The Federal Aviation Administration (FAA) operates one of the safest air transportation systems in the world. It is, however, a system under strain. The skies are becoming more crowded every day, with an estimated 1 billion passengers per year expected by 2015. The current aviation system cannot be expanded to meet this growth. The reauthorization of FAA is an opportunity to examine how the agency is managing the operation and safety of the air transportation system as it leads the transition to the Next Generation Air Transportation System (NextGen)--a major redesign of the current system. GAO's testimony focuses on key issues related to FAA's reauthorization, including (1) FAA's progress in implementing initiatives that could provide a solid foundation for NextGen, (2) issues that need to be addressed to help ensure a successful transition to NextGen, and (3) safety areas that are important for the continued safe operation of the current and future system. This statement is based on recent GAO reports and ongoing work on some management and safety initiatives.
FAA has made significant progress in moving to more businesslike and cost-effective operations and modernizing the air traffic control system. This progress should better position the agency for the complex implementation of NextGen. However, further work remains to fully address past problems in the modernization effort while at the same time finding new leadership--due to losses of key leaders at FAA and its Air Traffic Organization--that can continue an agencywide commitment to transformation. While FAA has improved its financial management capability, including implementing a new cost accounting system and developing a cost allocation methodology, it is not yet clear if that methodology provides a sound basis from which to derive the administration's proposed new cost-based funding structure for FAA. In addition, improved acquisition processes, such as establishing guidance on using Earned Value Management, are positive steps, but they need to be fully implemented across all critical acquisitions. As FAA works toward acquiring and deploying NextGen technology, it will also be important to phase out existing air traffic control equipment using a risk-based approach and continue to maintain existing systems. Key issues that FAA needs to address as it begins implementing NextGen include continued focus on coordination with the Joint Planning and Development Office (JPDO). FAA, in coordination with JPDO, is developing an implementation plan for NextGen that is expected to include details of the required technologies, procedures, and resources. This is a step in the right direction. While FAA estimates that its cost for NextGen programs may range between $15 billion and $22 billion, it will be important to determine which entities will fund and conduct the necessary developmental research. Also, GAO has recommended that FAA assess its capacity to handle the technical and contract management expertise to determine if it has the capabilities required to oversee the implementation of NextGen. FAA is considering action that would respond to this recommendation. To deal with current safety issues and the transition to NextGen, it will be important for FAA to address safety in the airport environment, where forecasted traffic growth could lead to increased ground congestion and safety hazards. FAA also needs to establish the appropriate regulatory approach for certain current airspace users, such as air ambulances, and new users, such as the emerging space tourism industry. In addition, to maintain and expand the margin of safety, especially if substantial growth in air traffic materializes, FAA will need to rely more on data than on labor-intensive inspections. GAO has recommended that FAA improve its safety data. FAA has taken some action to improve its data, but more work remains. FAA's ability to ensure a safe system will also be affected by its ability to hire, train, and deploy its workforce of air traffic controllers, inspectors, and technicians.
GAO-07-636T, Federal Aviation Administration: Key Issues in Ensuring the Efficient Development and Safe Operation of the Next Generation Air Transportation System
This is the accessible text file for GAO report number GAO-07-636T
entitled 'Federal Aviation Administration: Key Issues in Ensuring the
Efficient Development and Safe Operation of the Next Generation Air
Transportation System' which was released on March 22, 2007.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the Subcommittee on Aviation, Committee on Transportation and
Infrastructure, House of Representatives:
United States Government Accountability Office:
GAO:
For Release on Delivery Expected at 10 a.m. EDT:
Thursday, March 22, 2007:
Federal Aviation Administration:
Key Issues in Ensuring the Efficient Development and Safe Operation of
the Next Generation Air Transportation System:
Statement of Gerald L. Dillingham, Ph.D.
Director, Physical Infrastructure Issues:
GAO-07-636T:
GAO Highlights:
Highlights of GAO-07-636T, a testimony before the Subcommittee on
Aviation, Committee on Transportation and Infrastructure, House of
Representatives
Why GAO Did This Study:
The Federal Aviation Administration (FAA) operates one of the safest
air transportation systems in the world. It is, however, a system under
strain. The skies are becoming more crowded every day, with an
estimated 1 billion passengers per year expected by 2015. The current
aviation system cannot be expanded to meet this growth. The
reauthorization of FAA is an opportunity to examine how the agency is
managing the operation and safety of the air transportation system as
it leads the transition to the Next Generation Air Transportation
System (NextGen)”a major redesign of the current system. GAO‘s
testimony focuses on key issues related to FAA‘s reauthorization,
including (1) FAA‘s progress in implementing initiatives that could
provide a solid foundation for NextGen, (2) issues that need to be
addressed to help ensure a successful transition to NextGen, and (3)
safety areas that are important for the continued safe operation of the
current and future system. This statement is based on recent GAO
reports and ongoing work on some management and safety initiatives.
What GAO Found:
FAA has made significant progress in moving to more businesslike and
cost-effective operations and modernizing the air traffic control
system. This progress should better position the agency for the complex
implementation of NextGen. However, further work remains to fully
address past problems in the modernization effort while at the same
time finding new leadership”due to losses of key leaders at FAA and its
Air Traffic Organization”that can continue an agencywide commitment to
transformation. While FAA has improved its financial management
capability, including implementing a new cost accounting system and
developing a cost allocation methodology, it is not yet clear if that
methodology provides a sound basis from which to derive the
administration‘s proposed new cost-based funding structure for FAA. In
addition, improved acquisition processes, such as establishing guidance
on using Earned Value Management, are positive steps, but they need to
be fully implemented across all critical acquisitions. As FAA works
toward acquiring and deploying NextGen technology, it will also be
important to phase out existing air traffic control equipment using a
risk-based approach and continue to maintain existing systems.
Key issues that FAA needs to address as it begins implementing NextGen
include continued focus on coordination with the Joint Planning and
Development Office (JPDO). FAA, in coordination with JPDO, is
developing an implementation plan for NextGen that is expected to
include details of the required technologies, procedures, and
resources. This is a step in the right direction. While FAA estimates
that its cost for NextGen programs may range between $15 billion and
$22 billion, it will be important to determine which entities will fund
and conduct the necessary developmental research. Also, GAO has
recommended that FAA assess its capacity to handle the technical and
contract management expertise to determine if it has the capabilities
required to oversee the implementation of NextGen. FAA is considering
action that would respond to this recommendation.
To deal with current safety issues and the transition to NextGen, it
will be important for FAA to address safety in the airport environment,
where forecasted traffic growth could lead to increased ground
congestion and safety hazards. FAA also needs to establish the
appropriate regulatory approach for certain current airspace users,
such as air ambulances, and new users, such as the emerging space
tourism industry. In addition, to maintain and expand the margin of
safety, especially if substantial growth in air traffic materializes,
FAA will need to rely more on data than on labor-intensive inspections.
GAO has recommended that FAA improve its safety data. FAA has taken
some action to improve its data, but more work remains. FAA‘s ability
to ensure a safe system will also be affected by its ability to hire,
train, and deploy its workforce of air traffic controllers, inspectors,
and technicians.
What GAO Recommends:
This testimony does not contain recommendations. However, GAO reports
containing relevant recommendations are listed among the Related GAO
Products, some of which FAA is in the process of responding to.
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-636T].
To view the full product, including the scope and methodology, click on
the link above. For more information, contact Gerald L. Dillingham,
Ph.D., at (202) 512-2834 or dillinghamg@gao.gov.
[End of section]
Mr. Chairman and Members of the Subcommittee:
I appreciate the opportunity to testify before you today as you
consider the reauthorization of the Federal Aviation Administration
(FAA). FAA operates one of the safest air transportation systems in the
world. It is, however, a system under strain. The skies over America
are becoming more crowded every day. Demand for air travel has
increased in recent years, with over 740 million passengers flying in
fiscal year 2006, climbing toward an estimated 1 billion passengers per
year in 2015, according to FAA estimates. Already, with the increasing
demand for air travel, flight arrival delays have increased; such
delays are nearing the record levels of 2000, a year in which one in
four flights reached its destination behind schedule. The system is
also expected to absorb a variety of different types of aircraft in the
near future, ranging from the jumbo Airbus A380--which can hold more
than 500 passengers--to very light jets--which may greatly increase the
number of aircraft in the sky while transporting six or fewer
passengers on any given flight. The consensus is that the current
aviation system cannot be expanded to meet this projected growth.
In 2003, recognizing the need for system transformation, Congress
authorized the creation of the Joint Planning and Development Office
(JPDO), housed within FAA but involving several federal partner
agencies,[Footnote 1] to conceptualize and plan for the Next Generation
Air Transportation System (NextGen). NextGen is envisioned as a major
redesign of the air transportation system that will move from largely
ground-based radars to precision satellite-based navigation and
includes digital, networked communications; an integrated weather
system; layered, adaptive security; and more. The reauthorization of
FAA and the Airport and Airway Trust Fund provides a unique opportunity
to examine how the agency is managing the operation and safety of the
current air traffic control system as it prepares to implement NextGen.
My testimony today focuses on these questions: (1) What progress is FAA
making in implementing initiatives that could provide a solid
foundation for NextGen? (2) What are the key issues that need to be
addressed to help ensure a successful transition to NextGen? and (3)
What key safety areas need to be addressed for the continued safe
operation of the current and future air transportation system? My
statement is based on our recent reports as well as ongoing work for
this subcommittee assessing FAA's performance metrics for its
acquisitions, runway safety, and safety issues concerning the operation
of unmanned aircraft systems in the national airspace. We conducted
this work in accordance with generally accepted government auditing
standards.
In summary:
* Over the past few years, FAA has made significant progress in moving
to more businesslike and cost effective operations and modernizing the
air traffic control system, which should better position the agency for
the complex implementation of NextGen. However, further work remains to
fully address past problems in the modernization program. FAA has
improved its financial management, including implementing a new cost
accounting system and developing a cost allocation methodology;
however, it is not yet clear if the cost allocation methodology is
sufficiently valid and reliable to derive the administration's proposed
new cost-based funding for FAA. FAA has also sought to improve its
financial management with efforts to control and reduce costs. For
example, FAA plans to produce cost savings through outsourcing such as
with its planned contracting out of new surveillance technology, and
through facility consolidations. In addition to improvements in
financial management, FAA has improved its acquisition management,
which will be critical to a successful transition to NextGen. For
example, FAA has begun reviewing its major systems acquisitions and has
established guidance for using a project management technique known as
Earned Value Management[Footnote 2] in its acquisition management
system, although institutionalizing these improvements will continue to
be a challenge for FAA. FAA has also established performance measures
and targets for its critical acquisitions. While the acquisition and
deployment of NextGen technology are key issues facing the agency, it
will be critical that FAA continue to maintain existing systems and
phase out existing systems using a risk-based approach. And, although
FAA has initiated numerous financial, management, and acquisition
process improvements, the agency must work to institutionalize these
changes while at the same time finding new leadership--due to losses of
key leaders at FAA and its Air Traffic Organization (ATO)--that can
continue to enforce an agencywide commitment to change and continuous
improvement.
* As FAA begins implementing NextGen, key issues remain that will need
to be addressed, such as coordinating with JPDO, funding for NextGen-
related programs, and ensuring that FAA has both the technical and
contract management expertise that will be required to oversee this
complex undertaking. FAA has become steadily more focused on NextGen
over the past few years and is expanding and revamping its Operational
Evolution Plan--renamed the Operational Evolution Partnership--to
integrate with JPDO activities and become its implementation plan for
NextGen, including details of required technologies, procedures, and
resources. This is a step in the right direction. JPDO recently
reported that the total cost for NextGen infrastructure may range
between $15 billion and $22 billion. The agency also noted that it
expects a corresponding cost to system users, who will have to equip
themselves with the advanced avionics necessary to realize the full
benefits of some NextGen technologies, in the range of $14 billion to
$20 billion. Another transition challenge for FAA and JPDO is to
address questions about which entities will fund and conduct some of
the necessary research, development, and demonstration projects that
will be key to achieving certain NextGen capabilities and keeping the
development of new systems on schedule. We have also recommended that
FAA examine its strengths and weaknesses with regard to the technical
and contract management expertise that will be needed for NextGen
implementation. In response to our recommendation, FAA is considering
convening a blue ribbon panel to study the issue and make
recommendations to the agency. We believe that such a panel could help
FAA begin to address this challenge.
* To deal with current and future safety issues, it will be important
for FAA to also address several issues as it works to ensure that its
safety programs are aligned to meet future demand. First, ground safety
is an area of increasing concern because air traffic is forecast to
grow substantially during the coming decades, which will result in more
aircraft and increased congestion and safety hazards in the complex
airport environment. FAA needs to keep on schedule to deploy NextGen
technology that warns controllers of imminent ground collisions and
implement recommendations by the National Transportation Safety Board
(NTSB) (which continues to place runway incursions on its Most Wanted
Transportation Safety Improvements list). Second, FAA needs to
establish an appropriate regulatory approach for some current airspace
users, such as air ambulances, and new users such as the emerging space
tourism industry. For example, we suggested that Congress should
consider revisiting FAA's dual role for ensuring safety and promoting
the emerging space tourism industry and decide whether the elimination
of FAA's promotional role is necessary to alleviate a potential
conflict of interest. Third, to maintain and expand the margin of
safety--especially if substantial growth in air traffic materializes--
FAA cannot rely on its current oversight approach, which focuses on
labor-intensive inspections. Accurate, complete safety data would
provide FAA with an early warning of hazards that can lead to
accidents. We have recommended that FAA improve the accuracy and
completeness of its safety data and its analysis of that data. FAA is
in the early planning stages of addressing our recommendations, but
more work remains. Fourth, FAA's ability to ensure safety in NextGen
will be affected by its ability to manage its human capital, including
safety inspectors, engineers, technicians, and air traffic controllers.
FAA faces challenges in improving its staffing processes, addressing
human factors issues associated with significant increases in the
automation of air traffic management, replacing the large percentage of
staff expected to retire, and addressing the contentious relations with
its employee unions, which have the potential to hinder the agency's
ability to retain and recruit skilled staff.
Improved, Businesslike Operations Should Better Position FAA to
Implement and Manage NextGen, but Further Work Remains:
Although the NextGen effort involves multiple government agencies and
the private sector, FAA will be the entity largely responsible for
implementing the policies and systems necessary for NextGen while
safely operating the current air traffic control system 24 hours a day,
7 days a week. This means that FAA will be responsible for keeping a
number of large NextGen systems acquisitions on budget and on schedule
as it manages and sustains the current system. Historically, FAA has
had serious weaknesses in its financial management as well as chronic
cost and schedule difficulties with air traffic control system
acquisitions. During the past few years, FAA has made significant
progress in implementing businesslike processes and procedures for
financial management, acquisitions, and organization structures. The
implementation of these types of initiatives has improved FAA's
management of the current system and should better position the agency
to manage the enormously complex transition to NextGen. However,
further work remains to fully address past problems and
institutionalize these changes throughout the agency, especially given
the changing leadership within both FAA and its ATO.
FAA Has Improved Its Financial Management, although the Soundness of
Its Cost Allocation Methodology is Uncertain:
Sound financial management, including sound cost accounting and cost
allocation systems, is important for the current operation of FAA and
lays the foundation for the transformation to NextGen and proposed
changes to the agency's funding system laid out in the administration's
reauthorization proposal. In 1999, we placed FAA on our high-risk list
for its financial management practices, noting weaknesses that rendered
the agency vulnerable to fraud, waste, and abuse by undermining its
ability to manage operations and limiting the reliability of financial
information provided to Congress. In 2005, we removed FAA's financial
management from our high-risk list because the agency had made
significant progress, including implementing a new financial management
system called Delphi[Footnote 3] and receiving unqualified opinions
from auditors on its annual financial statements for fiscal years 2001
through 2005. Nonetheless, external auditors issued a qualified opinion
on FAA's fiscal year 2006 financial statement and repeated a material
internal control weakness that was reported in 2005. The concerns that
led to the qualified opinion stemmed from FAA's inability to support
the accuracy and completeness of its construction-in-progress account,
reported in the financial statement as $4.7 billion. FAA is working to
address the problem.
As part of its improved financial management, FAA has developed a cost
accounting system and a cost allocation methodology, which are critical
to the successful implementation of the new cost-based funding system
included in the administration's reauthorization proposal.[Footnote 4]
The proposal would change FAA's financing system from one based mainly
on excise taxes to one that provides a better link between revenues and
the costs that users of the national airspace system impose on the
system, according to the agency. FAA also says the proposal would
improve revenue adequacy, equity, and efficiency.[Footnote 5] While the
reauthorization proposal may address some of the equity and efficiency
concerns that FAA has raised with the current funding structure, we
have reported that it is not yet clear if FAA has developed a sound
cost allocation methodology from which to derive the new cost-based
funding.[Footnote 6] We are reviewing FAA's cost allocation methodology
and expect to issue a report later this year.
FAA has also improved its financial management through increased
efforts to achieve cost savings and cost avoidance throughout the
agency. For example, FAA is outsourcing flight service stations and
estimates a $2.2 billion savings over 12 years. Similarly, FAA is
seeking savings through outsourcing its planned nationwide deployment
of Automatic Dependent Surveillance-Broadcast (ADS-B), a critical
element of NextGen. FAA is planning to implement ADS-B through a
performance-based contract in which FAA will pay "subscription" charges
for the ADS-B services and the vendor will be responsible for building
and maintaining the infrastructure. (FAA also reports that the ADS-B
rollout will allow the agency to remove 50 percent of its current
secondary radars, saving money in the program's baseline. The remaining
radars will serve as a back-up system to ADS-B.) As for consolidating
facilities, FAA is currently restructuring ATO's administrative service
areas from nine offices to three offices, which FAA estimates will save
up to $460 million over 10 years.
We previously reported that FAA should pursue further cost control
options, such as exploring additional opportunities for contracting out
services and consolidating facilities. However, we recognize that FAA
faces challenges with consolidating facilities, an action that can be
politically sensitive. In recognition of this sensitivity, the
administration's reauthorization proposal presents a "BRAC-like"
initiative in which the Secretary of Transportation would be authorized
to establish an independent, five-member commission, known as the
Realignment and Consolidation of Aviation Facilities and Services
Commission, to independently analyze FAA's recommendations to realign
facilities or services. The commission would then send its own
recommendations to the President and Congress. In the past, we noted
the importance of potential cost savings through facility
consolidations; however, it must also be noted that any such
consolidations must be handled through a process that solicits and
considers stakeholder input throughout and fully considers the safety
implications of both proposed facility closures and consolidations.
Progress Has Been Made but Further Work Remains to Institutionalize
Recent Improvements in Management and Acquisition Processes:
A successful transition to NextGen will depend, to a great extent, on
FAA's ability to manage the acquisition and integration of multiple
NextGen systems. Since 1995, we have designated FAA's air traffic
control modernization program as high risk because of systemic
management and acquisition problems. However, in recent years, FAA has
made significant progress toward improving its acquisition management.
Realization of NextGen goals could be severely compromised if FAA's
improved processes are not institutionalized and carried over into the
implementation of NextGen, which is an even more complex and ambitious
undertaking than past modernization efforts.
To its credit, FAA has taken a number of actions to improve its
acquisition management. By creating ATO in 2003 and appointing a chief
operating officer (COO) to head ATO, FAA established a new management
structure and adopted more leading practices of private sector
businesses to address the cost, schedule, and performance shortfalls
that have plagued air traffic control acquisitions. ATO has worked to
create a flatter organization, with fewer management layers, and has
reported reducing executive staffing by 20 percent and total management
by 16 percent. In addition, FAA uses a performance management system to
hold managers responsible for the success of ATO. More specifically, to
better manage its acquisitions and address problems we have
identified,[Footnote 7] FAA has:
* undertaken human capital initiatives to improve its acquisition
workforce culture and build towards a results-oriented, high-performing
organization;
* developed and applied a process improvement model to assess the
maturity of its software and systems acquisitions capabilities
resulting in, among other things, enhanced productivity and greater
ability to predict schedules and resources; and:
* reported that it has established a policy and guidance on using
Earned Value Management (EVM) in its acquisition management system and
that 19 of its major programs are currently using EVM.[Footnote 8]
Institutionalizing these improvements throughout the agency will
continue to be a challenge for FAA. For example, the agency has yet to
implement its cost-estimating methodology, although, according to the
agency, it has provided training on the methodology to employees.
Furthermore, FAA has not established a policy to require use of its
process improvement model on all major acquisitions for the national
airspace system. Until the agency fully addresses these residual
issues, it will continue to risk program management problems affecting
cost, schedule, and performance. With a multibillion dollar acquisition
budget, addressing these issues is as important as ever.
FAA's Methodology for Tracking and Reporting Performance on Critical
Acquisitions is Subject of Ongoing Work for this Subcommittee:
In another effort to improve agency processes, FAA expanded its use of
performance measures to track its performance. In its fiscal year 2007
portfolio of goals, FAA lists 30 performance measures. As part of our
ongoing work,[Footnote 9] we are currently reviewing how FAA selects
and measures two of these goals in particular: critical acquisitions on
budget and critical acquisitions on schedule.[Footnote 10] FAA has
reported exceeding targets for both of these measures for the past 3
fiscal years. FAA's targets for fiscal year 2006 were to have 85
percent of critical acquisition programs within 10 percent of budget,
as reflected in its capital investment plan, and to have 85 percent of
critical acquisition programs on schedule. For fiscal year 2006, FAA
reported that its critical acquisitions were 100 percent on budget and
over 97 percent on schedule. This represents a major turnaround in a
program that remains on our high-risk list.
It will be important, as FAA begins to implement NextGen systems, to
maintain critical acquisitions on schedule and on budget in order to
meet the goal of transitioning to NextGen by 2025 and to prevent
escalation of the costs of NextGen. Our ongoing work is examining FAA's
performance and reporting on its critical acquisitions, including
applicable performance measures. We are also exploring FAA's use of the
most recently approved cost and schedule baselines, which may have
changed significantly since the start of an acquisition, to measure
program performance. Rebaselining acquisitions is an accepted practice
and there are valid reasons for doing so, such as when changes in a
program's requirements fundamentally alter the acquisition and make the
originally approved schedule unrealistic. Because rebaselining resets
the cost and schedule variances to zero, we want to verify that FAA's
practice is not masking acquisition performance problems. We expect to
issue a report on these issues later this year.
Although FAA Is Now Focusing on NextGen, It Must Continue to Manage and
Sustain the Current System:
While the acquisition and deployment of NextGen technology are key
issues facing the agency, it will be critical for FAA to continue to
maintain existing systems and phase out existing systems using a risk-
based approach. The adequacy of FAA's maintenance of existing systems
was raised following a power outage and equipment failures in Southern
California that caused hundreds of flight delays during the summer of
2006. Investigations by FAA and the Department of Transportation
Inspector General into these incidents identified a number of
underlying issues, including the age and condition of equipment.
Nationwide, the number of scheduled[Footnote 11] and unscheduled
outages of air traffic control equipment and ancillary support systems
has been increasing (see fig. 1). Increases in the number of
unscheduled outages indicate that systems are failing more frequently.
Figure 1: Number of Scheduled and Unscheduled Equipment Outages,
Calendar Years 2001-2006:
[See PDF for image]
Source: GAO analysis of FAA's NASPAS data.
[End of figure]
In addition, the duration of unscheduled equipment outages has also
been increasing in recent years from an average of about 21 hours in
2001 to about 40 hours in 2006 (see fig. 2), which may indicate, in
part, that maintenance and troubleshooting activities are requiring
more effort and longer periods of time. However, according to FAA, it
considers user impact and resource efficiency when planning and
responding to equipment outages. As a result, according to the agency,
although some outages will have longer restoration times, the agency
believes they do not adversely affect air traffic control operations.
It will be critical for FAA to monitor and address equipment outages to
ensure the safety and efficiency of the legacy systems, since they will
be the core of the national airspace system for a number of years and,
in some cases, will become part of NextGen.
Figure 2: Average Duration of Scheduled and Unscheduled Equipment
Outages, Calendar Years 2001-2006:
[See PDF for image]
Source: GAO's analysis of FAA's NASPAS data.
[End of figure]
Institutionalizing Change Within FAA Will Require Continued Strong
Leadership:
While FAA has implemented many positive changes to its management and
business processes in recent years, it currently faces the loss of key
leaders. We reported that the experiences of successful transformations
and change management initiatives in large public and private
organizations suggest that it can take 5 to 7 years or more until such
initiatives are fully implemented and cultures are transformed in a
sustainable manner. Such changes require focused, full-time attention
from senior leadership and a dedicated team.[Footnote 12] However, the
agency will have lost two of its significant agents for change--the FAA
administrator and the COO, who heads ATO--by the end of September 2007.
The administrator's term ends in September 2007; the COO left in
February 2007, after serving 3 years. This situation is exacerbated by
the fact that the current director of JPDO is new, having assumed that
position in August 2006. For the financial, management, and acquisition
improvements to further permeate the agency, and thus provide a firm
foundation upon which to implement NextGen, FAA's new leaders will need
to demonstrate the same commitment to improvement as the outgoing
leaders. This continued commitment to change is critical over the next
few years, as foundational NextGen systems begin to be implemented.
Because this is a critical time for FAA, the agency needs to move
expeditiously to find a new COO for ATO. It could be useful to have a
COO whose tenure lasted the length of the current statutory 5-year
term. This would allow for stable leadership at ATO during this
critical transition from planning to early implementation of NextGen.
Key Issues Remain in the Transition From Planning to Implementing
NextGen:
Several key issues will need to be addressed to help ensure a
successful transition to NextGen as FAA moves from the
conceptualization and planning of NextGen, handled largely through the
interagency collaborative efforts of FAA's JPDO, to the implementation
of NextGen technologies and systems. Those issues include (1)
continuing to focus on the coordination between ATO and JPDO and
stakeholder involvement; (2) determining which entities will fund the
necessary research, development, and demonstration projects for
NextGen; and (3) determining whether FAA has the technical and contract
management expertise necessary to oversee the complex implementation of
NextGen.
FAA Has Improved Coordination with JPDO, but Some Key Stakeholder
Involvement is Absent:
FAA has become steadily more focused on NextGen implementation, but
some key stakeholders, such as FAA technicians who will maintain
NextGen systems, are not currently involved. One of the most important
changes FAA has made with regard to NextGen is the expansion and
revamping of its Operational Evolution Plan (OEP)--renamed the
Operational Evolution Partnership--to become FAA's implementation plan
for NextGen. This is a step in the right direction. The OEP is being
expanded to apply to all of FAA and is intended to become a
comprehensive description of how the agency will implement NextGen,
including the required technologies, procedures, and
resources.[Footnote 13] (Figure 3 shows the OEP framework.) An ATO
official told us that the new OEP is expected to be consistent with
JPDO's key planning documents and partner agency budget
guidance.[Footnote 14] According to FAA, the OEP will allow it to
demonstrate appropriate budget control and linkage to NextGen plans and
will force FAA's research and development to be relevant to NextGen's
requirements. According to FAA documents, the agency plans to publish
the new OEP in June 2007.
Figure 3: New OEP Framework:
[See PDF for image]
Source: JPDO.
Note: The concentric rings indicate the nature of initiative
development from the outer ring (NextGen strategic initiatives), in
which new programs and concepts are analyzed and demonstrated; to the
second ring, where decisions are made regarding safety, operating
policy, performance standards, and certification requirements; to the
third ring (technical development), where concepts are prototyped and
investment analysis decisions are made. The progression through the
rings is not necessarily linear, and a program may be in more than one
ring at a time. Data communications, for example, is in the technical
development ring and also in the middle ring as policy and rulemaking
is considered. The core is divided into three sections, which indicate
the FAA offices that implement the final NextGen program.
[End of figure]
In an effort to further align FAA's efforts with JPDO's plans for
NextGen, FAA has created a NextGen Review Board to oversee the OEP.
This review board will be co-chaired by JPDO's director and ATO's vice
president of operations planning services. Initiatives, such as concept
demonstrations or research proposed for inclusion in the OEP will now
need to go through the review board for approval. Initiatives are to be
assessed for their relation to NextGen requirements, concept maturity,
and risk. An ATO official told us that the new OEP process should also
help identify some smaller programs that might be inconsistent with
NextGen and could be discontinued and will assist in project
integration. Additionally, as a further step towards integrating ATO
and JPDO, the administration's reauthorization proposal calls for the
JPDO director to be a voting member of FAA's Joint Resources Council
and ATO's Executive Council.
Some stakeholders, such as current air traffic controllers and
technicians, will play critical roles in NextGen, and their involvement
in planning for and deploying the new technology will be important to
the success of NextGen. In November 2006, we reported that air traffic
controllers were not involved in the NextGen planning effort.[Footnote
15] Controllers are beginning to become involved as they are now
represented on a key planning body. However, the technicians do not
participate in NextGen efforts. Input from current air traffic
controllers who have recent experience controlling aircraft and current
technicians who will maintain the new equipment is important in
considering human factors and safety issues. Our work on past air
traffic control modernization projects has shown that a lack of
stakeholder involvement early and throughout a project can lead to cost
increases and delays.
FAA Has Begun Budgeting for NextGen Programs, although Questions Remain
About the Funding of NextGen Research and Development:
JPDO recently reported some estimated costs for NextGen, including
specifics on some early NextGen programs.[Footnote 16] JPDO believes
the total federal cost for NextGen infrastructure through 2025 will
range between $15 billion and $22 billion. JPDO also reported a
preliminary estimate of the corresponding cost to system users to equip
themselves with the advanced avionics that are necessary to realize the
full benefits of some NextGen technologies may range from $14 billion
to $20 billion. JPDO, in its recently released 2006 Progress Report,
noted that this range for avionics costs reflects uncertainty about
equipage costs for individual aircraft, the number of very light jets
that will operate in high-performance airspace, and the amount of out-
of-service time required for installation.
In its capital investment plan for fiscal years 2008-2012, FAA includes
estimated expenditures for 11 line items that are considered NextGen
capital programs.[Footnote 17] The total 5-year estimated expenditures
for these programs is $4.3 billion. In fiscal year 2008, only 6 of the
line items are funded for a total of roughly $174 million; funding for
the remaining 5 programs would begin with the fiscal year 2009 budget.
According to FAA, in addition to capital spending for NextGen, the
agency will spend an estimated $300 million on NextGen-related research
and development from fiscal years 2008 through 2012. The
administration's budget for fiscal year 2008 for FAA includes a total
of $17.8 million to support the activities of JPDO.
The administration's reauthorization proposal would allow for $5
billion in Treasury debt financing authority for NextGen-related
capital needs for fiscal years 2013-2017. Projects that might be
appropriate for such financing include safety-critical and mission-
essential software and systems that controllers and traffic flow
managers will use to support certain aircraft operations in the NextGen
system, according to the proposal. However, the proposed borrowing
authority seems unlikely to have a major impact on FAA's ability to pay
for capital investment associated with moving to NextGen because the
payback period is relatively short. With a maximum payback period of 5
years, the advantage of matching the time period for paying for a
capital investment with the time period in which the benefits of that
investment are realized is unlikely to be achieved. Therefore, the
advantage of borrowing versus receiving appropriations for a period of
up to 5 years is unclear.
While FAA and JPDO have begun to release estimates for FAA's NextGen
investment portfolio, questions remain over which entities will fund
and conduct some of the necessary research, development, and
demonstration projects that will be key to achieving certain NextGen
capabilities and keeping the development of new systems on schedule. In
the past, a significant portion of aeronautics research and
development, including intermediate technology development, has been
performed by NASA. However, NASA's aeronautics research budget and
proposed funding shows a 30-percent decline, in constant 2005 dollars,
from fiscal year 2005 to fiscal year 2011. To its credit, NASA plans to
focus its research on the needs of NextGen. However, NASA is also
moving toward a focus on fundamental research and away from
developmental work and demonstration projects. FAA and JPDO face the
challenge of determining the nature and scope of the research and
technology development necessary to begin the transition to NextGen.
They also have to identify the entities that can conduct that research
and development and the source of funding to support it.
FAA Needs to Explore whether It Has the Technical and Contract
Management Expertise Necessary to Implement NextGen:
In the past, a lack of expertise contributed to weaknesses in FAA's
management of air traffic control modernization efforts, and industry
experts with whom we spoke questioned whether FAA will have the
technical expertise needed to implement NextGen. In addition to
technical expertise, FAA will need contract management expertise to
oversee the systems acquisitions and integration involved in NextGen.
In November 2006, we recommended that FAA examine its strengths and
weaknesses with regard to the technical expertise and contract
management expertise that will be required to define, implement, and
integrate the numerous complex programs inherent in the transition to
NextGen.[Footnote 18] In response to our recommendation, FAA is
considering convening a blue ribbon panel to study the issue and make
recommendations to the agency about how best to proceed with its
management and oversight of the implementation of NextGen. We believe
that such a panel could help FAA begin to address this challenge.
Aviation Safety Record Remains High, but Some Areas Need to be
Addressed for Current and Future Safety as FAA Transitions to NextGen:
As FAA works to develop the policies and systems to transition to
NextGen, it will be important for the agency to also ensure that its
safety programs are aligned with these changes. While recent safety
trends are generally positive, improving upon those trends will be
necessary simply to maintain the same level of safety if air traffic
doubles or triples during the coming decades. Moreover, certain recent
trends--such as the commercial air carrier fatal accident rate--may
warrant immediate attention. Although this accident rate has steadily
declined in recent years, FAA did not meet its performance target in
this area for fiscal year 2006 due to four accidents, including two
accidents on runway and ramp areas and one runway overrun. FAA's
ability to deal with current safety issues and the transition to
NextGen would be enhanced by (1) acquiring and deploying new safety
enhancing technologies; (2) establishing appropriate regulatory
approaches for current airspace users and emerging sectors; (3)
improving the accuracy and completeness of its safety data; and (4)
addressing human capital issues associated with hiring, training, and
deploying its skilled workforce of air traffic controllers, safety
inspectors, engineers, and technicians.
FAA Faces Challenges in Implementing Advanced Technology and Other
Measures to Improve Safety in the Airport Environment:
Safety in the airport environment is an area of increasing concern
because air traffic is forecast to grow substantially during the coming
decades. More aircraft and congestion at the airport will make
maintaining safety even more critical, as the airport environment
involves enormously complex interactions between air traffic
controllers and the people who operate on the airport surface,
including pilots, mechanics, maintenance technicians, and airport
employees. FAA's efforts to improve safety in the airport environment
include deploying NextGen technology, such as the Airport Surface
Detection Equipment Model X (ASDE-X),[Footnote 19] evaluating runway
status lights, and testing a low-cost surface surveillance system. FAA
pursues new technologies to improve runway safety because the incursion
rate at U.S. airports was higher in fiscal year 2006 than it was in
fiscal year 2002.[Footnote 20] (Incursions are potential collisions on
the ground.) However, the deployment of new technology has faced
schedule delays. FAA originally planned to deploy ASDE-X at 35 major
airports by 2007, but the technology is operational at only 8 airports
to date, and deployment at the remaining 27 airports is not scheduled
to be complete until 2011 (see fig. 4). At the same time, FAA is
evaluating the performance of runway status lights, another technology
aimed at preventing runway incursions by warning pilots when a runway
is unsafe for crossing or departure. FAA expects to decide this year
whether to deploy the system at 35 large airports at an estimated cost
of $300 million. Although the 35 airports that are to receive ASDE-X--
and may receive runway status lights--handle about 70 percent of
enplanements in the United States, they represent only about 6 percent
of the country's 573 commercial service airports. Therefore, FAA is
also evaluating a low-cost surface surveillance system that could meet
the needs of small-to medium-sized airports. The system is designed to
alert controllers of potential conflicts and hazards and provide direct
warnings to pilots entering or approaching active runways.
Figure 4: Airport Surface Detection Equipment Model X (ASDE-X)
Deployment Sites:
[See PDF for image]
Source: FAA.
[End of figure]
The number of serious incursions--incidents where a collision was
narrowly avoided--rose from 28 in fiscal year 2004 to 31 in fiscal year
2006. As a result, NTSB continues to place runway incursions on its
Most Wanted Transportation Safety Improvements list. FAA has not yet
implemented any of the six runway incursion prevention recommendations
that NTSB made in 2000. The recommendations include such things as
implementing at commercial airports ground movement safety systems that
provide a direct warning to flight crews of possible incursions and
changing air traffic control procedures.[Footnote 21] According to
NTSB, FAA has not completed its evaluation and implementation of
technology to address the recommendation on safety systems, and the two
agencies have not reached agreement on the recommendations to change
air traffic control procedures.
FAA is also making efforts to prevent runway overruns, which occur when
aircraft pass the ends of runways during aborted takeoffs or while
landing, by the construction of runway safety areas or the installation
of arresting material at the end of runways. In 2000, FAA established
its Runway Safety Area program to accelerate the construction of runway
safety areas--areas surrounding the runways designed to reduce the risk
of damage to aircraft from overruns. Since 2005, commercial service
airports have been required[Footnote 22] to bring their runway safety
areas into compliance with FAA standards by 2015. According to FAA, as
of January 2007, 70 percent of the 1,020 runways at 573 commercial
airports in the United States substantially comply with runway safety
area standards, up from 55 percent in 2000. In fiscal year 2006, the
Airport Improvement Program (AIP) awarded more than $240 million in
grants for runway safety area improvement projects. FAA indicates that
about $1.1 billion in AIP funds will be needed to complete the
remainder. The administration's budget request for FAA calls for $2.75
billion in AIP funds in fiscal year 2008, a substantial reduction from
the $3.5 billion funding levels for fiscal years 2006 and 2007. It will
be important for FAA to consider these runway safety areas as it
prioritizes AIP funds. FAA considers the installation of an Engineered
Materials Arresting System (EMAS), a bed of crushable concrete designed
to safely decelerate and stop overrunning aircraft, to be an acceptable
alternative for meeting runway safety area standards. As of December
2006, EMAS was installed on 21 runways at 16 U.S. airports and had
successfully stopped three aircraft from overrunning runways. We are
conducting ongoing work for this subcommittee on runway and ramp safety
and expect to issue our final report later this year.
FAA and Congress Should Address Regulatory Approaches to Some Current
Airspace Users and Emerging Sectors:
Future air traffic is expected to include not only increases in the
number of traditional airspace users, but new users as well. It will be
important for FAA to establish the appropriate regulatory approach for
current users and new users such as the emerging space tourism industry
and unmanned aircraft systems. For example, we recently found that
FAA's current oversight approach for air ambulances was not geared to
the unique operating characteristics and risks associated with that
sector.[Footnote 23] Further, in 2006, NTSB recommended, among other
things, that FAA require that all air ambulance operators comply with
Part 135 of Title 14 of the Code of Federal Regulations during all
flights with medical personnel on board.[Footnote 24] Under FAA
regulation, most air ambulances operate under rules specified in Part
135. However, pilots may operate under different standards, depending
on whether they are carrying patients. Without patients or passengers
on board, pilots may operate under rules specified in Part 91 of Title
14 of the Code of Federal Regulations. With patients on board, pilots
are required to operate under Part 135 rules. Parts 91 and 135 flight
rules differ significantly in two key areas--(1) weather and visibility
minimums and (2) rest requirements--with Part 135 requirements being
more stringent.
In many air ambulance trips, part of the trip may involve Part 135
rules, while another part may involve Part 91 rules. For example, scene
response missions for air ambulance helicopters frequently have three
legs--the flight en route to the accident scene, the transport of the
patient to the hospital, and the reposition of the helicopter back to
its base (see fig. 5). Only the leg during which patients or other
passengers (medical crew members are not considered passengers) are on
board must be flown under Part 135 flight rules. Of the 89 air
ambulance accidents that we examined from 1998 through 2005, 64 took
place during Part 91 flight and the remaining 25 took place during Part
135 flight. However, because air ambulance flights without patients or
passengers could be flown under Part 91 requirements, there may be more
than twice as many flights taking place under Part 91 compared with
Part 135. A better understanding of the trends in the air ambulance
industry, including accident data, will be important in deciding if the
current regulatory approach is appropriate or if more fundamental
changes, such as revising FAA regulations, need to be made.
Figure 5: Air Ambulance Scene Flight Response Legs:
[See PDF for image]
Source: GAO.
[End of figure]
As another example, the need for a different regulatory approach for
all-cargo operations has been raised. According to FAA, from 1998
through 2005, the accident rate for scheduled air cargo operators
declined significantly but was still about 2.5 times higher than the
accident rate for scheduled passenger operators. The Congressional
Research Service pointed out that the size of aircraft, the range of
operations flown by all-cargo operators, and the large growth in the
all-cargo sector introduce unique risks to operators, airports, and the
public that may call for revisiting the safety standards that apply to
all-cargo operations.[Footnote 25]
In recent work, we also raised issues concerning FAA's regulation of
the emerging space tourism industry.[Footnote 26] Specifically, we
suggested that Congress should consider revisiting the granting of
FAA's dual mandate for ensuring safety and promoting space tourism and
decide whether the elimination of FAA's promotional role is necessary
to alleviate a potential conflict. FAA licenses the operation of
commercial space launches and launch sites. Historically, these
launches carried commercial payloads and were unmanned. The prospect
for commercial space tourism materialized in 2004, after the successful
launches of SpaceShipOne raised the possibility of an emerging U.S.
commercial space tourism industry that would make human space travel
available to the public. Several companies are planning to start taking
paying passengers on suborbital flights within the next few years and a
number of commercial spaceports are being planned. For example, Virgin
Galactic intends to provide suborbital space flight from a planned
spaceport in New Mexico starting in 2009. It plans to carry 3,000
passengers over 5 years, with 100 individuals having already paid the
full fare of $200,000. Figure 6 shows current and planned spaceports.
In 1984, the Commercial Space Launch Act gave DOT the authority to
license and monitor the safety of commercial space launches and to
promote the industry. It is important that FAA's statutory
responsibility to promote the commercial space launch industry does not
interfere with its safety oversight of the industry as the space
tourism sector develops. We have no evidence that FAA's promotional
activities, such as sponsoring an annual industry conference and
publishing economic impact studies, have conflicted thus far with its
safety regulatory role, but conflicts could occur as the industry
matures.
Figure 6: Federal Commercial Launch Sites and Existing and Proposed
Spaceports in the United States, October 2006:
[See PDF for image]
Sources: FAA and GAO.
[End of figure]
In addition, FAA faces the challenge of determining the circumstances
under which it would regulate the safety of crew and space flight
participants. In 2004, the Commercial Space Launch Amendments Act
prohibited FAA from regulating crew and passenger safety before 2012,
except in response to high-risk incidents, serious injuries, or
fatalities. FAA has interpreted this limited authority as allowing it
to regulate crew safety in certain circumstances and has been proactive
in proposing regulations concerning emergency training for crews and
passengers. However, FAA has not developed safety indicators by which
it would monitor the developing space tourism sector and determine when
to step in and regulate human space flight. We have recommended that
the agency be proactive about safety rather than respond only after a
fatality or serious incident occurs by identifying and monitoring
safety indicators that might trigger the need for regulation before
2012. Actions have not been taken on our recommendations.
Another emerging sector that poses regulatory issues is unmanned
aircraft systems (UAS)[Footnote 27] (see fig. 7), which are expected to
be part of the mix of aircraft that will operate in NextGen. A small
number of UASs are currently used by government agencies for a variety
of purposes, such as border security, search and rescue, firefighting,
military training exercises, and other law enforcement and homeland
security initiatives. Recent projections indicate that over 10,000 UASs
could be in operation in the United States by 2015, but FAA believes
that the number may be less. We have work ongoing for this subcommittee
to assess issues such as the technological and regulatory issues that
remain in order for UASs to be safely integrated in the national
airspace system, the timeframes for completing such work, and the
identification of entities that should take the lead in such work. We
expect to issue a report later this year.
Figure 7: U.S. Air Force's Global Hawk UAS:
[See PDF for image]
Source: Department of Defense.
[End of figure]
Our preliminary work, indicates that UASs pose unique safety challenges
and questions. For example, what standards should UASs meet to ensure
that they detect, sense, and avoid other aircraft? What standards
should be set for UAS safety and reliability? How should FAA classify
UASs, which can range in size from very small, hand launched systems to
those similar in size to a large passenger aircraft? What pilot
qualifications are needed for UAS operators? FAA has begun to answer
such questions by reviewing its existing safety regulations developed
for manned aircraft to determine how or whether they need to be
modified to enable UASs to be safely integrated into the national
airspace system. FAA expects this to be a 5-to 10-year effort. In the
meantime, FAA will continue its existing oversight approach and review
each request to operate on a case-by-case basis. If FAA determines that
a UAS can operate safely under specified conditions, the agency issues
a certificate of authorization and the airspace is restricted during
the period of operation.[Footnote 28] In fiscal year 2006, FAA
processed 96 applications for certificates of authorization and issued
62 certificates. FAA projects that it will receive over 400
applications in 2010. The agency may have difficulty handling such an
increase under its existing case-by-case process, which could serve as
a de facto limit on the number of UASs operating in the next few years.
FAA Needs Improved Data and Analysis for Current Safety Oversight and
for the Transition to NextGen:
FAA cannot rely on its current oversight approach, which focuses on
labor-intensive inspections to maintain and expand the margin of
safety, especially if substantial growth in air traffic materializes.
FAA acknowledges this situation and sees the need to establish a safety
information system that can provide an early warning of hazards that
may lead to accidents and help the agency manage risk. However, our
past work has found problems with the accuracy and completeness of
FAA's safety data. For example, FAA does not collect actual flight
activity data for general aviation operators, air taxis, or air
ambulances. As a result, FAA lacks information to monitor the rate of
accidents and determine the effectiveness of its oversight. We have
recommended that FAA improve the accuracy and completeness of its
safety data and evaluate this information to identify nationwide
trends. FAA is in the early planning stages of addressing our
recommendations, but more work remains.
An important aspect of FAA's safety oversight is the use of over 13,000
private individuals and organizations, known as designees, to leverage
inspector resources. Designees act as representatives of the agency to
conduct many safety certification activities, such as administering
flight tests to pilots, inspecting repair work by maintenance
facilities, and approving designs for aircraft parts. In reviewing
FAA's designee programs, we found that the agency's oversight of
designees was hampered, in part, by limited data on designees'
performance.[Footnote 29] FAA is in the early stages of addressing our
recommendation to improve the consistency and completeness of designee
information. FAA is also changing and expanding the designee programs
by replacing certain designee programs with an organization designation
authorization. By expanding the number and types of organizational
designees, FAA's role is being further transformed to monitoring the
performance of organizations rather than overseeing the individuals who
perform the certification activities. It will be important for FAA to
have the data, evaluative processes, and a well-trained inspector staff
to effectively monitor the new program to make sure that safety is not
adversely affected.
FAA is in the early stages of addressing some of these data issues as
it begins planning a new system--Aviation Safety Information Analysis
and Sharing System--that would provide access to large volumes of
industry safety data. FAA began planning for the new system in 2006.
Because this activity is in the early planning stages, our concerns
about FAA's data remain relevant. The successful completion of this
planning effort will be critical to FAA's ability to improve safety. In
fiscal year 2008, FAA proposes budgeting $32 million for safety
databases and computer systems. As FAA prioritizes the activities that
it undertakes with these funds, it will be important to continue
addressing these critical data limitations.
In addition, FAA is shifting to a data-driven, risk-based approach to
maintaining the agency's approximately 40,000 pieces of air traffic
control equipment, but it has not yet determined its new data needs.
FAA is in the very early planning stages of a 10-year or longer effort
to switch to this new approach, termed reliability centered maintenance
(RCM), which private industry and other federal agencies, such as the
Department of Defense (DOD) and NASA, use to maintain equipment. FAA
expects the new approach to improve equipment performance. However, we
reported in November 2006 that FAA had not developed a plan to
implement RCM, has not determined the data needs for RCM, and has not
decided what training will be provided to staff.[Footnote 30] As the
agency moves forward with this approach, it will be important for FAA
to address the issues we identified as well as work with stakeholders,
including FAA maintenance technicians, to ensure that decisions are not
driven entirely by cost savings and that the safety and efficiency of
national airspace operations are not adversely affected.
FAA Faces Human Capital Challenges:
FAA's ability to ensure safety in NextGen will also be affected by its
ability to manage its human capital, including air traffic controllers,
safety inspectors, engineers, and technicians. FAA faces a challenge in
managing human capital due to contentious relations with its labor
unions. Fourteen unions represent more than 34,000 of FAA's 43,200 full
time permanent employees. With the exception of two unions--the
National Air Traffic Controllers Association (NATCA) and the
Professional Airway System Specialists (PASS), which represent about
23,000 FAA employees--12 unions have negotiated a contract or
memorandum of agreement with FAA, according to agency officials. In
April 2006, after reaching an impasse in negotiations with NATCA, FAA
used its authority[Footnote 31] to settle the impasse by imposing a
contract on its air traffic controllers. After 4 years of contract
negotiations with PASS, FAA reached an agreement in April 2006. The
PASS membership, however, according to an FAA official, rejected this
proposed contract. Subsequently, FAA filed a complaint with the Federal
Labor Relations Authority claiming an unfair labor practice, according
to the same FAA official. Until this complaint is adjudicated, the
previous PASS contract remains in effect, according to the FAA
official. Improving the contentious relationship between FAA and these
unions could have positive effects on both the safety of FAA operations
and the implementation of new air traffic management systems under
NextGen. For example, delays in union approvals that may be needed to
implement new systems could lead to delays in their implementation if
labor management relations are acrimonious. In addition, the current
contract situations have the potential to hinder FAA's ability to
retain and recruit skilled technical staff.
FAA estimates it will lose about 72 percent of its air traffic
controller workforce over the next 10 years. (See fig. 8.) To replace
these controllers, FAA plans to hire 15,004 new controllers from fiscal
years 2006 through 2016, according to the agency's March 2007
controller workforce plan. This recent hiring target is higher than
FAA's June 2006 hiring target[Footnote 32] to reflect recent data
indicating that controllers are retiring at a faster rate than FAA
anticipated. To meet these higher targets, FAA has expanded its hiring
sources, which had focused on individuals with prior FAA or DOD air
traffic control experience and graduates from FAA's collegiate training
initiative program to include the general public. This strategy is
needed, according to FAA officials, because DOD has recently become
less of a hiring source for controllers due to military incentives for
retaining controllers and DOD's higher salaries than FAA's entry-level
salary.[Footnote 33] However, those new hires that lack prior air
traffic control experience will require more training to become
certified controllers.[Footnote 34] Additionally, since it can take up
to 3 to 5 years for a controller to become certified, within a few
years, a large portion of the controller workforce may be trainees and
not fully certified. Based on FAA's hiring and retirement projections,
by 2010, about 40 percent of the air traffic controller workforce will
have 5 or fewer years of experience. This high percentage of newly
hired controllers will continue for a number of years, making it
important for FAA to carefully balance the ratio of trainees to
certified controllers at each air traffic control facility.
Figure 8: Estimated Controller Losses and Planned Hires, Fiscal Years
2006-2016:
[See PDF for image]
Source: FAA.
Note: Numbers for fiscal year 2006 represent actual losses and hires.
[End of figure]
In addition to the challenge of hiring and training new air traffic
controllers, it will be important to deploy them in an optimal manner
to reflect changing air traffic demands. FAA's recent controller
workforce plan includes facility-by-facility staffing standards for
fiscal year 2007 expressed as ranges.[Footnote 35] The staffing
standards are intended to take into consideration facility-specific
information, such as air traffic operations, productivity trends,
expected retirements, and the number of controllers in training. These
new standards are an improvement over FAA's historical approach, which
was to compute the number of controllers needed systemwide and
negotiate the distribution of these totals to the facility level.
However, FAA's current staffing does not align with the new standards
at about one-third of FAA's 314 facilities--93 of which are currently
overstaffed and 11 understaffed. This situation adds further complexity
to the controller hiring, training, and staffing issues that FAA must
carefully manage in the upcoming years. Furthermore, FAA has not
factored into its staffing standards or its projected hiring targets
the effect of new NextGen technologies on controller workload. The new
technologies will result in a more automated system that, over time, is
expected to change the role of controllers as well as productivity. In
future updates of the controller workforce plan, it will be important
to begin to factor in this impact.
Furthermore, having the right skill mix of safety inspectors and
technicians and deploying them to make best use of their skills is
especially important as new and developing sectors emerge. By 2010, 44
percent of FAA's inspector workforce of about 3,865 will be eligible to
retire. To begin addressing this situation, FAA has requested funding
to hire an additional 87 inspectors in fiscal year 2008. In addition to
maintaining a sufficient number of safety inspectors, it will be
important to deploy them where they are most needed. However, FAA lacks
a staffing model to accomplish this. The National Academy of Sciences
recently completed a study that analyzed FAA's staffing processes for
safety inspectors and identified a number of issues that the agency
needed to address. For instance, the study indicated that the current
staffing process does not focus resources in the areas of greatest need
and the match between individual inspectors' technical knowledge and
the facilities and operations they oversee is not always optimal. In
response to academy recommendations, FAA expects to develop a staffing
model, but the agency does not have a specific time frame for
initiating this effort. In addition, FAA lacks staffing standards for
its approximately 6,100 technicians, who are responsible for
maintaining the agency's air traffic control equipment. The development
of staffing models for safety inspectors and technicians is important
in the changing aviation environment and is critical to FAA's ability
to ensure that its safety programs and workload are aligned to meet the
future demands for which NextGen is preparing.
For further information about this testimony, please contact Dr. Gerald
L. Dillingham at (202) 512-2834 or dillinghamg@gao.gov. Individuals
making key contributions to this testimony include Faye Morrison,
Teresa Spisak, Nancy Boardman, Anne Dilger, Sharon Dyer, Kevin Egan,
Colin Fallon, Jim Geibel, Bob Homan, Rosa Leung, Ed Menoche, Taylor
Reeves, Richard Scott, Jeremy Sebest, Larry Thomas, Pam Vines, and
Carrie Wilkes.
[End of section]
Related GAO Products:
Federal Aviation Administration: Observations on Selected Changes to
FAA's Funding and Budget Structure in the Administration's
Reauthorization Proposal. GAO-07-625T. Washington, D.C.: March 21,
2007.
Aviation Safety: Improved Data Collection Needed for Effective
Oversight of Air Ambulance Industry. GAO-07-353. Washington, D.C.:
February 21, 2007.
Federal Aviation Administration: Challenges Facing the Agency in Fiscal
Year 2008 and Beyond. GAO-07-490T. February 14, 2007.
Next Generation Air Transportation System: Progress and Challenges
Associated with the Transformation of the National Airspace System. GAO-
07-25. Washington, D.C.: November 13, 2006.
FAA's Proposed Plan for Implementing a Reliability Centered Maintenance
Process for Air Traffic Control Equipment. GAO-07-81R. Washington,
D.C.: November 9, 2006.
Aviation Safety: FAA's Safety Efforts Generally Strong but Face
Challenges. GAO-06-1091T. Washington, D.C.: September 20, 2006.
Commercial Space Launches: FAA Needs Continued Planning and Monitoring
to Oversee the Safety of the Emerging Space Tourism Industry. GAO-07-
16. Washington, D.C.: September 20, 2006.
Aviation Safety: FAA's Safety Oversight System Is Effective but Could
Benefit from Better Evaluation of Its Programs' Performance. GAO-06-
266T. Washington, D.C.: November 17, 2005.
National Airspace System: Transformation will Require Cultural Change,
Balanced Funding Priorities, and Use of All Available Management Tools.
GAO-06-154. Washington, D.C.: October 14, 2005.
Aviation Safety: System Safety Approach Needs Further Integration into
FAA's Oversight of Airlines. GAO-05-726. Washington, D.C.: September
28, 2005.
Federal Aviation Administration: Stronger Architecture Program Needed
to Guide Systems Modernization Efforts. GAO-05-266. Washington, D.C.:
April 29, 2005.
Aviation Safety: FAA Needs to Strengthen the Management of Its
Designees Programs. GAO-05-40. Washington, D.C.: October 8, 2004.
Air Traffic Control: System Management Capabilities Improved, but More
can be Done to Institutionalize Improvements. GAO-04-901. Washington,
D.C.: August 20, 2004.
Information Technology: FAA Has Many Investment Management Capabilities
in Place, but More Oversight of Operational Systems is Needed. GAO-04-
822. Washington, D.C.: August 20, 2004.
FOOTNOTES
[1] JPDO was authorized by the Vision 100--Century of Aviation
Reauthorization Act (Pub. L. No. 108-176), which requires the office to
operate in conjunction with multiple government agencies, including the
Departments of Transportation, Commerce, Defense, and Homeland
Security; FAA; the National Aeronautics and Space Administration
(NASA); and the White House Office of Science and Technology Policy.
JPDO also involves industry and other stakeholders through the Next
Generation Air Transportation System Institute.
[2] Earned Value Management combines measurements of technical,
schedule, and cost performance with the intent of providing an early
warning of problems while there is time for corrective action.
[3] Delphi is a commercial off-the-shelf financial management system
that was acquired by the Department of Transportation and fully
implemented in FAA in 2003.
[4] The reauthorization proposal includes, among other things,
introducing direct user charges for commercial aircraft based on the
cost of the air traffic services they receive, eliminating many current
taxes, substantially increasing the fuel taxes general aviation
operators pay, charging both commercial and general aviation a fuel tax
to pay for airport capital improvements, and linking the contribution
to FAA's budget from the General Fund of the U.S. Treasury to the
public benefits FAA provides. Under the administration's proposal,
these changes would begin in fiscal year 2009.
[5] Revenue adequacy refers to the ability of FAA's funding system to
produce revenues commensurate with workload changes over time. Equity
refers to the equitable distribution of costs to aviation users.
Efficiency refers to incentives that encourage the efficient use of the
national airspace system.
[6] GAO, Federal Aviation Administration: Observations on Selected
Changes to FAA's Funding and Budget Structure in the Administration's
Reauthorization Proposal, GAO-07-625T (Washington, D.C.: Mar. 21,
2007).
[7] GAO, Federal Aviation Administration: Stronger Architecture Program
Needed to Guide Systems Modernization Efforts, GAO-05-266 (Washington,
D.C.: Apr. 29, 2005); Air Traffic Control: System Management
Capabilities Improved, but More can be Done to Institutionalize
Improvements, GAO-04-901 (Washington, D.C.: Aug. 20, 2004); and
Information Technology: FAA Has Many Investment Management Capabilities
in Place, but More Oversight of Operational Systems is Needed, GAO-04-
822 (Washington, D.C.: Aug. 20, 2004).
[8] EVM is a project management technique that combines measurements of
technical performance, schedule performance, and cost performance with
the intent of providing an early warning of problems while there is
time for corrective action.
[9] This work is in response to a joint request from this subcommittee
and the Subcommittee on Aviation of the Senate Commerce, Science, and
Transportation Committee.
[10] ATO has the lead responsibility for both of these goals.
[11] Scheduled outages occur for scheduled maintenance.
[12] GAO, National Airspace System: Transformation will Require
Cultural Change, Balanced Funding Priorities, and Use of All Available
Management Tools, GAO-06-154 (Washington, D.C.: Oct. 14, 2005).
[13] Prior to expansion of the OEP, the document centered on plans for
increasing capacity and efficiency at 35 major airports.
[14] The planning documents include the Concept of Operations,
Enterprise Architecture, and Integrated Work Plan. The Concept of
Operations describes how the transformational elements of NextGen will
operate in 2025. It is intended to establish general stakeholder buy-in
to the NextGen end state, transition path, and business case. The
Enterprise Architecture follows from the Concept of Operations and
describes the system in more detail. It will be used to integrate
planning efforts and drive partner agency guidance. The Integrated Work
Plan lays out a timeline for deploying and integrating NextGen systems.
[15] GAO, Next Generation Air Transportation System: Progress and
Challenges Associated with the Transformation of the National Airspace
System, GAO-07-25 (Washington, D.C.: Nov. 13, 2006).
[16] JPDO, Making the NextGen Vision a Reality: 2006 Progress Report to
the Next Generation Air Transportation System Integrated Plan
(Washington, D.C.: March 2007).
[17] FAA has six capital investment programs that it considers
transformational NextGen programs slated to receive funding in fiscal
year 2008: ADS-B nationwide implementation, System Wide Information
Management (SWIM), NextGen Data Communications, NextGen Network Enabled
Weather, National Airspace System Voice Switch, and NextGen Technology
Demonstration. In addition, five other programs are slated to begin
funding in 2009: NextGen System Development, NextGen High Altitude
Trajectory Based Operations, NextGen High Density Airports, NextGen
Networked Facilities, and NextGen Cross-Cutting Infrastructure.
[18] GAO-07-25.
[19] ASDE-X is the upgraded digitally-based technology that enables air
traffic controllers to detect potential runway conflicts by providing
detailed coverage of movement on runways and taxiways. ASDE-X warns
controllers of potential runway incursions.
[20] The rate was 5.4 incursions per 1 million tower operations in
fiscal year 2006 and 5.2 incursions per 1 million tower operations in
fiscal year 2002.
[21] Recommended changes to air traffic control procedures include
clarifying authorized runway crossings, increasing the situational
awareness of the flight crews for arriving aircraft at night or in poor
visibility conditions without relying on the controllers, and the use
of international landing clearance procedures and standard phraseology
for airport surface operations.
[22] Public Law 109-115.
[23] GAO, Aviation Safety: Improved Data Collection Needed for
Effective Oversight of Air Ambulance Industry, GAO-07-353 (Washington,
D.C.: Feb. 21, 2007).
[24] NTSB, Special Investigative Report on Emergency Medical Services
Operations (Washington, D.C.: 2006). According to NTSB, as of December
21, 2006, this recommendation and others made in this report were still
open.
[25] Congressional Research Service, Reauthorization of the Federal
Aviation Administration: Background and Issues for Congress
(Washington, D.C.: Jan. 29, 2007).
[26] GAO, Commercial Space Launches: FAA Needs Continued Planning and
Monitoring to Oversee the Safety of the Emerging Space Tourism
Industry, GAO-07-16 (Washington, D.C.: Oct. 20, 2006).
[27] Unmanned aircraft systems do not carry a human operator; they are
either programmed for autonomous flight (called a "drone") or are flown
remotely by a ground operator.
[28] A certificate of authorization allows an operator to use defined
airspace for a specified time (up to one year, in some cases) and
includes special provisions unique to each operation. For instance, a
certificate may include a requirement to operate only under visual
flight rules.
[29] GAO, Aviation Safety: FAA Needs to Strengthen the Management of
Its Designees Programs, GAO-05-40 (Washington, D.C.: Oct. 8, 2004).
[30] GAO, FAA's Proposed Plan for Implementing a Reliability Centered
Maintenance Process for Air Traffic Control Equipment, GAO-07-81R
(Washington, D.C.: Nov. 9, 2006).
[31] 49 U.S.C. §40122(a)(2).
[32] In June 2006, FAA planned to hire 11,851 new air traffic
controllers from 2006 through 2015. FAA's revised plan calls for hiring
13,641 new controllers for the same time period.
[33] Under FAA's recently implemented contract with air traffic
controllers, most current controllers continue to receive their
existing base salaries and benefits, while new controllers are hired at
lower wages.
[34] Only newly hired controllers without any previous experience or
specialized education are required to complete 5 weeks of initial
qualification training.
[35] For example, the staffing range at the Seattle-Tacoma
International Airport is from 23 to 29 controllers.
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts
newly released reports, testimony, and correspondence on its Web site.
To have GAO e-mail you a list of newly posted products every afternoon,
go to www.gao.gov and select "Subscribe to Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office 441 G Street NW, Room LM
Washington, D.C. 20548:
To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202)
512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S.
Government Accountability Office, 441 G Street NW, Room 7125
Washington, D.C. 20548:
Public Affairs:
Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800
U.S. Government Accountability Office, 441 G Street NW, Room 7149
Washington, D.C. 20548: