Briefing on Observations on the Office of Management and Budget's Report on the Human Resources Line of Business Initiative
Gao ID: GAO-08-1163R September 19, 2008
The Human Resources Line of Business (HR LOB) initiative, under Office of Management and Budget (OMB) direction and Office of Personnel Management (OPM) management, aims to increase operational efficiencies and cost savings governmentwide by transitioning outdated and decentralized federal agency human resources information technology systems to pre-qualified public sector or commercial shared service center providers. Section 747 of Division D of the Fiscal Year 2008 Consolidated Appropriations Act (Pub. L. No. 110-161) required OMB to provide to the Congressional Committees on Appropriations of the House and Senate a report on a number of issues, including the role of public-private competition as part of HR LOB, and for GAO to review OMB's report and brief the committees on GAO's views concerning the report. On September 10, 2008, we briefed congressional staff on the results of our review, and that briefing is reprinted in full as an enclosure to this letter. As agreed, this concludes our work performed under this mandate.
GAO-08-1163R, Briefing on Observations on the Office of Management and Budget's Report on the Human Resources Line of Business Initiative
This is the accessible text file for GAO report number GAO-08-1163R
entitled 'Briefing on Observations on the Office of Management and
Budget's Report on the Human Resources Line of Business Initiative'
which was released on September 19, 2008.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
GAO-08-1163R:
U.S. Government Accountability Office:
Washington, DC 20548:
September 19, 2008:
The Honorable Richard Durbin:
Chairman:
The Honorable Sam Brownback:
Ranking Member:
Subcommittee on Financial Services and General Government:
Committee on Appropriations:
United States Senate:
The Honorable José E. Serrano: Chairman:
The Honorable Ralph Regula:
Ranking Member:
Subcommittee on Financial Services and General Government:
Committee on Appropriations:
House of Representatives:
Subject: Briefing on Observations on the Office of Management and
Budget's Report on the Human Resources Line of Business Initiative:
The Human Resources Line of Business (HR LOB) initiative, under Office
of Management and Budget (OMB) direction and Office of Personnel
Management (OPM) management, aims to increase operational efficiencies
and cost savings governmentwide by transitioning outdated and
decentralized federal agency human resources information technology
systems to pre-qualified public sector or commercial shared service
center providers. Section 747 of Division D of the Fiscal Year 2008
Consolidated Appropriations Act (Pub. L. No. 110-161) required OMB to
provide to the Congressional Committees on Appropriations of the House
and Senate a report on a number of issues, including the role of public-
private competition as part of HR LOB, and for GAO to review OMB's
report and brief the committees on GAO's views concerning the report.
On September 10, 2008, we briefed your staff on the results of our
review, and that briefing is reprinted in full as an enclosure to this
letter. As agreed, this concludes our work performed under this
mandate.
We are sending copies of this letter to the directors of OMB and OPM
and other interested congressional committees. We will also make copies
available to others upon request. In addition, the letter will be
available on GAO's Web site at [hyperlink, http://www.gao.gov].
If you or your staff have any questions regarding this report, please
contact me at (202) 512-4841 or sherrilla@gao.gov. Contact points for
our Offices of Congressional Relations and Public Affairs may be found
on the last page of this report. Key contributors to this letter were
Carolyn Kirby, Assistant Director; Katherine Trimble; Karin Fangman;
and John Krump.
Signed by:
Andrew Sherrill:
Acting Director, Acquisition and Sourcing Management:
Enclosure:
[End of section]
Enclosure: Briefing Slides:
Briefing to Congressional Committees:
September 10, 2008:
Observations on the Office of Management and Budget‘s Report on the
Human Resources Line of Business Initiative:
Mandate under Fiscal Year 2008 Consolidated Appropriations Act,
Division D, Section 747:
FY 2008 Consolidated Appropriations Act, P.L. 110-161 (Dec. 26, 2007):
Two HR LOB Reporting Mandates:
Sec. 747(b): Office of Management and Budget (OMB) Director submits to
appropriations committees a report on the role of public-private
competition in the Human Resources Line of Business (HR LOB) initiative
addressing the following:
1) The role of Circular A-76 public-private competition or direct
conversion to contractor performance under the initiative;
2) The expected impact of the initiative on federal employment levels
at affected agencies;
3) An estimate of the initiative‘s annual and recurring savings and a
description of the methodology used to generate the estimate;
4) An estimate of the initiative‘s total transition costs; and;
5) Guidance for agencies to evaluate the initiative‘s benefits and to
develop alternative strategies in the absence of expected benefits.
Sec. 747(c): GAO reviews OMB‘s report on the HR LOB initiative and
briefs the committees on its views concerning the report.
[End of section]
Scope and Methodology:
* Reviewed the HR LOB report, dated June 25, 2008, that was submitted
by OMB‘s Director to congressional committees;
* Interviewed HR LOB officials at OMB and Office of Personnel
Management (OPM) to further discuss report and obtain supplemental
information for review;
* Consulted with other GAO staff with expertise in the areas of human
resources (HR) and information technology (IT) administration;
government IT initiatives; and federal program cost-benefit analysis
methodologies;
* We discussed a draft of this briefing with OMB and OPM. Overall,
officials agreed with our characterization of OMB‘s report to Congress
as well as with the supplemental information we provided and our
observations. Officials provided some clarification and additional
technical details, which we incorporated as appropriate; and;
* We conducted this performance audit between July and September 2008
in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe that
the evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives.
[End of section]
HR LOB Initiative Overview:
The initiative, under OMB direction and OPM management, aims to
increase operational efficiencies and cost savings governmentwide by
transitioning outdated and decentralized agency HR IT systems to one of
nine pre-qualified public sector or commercial shared service center
(SSC) providers:
Public sector SSCs:
National Finance Center (Agriculture);
Civilian Personnel Mgmt. Service (DOD)[Footnote 1];
Program Support Center (HHS) [Footnote 2];
National Business Center (Interior);
HR Connect (Treasury).
Commercial SSCs:
Accenture;
Allied Technology Group;
Carahsoft Technology;
IBM [Footnote 3].
* Customers = all federal agencies covering about 1.8 million civilian
employees to be serviced by SSCs after transfer of core HR IT functions
from in-house systems;
* HR LOB mandates that three core HR IT functions be transferred to a
public or commercial SSC:
1. personnel action processing (e.g., actions to appoint, separate);
2. benefits management (e.g., process health and retirement benefits);
3. compensation management (e.g., payroll processing);
* HR LOB makes it optional to transfer nine non-core HR Staff Support
functions: human resources strategy, organization and position
management, staff acquisition, performance management, compensation
management,[Footnote 4] human resources development, employee
relations, labor relations, and separation management.
* In order to select a public or commercial SSC to which their core
and/or non-core functions will be transferred, customer agencies are to
follow a 5-phase end-to-end ’migration roadmap“ overseen by OMB & OPM.
Phase –Agency Actions:
1. Assess –Envision best scenario for HR service delivery.
2. Define –Develop SSC requirements.
3. Select –Select SSC and negotiate service expectations.
4. Migrate –Move selected HR IT operations from agency to SSC.
5. Operate and Improve –Use performance results to identify
opportunities for improvement.
Timeline of HR LOB Initiative Actions:
* Spring 2004: OMB convened taskforce on standardization of HR business
functions and processes;
* August 2005: 5 public sector SSCs established;
* May 2007: Competition Framework for HR LOB migrations issued;
* Dec. 2007-Jan. 2008: 4 commercial SSCs are selected under General
Services Administration schedules program;
* Dec. 26, 2007-August 24, 2008: Statutory moratorium on use of funds
for HR LOB migrations;
* According to OMB and OPM, 3 agencies started migrations under HR LOB
prior to the moratorium (1 completed).
HR LOB-Related Migrations Under e-Payroll:
* Under the guidance of OMB and OPM, the pre-HR LOB e-Payroll
initiative was established in June 2002 to standardize and consolidate
the operations of 22 federal payroll system providers by migrating
operations to 4 selected public sector SSCs:
- According to OPM officials, this initiative is nearly complete;
- In addition, 3 agencies migrated all 3 core HR IT functions as part
of e-Payroll. While the agencies did not apply the competition
framework to their migrations, OMB and OPM have treated them as
comparable to full-scale HR LOB migrations of the three core functions.
[End of section]
Analysis: Role of public-private competition under Circular A-76, Sec.
747(b)(1):
OMB Report Highlights:
* When a customer agency is ready to select a SSC, the HR LOB
Competition Framework establishes two public-private competition
scenarios based on the number of full time equivalent (FTE[Footnote 5])
positions involved:
1. More than 10 FTEs: OMB officials told us in this scenario migrations
must be conducted in accordance with Circular A-76. The customer agency
must conduct a public-private competition among the most efficient
organization (MEO)[Footnote 6] and at least 3 public and 3 commercial
SSCs (1+3+3 public-private competition). No exceptions other than those
authorized under Circular A-76
2. 10 or fewer FTEs: A-76 procedures do not apply. Rather, a customer
agency must conduct a competition among at least 3 public & 3
commercial SSCs (3+3 public-private competition). No exceptions to 3+3
competition without OMB approval:
- Under scenario 2, OMB may authorize non-competitive migrations or
limited competitions involving only public or only commercial SSCs
(e.g., 1+1 public-public instead of the 3+3 public-private
competition).
GAO Observations and Supplemental Information:
* For its 2006 budget estimate for the initiative, OMB projected that
32 agencies would undergo HR LOB public-private competitive migrations
between 2007-2010.
* While the OMB report describes the role of A-76 public-private
competition in the migration process, it does not provide a clear
picture of how many agencies are expected to undergo the A-76 process
(scenario 1), which has been a focus of ongoing congressional concern:
- Instead, OMB and OPM officials stated that they expect most HR LOB
migrations to occur under scenario 2 (i.e., non-A-76 process) because
the focus is on migrating HR IT operations typically performed by
contractors rather than federal FTEs.
* As of Aug. 2008, no such competitions have occurred due in
part,according to OMB and OPM officials, to the statutory moratorium.
* Pending FY 2009 appropriations include an additional 1-year
moratorium on new A-76 studies that would prohibit HR LOB efforts under
scenarios 1 and 2.
[End of section]
Analysis: Impact on federal employment levels at affected agencies,
Sec. 747(b)(2):
OMB Report Highlights:
* Report suggests that impact of HR LOB on federal employment levels is
likely to be relatively low because:
- HR IT systems are typically operated and maintained by contractors.
Thus, the effects of migrations to SSCs have primarily impacted
contractors, not federal FTEs;
- Moreover, the report suggests that HR IT contractors are typically
overseen by small numbers of federal IT managers or HR specialists;
and;
- Federal IT managers directly affected by migrations have frequently
been redirected to other mission-related projects (which indicates that
federal IT FTEs have not been cut).
GAO Observations and Supplemental Information:
* OMB‘s 2006 projection was that 32 agencies would undergo HR LOB
migrations. The report provides two examples for expecting a low impact
on FTEs:
- One example is of a Department of Homeland Security migration under
the smaller-scale e-Payroll initiative and a second is of the
Department of Labor‘s anticipated plans for a full-scale HR LOB
migration.
* Thus the report‘s finding about the low impact on federal employment
levels appears to be based, in part, on a migration under e-Payroll,
which was a smaller scale SSC migration and may not be a reliable
predictor of the initiative‘s impact on federal HR IT employees
performing the wide range of core functions listed on slide 5.
* In addition, the report does not directly address the expected impact
of HR LOB on HR Staff Support FTEs performing the nine non-core
functions listed on slide 5.
* Customer agencies are required to collect data on affected HR IT and
HR Staff Support FTEs during the first two phases of each migration.
[End of section]
Analysis: Estimate of annual and recurring savings, sec. 747(b)(3):
OMB Report Highlights:
* OMB developed a rough-order-of-magnitude estimate of $1 billion (net
present value) in savings over 10 years (FYs 2006-2015) for the
initiative.
* Model:
- Status quo costs: reduction in status quo costs = gross savings;
- Gross savings: cost of establishing SSCs = net savings.
* Status quo costs were calculated using agencies‘ reported average
spending for FY 2004-2005.
* Reduction in status quo costs was estimated to be 50%.
* Costs (planning, acquisition, maintenance) of establishing SSCs over
10-year period were estimated to be $1.6 billion.
* OPM plans to revise the cost-benefit analysis for HR LOB for the FY
2010 budget process based on agency budget submissions (Exhibit 300).
GAO Observations and Supplemental Information:
* OMB report does not distinguish between annual[Footnote 7] and
recurring savings;
* OMB officials told us that the 10-year savings estimate is out of
date and likely would increase if recalculated with updated
information, including:
- Actual costs of establishing public sector and commercial SSCs;
- Changing assumptions on agency migration patterns;
* In addition to OPM‘s plan to revise the cost-benefit analysis for the
FY 2010 budget process, OMB officials told us they support the idea of
periodically providing to Congress revised savings estimates as HR LOB
progresses.
[End of section]
Analysis: Initiative‘s total transition costs, Sec. 747(b)(4):
OMB Report Highlights:
* OMB estimated that the integration and transition costs for migration
would average $5 million per agency:
- These costs include planning and verification, integration of
systems, data conversion and validation, and agency change management.
* Agency transition costs will vary significantly based on the size of
the agency and other factors.
* While HR LOB is in the early stages, actual costs to migrate appear
to be in line with the initial rough-order-of-magnitude estimate.
GAO Observations and Supplemental Information:
* Report does not provide an estimate of the total transition costs
attributable to the initiative, which officials indicated could involve
32 agencies:
- OPM officials told us that OMB‘s $5 million figure for average agency
transition costs is a ’soft“ estimate.
* Report provides two examples for claim that actual transition costs
are in line with the per-agency estimate. However, the extent to which
these examples are representative of future agency results is unclear.
* OPM told us it plans to collect and revise transition costs for the
2010 budget process, using cost data agencies submit for budget process
(Exhibit 300).
* While they did not indicate any plans to do so, OMB officials told us
they support the idea of providing to Congress revised cost estimates
as HR LOB progresses.
[End of section]
Analysis: Guidance to evaluate benefits and develop alternative
strategies, Sec. 747(b)(5):
OMB Report Highlights:
* Summarizes guidance and tools for the evaluation of agency benefits,
including:
- Identifying quality assurance processes and surveillance
methodologies;
- Establishing performance metrics to support periodic evaluation of
SSCs;
- Tracking results in a manner consistent with federal guidance.
* Report notes that pre-qualifying the SSCs serves to minimize many
risks associated with major systems migrations.
GAO Observations and Supplemental Information:
* LOB governance structure”which calls for regular contact between OPM,
agencies, and SSCs”is intended to facilitate agency efforts to identify
and address problems.
* The type of HR LOB performance data to be collected and monitored by
OPM could also be used to provide periodic performance and
accountability reporting to Congress and the public.
* Report does not reference any guidance provided to agencies for
developing alternative strategies should expected benefits fail to
materialize:
- OMB officials explained that if problems cannot be addressed,
agencies have eight other pre-qualified SSCs among which to re-compete.
[End of section]
Concluding Observations:
* Our related work on the Financial Management LOB initiative indicates
that an approach such as HR LOB, as described in OMB‘s report, holds
promise for enhancing the economy and efficiency of federal operations
in an environment of increasingly constrained federal resources.
* Since agencies are still in the early stages of implementing the HR
LOB initiative, the OMB report responded to the Sec. 747 reporting
requirements in large part by citing procedural requirements and rough-
order-of-magnitude estimates, rather than data on actual impacts of HR
LOB migrations.
* Periodic analyses of the data that are planned to be collected on
actual outcomes of HR LOB could provide greater insight on the progress
of the initiative.
[End of section]
Footnotes:
[1] Department of Defense.
[2] Department of Health and Human Services.
[3] International Business Machines.
[4] Non-core compensation management activities could include
consultative support, administrative support, and knowledge management.
[5] FTE is a measure of federal civilian staffing.
[6] OMB defines a MEO as the staffing plan of the agency, developed to
represent the agency‘s most efficient and cost-effective organization.
[7] For this review we have interpreted annual savings to mean one-time
savings, in contrast to recurring savings.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office:
441 G Street NW, Room LM:
Washington, D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: