Project-Based Rental Assistance
HUD Should Streamline Its Processes to Ensure Timely Housing Assistance Payments
Gao ID: GAO-06-57 November 15, 2005
The Department of Housing and Urban Development (HUD) provides subsidies, known as housing assistance payments, under contracts with privately owned, multifamily projects so that they are affordable to low-income households. Project owners have expressed concern that HUD has chronically made late housing assistance payments in recent years, potentially compromising owners'ability to pay operating expenses, make mortgage payments, or set aside funds for repairs. GAO was asked to discuss the timeliness of HUD's monthly housing assistance payments, the factors that affect payment timeliness, and the effects of delayed payments on project owners.
From fiscal years 1995 through 2004, HUD disbursed three-fourths of its monthly housing assistance payments on time, but thousands of payments were late each year, affecting many property owners. Over the 10-year period, 8 percent of payments were delayed by 2 weeks or more. Payments were somewhat more likely to be timely in more recent years. The process for renewing HUD's subsidy contracts with owners can affect the timeliness of housing assistance payments, according to many owners, HUD officials, and contract administrators that HUD hires to work with owners. HUD's renewal process is largely a manual, hard-copy paper process that requires multiple staff to complete. Problems with this cumbersome, paper-intensive process may delay contract renewals and cause late payments. Also, a lack of systematic internal processes for HUD staff to better estimate the amounts that HUD needs to obligate to contracts each year and monitor contract funding levels on an ongoing basis can contribute to delays in housing assistance payments. Although HUD allows owners to borrow from reserve accounts to lessen the effect of delayed housing assistance payments, 3 of 16 project owners told GAO that they had to make late payments on their mortgages or other bills--such as utilities, telephone service, or pest control--as a result of HUD's payment delays. Owners who are heavily reliant on HUD's subsidy to operate their properties are likely to be more severely affected by payment delays than other, more financially stable, owners. Owners reported receiving no warning from HUD when payments would be delayed, and several told GAO that such notification would allow them to mitigate a delay. Nonetheless, project owners, industry group officials, and HUD officials generally agreed that late housing assistance payments would be unlikely to cause an owner to leave HUD's housing assistance programs, because such a decision is generally driven primarily by local market factors.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-06-57, Project-Based Rental Assistance: HUD Should Streamline Its Processes to Ensure Timely Housing Assistance Payments
This is the accessible text file for GAO report number GAO-06-57
entitled 'Project-Based Rental Assistance: HUD Should Streamline Its
Processes to Ensure Timely Housing Assistance Payments' which was
released on December 15, 2005.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to Congressional Requesters:
November 2005:
Project-Based Rental Assistance:
HUD Should Streamline Its Processes to Ensure Timely Housing Assistance
Payments:
GAO-06-57:
GAO Highlights:
Highlights of GAO-06-57, a report to congressional requesters:
Why GAO Did This Study:
The Department of Housing and Urban Development (HUD) provides
subsidies, known as housing assistance payments, under contracts with
privately owned, multifamily projects so that they are affordable to
low-income households. Project owners have expressed concern that HUD
has chronically made late housing assistance payments in recent years,
potentially compromising owners‘ ability to pay operating expenses,
make mortgage payments, or set aside funds for repairs. GAO was asked
to discuss the timeliness of HUD‘s monthly housing assistance payments,
the factors that affect payment timeliness, and the effects of delayed
payments on project owners.
What GAO Found:
From fiscal years 1995 through 2004, HUD disbursed three-fourths of its
monthly housing assistance payments on time, but thousands of payments
were late each year, affecting many property owners. Over the 10-year
period, 8 percent of payments were delayed by 2 weeks or more. Payments
were somewhat more likely to be timely in more recent years (see
figure).
The process for renewing HUD‘s subsidy contracts with owners can affect
the timeliness of housing assistance payments, according to many
owners, HUD officials, and contract administrators that HUD hires to
work with owners. HUD‘s renewal process is largely a manual, hard-copy
paper process that requires multiple staff to complete. Problems with
this cumbersome, paper-intensive process may delay contract renewals
and cause late payments. Also, a lack of systematic internal processes
for HUD staff to better estimate the amounts that HUD needs to obligate
to contracts each year and monitor contract funding levels on an
ongoing basis can contribute to delays in housing assistance payments.
Although HUD allows owners to borrow from reserve accounts to lessen
the effect of delayed housing assistance payments, 3 of 16 project
owners told GAO that they had to make late payments on their mortgages
or other bills”such as utilities, telephone service, or pest control”as
a result of HUD‘s payment delays. Owners who are heavily reliant on
HUD‘s subsidy to operate their properties are likely to be more
severely affected by payment delays than other, more financially
stable, owners. Owners reported receiving no warning from HUD when
payments would be delayed, and several told GAO that such notification
would allow them to mitigate a delay. Nonetheless, project owners,
industry group officials, and HUD officials generally agreed that late
housing assistance payments would be unlikely to cause an owner to
leave HUD‘s housing assistance programs, because such a decision is
generally driven primarily by local market factors.
Timeliness of Housing Assistance Payments (Fiscal Years 1995-2004
Versus 2002-2004):
[See PDF for image]
Note: Percentages do not add to 100 percent due to rounding.
[End of figure]
What GAO Recommends:
GAO is making recommendations to the Secretary of HUD to improve the
timeliness of housing assistance payments and mitigate the effects of
delayed payments. Specifically, GAO recommends that HUD streamline and
automate the contract renewal process to prevent errors and delays. GAO
is also making other recommendations to improve HUD‘s monitoring of
contract funding levels and notifying owners about late payments.
HUD agreed with our conclusions and recommendations.
www.gao.gov/cgi-bin/getrpt?GAO-06-57.
To view the full product, including the scope and methodology, click on
the link above. For more information, contact David G. Wood at (202)
512-8678 or woodd@gao.gov.
[End of section]
Contents:
Letter:
Results in Brief:
Background:
HUD Made Three-fourths of Its Housing Assistance Payments On Time in
Fiscal Years 1995 Through 2004:
Contract Renewals, HUD Funding and Monitoring Issues, and Problems with
Some Owners' Vouchers Contributed to Payment Delays:
HUD's Payment Delays Have Caused Difficulties for Project Owners, but
Are Unlikely to Be a Significant Factor in Owners Opting Out of HUD
Contracts:
Conclusions:
Recommendations for Executive Action:
Agency Comments:
Appendixes:
Appendix I: Scope and Methodology:
Appendix II: Comments from the Department of Housing and Urban
Development:
Appendix III: GAO Contact and Staff Acknowledgments:
Figures:
Figure 1: Contract Administration Flowchart for HUD Multifamily Housing
Assistance Payments
Figure 2: Timeliness of Housing Assistance Payments (Fiscal Years 1995
Through 2004 Versus 2002 Through 2004)
Figure 3: Percentage of Payments That Were 2 Weeks or More Late (Fiscal
Years 1995 Through 2004)
Figure 4: Percentage of Contracts Experiencing at Least 1 Payment
Delayed by 2 Weeks or More (Fiscal Years 1995 Through 2004)
Figure 5: Percentage of Payments That Were 2 Weeks or More Late, by
Contract Administrator (Fiscal Year 2004)
Figure 6: Percentage of PBCA-Administered Payments That Were 2 Weeks or
More Late, by State (Fiscal Year 2004)
Figure 7: Percentage of Contracts Experiencing Chronically Late
Payments, by State (Fiscal Years 2002 Through 2004)
Figure 8: Percentage of Payments That Were 2 Weeks or More Late, by
Reason Code, Fiscal Years 2002 Through 2004, PBCA-and HUD-Administered
Contracts
Figure 9: Contract Renewal Process for PBCA-Administered Contracts
Figure 10: Percentage of Contract Renewals Exceeding 120 Days to
Process (Fiscal Years 2002 Through 2004)
Figure 11: Number of Contract Opt Outs (Fiscal Years 1995 Through
2004):
Abbreviations:
BPR: Business Process Reengineering:
HUD: Department of Housing and Urban Development:
OMHAR: Office of Multifamily Housing Assistance Restructuring:
MAHRA: Multifamily Assisted Housing Reform and Affordability Act of
1997:
PAS: Program Accounting System:
PBCA: performance-based contract administrator:
TRACS: Tenant Rental Assistance Certification System:
Letter November 15, 2005:
The Honorable Michael G. Oxley:
Chairman:
The Honorable Barney Frank:
Ranking Minority Member:
Committee on Financial Services:
House of Representatives:
The Honorable Bob Ney:
Chairman:
The Honorable Maxine Waters:
Ranking Minority Member:
Subcommittee on Housing and Community Opportunity:
Committee on Financial Services:
House of Representatives:
The Department of Housing and Urban Development (HUD) provides rental
assistance subsidies to privately owned, multifamily projects so that
they are affordable to low-income households. In fiscal year 2004, HUD
assisted approximately 1.6 million households through project-based
rental assistance contracts, committing about $4.4 billion to fund
these contracts with property owners. Owners rely on these subsidies
from HUD, often to a great extent, to pay for daily operating expenses,
such as staff salaries and maintenance, as well as to make their
monthly mortgage payments and set aside funds for contingencies and
major repairs. Although HUD's subsidy payments to owners are not
subject to a statutory or regulatory standard for timeliness, HUD's
goal, with some exceptions, is to provide the payments by the 1st
business day of the month.
Project owners, and various associations representing them, have
expressed concern that HUD has been late in paying some owners their
monthly subsidy and that late payments to owners have become a chronic
problem in recent years. According to some owners, late payments can
lead them to defer maintenance, miss payments on monthly utility bills,
or risk default on their mortgages. Furthermore, late payments might
influence owners to "opt out" of HUD's rental assistance programs when
their contracts with HUD expire, potentially resulting in a reduction
of affordable housing units for low-income households.
You asked us to review the effects that late housing assistance
payments may have on project owners and the availability of affordable
housing. Our report discusses (1) the extent to which HUD makes monthly
housing assistance payments in a timely manner, (2) the factors that
affect the timeliness of the payments, and (3) the effect(s) that
payment delays have on project owners and their willingness to continue
providing affordable housing.
To determine the extent to which HUD's housing assistance payments are
timely--that is, disbursed by the 1st business day of the month for
most contracts--we analyzed 10 years (fiscal years 1995 through 2004)
of HUD's monthly payment data. We analyzed trends in these data to
determine whether payment timeliness changed over time and whether
there were differences in payment timeliness by the type of contract
administrator (i.e., whether HUD staff or contractors processed monthly
vouchers). To determine the factors that affect the timeliness of
housing assistance payments, we analyzed the portion of HUD's monthly
payment data (generally, payments made in fiscal years 2002 through
2004) that captured the reasons particular payments were delayed. We
supplemented our analyses by interviewing HUD officials from
headquarters and eight field offices (which were selected to represent
a range of experiences by state--those with high and low percentages of
late payments), contract administrators, project owners, and industry
group officials. To assess the effects of payment delays on project
owners and their willingness to continue providing affordable housing,
we compared available HUD data on projects that opted out of HUD's
programs with monthly payment timeliness data to determine whether
these projects experienced more payment delays than projects that are
currently receiving assistance from HUD. At the HUD field offices where
we did site visits, we interviewed project owners and contract
administrators to determine (1) the reasons owners opted out of HUD's
programs, (2) the extent to which delayed housing assistance payments
may have factored into this decision, and (3) what other effects (e.g.,
financial difficulties) payment delays had on project owners. We also
discussed these issues with HUD and officials from eight industry
associations representing property owners. We conducted our work
between October 2004 and September 2005 in Baltimore, Maryland; Boston,
Massachusetts; Chicago, Illinois; Des Moines, Iowa; Kansas City,
Kansas; Kansas City, Missouri; Los Angeles, California; Manchester, New
Hampshire; Seattle, Washington; and Washington, D.C., in accordance
with generally accepted government auditing standards. Appendix I
provides additional details on our scope and methodology.
Results in Brief:
Most of HUD's housing assistance payments were timely--HUD disbursed by
the due date 75 percent of the 3.2 million monthly payments for fiscal
years 1995 through 2004; however, 25 percent of its payments were late.
For this 10-year period, HUD disbursed 89 percent of these monthly
payments either on time or less than 1 week late. However, 8 percent
(averaging about 25,000 payments per year) were significantly late--
that is, they were delayed by 2 weeks or more, a time frame in which
some owners indicated the late payment could affect their ability to
pay their mortgages on time. HUD made payments on an average of about
26,000 contracts per month. About one-third of these contracts
experienced at least 1 payment per year that was late by 2 weeks or
more. The timeliness of HUD's monthly housing assistance payments
varied over the 10-year period, decreasing in 1998, shortly after HUD
began implementing the Multifamily Assisted Housing Reform and
Affordability Act of 1997, which contained new contract renewal and
processing requirements. Timeliness gradually improved after 2001,
after HUD began using performance-based contract administrators to
administer a majority of the contracts. In the 3-year period of fiscal
years 2002 through 2004, HUD disbursed 79 percent of payments by the
due date, but 7 percent of these payments were significantly late, or
delayed by 2 weeks or more. Timeliness also varied depending on the
type of administrator responsible for processing the payments. In
fiscal year 2004, payments administered by HUD staff were more likely
to be late, while payments on contracts administered by performance-
based or traditional (nonperformance-based) contract administrators
were more likely to be on time. Timeliness also varied by state, based
on our analysis of fiscal year 2004 data.
The primary factors affecting the timeliness of HUD's housing
assistance payments were the process of renewing owners' contracts;
internal HUD processes for funding contracts and monitoring how quickly
each contract uses its funding; and untimely, inaccurate, or incomplete
submissions of monthly vouchers by project owners. First, monthly
housing assistance payments were more likely to be late when owners'
contracts to participate in HUD's programs were not renewed by their
expiration dates, according to HUD officials, property owners, and
contract administrators. Our analysis of available HUD data on the
reasons for some late payments in fiscal years 2002 through 2004 found
that the most common reason for payments that were 2 weeks or more late
was that the payment was being withheld pending contract renewal. HUD
officials and contract administrators said that delays on HUD's part--
stemming from a renewal process HUD officials agreed could be
cumbersome and paper intensive--could cause (or exacerbate) late
payments that result from the failure to have in place a renewal when a
contract reaches its expiration date. The timeliness, quality, and
completeness of owners' renewal submissions could also cause delays in
contract renewals, particularly when an owner's initial contract
expires and it must be renewed for the first time. Second, various
aspects of HUD's internal funding process may contribute to late
payments. HUD does not know exactly how much it will pay owners each
year because the amounts vary with tenant turnover, so HUD estimates
how much funding it needs to obligate, or commit, to each contract and
how quickly the contract will use these funds. However, HUD often
underestimates how much funding a contract will need in a given year,
and the agency lacks consistent processes for field office staff to
monitor contracts and allocate and obligate additional funds when
contracts use funds faster than anticipated. Failure to allocate and
obligate additional funds to contracts promptly can cause payments to
be late. Finally, according to HUD officials and contract
administrators, owners' untimely, inaccurate, or incomplete monthly
voucher submissions may also cause late housing assistance payments.
However, the contract administrators with whom we spoke generally
indicated they were able to correct errors in owners' submissions ahead
of time to ensure timely payments.
According to project owners with whom we met, delays in HUD's housing
assistance payments have had negative financial effects and may have
compromised owners' ability to operate their properties, but the delays
were unlikely to cause owners to opt out of HUD's programs or stop
providing affordable housing. Some owners said they had incurred late
fees on their mortgages and other bills or had experienced
interruptions in services at their properties because of delayed
payments. Effects of delayed payments could vary in severity, depending
on the financial condition of the property owner and the extent to
which the operation of the property was dependent on HUD's subsidy. For
example, a nonprofit owner of a single, fully subsidized property
(i.e., where all units receive a HUD subsidy) may have more difficulty
paying the mortgage or other bills for maintenance of the property than
would an owner with several properties that have a mix of market rate
and subsidized units. HUD allows owners to withdraw funds from their
replacement reserves (funds required to be set aside for future
property repair and capital improvements) to help cover operating
expenses when housing assistance payments are delayed. However, some
properties may not have sufficient reserves to cover such expenses.
Furthermore, owners said that HUD did not notify them of when or for
how long payments would be delayed, which prevented them from taking
steps to mitigate the effects of late payments. The owners and industry
group officials generally agreed that the negative effects of delayed
payments alone would not cause owners to opt out of HUD's programs,
although they could be a contributing factor. They cited market
factors, such as an owner's ability to obtain higher rents outside of
HUD programs, as the primary reason owners might opt out. Most of the
owners with whom we spoke stated that they would not opt out of HUD's
programs, because they are committed to providing affordable housing.
This report contains specific recommendations to the Secretary of HUD
to reduce payment delays associated with contract renewals, to better
estimate and monitor contract funding levels, and to notify owners
about late payments. We provided HUD with a draft of this report for
its review and comment. HUD concurred with our conclusions and
recommendations.
Background:
HUD operates a variety of project-based rental assistance programs
through which it pays subsidies, or housing assistance payments, to
private owners of multifamily housing that help make this housing
affordable for lower income households. In some cases, HUD subsidized
the construction of the housing (or substantial rehabilitation of
existing properties) through means such as discounted mortgages insured
by HUD's Federal Housing Administration; in others, such as the Section
202 Supportive Housing for the Elderly Program, HUD provided grants to
construct the housing. HUD entered into long-term contracts, often 20
to 40 years, committing it and the property owners to providing long-
term affordable housing. Under these contracts, tenants generally pay
30 percent of their adjusted income toward their rents, with the HUD
subsidy equal to the difference between what the tenants pay and the
contract rents that HUD and the owners negotiate in advance.
In the mid-to late-1990s, Congress and HUD made several important
changes to the duration of housing assistance contract terms (and the
budgeting for them), the contract rents owners would receive relative
to local market conditions, and the manner in which HUD administers its
ongoing project-based housing assistance contracts. Specifically:
* Because of budgetary constraints, HUD shortened the terms of
subsequent renewals, after the initial 20-to 40-year terms began
expiring in the mid-1990s. HUD reduced the contract terms to 1 or 5
years, with the funding renewed annually subject to
appropriations.[Footnote 1]
* Second, in 1997, Congress passed the Multifamily Assisted Housing
Reform and Affordability Act (MAHRA), as amended, in an effort, among
other things, to ensure that the rents HUD subsidizes remain comparable
with market rents.[Footnote 2] Over the course of the initial longer
term agreements with owners, contract rents in some cases came to
substantially exceed local market rents. MAHRA required an assessment
of each project when it neared the end of its original contract term to
determine whether the contract rents were comparable to current market
rents and whether the project had sufficient cash flow to meet its debt
as well as daily and long-term operating expenses. If the expiring
contract rents were below market rates, HUD could increase the contract
rents to market rates upon renewal (i.e., "mark up to market").
Conversely, HUD could decrease the contract rents upon renewal if they
were higher than market rents (i.e., "mark down to market").[Footnote
3]
* Finally, in 1999, because of staffing constraints (primarily in HUD's
field offices) and the workload involved in renewing the increasing
numbers of rental assistance contracts reaching the end of their
initial terms, HUD began an initiative to contract out the oversight
and administration of most of its project-based contracts. The entities
that HUD hired--typically public housing authorities or state housing
finance agencies--are responsible for conducting on-site management
reviews of assisted properties; adjusting contract rents; reviewing,
processing, and paying monthly vouchers submitted by owners; renewing
contracts with property owners; and responding to health and safety
issues at the properties. These performance-based contract
administrators (PBCA) now administer the majority of contracts--over
13,000 of approximately 23,000 contracts in fiscal year 2004.
According to HUD officials, the department has not yet transferred all
of its rental assistance contracts to the PBCAs. HUD plans to have
traditional, or nonperformance-based contractors, continue to
administer the approximately 5,000 contracts that they were
administering until these contracts expire; at which time, these
contracts will be assigned to the PBCAs. The traditional contract
administrators are, often, local public housing authorities handling a
very limited number of contracts. HUD itself also administers the
contracts under certain programs, such as the Section 202 Supportive
Housing for the Elderly Program and the Section 811 Supportive Housing
for Persons with Disabilities Program. HUD announced in April 2004 that
it was conducting a competitive sourcing effort to determine the most
efficient and cost-effective means to administer some of these
contracts. At the conclusion of this effort, HUD will seek new budget
authority to pay for contract administration services. Consequently,
while the PBCAs handle most of HUD's project-based housing, three types
of administrators are involved in day-to-day program oversight and
administration, including tasks involved in processing monthly housing
assistance payments.
To receive their monthly housing assistance payments, owners must
submit monthly vouchers to account for changes in occupancy and
tenants' incomes that affect the actual amount of subsidy due. However,
the manner in which the owners submit these vouchers and the process by
which they get paid varies depending on which of the three types of
contract administrators handles their contract (see fig. 1). For HUD-
administered contracts, the owner submits a monthly voucher to HUD for
verification, and HUD in turn pays the owner based on the amount in the
voucher. For PBCA-administered contracts, the owner submits a monthly
voucher to the PBCA, which verifies the voucher and forwards it to HUD
for payment. HUD then transfers the amount verified on the voucher to
the PBCA, which in turn pays the owner. In contrast, for traditionally
administered contracts, HUD and the contract administrator develop a
yearly budget, and HUD pays the contract administrator set monthly
payments. The owner submits monthly vouchers to the contract
administrator for verification, and the contract administrator pays the
amount approved on the voucher. At the end of the year, HUD and the
contract administrator reconcile the payments HUD made to the contract
administrator with the amounts the contract administrator paid to the
owner, exchanging payment as necessary to settle any difference.
Figure 1: Contract Administration Flowchart for HUD Multifamily Housing
Assistance Payments:
[See PDF for image]
[A] HUD is responsible for verifying vouchers submitted under HUD-
administered contracts, not PBCA-administered and traditionally
administered contracts.
[B] Unlike PBCA-administered contracts, for traditionally administered
contracts HUD pays the contract administrator a fixed monthly payment
on the basis of an annual budget, rather than monthly voucher amounts.
Payments are reconciled at the end of the year.
[End of figure]
HUD has an ongoing effort to improve its rental assistance programs'
business processes and make better use of information technology
related to those programs. In 2004, HUD launched a Business Process
Reengineering (BPR) initiative to, among other things, improve
inefficient and redundant processes, as identified by HUD's contractor
for this effort, and to integrate HUD's data systems. HUD expects its
contractor to identify its recommended changes by June 2006. According
to HUD officials, HUD does not currently have the funding in place to
implement the BPR.
HUD Made Three-fourths of Its Housing Assistance Payments On Time in
Fiscal Years 1995 Through 2004:
Between fiscal years 1995 and 2004, HUD disbursed three-fourths of its
monthly housing assistance payments by the due date, but thousands of
payments each year were late, affecting many property owners.[Footnote
4] For this 10-year period, about 8 percent of all payments were
delayed by 2 weeks or more, a time frame we characterize as
significant. On average, about one-third of housing assistance
contracts experienced at least 1 payment per year that was delayed by 2
weeks or more. Furthermore, the timeliness of housing assistance
payments has varied, with a decrease in 1998, but with a gradual
improvement since 2001. Timeliness also varied by type of contract
administrator, with payments for HUD-administered contracts more likely
to be late, based on our analysis of fiscal year 2004 payment data.
Timeliness varied considerably by state as well.
Over a 10-Year Period, 75 Percent of HUD's Payments Were On Time, but 8
Percent Were Significantly Late:
Overall, from fiscal years 1995 through 2004, HUD disbursed by the due
date 75 percent of the 3.2 million monthly housing assistance payments
on all types of contracts (see fig. 2). However, 8 percent of payments,
averaging 25,000 per year, were significantly late--that is, they were
delayed by 2 weeks or more and therefore could have negative effects on
owners who relied on HUD's subsidy to pay their mortgages. During this
period, 6 percent of the total payments (averaging 18,000 per year)
were 4 weeks or more late, including about 10,000 payments per year
that were 8 weeks or more late.
Figure 2: Timeliness of Housing Assistance Payments (Fiscal Years 1995
Through 2004 Versus 2002 Through 2004):
[See PDF for image]
Note: Percentages do not add to 100 percent due to rounding. Data
include HUD-administered, PBCA-administered, and traditionally
administered contracts.
[End of figure]
HUD does not have an overall timeliness standard by which it makes
payments to owners or its contract administrators, based in statute,
regulation, or HUD guidance. However, HUD contractually requires the
PBCAs (which administer the majority of contracts) to pay owners no
later than the 1st business day of the month. HUD officials said that
they also use this standard informally to determine the timeliness of
payments on HUD-administered and traditionally administered
contracts.[Footnote 5] Therefore, we considered payments to be timely
if they were disbursed by the 1st business day of the month. Based on
our discussions with project owners who reported that they relied on
HUD's assistance to pay their mortgages before they incurred late fees
(generally, after the 15TH day of the month), we determined that a
payment delay of 2 weeks or more was significant.
The Timeliness of Payments Has Varied over a 10-Year Period:
The timeliness of housing assistance payments over the 10-year period
(fiscal years 1995 through 2004) has shown some variation (see fig. 3).
The percentage of payments that were significantly late increased in
1998, which HUD and PBCA officials indicated likely had to do with
HUD's initial implementation of MAHRA and new contract renewal
procedures and processing requirements for project owners. Timeliness
has gradually improved since 2001, shortly after HUD first began using
the PBCAs to administer contracts.
Figure 3: Percentage of Payments That Were 2 Weeks or More Late (Fiscal
Years 1995 Through 2004):
[See PDF for image]
Note: Ten-year total number of payments: 3,212,982.
[End of figure]
The percentage of contracts experiencing significantly late payments
over the course of the year showed a similar variation over the 10-year
period, rising to 43 percent in fiscal year 1998 and decreasing to 30
percent in fiscal year 2004 (see fig. 4). As with the percentage of
late payments, the percentage of contracts with late payments increased
in fiscal year 1998 when HUD implemented requirements pursuant to
MAHRA. Over the 10-year period, about one-third of approximately 26,000
contracts experienced at least 1 payment per year that was delayed by 2
weeks or more.
Figure 4: Percentage of Contracts Experiencing at Least 1 Payment
Delayed by 2 Weeks or More (Fiscal Years 1995 Through 2004):
[See PDF for image]
Note: Ten-year average: 32 percent.
[End of figure]
Although HUD data showed a gradual decline in the percentage of late
payments and the number of contracts affected by late payments, in the
most recent 3-year period (fiscal years 2002 through 2004), the
percentage of payments that were 2 weeks or more and 4 weeks or more
late was nearly as high (7 percent and 5 percent) as over the 10-year
period (see fig. 2).
The Timeliness of Payments Varied Based on the Type of Contract
Administration:
Payments on HUD-administered contracts were more likely to be delayed
than those on contracts administered by the PBCAs and traditional
contract administrators, based on HUD's fiscal year 2004 payment data
(see fig. 5).
Figure 5: Percentage of Payments That Were 2 Weeks or More Late, by
Contract Administrator (Fiscal Year 2004):
[See PDF for image]
Note: Categorization by type of administrator is based on HUD contract
administration data as of February 2005. We limited our analysis to
2004 because the data from HUD do not allow us to identify for prior
fiscal years which type of contract administrator was responsible for
each contract and because, over the course of these years, HUD was in
the process of transferring contract administration responsibilities.
For a small number of the payments characterized as PBCA-administered
in this figure, HUD may have transferred processing to the PBCA during
the fiscal year.
[End of figure]
Payments on PBCA-and HUD-administered contracts have more elaborate
monthly processing requirements than do the payments on traditionally
administered contracts that HUD processes. Payments on PBCA-and HUD-
administered contracts require that the monthly vouchers be reviewed
and processed by a PBCA or HUD field office before a payment is
approved. As previously noted, for traditionally administered
contracts, HUD creates an annual budget, amortizes the budget over 12
payments for the year, disburses the set monthly payments, and makes
any necessary adjustments through a year-end settlement based on
voucher information submitted to the traditional contract
administrators.
The percentage of chronically late payments also varied by contract
administrator.[Footnote 6] In fiscal year 2004, 9 percent of HUD-
administered contracts experienced chronic late payments, while 3
percent of PBCA-administered contracts and 1 percent of the
traditionally administered contracts had chronic late payments.
Payment Timeliness Also Varied by State:
We analyzed HUD's payment data by state and found that timeliness
varied considerably for both PBCA-and HUD-administered contracts,
although the reasons for this variation are not clear. The percentage
of payments on PBCA-administered contracts that were 2 weeks or more
late in fiscal year 2004 ranged from 1 percent in North Dakota to 13
percent in the District of Columbia (see fig. 6). With some exceptions,
a single PBCA administers all of the PBCA-administered contracts for a
single state. However, late payments may be attributable to a number of
factors, and the HUD payment data do not provide an explanation for the
variations among the states.
Figure 6: Percentage of PBCA-Administered Payments That Were 2 Weeks or
More Late, by State (Fiscal Year 2004):
[See PDF for image]
[End of figure]
For HUD-administered contracts, 19 states had 15 percent or more of
their payments that were 2 weeks or more late in 2004. The percentage
of payments 2 weeks or more late ranged from 2 percent in North Dakota
to 35 percent in Wyoming. Again, the HUD payment data do not provide an
explanation for the state variation in payment delays.
The percentage of contracts that experienced chronic late payments also
varied by state. In fiscal years 2002 through 2004, 17 percent of the
contracts in Delaware and 13 percent in Connecticut and the District of
Columbia had 6 or more payments per year that were 2 weeks or more late
(see fig. 7). In contrast, less than 3 percent of contracts in most
states had chronic late payments.
Figure 7: Percentage of Contracts Experiencing Chronically Late
Payments, by State (Fiscal Years 2002 Through 2004):
[See PDF for image]
[End of figure]
Contract Renewals, HUD Funding and Monitoring Issues, and Problems with
Some Owners' Vouchers Contributed to Payment Delays:
The contract renewal process, HUD's internal processes for funding and
monitoring contracts, and owners' erroneous or untimely voucher
submissions affected payment timeliness. For instance, owners were more
likely to receive late monthly payments when their contracts with HUD
had not been renewed by their expiration dates. Moreover, HUD's process
of estimating how much funding it needs to obligate to contracts; HUD's
inconsistent approach to monitoring contracts to determine when
additional funding should be obligated; and lack of staff access to,
and training on, HUD payment databases also may have affected the
timeliness of housing assistance payments. Additionally, HUD's
interpretation of legislative restrictions on its ability to use
recaptured funds may have exacerbated payment delays. Finally, owners'
erroneous or untimely submissions of monthly vouchers could have caused
some of the untimely payments from HUD.
Payment Delays Were More Likely When a Contract Renewal Was Pending:
Late monthly voucher payments were more likely to occur when a contract
had not been renewed by its expiration date, according to many of the
HUD officials, contract administrators, and property owners with whom
we spoke. HUD's accounting systems require that an active contract be
in place with funding obligated to it before it can release payments
for that contract. Therefore, an owner cannot receive a monthly voucher
payment on a contract that HUD has not renewed.
Our analysis of HUD data from fiscal years 2002 through 2004 shows that
60 percent of the payments that were 2 weeks or more late was
associated with pending contract renewals, among late payments on PBCA-
and HUD-administered contracts for which HUD recorded the reason for
the delay (see fig. 8).[Footnote 7]
Figure 8: Percentage of Payments That Were 2 Weeks or More Late, by
Reason Code, Fiscal Years 2002 Through 2004, PBCA-and HUD-Administered
Contracts:
[See PDF for image]
Note: Of the 62,851 PBCA-and HUD-administered payments that were 2
weeks or more late during this 3-year period, HUD's database included a
reason code for 34,828, or 55 percent. The "other" category includes
pending verification of bank information, pending HUD review of a rent
increase, insufficient tenant data, or other missing data on owners'
payment vouchers. We excluded payments on traditionally administered
contracts because HUD does not collect data on the reasons for delays.
[End of figure]
A contract renewal may be "pending" when one or more parties involved
in the process--HUD, the PBCA, or the owner--have not completed the
necessary steps to finalize the renewal. Based on our interviews with
HUD officials, contract administrators, and owners, pending contract
renewals may result from owners' failing to submit their renewal
packages on time. Often the delay occurs when owners must submit a
study of market rents, completed by a certified appraiser, in order to
determine the market rent levels. However, late payments associated
with contract renewals may also occur because HUD has not completed its
required processing. For example, according to a HUD official, at one
field office we visited, contract renewals were delayed because HUD
field staff were behind in updating necessary information, such as the
new rent schedules associated with the renewals and the contract
execution dates in HUD payment systems.
HUD's contract renewal process itself also may take longer than
expected, contributing to late housing assistance payments, because the
process is largely manual and paper driven and requires multiple staff
in the PBCAs and HUD to complete (see fig. 9). Upon receipt of renewal
packages from owners, the PBCAs then prepare and forward signed
contracts (in hard copy) to HUD field offices, which execute the
contracts; in turn, the field offices send hard copies of contracts to
a HUD accounting center, which activates contract funding. In order to
allow sufficient time to complete the necessary processing, HUD's
policy currently requires owners to submit a renewal package to their
PBCAs 120 days before a contract expires, and gives the PBCAs 30 days
to forward the renewal package to HUD for completion (leaving HUD 90
days for processing). However, some of the owners with whom we spoke
told us that their contract renewals had not been completed by the
contract expiration dates, even though they had submitted their renewal
packages on time.
Figure 9: Contract Renewal Process for PBCA-Administered Contracts:
[See PDF for image]
[End of figure]
While initial contract renewals (upon expiration of the owner's initial
long-term contract) often exceeded the 120-day processing time,
subsequent renewals were less time-consuming and resulted in fewer
delays, according to HUD officials, the PBCAs, and owners. Initial
renewals could be challenging for owners because they often involved
HUD's reassessment of whether the contract rents were in line with
market rents. Additionally, the initial renewal represents the first
time that owners have to provide HUD with the extensive documentation
required for contract renewals in order to continue receiving housing
assistance payments. Our analysis of the most recent 3 years of HUD
data (fiscal years 2002 through 2004) shows that while 25 percent of
initial contract renewals exceeded the 120-day processing time frame
set by HUD, 17 percent of subsequent renewals exceeded that time frame,
as shown in figure 10. Increased timeliness on subsequent renewals
might be explained partly by owners' gaining competency--that is, the
PBCAs and owners described a "learning curve" when owners renewed their
contracts for the first time.
Figure 10: Percentage of Contract Renewals Exceeding 120 Days to
Process (Fiscal Years 2002 Through 2004):
[See PDF for image]
Note: HUD allows 120 days to process renewals.
[End of figure]
The processing times for contract renewals that HUD's data show do not
include some interactions between the PBCAs and owners. More
specifically, HUD's data systems capture the dates on which it receives
completed renewal packages from the PBCAs, but do not capture the dates
for earlier steps in the process. For instance, the data systems do not
capture the dates when owners initially submit renewal packages to the
PBCAs and, thus, the amount of time it may take the PBCAs and owners to
go "back and forth" to assemble completed packages.
According to our analysis, the processing time for the contract
renewals also was likely to exceed HUD's 120-day standard when owners
chose or were subject to one of two options at their initial renewals.
First, for properties with contract rents lower than comparable market
rents, owners had the option to request contract renewals under the
"mark-up-to-market" option, which required (1) owners to obtain an
appraiser's determination of comparable market rents and (2) HUD to
reassess the contract rents in order to raise them to applicable market
level rents. For fiscal years 2002 through 2004, 60 percent of the 471
contract renewals using the mark-up-to-market option took more than the
expected 120 days. Second, for expiring contracts with rents higher
than comparable market rents, contract administrators referred the
owners to HUD's Office of Multifamily Housing Assistance Restructuring
(OMHAR), a process that can lead to rents in renewed contracts that are
lower than those in the expiring contracts (the "mark-to-market"
option).[Footnote 8] For fiscal years 2002 through 2004, 56 percent of
the 1,276 contract renewals referred to OMHAR to reduce rents--and, in
many cases, to restructure the property owners' debt--took more than
the expected 120 days to process.
Recognizing that contract renewal is lengthy and cumbersome, HUD's goal
is to automate the renewal process and reduce the 120-day time frame
through a BPR effort for its rental assistance programs. HUD launched
this initiative in 2004 to, among other things, develop plans to
improve what it characterizes as "inefficient or redundant processes"
and to integrate data systems. For example, according to a senior HUD
official, the department's goal is to automate the entire contract
renewal process by 2007, eliminating the need for HUD and owners to
physically sign the contracts. According to HUD officials, this effort
would eventually include a more streamlined and automated contract
renewal process. However, this effort is in its early stages, and is
currently not focused on streamlining the contract renewal process or
addressing the problem of late housing assistance payments. HUD does
not have concrete plans regarding how it will accomplish these goals,
nor does it have funding in place to implement any of the
recommendations the reengineering effort might develop.
HUD's Difficulties in Assessing Rate of Funding Use and Monitoring
Funding Levels May Have Affected Timeliness of Housing Assistance
Payments:
The methods HUD uses to estimate the amount of funds needed for the
term of each of its project-based assistance contracts and the way it
monitors the funding levels on those contracts may also affect the
timeliness of housing assistance payments. When HUD renews a contract,
and when it obligates[Footnote 9] additional funding for each year of
contracts with 5-year terms, it obligates an estimate of the actual
subsidy payments to which the owner will be entitled over the course of
a year. However, those estimates are often too low, according to HUD
headquarters and field office officials and contract administrators.
For example, an underestimate of rent increases or utility costs or a
change in household demographics or incomes at a property will affect
the rate at which a contract exhausts its funds, potentially causing
the contract to need additional funds obligated to it before the end of
the year. If HUD underestimates the subsidy payments, the department
needs to allocate more funds to the contract and adjust its obligation
upwards to make all of the monthly payments.
Throughout the year, HUD headquarters uses a "burn-rate calculation" to
monitor the rate at which a contract exhausts or "burns" the obligated
funds and to identify those contracts that may have too little (or too
much) funding. According to some HUD field office and PBCA officials,
they also proactively monitor contract fund levels. Based on the rate
at which a contract exhausts its funds, HUD obligates more funds if
needed.
However, based on our analysis of available HUD data and our
discussions with HUD field office officials, owners, and contract
administrators, payments on some contracts were still delayed because
they needed to have additional funds allocated and obligated before a
payment could be made. As shown in figure 8, our analysis of HUD's
payment data shows that, where the reasons for delayed payments on PBCA-
and HUD-administered contracts were available, 11 percent of delays of
2 weeks or more were due to contracts needing additional funds
obligated. That is, those payments were delayed because, at the time
the owners' vouchers were processed, HUD had not allocated and
obligated enough funding to the contracts to cover the payments.
One potential factor contributing to payment delays related to
obligating contract funding is likely that staff at some HUD field
offices--unlike their counterparts in other field offices and staff at
some of the PBCAs--did not have access to data systems or were not
trained to use them to monitor funding levels. At some of the field
offices we visited, officials reported that they did not have access to
the HUD data systems that would allow them to adequately monitor
contract funding levels. For example, one field office official told us
that he needed access to one of HUD's accounting data systems to more
accurately monitor contract funding. According to this official, he
requested "read-only" access to this system, which requires a security
clearance, but never received information on the status of his
application from HUD headquarters. HUD field offices reported, and
headquarters confirmed, that some field officials have not received
training to carry out some functions critical to monitoring the burn
rate. One field office official reported that none of the staff in her
office had received training in a payment processing database, which is
critical for monitoring the status of monthly payments. A HUD
headquarters official reported that changes in the agency's workforce
demographics posed challenges because not all of the field offices have
staff with an optimal mix of skill and experience.
According to a senior HUD official, HUD's BPR is intended to provide a
systematic, agencywide solution to the contract funding issues that
field office officials have been trying to address on an ad hoc basis
to prevent payment delays. If this effort successfully addresses
contract funding monitoring agencywide through automation, as this
official suggested, HUD may not have to rely solely on the intervention
of its field officials.
HUD's Interpretation of Legislative Restrictions on Its Ability to Use
Recaptured Funds May Have Exacerbated Payment Delays:
Prior to fiscal year 2003, HUD used funds that it had recaptured from
some contracts to augment other contracts that required additional
funds.[Footnote 10] Based on HUD's interpretation of its appropriations
acts for fiscal years 2003 and 2004, the agency determined that
recaptured funds were not available in those years to fund contract
amendments.[Footnote 11] According to HUD officials, this made it
difficult to budget for amendments in those years and could have
affected the timeliness with which HUD funded some contracts and made
related housing assistance payments. HUD's fiscal year 2005
appropriation specifically authorized the use of recaptured funds for
contract amendments.[Footnote 12]
According to HUD headquarters officials, operating under a continuing
resolution rather than an appropriation should not affect the
timeliness of housing assistance payments.[Footnote 13] According to
HUD budget officials, under a continuing resolution, HUD has funding
available to meet its contractual obligations to pay project owners
and, if need be, to renew rental assistance contracts.[Footnote 14]
Owners' Untimely, Inaccurate, or Incomplete Submissions May Have
Affected the Timeliness of Housing Assistance Payments:
The PBCAs with which we met estimated that 10 to 20 percent of owners
submit late vouchers each month. For example, one PBCA reported that
about 20 percent of the payments it processed in 2004 were delayed due
to late owner submissions. However, the PBCAs also reported that they
generally could process vouchers in less than the allowable time--20
days--agreed to in their contracts with HUD and resolve any errors with
owners to prevent a payment delay. According to PBCA officials, there
are often several "back-and-forth" interactions with owners to resolve
errors or inaccuracies. Typical owner submission errors include failing
to account correctly for changes in the number of tenants or tenant
income levels, or failing to provide required documentation. As we
previously noted, because HUD's data systems do not capture the back-
and-forth interactions PBCA officials described to us, we could not
directly measure the extent to which owners' original voucher
submissions may have been late, inaccurate, or incomplete.
HUD officials and the PBCAs reported that owners had a learning curve
when contracts were transferred to the PBCAs because the PBCAs reviewed
monthly voucher submissions with greater scrutiny than HUD had in the
past. The timeliness of payments may also be affected by a PBCA's own
internal policies for addressing owner errors. For example, in order to
prevent payment delays, some of the PBCA officials with whom we spoke
told us that they often process vouchers in advance of receiving
complete information on the owners' vouchers. In contrast, at one of
the PBCAs we visited, officials told us that they will not process an
owner's voucher for payment unless it fully meets all of HUD's
requirements.
HUD's Payment Delays Have Caused Difficulties for Project Owners, but
Are Unlikely to Be a Significant Factor in Owners Opting Out of HUD
Contracts:
HUD's payment delays have had negative financial effects on project
owners, but they are unlikely to result in owners opting out of HUD's
programs. Owners with whom we spoke reported that they have incurred
late fees on their mortgages and other bills and have had difficulty
operating their properties as a result of payment delays. The severity
of the effects depended on the financial condition of the property
owner and the extent to which the owner relied on HUD's subsidy to make
the mortgage payment and operate the property. HUD did not notify
owners when payments would be late, and owners said that this lack of
notice exacerbated the effect of late payments. However, delayed
payments alone were unlikely to result in opt outs, although they could
have been a contributing factor, according to owners as well as
officials from industry groups and HUD. Finally, our analysis of HUD
payment data indicated that there was little difference in payment
delays between properties that have opted out of, and those that still
participate in, HUD's programs.
Some Owners Report Difficulties in Paying Mortgages and Other Bills and
Operating Their Properties as a Result of Payment Delays:
Some owners report that they have not been able to pay their mortgages
or other bills on time as a result of HUD's payment delays.[Footnote
15] Three of the 16 owners with whom we spoke reported having to pay
their mortgages or other bills late as a result of HUD's payment
delays. One owner reported that he was in danger of defaulting on one
of his properties as a direct result of late housing assistance
payments. Another owner reported having paid $4,000 in late fees to a
utility company because she was unable to pay the bill on time. Another
owner was unable to provide full payments to vendors, including
utilities, telephone service, plumbers, landscapers, and pest control
services during a 3-month delay in receiving housing assistance
payments. According to this owner, her telephone service was
interrupted during the delay and her relationship with some of her
vendors suffered. For example, the pest control and plumbing vendors
would continue to provide services only if they received cash in
advance. This owner also expressed concern about how the late and
partial payments to vendors would affect her credit rating. Industry
groups with whom we spoke also raised concerns about their members'
inability to pay mortgages and other bills when HUD's housing
assistance payments were delayed.
If owners are unable to pay their vendors or their staff, services to
the property and the condition of the property could suffer. At one
affordable housing project for seniors that we visited, the utility
services had been interrupted because of the owner's inability to make
the payments. At the same property, the owner told us that she could
not purchase cleaning supplies and had to borrow supplies from another
property. One of the 16 owners with whom we spoke told us that they
were getting ready to furlough staff during the time that they were not
receiving payments from HUD. According to one HUD field office
official, owners have complained about not being able to pay for needed
repairs or garbage removal while they were waiting to receive a housing
assistance payment. According to one industry group official, payment
delays could result in the gradual decline of the condition of the
properties in instances where owners were unable to pay for needed
repairs.
Effects of Delayed Payments on Owners Varied Based on Several Factors,
Particularly the Owners' Financial Condition and Degree of Reliance on
HUD's Subsidy:
According to owners as well as industry group and HUD officials, owners
who are heavily reliant on HUD's subsidy to operate their properties
are more severely affected by payment delays than other owners.
Particularly, owners who own only one or a few properties and whose
operations are completely or heavily reliant on HUD's subsidies have
the most difficulty weathering a delay. Two of the 16 owners with whom
we spoke reported that they could not pay their bills and operate the
properties during a payment delay. These owners were nonprofits, each
operating a single property occupied by low-income seniors. In both
cases, the amount of rent they were receiving from the residents was
insufficient to pay the mortgage and other bills. Neither of these
owners had additional sources of revenue.
In contrast, owners with several properties and other sources of
revenue were less severely affected by HUD's payment delays. Three of
the owners with whom we spoke reported that they were able to borrow
funds from their other properties or find other funding sources to
cover the mortgage payments and other bills. All 3 of these owners had
a mix of affordable and market rate properties. According to HUD and
PBCA officials, owners who receive a mix of subsidized and market rate
rents from their properties would not be as severely affected by a
payment delay as owners with all subsidized units. For example,
representatives of 2 of the owners stated that they did not have to
take any measures to address delays in housing assistance. One owner is
an investment firm for a pension fund that maintains a large portfolio
of mostly market rate properties. According to a representative of the
firm, delayed housing assistance payments had not caused financial
difficulties, but the delay had presented accounting difficulties for
the firm. The other owner is a nonprofit with several properties.
According to a representative of the owner, the rents paid by the
residents of all of the properties were a larger part of the
nonprofit's revenue than the HUD subsidy, so the nonprofit was not
negatively affected by an occasional delay in housing assistance
payments.
HUD allows owners to borrow from their reserve accounts to help
mitigate the effects of delayed housing assistance payments, but some
owners either do not have reserves or their reserves are not sufficient
to cover the period of the delay. HUD requires HUD-insured properties
and properties with HUD-held mortgages to set aside funds in a reserve
account, which is designed primarily to help fund capital improvements
on the properties. HUD also allows owners to withdraw funds from this
account in the event of HUD's payment delays, so that owners are able
to make their mortgage payments. However, properties that are not
insured by HUD and do not have a HUD-held mortgage may not have a
reserve account, and, according to HUD and industry group officials,
owners with small or newer properties may not have sufficient reserves
to cover delays. Even if the reserves were sufficient, industry group
officials have pointed out that owners might have to defer capital
improvements during payment delays, and also lose interest that they
would otherwise accrue in the reserve account. Some projects also have
a residual receipts account from which owners may borrow. HUD requires
nonprofits and limited dividend multifamily projects that are HUD-
insured or have a HUD-held mortgage to maintain a residual receipts
account for monies beyond the owner's maximum allowable distribution or
profit.[Footnote 16]
Lack of Notice about Payment Dates and Lengths of Delays Has
Exacerbated Problems for Owners:
HUD has no system for notifying owners when a payment delay will occur
or when it will be resolved, which industry associations representing
many owners as well as the owners with whom we met indicated impedes
their ability to adequately plan to cover expenses until receiving the
late payment. Most of the owners with whom we spoke reported that they
received no warning from HUD that their payments would be delayed.
Several of the owners told us that notification of the delay and the
length of the delay would give them the ability to decide how to
mitigate the effects of a late payment. For example, owners could then
immediately request access to reserve accounts if the delay were long
enough to prevent them from paying their mortgages or other bills on
time. Industry group officials with whom we met agreed that a
notification of a delayed payment would benefit their members.
Delayed Housing Assistance Payments Were Unlikely to Cause Owners to
Opt Out of HUD's Programs or Discontinue Involvement in Providing
Affordable Housing:
Project owners, industry group officials, contract administrators, and
HUD officials we interviewed generally agreed that market factors
primarily drove an owner's decision to opt out of HUD programs. Owners
generally opt out when they can receive higher market rents or when it
is financially advantageous to convert their properties to
condominiums. In previous work, we reported that financial and market
considerations were factors likely to affect owners' decisions to opt
out of HUD's programs.[Footnote 17] For profit-motivated owners, this
decision can be influenced by the condition of the property and the
income levels of the surrounding neighborhood. Owners were more likely
to opt out if they could upgrade their properties at a reasonable cost
to convert them to condominiums or rental units for higher income
tenants.
Most of the owners with whom we spoke, including some profit-motivated
owners, reported that they would not opt out of HUD programs because of
their commitment to providing affordable housing. Industry group
officials also stated that most of their members are "mission driven,"
or committed to providing affordable housing.
According to some owners with whom we spoke, owners have accepted
payment delays as the price of doing business with HUD. However,
industry group and HUD officials stated that delayed payments could be
a contributing factor in some opt outs. According to HUD officials,
owners with primarily market rents in their buildings were more likely
to opt out because the owners felt that the rents from subsidized units
were not worth the burden of HUD's documentation and reporting
requirements. Only 1 (a real estate investment firm for a pension fund)
of the 16 owners we interviewed stated that the firm would opt out of
HUD programs if the payment delays were longer. According to
representatives of this firm, their company has a fiduciary
responsibility to the pension fund. If they began losing money on their
affordable housing projects, they would have to sell them.
Our analysis of HUD's monthly payment data for fiscal years 1995
through 2004 revealed little difference in the percentage of late
payments for those contracts that opted out and those still
participating in HUD's programs (9.6 percent and 9.2 percent,
respectively). In addition, we found that over the 10-year period,
1,764 housing assistance contracts out of the 13,051 that were eligible
to do so opted out of HUD's programs. These opt outs represented 1,460
affordable housing projects (a project may have more than 1 contract,
hence the number of contracts exceeds the number of projects). The
number of contracts opting out over this period peaked in fiscal year
1998, with 392 contracts opting out, and gradually declined to 54 in
fiscal year 2004 (see fig. 11).
Figure 11: Number of Contract Opt Outs (Fiscal Years 1995 Through
2004):
[See PDF for image]
Note: Ten-year total: 1,764.
[End of figure]
The number of opt outs likely declined after the passage of MAHRA and
HUD's subsequent efforts to preserve affordable housing by allowing
owners to increase the contract rents with HUD to market rates, thereby
making it more financially viable for owners to continue participating
in HUD's programs.
Conclusions:
HUD plays an important role in ensuring the continued availability of
affordable housing by providing subsidies to owners of multifamily
rental properties and encouraging owners to remain in its programs.
Over the 10-year period we examined, HUD made most payments on time--
that is, by the 1stbusiness day of the month. However, a significant
percentage of HUD's payments were late. The delays, particularly those
of 2 weeks or more, can cause financial hardships for property owners.
For example, the subsidies not only help pay mortgages, but also the
daily operating expenses of many owners. In retrospect, new
requirements under MAHRA and the transition to a new system of contract
administration likely increased delays, particularly in the late 1990s.
The initial difficulties in implementing MAHRA requirements have
abated, and HUD largely has completed the transition to performance-
based contract administration. However, while the timeliness of housing
assistance payments has improved in recent years, the number of
significantly late payments remains a concern.
Although HUD has made changes to improve contract administration, it
has not comprehensively addressed the factors that most affect the
timeliness of payments--that is, its contract renewal and contract
funding and monitoring processes. HUD has recognized that its contract
renewal process is cumbersome and inefficient and wants to cut contract
processing time as one goal of a broader BPR effort. However, that
effort has just gotten under way and currently is not closely focused
on the housing assistance payment process. As a result, if HUD were to
rely solely on the reengineering effort, it would miss opportunities to
effect more immediate improvements to the processing of contract
renewals. In addition, HUD effectively could prevent many delayed
payments by better estimating the amounts it needs to obligate to
contracts each year, more systematically monitoring contract funding
levels on an ongoing basis, and promptly allocating and obligating
additional funding to contracts when necessary. Currently, while
contract funding needs can increase for unforeseen reasons, HUD often
underestimates how much funding a contract will need when it obligates
funds at the beginning of a year. Furthermore, HUD's existing
monitoring has not prevented payment delays associated with contracts
needing additional funding obligated in order for HUD to pay the owner.
As previously noted, HUD has opportunities to improve its contract
processes and avoid the often damaging disruptions late payments could
cause. While project owners and industry groups have indicated that
late housing payments alone would not lead them to opt out of HUD
programs, late housing assistance payments have serious consequences
for owners and potentially for the residents they serve. But, HUD also
has opportunities to mitigate the effects of payments that it cannot
make on time. More specifically, if HUD were to notify project owners
of delays and their likely duration, owners could make contingency
plans or otherwise address the delayed payments.
Recommendations for Executive Action:
To improve the timeliness of housing assistance payments and mitigate
the effects on owners when payments are delayed, we recommend that the
Secretary of Housing and Urban Development take the following three
actions:
* streamline and automate the contract renewal process to prevent
processing errors and delays and eliminate paper/hard-copy requirements
to the extent practicable;
* develop systematic means to better estimate the amounts that should
be allocated and obligated to project-based housing assistance payment
contracts each year, monitor the ongoing funding needs of each
contract, and ensure that additional funds are promptly obligated to
contracts when necessary to prevent payment delays; and:
* notify owners if their monthly housing assistance payments will be
late and include in such notifications the date by which HUD expects to
make the monthly payment to the owner.
Agency Comments:
We provided a draft of this report to HUD for its review and comment.
In a letter from the Assistant Secretary for Housing, Federal Housing
Commissioner (see app. II), HUD stated that it concurred with our
conclusions and agreed that the implementation of our recommendations
would improve payment timeliness. Specifically, HUD agreed to review
its process for renewing and amending rental assistance contracts to
identify areas that can be streamlined and automated. HUD also agreed
that developing a more systematic means to estimate contract funding
needs would further improve payment timeliness. HUD stated that it has
obtained a contractor to determine how to improve its system of
estimating contract funding needs. Additionally, HUD agreed that
notification to owners when payments will be late is desirable and that
it will examine the feasibility of providing such notification.
As agreed with your offices, unless you publicly announce its contents
earlier, we plan no further distribution of this report until 30 days
after the date of this letter. At that time, we will send copies of
this report to the Chairman and Ranking Minority Member, Senate
Committee on Banking, Housing, and Urban Affairs, and the Chairman and
Ranking Minority Member of its Subcommittee on Housing and
Transportation. We will also send copies to the Secretary of Housing
and Urban Development and the Director of the Office of Management and
Budget. We will make copies available to others upon request. The
report will also be available at no charge on GAO's Web site at
http://www.gao.gov.
Please contact me at (202) 512-8678 or [Hyperlink, woodd@gao.gov] if
you or your staff have any questions about this report. Contact points
for our Offices of Congressional Relations and Public Affairs may be
found on the last page of this report. Key contributors to this report
are listed in appendix III.
Signed by:
David G. Wood:
Director, Financial Markets and Community Investment:
[End of section]
Appendixes:
Appendix I: Scope and Methodology:
To determine the extent to which the Department of Housing and Urban
Development's (HUD) housing assistance payments are timely, we obtained
from HUD and analyzed 10 years of monthly payment data (fiscal years
1995 through 2004). We identified the timeliness of each payment within
HUD's data systems by comparing the date that the U.S. Treasury
disbursed the payment with the date that the payment was due--the 1st
business day of the month. We did not look at the dollar amount of
these payments. For contracts administered by performance-based and
traditional (or nonperformance-based) administrators, the Treasury
payment is disbursed to the administrator, which in turn makes payments
to the project owners. In contrast, for HUD-administered contracts, the
Treasury disburses payments directly to the owners.
We analyzed trends in timeliness over the 10-year period as well as the
most recent 3-year period (fiscal years 2002 through 2004) for a more
current picture of payment timeliness. We also calculated the
percentage of payments that had various degrees of lateness (such as 1
to 6 days or 4 weeks or more). For fiscal year 2004, we compared
timeliness for payments processed by the different types of contract
administrators involved in this process (i.e., HUD field offices,
performance-based contract administrators (PBCA), and traditional
contract administrators, for which the HUD Financial Management Center
processes payments). We limited our analysis to fiscal year 2004
because the data we obtained from HUD do not allow us to identify for
prior fiscal years which type of contract administrator was responsible
for each contract, and, over the course of these years, HUD was in the
process of transferring contract administration responsibilities to the
PBCAs. To better understand the payment process, we interviewed
officials from both HUD's Office of Multifamily Housing and HUD's
Financial Management Center and reviewed relevant documentation on the
payment process.
We used various HUD databases to analyze the timeliness of housing
assistance payments. Specifically, we used data from HUD's Program
Accounting System (PAS) for payments on contracts administered by HUD
and the PBCAs and data from the HUD Central Accounting and Program
System for contracts administered by nonperformance-based contract
administrators (traditionally administered contracts). We also used
these data to determine the percentage of significantly late payments
(i.e., 2 weeks or more late), including the distribution by type of
contract administrator. We also used the PAS data to analyze
differences in payment timeliness by state for PBCA-and HUD-
administered contracts.
In order to assess the reliability of the data previously described, we
reviewed related documentation and interviewed agency officials who
work with these databases. In addition, we performed internal checks to
determine the extent to which the data fields were populated and the
reasonableness of the values contained in the fields. During our
internal checks, we excluded from our analysis 7 percent of the
payments recorded in PAS due to unreasonable values for the payment
date. We concluded that the data we used were sufficiently reliable for
the purposes of this report.
To determine the factors that affect the timeliness of HUD's housing
assistance payments, we interviewed HUD headquarters officials
responsible for managing and budgeting for the project-based assistance
contracts and payments as well as officials from industry groups
representing a variety of property owners and management agents. We
also conducted site visits to eight locations that we selected by
including those with high and low percentages of late
payments.[Footnote 18] For these site visits, we interviewed the
relevant field office officials involved in processing housing
assistance payments, renewing housing assistance contracts, and
conducting oversight of the PBCAs. We interviewed officials of the
PBCAs for each of the states we visited.[Footnote 19] In each of the
eight locations, we also interviewed 2 project owners with some
experience with payment delays. We randomly selected 15 of the 16
owners we interviewed; HUD field office officials identified 1 of the
project owners during the phase of our work when we were gathering
initial background information. For all of our interviews for these
site visits, we used a semistructured interview guide to ensure
consistency. We also reviewed relevant documentation provided by HUD
field officials, the PBCAs, and project owners.
We used available HUD data to characterize the reasons for some payment
delays for fiscal years 2002 through 2004. We matched PAS payment data
on PBCA-and HUD-administered contracts with data on reasons for payment
delays from HUD's Tenant Rental Assistance Certification System
(TRACS). We could only determine the reason for delays for 55 percent
of the late payments. For almost all of the remaining 45 percent of the
payments, HUD's data systems did not accept the voucher--for these
payments there was no error code associated with the delay. Although
the data on reasons for delays are thus not representative of all late
payments in these years, the testimonial evidence we obtained though
our discussions with property owners, contract administrators, and HUD
officials corroborated the results of our data analysis. HUD did not
collect data on the reasons for delayed payments on traditionally
administered contracts.
We also analyzed data to examine the timeliness of contract renewals
with the various types of rent adjustments that owners may seek. To
determine the extent to which HUD renewed or adjusted its contracts
with property owners within the 120-day time frame that the agency has
established, we used data from HUD's Real Estate Management System
covering fiscal years 2002 through 2004. In order to assess the
reliability of the data we used to determine reasons for late payments
and delays in contract renewals, we reviewed related documentation. In
addition, we performed internal checks to determine the extent to which
the data fields were populated and the reasonableness of the values
contained in the fields. We concluded that the data we used were
sufficiently reliable for the purposes of this report.
To assess the effects of housing assistance payment delays on project
owners and their willingness to continue providing affordable housing,
we compared available HUD payment data on projects that have opted out
of HUD's programs with those currently receiving assistance to
determine if these projects had experienced more payment delays. We
tested for statistically significant differences in the timeliness of
payments among properties that had and had not opted out. We held
meetings with a variety of industry groups to obtain their views on how
late payments may affect project owners and their willingness to
continue providing affordable housing. We also spoke with HUD field
office officials, the PBCAs, and project owners on our eight site
visits, as previously mentioned, regarding the effects of late payments
on project owners.
We conducted our work between October 2004 and September 2005 in
Baltimore, Maryland; Boston, Massachusetts; Chicago, Illinois; Des
Moines, Iowa; Kansas City, Kansas; Kansas City, Missouri; Los Angeles,
California; Manchester, New Hampshire; Seattle, Washington; and
Washington, D.C., in accordance with generally accepted government
auditing standards.
[End of section]
Appendix II: Comments from the Department of Housing and Urban
Development:
U.S. DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT:
ASSISTANT SECRETARY FOR HOUSING-FEDERAL HOUSING COMMISSIONER:
WASHINGTON, DC 20410-8000:
October 25, 2005:
Mr. David G. Wood, Director:
Financial Markets and Community Investment:
United States Government Accountability Office:
441 G Street, NW:
Washington, D.C. 20548:
Dear Mr. Wood:
Thank you for the opportunity to provide comments on the Government
Accountability Office (GAO) draft report: PROJECT-BASED RENTAL
ASSISTANCE: HUD Should Streamline Its Processes to Ensure Timely
Housing Assistance Payments (GAO-06-57).
The report concludes that over the 10-year period examined, HUD made
most payments on time, as defined as the first business day of the
month, but that a significant percentage of payments were late and that
such delays can cause financial hardship to property owners.
GAO has noted that while timeliness of payments has improved since the
ramp up of the post-MAHRA (Multifamily Assisted Housing Reform and
Affordability Act of 1997) requirements, and the implementation of the
Performance Based Contract Administrator (PBCA) conversion, additional
measures should be undertaken to address factors that most affect the
timeliness of payments and to mitigate the effects of payments that
cannot be made on time. HUD concurs in these conclusions. GAO has made
three specific recommendations for improvement:
1. Streamline and automate the contract renewal process to prevent
processing errors and delays and eliminate paper/hard copy requirements
to the extent practicable.
2. Develop systematic means to better estimate the amounts that should
be allocated and obligated to project-based housing assistance payment
contracts each year, monitor the ongoing funding needs of each
contract, and ensure additional funds are promptly obligated to
contracts when necessary to prevent payment delays.
3. Notify owners if their monthly housing assistance payments will be
late and include in such notifications the date by which HUD expects to
make the monthly payment to the owner.
HUD agrees that the implementation of these recommendations would
improve the timeliness of payments and has the following specific
comments:
Streamlining and automating the business process for renewing and
amending assistance contracts will require a comprehensive review of
existing procedures and policies. This review is currently being
undertaken as part of comprehensive program Business Process
Reengineering (BPR). We anticipate that this initiative will identify
areas where efficiencies in process can be realized, including
addressing the fact that the current renewal and amendment process
relies heavily on paper transactions and extensive participation of
HUD, PBCAs, and project owners.
Developing more systematic means to estimate funding needs and a more
efficient allocation plan would also improve the timeliness of
payments. The Department plans on achieving improvements in this area
through training, data quality reviews, and data systems maintenance.
To determine how best to improve the current estimation/allocation
system, HUD has obtained a contractor to analyze the current systems
and make recommendations as to improvements that will allow us to
better identify emerging funding requirements as well as improve the
allocation of available resources.
Finally, HUD agrees that notification of owners if anticipated payments
are delayed is desirable. HUD believes that the systemic enhancements
outlined above will lead to a clearer understanding of the reasons for
delayed payments and identify measures that may resolve such problems.
HUD will also examine the feasibility of notifying project owners if
HUD anticipates that there will be a significant delay in payment due
to an issue beyond the control of the owner.
In conclusion, HUD appreciates the GAO's review and recommendations and
recognizes the need for improvements identified. We look forward to
working with GAO and our other partners in addressing these issues over
the coming months.
Sincerely,
Signed by:
Brian D. Montgomery:
Assistant Secretary for Housing-Federal Housing Commissioner:
[End of section]
Appendix III: GAO Contact and Staff Acknowledgments:
GAO Contact:
David G. Wood, (202) 512-8678:
Staff Acknowledgments:
In addition to those named above, Bill MacBlane, Assistant Director;
Jackie Garza; Patty Hsieh; Jane Kim; Don Porteous; Julianne Stephens
Dieterich; Alison Martin; Marc Molino; Linda Rego; Barbara Roesmann;
and Stu Seman made key contributions to this report.
(250216):
FOOTNOTES
[1] Contracts with terms for greater than 1 year include language
noting that they are "subject to annual appropriations," meaning that
the terms apply only if HUD gets an appropriation sufficient to fund
the contracts beyond the 1st year.
[2] Pub. L. No. 105-65, title V, 111 Stat. 1384 (Oct. 27, 1997) (set
out at 42 U.S.C. § 1437f note).
[3] Prior GAO reports on HUD's mark-to-market efforts include the
following: GAO, Multifamily Housing: Physical and Financial Condition
of Mark-to-Market At-Risk Properties, GAO-02-953 (Washington, D.C.
Sept. 6, 2002); Multifamily Housing: Issues Related to Mark-to-Market
Program Reauthorization, GAO-01-800 (Washington, D.C. July 11, 2001);
and Multifamily Housing: HUD's Restructuring Office's Actions to
Implement the Mark-to-Market Program, GAO/RCED-00-21 (Washington, D.C.
Jan. 20, 2000).
[4] For contracts administered by the PBCAs and traditional contract
administrators, HUD disburses funds to the contract administrator,
rather than directly to the owner. HUD's data systems do not track the
date the owner received payment under these contracts. As a result, we
do not have data to reflect the exact payment date and, instead, for
these contracts, we characterize timeliness based on the date the U.S.
Treasury disbursed funds to the contract administrator. Based on our
discussions with PBCA officials, it takes the PBCAs generally 1 to 5
days to turn around payments to owners.
[5] We did not include payment data for contracts under the Section 236
Rental Assistance Payment and the Rent Supplement programs for which
HUD does not begin processing payments until after the 1st business day
of the month. These represent only 2 percent all project-based rental
assistance contracts.
[6] We defined chronically late payments as contracts with 6 or more
payments per year that were 2 weeks or more late.
[7] HUD data recorded the reason for the delay for 55 percent of the
PBCA-and HUD-administered payments that were 2 weeks or more late in
fiscal years 2002 through 2004. We could not determine the reasons for
the delay in the remaining 45 percent of the late payments. For almost
all of the remaining 45 percent of payments, HUD's data systems did not
accept the voucher in time for a timely payment. According to HUD
officials, late acceptance of the voucher, for example, could be the
result of a problem with the voucher or that it was submitted late by
the owner or the PBCA. HUD does not collect data that would include the
reasons for delayed payments on traditionally administered contracts.
[8] Section 571 of the Multifamily Assisted Housing Reform and
Affordability Act of 1997 established OMHAR to carry out the Mark-to-
Market Program to reduce rents to market levels and restructure the
debt for properties with expiring long-term contracts. OMHAR's
existence terminated on September 30, 2004. At that time, HUD created
the Office of Affordable Housing Preservation to continue the Mark-to-
Market Program.
[9] An obligation is a definite commitment that creates a legal
liability of the government for the payment of goods and services
ordered or received, or a legal duty on the part of the United States
that could mature into a legal liability by virtue of actions on the
part of the other party beyond the control of the United States.
Payment may be made immediately or in the future. An agency incurs an
obligation, for example, when it places an order, signs a contract,
awards a grant, purchases a service, or takes other actions that
require the government to make payments to the public or from one
government account to another.
[10] Recaptured funds are funds that an agency had previously obligated
(e.g., agreed to pay in a housing assistance payment contract) but that
the agency deobligated when it determined that the funds would not be
needed for these contracts. In some cases, an agency may use recaptured
funds for other program activities, reducing its need for new
appropriations. In other cases, Congress may rescind recaptured funds.
[11] A contract amendment is a mutually agreed-upon change (between HUD
or a contract administrator and a project owner) to an obligation of
funds. For example, a contract amendment may be allowed to cover
increased contract rents resulting from increased costs, decreases in
family incomes, or both.
[12] Consolidated Appropriations Act, 2005, Pub. L. No. 108-447, div.
I, title II, 118 Stat. 2809 (Dec. 8, 2004).
[13] A continuing resolution is legislation enacted by Congress to
provide budget authority for federal agencies and/or specific
activities to continue in operations until the regular appropriations
are enacted. Continuing resolutions are enacted when action on
appropriations is not completed by the beginning of a fiscal year.
[14] Some PBCAs, project owners, and industry group representatives
with whom we spoke were under the impression that continuing
resolutions might preclude contract renewals or cause untimely housing
assistance payments. Many of them indicated they had been told by HUD
field officials that payment delays in the beginning of the federal
fiscal year were a result of continuing resolutions.
[15] We did not independently assess the owners' ability to meet their
financial obligations without the HUD subsidy payments that were late.
[16] HUD requires nonprofit and limited dividend property owners to
deposit surplus cash into a residual receipts account, which is an
asset of the owner but held under HUD's control.
[17] GAO, Multifamily Housing: More Accessible HUD Data Could Help
Efforts to Preserve Housing for Low-Income Tenants, GAO-04-20
(Washington, D.C. Jan. 23, 2004).
[18] These were California, the District of Columbia, Illinois, Iowa,
Maryland, Massachusetts, New Hampshire, and Washington.
[19] We chose to interview the PBCAs rather than traditional contract
administrators because the PBCAs handle the bulk of HUD's housing
assistance contracts--over 13,000 out of about 23,000 in fiscal year
2004--and, thus, their experiences and perspectives are applicable to
more of the universe of HUD's payments. Furthermore, HUD is gradually
assigning more of the traditional contract administrators' duties to
the PBCAs, which, considering the time available to us to conduct these
site visits, added to our judgment that focusing on the PBCAs was
appropriate.
GAO's Mission:
The Government Accountability Office, the investigative arm of
Congress, exists to support Congress in meeting its constitutional
responsibilities and to help improve the performance and accountability
of the federal government for the American people. GAO examines the use
of public funds; evaluates federal programs and policies; and provides
analyses, recommendations, and other assistance to help Congress make
informed oversight, policy, and funding decisions. GAO's commitment to
good government is reflected in its core values of accountability,
integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains
abstracts and full-text files of current reports and testimony and an
expanding archive of older products. The Web site features a search
engine to help you locate documents using key words and phrases. You
can print these documents in their entirety, including charts and other
graphics.
Each day, GAO issues a list of newly released reports, testimony, and
correspondence. GAO posts this list, known as "Today's Reports," on its
Web site daily. The list contains links to the full-text document
files. To have GAO e-mail this list to you every afternoon, go to
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order
GAO Products" heading.
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office
441 G Street NW, Room LM
Washington, D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm
E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Public Affairs:
Jeff Nelligan, managing director,
NelliganJ@gao.gov
(202) 512-4800
U.S. Government Accountability Office,
441 G Street NW, Room 7149
Washington, D.C. 20548: