Federal Construction

Use of Construction Management Services Gao ID: GGD-90-12 January 18, 1990

Pursuant to a congressional request, GAO reviewed eight agencies' use of the construction management concept for building construction and renovation, focusing on the feasibility of adapting private-sector construction management practices to the federal government.

GAO found that: (1) the federal government selectively used the construction management concept for about 20 years; (2) although two agencies experimented with using construction managers more like general contractors in an effort to cut overall project time and cost, they de-emphasized phased construction after numerous contractors successfully filed claims arising from construction delays; (3) although federal agencies could adapt the private-sector construction concept to federal programs, they were limited by law in how much authority over spending and other decisions they could delegate to agents; (4) regulations covering competition and potential conflicts of interest also discouraged the federal government from using contractor construction management; (5) between 1986 and 1988, the 6 civilian and 2 defense agencies completed 268 building construction projects costing more than $10 million each; and (6) 117 projects experienced time delays exceeding 6 months and 62 experienced cost increases exceeding 10 percent.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.