Primarily families and the elderly; Program rent levels affordable to households with: 80% of AMI or less for all 515 units with rental assistance. Rental housing production program: FHA multifamily mortgage insurance[A]; Household type served: Multiple household types; Program rent levels affordable to households with: No income requirements/ market rate rents. Source: GAO. [A] These mortgage insurance programs are Section 221(d)(4), Section 221(d)(3), and Rental Housing for the Elderly (Section 231). In recent years, few mortgages have been insured with Section 231 because borrowers who intend to develop elderly rental properties rely on Section 221(d)(4) or Section 221(d)(3). [End of table] Low-Income Housing Tax Credits (tax credits), Tax-Exempt Multifamily Housing Bonds (tax-exempt bonds), and HOME set aside some of their units for very low-income households and can provide housing for the elderly (table 14). Congress has granted considerable latitude to state and local agencies that administer these programs in deciding who will be served with federal housing resources.[Footnote 14] In addition, mortgage insurance programs for multifamily rental properties under HUD's Federal Housing Administration (FHA) currently do not have any specific age or income requirements for tenants. However, since rents for newly developed FHA-insured properties are often set at market levels, these programs may not be able to reach very low-income households without the use of other subsidies. Annual Housing Production Levels: Although Section 202's annual production levels are small when compared to the total production levels of other housing programs, such as tax credits--the largest of all current production programs--Section 202, nonetheless, is a relatively important source of subsidized rental housing units for the elderly. Table 15 presents the volume of new production by rental housing production program. The volume of housing production illustrates individual program activity but, due to limitations in the data, it is not possible to accurately estimate what percentage of elderly units produced through federal housing programs is from Section 202 because units produced through these programs can overlap with each other. For example, HOME funding can be used in conjunction with programs such as tax credits, tax-exempt bonds, or HUD mortgage insurance programs to finance new production. As a result, adding units together for any of the programs in table 15 will likely result in double counting. Table 15: Approximate Volume of New Production of Housing Units by Active Federal Rental Housing Programs: Production program: Section 202 Supportive Housing; Approximate number of new or rehabilitated per annum: Elderly units: 5,700; Approximate number of new or rehabilitated per annum: Total units: 5,700.; Percent of total: Elderly units: 100%. Production program: Low-Income Housing Tax Credits; Approximate number of new or rehabilitated per annum: Elderly units: 13,200; Approximate number of new or rehabilitated per annum: Total units: 86,000. Percent of total: 15%. Production program: Tax-Exempt Multifamily Housing Bonds; Approximate number of new or rehabilitated per annum: Elderly units: 5,600; Approximate number of new or rehabilitated per annum: Total units: 33,300; Percent of total: 17%. Production program: HOME Investment Partnerships; Approximate number of new or rehabilitated per annum: Elderly units: 4,000; Approximate number of new or rehabilitated per annum: Total units: 17,000; Percent of total: Elderly units: 24%. Production program: Section 515 Rural Rental Housing; Approximate number of new or rehabilitated per annum: Elderly units: 800; Approximate number of new or rehabilitated per annum: Total units: 1,800; Elderly units: 44%. Production program: Section 811 Supportive Housing; Approximate number of new or rehabilitated per annum: Elderly units: NA; Approximate number of new or rehabilitated per annum: Total units: 1,300; Percent of total: Elderly units: NA. Production program: FHA multifamily mortgage insurance; Approximate number of new or rehabilitated per annum: Elderly units: 900; Approximate number of new or rehabilitated per annum: Total units: 26,400; Percent of total: Elderly units: 3%. Source: GAO. Notes: For Section 202, Section 811, and the FHA multifamily mortgage insurance programs, we estimated the average number of total and elderly units endorsed annually from 1998 to 2001 based on HUD program data. We reported the number of elderly units for tax credits based on the 2002 report from the Commission on Affordable Housing and Health Facility Needs for Seniors in the 21ST Century and for tax-exempt bonds based on the National Council of State Housing Agencies' State HFA Factbook: 2001 NCSHA Annual Survey Results. In addition, for tax credits, we estimated the average number of units placed in service annually from 1998 to 2000 based on HUD's Low-Income Housing Tax Credit Database. Finally, we relied on estimates from program officials for HOME and Section 515. [End of table] Due to differing sources of data and, in some cases, lack of official data, these estimates are rough approximations of actual production activity and are intended to be illustrative. Many of these programs overlap with each other. As a result, adding units together for any of the programs will likely result in double counting. [End of section] Appendix V: Section 202 Program Data: This appendix provides additional information on the extent to which Section 202 projects meet the Department of Housing and Urban Development's (HUD's) 18-month processing time guideline. In particular, we present data on projects' status in meeting the guideline, HUD field offices' rate of success in meeting the guideline, and the factors cited by HUD in its approvals of processing time extensions. Table 16 profiles the projects funded in fiscal years 1998 through 2000 according to the projects' status in gaining HUD's approval to start construction. Table 16: Distribution of Section 202 Projects, Capital Advance Funds, and PRAC Funds, by Fiscal Year and Construction Approval Status: Fiscal year: 1998: Number of projects: Met 18-month guideline: 47; Exceeded 18-month guideline: Approved for construction after 18 months: 108; Exceeded 18-month guideline: Pending approval for construction: 11; Exceeded 18-month guideline: Funding award cancelled: 0. Percent of projects: Met 18-month guideline: 28%; Exceeded 18-month guideline: Approved for construction after 18 months: 65%; Exceeded 18-month guideline: Pending approval for construction: 7%; Exceeded 18-month guideline: Funding award cancelled: -. Capital advance funds: Met 18-month guideline: $113 million; Exceeded 18-month guideline: Approved for construction after 18 months: $337 million; Exceeded 18-month guideline: Pending approval for construction: $43 million; Exceeded 18-month guideline: Funding award cancelled: -. PRAC funds (rental assistance); Met 18- month guideline: $23 million; Exceeded 18-month guideline: Approved for construction after 18 months: $68 million; Exceeded 18-month guideline: Pending approval for construction: $9 million; Exceeded 18-month guideline: Funding award cancelled: -. Total funds: Met 18-month guideline: $136 million; Exceeded 18-month guideline: Approved for construction after 18 months: $406 million; Exceeded 18-month guideline: Pending approval for construction: $52 million; Exceeded 18-month guideline: Funding award cancelled: -. Percent of total funds: Met 18-month guideline: 1999: 23%; Exceeded 18-month guideline: Approved for construction after 18 months: 1999: 68%; Exceeded 18-month guideline: Pending approval for construction: 1999: 9%; Exceeded 18-month guideline: Funding award cancelled: 1999: -. Fiscal year: 1999: Number of projects: Met 18-month guideline: 44; Exceeded 18-month guideline: Approved for construction after 18 months: 84; Exceeded 18-month guideline: Pending approval for construction: 34; Exceeded 18-month guideline: Funding award cancelled: 3. Percent of projects: Met 18-month guideline: 27%; Exceeded 18-month guideline: Approved for construction after 18 months: 51%; Exceeded 18-month guideline: Pending approval for construction: 21%; Exceeded 18-month guideline: Funding award cancelled: 2%. Capital advance funds: Met 18-month guideline: $108 million; Exceeded 18-month guideline: Approved for construction after 18 months: $284 million; Exceeded 18-month guideline: Pending approval for construction: $127 million; Exceeded 18-month guideline: Funding award cancelled: $15 million. PRAC funds; Met 18-month guideline: $22 million; Exceeded 18-month guideline: Approved for construction after 18 months: $57 million; Exceeded 18-month guideline: Pending approval for construction: $28 million; Exceeded 18-month guideline: Funding award cancelled: $3 million. Total funds: Met 18-month guideline: $130 million; Exceeded 18-month guideline: Approved for construction after 18 months: $341 million; Exceeded 18-month guideline: Pending approval for construction: $155 million; Exceeded 18-month guideline: Funding award cancelled: $18 million. Percent of total funds: Met 18-month guideline: 2000: 20%; Exceeded 18-month guideline: Approved for construction after 18 months: 2000: 53%; Exceeded 18-month guideline: Pending approval for construction: 2000: 24%; Exceeded 18-month guideline: Funding award cancelled: 2000: 3%. Fiscal year: 2000: Number of projects: Met 18-month guideline: 41; Exceeded 18-month guideline: Approved for construction after 18 months: 40; Exceeded 18-month guideline: Pending approval for construction: 82; Exceeded 18-month guideline: Funding award cancelled: 0. Percent of projects: Met 18-month guideline: 25%; Exceeded 18-month guideline: Approved for construction after 18 months: 25%; Exceeded 18-month guideline: Pending approval for construction: 50%; Exceeded 18-month guideline: Funding award cancelled: -. Capital advance funds; Met 18-month guideline: $109 million; Exceeded 18-month guideline: Approved for construction after 18 months: $124 million; Exceeded 18-month guideline: Pending approval for construction: $283 million; Exceeded 18-month guideline: Funding award cancelled: -. PRAC funds; Met 18-month guideline: $21 million; Exceeded 18-month guideline: Approved for construction after 18 months: $27 million; Exceeded 18-month guideline: Pending approval for construction: $58 million; Exceeded 18-month guideline: Funding award cancelled: -. Total funds; Met 18-month guideline: $131 million; Exceeded 18-month guideline: Approved for construction after 18 months: $150 million; Exceeded 18-month guideline: Pending approval for construction: $341 million; Exceeded 18-month guideline: Funding award cancelled: -. Percent of total funds; Met 18- month guideline: Total: 21%; Exceeded 18-month guideline: Approved for construction after 18 months: Total: 24%; Exceeded 18-month guideline: Pending approval for construction: Total: 55%; Exceeded 18-month guideline: Funding award cancelled: Total: -. Total: Number of projects; Met 18-month guideline: 132; Exceeded 18-month guideline: Approved for construction after 18 months: 232; Exceeded 18-month guideline: Pending approval for construction: 127; Exceeded 18-month guideline: Funding award cancelled: 3. Percent of projects; Met 18-month guideline: 27%; Exceeded 18-month guideline: Approved for construction after 18 months: 47%; Exceeded 18-month guideline: Pending approval for construction: 26%; Exceeded 18-month guideline: Funding award cancelled: 1%. Capital advance funds; Met 18-month guideline: $330 million; Exceeded 18-month guideline: Approved for construction after 18 months: $746 million; Exceeded 18-month guideline: Pending approval for construction: $453 million; Exceeded 18-month guideline: Funding award cancelled: $15 million. PRAC funds; Met 18-month guideline: $66 million; Exceeded 18-month guideline: Approved for construction after 18 months: $152 million; Exceeded 18-month guideline: Pending approval for construction: $94 million; Exceeded 18-month guideline: Funding award cancelled: $3 million. Total funds; Met 18-month guideline: $396 million; Exceeded 18-month guideline: Approved for construction after 18 months: $897 million; Exceeded 18-month guideline: Pending approval for construction: $547 million; Exceeded 18-month guideline: Funding award cancelled: $18 million. $18 million: Percent of total funds; Met 18-month guideline: 21%; Exceeded 18-month guideline: Approved for construction after 18 months: 48%; Exceeded 18-month guideline: Pending approval for construction: 29%; Exceeded 18-month guideline: Funding award cancelled: 1%. Source: GAO analysis of HUD Development Application Processing (DAP) System, December 2002. Note: Percentages do not always add to 100 because of rounding. Total funds do not always equal the sum of capital advance and project rental assistance contract (PRAC) funds because of rounding. [End of table] Table 17 compares the status of projects located in metropolitan and nonmetropolitan areas in gaining approval to start construction within either 18 or 24 months. In both cases, metropolitan projects were about twice as likely as projects in nonmetropolitan areas to take more than either 18 or 24 months to be approved. That is, the odds of a metropolitan project taking more than 18 or 24 months to be approved for construction were about twice the odds of a nonmetropolitan project taking more than 18 or 24 months, respectively. Table 17: Status of Metropolitan and Nonmetropolitan Projects in Gaining Construction Start Approval, Projects Funded in Fiscal Years 1998 to 2000: [See PDF for image] Source: GAO analysis of HUD DAP system, December 2002. [End of table] Tables 18, 19, and 20 present the rate of project approvals within either 18 or 24 months for all field offices that have responsibility for processing Section 202 projects. Table 18 shows the results for all projects, table 19 shows the results only for projects located in metropolitan areas, and table 20 shows the results for projects located in nonmetropolitan areas. The rate of project approvals for each field office is the percentage of projects, funded between fiscal years 1998 and 2000, that HUD approved for construction within the 18-month processing time guideline or within the 24-month period after the funding award--that is, 18 months plus the 6-month discretionary extension. Table 18: Field Office Performance in Approving Projects to Start Construction, All Projects Funded in Fiscal Years 1998 to 2000: Field office: Atlanta; Project approval rate (%): Within 18 months: 11; Project approval rate (%): Within 24 months: 67; Number of projects: 9. Field office: Baltimore; Project approval rate (%): Within 18 months: 18; Project approval rate (%): Within 24 months: 36; Number of projects: 11. Field office: Birmingham; Project approval rate (%): Within 18 months: 80; Project approval rate (%): Within 24 months: 80; Number of projects: 5. Field office: Boston; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 15; Number of projects: 20. Field office: Buffalo; Project approval rate (%): Within 18 months: 29; Project approval rate (%): Within 24 months: 64; Number of projects: 14. Field office: Caribbean; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of projects: 2. Field office: Charleston; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of projects: 3. Field office: Chicago; Project approval rate (%): Within 18 months: 21; Project approval rate (%): Within 24 months: 57; Number of projects: 14. Field office: Cleveland; Project approval rate (%): Within 18 months: 8; Project approval rate (%): Within 24 months: 58; Number of projects: 12. Field office: Columbia; Project approval rate (%): Within 18 months: 78; Project approval rate (%): Within 24 months: 89; Number of projects: 9. Field office: Columbus; Project approval rate (%): Within 18 months: 50; Project approval rate (%): Within 24 months: 56; Number of projects: 16. Field office: Denver; Project approval rate (%): Within 18 months: 33; Project approval rate (%): Within 24 months: 58; Number of projects: 12. Field office: Des Moines; Project approval rate (%): Within 18 months: 29; Project approval rate (%): Within 24 months: 71; Number of projects: 7. Field office: Detroit; Project approval rate (%): Within 18 months: 50; Project approval rate (%): Within 24 months: 70; Number of projects: 10. Field office: Fort Worth; Project approval rate (%): Within 18 months: 43; Project approval rate (%): Within 24 months: 71; Number of projects: 14. Field office: Greensboro; Project approval rate (%): Within 18 months: 93; Project approval rate (%): Within 24 months: 93; Number of projects: 14. Field office: Hartford; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 10; Number of projects: 10. Field office: Houston; Project approval rate (%): Within 18 months: 14; Project approval rate (%): Within 24 months: 71; Number of projects: 7. Field office: Indianapolis; Project approval rate (%): Within 18 months: 67; Project approval rate (%): Within 24 months: 83; Number of projects: 6. Field office: Jackson; Project approval rate (%): Within 18 months: 25; Project approval rate (%): Within 24 months: 75; Number of projects: 4. Field office: Jacksonville; Project approval rate (%): Within 18 months: 13; Project approval rate (%): Within 24 months: 50; Number of projects: 16. Field office: Kansas City; Project approval rate (%): Within 18 months: 29; Project approval rate (%): Within 24 months: 71; Number of projects: 7. Field office: Knoxville; Project approval rate (%): Within 18 months: 50; Project approval rate (%): Within 24 months: 100; Number of projects: 6. Field office: Little Rock; Project approval rate (%): Within 18 months: 83; Project approval rate (%): Within 24 months: 100; Number of projects: 18. Field office: Los Angeles; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 30; Number of projects: 20. Field office: Louisville; Project approval rate (%): Within 18 months: 67; Project approval rate (%): Within 24 months: 92; Number of projects: 12. Field office: Manchester; Project approval rate (%): Within 18 months: 9; Project approval rate (%): Within 24 months: 64; Number of projects: 11. Field office: Milwaukee; Project approval rate (%): Within 18 months: 6; Project approval rate (%): Within 24 months: 39; Number of projects: 18. Field office: Minneapolis; Project approval rate (%): Within 18 months: 45; Project approval rate (%): Within 24 months: 91; Number of projects: 11. Field office: Nashville; Project approval rate (%): Within 18 months: 40; Project approval rate (%): Within 24 months: 80; Number of projects: 10. Field office: New Orleans; Project approval rate (%): Within 18 months: 27; Project approval rate (%): Within 24 months: 45; Number of projects: 11. Field office: New York; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 36; Number of projects: 22. Field office: Newark; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 22; Number of projects: 9. Field office: Oklahoma City; Project approval rate (%): Within 18 months: 67; Project approval rate (%): Within 24 months: 67; Number of projects: 3. Field office: Omaha; Project approval rate (%): Within 18 months: 50; Project approval rate (%): Within 24 months: 100; Number of projects: 6. Field office: Philadelphia; Project approval rate (%): Within 18 months: 18; Project approval rate (%): Within 24 months: 41; Number of projects: 17. Field office: Phoenix; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 22; Number of projects: 9. Field office: Pittsburgh; Project approval rate (%): Within 18 months: 11; Project approval rate (%): Within 24 months: 33; Number of projects: 9. Field office: Portland; Project approval rate (%): Within 18 months: 27; Project approval rate (%): Within 24 months: 64; Number of projects: 11. Field office: Providence; Project approval rate (%): Within 18 months: 40; Project approval rate (%): Within 24 months: 40; Number of projects: 5. Field office: Richmond; Project approval rate (%): Within 18 months: 8; Project approval rate (%): Within 24 months: 17; Number of projects: 12. Field office: San Antonio; Project approval rate (%): Within 18 months: 20; Project approval rate (%): Within 24 months: 60; Number of projects: 5. Field office: San Francisco; Project approval rate (%): Within 18 months: 7; Project approval rate (%): Within 24 months: 38; Number of projects: 29. Field office: Seattle; Project approval rate (%): Within 18 months: 22; Project approval rate (%): Within 24 months: 44; Number of projects: 9. Field office: St Louis; Project approval rate (%): Within 18 months: 22; Project approval rate (%): Within 24 months: 89; Number of projects: 9. Field office: Total (all offices); Project approval rate (%): Within 18 months: 27; Project approval rate (%): Within 24 months: 55; Number of projects: 494. Source: GAO analysis of HUD DAP system, December 2002. [End of table] Table 19: Field Office Performance in Approving Metropolitan Projects to Start Construction, All Metropolitan Projects Funded in Fiscal Years 1998 to 2000: Field office: Atlanta; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 67; Number of metropolitan projects: 6. Field office: Baltimore; Project approval rate (%): Within 18 months: 22; Project approval rate (%): Within 24 months: 44; Number of metropolitan projects: 9. Field office: Birmingham; Project approval rate (%): Within 18 months: 67; Project approval rate (%): Within 24 months: 67; Number of metropolitan projects: 3. Field office: Boston; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 19; Number of metropolitan projects: 16. Field office: Buffalo; Project approval rate (%): Within 18 months: 18; Project approval rate (%): Within 24 months: 55; Number of metropolitan projects: 11. Field office: Caribbean; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of metropolitan projects: 2. Field office: Charleston; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of metropolitan projects: 1. Field office: Chicago; Project approval rate (%): Within 18 months: 25; Project approval rate (%): Within 24 months: 50; Number of metropolitan projects: 12. Field office: Cleveland; Project approval rate (%): Within 18 months: 10; Project approval rate (%): Within 24 months: 60; Number of metropolitan projects: 10. Field office: Columbia; Project approval rate (%): Within 18 months: 100; Project approval rate (%): Within 24 months: 100; Number of metropolitan projects: 4. Field office: Columbus; Project approval rate (%): Within 18 months: 54; Project approval rate (%): Within 24 months: 62; Number of metropolitan projects: 13. Field office: Denver; Project approval rate (%): Within 18 months: 14; Project approval rate (%): Within 24 months: 29; Number of metropolitan projects: 7. Field office: Des Moines; Project approval rate (%): Within 18 months: 40; Project approval rate (%): Within 24 months: 80; Number of metropolitan projects: 5. Field office: Detroit; Project approval rate (%): Within 18 months: 56; Project approval rate (%): Within 24 months: 67; Number of metropolitan projects: 9. Field office: Fort Worth; Project approval rate (%): Within 18 months: 46; Project approval rate (%): Within 24 months: 69; Number of metropolitan projects: 13. Field office: Greensboro; Project approval rate (%): Within 18 months: 86; Project approval rate (%): Within 24 months: 86; Number of metropolitan projects: 7. Field office: Hartford; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 10; Number of metropolitan projects: 10. Field office: Houston; Project approval rate (%): Within 18 months: 14; Project approval rate (%): Within 24 months: 71; Number of metropolitan projects: 7. Field office: Indianapolis; Project approval rate (%): Within 18 months: 60; Project approval rate (%): Within 24 months: 80; Number of metropolitan projects: 5. Field office: Jackson; Project approval rate (%): Within 18 months: -; Project approval rate (%): Within 24 months: -; Number of metropolitan projects: 0. Field office: Jacksonville; Project approval rate (%): Within 18 months: 13; Project approval rate (%): Within 24 months: 50; Number of metropolitan projects: 16. Field office: Kansas City; Project approval rate (%): Within 18 months: 33; Project approval rate (%): Within 24 months: 67; Number of metropolitan projects: 6. Field office: Knoxville; Project approval rate (%): Within 18 months: 33; Project approval rate (%): Within 24 months: 100; Number of metropolitan projects: 3. Field office: Little Rock; Project approval rate (%): Within 18 months: 75; Project approval rate (%): Within 24 months: 100; Number of metropolitan projects: 4. Field office: Los Angeles; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 30; Number of metropolitan projects: 20. Field office: Louisville; Project approval rate (%): Within 18 months: 80; Project approval rate (%): Within 24 months: 100; Number of metropolitan projects: 5. Field office: Manchester; Project approval rate (%): Within 18 months: 25; Project approval rate (%): Within 24 months: 50; Number of metropolitan projects: 4. Field office: Milwaukee; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 27; Number of metropolitan projects: 11. Field office: Minneapolis; Project approval rate (%): Within 18 months: 33; Project approval rate (%): Within 24 months: 83; Number of metropolitan projects: 6. Field office: Nashville; Project approval rate (%): Within 18 months: 40; Project approval rate (%): Within 24 months: 80; Number of metropolitan projects: 5. Field office: New Orleans; Project approval rate (%): Within 18 months: 25; Project approval rate (%): Within 24 months: 75; Number of metropolitan projects: 4. Field office: New York; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 36; Number of metropolitan projects: 22. Field office: Newark; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 22; Number of metropolitan projects: 9. Field office: Oklahoma City; Project approval rate (%): Within 18 months: 67; Project approval rate (%): Within 24 months: 67; Number of metropolitan projects: 3. Field office: Omaha; Project approval rate (%): Within 18 months: 50; Project approval rate (%): Within 24 months: 100; Number of metropolitan projects: 4. Field office: Philadelphia; Project approval rate (%): Within 18 months: 21; Project approval rate (%): Within 24 months: 43; Number of metropolitan projects: 14. Field office: Phoenix; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 40; Number of metropolitan projects: 5. Field office: Pittsburgh; Project approval rate (%): Within 18 months: 14; Project approval rate (%): Within 24 months: 43; Number of metropolitan projects: 7. Field office: Portland; Project approval rate (%): Within 18 months: 17; Project approval rate (%): Within 24 months: 33; Number of metropolitan projects: 6. Field office: Providence; Project approval rate (%): Within 18 months: 40; Project approval rate (%): Within 24 months: 40; Number of metropolitan projects: 5. Field office: Richmond; Project approval rate (%): Within 18 months: 13; Project approval rate (%): Within 24 months: 25; Number of metropolitan projects: 8. Field office: San Antonio; Project approval rate (%): Within 18 months: 25; Project approval rate (%): Within 24 months: 75; Number of metropolitan projects: 4. Field office: San Francisco; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 43; Number of metropolitan projects: 21. Field office: Seattle; Project approval rate (%): Within 18 months: 13; Project approval rate (%): Within 24 months: 38; Number of metropolitan projects: 8. Field office: St Louis; Project approval rate (%): Within 18 months: 17; Project approval rate (%): Within 24 months: 83; Number of metropolitan projects: 6. Field office: Total (all offices); Project approval rate (%): Within 18 months: 22; Project approval rate (%): Within 24 months: 51; Number of metropolitan projects: 356. Source: GAO analysis of HUD DAP system, December 2002. [End of table] Table 20: Field Office Performance in Approving Nonmetropolitan Projects to Start Construction, All Nonmetropolitan Projects Funded in Fiscal Years 1998 to 2000: Field office: Atlanta; Project approval rate (%): Within 18 months: 33; Project approval rate (%): Within 24 months: 67; Number of nonmetropolitan projects: 3. Field office: Baltimore; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of nonmetropolitan projects: 2. Field office: Birmingham; Project approval rate (%): Within 18 months: 100; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 2. Field office: Boston; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of nonmetropolitan projects: 4. Field office: Buffalo; Project approval rate (%): Within 18 months: 67; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 3. Field office: Caribbean; Project approval rate (%): Within 18 months: - ; Project approval rate (%): Within 24 months: -; Number of nonmetropolitan projects: 0. Field office: Charleston; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of nonmetropolitan projects: 2. Field office: Chicago; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 2. Field office: Cleveland; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 50; Number of nonmetropolitan projects: 2. Field office: Columbia; Project approval rate (%): Within 18 months: 60; Project approval rate (%): Within 24 months: 80; Number of nonmetropolitan projects: 5. Field office: Columbus; Project approval rate (%): Within 18 months: 33; Project approval rate (%): Within 24 months: 33; Number of nonmetropolitan projects: 3. Field office: Denver; Project approval rate (%): Within 18 months: 60; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 5. Field office: Des Moines; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 50; Number of nonmetropolitan projects: 2. Field office: Detroit; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 1. Field office: Fort Worth; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 1. Field office: Greensboro; Project approval rate (%): Within 18 months: 100; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 7. Field office: Hartford; Project approval rate (%): Within 18 months: -; Project approval rate (%): Within 24 months: -; Number of nonmetropolitan projects: 0. Field office: Houston; Project approval rate (%): Within 18 months: -; Project approval rate (%): Within 24 months: -; Number of nonmetropolitan projects: 0. Field office: Indianapolis; Project approval rate (%): Within 18 months: 100; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 1. Field office: Jackson; Project approval rate (%): Within 18 months: 25; Project approval rate (%): Within 24 months: 75; Number of nonmetropolitan projects: 4. Field office: Jacksonville; Project approval rate (%): Within 18 months: -; Project approval rate (%): Within 24 months: -; Number of nonmetropolitan projects: 0. Field office: Kansas City; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 1. Field office: Knoxville; Project approval rate (%): Within 18 months: 67; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 3. Field office: Little Rock; Project approval rate (%): Within 18 months: 86; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 14. Field office: Los Angeles; Project approval rate (%): Within 18 months: -; Project approval rate (%): Within 24 months: -; Number of nonmetropolitan projects: 0. Field office: Louisville; Project approval rate (%): Within 18 months: 57; Project approval rate (%): Within 24 months: 86; Number of nonmetropolitan projects: 7. Field office: Manchester; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 71; Number of nonmetropolitan projects: 7. Field office: Milwaukee; Project approval rate (%): Within 18 months: 14; Project approval rate (%): Within 24 months: 57; Number of nonmetropolitan projects: 7. Field office: Minneapolis; Project approval rate (%): Within 18 months: 60; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 5. Field office: Nashville; Project approval rate (%): Within 18 months: 40; Project approval rate (%): Within 24 months: 80; Number of nonmetropolitan projects: 5. Field office: New Orleans; Project approval rate (%): Within 18 months: 29; Project approval rate (%): Within 24 months: 29; Number of nonmetropolitan projects: 7. Field office: New York; Project approval rate (%): Within 18 months: -; Project approval rate (%): Within 24 months: -; Number of nonmetropolitan projects: 0. Field office: Newark; Project approval rate (%): Within 18 months: -; Project approval rate (%): Within 24 months: -; Number of nonmetropolitan projects: 0. Field office: Oklahoma City; Project approval rate (%): Within 18 months: -; Project approval rate (%): Within 24 months: -; Number of nonmetropolitan projects: 0. Field office: Omaha; Project approval rate (%): Within 18 months: 50; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 2. Field office: Philadelphia; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 33; Number of nonmetropolitan projects: 3. Field office: Phoenix; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of nonmetropolitan projects: 4. Field office: Pittsburgh; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of nonmetropolitan projects: 2. Field office: Portland; Project approval rate (%): Within 18 months: 40; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 5. Field office: Providence; Project approval rate (%): Within 18 months: -; Project approval rate (%): Within 24 months: -; Number of nonmetropolitan projects: 0. Field office: Richmond; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of nonmetropolitan projects: 4. Field office: San Antonio; Project approval rate (%): Within 18 months: 0; Project approval rate (%): Within 24 months: 0; Number of nonmetropolitan projects: 1. Field office: San Francisco; Project approval rate (%): Within 18 months: 25; Project approval rate (%): Within 24 months: 25; Number of nonmetropolitan projects: 8. Field office: Seattle; Project approval rate (%): Within 18 months: 100; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 1. Field office: St Louis; Project approval rate (%): Within 18 months: 33; Project approval rate (%): Within 24 months: 100; Number of nonmetropolitan projects: 3. Field office: Total (all offices); Project approval rate (%): Within 18 months: 39; Project approval rate (%): Within 24 months: 67; Number of nonmetropolitan projects: 138. Source: GAO analysis of HUD DAP system, December 2002. [End of table] Table 21 shows the average number of months that projects took to complete various stages of the development process between Congress's appropriation of funds for the Section 202 program and completion of construction. For projects funded between fiscal years 1998 and 2000 that had been approved to start construction at the time of our analysis, the average time taken from appropriation to approval to start construction was 36 months. Projects that had also completed construction took another 11 months, on average, from beginning to end of construction. From appropriation to end of construction, the average time taken was 47 months or almost 4 years. Table 21: Average Duration of Stages of Section 202 Project Development, Projects Funded Fiscal Years 1998 to 2000 That Were Approved to Start Construction: [See PDF for image] Source: GAO analysis of HUD DAP system, December 2002. [A] The average time for construction is based on a total of 193 projects that completed construction: 110 from 1998, 69 from 1999, and 114 from 2000. [B] The number of projects includes only projects that were approved to start construction. An additional 11 projects from 1998, 37 projects from 1999, and 82 projects from 2000 were not approved for construction at the time of our analysis. [End of table] Table 22 summarizes the factors that HUD cited in extending the processing time for projects beyond 24 months after the funding award. This table draws on extension waivers approved between January 1998 and June 2002 for projects funded between fiscal years 1998 and 2000, showing the number and percentage of extended projects affected by each factor. Table 22: Factors Cited by HUD in Approved Time Extensions for Section 202 Projects Funded in Fiscal Years 1998 to 2000: Factor: Financing and cost issues; Number of extended projects affected: 29; Percent of extended projects affected: 35%. Seeking additional funding; Number of extended projects affected: 17; Percent of extended projects affected: 20%. Construction issues[A]; Number of extended projects affected: 11; Percent of extended projects affected: 13%. Other financial issues; Number of extended projects affected: 5; Percent of extended projects affected: 6%. State and local government issues; Number of extended projects affected: 27; Percent of extended projects affected: 32%. Historic preservation; Number of extended projects affected: 1; Percent of extended projects affected: 1%. Local review, approval, or permits; Number of extended projects affected: 17; Percent of extended projects affected: 20%. Zoning issues; Number of extended projects affected: 11; Percent of extended projects affected: 13%. Other state and local issues; Number of extended projects affected: 3; Percent of extended projects affected: 4%. Design/architect issues; Number of extended projects affected: 15; Percent of extended projects affected: 18%. Site change; Number of extended projects affected: 14; Percent of extended projects affected: 17%. Environmental issues; Number of extended projects affected: 8; Percent of extended projects affected: 10%. Site control; Number of extended projects affected: 8; Percent of extended projects affected: 10%. Community concerns/local opposition; Number of extended projects affected: 8; Percent of extended projects affected: 10%. Other site issues; Number of extended projects affected: 7; Percent of extended projects affected: 8%. Legal challenges; Number of extended projects affected: 6; Percent of extended projects affected: 7%. General delay in project processing[B]; Number of extended projects affected: 19; Percent of extended projects affected: 23%. Source: GAO analysis of HUD data. Note: GAO analyzed HUD-approved project processing time extensions. 84 projects received a total of 103 extensions. Percentages do not total 100 because many projects received extensions for multiple reasons. [A] Construction issues include increased construction costs and difficulty finding a qualified contractor or obtaining a bid within the capital advance amount. [B] General delays in project processing include cases where HUD cited the need for time for sponsors to submit or modify required paperwork and for HUD to review paperwork, without stating a more specific reason. [End of table] [End of section] Appendix VI: Survey of HUD Field Office Representatives: [See PDF for image] [End of figure] [End of section] Appendix VII: Survey of Section 202 Sponsors and Consultants: [See PDF for image] [End of figure] [End of figure] [End of section] Appendix VIII: Comments from the Department of Housing and Urban Development: U.S. DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT WASHINGTON, D.C. 20410-8000: May 15, 2003: OFFICE OF THE ASSISTANT SECRETARY: FOR HOUSING-FEDERAL HOUSING COMMISSIONER: Mr. David G. Wood Director: Financial Markets and Community Investment United States General Accounting Office Washington, DC 20548: Dear Mr. Wood: Thank you for the opportunity to provide comments on the General Accounting Office (GAO) draft report: ELDERLY HOUSING: Project Funding and Other Factors Delay Assistance to Needy Households (GAO-03-512). The GAO report reflects an excellent understanding of the importance of the Section 202 Supportive Housing Program in the delivery of affordable housing to very low-income elderly households. We are pleased that one of your observations of the report is that only a relatively small part of the unexpended funds, about 14 percent, are associated with pipeline projects that have exceeded HUD's 18-month processing time guideline. The report also verifies that the number of projects scheduled to reach construction start will double in the next 6 months, suggesting that the remaining projects represent an even smaller share of the unexpended balances --approximately 7 percent. Our comments do not question the conclusions in the report. Instead, they are provided to give an indication of the progress we have made in reducing the Section 202 pipeline since 2001. In a report prepared for GAO in early fiscal year 2002, the Department identified 118 Section 202 pipeline projects that had exceeded HUD's processing time guidelines. As a result of the Department's aggressive efforts to close, in particular, these pipeline projects; there are only 36 of these projects remaining in the pipeline. We expect most of these remaining projects to reach construction start by the end of the current fiscal year. We are working diligently with our field offices to assist the sponsors of 8 projects that were funded in Fiscal Year 1997 or earlier to reach a construction start by the end of this fiscal year. The Department certainly recognizes the importance of timely processing for the Section 202 program and we have made that a priority. We believe substantial improvement has been made since the end of FY 2000, the concluding date for the analysis in this report. Due to increased Headquarters monitoring, the number of projects reaching construction start within 24 months has increased by 10 percent. In addition, late in the last fiscal year, we conducted training to our field office staff on processing Section 202 applications for the first time in ten years. The Department is aware that in some areas of the country, capital advances may be insufficient to cover the cost of developing Section 202 projects. We have initiated steps to examine how HUD's Section 202 development cost limits compare with other objectively measurable indicators of local construction costs. We are also aware that when sponsors seek additional funds from other sources, the development time is increased. However, if the Department increased the allowable per unit cost limitations, there would be a reduction in the number of units built under the Section 202 program. In addition, the successful partnerships that have been developed with states, localities and other interested parties over time would disappear. We plan to explore this issue with the stakeholders of the Section 202 program early this summer. Our specific comments on the Report's recommendations are as follows: Recommendation: * Evaluate the effectiveness of the current methods for calculating capital advances. Response: We agree with this recommendation. We have already initiated steps to examine how HUD's Sections 202 and 811 development cost limits compare with other objectively measurable indicators of local construction costs. Recommendation: * Make any necessary changes to these methods, based on this evaluation, so that capital advances adequately cover the development costs of Section 202 projects consistent with HUD's project design and cost standards. Response: We will consider this recommendation and will be discussing this recommendation with Section 202 stakeholders this summer. Recommendation: * Provide regular training to ensure that all field office staff are knowledgeable of and held accountable for following current processing procedures. Response: We agree with this recommendation. As noted in this report, during Fiscal Year 2002, we provided the first training to field staff in 10 years. Subject only to resource limitations, we will continue to implement an effective training program. Our next training will include technical processing training for field staff to assure that there is consistent processing in the field offices. Recommendation: * Update its handbook to reflect current processing procedures. Response: We agree with this recommendation. We have begun the process of consolidating and updating the Section 202 Program Handbooks. Recommendation: * Improve the accuracy and completeness of information entered in the Development Application Processing (DAP) system by field office staff and expand the system's capabilities to track key processing stages. Response: We agree with this recommendation. There was an intensive effort to verify the accuracy of the information in the DAP system during Fiscal Year 2002. Expanding the capabilities of the DAP system is a top Information Technology priority of the Office of Housing. The Department is committed to ensuring that the Section 202 Program continues to address the need for affordable elderly housing. GAO's assistance in monitoring this program and the Department's performance has been very beneficial. John C. Weicher: Assistant Secretary for Housing - Federal Housing Commissioner: Signed by John C. Weicher: [End of section] (250083): FOOTNOTES [1] For fiscal year 2004, HUD proposed to separate the Housing for Special Populations account into two accounts--Housing for the Elderly and Housing for Persons with Disabilities. [2] The period of availability for obligating Section 202 funds has been limited in recent years. The fiscal year 2003 appropriations act, for example, requires HUD to obligate fiscal year 2003 funds for the Section 202 program by the end of fiscal year 2006. Under 31 U.S.C. 1552, HUD is required to disburse, and the project owner to expend, all obligated Section 202 funds by the end of the fifth fiscal year after the period of availability for obligation ends--in the case of Section 202 funds for fiscal year 2003, no later than the end of fiscal year 2011. Any remaining balance (whether obligated or unobligated) in the account after the fifth year is to be canceled and is not available for obligation or expenditure. [3] PRACs provide rental assistance payments to a property to pay the difference between the units' approved operating costs and the tenant rental contributions (generally 30 percent of adjusted income). [4] U.S. Census Bureau, Current Housing Reports - Series H150/01, American Housing Survey for the United States: 2001. This report can be found at http://ww.huduser.org/datasets/ahs.html. [5] For a description of the sample design, refer to Appendix B of U.S. Census Bureau, Current Housing Reports - Series H150/01, American Housing Survey for the United States: 2001. [6] The formulas and methodology for computing these sampling errors are provided in Appendix D of U.S. Census Bureau, Current Housing Reports - Series H150/01, American Housing Survey for the United States: 2001. [7] A more complete discussion of these sources of error (including response inconsistencies for various questions) can be found in Appendix D of the Census' Current Housing Reports for 2001. [8] U.S. Census Bureau, Current Housing Reports - Series H121/95-01, American Housing Survey: A Quality Profile, July 1996. [9] In the absence of additional income, an elderly homeowner can, among other things, downsize to a more affordable home, seek property tax relief, or access the home's equity through a home equity conversion mortgage ("reverse mortgage"). [10] HOME also provides homeownership assistance. [11] Although properties with FHA-insured multifamily mortgages today are often termed unassisted because they do not receive project-based rental assistance, projects may receive grants, tax concessions, subsidies, and other subsidies from federal, state, and local governments. [12] Since 1994, public housing has not received new appropriations to fund incremental units. HUD funds the replacement of existing public housing units through the HOPE VI program. This program, however, does not increase the supply of affordable housing. [13] These programs included Section 8 New Construction/Substantial Rehabilitation, Section 8 Loan Management Set Aside, Section 8 Property Disposition, and Section 8 Moderate Rehabilitation. Some of these programs overlapped with other mortgage subsidy programs. [14] For example, every year the Internal Revenue Service requires that the state agencies responsible for awarding tax credits under the tax credit program submit updated plans that outline how they will distribute their allocations of tax credits. See HUD's 2002 report Analysis of State-Qualified Allocation Plans for the Low-Income Housing Tax Credit Program. GAO's Mission: The General Accounting Office, the investigative arm of Congress, exists to support Congress in meeting its constitutional responsibilities and to help improve the performance and accountability of the federal government for the American people. GAO examines the use of public funds; evaluates federal programs and policies; and provides analyses, recommendations, and other assistance to help Congress make informed oversight, policy, and funding decisions. GAO's commitment to good government is reflected in its core values of accountability, integrity, and reliability. Obtaining Copies of GAO Reports and Testimony: The fastest and easiest way to obtain copies of GAO documents at no cost is through the Internet. GAO's Web site ( www.gao.gov ) contains abstracts and full-text files of current reports and testimony and an expanding archive of older products. The Web site features a search engine to help you locate documents using key words and phrases. You can print these documents in their entirety, including charts and other graphics. Each day, GAO issues a list of newly released reports, testimony, and correspondence. GAO posts this list, known as "Today's Reports," on its Web site daily. The list contains links to the full-text document files. To have GAO e-mail this list to you every afternoon, go to www.gao.gov and select "Subscribe to e-mail alerts" under the "Order GAO Products" heading. Order by Mail or Phone: The first copy of each printed report is free. Additional copies are $2 each. A check or money order should be made out to the Superintendent of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or more copies mailed to a single address are discounted 25 percent. Orders should be sent to: U.S. General Accounting Office 441 G Street NW, Room LM Washington, D.C. 20548: To order by Phone: Voice: (202) 512-6000: TDD: (202) 512-2537: Fax: (202) 512-6061: To Report Fraud, Waste, and Abuse in Federal Programs: Contact: Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov Automated answering system: (800) 424-5454 or (202) 512-7470: Public Affairs: Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S. General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C. 20548: